chilled water plant design - direktori file...
TRANSCRIPT
© 2003 American Standard Inc.
Chilled Water Plant Design
Agenda
Earthwise System
Variable Primary Flow
Series Configuration
Case Study – 20,000RT Project Parallel, primary/secondary, low temp, YK
Series-counter, primary/secondary, low temp, low flow YD
Series-counter, primary/secondary, low temp, low flow CDHG
Series-counter, VPF, low temp, low flow, CDHG
Goal:Minimize Capital & Operating Costs
Improve:Reliability, Efficiency, & Comfort
Energy ConsumptionFirst Cost
Good for Business...
Offers lower first cost and lower operating cost.
Good for the Environment:
Reduced utility generated greenhouse gas emissions.
Reduces pumping costs...
A low flow, low temp, high efficiency system
Leverages today’s technology
Equipment - Chillers, Controls
System options
EarthWise Chilled Water Systems:
chillers
+$
+$
control
s
piping,
pumps
–$
Low Flow Chilled Water Plant Design …A Paradigm Shift - New ―Rules of Thumb‖
New ―rules of thumb‖
44° (6.7°) Lower chilled water supply
(such as 41° F = 5 ° C)
Larger T across evaporator
(such as 16° F= 8.9° C)
that’s at 1.5 gpm/ton
Lower flows through condenser
(such as 15°F = 8.4° C or 2 GPM/ton)
that’s something less than 3.0 gpm/ton
Tons = gpm * t / 24t (°C) gpm/ton
11 (20oF)
10 (18oF)
8.9 (16oF)
7.8 (14oF)
6.7 (12oF)
5.6 (10oF)
4.4 (8oF)
3.3 (6oF)
2.2 (4oF)
1.2
1.3
1.5
1.7
2.0
2.4
3.0
4.0
6.0
Pumps are
working.
Chillers are
working.
example chilled water plant …
Design Formulas
Chiller technology improvements
Cataloged at standard ARI conditions
Year
kW/ton
0.90
0.80
0.70
0.60
0.50
2000199519901985198019751970
Affect of reduced flow on pumps
Pump is smaller (lower cost)
Pump uses less power
0
20
40
60
80
100
0 20 40 60 80 100
% Waterflow
% Full load power
System Power
chiller chiller
pumpspumps
tower
tower
Traditional
System
Low Flow
Evaporator &
Condenser
Summary : EarthwiseTM Systems
Pump size
Tower size
Piping Size
Operating Cost
First Cost
How about Coil ?
Chilled water side
Coil
It’s a simple heat transfer device
Reacts to colder entering waterby returning it warmer
LMTD = TD2 - TD1
Ln (TD2 / TD1)
temperature
distance
80 F
air
55 F
TD2
44 F54 F water
TD1
LMTD44° F = 17.44
LMTD41° F = 18.13
41 F
57 F
How about Tower ?
Condenser side opportunity
Q=U A1 delta T1 = U A2 delta T2
Delta T1 = 94.2-78 = 16.2F (34.6-25.6 = 9 C)
Delta T2 = 99.1-78 = 21.1F (37.3-25.6 = 11.7 C)
A1*16.2 = A2*21.1
A2 = 0.77 A1
Tower exchanges heat between the entering (warmest) water temp and the ambient wet bulb
Low Flow Chilled Water Plant Design …
What are other’s saying??? Kelly and Chan (Vanderweil Engineering)
HPAC January 1999: Optimizing Chilled Water Plants”
Chilled water T: 18° & Condenser water T: 14.2°F
“With the same cost chillers, at worst, the annual operating cost with lower flows be about equal to “standard” flows but still at a lower first cost”
PG&E: CoolTools™ Chilled water T: 12°F to 20 °F
Condenser water T: 12°F to 18 °F (multi-stage)
0
200
400
600
41/16 42/14 43/12 44/10
Chilled water supply
temperature/DeltaT
kWh
/to
n/y
ear
Chilled waterpump
Chiller
© 2003 American Standard Inc.
