data center cooling efficiency: understanding the science of the 4 delta t's
TRANSCRIPT
Data Center Cooling Efficiency: Understanding the Science of the 4 Delta T’s
Lars Strong, P.E., Upsite Technologies
Airflow Management Awareness Month
June 22, 2016
Lars is a thought leader and recognized expert on data center optimization. He currently serves as the Senior Engineer and Company Science Officer of Upsite Technologies. Lars is a certified U.S. Department of Energy Data Center Energy Practitioner (DCEP) HVAC Specialist.
05/03/2023 © Upsite Technologies, Inc. 2
Lars Strong
Delta T PUE Bypass Airflow Commonly Known Delta T’s Less Known Delta T’s Remedial Considerations
05/03/2023 © Upsite Technologies, Inc. 3
Agenda
DELTA T (ΔT)
© Upsite Technologies, Inc.05/03/2023 4
Delta T (ΔT)= change in temperature
“The ΔT” - Facilities: across cooling unit coils (Δ between supply and return)- IT: through IT equipment
There are actually 4 ΔT’s
05/03/2023 © Upsite Technologies, Inc. 5
Delta T (ΔT)
The 4 ΔT’s
1. Through IT equipment2. IT equipment exhaust to
cooling unit3. Through cooling unit4. Cooling unit supply to IT
equipment intake
05/03/2023 © Upsite Technologies, Inc. 6
The 4 ΔT’s
PUE – RELATION TO AIRFLOW MANAGEMENT
© Upsite Technologies, Inc.05/03/2023 7
PUE
© Upsite Technologies, Inc.05/03/2023 8
Total Load
IT LoadPUE =
Other than IT load, cooling load is often the largest portion of total loadAirflow management is fundamental to both effective and efficient coolingMechanical plant + cooling fans: 35% of total load, 73% of non IT Load
Raised floor
area (sq ft)
# of running cooling units
Raised floor
bypass open
area (%)
Hot spots (%
of cabinets
)
Cold spots (%
of cabinets) (Data from 6 sites)
Proper perforated tile
placement (%)
Cooling Capacity Factor (CCF)
Averages 7,527 8 48% 20% 35% 77% 3.9Minimum 720 2 13% 0% 0% 7% 1.2Maximum 37,00
040 93% 86% 86% 100% 32.0
Recommended
n/a n/a <10% 0% 0% 100% 1.2Conclusion: Inefficient cooling configuration / airflow management is the problem; capacity is not the problem.
Airflow Management Research
© Upsite Technologies, Inc.05/03/2023 9
BYPASS AIRFLOW
© Upsite Technologies, Inc.05/03/2023 10
Bypass Airflow Clarified
© Upsite Technologies, Inc.© Upsite Technologies, Inc.05/03/2023 11
Common ratios before raised floor open area management
Bypass Airflow Clarified
© Upsite Technologies, Inc.© Upsite Technologies, Inc.05/03/2023 12
Common ratios after raised floor open area management
Bypass Airflow Clarified
© Upsite Technologies, Inc.© Upsite Technologies, Inc.05/03/2023 13
Ratios after balancing supply flow rate to IT demand flow rate
MORE COMMONLY KNOWN ΔT’S
© Upsite Technologies, Inc.05/03/2023 14
The 4 ΔT’s
1. Through IT equipment2. IT equipment exhaust to
cooling unit3. Through cooling unit4. Cooling unit supply to IT
equipment intake
05/03/2023 © Upsite Technologies, Inc. 15
ΔT Through IT Equipment
Regardless of airflow management in the computer room, the IT equipment airflow temperature rise will be constant for a given work load.
Every kilowatt of electricity consumed by IT equipment becomes a kW of heat added to the flow of cooling air through the IT equipment.
There is a fixed relationship between airflow, temperature differential and heat (energy).
