Construction Documentation Report CEPRA 1596 CONSTRUCTION DOCUMENTATION REPORT VIRGINIA POINT WETLAND PROTECTION PROJECT CEPRA 1596 Prepared for: Texas General Land Office 1700 North Congress Avenue Austin, Texas 78701 Prepared by: AECOM 19219 Katy Freeway, Suite 100 Houston, TX 77094 September 30, 2016

Upload: others

Post on 31-Dec-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Construction Documentation Report CEPRA 1596

CONSTRUCTION DOCUMENTATION REPORT

VIRGINIA POINT

WETLAND PROTECTION PROJECT

CEPRA 1596

Prepared for:

Texas General Land Office

1700 North Congress Avenue

Austin, Texas 78701

Prepared by:

AECOM

19219 Katy Freeway, Suite 100

Houston, TX 77094

September 30, 2016

Page 2: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Construction Documentation Report CEPRA 1596

Table of Contents

Page

1.0 Construction Documentation Report ................................. 1

1.1 Statement of Work ............................................................................ 1

1.2 Construction Verification Report Organization ................................ 2

1.3 Conclusion......................................................................................... 2

Appendix A: Weekly Status Reports

Appendix B: Contractor Status Reports

Appendix C: Progress Meeting Notes

Appendix D: Submittals

Appendix E: Revision Documents

Appendix F: As-Built Drawings with Survey Verification

Page 3: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Construction Documentation Report CEPRA 1596

1.0 Construction Documentation Report

1.1 Statement of Work

From May 12, 2016 to September 19, 2016, AECOM performed construction oversight

activities to verify the quality of construction and the Contractor’s compliance with the

design documents for the Virginia Point Wetland Protection Project, CEPRA Project

1596. The work consisted of site visits and weekly progress reporting for the duration of

construction.

Field construction oversight tasks included the following activities:

Verify structure’s constructed elevations and lateral extents;

Document construction activities through site progress photos;

Conduct substantial completion inspection with GLO, which includes

preparing and issuing a punch list of items needing correction and issuing

the official Certificate of Substantial Completion for signature; and,

Conduct final inspection of project completion.

Office construction activities included the following items:

Undertake a pre-construction planning meeting at the site with the

Contractor;

Coordinate work activities with the Contractor;

Conduct monthly construction progress meetings with Contractor and

GLO and issue official minutes of the meeting;

Review and process the Contractor’s Submittals and Request for

Information (RFI’s);

Review Contractor’s invoices against progress and submit approval

recommendations based on percent complete; and,

Review Contractor’s closeout documents and transmit to GLO for record.

Page 4: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Construction Documentation Report CEPRA 1596

1.2 Construction Verification Report Organization

The report provides documentation of the materials that were used for construction, the

location of the structures that were built, and modifications to the base design that were

implemented. The report is organized into the following sections:

Appendix A – Weekly Status Reports

Appendix B – Contractor Status Reports

Appendix C – Progress Meeting Notes

Appendix D – Submittals

Appendix E – Revision Documents

Appendix F – As-Built Drawings with Survey Verification

1.3 Conclusion

Based on the field inspections and survey verification, the project was constructed in

accordance with the contract documents.

Page 5: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Appendix A

Weekly Status Reports

Page 6: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #1

PROJECT STATUS:

The following activities have been ongoing during the fourth week of construction:

Began receiving rip rap and toe protection stone from Texas and Kentucky sources

Began staking offshore breakwaters B15 – B30

Began placing rip rap for breakwater B30

ISSUES, RESOLUTIONS, AND NOTES:

Pre-construction survey and mobilization took place during the first week of construction

(week of April 25, 2016).

Kentucky rip rap will be used as primary source due to supply and transportation logistics.

Breakwater footprint templates will be based on +3.0’ crest elevation. Side slopes may be

adjusted on-site for +1.5’ crest elevations to achieve larger base template.

AECOM provided clarification on breakwater crest transitions from +3.0’ to +1.5’ elevations.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap for breakwaters

Site visit to be held with General Land Office on 5/18/16

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

To Carla Kartman, Project Manager, GLO Page 1

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #1

From Chris Levitz, PE, AECOM

Date May 12, 2016

Page 7: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

01-01 Offshore Stockpile of Rip Rap Stone

01-02 Rip Rap Stone (left) and Toe Proection Stone (right) Stockpiles

Page 8: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

01-03 Staging, Staking, and Construction

01-04 Rip Rap Placement for Breakwater B30

Page 9: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #2

PROJECT STATUS:

The following activities have been ongoing during the fifth week of construction:

Continued receiving rip rap and toe protection stone from Kentucky source.

Completed breakwaters B29 and B30. Construction verification survey performed.

Began placing rip rap for breakwater B28.

ISSUES, RESOLUTIONS, AND NOTES:

No construction activities performed on May 16th and part of May 17th due to weather.

Tides are generally high, but have not caused construction issues or delays.

Construction process used for breakwater B29 preferred to that used for B30 (building to

+3.0’ crest elevations and sloping down to +1.5’, rather than building from +1.5’ up to +3.0’).

Estimated construction pace is 3 to 4 breakwaters per week, given normal conditions.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap for breakwaters.

Site visit to be held with General Land Office on afternoon of 5/31/16.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #2

From Chris Levitz, PE, AECOM

Date May 18, 2016

Page 10: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

02-01 Construction of Breakwater B28

02-02 Completed Breakwater B29

Page 11: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

02-03 Completed Breakwaters B30 (left) and B29 (right)

02-04 Shallow Draft Staging Area

Page 12: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #3

PROJECT STATUS:

The following activities have been ongoing during the sixth week of construction:

Moved offshore staging area due northeast. New location approximated on attached figures.

Completed construction of breakwaters B28 and B27. Construction verification survey

forthcoming.

Began construction of breakwater B26.

ISSUES, RESOLUTIONS, AND NOTES:

Construction delays due to inclement weather.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for breakwaters.

Field meeting to be held with General Land Office on May 31, 2016 at 3 PM.

AECOM site visit scheduled for June 9, 2016.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #3

From Chris Levitz, PE, AECOM

Date May 24, 2016

Page 13: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

03-01 Completed Breakwater B27

03-02 Construction In Progress Breakwater B26

Page 14: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

03-03 Transporting Barge to Offshore Staging Area

03-04 Deep Draft Staging Area

Page 15: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B9

B1

B11

B5

B7

B12

B8

B14

B3B2

B4

B15

B13

B6

B10

B16

R1

A6

A10

A7

A9A8

A4

A1

A5

A2

A15

A3

A16

A13

A14

A17

A11

A12

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:05/25/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:05/25/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (14)

Staked, Not Constructed (2)

Construction In Progress (0)

Construction Complete (0)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress05/24/16

Page 16: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:05/25/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:05/25/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (17)

Staked, Not Constructed (13)

Construction In Progress (1)

Construction Complete (4)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

OffshoreStaging Area

Shallow DraftStaging Area

Construction Progress05/24/16

Page 17: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596Status Report #4

PROJECT STATUS:

The following activities have been ongoing during the seventh week of construction:

Field meeting held with General Land Office and Scenic Galveston on May 31, 2016 at 3 PM.

Completed construction of breakwaters B26 through B21. Construction verification survey

has been submitted for B30 through B25 and is under review.

Began construction of breakwater B20.

ISSUES, RESOLUTIONS, AND NOTES:

Construction delays due to inclement weather.

Up to four (4) signs to be placed at breakwater cells. Change order forthcoming.

o GLO to confirm if SG, GLO, and USFWS / CIAP logos and navigation warnings can

be shown on the same signs.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for breakwaters.

AECOM site visit scheduled for June 9, 2016.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #4

From Chris Levitz, PE, AECOM

Date May 31, 2016

Page 18: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

04-01 Completed Breakwaters

04-02 +3.0’ (High) and +1.5’ (Low) Crests of Breakwaters

Page 19: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

04-03 Pelicans Sitting on Breakwater

04-04 Shallow Draft Staging and Construction

Page 20: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B9

B1

B11

B5

B7

B12

B8

B14

B3B2

B4

B15

B13

B6

B10

B16

R1

A6

A10

A7

A9A8

A4

A1

A5

A2

A15

A3

A16A13

A14

A17

A11

A12

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:06/01/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:06/01/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (14)

Staked, Not Constructed (2)

Construction In Progress (0)

Construction Complete (0)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress05/31/16

Page 21: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:06/01/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:06/01/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (17)

Staked, Not Constructed (7)

Construction In Progress (1)

Construction Complete (10)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

OffshoreStaging Area

Shallow DraftStaging Area

Construction Progress05/31/16

Page 22: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #5

PROJECT STATUS:

The following activities have been ongoing during the eighth week of construction:

Six (6) full rock barges arrived and stone is being stockpiled in offshore staging area.

Completed staking breakwaters B14 through B11. Completed construction of breakwaters

B20 through B18; survey forthcoming. Began construction of breakwater B17.

ISSUES, RESOLUTIONS, AND NOTES:

Discussed placement of breakwater toe stones. Toe stone should generally be spread flat to

a height of 6 inches on offshore side of breakwaters, as opposed to mounding.

Noted that best construction practice is and will be to ensure construction team members are

safely out of the line of fire when working in the water near to the excavators.

Certified payroll records shall be submitted with each new invoice. Payroll records for existing

invoices will be back-submitted.

Rip rap gradations will be submitted for newly received stone.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for breakwaters.