Chilled Water System Optimization
• Decoupled Systems
• Variable Flow Systems
• Series Chiller Configuration
Decoupled Systems moving to…
Variable Flow Systems
Primary-secondary and VPF comparison
VPF
No secondary pumps
Chiller and pump staging not necessarily connected
Bypass line and valve for minimum flow control
Reduced installed cost
Reduced operating cost
Primary-secondary
Primary pumps
Secondary pumps
Chiller and primary pumps staged in pairs
Bypass line (no valve) allows constant evaporator water flow
CHW system type Primary/ secondary
Variable primary flow
Cooling load, tons 500 500
Total CHW flow rate 1,000 1,000
Primary pump head, feet
50 120
Secondary pump head, feet
70 NA
Primary-secondary and VPF comparison
Design Conditions :
ARTI-21CR/611-20070-01
CHW system type Primary/ secondary
Variable primary flow
CHW pump equip cost, $ 10,516 7,358
CHW pump installation cost, $ 2,857 1,486
Piping & fittings installed cost, $ 19,070 NA
VFD / Starter installed cost, $ 9,860 14,550
Bypass / decoupler installed cost, $ 1,328 929
Bypass valve installed cost, $ NA 1,548
Flow meter installed cost, $ NA 1,800
Total installed cost, $ 43,631 27,671
Total installed cost, $ Base -15,960
Total installed cost, % Base -37
Primary-secondary and VPF comparison
VPF SystemMinimum flow and control
VFDmodulating control valvefor minimum chiller flow
controlvalve
bypass line
P
P
P
P
VPF system - when to use?
Flows vary
Chillers with adaptive controls
Operator understands plant operation
Retrofits - even small jobs
Why consider VPF now?
Chiller control sophistication
First cost savings
Pump space
Pump wiring
Piping and connection
Operating cost savings
Pumps
Cooling Tower
Feedforward Control
Feedforward control is an open loop predictive control strategy that measures and compensates for load changes by using entering water temperature as an indication of load change.
With feedforward control, the chiller can respond faster to load changes.
Feedforward Control
Flow compensation works by calculating a new delta temperature as flow changes.
Maintains stability at low flow rates
Rejects disturbance caused by variable flow
UCP2 Feedback
42 º?? º
UCP 2
CH 530
CH 530 Feedback
42 º?? º
Feedforward
Σ
Capacity Control
w/o Water Flow Compensation
30
40
50
60
70
80
90
100
110
120
130
0:00:00 0:10:00 0:20:00 0:30:00 0:40:00 0:50:00
Time (hour:min:sec)
Wat
er T
emp
[deg
F]
-500.00
-300.00
-100.00
100.00
300.00
500.00
700.00
900.00
1,100.00
1,300.00
1,500.00
Wat
er F
low
[gp
m]
Evaporator Water Flow
Evap Entering Water Temp
Evap Leaving Water TempChiller off Chiller
off
Chiller on
50% Flow Reduction
With Compensation
Capacity Control
with Water Flow Compensation
30
40
50
60
70
80
90
100
110
120
130
0:00:00 0:10:00 0:20:00 0:30:00 0:40:00 0:50:00
Time (hour:min:sec)
Wa
ter
Te
mp
[d
eg
F]
-500.00
-300.00
-100.00
100.00
300.00
500.00
700.00
900.00
1,100.00
1,300.00
1,500.00
Wa
ter
Flo
w [
gp
m]
Evaporator Water Flow
Evap Entering Water Temp
Evap Leaving Water
Temp
variable primary flow
Advantages
Reduces capital investment
Saves mechanical-room space
Improves system reliability
VPF advantages
Lower Capital Cost
Fewer …
Pumps
Motors
Pump bases
Starters and wiring
Fittings and piping
Less labor
VPF advantages
More Available Space
Opportunity to …