05/03/2023 © Upsite Technologies, Inc. 16
ΔT Through IT Equipment
05/03/2023 © Upsite Technologies, Inc. 17
ΔT Through IT Equipment
Heat Transfer Equation
CFM =
CFM = cubic feet per minute of airflow through the server3.16 = factor for density of air at sea level in relation to F⁰ΔT = temperature rise of air through the server in F⁰
3.16 x W Delta T
05/03/2023 © Upsite Technologies, Inc. 18
ΔT Through IT Equipment
CFM/kW
IT Equipment Required Flow Rate IT
Equipment Delta T
(deg F)15° 20° 25° 30° 35° 40°
Required flow rate (CFM/kW)
211
158
126
105
90
79
“Blade” servers at 35 F ⁰ ΔT consume 90 CFM / kW
“Pizza box” servers at 20 F ⁰ ΔT consume 158 CFM / kW
UPS load (kW) x CFM/kW = Total IT CFM
UPS load (kW) x 100 CFM/kW = approximate IT cooling demand (CFM) Compare this to total cooling flowrate to determine room bypass airflow rate
05/03/2023 © Upsite Technologies, Inc. 19
ΔT Through IT Equipment
Examples
The 4 ΔT’s
1. Through IT equipment2. IT equipment exhaust to
cooling unit3. Through cooling unit4. Cooling unit supply to IT
equipment intake
05/03/2023 © Upsite Technologies, Inc. 20
ΔT Through Cooling Unit
Ideally ΔT through cooling units would match ΔT through IT equipment, then total volumetric flow rate (CFM) of conditioned air could match the total flow rate of IT equipment
Legacy DX units ΔT was fixed at about 18˚ F
A 5˚ F increase in return air temperature might result in a 3˚ or 4˚ increase in the supply temperature
05/03/2023 © Upsite Technologies, Inc. 21
ΔT Through Cooling Unit
Chilled water cooling units have a much wider range of ΔT
Cooling units can be designed for much higher ΔT
Designers of high density data centers with high ΔT IT equipment are working with cooling unit manufactures to provide cooling units with a 45˚ F ΔT
05/03/2023 © Upsite Technologies, Inc. 22
ΔT Through Cooling Unit
LESS COMMONLY KNOWN ΔT’S
© Upsite Technologies, Inc.05/03/2023 23
The 4 ΔT’s
1. Through IT equipment2. IT equipment exhaust
to cooling unit3. Through cooling unit4. Cooling unit supply to IT
equipment intake
05/03/2023 © Upsite Technologies, Inc. 24
ΔT IT Equipment Exhaust to Cooling Unit
In most data centers the ΔT from the servers back to the cooling source is negative, the temperature of the return air tends to decrease after it is exhausted from the IT equipment
The cause is very straightforward: excess cooling air is bypassing the IT equipment and returning to the cooling units, reducing the temperature of the return air along the way
05/03/2023 © Upsite Technologies, Inc. 25
ΔT IT Equipment Exhaust to Cooling Unit
05/03/2023 © Upsite Technologies, Inc. 26
ΔT IT Equipment Exhaust to Cooling Unit
© Upsite Technologies, Inc.© Upsite Technologies, Inc.05/03/2023 27
Hot area shows air that passed through IT equipment
Cooler area shows bypass airflow
ΔT IT Equipment Exhaust to Cooling Unit
The 4 ΔT’s
1. Through IT equipment2. IT equipment exhaust to
cooling unit3. Through cooling unit4. Cooling unit supply to
IT equipment intake
05/03/2023 © Upsite Technologies, Inc. 28
ΔT Cooling Unit to IT Equipment Intakes
It is surprising that the ΔT between the cooling unit supply/output and the server inlet is not on many radars
Supply temperatures around 55˚ F are fairly typical, approximately 9˚ F below the recommended minimum temperature for data processing equipment per the ASHRAE environmental guidelines
Low supply temperature is often not a problem because by the time it reaches the IT equipment it has warmed dramatically
05/03/2023 © Upsite Technologies, Inc. 29
ΔT Cooling Unit to IT Equipment Intakes
05/03/2023 © Upsite Technologies, Inc. 30
ΔT Cooling Unit to IT Equipment Intakes
© Upsite Technologies, Inc.© Upsite Technologies, Inc.05/03/2023 31
Infrared Image of Operating Data Center• Cold spots and hot
spots in every cabinet
• Trying to solve poor AFM with cold supply
ΔT Cooling Unit to IT Equipment Intakes
REMEDIAL CONSIDERATIONS
© Upsite Technologies, Inc.05/03/2023 32
Any server inlet temperature that is more than 5˚F above the supply temperature being produced by cooling units means that there is hot air
If the return air intake of the cooling units is more than 5˚F lower than the exhaust temperature from the IT equipment, then there is a bypass airflow problem.
