CONCRETE WORKS (PRODUCTION,HAULAGE AND PLACING)
Objective
To define the standard procedures for production, transportation,
placement/compaction, curing and protection of plain and reinforced
structural concrete
Scope
This methodology covers all plant, labor, equipment, materials to be
used in performing all operations in connection with the furnishing,
manufacturing, transportation, placement, vibration, finishing and
curing of plain & reinforced concrete as per applicable codes and
standards given there in the contract documents. All concrete work will
conform to requirements of ACI 318-08 and modifications.
Procedures
Concrete Materials and Arrangements
Submittals Samples of specified materials such as cement,
admixtures, coarse and fine aggregates including names of sources
and their description along with relevant literature, delivery and
storage record, details of construction plant, shop drawings ,
method statements, certificates and mill test data, results of routine
tests and daily reports, bar bending schedules and concreting
record will be submitted for approval.
-
8/12/2019 Concrete Works (Main One)
2/11
Cement Ordinary Portland cement and slag cement as specified
conforming to ASTM C-150-98 type - 1 standard shall be brought,
stored in dry place, and tested whenever required. Only one brand
of each type of cement will be used for concrete in any individual
member of the structure and will be used as early as possible after
delivery at site. The mixing of different types of cements shall not be
adopted. Mill testing certificates will be produced from time to time.
Admixtures Admixtures such as air entraining agents, water
reducing admixtures including plasticizers or super plasticizers or
retarders will be used as approved and required by the Engineer.Admixtures will be well agitated to ensure uniformity before use in
concrete. Admixtures will comply with ASTM Designation C-494
Type D and will not contain calcium chloride. Admixture will be
handled and stored in accordance with the manufacturers
recommendations.
Coarse Aggregates Specified coarse aggregate will be obtained
and used of sizes given in mixed design from the approved sources.
The grading of the aggregates used will be conforming to ASTM C-
33-74 standards as specified in specifications. The size of the
aggregates will fall within the range of 3/16of an inch to 3 inches.
Coarse aggregate will consist of natural deposits or quarried and
crushed rock or boulders. The sum of the percentages of all the
deleterious substances will not exceed three percent, by weight.
Fine Aggregate - Fine aggregates will be hard coarse sand, crushed
stone or gravel obtained from approved quarry/source and shall
conform to requirements of ASTM C-33-99. The sum of the
-
8/12/2019 Concrete Works (Main One)
3/11
percentages of all the deleterious substances will not exceed five
percent, by weight.
Water - Potable water will be used for cleaning of aggregates,
mixing in concrete, mortar and grout and their curing. Water will be
obtained from source approved by the engineer and would be free
from injurious amounts of oil, acid, salt, alkali, organic matter. The
water for curing shall have PH value of 6 to 8 and shall not contain
impurities which cause de-coloration of concrete. The contaminated
water may only be used having specified impurities with their
permissible limits in unavoidable circumstances. Delivery and Storage Record comprising details of cement,
aggregates, chemicals/admixtures delivered at Batching Plant will
be maintained for any time inspection. Deliveries of different types
of concrete supplied at site shall also be recorded in details.
Covered Sheds (if required) will be installed to protect aggregates
from direct sun-heat. Separate stockpiles will be provided for each
size or classification of aggregates.
Constructional PlantDetails of major constructional plants such as
batching plants, mixers, concrete pumping equipment, hoists and
cranes along with general layout plans and flow diagram will be
submitted for the review and approval of the Engineer.
Inspection of Concrete Pouring Arrangements Verification and
approval of formwork and rebar fixing will be assured before the
preparation of delivery of any type of concrete. Batching Plant
operators will be very well conversant with the Concrete Mix
Designs of all required types of concrete.
-
8/12/2019 Concrete Works (Main One)
4/11
Quality Assurance ICPL will furnish certificates, mill-test-data,
calibration certificates of scales and machines.
Concrete Records ICPL will submit record of daily poured
concrete on approved format and pour slips.