AECOM site visit scheduled for June 16, 2016.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #5

From Chris Levitz, PE, AECOM

Date June 9, 2016

Page 23: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

05-01 Completed Breakwaters

05-02 Breakwater Construction Activities

Page 24: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

05-03 Unprotected Shoreline and Staking of Future Breakwaters

05-04 Stockpiled Rip Rap Stone

Page 25: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B9

B1

B11

B5

B7

B12

B8

B14

B3B2

B4

B15

B13

B6

B10

B16

R1

A6

A10

A7

A9A8

A4

A1

A5

A2

A15

A3

A16

A13

A14

A17

A11

A12

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:06/09/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:06/09/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (10)

Staked, Not Constructed (6)

Construction In Progress (0)

Construction Complete (0)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress06/09/16

OffshoreStaging Area

Page 26: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:06/09/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:06/09/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (13)

Staked, Not Constructed (8)

Construction In Progress (1)

Construction Complete (13)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress06/09/16

OffshoreStaging Area

Page 27: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #6

PROJECT STATUS:

The following activities have been ongoing during the ninth week of construction:

Completed staking breakwaters B10 through B9. Began construction of breakwater B14.

Completed construction of breakwaters B17 through B15. Performed construction survey of

breakwaters B19 through B16.

Performed repairs on spud barges and field equipment.

ISSUES, RESOLUTIONS, AND NOTES:

Low tide conditions slowed construction progress. This was compounded by the shallow work

near oyster reefs.

Navigation and construction around oyster reefs was not deemed a significant issue.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for breakwaters.

AECOM/Scenic Galveston site visit scheduled for June 23, 2016. Site visit with GLO

scheduled for June 29, 2016.

Change orders for site signage and removal of pilings to be issued.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #6

From Chris Levitz, PE, AECOM

Date June 16, 2016

Page 28: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

06-01 Completed Breakwater Cell

06-02 Breakwater in Low Tide Conditions

Page 29: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

06-03 Staking of Future Breakwaters

06-04 Unsubmerged Reef

Page 30: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B9

B1

B11

B5

B7

B12

B8

B14

B3B2

B4

B15

B13

B6

B10

B16

R1

A6

A10

A7

A9A8

A4

A1

A5

A2

A15

A3

A16

A13

A14

A17

A11

A12

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:06/20/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:06/20/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (8)

Staked, Not Constructed (5)

Construction In Progress (1)

Construction Complete (2)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress06/16/16

OffshoreStaging Area

Page 31: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:06/20/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:06/20/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (12)

Staked, Not Constructed (6)

Construction In Progress (1)

Construction Complete (16)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress06/16/16

OffshoreStaging Area

Page 32: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #7

PROJECT STATUS:

The following activities have been ongoing during the tenth week of construction:

Began construction of breakwater B12.

Completed construction of breakwaters B14 through B13.

ISSUES, RESOLUTIONS, AND NOTES:

Construction still taking place in shallow areas near oyster reefs.

Navigation and construction around oyster reefs was not deemed a significant issue, beyond

slower construction progress due to light-loading of barges.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for breakwaters.

Site visit with GLO scheduled for Wednesday, June 29th. Project meeting to precede

(location TBD).

Site visit with Scenic Galveston board members scheduled for Thursday, July 7th.

Change orders for site signage and removal of pilings to be issued.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #7

From Chris Levitz, PE, AECOM

Date June 23, 2016

Page 33: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

07-01 Construction of Breakwater B12

07-02 Changing Barges

Page 34: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

07-03 Second Cell of Breakwaters

07-04 Breakwater and Marine Debris

Page 35: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B9

B1

B11

B5

B7

B12

B8

B14

B3B2

B4

B15

B13

B6

B10

B16

R1

A6

A10

A7

A9A8

A4

A1

A5

A2

A15

A3

A16

A13

A14

A17

A11

A12

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:06/24/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:06/24/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (8)

Staked, Not Constructed (3)

Construction In Progress (1)

Construction Complete (4)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress06/23/16

OffshoreStaging Area

Page 36: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:06/24/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:06/24/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (12)

Staked, Not Constructed (4)

Construction In Progress (1)

Construction Complete (18)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress06/23/16

OffshoreStaging Area

Page 37: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #8

PROJECT STATUS:

The following activities have been ongoing during the eleventh week of construction:

Began construction of breakwater B31.

Completed construction of breakwaters B9 through B10.

Surveyors staked breakwaters B33 through B38 and conducted post-construction surveys.

ISSUES, RESOLUTIONS, AND NOTES:

Additional toe stone will be placed on all bay-facing sides of “Y” breakwaters (B9 and B31).

Per field observations, the areas indicated on the piling removal drawings generally reflect

the proposed pilings to be removed.

APOLLO will provide cost proposal for additional Project Signage and Piling Removal tasks.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for breakwaters.

Site visit with AECOM and SG scheduled for Thursday, July 7th.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #8

From Chris Levitz, PE, AECOM

Date June 29, 2016

Page 38: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

08-01 Pilings to be Removed

08-02 Breakwater Cell Facing Galveston Causeway

Page 39: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

08-03 Construction of “Y”-shaped Breakwater B9

08-04 Breakwater and Piping Plover

Page 40: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B9

B1

B11

B5

B7

B12

B8

B14

B3B2

B4

B15

B13

B6

B10

B16

R1

A6

A10

A7

A9A8

A4

A1

A5

A2

A15

A3

A16

A13

A14

A17

A11

A12

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:06/29/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:06/29/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (29)

Staked, Not Constructed (0)

Construction In Progress (1)

Construction Complete (7)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress06/29/16

OffshoreStaging Area

Page 41: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:06/29/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:06/29/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (12)

Staked, Not Constructed (2)

Construction In Progress (0)

Construction Complete (21)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress06/29/16

OffshoreStaging Area

Page 42: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #9

PROJECT STATUS:

The following activities have been ongoing during the twelfth week of construction:

Completed construction of breakwater B31. Began construction of breakwaters B34 and B35.

Surveyors conducted post-construction surveys.

Received 4-barge shipment of riprap.

ISSUES, RESOLUTIONS, AND NOTES:

Low tide conditions slowed construction progress.

Breakwaters B32 and B33 will be constructed at a later date, either when higher tides come

in or using shallow-water equipment (i.e., marsh buggies).

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for breakwaters.

Site visit with AECOM and SG scheduled for Thursday, July 14th.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #9

From Chris Levitz, PE, AECOM

Date July 7, 2016

Page 43: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

2

09-01 Construction of B34 and B35; Staking for B32 and B33

09-02 “Y”-Shaped Breakwater B31

Page 44: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

3

09-03 Completed Cell of Breakwaters from B31, Facing NE

09-04 Existing Marsh and Reef near B31

Page 45: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B9

B1

B11

B5

B7

B12

B8

B14

B3B2

B4

B15

B13

B6

B10

B16

R1

A6

A10

A7

A9A8

A4

A1

A5

A2

A15

A3

A16

A13

A14

A17

A11

A12

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:07/08/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:07/08/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (29)

Staked, Not Constructed (0)

Construction In Progress (0)

Construction Complete (8)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress07/07/16

Page 46: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:07/08/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:07/08/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (6)

Staked, Not Constructed (5)

Construction In Progress (2)

Construction Complete (22)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress07/07/16

OffshoreStaging Area

Page 47: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #10

PROJECT STATUS:

The following activities have been ongoing during the thirteenth week of construction:

Completed construction of breakwaters B35 – B37. Began construction of breakwater B38.

Surveyors conducted post-construction surveys and staked breakwaters B39 – B44.

ISSUES, RESOLUTIONS, AND NOTES:

Low tide conditions slowed construction progress. The nearshore end of Breakwater B32

may be field-adjusted (shortened) to account for shallow water conditions.

AECOM and APOLLO to coordinate on placement locations for the nearshore “A”

breakwaters and optional revetment.

Project signage will be placed on site; change order pending.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for breakwaters.

Site visit with AECOM and SG scheduled for Friday, July 22nd

.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #10

From Chris Levitz, PE, AECOM

Date July 14, 2016

Page 48: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

2

10-01 Construction of B37 and B38

10-02 Breakwaters B34 and B35

Page 49: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

3

10-03 Staking for Breakwaters B32 and B33

10-04 Second and Third Breakwater Cells

Page 50: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B9

B1

B11

B5

B7

B12

B8

B14

B3B2

B4

B15

B13

B6

B10

B16

R1

A6

A10

A7

A9A8

A4

A1

A5

A2

A15

A3

A16

A13

A14

A17

A11

A12

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:07/15/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:07/15/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (29)

Staked, Not Constructed (0)

Construction In Progress (0)

Construction Complete (8)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress07/14/16

Page 51: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:07/15/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:07/15/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (0)

Staked, Not Constructed (8)

Construction In Progress (1)

Construction Complete (26)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress07/14/16

OffshoreStaging Area

Page 52: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596Status Report #11

PROJECT STATUS:

The following activities have been ongoing during the thirteenth week of construction:

Completed construction of breakwaters B38 – B40 and B44. Began construction of

breakwater B43.

Surveyors staked breakwaters B1 – B8 and portions of breakwaters A1 – A17.

ISSUES, RESOLUTIONS, AND NOTES:

The nearshore end of Breakwater B32 may be field-adjusted (shortened) to account for

shallow water conditions. Also, this vicinity has an artifact cistern in the vicitnity that needs to

be marked for avoidance during construction.

AECOM and APOLLO to coordinate on placement locations for the nearshore “A”

breakwaters and optional revetment.

Project signage will be placed on site; change order pending.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for breakwaters.

Site visit with AECOM and SG scheduled for Friday, July 29th.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #11

From Chris Levitz, PE, AECOM

Date July 22, 2016

Page 53: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

2

11-01 Construction of B43

11-02 Transferring Stone Between Barges

Page 54: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

3

11-03 Completed Breakwaters B40 and B39

11-04 Construction Near Shoreline

Page 55: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B9

B1

B11

B5

B7

B12

B8

B14

B3B2

B4

B15

B13

B6

B10

B16

R1

A6

A10

A7

A9A8

A4

A1

A5

A2

A15

A3

A16

A13

A14

A17

A11

A12

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:07/22/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:07/22/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (11)

Staked, Not Constructed (18)

Construction In Progress (0)

Construction Complete (8)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress07/22/16

Page 56: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:07/22/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:07/22/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (0)

Staked, Not Constructed (4)

Construction In Progress (1)

Construction Complete (30)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress07/22/16

OffshoreStaging Area

Page 57: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #12

PROJECT STATUS:

The following activities have been ongoing during the fifteenth week of construction:

Site visit was omitted for the week of July 24th due to delay in rip rap shipment and storms

slowing construction progress. Next rip rap shipment is expected to arrive on or before

August 7th.

