deep geologic repository (dgr) for l&ilw sedor.pdf · opg/nwmo dgr s i a topg/nwmo dgr service...
TRANSCRIPT
Deep Geologic Repository (DGR)for L&ILW
UNENE CourseJune 18, 2011
DGR P t ti O tliDGR Presentation Outline
• Background Informationg• DGR Project Overview• Regulatory Milestones/EA ResultsRegulatory Milestones/EA Results• Engagement• GeoscienceGeoscience • Safety Assessment• Summary• Summary
2
BACKGROUND INFORMATIONBACKGROUND INFORMATION
3
Nuclear Waste StreamsNuclear Waste Streams
Low level waste
Intermediate level waste
4High level waste (not placed in this DGR)
L&ILW W t E lL&ILW Waste Examples
Compactable / Incinerable
twaste
Incinerator ash
Non-processible waste –e.g. old heat exchangers
Water cleanup IX resin beads
5
L&ILW A tL&ILW AmountsWaste Category Number of
ContainersContainers
LLWIncinerator ash 1,000Compacted wastes 7 000Compacted wastes 7,000Non-processible wastes 27,000Water cleanup IX resins and sludges 4,000Steam generators segments 500Sub-total LLW 39,000
ILWWater cleanup IX resins 2,000Water cleanup IX resins 2,000Water filters and equipment, core components, misc items 8,000
Retube Wastes (eg. Pressure Tubes ) 1,000Sub-total ILW 11,000
6
11,000Total 50,000
W t R di ti itWaste Radioactivity
7
OPG’s Western Waste Management Facility
• Over 40 years of safe interim storage• All L&ILW from OPG-owned 20 nuclear
reactors as well as the used fuel from the
8
reactors, as well as the used fuel from the Bruce site
Hi t f OPG’ L&ILW DGR P j tHistory of OPG’s L&ILW DGR Project2002: OPG and Municipality of Kincardine (host for the Bruce
nuclear site) signed Memorandum of Understanding tonuclear site) signed Memorandum of Understanding to explore options for long-term management of L&ILW
2004: Completed options study, including international visitsKincardine Council selected Deep Geologic RepositoryKincardine Council selected Deep Geologic Repository (DGR) option for L&ILWOPG/Kincardine signed DGR Hosting Agreement
2005: Community Poll taken by municipality. Results favorable to y y p yundertaking the project.Project Description submitted, EA commences
2006-2009: Detailed project activities managed by OPG 2009: OPG contracted NWMO to conduct activities to obtain EA
approval and Site Preparation/Construction Licence.2010: OPG contracted NWMO to prepare detailed
design/engineering for construction
9
design/engineering for construction
DGR PROJECT OVERVIEWDGR PROJECT OVERVIEW
10
Aspects of the DGR Project• 200,000 m³ (as packaged)
capacity for low and
Aspects of the DGR Project
capacity for low and intermediate level waste
• Geological conditions are ideal:ideal:– DGR will be constructed in
very low - permeability limestone at 680 metreslimestone at 680 metres(2,230 ft.) beneath a 200-metre-thick (650 ft.) cap of low-permeability shale
– Multiple natural geologic barriers will safely isolate and contain the waste
11
contain the waste
T i l L L l W t E l t RTypical Low Level Waste Emplacement Room
12
Typical Intermediate Level Waste Emplacement RoomTypical Intermediate Level Waste Emplacement Room
13
OPG/NWMO DGR S i A tOPG/NWMO DGR Service Agreement
• OPG is the owner, licensee and operator of DGR , pfor low and intermediate level waste (L&ILW)
• January 2009 - OPG contracts NWMO to provide technical services and other support through the regulatory approvals processregulatory approvals process
• Adaptive Phased Management for used fuel and• Adaptive Phased Management for used fuel and OPG’s DGR for L&ILW are separate projects
1414
REGULATORY PROCESSREGULATORY PROCESS
15
Mil t i EA PMilestones in EA Process2005: Submitted project description to the CNSC to initiate the regulatory processregulatory process
2006: Scoping hearing to determine the level of EA
2007: Federal Minister of Environment supports Panel Environmental Assessment:
• Joint Review Panel process introduced to address EA and application for site preparation and construction license
2009: Final guidelines issued for Environmental Impact2009: Final guidelines issued for Environmental Impact Statement and Joint Review Panel Agreement
16
Milestones in EA Process (continued)
2011: Submitted Environmental Impact Statement and