Proportioning of Concrete
Trial mixes and tests will be carried out for the purpose of designing
the mixes and for quality control with regard to the required
strength, density and durability. It is pertinent to mention here that
different compressive strengths of concrete are required keeping in
view the size and load carrying capacity of the structural members.
Material Engineer will conduct trial mixes as directed by the
Engineer and cylinders samples will be casted with complete testing
record such as mix proportions, temperature, slump etc. The trials
will be done using at least 03 different w/c ratios which will produce
a range of strength required for the works. For each w/c ratio cylinders will be casted and tested. From
compressive strength test results, curve for strength vs w/c ratio will
be drawn to ascertain accurate w/c ratio required for desirable
compressive strength.
The cement contents and mixed proportions to be used will be such
that w/c ratio is not exceeded when maximum slump is permitted.
Concrete mixes will be designed to use the larger size and
maximum amount of coarse aggregate to produce the proper place-
ability, durability, compressive strength and other required
properties.
-
8/12/2019 Concrete Works (Main One)
5/11
Aggregates will be batched by weight. The weighing machine will be
accurate within 2% limits. In case of volumetric measurement,
control on volume shall be assured. The measuring boxes should
be deep and narrow and fitted with handle.
Calculated water will be added within 25 % of specified mixing time.
Approved Design Mixes will be conveyed to all lab & Production
control staff to avoid any mistake in the mix proportion handling.
Before raising formal inspection request, ICPL QA/QC Engineer
shall inspect the works and if found satisfactory, shall proceed with
the Engineers representative for final inspection & approval.
Concrete Production & Transportation
Batching Plant of sufficient capacity will be set up as per the
requirements of the project.
All types of concrete specified in the contract documents shall be
designed, produced and supplied by the in-house batch plants. Allconstructional plant will be set up as per approved Layout plan.
In case mixing machines are to be used, they must have sufficient
capacity to produce the concrete continuously without having any
cold joint. Minimum mixing time of 2 min shall be used for mixers
with 0.25 to 0.2 cum capacity.
Preferably computerized scales for weigh measurement of raw
material at batching plant will be installed and maintained. An
accurate recorder will be provided that shows batching weights.
Imprint made by a calendar type showing day, time etc.
-
8/12/2019 Concrete Works (Main One)
6/11
Approved Design Mixes will be conveyed to all lab & Production
control staff to avoid any mistake in the mix proportion handling.
Concrete will be transported from production to final deposit location
as rapidly as practicable to control the segregation and any loss of
required workability. The concrete will not be dropped more than
900 mm for transportation to prevent the segregation.
The w/c ratio shall be adjusted such that concrete with suitable
workability, density, impermeability, durability and required strength
could be obtained without the use of excessive amount of cement.
Addition of water to compensate the stiffening of concrete will not beadopted. Uniformity in concrete consistency from batch to batch
shall be assured.
Concrete will be transported with concrete pumps directly in contact
with batching plants and through transit mixers to the remote work
locations or any other arrangement like hoists or bucket operated
with tower crane.
Concrete Placing
After production and transportation of concrete all type of
confirmatory tests will be managed by Q/A & Q/C staff. This will
include slump test at batch plant & site, temperature control, lead
time control & homogeneity of concrete.
Concrete will be placed only after the approval of formwork, steel
fixing, embedded parts installation, bracing of form etc by the
Engineer. The concrete will be placed in such a manner which will
require as little re-handling as possible.
-
8/12/2019 Concrete Works (Main One)
7/11
Immediately before placing concrete, all surfaces upon or against
which the concrete is to be places will be free from standing water,
mud, debris or loose material. The surfaces of all absorptive
materials against which the concrete is to be placed shall be
thoroughly moistened in order to avoid any suction of water from
freshly placed concrete.
Placing will be carried out at such a rate that the concrete which is
being integrated with fresh concrete is will plastic. Concrete will be
places and compacted well within the initial setting time. Concrete
will be deposited as close as possible to its final position in the formand avoiding to maximum its horizontal movement.
