ensuring safety in occupied buildings - r4risk
TRANSCRIPT
![Page 1: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/1.jpg)
R4RiskL14, 222 Kings Way (PO Box 5023)
South Melbourne VIC 3205
P: (03) 9268 9700
F: (03) 8678 0650
www.r4risk.com.au
©R4Risk 2021
Ensuring Safety in Occupied Buildings
Elio Stocco
Director
28 April 2021
![Page 2: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/2.jpg)
©R4Risk 2021
Your Speaker
• Elio Stocco
• Director & Principal Risk Consultant
• CEng, RPEQ, Feng (TÜV Rheinland)
• Over 30 years’ experience
o Operations / process safety / risk management consulting
• Technical Expertise:
o Hazard identification and risk assessment (HAZOP, SIL,
LOPA, CHAZOP)
o Safety case development and auditing
o Emergency response planning
o Fire, toxic and explosion modelling
o Occupied buildings risk assessment
225 May 2020
![Page 3: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/3.jpg)
©R4Risk 2021
R4Risk – Risk Management & Process Safety
3
Technical Studies Process Safety Management
• Hazard Identification (HAZOP, HAZID)
• Layer of Protection Analysis (LOPA)
• Safety Integrity Level (SIL)
• Fire Safety Studies
• Quantitative Risk Assessment (QRA)
• Consequence Analysis
• Emergency Response Planning
• Hazardous Area Assessment
• Occupied Building Risk Assessment (OBRA)
• Dangerous Goods Management
• Major Hazard Facilities Safety Management
• Process Safety Management Studies
• Safety Case Development
• Safety Case Compliance Auditing
• Safety Case / Report Approved Assessor
• Safety Management System Development
• Accident Investigation
Business Risk Management Training
• Business and Operational Risk Management
• Enterprise-Wide Risk Management
• Process Safety and Risk Management Training
• Risk Mentoring
25 May 2020
![Page 4: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/4.jpg)
©R4Risk 2021
Overview
• Previous incidents
– Fires, explosion and toxic events
• Describe the guidance to manage the risk to personnel inside
buildings
• Siting evaluation based on explosion
4
![Page 5: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/5.jpg)
©R4Risk 2021
Flixborough: June 1, 1974
5
• A vertical crack in reactor No.5 was leaking cyclohexane.
• Reactor was removed with a bypass assembly installed
• Bypass ruptured releasing a large quantity of cyclohexane
• Formed flammable vapour mixture found a ignition source
• 28 workers killed with 36 suffered injuries
• 18 fatalities in the collapsed control room
![Page 6: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/6.jpg)
©R4Risk 2021
Jet Fire: Hickson & Welch, 1992
6
• Clean operation was organised to remove residue from vessel used to distil organic liquid in a batch process
• Residue (MNT, organic nitro products) was heated to assist removal
• Exothermic reaction within residue leading to the jet flame erupting from manway, approx. 50 m
• Flame cut through an office / control building nearby
• Flame reached four-storey office block, shattering windows and setting rooms on fire
• 5 workers killed and numerous injured
![Page 7: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/7.jpg)
©R4Risk 2021
BP Texas City: 23 March 2005
7
• Restarting of a hydrocarbon isomerisation unit
• Overpressure of flooded distillation tower causing a release from the vent stack
• Large flammable vapour cloud (~19,000 m2 area)
• Suspected ignition source an idling diesel pickup truck
• 15 workers killed with 180 injured
• Majority of fatalities where personnel in trailers near vent stack
![Page 8: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/8.jpg)
©R4Risk 2021
Texas City: Overpressure Impact
8
CSB (2007), "Investigation Report of Refinery Explosion and Fire, BP Texas City, Texas”
![Page 9: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/9.jpg)
©R4Risk 2021
Toxic Releases
• Richmond, California USA (July 26, 1993)– Oleum release from tank car
– Employees in the direct path sheltered indoors
– No injuries reported to employees but 22 hospitalised in the community
• Nitro, West Virginia USA (December 5, 1995)– Release of a phosphorus chloride compound
– Rain results in formation of HCl cloud that drifted off-site
– 800 employees sheltered-in-place, no injuries reported
• Ludington, Michigan USA (February 7, 1993)– Release of bromine gas
– Sheltered-in-place for 3 hours
– No injuries
9
![Page 10: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/10.jpg)
©R4Risk 2021
Management of Hazards for Occupied Buildings
• Guidance developed for building occupants
– API RP 752: Location of Process Plant Buildings (2009)
– API RP 753: Location of Process Plant Portable Buildings (2007, Reaffirmed Aug 2020)
• Planning strategies address different hazards:
– Building collapse when subject to blast loads from explosion
– Thermal hazards from fires
– Ingress of toxic vapour
• Assessment approach
– Consequence based
– Risk based
– Spacing tables
10
![Page 11: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/11.jpg)
©R4Risk 2021
API RP-752:
Location of Process Plant Buildings
• New and existing rigid structures permanently placed
• Management process for siting evaluations:
– Locate personnel away from process areas
