distributed energy resource an aeso perspectiveapic/uploads/forum/p7f2018.pdf · an aeso...

13
2018-05-08 1 Distributed Energy Resource an AESO Perspective Steve Heidt P. Eng., AESO About the AESO Grid planner and operator reliability is our highest priority Connects new generation and load Facilitates wholesale electricity market Operates Renewable Electricity Program (REP) to achieve ‘30 by 30’ green energy goal 2 02/21/2018 Public

Upload: others

Post on 25-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

1

Distributed Energy Resourcean AESO Perspective

Steve Heidt P. Eng.,

AESO

About the AESO

• Grid planner and

operator – reliability is

our highest priority

• Connects new

generation and load

• Facilitates wholesale

electricity market

• Operates Renewable

Electricity Program

(REP) to achieve ‘30 by

30’ green energy goal

202/21/2018 Public

Page 2: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

2

Snapshot: Alberta’s power system

3

• High industrial load

• 26,000+ km of transmission

• ~240 generating units

• ~650 substations

• 16,346 MW installed generation

– 11,697 MW winter peak (Jan. 11/18)

• Strong transmission system to

support competitive wholesale

power market

• ~200 projects active in AESO

connection queue

02/21/2018 Public

Evolving generation mix – transition

from coal to gas/renewables

By 2037:

• Coal ↓ 6,299 MW

• Cogen ↑ 405 MW

• Gas-fired ↑ 6,658 MW

• Coal-to-gas ↑ 790 MW

• Renewables ↑ 6,350 MW

402/21/2018 Public

Page 3: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

3

Transmission Operation Basics

• Energy Balance Equation

– Main rule is that Supply = Demand

– Generation + Import = Load + Losses + Exports

• Short on Supply => reduction in speed (or import through a AC

Tie)

• Conventional Generation are Electro-Mechanically coupled

to the Grid

– Large Mass generators spinning at grid frequency

– System inertia

5

Example: Frequency Response

6Source: https://www.ferc.gov/industries/electric/indus-act/reliability/frequencyresponsemetrics-report.pdf

Disturbance

Inertial Response

Frequency Nadir

Primary Frequency

Response

Page 4: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

4

DER

• Wind, Solar and Battery Storage resources are Electronically

Coupled to the grid

– Inverters have a very fast electronics (DC to AC)

– This is a Digital Revolution in power generation, with the ability

to program the behaviors we need … But we need to fully

understand exactly what we want

7

Definition of REVOLUTION

– a sudden, radical, or complete change

– activity or movement designed to effect fundamental changes

in the socioeconomic situation

– a fundamental change in the way of thinking about or

visualizing something

– a changeover in use or preference especially in technology ie.

the computer revolution, the foreign car revolution..

• Maybe a Power System Revolution…

• Mainly thanks to Power Electronics

From a Nikola Tesla Model => Sustainability Model

Source: Merrian-Webster Dictionary8

Page 5: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

5

DER - Definitions

• NERC Definition

– A Distributed Energy Resource (DER) is any resource on the

distribution system that produces electricity and is not

otherwise included in the formal NERC definition of the Bulk

Electric System (BES).

• In Alberta (Informal)

– Distributed Energy Resource (DER) is any resource on the

distribution system that produces electricity

– Resources greater than 5 MW are Pool Participants

• Bound by some Rules and Standards

9

Help from industry

• Germany Experience

– Renewables went from 6% to 31% in 15 years

• Industry on DER

– IEEE 1547 – Interconnection and Interoperability of Distributed

Energy Resources with Associated Electric Power Systems

Interfaces (April 2018)

– 2003 DER shall not actively regulate the voltage

– 2014 DER may actively participate to regulate the voltage by

changes of real and reactive power

– 2018 DER shall provide voltage regulation capability by

changes of active and reactive power

• AESO is using this as a guide

10

Page 6: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

6

Could DER cause Reliability Concerns?

• It's possible, if you're not prepared!

• In mid 2017 there was 475 MW on Alberta’s system

– Have not seen concerns at that level … so far

– But when will we have concerns/troubles?

11

Could DER cause Reliability Concerns?

• It's possible, if you're not prepared!

• In mid 2017 there was 475 MW on Alberta’s system

– Have not seen concerns at that level … so far

– But when will we have concerns/troubles?

