  • 8/11/2019 Construction Status 2-3-2014

    1/3

    Construction Status Up to 2-3-2014

    General

    Site Leveling for the Site. (100%) Transport Palm trees outside the site (100%)

    Constructing the wooden fences for the site (100%)

    Prepare site office (100 %)

    Prepare the site layout facilities (100%)

    Operation for the Dewatering System (100%)

    Transformer boxes (2 No)

    Install the earthing cable Box (100%) Back filling the earthing trench (100%)

    Pouring Concrete grade 40 for base slab (100 %)

    Pouring concrete for Internal & External Walls till +4.2 (100%)

    Grinding & Repair for Internal Wall (100%)

    Grinding & Repair for External Wall (25%)

    Transformer boxes (6 No)

    Install the earthing cable Box (100%)

    Back filling the earthing trench (100%)

    Pouring Concrete grade 40 for base slab (100 %)

    Pouring concrete for Internal & External Walls till +4.2 (100%)

    Grinding & Repair for Internal Wall (100%)

    Grinding & Repair for External Wall (25%)

    Electrical & Control Building

    Install the earthing cable Box (100%)

    Pouring RC base slab (100%)

    Pouring concrete for basement Walls & columns (100%)

    Pouring Concrete for ground floor slab (100%)

  • 8/11/2019 Construction Status 2-3-2014

    2/3

    Pouring Columns ground floor columns (100%)

    Pouring roof slab from axis 1E to axis 17E (100%)

    Water proofing for walls & columns (100%)

    Basement Surface finishing from axis 1E to axis 17E (100%)

    Formwork for slope screed inside the basement (60%)

    Pouring Concrete for Parapet from axis 1E to 1.5m after axis 8E(100%)

    Formwork for Parapet from axis 1.5m after axis 8E to axis 17E(100%)

    Steel fixing for Parapet from axis 1.5m after axis 8E to axis 17E(50%)

    Repair & finishing from axis 1E to axis 9E (100%)

    Installation for angles of the drain channel (100%)

    Installation of the Frame of the drain pit (100%)

    Oil Paint for basement Walls from axis 1E to axis 9E (5%)

    Block work Mockup for internal wall (100%)

    Pump House

    Install the Earthing Cable (100%)

    Pouring concrete for RC basement (100%)

    Install Sylomer for PG1 & PG2 (100%)

    Pouring concrete for RC foundation for pump (100%)

    Pouring Concrete for Walls & Columns (100%)

    Pouring Concrete for laydown area (100%) Water proofing for walls & columns (100%)

    Backfilling in front of axis J (50%)

    Utility Building

    Pouring RC isolated footings (100%)

    Pouring Concrete for columns & ground beams (100%)

    Formwork for Roof slab (30%)

    Surge Vessel (For PG1)

    Excavation for Surge Vessel basement (100%)

    Pouring blinding concrete (100%)

    Water proofing for blinding concrete (100%)

  • 8/11/2019 Construction Status 2-3-2014

    3/3

    Formwork for R.C foundation (70%)

    Steel Fixing for R.C foundation (30%)

    Surge Vessel (For PG2)

    Excavation for Surge Vessel basement (100%) Pouring blinding concrete (70%)

    Water proofing for blinding concrete (100%)

    Formwork for R.C foundation (50%)

    Steel Fixing for R.C foundation (20%)