The concrete will be consolidated by vibration so that concrete is
thoroughly worked around reinforcement, embedded items, into
corners of form eliminating all air and stone pockets which may
cause honeycombing and planes of weakness. Internal vibrators
shall have sufficient frequency and amplitude to achieve
consolidated concrete. At each insertion of vibrating shaft for 5 to 15
sec time shall be given for thorough consolidation.
The time between the mixing and placing will be reduced for rich
mixes or if the work is carried out at high temperature or exposed to
dry weather. In any circumstances this time span shall not exceed
30-45 minutes.
During placement care will be taken not to disturb rebar, have
proper walkways / passages, standby vibrators (mechanically or
electrically operated), temperature observation, approved
construction joints, avoiding cold joints & stability of embedded
-
8/12/2019 Concrete Works (Main One)
8/11
-
8/12/2019 Concrete Works (Main One)
9/11
mass concrete & 32 C for Normal concrete) in addition to the
approval of the Engineer.
The water for mixing concrete will be cooled by the use of crushed
ice & chillers. The ingredients will also be cooled before mixing with
water.
The aggregates may be stacked under shade if required. This will
be further cooled by sprinkling cold water on coarse aggregate.
Curing of Concrete
Freshly placed concrete will be protected against any premature
drying, excessively hot and cold temperature and will be maintained
with minimum moisture loss at constant temperature for the period
necessary for hydration of cement consequently hardening of
concrete.
Curing of concrete surfaces not in contact with form will be done
with water sprinkling, wet hessian cloth, covering with waterproofsheet or application of curing compound (if necessarily required).
Horizontal members like raft, foundations and slabs will be cured
with ponding on their top surface. Vertical members like walls,
columns and vertical sides of the beams will be cured with water
sprinkler and hessian cloth periodically is wetted.
Moisture loss from surfaces in contact with form shall be
continuously wet for controlling the temperature till the form is safely
removed. Curing will be continued for 14 days for all types of
concrete
-
8/12/2019 Concrete Works (Main One)
10/11
Curing period may be terminated earlier if the cylinders casted from
the relevant concrete member are placed in the vicinity with all
similar conditions shows 70% of average compressive strength on
their early testing (usually after 07 days).
During the curing period concrete will be protected from damaging
due to mechanical disturbances and excessive vibrations.
Testing of Concrete
During placement of concrete, cylinders will be casted for
compressive strength test as per the standards mentioned in the
specifications. ICPLs QA& QC engineer shall assist to the
Engineers staff from casting to crushing of cylinders at every stage.
After 07 & 28 days testing of the samples, report will be submitted
for approval of the Engineer. Generally one test sample consisting
of 06 # cylinders shall be prepared from any one class of concrete
per day or 50 cum of concrete whichever is greater. All six sampleswill be tested with division of 02# each on 03 days, 07 days & 28
days. Test cylinders will be clearly marked with date identification
mark and location of concrete.
A test sample data sheet for record purposes will be prepared for
each set of samples. For any concrete mix, compressive strength of
any one specimen or average compressive strength of three
specimens is not less than specified strength or the difference
between the greatest and least strengths is not more than 20% of
that average value.
-
8/12/2019 Concrete Works (Main One)
11/11
The test results will be compiled on monthly basis for complete
recording and ready references.
TOOLS & EQUIPMENTS
Batching plant, Concrete pumps, Vibrators, Slump cones, Personal
Protective Equipment, Cylinders, Wheel-barrows etc
Related documents
Corrective Action Request (CAR) form
Quality of Coarse/Fine aggregate.
Survey Report
Weather record
Flat and elongated particles
Calculation Sheet Aggregate Combination for Concrete Design Mix.
Specific gravity test
Cement Soundness test
Unit weight (Loose / Rodded)
Summary of Daily Concrete
Concrete compression test
Monthly / Weekly summary of compression strength of concrete
Request/Report for Inspection/Test (RIT)