· environment and social compliance audit report . independent environmental, health, safety...
TRANSCRIPT
Environment and Social Compliance Audit Report Independent Environmental, Health, Safety & Social (EHS&S) Compliance Assessment Report Project Number: 44951-014 June 2016
BAN: Bibiyana II Gas Power Project
Prepared by ERM India Private Limited a member of Environmental Resources Management Group of companies on behalf of (Summit Bibiyana II Power Company Limited) for Asian Development Bank This environment and social compliance audit report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
The world’s leading sustainability consultancy
Fourth Independent Environmental, Health, Safety & Social (EHS&S) Compliance Assessment during Construction Phase of Bibiyana II Power Project, Habiganj, Bangladesh
Draft Final Report
1 June 2016
www.erm.com
Summit Bibiyana II Power
Company Limited (SBIIPCL)
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
I
CONTENTS
1 INTRODUCTION 1
1.1 BACKGROUND 1
1.2 OBJECTIVES AND SCOPE OF WORK 2
1.3 COMPLIANCE ASSESSMENT FRAMEWORK AND EVALUATION CRITERIA 3
1.4 ERM TEAM FOR SITE VISIT 3
1.5 APPROACH TO THE COMPLIANCE ASSESSMENT 4
1.6 LIMITATION 7
1.7 LAYOUT OF THIS REPORT 8
2 PROJECT APPRECIATION AND CURRENT STATUS OF THE PROJECT 9
2.1 THE PROJECT 9
2.2 PROJECT DEVELOPER 9
2.3 CURRENT PROJECT STATUS 10
3 SUMMARY OF KEY OBSERVATIONS 12
3.1 ENVIRONMENTAL, HEALTH & SAFETY 12
3.2 SOCIAL OBSERVATION 22
4 COMPLIANCE STATUS OF CAP & ESMMP AND IFC ESAP 36
5 EHS&S REGULATORY COMPLIANCE ASSESSMENT 59
6 CORRECTIVE ACTION ITEMS 67
7 CONCLUSION 72
ANNEX A PHOTO DOCUMENTATION
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
II
ABBREVIATIONS
ADB Asian Development Bank BATS Bangladesh Air Traffic Services BCAS Bangladesh Centre for Advance Studies BIWTA Bangladesh Inland Water Transport Authority BPDB Bangladesh Power Development Board BRTA Bangladesh Road Transport Authority CAP Corrective Action Plan CCPP Combined Cycle Power Plant CDO Community Development Officer CDP Community Development Plan CIB Chief Inspector of Boilers CMT Construction Management Team CO Carbon Monoxide COD Commercial Operations Date DGM Deputy General Manager DOE Department of Environment DOEXP Department of Explosives EHS Environment, Health and Safety EHS&S Environmental, Health, Safety and Social EPC Engineering, Procurement and Construction ERM Environmental Resources Management ESAP Environmental and Social Action Plan ESIA Environmental and Social Impact Assessment ESMMP Environmental and Social Management and
Monitoring Plan FNTP Full Notice to Proceed GIIP Good International Industry Practices GLC Ground Level Concentration GOB Government of Bangladesh GRM Grievance Redress Mechanism GSA Gas Supply Agreement GT Gas Turbine HIRA Hazard Identification and Risk Assessment HIRAC Hazard and Risk Assessment and Control HR Human Resources HRSG Heat Recovery Steam Generator HSD High Speed Diesel IA Implementation Agreement IFC International Finance Corporation IsDB Islamic Development Bank ISO International Organisation for Standardisation JCCR Joint Committee for Community Relation JGTDSL Jalalabad Gas Transmission and Distribution System
Limited JHA Job Hazard Analysis L&FS Life and Fire Safety LLA Land Lease Agreement LPG Liquid Petroleum Gas LRP Livelihood Restoration Plan MoM Minutes of Meeting MSDS Material Safety Data Sheet
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
III
NEPC First Northeast Electrical Power Engineering Co NEPC-S Northeast Electric Power Engineering & Services
Company NGO Non-Governmental Organisation NOx Oxides of Nitrogen OHSAS Occupational Health and Safety Management System OJT On-Job Training PAF Project Affected Family PGCB Power Grid Company of Bangladesh PM Particulate Matter PAH Project Affected Household PAP Project Affected Person PPA Power Purchase Agreement PPE Personal Protective Equipment RAP Resettlement Action Plan RFP Request for Proposal RMP Rural Medical Practitioner SBIIPCL Summit Bibiyana II Power Company Limited SIA Social Impact Assessment SIMCPL Summit Industrial and Mercantile Corporation (Pvt.)
