Page 1: Customer Information System Replacement Project Update...Jan 04, 2013  · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the

Customer Information System Replacement Project Update

January 4, 2012

Page 2: Customer Information System Replacement Project Update...Jan 04, 2013  · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the

Technology Strategic Goals

10 year goal – Employ state-of-the-art technology to maximize reliability and customer service.

3 year goal – Maximize the use of technology to improve utility operations.

Page 3: Customer Information System Replacement Project Update...Jan 04, 2013  · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the

Utility Billing for Electric, Water, Sewer, Refuse, UUT

• 400 users in 3 major departments

• 111,000 bills monthly

• $32,000,000 avg. monthly revenue

• 60,000 monthly customer contacts

• 400 Internet Service Requests per month

• 12,000 Credit Card Payments per month

• 180,000 service orders per year

Customer Information System - Facts

Page 4: Customer Information System Replacement Project Update...Jan 04, 2013  · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the

Replacement 1999 • Successful Implementation

• Timeline: May 1997 – October 1999 “Go Live”

• Y2K conversion, Increase functionality

2010 – Approval to procure new CIS

• AAC Utility Partners – Selection Consultant 2012 – New CIS Awarded by Board

• $9,200,000 Project Cost

• Expected “go-live” July 2014

Customer Information System - Background

Page 5: Customer Information System Replacement Project Update...Jan 04, 2013  · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the

Project Status

Project Kicked off July 1

Project Team assembled

Initial project training complete

Business process documentation complete

Project web-site fully functional

Page 6: Customer Information System Replacement Project Update...Jan 04, 2013  · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the

Project Quality Auditor Review

Monthly review by consultant outside project team

Fourteen measures/metrics of project health

Reviewed by Management and Steering Committee

Includes specific recommendations

Page 7: Customer Information System Replacement Project Update...Jan 04, 2013  · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the

Dashboard Key

Page 8: Customer Information System Replacement Project Update...Jan 04, 2013  · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the

Project Dashboard

Project Integration Scope Mgmt Time Mgmt Cost Mgmt Deliverable Mgmt

HR Mgmt Knowledge Transfer OCM Risk Mgmt Quality Mgmt

Data Conversion Training Project Team Overall Project

Page 9: Customer Information System Replacement Project Update...Jan 04, 2013  · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the

Project Summary

GENERAL COMMENTS

1. Great team – S&S and RPU!

2. All SOW requirements to date have been met

3. Problem areas easy to address

SIGNIFICANT UNADDRESSED RISKS

• RPU Team Assignments

• Risk Management

Change Controls: No Cost Changes: No Schedule Changes: No

Page 10: Customer Information System Replacement Project Update...Jan 04, 2013  · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the

Next Steps

Business Process Design

Align Riverside practice to software functions

January – June 2013

Process and Software Testing

June 2013 – December 2013

Page 11: Customer Information System Replacement Project Update...Jan 04, 2013  · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the

Recommendation

That the Board of Public Utilities

Receive and File this report.