Add other equipment
Select larger, more efficient chillers
Improve service access
VPF advantages
Improved Reliability
Provides system with …
Fewer pumps and accessories
Better balance between pumps and chillers online
VPF advantages
Greater Flexibility
any flow rate …
any T
chiller selection
Considerations
Evaporator flow limits (consult manufacturer)
Rate-of-change tolerance
Flow ―range-ability‖
Difference between design flow rate and evaporator’s minimum flow limit
chiller selection considerations
Evaporator Flow Limits
traditional limits 3.0 11–12
revised limits: standard 1.5 —tubes
high- 2.0 —performancetubes
flooded or falling-film evaporators
water velocity, fps
minimum maximum
4.6-to-1 turndown
1.9-to-1 turndown
variable flow Selection
chiller selection considerations
Evaporator Flow Limits
Purpose:
Lower limit … • refrigerant carryover
• controller stability
• heat transfer
Upper limit … • erosion
• affordable pressure
drop
chiller selection considerations
Rate-of-Change Tolerance
allowable flow-rate change*
chiller (compressor) type (% of design flow per minute)
• centrifugal 10% for process cooling30% for comfort cooling
• helical-rotary 10% for process cooling30% for comfort cooling
• scroll 10% for all applications
* Tolerances pertain specifically
to Trane chillers
What are other’s saying???
Variable Primary Flow Chilled Water
Plant Design …
VFP systems:
• Reduces total annual plant energy 3-8%
• Reduces first cost 4-8%
• Reduces life-cycle cost 3-5%*
*Relative to conventional Decoupled chilled-water systems.
VPF SystemMore information
Http:/trane.com/commercial/library/newsletters.asp (1999 and 2002)
―Don’t Ignore Variable Flow,‖ Waltz, Contracting Business, July 1997
―Primary-Only vs. Primary-Secondary Variable Flow Systems,‖ Taylor, ASHRAE Journal, February 2002
―Comparative Analysis of Variable and Constant Primary-Flow Chilled-Water-Plant Performance,‖ Bahnfleth and Peyer, HPAC Engineering, April 2001
―Campus Cooling: Retrofitting Systems,‖ Kreutzmann, HPAC Engineering, July 2002
Parallel VPF Systems
Series Configuration
Systems
58° F 50° F
42° F
moving to…
Series configuration -when should I use it?
Gas/electric (hybrid) fuel mix
Mixed chillers
Low-flow systems
Series configuration -benefits
Fuel flexibility
Control flexibility
Low distribution costs
VPF system configurationsSeries arrangement
Simple loading of either chiller
More efficient
upstream Chiller can be Absorption, Screw, etc….
VFD
VPF system configurationsSeries-Parallel Flow
VFD
41°F57°F
47.98°F
103.85°F 89.6°F89.6°F
89.6°F89.6°F
103.85°F
103.85°F103.85°F
570/730 Tons Simplex
45/55 split
VPF system configurationsSeries-Counter Flow
VFD
41°F57°F
48.96°F
103.82°F 89.6°F
96.63°F
89.6°F
103.82°F
96.63°F
650 Tons * 2 Simplex
50/50 split
Single
Compressor
Chiller
103.85° F
Lift
62.85° F
41° F
105.6° F
Lift
57.62° F
47.98° F
Series-Parallel flow
Arrangement
Upstream Chiller
102.12° F
Lift
61.12° F
41° F
Downstream Chiller
Upstream chiller: 105.6 - 47.98 = 57.62
Downstream chiller: 102.12 - 41 = 61.12
Average lift: 59.37 (vs. 62.85 for single compressor)
VPF system configurationsSeries-Parallel Flow
Single
Compressor
Chiller
103.82° F
Lift
62.82° F
41° F
103.82° F
Lift
54.86° F
48.96° F
Series-Counter flow
Arrangement
Upstream Chiller
96.63° F