APOLLO, Scenic Galveston, Naismith, and AECOM waded on site to field-inspect proposed

locations of the nearshore “A” breakwaters and relocate for access and constructability.

ISSUES, RESOLUTIONS, AND NOTES:

Project team coordination is ongoing for locations for the nearshore “A” breakwaters and the

optional “R” revetment. Where possible, the -1.0’ contour may be used, longer breakwater

crests may be undulated, and breakwaters may be used in place of revetment.

Project signage will be placed on site; change order pending.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for breakwaters.

Construct breakwaters B1 through B8, followed by “A” breakwaters.

Site visit with AECOM and SG scheduled for Thursday, August 11th.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #12

From Chris Levitz, PE, AECOM

Date August 4, 2016

Page 58: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

2

12-01 Field Meeting for Placement of “A” Breakwaters

12-02 Reef and Shoreline near Breakwaters A12 – A17

Page 59: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

3

12-03 Shoreline Near Breakwaters A6 – A11

12-04 Shoreline Near Optional Additive Revetment, R1

Page 60: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B9

B1

B11

B5

B7

B12

B8

B14

B3B2

B4

B15

B13

B6

B10

B16

R1

A6

A10

A7

A9A8

A4

A1

A5

A2

A15

A3

A16

A13

A14

A17

A11

A12

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:08/04/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:08/04/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (11)

Staked, Not Constructed (18)

Construction In Progress (0)

Construction Complete (8)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress08/04/16

Page 61: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:08/04/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:08/04/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (0)

Staked, Not Constructed (2)

Construction In Progress (1)

Construction Complete (32)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress08/04/16

OffshoreStaging Area

Page 62: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #13

PROJECT STATUS:

The following activities have been ongoing during the seventeenth week of construction:

Site visit was omitted for the week of August 8th due to storms in the area which slowed

construction progress.

Moved equipment to the last offshore cell (B1 - B8) and brought shallow water marsh

excavating equipment on site. Began construction of breakwater B1.

ISSUES, RESOLUTIONS, AND NOTES:

Change Order #2 for project signage has been executed.

Executed ESI #1 to allow 2.5H:1V side slopes on breakwaters B1 – B8.

Issued ESI #2 for the revised alignment of breakwaters B7 – B8 and A1 – A12. SG to confirm

location of breakwaters.

ESI #3 is in progress for revising the optional additive revetment area.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for breakwaters. Construct breakwaters B1

through B8 and stake “A” breakwaters.

Site visit with AECOM and SG scheduled for Thursday, August 25th.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #13

From Chris Levitz, PE, AECOM

Date August 19, 2016

Page 63: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

2

13-01 Completed Breakwaters B32 and B33

13-02 Construction Equipment and Nearshore Staging Area

Page 64: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

3

13-03 Staking of Breakwater Cell B1 – B8

13-04 Construction of Breakwater B1

Page 65: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:08/22/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:08/22/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (14)

Staked, Not Constructed (7)

Construction In Progress (0)

Construction Complete (8)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress08/19/16

OffshoreStaging Area

A1A2

A3A4

A5A6

A7A8

A12A11A9

A10

B2

B3

B4

B5

B6

B7

B1

B8

R1

B15

B16

B14

B13

B12

B11

B10

B9

Page 66: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:08/22/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:08/22/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (0)

Staked, Not Constructed (0)

Construction In Progress (0)

Construction Complete (35)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress08/19/16

Page 67: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #14

PROJECT STATUS:

The following activities have been ongoing during the eighteenth week of construction:

Completed construction of breakwaters B1 – B5 and began construction of B6.

Naismith staked breakwaters B7 – B8 and A1 - A12 based on ESI #2.

ISSUES, RESOLUTIONS, AND NOTES:

Executed ESI #2 for the revised alignment of breakwaters B7 – B8 and A1 – A12.

ESI #3 is in progress for revising the optional additive revetment area.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for breakwaters. Complete construction of “B”

breakwaters and begin construction of “A” breakwaters.

Place project signage on site.

Site visit with AECOM, GLO, and SG scheduled for Thursday, September 1st at 10 a.m.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #14

From Chris Levitz, PE, AECOM

Date August 25, 2016

Page 68: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

2

14-01 Waves Breaking on Completed Breakwaters

14-02 Construction of Breakwater B6 and Breakwaters B1 – B5

Page 69: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

3

14-03 Breakwaters B1 – B3

14-04 Staking for Nearshore “A” Breakwaters

Page 70: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:08/25/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:08/25/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (1)

Staked, Not Constructed (14)

Construction In Progress (1)

Construction Complete (13)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress08/25/16

OffshoreStaging Area

A1A2

A3A4

A5A6

A7A8

A12A11A9

A10

B2

B3

B4

B5

B6

B7

B1

B8

R1

B15

B16

B14

B13

B12

B11

B10

B9

Page 71: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:08/25/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:08/25/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (0)

Staked, Not Constructed (0)

Construction In Progress (0)

Construction Complete (35)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress08/25/16

Page 72: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #15

PROJECT STATUS:

The following activities have been ongoing during the nineteenth week of construction:

Completed construction of breakwaters B6 – B7, A1 – A2, and A5 – A7.

Began construction of breakwater A4. Ordered final rip rap shipment (one barge).

ISSUES, RESOLUTIONS, AND NOTES:

ESI #3 is in progress for revising the optional additive revetment area.

Removing pilings is not anticipated to be completed under this contract.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for “A” breakwaters.

Place project signage on site.

Site visit with AECOM, GLO, NFWF, and SG scheduled for Thursday, September 8th at 10

a.m.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Rip rap shipment

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #15

From Chris Levitz, PE, AECOM

Date September 1, 2016

Page 73: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

2

15-01 Breakwater B4 – B8 and A1 – A2

15-02 Current Staging and Construction of Breakwater A4

Page 74: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

3

15-03 Staking for Breakwaters A8 – A12

15-04 Breakwaters A4 – A7

Page 75: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:09/01/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:09/01/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (1)

Staked, Not Constructed (6)

Construction In Progress (1)

Construction Complete (21)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress09/01/16

OffshoreStaging Area

A1A2

A3A4

A5A6

A7A8

A12A11A9

A10

B2

B3

B4

B5

B6

B7

B1

B8

R1

B15

B16

B14

B13

B12

B11

B10

B9

Page 76: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:09/01/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:09/01/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (0)

Staked, Not Constructed (0)

Construction In Progress (0)

Construction Complete (35)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress09/01/16

Page 77: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #16

PROJECT STATUS:

The following activities have been ongoing during the twentieth week of construction:

Completed construction of breakwaters A3 – A4 and A8 – A9.

Placed project signage.

Began construction of breakwater A10.

ISSUES, RESOLUTIONS, AND NOTES:

ESI #3 has been executed for revising the optional additive revetment area.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for “A”.

Stake and construct “R” breakwaters.

Site visit with AECOM, GLO, and SG scheduled for Thursday, September 15th at 10 a.m.,

pending Substantial Completion.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Rip rap shipment

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #16

From Chris Levitz, PE, AECOM

Date September 8, 2016

Page 78: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

2

16-01 Project Sigange

16-02 Breakwaters A10 – A8

Page 79: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

3

16-03 Completed Breakwaters A1 – A4

16-04 Breakwaters B1 – B2 and Project Sign

Page 80: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:09/08/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:09/08/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (2)

Staked, Not Constructed (2)

Construction In Progress (1)

Construction Complete (25)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress09/08/16

A1A2

A3A4

A5A6

A7A8

A12A11A9

A10

B2

B3

B4

B5

B6

B7

B1

B8

R1

B15

B16

B14

B13

B12

B11

B10

B9

R2

Page 81: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:09/08/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:09/08/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (0)

Staked, Not Constructed (0)

Construction In Progress (0)

Construction Complete (35)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress09/08/16

Page 82: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #17

PROJECT STATUS:

The following activities have been ongoing during the twenty-first week of construction:

Completed construction of breakwaters A10 – A12 and R1.

Began construction of breakwater R2.

ISSUES, RESOLUTIONS, AND NOTES:

Apollo will begin demobilizing upon completion of R2.

Aerial photo of site will be taken during low-tide conditions, as practicable.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Continue placing rip rap, toe stone, and sills for “R” breakwaters.

Complete and finalize construction surveys, aerial photo, and submittals.

Substantial completion site visit with AECOM and GLO on Monday, September 19th at 2 p.m.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Rip rap shipment

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #17

From Chris Levitz, PE, AECOM

Date September 15, 2016

Page 83: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

2

17-01 Wave Action on Offshore Breakwaters

17-02 Construction of R2

Page 84: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

3

17-03 Completed Breakwaters A11 and A12

17-04 Wave Action on Nearshore Breakwaters

Page 85: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:09/15/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:09/15/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (0)

Staked, Not Constructed (0)

Construction In Progress (1)

Construction Complete (29)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress09/15/16

A1A2

A3A4

A5A6

A7A8

A12A11A9

A10

B2

B3

B4

B5

B6

B7

B1

B8

R1

B15

B16

B14

B13

B12

B11

B10

B9

R2

Page 86: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:09/15/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:09/15/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (0)

Staked, Not Constructed (0)

Construction In Progress (0)

Construction Complete (35)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress09/15/16

Page 87: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

\

1

AECOM

19219 Katy Freeway

Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

CEPRA 1596 Status Report #18

PROJECT STATUS:

The following activities have been ongoing during the twenty-second week of construction:

Completed construction of breakwater R2 and began demobilizing.

