a closer look at the olmsted dam project

Upload: courier-journal

Post on 02-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 A closer look at the Olmsted dam project

    1/1

    24

    24

    57

    57

    60Paducah

    OhioRiverOlmsted

    Wickliffe

    Mound City

    Cairo

    Metropolis

    Smithland

    Joppa

    127

    121

    145

    3

    45

    45

    60

    Mississip

    piRi

    ver

    MississippiRiver

    Tenn

    esseeR

    iver

    5 miles

    N MAP

    AREA

    KENTUCKY

    Louisville

    Lock andDam 52

    Lock andDam 53

    OLMSTEDLOCKS AND

    DAMPROJECT

    BUILDING A NEW DAM

    ON THE OHIO RIVER

    BIGJOBONE

    The Olmsted Dam on the western end of the Ohio River is beingbuilt as precast pieces on land that are then moved to the river for

    completion in one of the largest construction projects under wayin the United States.

    The Army Corps of Engineers plan is to build its first dam on amajor river without first building temporary coffer dams to createdry areas on the riverbed for construction workers. Instead, thecorps and its contractors are manufacturing 3,500-ton to 5,000-ton concrete shells on land, then lifting, moving and loweringthem in place, connecting them together like pieces of Lego toys.

    Cradle

    Shell

    Shell

    MAKING A SHELL, THE BUILDING BLOCKS OF THE PROJECTUsing concrete mixed at the site, reinforcement rods and supporting structures,workers build a series of concrete shells on land. Each will become a piece ofthe dam. The biggest shells are 125 feet by 102 feet and about 30 feet high.

    TRAVEL SPEED: Loaded, the gantry crane travels at10 feet per minute.

    LIFTING CAPACITY: 5,100 tons

    Super gantry crane facts and figures

    Catamaran barge facts and figures

    COST: $9.5 million (for crane alone, does notinclude assembly, foundations or lifting equipment).

    Catamaran barge

    Super

    gantrycrane

    CATAMARAN BARGE

    PLACING A SHELLBefore placing the shell, the bottom of the river is graded andcovered with stone, and foundation piles are driven into theriver bottom. Using the most precise global positioningequipment, the shells are lowered into the water in sequence,either on top of each other or next to each other, with amargin of error of less than one inch.

    MOVING A SHELL

    Supports

    Supports

    Supports

    Frontview

    Frontview

    Once a shell is complete, a steellifting frame is attached. A specialcrane built just for the Olmstedproject rides on rails to move the shellto the top of a skidway, just abovethe Ohio River.

    Concrete shell

    Supergantrycrane

    Lifting frame

    Lifting frame

    Cradle

    Sideview

    Skidway

    1

    1

    2

    2

    3

    3

    4

    4

    5

    5

    Ohio River Supports

    LOCKS

    DAM

    DAMLOCKS

    Catamaran

    barge

    Super

    gantry

    crane

    Skid

    way

    Once each shell is inplace, its void isfilled with concrete,displacing water.

    The shell is placed on a wedge-shaped steel cradlewith wheels and another piece of equipmentslowly lowers the shell down the riverbank, wherethe catamaran barge waits to pick it up.

    Gates and wickets will be used to control the water levels. Heres how they work:

    CONTROLLING THE FLOW

    When the river is low When the river is high

    Cradle

    140 ft.

    160 ft.100 ft.

    Sixty four, 36diameter steelwheels areused to movethe cranes

    N

    Aerial photo by Google Earth

    STEVE REED/THE COURIER-JOURNALSOURCE: Army Corps of Engineeers

    COST: $19 million (barge alone, does

    not include assembly or lifting equipment.)

    Shell lifters

    Shell lifters

    Shell lifters

    Shell lifters

    Shell lifters

    Shell lifters

    Shell lifters

    ShellsSizecomparison

    PROPULSION:Two 4,500-horsepowerpush boats

    LIFTING CAPACITY: 4,500 tons

    SPEED: Will not exceed 6 feetper second.

    The wickets are lowered, allowing barges to navigateover the dam and avoid the locks.

    Wickets are raised and gates closed, creating a pool forbarge transport and safe passage through the locks.

    Gates Locks Locks

    Navigable passareaWickets

    Wickets

    THE TRIP TO THE PLACEMENT SITEEquipment on the barge lifts the shell off the cradle andholds the shell in place, while towboats push the bargeout to the dam site.

    6-foot tall man

    6-foottall man

    As more water isblocked by the

    wickets of t

    he damin this area of the

    river, the water levelrises, allowingvessels to pass

    throughthe locks.

    As more water isblocked by the

    wickets o

    f the damin this area of the

    river, the water levelrises, allowingvessels to pass

    throughthe locks.

    Navigabledamsection

    Gateddam

    section

    Navigabledamsection

    Gateddam

    section

    To see videos of the Olmsted Dam Project go to:courier-journal.com/olmsteddam

    ONLINE