delay and analysis (ppt)

29
Delay Analysis & AoA schedules

Upload: leilani-johnson

Post on 22-Nov-2015

121 views

Category:

Documents


5 download

DESCRIPTION

Delay and Analysis (PPT)

TRANSCRIPT

  • Delay Analysis & AoA schedules

  • Basics of DelaysWhat is a Delay?Act or event which extends time required to perform or complete work of the contractWho causes delay?OwnerContractorNeither (Force Majeure)Both

  • Categories of DelaysIndependent DelaysSerial DelaysConcurrent Delays

  • Types of DelaysFloat DelaysCompletion DelaysInexcusable DelaysNon-Compensable DelaysExcusable DelaysConcurrent DelaysCompensable Delays

  • Inexcusable DelaysUsed in reference to delays caused by contractors, subs or vendors that delay the projectExamplesFailure to properly man projectFailure to submit documents on timeFailure to coordinate equipment, material deliveriesPoor planning and mismanagementContractor is often asked to pay damages (LDs)

  • Excusable Delays - 1Non CompensableUnforeseen events that are not the fault of the owners or the contractorsE.g.Acts of GodFires, StrikesPolitical EventsUsually only Time implicationsForce Majeure clauses in contracts decide how to deal with these delays

  • Excusable Delays - 2CompensableDelays caused by owner or for which owner has accepted liabilityE.g.Change OrdersDelayed responsesWork SuspensionsTime and Cost implicationsClauses in contracts decide how to deal with these delaysNo Damage for Delays clauses may also be present

  • Concurrent DelaysOwner and Contractor both delay the same activity or activities in the same timeframeMultiple Delays to activities on parallel Critical Paths within same time-frameExampleChange order coinciding with late equipment deliveryLate response to an RFI at the same time as a strike

  • Concurrent Delays

  • Pacing DelayContractor A is delayedTherefore Contractor B slows down work on parallel Activities

    Contractors have a legal right to slow down!

  • Key Requirement for Delay AnalysisA Network Schedule that isCompleteWith Reliable InformationIs ApprovedReflects the Intended PlanIs not manipulated (by loading activities)Is Constantly Updated

  • Network Schedule TipsShould be prepared by, or in consultation with the contractorShould have inputs fromContract DocumentsProject Manager, EstimatorSuperintendents and SubcontractorsClients and ArchitectsIterative, Negotiated, Inclusive Process

  • Delay Analysis TechniquesFloat Analysis

    As-Built Analysis

    As-Planned Analysis

    Concurrent Delay Analysis

    Window/Snapshot Method

  • 1. Float AnalysisIndependent Float belongs to the activityTF, FF belong to a chainProportion Float according to Activity DurationDetermine delays and effect on critical paths

  • As Built AnalysisCreate final As Built scheduleCompare with As Planned scheduleCalculate Difference this is Delay owed by the other sideFind events to explain these differences

  • As Planned AnalysisCreate As-Planned vs. As-Built schedulesDetermine delay events (caused by the other side)Add these events, re-calculate scheduleDetermine Time extension, compensation owed etc

  • Concurrent AnalysisA (5 days)B (7 days) - CriticalA (8 days)B (9 days) - CriticalAs PlannedAs BuiltOwner caused delay= 3 daysContractor caused delay= 2 daysTotal Contractor Liability = 1 day

  • Concurrent AnalysisCreate As-Planned and As-Built schedulesEstimate Critical Path DelaySubtract concurrent owner-caused or unforeseen delaysUse the remainder to apportion time extensions or costs

  • Choosing a Delay Analysis MethodDelay Analysis is still an art not a scienceDepends on time availableSnapshot method takes too longDepends on data availableDepends on accuracy desiredAs Planned and As Built methods are quick but inaccurate

  • AoA AnalysisNodesMilestones=LinksActivities=A12Excavate3 DaysConstruction Network

  • Criteria for creation of AoA NetworksRepresents Activities on Arrows with Start/Finish milestonesEstimate Activity Duration and represent it on the arrowEnsure each activity has a unique I and jnode Create artificial restraintsSolve the Network

  • Lets Create an AoA Network for the Following activities

  • AoA Diagram

  • Solving the Network101216222628142418200Start11A5F5I3K7D3 B 17J19 H5 G9 E 9C

  • Forward Pass Early Event Times101216222628142418200Start11A5F5I3K7D3 B 17J19 H5 G9 E 9C031192016113740

  • Backward Pass Late Event Times101216222628142418200Start11A5F5I3K7D3 B 17J19 H5 G9 E 9C03119201611374040371820321118013

  • Solving the Network10-12-16-24-26-28 is the critical pathCalculate ES of each activityEarly Event Time of i NodeCalculate EF of each activityES + DurationCalculate LF of each ActivityLate Event Time of j NodeCalculate LS of each ActivityLF DurationCalculate Floats, Critical Path

  • Convert to PDM

  • Thank You

    Plans are usually made with the unlimited resource assumptionFloat Consumption delays typically do not impact overall schedule and often do not result in extra costs or time extensions. However, there could be cases where these activities can be claimed as delays that result in extra overhead costs or equipment rental costs etc

    These usually result in time extensions but no cost implicationsSome times if events are not explicitly in Force Majeure, they can lead to claimsThese usually result in time extensions AND in cost implicationsSome times if events are not explicitly in Force Majeure, they can lead to claimsThis is too simplistic a methodThis is slightly more scientific but omits concurrent delays and cause and effect situationsSame example from text bookDotted lines show logical and not physical constraints