Held substantial completion site visit.

ISSUES, RESOLUTIONS, AND NOTES:

Aerial photo of site will be taken during low-tide conditions, as practicable.

PROJECTED TASKS FOR THE NEXT TWO WEEKS:

Complete and finalize construction survey submittals and aerial photograph.

Complete demobilization.

File substantial completion certificate with GLO by Thursday, September 22nd

.

ISSUES THAT MAY IMPACT WORK SCHEDULE:

Inclement weather

Tides

To Carla Kartman, Project Manager, GLO Page 1 of 3

Subject CEPRA 1596 – Virginia Point Wetland Protection Project – Status Report #18

From Chris Levitz, PE, AECOM

Date September 19, 2016

Page 88: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

2

18-01 Completed Breakwaters R1 and R2, Looking North

18-02 Completed Breakwaters R1 and R2, Looking South

Page 89: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

3

18-03 Completed Breakwaters R1 and R2

18-04 Natural Reef, Project Sign, and Breakwater at Low Tide

Page 90: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:09/20/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:09/20/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (0)

Staked, Not Constructed (0)

Construction In Progress (0)

Construction Complete (30)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress09/19/16

A1A2

A3A4

A5A6

A7A8

A12A11A9

A10

B2

B3

B4

B5

B6

B7

B1

B8

R1

B15

B16

B14

B13

B12

B11

B10

B9

R2

Page 91: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:09/20/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:09/20/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (0)

Staked, Not Constructed (0)

Construction In Progress (0)

Construction Complete (35)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress09/19/16

Page 92: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Appendix B

Contractor Status Reports

Page 93: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 9, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

None None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No construction activities occurred.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 94: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 10, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

2 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Moved spud barges, equipment and small rock barges to area near B30. No construction activities occurred.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 95: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 11, 2016 WEATHER: Ptly Cldy, E/SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B30 Rock supply barges arrived in Dickinson and at staging area near B30. Staked perimeter of B30 and placed geotextile fabric. Placed rock for construction of B30. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 96: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 12, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B30 and B29 Placed rock for construction of B30. Using on-site survey equipment to measure elevations and verify breakwater alignment. Staked perimeter of B29. Installed geotextile fabric for B29.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: Representatives from AECOM and Scenic Galveston were on-site to view B30 construction.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 97: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 13, 2016 WEATHER: Ptly Cldy, E winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B29 Completed B30. Placed rock for construction of B29. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 98: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 14, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

None Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B29 Placed rock for construction of B29. Using on-site survey equipment to measure elevations and verify breakwater alignment. Staked perimeter of B28. Naismith Marine on site to install additional survey control point near B30.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 99: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 15, 2016 WEATHER: Cldy, light rain, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

None None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B29 and B28 Placed rock for construction of B29. Using on-site survey equipment to measure elevations and verify breakwater alignment. Completed B29. Installed geotextile fabric for B28.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 100: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-11-16 – Placing geotextile fabric for B30.

Page 101: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-12-16 – Initial placement of rock within B30 template.

5-13-16 – Completion of B30.

Page 102: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-14-16 – Construction of B29.

5-14-16 – Transferring rock to the work area.

Page 103: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-14-16 – Placement of toe stone for B29.

Page 104: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-14-16 – Placement of toe stone for sill between B30 and B29.

Page 105: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-15-16 – Water level view of B29.

Page 106: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 16, 2016 WEATHER: Cldy, Storms, rain, high SE

winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No construction activities occurred due to rain storms and high winds.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Heavy rain, storms and high winds prevented work activities.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 107: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 17, 2016 WEATHER: Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B28 Placed rock for B28. Using on-site survey equipment to measure elevations and verify breakwater alignment. Staked perimeter of B27. Naismith Marine on-site to survey B30 and B29.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 108: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 18, 2016 WEATHER: Cldy, AM rain, E/SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B28 Work delayed in early morning due to brief rain storm. Placed rock for construction of B28. Using on-site survey equipment to measure elevations and verify breakwater alignment. Representatives from GLO, AECOM and Scenic Galveston visit work area after progress meeting. Transferred rock to barges at staging area to allow relocation of the staging barge.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: Progress meeting with GLO, AECOM and Scenic Galveston representatives.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Early morning rain storm delayed work activities until mid-morning.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 109: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 19, 2016 WEATHER: Cldy, SE winds; strong storms,

50 to 60 mph winds during afternoon storms

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B28 Relocated staging barge to an area across from B27. Placed rock for construction of B28. Using on-site survey equipment to measure elevations and verify breakwater alignment. Stopped work and secured equipment, boats and barges due to incoming afternoon storm front.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Stopped work and secured equipment, boats and barges due to incoming afternoon storm front. Heavy rain and high winds up to 50 to 60 mph during the afternoon.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 110: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 20, 2016 WEATHER: Ptly Cldy, E winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B28 Placed rock for construction of B28. Using on-site survey equipment to measure elevations and verify breakwater alignment. Completed riprap placement on B28.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 111: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 21, 2016 WEATHER: Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B28 and B27 Placed toe stone to complete construction of B28 and sill between B29 and B28. Using on-site survey equipment to measure elevations and verify breakwater alignment. Placed geotextile fabric for B27. Started rock placement for B27. Stopped work mid-afternoon due to potential strong thunderstorm moving into area.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Stopped work at mid-afternoon due to potential strong thunderstorm moving into area.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 112: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 22, 2016 WEATHER: Cldy, AM TStorm, E/NE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

None None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B27 Placed rock for construction of B27. Using on-site survey equipment to measure elevations and verify breakwater alignment. Stopped work mid-morning due to incoming thunderstorm, lightning and high NE/E winds.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Stopped work mid-morning due to incoming thunderstorm, lightning and high NE/E winds.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 113: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-18-16 – Placing rock for B28.

5-18-16 – Transferring loaded barge from staging area to work area.

Page 114: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-20-16 – View of B28, B29 and B30.

Page 115: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-21-16 – Placing toe stone for sill between B29 and B28.

Page 116: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-21-16 – Placement of toe stone for B28.

Page 117: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-21-16 – Installing geotextile fabric for B27.

Page 118: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 23, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B27 and B26 Placed rock for construction of B27. Using on-site survey equipment to measure elevations and verify breakwater alignment. Staked perimeter of B26. Placed toe stone for B27 and sill between B28 and B27. Completed B27 and moved to B26. Placed geotextile fabric for B26.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 119: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 24, 2016 WEATHER: Cldy, E/SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B26 Placed rock for construction of B26. Using on-site survey equipment to measure elevations and verify breakwater alignment. Placed toe stone for sill between B27 and B26.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: AECOM representatives on-site for site inspection.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 120: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 25, 2016 WEATHER: Ptly Cldy, ES/SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B26 and B25 Place toe stone for B26. Moved to B25. Installed geotextile fabric for B25. Placed rock for construction of B25. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 121: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 26, 2016 WEATHER: Cldy, high SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B25 and B24 Placed toe stone for B25 and sill between B26 and B25. Moved to B24. Installed geotextile fabric for B24. Placed rock for B24. Naismith Marine on-site to survey B28, B27, B26 and B25. Installed toe stone for B24 and sill between B25 and B24. Moved to B23.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 122: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 27, 2016 WEATHER: Cldy, Very high SE winds

(25 to 40 mph winds), PM thunderstorms

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B23 Installed geotextile fabric for B23. Placed small amount of rock for construction of B23. Very high winds and surf conditions prevented safe barge movement to and from staging area. Stopped work mid-morning and secured equipment, boats and barges.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Stopped work around mid-morning and secured equipment, boats and barges due to very strong winds and surf conditions. Unsafe conditions for transferring rock barges.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 123: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 28, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B23 Placed rock for B23. Using on-site survey equipment to measure elevations and verify breakwater alignment. Placed toe stone for B23 and sill between B24 and B23. Moved to B22. Placed geotextile fabric for B22.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 124: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 29, 2016 WEATHER: Ptly cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B22 Placed rock for construction of B22. Using on-site survey equipment to measure elevations and verify breakwater alignment. Shallow water conditions slowed barge transferring activities. Placed toe stone for B22 and sill between B23 and B22. Moved to B21.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 125: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-24-16 – Placing rock for B26.

5-26-16 – Installing toe stone for B25.

Page 126: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Completion of B24.

5-26-16 – Installing toe stone for sill between B25 and B24.

Page 127: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-27-16 – View of B24 thru B30 during high wind and wave conditions.

5-28-16 – Finalizing B23.

Page 128: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-29-16 – View of B27 thru B23 during low tide conditions.

5-29-16 – Constructing B22.

Page 129: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 30, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B21 Placed geotextile fabric for B21. Placed rock for construction of B27. Using on-site survey equipment to measure elevations and verify breakwater alignment. Very shallow area along south end of B21 which made access difficult. Staked perimeter of B20. Placed toe stone for B21 and sill between B22 and B21. Moved to B20.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 130: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: May 31, 2016 WEATHER: Ptly Cldy, E/SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B20 Placed geotextile fabric for B20. Placed rock for construction of B20. Using on-site survey equipment to measure elevations and verify breakwater alignment. Very slow progress due to low tide conditions.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: GLO, AECOM and Scenic Galveston representatives tour the work area.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 131: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 1, 2016 WEATHER: Cldy, Rain showers, E/SE

winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B20 Continue placing rock to complete B20. Placed toe stone and sill between B21 and B20. Using on-site survey equipment to measure elevations and verify breakwater alignment. Naismith Marine on site to survey completed breakwaters B24 thru B20 and stake B14 thru B9. Move to B19. Six (6) full rock barges arrive and are placed at the staging area.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 132: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 2, 2016 WEATHER: Cldy, TStorms, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B19 Placed geotextile fabric for B19. Stopped work due to incoming thunderstorms, heavy rain and lightning.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Stopped work around mid-morning due to incoming thunderstorms, heavy rain and lightning.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 133: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 3, 2016 WEATHER: Cldy, thunderstorms, lightning,

SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B19 No work conducted due to thunderstorms and lightning.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: No work conducted due to thunderstorms and lighting.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 134: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 4, 2016 WEATHER: Cldy, Thunderstorms, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B19 No work conducted due to thunderstorms.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: No work conducted due to thunderstorms.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 135: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 5, 2016 WEATHER: Ptly cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B19 Placed rock for construction of B19. Using on-site survey equipment to measure elevations and verify breakwater alignment. Staked perimeter of B18.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 136: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-30-16 – Installing geotextile fabric for B21.