These 5˚F guidelines for calibrating ΔT’s are suggestions that will help move a data center into the top 20% of efficiently and effectively performing data centers.
05/03/2023 © Upsite Technologies, Inc. 33
Remedial Considerations
Monitoring all four ΔT’s can provide valuable assistance for optimizing the data center
The goal, particularly if free cooling is available to the data center, is to get the differentials between the cooling supply and IT intake, and server exhaust and the cooling unit return as close to zero as possible, this will increase free cooling hours.
Raise control temperatures to improve cooling unit capacity and efficiency
IR Thermometer and IR cameras are very valuable tools
05/03/2023 © Upsite Technologies, Inc. 34
Remedial Considerations
A holistic approach An iterative process ‘Check in’ at the room level
after making any AFM improvements
Watch video at:upsite.com/resources/airflow-management/
Upsite’s 4 R’s of Airflow Management™
© Upsite Technologies, Inc.05/03/2023 35
Raised Floor: Manage openings in the raised floor so that all cold air is entering the room through supply tiles located in front of IT equipment
Rack: Manage all openings through and below the rack or cabinet enclosure, so air can only pass through the IT equipment.
Row: Manage all openings between cabinets so no air can pass between them, and manage openings at the end of the aisle and above cabinets to contain cold air and prevent hot air wrapping around the ends of rows or over cabinets.
Room: Manage the conditioned airflow (flow rate and temperature) so that the maximum established IT inlet temperature is not exceeded, and there are no hotspots.
05/03/2023 © Upsite Technologies, Inc. 36
Upsite’s 4 R’s of Airflow Management™
37
Upsite’s 4 R’s of Airflow Management™Raised Floor
Integral GrommetP/N: 1010
Mini GrommetP/N: 10077
Round GrommetP/N: 40001 (4”) 40003 (6”)
Surface Mount Grommet
P/N: 2020 (Original) 2030 (Large)
2040 (Xlarge)
Extended Brush GrommetP/N: 10012 (3” x 24”) 10013 (6” x 24”) 10097 (3” x 60”) 10098 (6” x 60”)
Row
Under Rack Panel 10126 (27.5”) 10127 (31.5”) Adjustable Rack
Gap PanelP/N: 10164
Rack Top Baffles P/N: 10160/1
Bi-Directional DoorsP/N: 10163
Modular Containment
Room
Temp Sensor
Temp + Humidity
Sensor
Leak Detection Sensing
Rope
Temp Sensor w/ Digital InputTemp
Sensor
EMS 300 Wireless Network Manager
EMS 200 Wired Network Manager
Point Repeater
Rack
White Blanking PanelP/N: 10114 (1U) 10115 (2U)
1U Black Blanking PanelP/N: 10031 (19”) 10177 (23”)
2U Black Blanking Panel
P/N: 10033
Rack Airflow Management KitPass Through Blanking Panel
P/N: 10112 (1U) 10113 (2U)
Rack Mount GrommetP/N: 40002
05/03/2023 © Upsite Technologies, Inc. 38
June 1: The Science Behind Airflow ManagementPresented by Lars Strong, P.E., and Mark Seymour
June 8: Myths of Data Center ContainmentPresented by Lars Strong, P.E.
June 15: How IT Decisions Impact FacilitiesPresented by Lars Strong, P.E., and Ian Seaton
June 22: The 4 Delta T’s of Airflow ManagementPresented by Lars Strong, P.E.
Watch all recordings at upsite.com/airflow-management-awareness-month
Airflow Management Awareness Month
Thank you!
@UpsiteTech
blog.upsite.com
On LinkedIn
Lars Strong, P.E.Senior Engineer, Upsite [email protected]
Follow Upsite for the latest news and information on data center AFM.