Milestones in EA Process (continued)
pPreliminary Safety Report – April 14th
Following submission: g• Six-month public review period for DGR will be announced
• Profile of DGR will be heightened during comment period with more media attention, both locally and internationally
• Strong public support is necessary for success of DGR Project
2012: Public hearings before Joint Review Panel• Final decision by Federal Government expected
Sit ti d t ti li t d t b t d
17
• Site preparation and construction license expected to be granted
Data Gathered in Support of the EAData Gathered in Support of the EA• Four-year geologic
i ti tiinvestigation• Design/engineering• Safety Assessment• Environmental field workEnvironmental field work • Public consultation program
18
f th L&ILW DGRResults of EA of the L&ILW DGR• Four years of investigations, analyses and
studies with independent peer review
• Interaction between Valued Ecosystem Components (e.g. flora and fauna) and DGR Project were assessedDGR Project were assessed
• Conclusion:
All studies indicate that the DGR Project will not have any significant adverse effects on the public or environment
19
ENGAGEMENT AND TWO-WAYAND TWO-WAY DIALOGUE
20
• Community relationship building
• Transparency and opennessTransparency and openness
• Multi-faceted approach
•Two-way dialogue y g
21
GEOSCIENCEGEOSCIENCE
22
R i l G l (1)Regional Geology (1)
23
R i l G l (2)Regional Geology (2)
24
R i l G l C S ti ViRegional Geology Cross Section View
25
S i i M it iSeismic Monitoring
26University of Western Ontario (POLARIS)/Geologic Survey of Canada
N t l R Oil/GNatural Resources – Oil/Gas
27
G l i Att ib t f DGR SitGeologic Attributes of DGR Site
1. Predictable2. Multiple Natural Barriers3. Contaminant Transport
Diffusion DominatedDiffusion Dominated4. Seismically Quiet5. Natural Resource
Potential Low6. Shallow Groundwater
Resources IsolateResources Isolate7. Geomechanically Stable
28
SAFETY ASSESSMENT
29
Safety Case (1)
30
Safety Case (2)
Safety Assessment- Quantify potential impacts- Considers likely and unlikely scenarios- Compares against regulations- Verifies safety margin & supports optimization
31
Regulatory Context
• Federal EIS Guidelines• Federal EIS Guidelines • CNSC policy P-290 – Managing radioactive wastes• CNSC guidance G-320 – Assessing the Long TermCNSC guidance G 320 Assessing the Long Term
Safety of Radioactive Waste Management• Nuclear Safety and Control Act and associated
applicable regulations• Canadian regulations and guidance consistent with
international recommendationsinternational recommendations (especially IAEA – International Atomic Energy Agency)
32
Operational (Preclosure) Safety
33
Accidents – Hazard Identification
Operating Initiating Events
Initiating Events Equipment Hazardous Materials
Hazardous Events
Consequences
Cause
Operating Initiating EventsPower failure
Equipment failureCage failureHuman error
Vehicle accidentWaste Containers
ILWLLW
Waste typeILWLLW
Inadequate shielding
Breach
Fi
Radiological
RadiologicalChemical
Radiological
Geotechnical Initiating EventsSeismic activity
Rock fall TruckForklif tCrane
Fire
Explosion
RadiologicalChemical
RadiologicalChemical
External Initiating EventsSevere rainfallExtreme wind
Extreme snow loadUnderground f looding
E t l f i
CraneHoist
Power failure
H2 and CH4 in emplacement Explosion Radiological
34
External f ireAirplane crash
LightningMeteor impact
emplacement rooms
Explosion Chemical
B di A id tBounding Accidents
• FireFire• Container Breach (Low Energy)
C t i B h (Hi h E )• Container Breach (High Energy)• Inadequate Shielding• Ventilation System Failure
35
Example Accident analysisExample – Accident analysis
Release Transport Effects
Q = MAR x DR x ARF x RF x LPF
Q – Amount Released
MAR – Material (Containers) At Risk
DR – Damage Ratio
ARF – Airborne Release Fraction
RF – Respirable FractionAtmospheric Dilution
LPF – Leak Path Factor VENTILATION RATE
QCP
Air Concentration
Cw
36PUBLICWORKER
Operational Safety: Summary
Normal operationsN li ibl di l i l i t t bli• Negligible radiological impacts to public
• Doses to worker within targets, and below limits.