5-30-16 – View of B21 prior to installing toe stone.

Page 137: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

5-31-16 – Installing geotextile fabric for B20.

6-1-16 – Placing rock for B20.

Page 138: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

6-1-16 – Placing toe stone along B20.

Page 139: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

6-5-16 – View of B20 thru B30.

Page 140: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 6, 2016 WEATHER: Ptly Cldy, N winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B19 and B18 Completed B19. Moved to B18 and placed geotextile fabric for first half of B18. Placed rock for construction of first half B18. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 141: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 7, 2016 WEATHER: Ptly Cldy, E/NE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B20 Continue placing rock for first half of B18. Placed toe stone for sill between B19 and B18. Placed geotextile fabric for second half of B18. Placed rock for construction of second half of B18. Using on-site survey equipment to measure elevations and verify breakwater alignment. Very slow progress due to low tide conditions and accessing around oyster reef.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 142: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 8, 2016 WEATHER: Ptly Cldy, E/SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B18 Continue placing rock to complete B18. Placed toe stone along B18. Using on-site survey equipment to measure elevations and verify breakwater alignment. Moved to B17 and placed geotextile fabric for B17. Began placing rock for B17. Very shallow water slowed progress.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 143: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 9, 2016 WEATHER: Ptly Cldy, TStorms, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B17 Continue placing rock for B17. Place toestone for sill between B18 and B17. Using on-site survey equipment to measure elevations and verify breakwater alignment. Staked perimeter of B16. Stopped work in early afternoon due to potential incoming thunderstorms.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: AECOM and Scenic Galveston representatives toured the work area.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Stopped work in early afternoon due to potential incoming thunderstorms.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 144: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 10, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B17 and B16 Complete rock placement for B17. Placed toe stone along B17. Using on-site survey equipment to measure elevations and verify breakwater alignment. Moved to B16 and placed geotextile fabric.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 145: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 11, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B16 Place rock for B16. Using on-site survey equipment to measure elevations and verify breakwater alignment. Very low tide in early morning and late afternoon slows progress.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 146: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 12, 2016 WEATHER: Cldy, TStorms, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B16 Placed rock for construction of B16. Using on-site survey equipment to measure elevations and verify breakwater alignment. Very low tide in early morning slows progress. Stopped work at approximately 4:30 pm due to incoming thunderstorms and lightning.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Stopped work at approximately 4:30 pm due to incoming thunderstorms and lightning.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 147: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

6-6-16 – Placing rock for B18.

6-7-16 – Continuing second half of B18.

Page 148: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

6-8-16 – View of first half of B18 looking south.

6-9-16 – View of rip rap and toe stone on storage barges at staging area.

Page 149: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 13, 2016 WEATHER: Ptly Cldy, S winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B16 and B15 Continued rock placement for B16. Using on-site survey equipment to measure elevations and verify breakwater alignment. Placed toe stone for B15 for completion. Moved to B15 and placed geotextile fabric. Placed rock for construction of B15. Naismith Marine on site to survey B19, B18, B17 and B16. Also staked B10 and B9.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 150: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 14, 2016 WEATHER: Ptly Cldy, S/SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B15 Continue placing rock for B15. Placed toe stone for sill between B16 and B15. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 151: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 15, 2016 WEATHER: Ptly Cldy, S winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B15 and B14 Continue placing rock to complete B18. Placed toe stone along B15. Using on-site survey equipment to measure elevations and verify breakwater alignment. Completed B15 and moved to B14. Placed geotextile fabric for B14. Began placing rock for B14. Very low tide conditions slowed progress.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 152: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 16, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

12 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Made repairs to spud barge. Some of the internal bracing for the deck plates needed welding and repairs. Made repairs to cracked bucket on trackhoe at staging area. Naismith Marine on site to survey B15 and update files for on site survey equipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: AECOM representatives toured the work area.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Spud barge at breakwater area and trackhoe bucket at staging area needed repairs.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 153: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 17, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

12 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Made repairs to spud barge. Some of the internal bracing for the deck plates needed welding and repairs. Made repairs to cracked bucket on trackhoe at staging area..

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Spud barge at breakwater area and trackhoe bucket at staging area needed repairs.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 154: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 18, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B14 Place rock for B14. Using on-site survey equipment to measure elevations and verify breakwater alignment. Very low tide in early afternoon slows progress.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 155: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 19, 2016 WEATHER: Ptly Cldy,SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

3 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Made repairs to cracks on one spud for the spud barge at breakwater area.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Made repairs to cracks on one spud for the spud barge at breakwater area.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 156: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

6-13-16 – Placing toe stone for B16.

6-14-16 – Placing toe stone for sill between B16 and B15.

Page 157: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

6-18-16 – Placing rock for B14.

6-18-16 – Low tide conditions exposes oyster reef.

Page 158: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 20, 2016 WEATHER: Ptly Cldy, S winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B14 and B13 Placing rock to complete B14. Placed toe stone for B14. Move to B13 and install geotextile fabric. Begin placing rock for B13. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 159: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 21, 2016 WEATHER: Ptly Cldy, S/SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B13 and B12 Continue placing rock for B13. Placed toe stone for sill between B14 and B13 and along B13. Complete B13 and move to B12. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 160: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 22, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B12 Place geotextile fabric for B12. Place rock for B12. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 161: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 23, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B12 and B11. Continue placing rock for B12. Complete B12. Place toe stone for sill between B13 and B12 and along B12. Using on-site survey equipment to measure elevations and verify breakwater alignment. Move to B11 and place geotextile fabric for B11. Naismith Marine on site to survey B15, B14 and B13.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: AECOM and Scenic Galveston representatives toured the work area.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 162: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 24, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B11 Placed rock for B11. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 163: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 25, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B11 and B10 Continue placing rock for B11. Place toe stone for sill between B12 and B11 and along B11. Complete B11 and move to B10. Place geotextile fabric for B10. Start placing rock for B10. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 164: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 26, 2016 WEATHER: Ptly Cldy,SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

7 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Performed general maintenance on equipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 165: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

6-20-16 – View of B14 looking south.

6-21-16 – Placing toe stone along B13.

Page 166: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

6-23-16 – Placing geotextile for B11.

Page 167: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

6-25-16 – View of B11 looking south.

Page 168: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 27, 2016 WEATHER: Ptly Cldy, S winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B10 Placing rock to complete B10. Using on-site survey equipment to measure elevations and verify breakwater alignment. Placed toe stone for B10. Move to B9. Low tide prevented moving into NW extension of B9.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 169: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 28, 2016 WEATHER: Ptly Cldy, E/SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B9 Waited for tide to rise in order to move spud barge into position to start NW extension of B9. Moved barge as far as possible into NW portion of B9. Started to place geotextile fabric but storm clouds moved in with a significant amount of lighting. Stopped work after lunch.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Stopped work after lunch due to storm clouds moving in with a significant amount of lighting around the work area.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 170: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 29, 2016 WEATHER: Ptly Cldy, E winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B9 Place geotextile fabric for NW extension of B9. Started placing rock for B9. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: GLO, AECOM and Scenic Galveston representatives on-site for progress meeting and tour of work area. AECOM requested that additional toe stone be placed along certain portions of B9 and B31.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 171: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: June 30, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B9. Continue placing rock for B9. Using on-site survey equipment to measure elevations and verify breakwater alignment. Placed additional toe stone as AECOM requested. Completed NW extension and moved to N portion of B9. Place geotextile fabric and begin placing rock. Naismith Marine on site to survey B12, B11 and B10 as well as stake B33 thru B38. Low tide slowed barge transfer in afternoon.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: AECOM and Scenic Galveston representatives toured the work area.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 172: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 1, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B9 Completed placing rock for N portion of B9. Toe stone along N portion of B9. Placed additional toe stone as AECOM requested. Moved to S portion of B9. Placed geotextile fabric and started placing rock. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 173: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 2, 2016 WEATHER: Ptly Cldy, high SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B9 and B31 Completed S portion of B9. Placed toe stone along S portion of B9 as well as for sill between B9 and B10. Moved to B31. Placed geotextile fabric for W extension of B31 and began placing rock. Using on-site survey equipment to measure elevations and verify breakwater alignment. Installed additional toe stone as AECOM requested. Completed W extension of B31. Low tide prevented moving the spud barge.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 174: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 3, 2016 WEATHER: Ptly Cldy, high SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B31 Moved spud barge into position for N portion of B31. Prepared geotextile fabric. Performed general maintenance on equipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 175: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

6-27-16 – View of B10 looking south.

6-29-16 – Placing additional toe stone along NW extension of B9.

Page 176: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

6-29-16 – Transferring very light rock barges to B9 due to depth and tide conditions.

7-1-16 – View of B9 along S portion of breakwater.

Page 177: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

7-2-16 – Partial view of B9 completed.

7-2-16 – Placing geotextile fabric for W extension of B31.

Page 178: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

7-2-16 – Completed W extension of B31.

