Starfire Energy’s 10 kg/day Rapid Ramp NH3
System Development
Funded by ARPA-E 2015 Open # DE-AR0000685DOE SBIR # DE-SC0019846Colorado OEDIT # CTGG1 19-3593
Starfire Energy IncJoe Beach, CEO
Rapid Ramp
![Page 2: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/2.jpg)
2
Starfire Energy is a clean energy company
● Research, development, deployment● Solar, hydrogen, business background● 7 full-time, 2 part-time staff
![Page 3: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/3.jpg)
3
Clean power plants into clean fuel factories
New US Great Plains wind● $0.012 – $0.020/kWh● 50% – 65% capacity factor
New US Southwest solar● $0.04 - $0.07/kWh● 20% - 30% capacity factor
![Page 4: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/4.jpg)
4
Clean power plants into clean fuel factories
New US Great Plains wind● $0.012 – $0.020/kWh● 50% – 65% capacity factor
New US Southwest solar● $0.04 - $0.07/kWh● 20% - 30% capacity factor
![Page 5: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/5.jpg)
5
Fuel synth. must mesh with variable power
New US Great Plains wind● $0.012 – $0.020/kWh● 50% – 65% capacity factor
New US Southwest solar● $0.04 - $0.07/kWh● 20% - 30% capacity factor
![Page 6: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/6.jpg)
6
“Rapid Ramp NH3”: flexible ammonia synth.
● N2 and H2 used as they are made● No massive reactant buffering
NitrogenUnit
HydrogenUnit
Rapid RampNH3
AmmoniaStorage
Air
Water
CleanElectricity
N2
H2
NH3
![Page 7: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/7.jpg)
7
Monolith catalyst & NH3 adsorption are key
Monolith catalyst● High catalyst utilization● Near-zero pressure drop
NH3 adsorption removal● No liquefaction constraints● Any reactor P or T
N2
H2
NH3
N2
H2
Adsorption Bed
Saturated
Unsaturated
![Page 8: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/8.jpg)
8
Implementing process in 10 kg/day system
● PSA nitrogen● AEM hydrogen● 30 bar e-chem
H2 compress.
● Pneumatic N2 press. boost
![Page 9: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/9.jpg)
9
Building 10 kg/day system as we speak
Electrolyzer
AirCompressor
Air Dryer
N2Booster N2 PSA
Heat Exchanger & Reactor
CirculationPump
LiquefactionCompressor
Regen.Pump
![Page 10: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/10.jpg)
10
10 kg/day is first of several iterations
● 10-25x scaling increments to 50 tpd● Each scale has a purpose● Integration, modularization, market
validation, mass production
ProofOf
Concept
LaboratoryScale
Reactor
10 kg/dayIntegrated
System
100 kg/dayModularSystem
2 tpdCustomer
Offtake
50 tpdSystemsFor sale
SmallSystemsFor sale
2 tpdSystemsFor sale
2016-2017 2018 2019 2020 2021 2022 2023
50 tpdSystemDesign
![Page 11: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/11.jpg)
11
Modular systems reduce business risk
● Cost $10M’s instead of $1000M● Add units as need increases● Deploy near end-use● Deploy near clean energy
VS
Increase number of modular units
Increase unit size
Two ways to increase capacity
![Page 12: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/12.jpg)
12
Unit size & mass prod. reduce NH3 cost
● Assumes 65% CF, $0.01/kWh● Unit size dictated by capex and desired initial NH3 cost● Mass production continues to drive down cost
![Page 13: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/13.jpg)
13
Synthesis tech refinement continues
● Lower capex membrane-less H2
● Variable-power membrane N2 ● Better adsorbent material & process● Capex – operating pressure – NH3 cost
![Page 14: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/14.jpg)
14
Expanding into NH3 fuel utilization
● Monolith NH3 cracking catalysts● Natural gas burner conversion ● High purity, high pressure H2 from NH3
Catalyst
![Page 15: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/15.jpg)
15
Expanding Starfire Energy’s NH3 team
Year Staff
2015 1
2016 2
2017 3
2018 4
2019 7 + 1 part-time
![Page 16: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/16.jpg)
16
Questions?
● Monolith catalyst & NH3 adsorption● 10 kg/day system being built● Iterate to 50 tpd modular system● Mass produce to drive down costs● Developing NH3 fuel utilization tech
![Page 17: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/17.jpg)
17
Additional slides
![Page 18: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/18.jpg)
18
Synthesis rate ramps with reactant flow
0 300
150
30
60
90
120 180
210
240
270
Haber-Bosch
Rapid RampCapability
Low CapEx
Operating Pressure, bar
![Page 19: Starfire Energy’s 10 kg/day Rapid Ramp NH System Development€¦ · 12/11/2019 · Modular systems reduce business risk Cost $10M’s instead of $1000M Add units as need increases](https://reader033.vdocument.in/reader033/viewer/2022051902/5ff1c17a2f6c3424fa5d7534/html5/thumbnails/19.jpg)
19
“Rapid Ramp” demonstrated
● 75% H2, 25% N2
● Flow increased by opening recirculator throttle valve
● Rate follows flow very closely● Rate ramp rate = flow ramp rate