olmsted locks & dam construction status

15
BUILDING STRONG 1 Louisville District Olmsted Locks & Dam Construction Status Inland Waterways User Board Chicago, IL 18 November 2008

Upload: others

Post on 01-Oct-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Olmsted Locks & Dam Construction Status

BUILDING STRONG 1Louisville District

Olmsted Locks & DamConstruction Status

Inland Waterways User BoardChicago, IL

18 November 2008

Page 2: Olmsted Locks & Dam Construction Status

BUILDING STRONG 2

August 2008 Aerial View

Page 3: Olmsted Locks & Dam Construction Status

BUILDING STRONG 3

Gantry Crane

Features Include:

Lifting Capacity- 5,100 tons

Clearance Dimensions –100-foot vertical and 130-

foot horizontal

Page 4: Olmsted Locks & Dam Construction Status

BUILDING STRONG 4

Lower Marine Skidway

Page 5: Olmsted Locks & Dam Construction Status

BUILDING STRONG 5

Stilling Basin Shell Bearing Wall Erection

Page 6: Olmsted Locks & Dam Construction Status

BUILDING STRONG 6

Lower Pier Shell Base Support Structure

Page 7: Olmsted Locks & Dam Construction Status

BUILDING STRONG 7

Ringer Barge and Crane

Features Include: A Manitowoc 60-foot diameter platform ringer crane with 660 ton capacity, 200-

foot boom & 1,200,000 lbs of counterweight mounted on a

200-foot by 100-foot by 12-foot deep flat deck barge.

Page 8: Olmsted Locks & Dam Construction Status

BUILDING STRONG 8

Catamaran Lift BargeFeatures Include: 4500 Ton Capacity, Clear

opening of 130’, Starboard & Port Barges 90’x 200’ x 15’, Gantry beam 15’ deep and 63’

above deck, Design Draft 11’, Overall Dimensions 200’ by 310’

Page 9: Olmsted Locks & Dam Construction Status

BUILDING STRONG 9

Dam in River Activities

Page 10: Olmsted Locks & Dam Construction Status

BUILDING STRONG 10

Excavator BargeFeatures Include:

3 Legged Jacking Spuds –Capable of Lifting the barge out

of buoyancy to allow the GPS System to be accurately located, which will allow the excavator’s

electronic system to excavate within plus 0” , minus 6”

tolerance.

Page 11: Olmsted Locks & Dam Construction Status

BUILDING STRONG 11

Filling Grout Mat

Page 12: Olmsted Locks & Dam Construction Status

BUILDING STRONG 12

Dam in River Activities

Page 13: Olmsted Locks & Dam Construction Status

BUILDING STRONG 13

Construction Schedule

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

Demo L&D 52 & 53

Dam

Bldgs & Grounds

DS Mooring Cells

Gate Storage

Bulkheads

Approach Walls

Boat Ramp

BWMA

Lock

Prototype

Cofferdam

Road & Office

Page 14: Olmsted Locks & Dam Construction Status

BUILDING STRONG 14

Dam Contract Funding

FY- 09 $12,000,000 (Thru 31 Oct 2008)FY- 08 $92,309,809FY- 07 $95,000,000FY- 06 $78,866,827FY- 05 $44,521,000FY- 04 $4,050,000

Total Obligated to Contract = $326,747,636Most Likely Cost of Dam = $1,058,700,000

Page 15: Olmsted Locks & Dam Construction Status

BUILDING STRONG 15