Page 179: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 4, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B31 Placing rock to complete N end of B31. Placed toe stone along this portion. Moved to S end of B31. Placed geotextile fabric and started placing rock. Using on-site survey equipment to measure elevations and verify breakwater alignment. Placed toe stone for S end of B31 plus additional area requested by AECOM. B31 completed.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 180: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 5, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B34 Tried to move to B32 and B33 but water was too shallow due to low tide. Moved to B34 and placed geotextile fabric. Begin placement of rock. Using on-site survey equipment to measure elevations and verify breakwater alignment. Tide levels dropped significantly after lunch. Steering cable broken on shallow water tug boat so work stopped around 3:30 pm.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Stopped work in afternoon due to broken steering cable on shallow water tug boat.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 181: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 6, 2016 WEATHER: Ptly Cldy, E winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B9 Made repair to shallow water tug boat. Continued placing rock for B34. Placed toe stone and completed B34. Water too shallow due to low tide so could not move to B35. Current position of the spud barge enabled placement of geotextile fabric on N half of B35. Placed rock on N end of B35. Using on-site survey equipment to measure elevations and verify breakwater alignment. Naismith Marine on site to survey B9, B31 and B34.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 182: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 7, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B35 Moved spud barge in front of B35. Placed remaining geotextile fabric and started placing additional rock. Using on-site survey equipment to measure elevations and verify breakwater alignment. Low tide prevented shallow barge transfer in afternoon. Four (4) new loaded rock barges arrived. They could not access the staging area due to low tide and shallow water.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: AECOM and Scenic Galveston representatives toured the work area.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Low tide in the afternoon prevented access for shallow water barges.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 183: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 8, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B35 Waited for high tide in late morning. Majority of the day spent gradually moving the four (4) new rock barges to the staging area as water depths allowed. All new rock barges were moved to final staging area. No barge access to B35 in the afternoon due to shallow water and low tide.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: No access for shallow water barges for B35 due to low tide conditions.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 184: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 9, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B35 Waited for high tide by mid-morning to move in shallow water rock barges for B35. Placed additional rock and toe stone to complete B35. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 185: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 10, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Tried to move spud barge into position for B36 but tide levels did not rise enough so the water was too shallow. Performed general maintenance on equipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 186: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

7-4-16 – View of completed N end of B31.

7-4-16 – View of completed S end of B31. Placing additional toe stone along S end.

Page 187: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

7-5-16 – Placing geotextile fabric for B34.

7-6-16 – Completion of B34.

Page 188: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

7-7-16 – No access for shallow water barges due to tide conditions.

7-9-16 – Placing toe stone for B35.

Page 189: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 11, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B36 Moved to B36. Placed geotextile fabric and started placing rock. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 190: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 12, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B36 and B37 Continued placing rock on B36. Placed toe stone and completed B36. Moved to B37. Placed geotextile fabric.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 191: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 13, 2016 WEATHER: Ptly Cldy, E winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B37 Made upgrades to locking and securing mechanisms for the metal storage box and small skiff. Started placing rock for B37. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain: Someone broke into the locked metal storage container last night and stole hand tools and power tools. There was an attempt to steal the small skiff that was secured on the barge but it remained on site.

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 192: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 14, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B37 and B38 Completed riprap and toe stone placement for B37. Moved spud barge to B38. Placed geotextile fabric and started placing rock. Using on-site survey equipment to measure elevations and verify breakwater alignment. AECOM and Scenic Galveston representatives tour the work areas. Naismith Marine on site to survey B35, B36 and B37. They also staked B39 thru B44.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: AECOM and Scenic Galveston representatives toured the work areas.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 193: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 15, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B38 and B39 Continue placing rock for B38. Place toe stone and complete B38. Move to B39. Placed geotextile fabric.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 194: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 16, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B39 Started placing rock for B39. Using on-site survey equipment to measure elevations and verify breakwater alignment. Transferred rock from one loaded rock barge staged near the ship channel. Moved barge to staging area near work area.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 195: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 17, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Transferred rock from remaining loaded rock barge near ship channel and moved it to the staging area near the work area.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 196: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 18, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B39 Continue placing rock for B39. Using on-site survey equipment to measure elevations and verify breakwater alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 197: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 19, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B39 and B40 Finish placing rock for B39. Using on-site survey equipment to measure elevations and verify breakwater alignment. Move to B40. Place geotextile fabric. Started placing rock for B40.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 198: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 20, 2016 WEATHER: Ptly Cldy, E winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B40 and B44. Continue placing rock for B40. Using on-site survey equipment to measure elevations and verify breakwater alignment. Finished work for B40. Moved to B44 to take advantage of higher tide. Placed geotextile fabric and started placing rock.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 199: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 21, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B44 Continue placing rock for B44. Using on-site survey equipment to measure elevations and verify breakwater alignment. Finished work for B44. Naismith Marine on site to survey B38, B39, B40 and B44. Also staked B1 thru B8 and several of the A breakwaters.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 200: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 22, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B43 Moved to B43. Placed geotextile fabric and started placing rock. AECOM and Scenic Galveston representatives tour the work areas.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: AECOM and Scenic Galveston representatives tour the work areas.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 201: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 23, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities occurred.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 202: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 24, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities occurred.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 203: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 25, 2016 WEATHER: Cldy, SE winds, afternoon

lightning and rain storms

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B43 and B42 Continue placing rock for B43. Using on-site survey equipment to measure elevations and verify breakwater alignment. Completed B43 and moved to B42. Placed geotextile fabric for B42. Severe lightning and rain storms stopped field activities at approximately 2 pm.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Severe lightning and rain storms stopped field activities at approximately 2 pm.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 204: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 26, 2016 WEATHER: Ptly Cldy, SE winds, afternoon

thunderstorms

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B42 Start placing rock for B42. Using on-site survey equipment to measure elevations and verify breakwater alignment. Low tide conditions in the afternoon making access difficult for small tug boat. Thunderstorms in the area and lightning stop field activities at approximately 4 pm.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 205: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 27, 2016 WEATHER: Cldy, SE winds, morning

thunderstorms

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B42 and B41. Waited for morning thunderstorms to pass through area. Started work at approximately 9 am. Continue placing rock for B42. Using on-site survey equipment to measure elevations and verify breakwater alignment. Finished work for B42. Moved to B41. Placed geotextile fabric and started placing rock.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Morning thunderstorms delayed the start of work activities until approximately 9 am.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 206: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 28, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B41 Continue placing rock for B41. Using on-site survey equipment to measure elevations and verify breakwater alignment. Used remaining rock and stopped work at approximately 3 pm. Waiting for delivery of next rock shipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting for delivery of next rock shipment.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 207: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 29, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities. Waiting for delivery of next rock shipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting for delivery of next rock shipment.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 208: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 30, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities occurred. Waiting for delivery of next rock shipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting for delivery of next rock shipment.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 209: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: July 31, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities occurred. Waiting for delivery of next rock shipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting for delivery of next rock shipment.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 210: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Placing toe stone along B42.

View of B42, B43 and B44.

Page 211: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 1, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities occurred. Waiting for delivery of next rock shipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting for delivery of next rock shipment.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 212: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 2, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities occurred. Waiting for delivery of next rock shipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting for delivery of next rock shipment.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 213: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 3, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities occurred. Waiting for delivery of next rock shipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting for delivery of next rock shipment.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 214: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 4, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

2 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities occurred. Waiting for delivery of next rock shipment. AECOM, Scenic Galveston and APOLLO representatives reviewed access and constructability issues for remaining breakwaters. Naismith Marine on site to assist with surveying existing oyster reef boundaries.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: AECOM, Scenic Galveston and APOLLO representatives reviewed access and constructability issues for remaining breakwaters.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting for delivery of next rock shipment.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 215: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 5, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities. Waiting for delivery of next rock shipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting for delivery of next rock shipment.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 216: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 6, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities occurred. Waiting for delivery of next rock shipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting for delivery of next rock shipment.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 217: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 7, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

3 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Next rock shipment arrives on site. Stage rock barges with spud barges near previous staging location. Working on repairs to large tug boat.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 218: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 8, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities occurred. Waiting for repairs to APOLLO tug boat.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting for repairs on APOLLO tug boat.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 219: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 9, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No field activities occurred. Waiting for repairs to APOLLO tug boat.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting for repairs to APOLLO tug boat.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 220: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 10, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

3 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Transferred spud barge and deck barge to work areas.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 221: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 11, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

3

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Transferred additional deck barges, marsh excavators and work barges to work areas near B41. Staged rock barges for unloading purposes.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 222: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 12, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B41 and B32 Staged work barges at B41. Placed small amount of rock to complete the remaining portion of B41. Used on-site survey equipment to confirm elevations and alignment. Moved barges and marsh hoe excavators to B32. Low tides in the afternoon limited access for small rock barges and shallow water tug boat.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Low tides in afternoon prevented access for small rock barges and shallow water tug boat.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 223: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 13, 2016 WEATHER: Cldy, S winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B32 Placed geotextile fabric for B32. Started placing rock for B32. Used on-site survey equipment to confirm elevations and alignment. Transferring rock to the breakwater is restricted due to low tides and limited access with small rock barges and shallow water tug boat.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Transferring rock to the breakwater is restricted due to low tides and limited access with small rock barges and shallow water tug boat.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 224: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 14, 2016 WEATHER: Cldy, Thunderstorms, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None No work activities occurred due to thunderstorms and lightning in the area.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: No work activities occurred due to thunderstorms and lightning in the area.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 225: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

8-12-16 - Placing rock for remaining portion of B41.

8-12-16 - Completion of B41.

Page 226: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

8-13-16 - Transferring rock from multiple barges to access B32 in very shallow water.

8-13-16 - Placing rock over geotextile fabric for B32 using marsh excavator equipment.