Ltd SO2 Sulphur Dioxide SOP Standard Operating Procedure ST Steam Turbine TBT Tool Box Talk TK Bangladeshi Taka TNA Training Need Assessment WB World Bank WHO World Health Organisation
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
IV
Executive Summary ERM has been involved by by Summit Bibiyana II Power Company Limited
(SBIIPCL) in performing Environmental, Health, Safety and Social (EHSS)
Compliance Assessment of its 341MW natural gas fired combined cycle power
plant (CCPP) located at Parkul Village in Aushkandi Union under Nabiganj
Upazilla of Habiganj District, Bangladesh. The compliance assessment
framework includes guidelines prescribed by IFC & ADB including applicable
national and local EHSS regulations. The current assessment covers for the
period October 2015 to February 2016 with site visit undertaken by the ERM
team during 25th - 28th February 2016.
The EPC Contractor has recently completed the necessary construction works
regarding operation of combined cycle power generation – only minor
accessory construction related activities are now being done. Single cycle
operation of the power plant commenced from 6th June 2015 with COD for
combined cycle operations being declared on 28th December 2015. For
operations SBIIPCL has engaged China Northeast Electric Power Engineering
and Services Co. Ltd (NEPC-S) as the Operations and Maintenance (O&M)
Contractor. However, EPC Contractor will still be responsible for all sorts of
construction, maintenance and operation of the power plant. O&M Contractor
will commence with their activities following handing over the project to them
by the EPC Contractor. After handing over, EPC Contractor will remain in the
plant for two more years as part of construction guarantee/warranty with
limited staff/personnel.
With respect to EHSS regulatory permitting the project is found to be in
compliance for both construction and operations except for the permit
required for diesel storage near the fire pump room. The construction phase
stands to be completed in December 2015 following declaration of COD for
combined cycle operations in 28th December 2015. SBIIPCL is assessed to have
demonstrated satisfactory compliance to the construction phase ESAP and
ESMMP commitments. However, SBIIPCL to continue with their efforts to
comply with some of the commitment for this phase particularly related river
bank erosion monitoring, maintenance of traffic safety signages’s and avifauna surveys.
For operations, both SBIIPCL and NEPC-S were found to be on track towards
managing the HSSE aspects applicable for this phase. To this regard necessary
policies and EHS procedures have been developed and is currently under
implementation. However efforts need to be made by NEPC-S to update the
Waste Management Procedure, Chemical Handling Procedure, and
Emergency Response Procedure in consistent with the national regulations
and lending agency guidelines. Further, SBIIPCL along with NEPC-S is
required to perform a quantitative risk assessment study of the project
operational risks. This in turn needs to be communicated along with response
actions to the nearby communities who are likely to be affected, to enhance
emergency preparedness. Assessment of project fire safety risks and
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
V
preparedness is also pending and need to be undertaken on a fast track to
meet the ESAP timeline.
SBIIPCL along with NEPC-S to continue with their efforts towards
demonstrating compliance to legal commitments particularly with respect to
periodic examination of lifting equipment’s and pressure vessels; provision of secondary containment for designated hazardous waste storage area; first
aider certification; firefighting training and equipping first aid
room/dispensary with adequate resources.
The compliance status and/or overall progress related operation stage
findings will be assessed and verified by ERM during next independent
monitoring due in next 6 months i.e. in August 2016.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
1
1 INTRODUCTION
1.1 BACKGROUND
Environmental Resources Management (ERM) was commissioned by Summit
Bibiyana II Power Company Limited (SBIIPCL) in order to conduct
independent monitoring/auditing of the Project (341MW natural gas fired
combined cycle power plant (CCPP)), on behalf of the lenders, which include
Asian Development Bank (ADB), International Finance Corporation (IFC) and
Islamic Development Bank (IsDB) (the “Lenders”), after it was agreed by the
Lenders and Borrower (SBIIPCL) to engage ERM in the role of Financiers'
Environmental and Social Adviser for the purpose of the Borrower’s Compliance with Lenders’ Environmental and Social Requirements, and to respond
to environmental and social concerns that the Lenders may have from time to
time.
ERM was commissioned on 17th September 2014 for independent
Environmental, Health, Safety and Social (EHS&S) Compliance Audit as an
internal audit requirement. The first audit by ERM was conducted in the last
week of September 2014 and final report of audit was submitted on 3rd
November 2014. After the first EHS&S compliance audit, based on the
discussions with prospective lenders, SBIIPCL had engaged Bangladesh
Centre for Advance Studies (BCAS) as Borrower’s monitoring auditor/consultant for the compliance monitoring, considering that the same
agency was involved during the Environmental and Social Impact Assessment
(ESIA) of the Project. In order to conduct independent monitoring/auditing
on behalf of the lenders, it was agreed by the Lenders and Borrower to engage
ERM to quarterly compliance audits.
