dsf cooling plant progress

8
DSF cooling plant progress A. Francescon and M. Janda

Upload: nuncio

Post on 23-Jan-2016

30 views

Category:

Documents


0 download

DESCRIPTION

DSF cooling plant progress. A. Francescon and M. Janda. Test section status. The test section is already built on the Bosch. We only miss: one differential pressure transmitter tranparent plastic pipe as windows temperature transmitters flowmeter. Test section next activities. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: DSF cooling plant progress

DSF cooling plant progress

A. Francescon and M. Janda

Page 2: DSF cooling plant progress
Page 3: DSF cooling plant progress

Test section status

The test section is already built on the Bosch.

We only miss:• one differential pressure transmitter• tranparent plastic pipe as windows• temperature transmitters• flowmeter

Page 4: DSF cooling plant progress

Test section next activities

• Dummy sector degassing• Test section cleaning• Flowmeter installation and connection to

ELMB.

Page 5: DSF cooling plant progress

The plant

The plant should be ready to move to DSF.

After the arrival we havo to:• connect the loops to the SS pipes outside DSF;• close the line inside DSF (maybe excluding the test

section?);• (install capillaries in between?).

Then we can start to test the plant, initially without the test section, then adding also the test section.

Page 6: DSF cooling plant progress
Page 7: DSF cooling plant progress
Page 8: DSF cooling plant progress

Other activities

• ELMB and sensor calibration;• Finalize the readout of all sensors;• Integration between data from the plant and

data from the test section in a single PVSS project.