Page 227: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 15 , 2016 WEATHER: Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B32 Continue placing rock for B32. Used on-site survey equipment to confirm elevations and alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 228: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 16, 2016 WEATHER: Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B32 and B33 Complete B32. Move to B33 and place geotextile fabric. Begin placing rock. Work stopped mid-afternoon due to incoming thunderstorm.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Work stopped mid-afternoon due to incoming thunderstorm.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 229: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 17, 2016 WEATHER: Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B33 Continue placing rock for B33. Used on-site survey equipment to confirm elevations and alignment. Completed B33.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 230: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 18, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B1 Moved work barges and marsh excavators to B1. Placed geotextile fabric. Begin placing rock for B1. Used on-site survey equipment to confirm elevations and alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 231: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 19, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B1 and B2 Continue placing rock for B1. AECOM and SG representatives tour work area. Used on-site survey equipment to confirm elevations and alignment. Complete B1. Move to B2 and place geotextile fabric.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 232: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 20, 2016 WEATHER: Ptly Cldy, S winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B2 and B3 Started placing rock for B2. Used on-site survey equipment to confirm elevations and alignment. Completed B2. Move to B3 and place geotextile fabric and start placing rock.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 233: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 21, 2016 WEATHER: Ptly Cldy, S winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B3 Continue placing rock for B3. Used on-site survey equipment to confirm elevations and alignment. Stopped work in early afternoon due to strong thunderstorms and lightning.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: No work activities occurred due to strong thunderstorms and lightning in the area.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 234: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

8-17-16 - Placing rock for B33.

8-20-16 – Placing rock for B2.

Page 235: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

8-20-16 – Placing geotextile fabric for B3 using marsh hoe equipment.

8-20-16 – View of B1 and B2.

Page 236: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 22, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B3 and B4 Continue placing rock for B3. Complete B4 and move to B4. Place geotextile fabric and rock. Complete B4. Used on-site survey equipment to confirm elevations and alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 237: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 23, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B5 Move to B5. Place geotextile fabric and rock. Used on-site survey equipment to confirm elevations and alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 238: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 24, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B5 and B6 Finish placing rock for B5. Move to B6. Place fabric and start placing rock. Used on-site survey equipment to confirm elevations and alignment. Naismith Marine on site to survey B41, B32, B33, B1 thru B5. They also staked A1 thru A12. Tides dropped significantly in mid-afternoon and could not move any barges near template. Stopped work at 3:30 pm.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Very low tides in mid-afternoon prevented moving barges near the work template.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 239: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 25, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B6 and B7 Continue placing rock for B6. Completed B6 and moved to B7. Placed geotextile fabric and started placing rock. Used on-site survey equipment to confirm elevations and alignment. AECOM and Scenic Galveston representatives tour work areas.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: AECOM and Scenic Galveston representatives tour work areas.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 240: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 26, 2016 WEATHER: Cldy, AM storms, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B7 and B8 Continue placing rock for B7. Finished B7 and moved to B8. Placed geotextile fabric and started placing rock. Used on-site survey equipment to confirm elevations and alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 241: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 27, 2016 WEATHER: Cldy, S winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

B8 Continue placing rock for B8. Finished B8. Used on-site survey equipment to confirm elevations and alignment. Made repairs to barges and equipment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 242: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 28, 2016 WEATHER: Cldy, Rain, S winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Made repairs to barges and equipment. Move and set up at A1.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 243: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

8-23-16 – View of B1 thru B4.

8-24-16 – Placing rock for B5.

Page 244: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

8-25-16 – Transferring barges with marsh excavator at B6.

8-27-16 – View of B8 thru B6.

Page 245: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 29, 2016 WEATHER: Cldy, Storms, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

A1 Place geotextile fabric for A1. Start placing rock. Used on-site survey equipment to confirm elevations and alignment. Thunderstorms and lightning in the area stop work about 11:30 am.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Thunderstorms and lightning in the area stop work about 11:30 am.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 246: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 30, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

A1, A2 and A7 Continue placing rock for A1. Complete A1 and move to A2. Place geotextile fabric and rock. Complete A2 and move to A7. Place geotextile fabric and rock. Used on-site survey equipment to confirm elevations and alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 247: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: August 31, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

A7, A6 and A5 Finish placing rock for A7. Move to A6. Place fabric and start placing rock. Finish A6 and move to A5. Placed geotextile fabric and started placing rock. Used on-site survey equipment to confirm elevations and alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 248: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 1, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

A5, A4 and A3 Continue placing rock for A5. Completed A5 and moved to A4. Placed geotextile fabric and started placing rock. Completed A4 and moved to A3. Placed geotextile fabric and started placing rock. Used on-site survey equipment to confirm elevations and alignment. GLO and AECOM representatives tour work areas.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: GLO and AECOM representatives tour work areas.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 249: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 2, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

A3, A8 and A9 Continue placing rock for A3. Finished A3 and moved to A8. Placed geotextile fabric and started placing rock. Finished A8 and moved to A9. Placed geotextile fabric. Used on-site survey equipment to confirm elevations and alignment. Naismith Marine on site to survey B6 thru B8 and A1 thru A7.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 250: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 3, 2016 WEATHER: Ptly Cldy, S winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

A9 and A10 Placed rock for A9. Finished A9 and moved to A10. Placed geotextile fabric and placed remaining rock. Used on-site survey equipment to confirm elevations and alignment. No rock remaining until a new delivery arrives. Made repairs to barges.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Ran out of rock needed to complete A10, A11, A12 and the additive breakwater area. Waiting on next rock delivery.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 251: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 4, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

5 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Made repairs to barges. Waiting on next barge delivery of remaining rock needed to complete the project.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Ran out of rock needed to complete A10, A11, A12 and the additive breakwater area. Waiting on next rock delivery.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 252: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

8-30-16 – Completing A2.

8-31-16 – View of completed breakwater A7.

Page 253: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

8-31-16 – View of completed breakwater A6 and A7.

9-1-16 – Transferring rock barges near A5 with marsh excavator.

Page 254: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

9-1-16 – Placing toe stone for A5.

9-2-16 – Naismith Marine surveying A3.

Page 255: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 5, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Made repairs to barges. Waiting on next barge delivery of remaining rock needed to complete the project.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting on next rock delivery.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 256: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 6, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Waiting on next barge delivery of remaining rock needed to complete the project.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting on next rock delivery.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 257: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 7, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Installed project signs at four locations. Waiting on next rock delivery to complete the project.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting on next rock delivery.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 258: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 8, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

1 Naismth Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None AECOM and Scenic Galveston representatives tour work areas. Waiting on next rock shipment to complete the project. Naismith Marine stakes locations for R1 and R2.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: GLO and AECOM representatives tour work areas.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting on next rock delivery.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 259: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 9, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Waiting on next rock delivery to complete the project.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting on next rock delivery.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 260: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 10, 2016 WEATHER: Ptly Cldy, NE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Waiting on next rock delivery to complete the project.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting on next rock delivery.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 261: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 11, 2016 WEATHER: Ptly Cldy, E winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Made repairs to barges. Waiting on next barge delivery of remaining rock needed to complete the project.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting on next rock delivery.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 262: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

9-7-16 – Example of project signs installed near breakwaters.

Page 263: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 12, 2016 WEATHER: Ptly Cldy, NE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

0 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Moved repaired barges into position at job site. Waiting on next barge delivery of remaining rock needed to complete the project.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting on next rock delivery.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 264: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 13, 2016 WEATHER: AM rain, Ptly Cldy, NE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

A10, A11 and A12 Waiting on next barge delivery of remaining rock needed to complete the project. Rock barge arrives just after noon. Continued placing rock for A10. Finished A10 and moved to A11. Placed geotextile fabric and placed rock for A11. Finished A11 and moved to A12. Placed geotextile fabric. Used on-site survey equipment to confirm elevations and alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain: Waiting on next rock delivery until noon.

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 265: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 14, 2016 WEATHER: Ptly Cldy, E/NE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

A12, R1 and R2 Finished A12 and moved to R1. Placed geotextile fabric and started placing rock. Finished R1 and moved to R2. Placed geotextile fabric and started placing rock. Used on-site survey equipment to confirm elevations and alignment.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 266: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 15, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

9 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

R2 Continued placing rock for R2. Finished R2 at approx. 10:30 am. Used on-site survey equipment to confirm elevations and alignment. AECOM and Scenic Galveston representatives tour work areas.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain: GLO and AECOM representatives tour work areas.

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 267: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 16, 2016 WEATHER: Ptly Cldy, E winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

8 Naismith Marine

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Begin coordinating and staging barges/equipment for demobilization purposes. Naismith Marine on-site to survey breakwaters A8 thru A12 plus R1 and R2.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 268: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 17, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

5 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Remove remaining staking from breakwaters, reef areas and survey stations. Continue demobilization activities.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 269: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

APOLLO ENVIRONMENTAL STRATEGIES, INC.

P.O. Box 12114

Beaumont, Texas 77726 409.833.3330

Virginia Point Wetland Protection Project Galveston County, Texas

CEPRA #1596 DATE: September 18, 2016 WEATHER: Ptly Cldy, SE winds

PERSONNEL ON-SITE: SUBCONRACTOR ON-SITE:

3 None

DAILY ACTIVITIES/PRODUCTION / PERCENT COMPLETE:

Breakwater No. Other:

None Continue demobilization activities.

Any Accidents or Unusual Events? Yes No If yes, explain:

Any Meetings and Significant Decisions? Yes No If yes, explain:

Any Stoppages, Delays, Shortages or Losses? Yes No If yes, explain:

Any Orders and Request of Governing Authorities? Yes No If yes, explain:

Any Change Orders Received, Implemented? Yes No If yes, explain:

Page 270: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Appendix C

Progress Meeting Notes

Page 271: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

AECOM

19219 Katy Freeway, Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

Agenda

This transmission is confidential and intended solely for the person or organization to whom it is addressed. It may contain privileged

and confidential information. If you are not the intended recipient, you should not copy, distribute or take any action in reliance on it.

Discussion Topics:

I. Status of Construction

A. Current Status of Construction

a. Breakwaters B29 and B30 have been completed. Final verification

survey conducted by Naismith, to be reviewed for confirmation of

construction process.

b. Construction staking has been completed for breakwaters B15 – B32.

B. Schedule

a. APOLLO anticipates construction of 3 to 4 breakwaters per week,

assuming no delays.

b. Nearshore “A” breakwater construction projected for July 2016.