• How about this for a test..

– What would you see if you had a 12,000 MW system with

6,000 MW of DER? (this is not a forecast – It’s a test)

– What concerns show up?

12

Page 7: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

7

Thinking your way through it?

• Supply adequacy & Forecasts

– Where are the DERs?

– What their’s fuel type?

• Wind, Solar, Gas, Battery, Other

– What is their pattern of generation levels?

– Where are they connected to (which Substation / Area)?

– What is their ride through capability?

– What happens during a Solar Eclipse / Storms / Holidays?

13

Thinking your way through it?

• Supply adequacy & Forecasts

– Where are the DERs?

– What their’s fuel type?

• Wind, Solar, Gas, Battery, Other

– What is their pattern of generation levels?

– Where are they connected to (which Substation / Area)?

– What is their ride through capability?

– What happens during a Solar Eclipse / Storms / Holidays?

• We need good data and be able to forecast.

14

Page 8: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

8

CAISO’s “Duck Curve”

– California’s version of NDV Daily Curve

Net Demand = Load Demand – Variable Generation

In California the variable generation is mainly solar generation

15

18,000

19,000

20,000

21,000

22,000

23,000

24,000

25,000

26,000

27,000

28,000

29,000

30,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

MW

Average of CAISO's Load for 5 Consecutive weekdays --- 2008 VS. 2018

CAISO Load 2008 CAISO Load 2018

Pa

ge

1

Actual California Spring “Gross Load” March 2008 vs. March 2018

Page 9: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

9

Thinking your way through it

• What is our true system load?

• How are DER generating now?

• How are DER offsetting distribution load?

• Will this effect our Operation Reserves?

• How do we know if our forecasts on DER is close?

• Do we have enough supply adequacy?

17

Thinking your way through it

• What is our true system load?

• How are DER generating now?

• How are DER offsetting distribution load?

• Will this effect our Operation Reserves?

• How do we know if our forecasts on DER is close?

• Do we have enough supply adequacy?

• We need Real Time Visibility

– > 1MW (projected)

– Grouped by fuel class and

– Feeder Substation or Area18

Page 10: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

10

Thinking your way through it

• How does DER effect System events

– Frequency Events

– Voltage events

– Older Technical standards like IEEE 1547 says

• Must trip or may ride through

19

Thinking your way through it

• How does DER effect System events

– Frequency Events

– Voltage events

– Older Technical standards like IEEE 1547 says

• Must trip or may ride through

– We need ISO Rules

• Defined Criteria for

– Must Ride through

– May trip

• Revised IEEE 1547 outline industry expectations

20

Page 11: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

11

Thinking your way through it

• Tariff

– Cost causation

– DER pay for their part of transmission costs

• Transmission Remedial Actions Schemes

– In a transmission constrained area should DER be RAS(s)?

• Governor Controls

– Under and Over Frequency

• Power Limiting Controls

– Direct down Capability

21

Thinking your way through it

• DER Metering / Settlement Information

– Rules and Modification outlining settlement changes?

• Market Rules and the applicability to DER

– Does the Market need modifications?

– Should the Must offer/must comply change?

• Planned / unintentional Islanding (and anti-islanding) for

Transmission Events

– Transmission Based Islanding standards?

22

Page 12: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

12

DFO rules

• Technical Rules

– Controllability (Dispatch Down or off)

• ISO needs this too

– Voltage Control, Voltage Regulation

• Reactive Power Capability and reactive power control

• AVR like controls

– Volt-Var Control

– Volt-Watt Control

– Planned / unintentional Islanding (and anti-islanding) for

distribution events

23Draft - Subject to change

Industry Background

• The ISO

– Direct/obligate pool participants in accordance with ISO rules.

(Generators that are >5MW, TFOs, and DFOs)

– Direct the DFOs to manage DERs that are not pool

participants to manage transmission reliability.

• DFO manages/directs distribution reliability

• For all other future ISO requirements

– the ISO would obligate the DFO who in turn would enforce

these requirements onto DER owners.

24

Page 13: Distributed Energy Resource an AESO Perspectiveapic/uploads/Forum/P7f2018.pdf · an AESO Perspective Steve Heidt P. Eng., AESO About the AESO •Grid planner and operator –reliability

2018-05-08

13

Thank you