Dr Louis Gunnigan
Dublin Institute of Technology Campus Planning Team
DIT New City Centre Campus at Grangegorman
20 May 2015
• Background
• Governance
• Milestones
• Challenges
• Progress
• Future Works
Agenda
• 120+ years of excellence in education
• 39 locations around Dublin
• 10% of third level in Ireland
• National provider
• Applied, career-focused education
• Degree-awarding; apprenticeship to PhD
• 80% of graduates employed in
professions
• Always ranked in top 4 for CAO
applications
• Ranked in top 4% THES world rankings
Dublin Institute of Technology
20,000
students
200 part-time
programmes
4,000 graduates &
500 postgraduates
per year
85 full-time
programmes
1,800 staff
4 colleges
DIT across the city
Bolton St.
Chatham Row
Cathal Brugha St.
Aungier St.
Kevin St.
Rathmines
Mountjoy Sq.
DIT before Grangegorman
• To provide education that meets DIT’s social,
economic, and cultural mission.– Via student-centred learning.
– Using leading-edge technology.
– With facilities currently lacking.
Why Move?
Student Accommodation
Sports
Recreation
• Synergies and opportunities
• Consistently excellent integrated student experience
Significant costs to upgrade
existing premises
Lack of critical mass – clubs
and societies
Interdisciplinary activities
New & emerging disciplines
Modularised offerings
30 Ha site in the heart of Dublin.
1.3km
City Centre Site
DIT’s Part of the City
Trinity
College
UCD
DIT
DCU
Project Governance
Masterplan
Integration with surrounding streets
Urban scale and form
Incorporating existing protected structures
Exploiting existing landscape and views
•2009 Urban Design Award US Institute of Architects
•2009 World Architecture Festival
•2010 Chicago Athenaeum 2010 American Architecture Award
•2012 American Institute of Architects (AIA) National Honor Award for Regional & Urban Design
•2012 Honor Award - Society for College and University Planning
• Comprehensive strategic planning framework for
380,000m2 of phased development
• Extensive public consultation
• Approval of SDZ by Dublin City Council
• Approval on appeal from the An Bord Pleanála
Strategic Development Zone (SDZ)
DIT Milestones to date
DIT Campus Planning Office
relocates to Grangegorman
2007Preparation of Draft DIT
Strategic Briefs
DIT Campus Planning Office
Established2002
“Joining the Dots”Employment Study
May 2009
Masterplan Approved 2008
Cabinet DecisionJuly 2010
& Government
Launch September
2010
Concept planning Education
Related Lands
Transferred Feb 2012 to
GDA
SDZ Planning Approval May 2012 New
Implementation Programmes for
DIT May 2012
Government announce
revised funding
arrangementsJuly 2012
2013First building
works contracts
begin
First 1000 students arrived
Sept 2014
Future DIT Milestones
DIT becomes part of Dublin
Technological University 2015/16
Central and East Quads complete10,000 students on site
Sept 2017
Greenway Hub (EHSI/Hothouse Building)
to open Q1 2016
GDA sells DIT buildings at Kevin St and
Cathal Brugha St2018
Construction begins on Student
Accommodation and Library Building
2016
West Quad (Business College)
complete 2020
Engineering and Built
Environment Quad complete
2023
Energy Centre constructed and commissioned
2016
Progress - Grangegorman 2008 - 2015
Progress
Nov 2013
Nov 2014
Current Principle Funding Sources
Pre-Planning
Grangegorman Works Packages – Status at May 2015
Procurement / Construction
Design/Planning
Completed
Future Works Packages
Site Infrastructure & Public Realm
HSE
Community
Nursing Unit
DIT Student
Accommodation
Phase 1
DIT Foodhall
Prussia St
GateEnergy
Centre
DIT
Academic
Hub Ph1
DIT Indoor
Sports Ph1
DOES
Primary
School
DIT Central Quad
DIT East QuadBroadstone
GateHSE Primary
Care
DIT
Greenway
Hub
DIT
Broombridge
Phase 1
DIT
Stabilisation
Works
Dublin Bus
Bus Park
DIT PPP
DIT
Adaptive Reuse
Clock Tower
DIT Demolitions
Contracts 1 & 2
DIT
Adaptive Reuse
Contracts 1 & 2
HSE
Phoenix Centre
DIT Eng/BE
Quad
DIT
Student
Centre
DIT West
Quad
DIT Student
Accommodation
Phase 2
DIT
Adaptive Reuse
Contract 3
Demolition– complete
Stabilisation– Underway
Site Infrastructure works
SIPR- West side complete
- Smithfield SW drain Completed
- East side Works substantially complete
LUAS works
Bus parking structure SIPRStabilisation of Lower House
Energy Distribution
Primary Underground Services Utilities Route - Masterplan
Primary Underground Services Utilities Route - Tranche 1 &
Masterplan
T
P
P
EXISTING ESBN SUBSTATION (HSE)
PROPOSED ESBN SUBSTATION (WEST)
TEMPORARY EXISTING ESBN SUBSTATION
(MORTUARY BLD)
PROPOSED ESBN SUBSTATION (EAST)
FUTURE ENERGY CENTRECOMMUNICATIONS ROOM B (MORTUARY
BLD)
COMMUNICATIONS ROOM A
(TOP HOUSE)
NATURAL GAS TIE-IN POINT (TBC)
INCOMING CABLE CHAMBER
Services Infrastructure
Adaptive Reuse
Adaptive Reuse
North House Studios
Adaptive Reuse
Adaptive Reuse – Cluster Buildings
North House
Adaptive reuse
Adaptive Reuse – (Cluster Buildings)
Complete Q1 2016
Floor Area 4,700m2
Design & Build Contract
Greenway HubGreenway Hub (ESHI and Hothouse)
East Quad
• ~16,000 m2
• ~3,000 students
• Creative arts and digital
media
Programme 2 - PPP Development (2012-17)
Central Quad
• ~34000m2
• ~7,000 students
• Consolidation of science,
health, food, tourism,
electrical/electronic
engineering
Phase 3 - New Construction Works up to 2018
HSE Primary Care
DOES Educate Together
Primary School
DIT Central Quad
DIT Student Accommodation Phase 1
& Dining Hall and Student Centre
DIT East Quad
DIT Academic Hub Phase 1
DIT Energy Centre Phase 1
DIT Sports Centre Phase 1
RPA LUAS
Broadstone Gate
Prussia St Gate
• Sports Phase 2 (6,000m2)
• Academic Hub Phase 2 (5,000m2)
• Relocation of Focus Building (3,000m2)
• Business Quad (8,500m2)
• Engineering/Built Environment Quad (27,000m2)
• Other Learning spaces (7,000m2)
• Second Dining Hall (7,500m2)
• Refurb of remaining of protected structures (2,000m2)
• 900 further Student Beds (total 57,000m2)
• Retail (3,600m2)
• Maintenance/Services/Utilities (2,800m2)
• Industry/Incubation Centre (10,800m2)
• Additional research space (6,300m2)
• Additional performance space (3,600m2)
• Further Expansion spaces (34,000m2)
(All areas provisional)
Programmes 4, 5 and beyond
• Huge programme of works
• Diverse contract types
• Multiple funding sources required
• All current milestones achieved
• On time to achieve 2017 milestone
• Enormous programme of works over next 4/5 years
Conclusion