Lift
55.63° F
41° F
Downstream Chiller
Upstream chiller: 103.82 - 48.96 = 54.86
Downstream chiller: 96.63 - 41 = 55.63
Average lift: 55.24 (vs. 62.82 for single compressor) (vs. 59.37 for series parallel flow (7%))
Better chiller efficiency, but high P
VPF system configurationsSeries-Counter Flow
Example : …
Let’s prove it from Topss Selection :
650-ton chiller
44.6°F chilled water with 9°F T
3 gpm/ton condenser water flow
initial selection
condenser flow rate:3 gpm/ton
Downstream chiller:
chilled water flow 1950 gpm (system)
condenser water flow 1300 gpm (chiller)
leaving chilled water 41°F
chiller capacity 45% of system total
Series-parallel Flow
downstream chiller:
Bundle size : 630
Series-parallel Flow
Upstream chiller:
chilled water flow 1950 gpm (system)
condenser water flow 1300 gpm (chiller)
leaving chilled water 47.98°F
chiller capacity 55% of system total
Series-parallel Flow
upstream chiller:
Selection #25
Series-parallel Flow
Downstream chiller:
chilled water flow 1950 gpm (system)
condenser water flow 2600 gpm (chiller)
leaving chilled water 41°F
chiller capacity 50% of system total
Series-counter Flow
downstream chiller:
Less pressure drop
Series-counter Flow
Upstream chiller:
chilled water flow 1950 gpm (system)
condenser water flow 2600 gpm (chiller)
leaving chilled water 48.96°F
chiller capacity 50% of system total
Series-counter Flow
upstream chiller:
Selection #7
Series-counter Flow
series system advantages:
better price & ROI
1
1. Series counter flow:Selection # 7 + 30.585Kw/ton, ave $307,366/chiller
2. Series parallel flow:Selection #41 + 250.615 kw/ton, ave $318,049/chiller
2
44.6/53.9F; 89.6 F / 3gpm/ton
Dubai 20,000 Tons Plant
Base Case:
10 Chillers
Evaporators and condensers piped in parallel
Cooling towers
Primary-Secondary chilled water system
Condenser water pumps
0.780 kW/ton at specified conditions
example chilled water plant …
Series-Series Counter flow
5.43 cents / kWh
$0.0068 / gallon of water
Economics
Base Case Layout
56 F
40 F
•Chilled water 56 - 40 F (16 ° T)
•Condenser flow rate of 3 gpm/ton
(10 ° T)
Alternative 1 – YD Chiller
Four 5000 ton chiller modules
Series-Counterflow
Primary-Secondary
0.703 kW/ton
Fewer pumps
Reduced chilled water flow rate (increased T)
Alt 1: Series Counterflow
104.5°F 99.7°F 95°F
57.25°F 48.2°F 39.2°FUpstream chiller Downstream chiller
Compressor Lift
Single
Compressor
Chiller
104.5° F
Lift
65.3° F
39.2° F
104.5° F
Lift
56.3° F
48.2° F
Series-
Counterflow
Arrangement
Upstream Chiller
99.7° F
Lift
60.5° F
39.2° F
Downstream Chiller
Upstream chiller: 104.5 - 48.2 = 56.3
Downstream chiller: 99.7 - 39.2 = 60.5
Average lift: 58.4 (vs. 65.3 for single compressor)
Better chiller efficiency
Alt 2: Decreased condenser rates, Trane Duplex chillers
Increased T (reduced flow) of chilled and condenser water
Reduced installed cost
Pipes
Pumps
Cooling towers
Chiller module is more efficient .650 kW/ton
Duplex chillers ―lift‖
Base cooling tower conditions
104.4° F
95° F
range 10° F
approach = 8° F87° F design
wet bulb
3 gpm/ton
Base cooling tower conditions
Base
Flow rate (gpm) 6000
Design wet bulb (deg F) 87
Approach (deg F) 8
EWT (deg F) 104.4
LWT (deg F) 95
Fan power (kW) 96
Affect of reduced flow on cooling towers
Reduce ―box size,‖ or...
Reduce fan power, or...