AccidentsAccidents• Very small radiological impacts to public and workers• Below limits• Below limits
Overall consistent with WWMF experience
37
Long-term (postclosure) Safety
38
Scenarios Assessed
Normal Evolution ScenarioNormal Evolution Scenario• Likely future evolution of site• Assume people live on site in future.Assume people live on site in future.
Disruptive (“what if”) Scenarios• Human Intrusion:
Inadvertent intrusion into DGR via exploration borehole• Poorly Sealed Borehole:
P l l d it i ti ti b h lPoorly sealed site investigation borehole • Severe Shaft Seal Failure• Vertical Fault:
39
• Vertical Fault:A vertical fault in rock opened by a large earthquake.
Illustration of Pathways Analysed forIllustration of Pathways Analysed for Normal Evolution Scenario
40
Normal Evolution Scenario - Results
• Slow water seepage into DGR; full saturation expected to take more than 1,000,000 years.
• Organic wastes and steel containers degrade slowly; resulting in formation of gas, mostly methane.Almost all radioacti it is retained ithin and deca s• Almost all radioactivity is retained within, and decays within, the repository and surrounding rock.
• Negligible amounts may be released after long timesNegligible amounts may be released after long times.• Nuclides of interest: Carbon-14 as gas; Chlorine-36,
Iodine-129, Niobium-94 and Zirconium-93 in water.
41
,
Example of Detailed Model ResultsProfile of Cl-36 concentration, showing
Cl-36 is retained in the rocks around DGR
42(NE-RS case)
Calculated Peak Dose Rates:Normal Evolution Scenario
Reference Case, water limitedReference Case, final preliminary design
Reference Case
Alternative critical groupsSimplified Base Case
Instant resat. & release, no sorption, no gas gen.100 m surface erosion
Instant resaturation, no gas generationIncreased inventory
Tundra climate state
r Nor
mal
Evo
lutio
n
Bac
kgro
und
Rad
iatio
n
I d ti tInstant resat. & release, no sorption, no gas gen.
Increased permeability of shaft and repository EDZsDecreased degradation rates
Simplified Base Case, water limitedNo methanogenic gas reactions
Horizontal g/w flow in Guelph and Salina A1 upper carbonateAlternative critical groups
Dos
e C
riter
ion
for
Dos
e fr
om N
atur
al B
1.0E-15 1.0E-12 1.0E-09 1.0E-06 1.0E-03 1.0E+00
Increased gas gen. & reduced shaft seal performanceIncreased gas gen. & reduced shaft seal perf., final prelim. design
Increased gas generation rates
Maximum Calculated Effective Dose (mSv/a)
Reference Case and variant cases
Simplified Base Case and variant cases
43
Calculated Peak Dose Rates:Disruptive Scenarios
Severe Shaft Failure
Human Intrusion
Normal Evolution Scenario: Reference Case
grou
nd
Vertical Fault
Poorly Sealed Borehole
Severe Shaft Failure
Dos
e C
riter
ion
for
Dis
rupt
ive
Eve
nts
Dos
e fr
om N
atur
al B
ackg
Rad
iatio
n
1.0E-15 1.0E-12 1.0E-09 1.0E-06 1.0E-03 1.0E+00Maximum Calculated Effective Dose (mSv/a)
D
44
SUMMARY
45
DGR SummaryDGR Summary• Long-term management facility for low and intermediate nuclear waste
only. Used fuel will not be placed in the DGR.
• Extensive regulatory process is one of several mechanisms to ensure safety of public and the environment.
• Extensive community support dialogue and engagementExtensive community support, dialogue and engagement.
• Bruce nuclear site is ideally suited for DGR because of the natural attributes of the rock.
• DGR is consistent with OPG’s long-standing record of safety excellence.
• DGR will be constructed if it is safe to do so, and only with regulatory approval and community support.
• The completed peer-reviewed studies validate the safety case; the regulatory process provides oversight to confirm.
46
Th kThank-you
FFor more information, please visit
47
, pwww.opg.com/dgr