C. Upcoming Activities

a. Tentative plan is to construct B31 – B9, followed by B1 – B8.

D. Site Visit Schedule

a. AECOM will perform weekly site visits. Tentative schedule attached.

b. Scenic Galveston to schedule site visit for board members.

II. Issues

A. Weather

a. Storms have delayed construction activities for week of 5/16.

B. Tides

a. Tides have been high, but have not adversely impacted construction.

C. Safety

a. No issues reported.

b. Life jackets required for all personnel during boating activities.

c. Be aware that snakes may be present on upland areas.

D. Other

a. Consideration will be given to adjusting nearshore “A” breakwaters

further from the coastline, but still nearshore of the existing reefs.

b. Signage requirement is specified by the Coast Guard. Permit does not

require signs to be placed at breakwaters.

c. GLO and Scenic Galveston to discuss removal of ~30 existing pilings.

Subject Construction Progress Meeting #1

Date / Time May 18, 2016 / 9:00 AM

Attendees See attached

Location 1600 Campbell Bayou Road, Texas City, Texas 77590

AECOM Project No. 60433394

Project Name CEPRA 1596 – Virginia Point Wetland Protection Project

Page 272: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

III. Pending Paperwork

A. RFI / ESI

a. Both Texas and Kentucky rip rap source submittals have been

approved. ESI not required.

B. Time Change Order

a. APOLLO to issue for Union Pacific stone source delays.

C. Other

a. GLO to re-issue NTP letter to APOLLO by 5/20/16.

IV. Other Items

A. March / April Payment Request (Approved)

a. Time change orders are not required to be submitted with each

invoice.

B. Status Reports

a. AECOM and APOLLO will submit weekly status reports documenting

construction and oversight activities.

V. Identify Date of Next Meeting

A. May 31, 2016 – Field meeting with GLO, SG, and AECOM.

VI. Field Visit

Page 273: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:
Page 274: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:
Page 275: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Virginia Point Construction Oversight Calendar Wednesday, May 18, 2016 – Thursday, August 25, 2016 Time zone: (UTC-06:00) Central Time (US & Canada) (Adjusted for Daylight Saving Time)

May 2016

Su Mo Tu We Th Fr Sa

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

June 2016 Su Mo Tu We Th Fr Sa

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

July 2016 Su Mo Tu We Th Fr Sa

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

August 2016 Su Mo Tu We Th Fr Sa

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Virginia Point - Construction Progress Meeting #1

Wed, May 18 9:00 AM – 9:30 AM

Site Visit Tue, May 24 10:00 AM – 12:00 PM

Site Visit Tue, May 31 10:00 AM – 12:00 PM

Site Visit Thu, Jun 09 10:00 AM – 12:00 PM

Site Visit Thu, Jun 16 10:00 AM – 12:00 PM

Site Visit Thu, Jun 23 10:00 AM – 12:00 PM

Site Visit Thu, Jun 30 10:00 AM – 12:00 PM

Site Visit Thu, Jul 07 10:00 AM – 12:00 PM

Site Visit Thu, Jul 14 10:00 AM – 12:00 PM

Site Visit Fri, Jul 22 10:00 AM – 12:00 PM

Page 276: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Site Visit Thu, Jul 28 10:00 AM – 12:00 PM

Site Visit Thu, Aug 04 10:00 AM – 12:00 PM

Site Visit Thu, Aug 11 10:00 AM – 12:00 PM

Site Visit Fri, Aug 19 10:00 AM – 12:00 PM

Site Visit Thu, Aug 25 10:00 AM – 12:00 PM

Page 277: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B9

B1

B11

B5

B7

B12

B8

B14

B3B2

B4

B15

B13

B6

B10

B16

R1

A6

A10

A7

A9A8

A4

A1

A5

A2

A15

A3

A16

A13

A14

A17

A11

A12

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:05/19/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:05/19/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (14)

Staked, Not Constructed (2)

Construction In Progress (0)

Construction Complete (0)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress05/18/16

Page 278: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B38B39

B40

B19

B23

B18

B41

B44

B37

B20

B36

B35

B33

B26

B21B22

B24

B29

B28

B25

B30

B42

B32

B43B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:05/19/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:05/19/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (12)

Staked, Not Constructed (13)

Construction In Progress (1)

Construction Complete (2)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

OffshoreStaging Area

Shallow DraftStaging Area

Construction Progress05/18/16

Page 279: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

AECOM

19219 Katy Freeway, Suite 100

Houston, Texas 77094

www.aecom.com

281 646 2400 tel

281 646 2401 fax

Meeting Minutes

This transmission is confidential and intended solely for the person or organization to whom it is addressed. It may contain privileged

and confidential information. If you are not the intended recipient, you should not copy, distribute or take any action in reliance on it.

Discussion Topics:

I. Status of Construction

A. Current Status of Construction

a. Breakwaters B30 through B10 have been completed.

b. Naismith will be on site this week for post-construction survey and

staking B33 through B37.

B. Schedule

a. Construction activities are expected to be completed in late August.

C. Upcoming Activities:

a. Construct B31, tide permitting, and then work north to south through

B44.

D. Site Visit Schedule

a. Scenic Galveston may schedule Board Member site visit on 7/7/16 or

may continue to bring members on individual trips, as practical.

b. GLO

c. NFWF site visit TBD.

II. Issues

A. Weather

a. No issues reported.

B. Tides

a. No issues reported.

C. Safety

a. No issues reported.

D. Other

a. Toe Stone on “Y” Breakwaters B9 and B31 – Build riprap to template

and place toe stone as practicable on all bay-facing breakwater

components, understanding that some toe stone may fall outside of

geotextile template.

Subject Construction Progress Meeting #2

Date / Time June 29, 2016 / 9:30 AM

Attendees See attached

Location 1600 Campbell Bayou Road, Texas City, Texas 77590

AECOM Project No. 60433394

Project Name CEPRA 1596 – Virginia Point Wetland Protection Project

Page 280: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

III. Pending Paperwork

A. Submittals

a. VP-18 is under review by AECOM.

b. New gradation will be submitted with next riprap shipment.

B. Time Change Order

a. APOLLO to re-submit TC-01 and TC-02 as a combined Time Change

Order #1 for 36 day extension.

C. June Pay Request

a. GLO processing

IV. Other Items

A. Additional Scope

a. APOLLO to provide cost proposal for additional (1) Project Signage

and (2) Piling Removal scopes.

B. Official Project Title

a. GLO to verify CIAP project name.

V. Identify Date of Next Meeting

A. TBD - 7/15/16 Conference Call or 7/22/16 Field Meeting

VI. Field Visit

Page 281: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:
Page 282: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

Virginia Point Construction Oversight Calendar Wednesday, May 18, 2016 – Thursday, August 25, 2016 Time zone: (UTC-06:00) Central Time (US & Canada) (Adjusted for Daylight Saving Time)

May 2016

Su Mo Tu We Th Fr Sa

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

June 2016 Su Mo Tu We Th Fr Sa

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

July 2016 Su Mo Tu We Th Fr Sa

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

August 2016 Su Mo Tu We Th Fr Sa

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Progress Meeting and Site Visit with General Land Office

Wed, Jun 29 9:30 AM – 11:30 AM

Site Visit with Scenic Galveston Board Members

Thu, Jul 07 10:00 AM – 12:00 PM

Site Visit Thu, Jul 14 10:00 AM – 12:00 PM

Site Visit Fri, Jul 22 10:00 AM – 12:00 PM

Site Visit Thu, Jul 28 10:00 AM – 12:00 PM

Site Visit Thu, Aug 04 10:00 AM – 12:00 PM

Site Visit Thu, Aug 11 10:00 AM – 12:00 PM

Site Visit Fri, Aug 19 10:00 AM – 12:00 PM

Site Visit Thu, Aug 25 10:00 AM – 12:00 PM

Page 283: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B9

B1

B11

B5

B7

B12

B8

B14

B3B2

B4

B15

B13

B6

B10

B16

R1

A6

A10

A7

A9A8

A4

A1

A5

A2

A15

A3

A16

A13

A14

A17

A11

A12

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:06/29/16

1

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:06/29/16

File Name:VP_ConstProg1.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

1.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusNot Staked, Not Constructed (29)

Staked, Not Constructed (0)

Construction In Progress (1)

Construction Complete (7)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Shallow DraftStaging Area

Construction Progress06/29/16

OffshoreStaging Area

Page 284: CONSTRUCTION DOCUMENTATION REPORT VIRGINIA ......2018/09/12  · CEPRA 1596 Status Report #2 PROJECT STATUS: The following activities have been ongoing during the fifth week of construction:

B17

B31

B11

B38

B40

B39

B12

B14

B15

B13

B23

B19

B18

B41

B44

B37

B20

B16

B36

B35

B33

B21

B26

B22

B24

B29

B28

B25

B30

B42

B32

B43

B34

B27

Virginia PointConstruction Progress

Texas General Land OfficeClient:

Project No.:

Drawn by:TN

Date:06/29/16

2

Title:

25015347Figure:

19219 KATY FREEWAY, SUITE 100HOUSTON, TX 77094TEL: 281.646.2400FAX: 281.646.2401

Chk'd by:CL

Date:06/29/16

File Name:VP_ConstProg2.mxd

Scale:As

Shown

CEPRA 1596 - Virginia PointWetland Protection Project

Galveston Bay

VirginiaPoint

Path:

O:\P

rojec

ts\W

TR\60

4333

94_V

irgPn

tCon

\GIS

\MXD

\VP_

Cons

tProg

2.mxd

Project:

In Partnership with Scenic Galveston

³

Breakwater Construction StatusConstStatus

Not Staked, Not Constructed (12)

Staked, Not Constructed (2)

Construction In Progress (0)

Construction Complete (21)

Approximate Staging Area LocationOffshore

Shallow Draft

0 800 1,600400Feet

Construction Progress06/29/16

OffshoreStaging Area