Claims Management and Disputes Jim Bidgood & Brian Krulick PRESENTED BY:

Upload: others

Post on 01-Jun-2020

21 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

Claims Management and Disputes

Jim Bidgood & Brian Krulick

PRESENTED BY:

Page 2: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

2

Managing Construction Disputes

Three Phases:

Pre-Construction

Construction

Post-Construction / Litigation

Page 3: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

3

Pre-Construction

Establish ESI Protocols

Organization

Retention

Shared File Management Systems

Page 4: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

4

Pre-Construction

Project Assessment

Commercial Team should consult with Construction/Project Implementation Team during contract negotiation

Due Diligence: Owner, General Contractor, Subcontractors

Page 5: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

5

Pre-Construction

Know when you have a Contract

“We never signed the contract”

Letters of Intent

Agreements to Agree

Page 6: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

6

Pre-Construction Carefully Read and Understand the Contract

Reporting Requirements

Notice Provisions

Flow-Down Provisions

Indemnity

Attachments, Exhibits, Incorporation by Reference

Priority

Page 7: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

7

Pre-Construction

Do Not Negotiate Murky or Potentially Problematic Provisions

Be Clear

Do Not Assume Your Interpretation Will Prevail

“For the avoidance of doubt…”

Page 8: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

8

Pre-Construction

Be Diligent and Thorough Performing Pre-Construction Work

Site/Field Inspections

Estimates

Schedules

Subcontractors

Materials/Equipment Procurement

Page 9: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

9

Pre-Construction

Project Schedules

Realistic and Executable

Include Procurement

Plan for Delays and Disruptions

Page 10: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

10

Pre-Construction

Identify Risks in Advance and Consult Specialists

Complex/Unusual Site Conditions

Local Laws/Building Codes

Government Relations

Page 11: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

11

Construction

Document Issues

Daily Reports

Letters

Site Meetings/Meeting Minutes

Executive Level Meetings

Page 12: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

12

Construction

Accurate Project Records

Review and Update Regularly

Photographs and Videos

Require All Personnel To Follow Protocols

Page 13: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

13

Construction

Deal With Issues As They Arise – Do Not Postpone Them

Open Communication

Trust But Verify

If you do postpone, make a record; do not waive claims

Tolling Agreements - Statute of Limitations

Page 14: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

14

Construction

Give Notice Properly

Timely

Method of Delivery

Contractually Designated Recipient

Strict Notice vs. Substantial Compliance

Page 15: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

15

Construction

Follow the Contract

Insist on it from your Counterparty

Field Directives – Authorized Representative Only

Failure to Follow Contract Waiver

Page 16: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

16

Construction Be Aware of Danger Zones

Delays

Scope/Extra Work

Inefficiency/Cumulative Impact Claims

Soils/Differing Site Conditions

Design

Quality of Work

Engage experts/specialists

Page 17: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

17

Construction

Keep Communications Professional

Stick to the facts, do not get personal

Electronic communications (email, texts, chats, etc.) are FOREVER

Do not use foul language

Do not air dirty laundry

Protect Privileged Communications

Page 18: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

18

Construction

Duty to Mitigate

Even if not in expressly stated in the Contract

Failure to mitigate can be a breach

Your own and your counterpart’s breach

Page 19: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

19

Post-Construction/Litigation

Claims/Litigation Team

Knowledgeable Project Personnel

Construction

Project Controls (Scheduling and Costs)

Page 20: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

20

Post-Construction/Litigation

Understand the Forum

Court vs. Arbitration

State Court vs. Federal Court

Jury Trial

Choice of Law

International Arbitration

Page 21: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

21

Post-Construction/Litigation

Always Look for Settlement Opportunities

Nothing is Guaranteed

Principles are Expensive

Settlement = Certainty

Page 22: Claims Management and Disputes - Smith Currie · Managing Construction Disputes Three Phases: Pre-Construction Construction Post-Construction / Litigation. 3 Pre-Construction Establish

22

James K. Bidgood, Jr.404.582.8031

[email protected]

Questions?Brian N. Krulick