Reduce ―approach temperature‖
Same cooling tower at reduced flow rate
105.1° F
93° F
range 12.1° F
approach = 6° F87° F design
wet bulb
2.42 gpm/ton
Same cooling tower at reduced flow rate
Base Same tower
lower flow
Flow rate (gpm) 6000 4840
Design wet bulb (deg F) 87 87
Approach (deg F) 8 6
EWT (deg F) 104.4 105.1
LWT (deg F) 95 93
Fan power (hp) 96 96
Affect of temperatures on the chiller
Decreased chilled water leaving temperature takes more power
Increased condenser water leaving temperature takes more power
Alt 2: Trane Duplex Series Counterflow
105°F 99°F 93°F
57.25°F 48.2°F 39.2°FUpstream chiller Downstream chiller
102°F 96°F
52.7°F 43.7°F
Trane Duplex Series Counterflow, ―Average Lift‖
Upstream chiller
upstream circuit: 105 - 52.7 = 52.3
downstream circuit: 102 - 48.2 = 53.8
Downstream chiller
upstream circuit: 99 - 43.7 = 55.3
downstream circuit: 96 - 39.2 = 56.8
Average lift: 54.5 vs. 65.3 for single compressorvs. 58.4 for ―other‖ series counterflow (7%)
Better chiller efficiency
Alt 2: Summary
Reduced flows: installed cost savings
Smaller condenser pipes
Smaller chilled water pipes
Smaller cooling towers
Smaller condenser pumps
Smaller chilled water pumps
Operating cost savings
Better chiller efficiency (reduced lift due to Trane Duplex modules)
Reduced pumping power
Reduced make-up water consumption
Alt 3: Variable Primary Flow Reduced number of
pumps
Fittings
Piping
Electrical connections
Controls
Responds to ―Low T Syndrome‖
Reduced operating costs
Base case: 10 parallel chillers, primary-secondary, 16 ° T Chilled water, 10 ° T condenser water
4 Chiller modules, series counterflowprimary-secondary 18 ° T Chilled water, 10 ° T condenser water
Trane Duplex modules, series counterflow, primary-secondary, 18 ° T Chilled water, 12 ° T condenser water
Trane Duplex modules, series counterflow, variable primary flow18 ° T Chilled water, 12 ° T condenser water
Alternatives
Case 1 (competitor) Case 2 (competitor) Case 3 TAS/Trane Case 4 TAS/TraneParallel R-134a Chiller Design Series R-134a Chilling Design Series R-123 Chilling Design Series R123 Chilling Design
Primary Secondary Pumping Primary Secondary Pumping Primary Secondary Pumping Variable Primary & Reduced Chw pipe
Tabreed Type, York Chillers JBR, York/Stellar YD Chillers JBR, TAS/Trane Optimal, TAS/Trane
Capacity-TR 20000 20000 20000 20000
Chiller kW 15600 14056 12994 12994
Number of chillers 10 4 4 4
kw/TR 0.78 0.703 0.650 0.650
Evaporator Water GPM 30000 26668 26668 26668
Evaporator Water T-In 55.94 57.25 57.25 57.25
Evaporator Water T-Out 39.92 39.2 39.2 39.2
Evaporator Water dT 16.02 18.05 18.05 18.05
Condenser Water GPM 60000 60000 48400 48400
Condenser Water T-In 95 95 93 93
Condenser Water T-Out 104.54 104.54 105.1 105.1
Evaporator Water bHP/pump 122 214 117 0
Evaporator Water kW 909 638 348 0
kW/pump 91 160 87 0
Condenser Water bHP/pump 136 341 293 293
Condenser Water kW 1016 1016 872 872
kW/pump 101.6 254 218 218
Distribution Pump bHP 1940 1362 1356 1823