– Minimise the use of buildings close to process areas
– Manage occupancy within those buildings close to process areas
– Buildings intended for occupancy should be designed, constructed, modified and
maintained to protect against hazards
– Manage the building occupancy as part of facility operation
11
![Page 12: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/12.jpg)
©R4Risk 2021
API Assessment Approach
• Determine buildings to be included in assessment scope
– Permanent / temporary / new
• Identify process hazards with potential to impact buildings
– For each hazard, model related scenario(s) to determine impact
• Chose the building evaluation criteria
– Consequence-based
– Risk-based
– Spacing tables
12
![Page 13: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/13.jpg)
©R4Risk 2021
API Assessment Approach (Cont’d)
• Evaluate building response to determined level of impact
• Compare impact with building siting evaluation criteria
• For an existing building, mitigation options need to be considered when
the criteria is not met
• Develop and implement the mitigation plan
• Personnel performing building site evaluation must have competence in
analysis techniques
13
![Page 14: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/14.jpg)
©R4Risk 2021
API RP-752:
Management of Change (MOC)
• Operator should identify the situations requiring MOC:
– A new building intended for occupancy
– Modification to existing building that may alter vulnerability to different events
– Moving from not intended for occupancy to occupied
– Change in number of personnel or time spent
– Change in the process operation
• Hazardous material inventory
• New equipment
14
![Page 15: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/15.jpg)
©R4Risk 2021
Siting of New Buildings
• For new buildings
– Similar overall approach
– The building is then designed to meet the building siting evaluation criteria
15
![Page 16: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/16.jpg)
©R4Risk 2021
API RP-753:
Location of Portable Buildings
• Portable buildings– Offices, Training Rooms, Conference Rooms, Change houses
• Guiding principles similar to API RP-752– Modified for portable buildings
• Restrictions on personnel– Only essential personnel are allowed close to process units
– Placement requires detailed analysis
• Guidance for explosion hazards– Zones
16
![Page 17: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/17.jpg)
©R4Risk 2021
Consequence-Based or Risk-based
• Consequence –Based Approach
• Risk–Based Approach
• In scenario development both consider:
– Site specific data: material, inventories, operating conditions, process layout
– Industry knowledge on history of incidents at similar sites
17
![Page 18: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/18.jpg)
©R4Risk 2021
Evaluation of Existing Building Siting
• Identify VCE scenarios within plant
• Assess potential for VCEs to impact existing buildings
• Determine blast loads experienced by building
• Results compared with siting evaluation criteria
18
![Page 19: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/19.jpg)
©R4Risk 2021
Evaluating Location Based on Blast
19
2
1 3
![Page 20: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/20.jpg)
©R4Risk 2021
Building Damage Curves
20
US DDESB (2009), "Approve methods and algorithms for DOD Risk-Based Explosive siting"
![Page 21: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/21.jpg)
©R4Risk 2021
Evaluating Location Based on Blast
21
2
![Page 22: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/22.jpg)
©R4Risk 2021
Evaluating Location Based on Blast
22
1 3
![Page 23: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/23.jpg)
©R4Risk 2021
Mitigation Options
• Hierarchy of Mitigation Measures• Passive
• Active
• Procedural
• Typical option used
– Reduce consequence of release• However this maybe difficult to do as process is normally fixed
– Strengthening of building• Requires detailed structural analysis
– Relocation of personnel to alternate locations• Non-essential v. Essential
– Abandon the building
23
![Page 24: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/24.jpg)
©R4Risk 2021
Conclusions
• Use industry developed guidance for locating buildings in process areas
– Existing buildings should be checked
– Ensure siting evaluation is undertaken for portable buildings
• Manage building occupancy as part of facility’s operation through the
MOC process
• Use experts to apply building siting evaluation
24
![Page 25: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/25.jpg)
©R4Risk 2021
Upcoming Events
25
Webinars
o Linking Risk Assessments to Process
Safety Management (May 26 2021)
o After the Bowties – The Story
Continues (29 June 2021)
o Fire Safety Studies (29 July 2021)
Online Live Training
o Introduction to LOPA (19 – 20 May
2021)
o Risk Assessment Leader (25 – 28
May 2021)
o Introduction to Process Safety (22 –
23 June 2021)
For more information and registration, visit www.r4risk.com.au or contact [email protected]
![Page 26: Ensuring Safety in Occupied Buildings - R4Risk](https://reader030.vdocument.in/reader030/viewer/2022012705/61a73bcfc56ffa10ab0d58bc/html5/thumbnails/26.jpg)
©R4Risk 2021
Q&A Session
26