The Project is a 341MW natural gas fired combined cycle power plant (CCPP)
having one Gas Turbine (GT), one Heat Recovery Steam Generator (HRSG)
and one Steam Turbine (ST). The Project is located at Parkul Village in
Aushkandi Union under Nabiganj Upazilla of Habiganj District, Bangladesh.
The audit was to primarily assess the compliance status of the project with
respect to the EHS&S Corrective Action Plan (CAP) developed as part of the
Independent EHS&S Compliance Audit reporting submitted by ERM on 3rd
November 2014, IFC’s Environmental & Social Action Plan (ESAP) as well as to
verify the internal EHS&S, Labour and Social audit verification being
conducted by BCAS in February 2016.
A total of 3 audits have been undertaken till date since September 2014, with
this being the fourth in the series. The present audit was undertaken from 8th-
10th September 2015 was to primarily assess the compliance status of the
project with respect to IFC ESAP and EHSS CAP as mentioned above.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
2
1.2 OBJECTIVES AND SCOPE OF WORK
The primary objective of this assignment was to assess the compliance status
of the Project and its various components with respect to the agreed CAP
between borrowers and lenders, IFC ESAP, Construction & Operations Phase
Environmental & Social Management & Monitoring Plan (ESMMP) of the EIA,
action plan resulting from labour and social audit by BCAS, applicable legal
requirements and to identify any key EHS&S’s issues (if any) for the Project:
The scope of the compliance audit was as follows:
a) To assess the Project’s compliance with the environment, health, safety and social (EHS&S) requirements of the audit framework (described
subsequently);
b) To review the effectiveness of implementation of mitigation measures and
monitoring programmes at site developed as part of the ESIA study;
c) To review the status of environment management, health and safety,
protection of labour force, during construction and operation phases of the
Project;
d) To review the status of environmental and social action plan (ESAP)
compliance, which came out from the first compliance monitoring during
the construction stage conducted by ERM and social impact assessment
(SIA) conducted by BCAS;
e) To review the status of ESAP as formulated by IFC and agreed by
SBIIPCL;
f) To review the implementation of the resettlement action plan (RAP) and
livelihood restoration plan (LRP) developed for the Project;
g) To review the company’s existing management system, standard operating procedures (SOPs) and training in relation to EHS&S and
identification of areas for improvement/ enhancement;
h) To review the health and safety records of site and compliance with
respect to the site specific safety management system adopted by the EPC
and O&M contractors and by the company; and
i) To provide objective reports to the international lenders confirming
compliance and if not, recommending additional corrective actions, as
appropriate to the Project during construction and operation stages.
It was understood that new issues could have possibly emerged with
commencement of combined cycle operations since 28th December 2015. The
scope includes identifying those issues and assessing how the project is
managing them. The present assignment has tried to capture the operation
and maintenance related issues, as the construction phase is over and the
Provisional Acceptance Certificate (PAC) to the EPC contractor (NEPC) is
likely to be issued in next couple of months and after that the complete plant
operations will be handled by the O&M Contractor (NEPC-S). The objective is
to suitably monitor the performance of NPEC-S during the next scheduled
compliance assessment to be due in 6 months’ time.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
3
1.3 COMPLIANCE ASSESSMENT FRAMEWORK AND EVALUATION CRITERIA
The EHS&S compliance assessment was carried out and evaluated against the
following criteria:
Applicable Local and National environment, occupational safety, health and social legislations;
IFC Performance Standards on Social and Environmental Sustainability (2012);
ADB Safeguard Policy Statement (2009);
IFC/WB Environment, Health and Safety Guidelines – General and for Thermal Power Plants;
Good International Industry Practices (GIIP) including elements of ISO 14001, OHSAS 18001 Occupational Health and Safety Management System;
EHS&S CAP integral to the Independent EHS&S Compliance Audit Report of ERM dated 3rd Nov 2014;
All requirements specified in the Labour Audit report prepared by BCAS dated 25 June 2015;
All requirement specified in the Environmental & Social Monitoring Report and Social Audit report prepared by BCAS dated February 2016;
All requirements and mitigating or monitoring measures specified in the ESMMP of the ESIA report prepared by BCAS dated July 2014; and
All requirements and mitigating or monitoring measures specified in the ESIA as well as RAP and LRP.