Distribution Pump bHP 1445 1015 1010 1358
Fan bHP 1293 1293 1293 1293
Fan kW 963 963 963 963
Fan kW/TR 0.0482 0.0482 0.0482 0.0482
Water Consuptiom GPM 879 879 852 852
Water Consumption gallons/ton-hour 2.64 2.64 2.56 2.56
Equipment Power 19933 17689 16187 16187
Misc Power 268 268 268 268
kw/TR 1.010 0.898 0.823 0.823
Annual Full Load Operating Hours
Water Rate $/gal 0.0068 0.0068 0.0068 0.0068
Energy Rate $/kW-HR 0.0543 0.0543 0.0543 0.0543
Annual Water Cost Total 1,738,216$ 1,721,515$ 1,634,278$ 1,634,278$
Annual Energy Cost 4,087,975$ 3,858,686$ 3,346,897$ 3,316,355$
Total Annual Operating Cost 5,826,191$ 5,580,202$ 4,981,175$ 4,950,633$
Savings Vs. Case 1 245,989$ 845,016$ 875,558$
Savings Vs. Case 2 599,027$ 629,568$
Savings Vs. Case 3 30,541$
Power Consumption
Financial Considerations
Analysis of Alternative 20,000 ton District Cooling Designs for the UAE (87WB)
Chiller
Pumps
Cooling Tower
Energy Use
-
10,000,000
20,000,000
30,000,000
40,000,000
50,000,000
60,000,000
70,000,000
80,000,000
kWh
Ba
se
- 1
0 c
hille
rs
4 M
od
ule
s -
Pri
ma
ry/S
eco
nd
ary
Tra
ne
Du
ple
x
mo
du
les,
Pri
ma
ry/S
eco
nd
ary
Tra
ne
Du
ple
x
mo
du
les,
Va
ria
ble
Pri
ma
ry F
low
Dubai, 20,000 ton plant, Annual kWh
Primary pumps
Distribution pumps
Condenser pumps
Tower Fans
Chillers
Estimated operating cost
$-
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
Ba
se
- 1
0 c
hill
ers
4 M
od
ule
s -
Prim
ary
/Se
co
nd
ary
Tra
ne
Du
ple
x
mo
du
les,
Prim
ary
/Se
co
nd
ary
Tra
ne
Du
ple
x
mo
du
les, V
aria
ble
Prim
ary
Flo
w
Dubai, 20,000 ton plant, Estimated Annual Operating Cost
Annual Make-
up water costAnnual Electric
Cost
=$599,000
Net Present Valueutility savings only
Dubai, 20,000 ton plant, Net Present Value
$-
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
Alt 2-1 Alt 3-1 Alt 4-1
Significant benefits available
By
Reducing condenser water flow
Reducing chilled water flow
Duplex series-counterflow arrangement
Trane Duplex modules
Save
Both capital and operating costs
VPF saves additional
Capital costs
Operating costs
example chilled water plant …
Series-Series Counter flow
Washington D.C. 10,500 tons chilled water plant
91.3 oF98.9 oF
55 oF37 oF
85 oF
45.1 oF
Conclusion :
Greater Focus on System Efficiency and …..
Lower Operating & Installation Cost Low-Flow Systems
annu
al e
nerg
y co
nsum
ptio
n, k
Wh
base case
chiller
cooling tower fans
low flow
750,000
600,000
450,000
300,000
150,000 pumps
0
2.4 gpm/ton
[0.043 L/s/kW]
44°F [6.7°C]
54°F[12.2°C]
85°F[29.4°C]
95°F[35°C]
3.0 gpm/ton
[0.054 L/s/kW]
ARI conditions1.5 gpm/ton
[0.027 L/s/kW]
41°F [5°C]
57°F[13.9°C]
85°F[29.4°C]
100°F[37.8°C]
2.0 gpm/ton
[0.036 L/s/kW]
low-flow conditions
evaporator
flow rate
condenser
flow rate
evaporator
flow rate
condenser
flow rate
Trend Toward Lower Flow Rates
EarthWise™
Chilled Water Systems
First
Cost
Operating
Cost
Exploit technology!
• Low flow
• Low temperature
• High efficiency
Leverage:
• Optimized Controls
• Variable Primary Flow
• Series Evaporators
Questions or Comments?