Customer Information System Replacement Project Update
January 4, 2012
![Page 2: Customer Information System Replacement Project Update...Jan 04, 2013 · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the](https://reader035.vdocument.in/reader035/viewer/2022071406/60fc388d62745a49146d4c7e/html5/thumbnails/2.jpg)
Technology Strategic Goals
10 year goal – Employ state-of-the-art technology to maximize reliability and customer service.
3 year goal – Maximize the use of technology to improve utility operations.
![Page 3: Customer Information System Replacement Project Update...Jan 04, 2013 · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the](https://reader035.vdocument.in/reader035/viewer/2022071406/60fc388d62745a49146d4c7e/html5/thumbnails/3.jpg)
Utility Billing for Electric, Water, Sewer, Refuse, UUT
• 400 users in 3 major departments
• 111,000 bills monthly
• $32,000,000 avg. monthly revenue
• 60,000 monthly customer contacts
• 400 Internet Service Requests per month
• 12,000 Credit Card Payments per month
• 180,000 service orders per year
Customer Information System - Facts
![Page 4: Customer Information System Replacement Project Update...Jan 04, 2013 · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the](https://reader035.vdocument.in/reader035/viewer/2022071406/60fc388d62745a49146d4c7e/html5/thumbnails/4.jpg)
Replacement 1999 • Successful Implementation
• Timeline: May 1997 – October 1999 “Go Live”
• Y2K conversion, Increase functionality
2010 – Approval to procure new CIS
• AAC Utility Partners – Selection Consultant 2012 – New CIS Awarded by Board
• $9,200,000 Project Cost
• Expected “go-live” July 2014
Customer Information System - Background
![Page 5: Customer Information System Replacement Project Update...Jan 04, 2013 · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the](https://reader035.vdocument.in/reader035/viewer/2022071406/60fc388d62745a49146d4c7e/html5/thumbnails/5.jpg)
Project Status
Project Kicked off July 1
Project Team assembled
Initial project training complete
Business process documentation complete
Project web-site fully functional
![Page 6: Customer Information System Replacement Project Update...Jan 04, 2013 · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the](https://reader035.vdocument.in/reader035/viewer/2022071406/60fc388d62745a49146d4c7e/html5/thumbnails/6.jpg)
Project Quality Auditor Review
Monthly review by consultant outside project team
Fourteen measures/metrics of project health
Reviewed by Management and Steering Committee
Includes specific recommendations
![Page 7: Customer Information System Replacement Project Update...Jan 04, 2013 · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the](https://reader035.vdocument.in/reader035/viewer/2022071406/60fc388d62745a49146d4c7e/html5/thumbnails/7.jpg)
Dashboard Key
![Page 8: Customer Information System Replacement Project Update...Jan 04, 2013 · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the](https://reader035.vdocument.in/reader035/viewer/2022071406/60fc388d62745a49146d4c7e/html5/thumbnails/8.jpg)
Project Dashboard
Project Integration Scope Mgmt Time Mgmt Cost Mgmt Deliverable Mgmt
HR Mgmt Knowledge Transfer OCM Risk Mgmt Quality Mgmt
Data Conversion Training Project Team Overall Project
![Page 9: Customer Information System Replacement Project Update...Jan 04, 2013 · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the](https://reader035.vdocument.in/reader035/viewer/2022071406/60fc388d62745a49146d4c7e/html5/thumbnails/9.jpg)
Project Summary
GENERAL COMMENTS
1. Great team – S&S and RPU!
2. All SOW requirements to date have been met
3. Problem areas easy to address
SIGNIFICANT UNADDRESSED RISKS
• RPU Team Assignments
• Risk Management
Change Controls: No Cost Changes: No Schedule Changes: No
![Page 10: Customer Information System Replacement Project Update...Jan 04, 2013 · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the](https://reader035.vdocument.in/reader035/viewer/2022071406/60fc388d62745a49146d4c7e/html5/thumbnails/10.jpg)
Next Steps
Business Process Design
Align Riverside practice to software functions
January – June 2013
Process and Software Testing
June 2013 – December 2013
![Page 11: Customer Information System Replacement Project Update...Jan 04, 2013 · January – June 2013 Process and Software Testing June 2013 – December 2013 . Recommendation That the](https://reader035.vdocument.in/reader035/viewer/2022071406/60fc388d62745a49146d4c7e/html5/thumbnails/11.jpg)
Recommendation
That the Board of Public Utilities
Receive and File this report.