1.4 ERM TEAM FOR SITE VISIT
A three member ERM team had conducted the site visit and consultations
between 25th - 28th February 2016. The composition of the ERM team was as
follows:
Naval Chaudhary (Environmental Specialist): Naval is working as
Principal Consultant with ERM India in the Impact Assessment and
Planning (IAP) division. He has master degree in environmental science
and engineering from Indian Institute of Technology, Bombay and more
than 9 years of experience in the field of environmental and social impact
assessment (ESIA), environmental and social due diligence, environmental
auditing, environmental permitting, air quality dispersion modelling,
noise prediction and shadow flicker assessment. His work experience
covers environmental assessment studies for a variety of sectors including
Industry Sector (thermal power plant, fertilisers, pharmaceuticals,
automobiles, oil and gas, hydropower, mining, steel, engineering, etc.);
renewable energy (wind and solar power); Infrastructure Sector (Multi-
Product SEZs, Sector Specific SEZs, Industrial Areas and Estates, and river
bank erosion management); Submarine Cables; & Linear Projects
(Highways, Railways). He has worked in varied geographies, which gives
him a wide international perspective on issues. In last five years he has
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
4
worked in Bangladesh, United Arab Emirates, Liberia, Nigeria and
Pakistan (desk-based).
Subhradeb Pramanik (Health & Safety Specialist): Subhradeb Pramanik
holds a Master Degree in Environmental Science and is presently working
as a Senior Consultant at ERM India in Kolkata office. He has about 9
years of experience in field of EHS audits, due-diligence, site assessment
and environmental impact assessments (EIAs) studies. Over the years he
has played a key role in managing numerous projects in oil & gas, roads,
mining, chemical, manufacturing, power and transmission sector. His
primary focus and experience lies in the development and implementation
of management systems, compliance monitoring, regulator reviews and
EHSS performance audits. Apart from this he has also worked as a key
EHS auditor for both Inogen Group and ARCADIS SENES India to
support the implementation of their Due Diligence and Phase I & 2
programs for nearly 50 projects for key multinational clients in textile,
metallurgical, chemicals and building sector.
Tufail Khan (Social Specialist): Tufail Khan is a Consultant with the
Impact Assessment & Planning Practice Team at ERM India Pvt Limited.
Over his 10 years of experience, Tufail have worked with SENES
Consultants India Pvt (A Canadian Environment Consultancy firm),
THDC India Ltd (A Mini Ratna PSU in Hydro power generation projects)
and currently with ERM India Pvt Ltd at Gurgaon. Carrying out studies
related to Social Impact Assessment and Resettlement & Rehabilitation
have been his core functional areas throughout his total experience.
Construction projects, Hydro power project, Thermal power projects,
Wind power projects, solar power projects, mining projects etc. are the
sectors wherein he has been actively involved and worked. Tufail has also
long experience of implementing Resettlement & Rehabilitation action
plan and working with communities at very grass root level.
1.5 APPROACH TO THE COMPLIANCE ASSESSMENT
The following approach and methodology was adopted for the current
assignment.
Kick-Off Meeting
The site visit began with a kick off meeting with the Project Management &
site EHS&S personnel at Sylhet. The kick off meeting helped in developing
understanding on the current status of the Project implementation and
developments at the site. The ERM team also explained the purpose of the
assignment as well as shared the approach and key activities that were
planned in the course of the audit.
Documents Review
The relevant Project documents pertaining to the EHS and social compliances
were reviewed at the site. This was aimed at understanding the ongoing
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
5
implementation, record maintenance, internal monitoring and reporting and
mandatory regulatory compliances required for the project. Key documents
reviewed include:
a) ESIA Report of the Project (July 2014 – 7th Draft);
b) Environment and Social Monitoring Report prepared by BCAS (February
2015);
c) Environmental, Health, Safety & Social Monitoring Plan (SBIIPCL-EHS-
007) prepared by SBIIPCL;
d) CAP Status and Comments spreadsheet;
e) SBIIPCL Project Legal Register;
f) SBIIPCL EHS and Social Policies for Operations:;
g) Records of online and manual stack emissions monitoring, ambient air
and noise monitoring, surface, ground water and treated effluent sampling
and analysis;
h) Environmental & Social Management & Monitoring (ESSMP) Compliance
Status for Constructions as prepared by BCAS (February 2016);
i) Bird Survey Report dated December 2015;
j) Monthly Environmental Performance Report as submitted by SBIIPCL to
Department of Environment (DoE), Bangladesh for Jan 2016 and Feb 2016;
k) Report on the Monitoring the Fisheries Conditions for the Impact Zone of
SBIIPCL project prepared by Dr. Md. Monirul Islam (February 2016);
l) Copies of EHSS Procedure for Project Operations;
m) Accident & Incident Register;
n) Chemical Inventory Sheet maintained by NEPC;
o) Sample inspection checklists of lifting machines/equipment;
p) Sample set of Work Permits;
q) Sample set of Safety Training Records;
r) Sample set of Weekly EHS Inspections;
s) Annual EHS Training Calendar;
t) Sample copies of HSE meetings;
u) Sample copies of Monthly Reports for Operations;
v) NPEC-S Health Certificate Register;
w) Renewed license copies of factory, Carbon dioxide, Diesel and Hydrogen
storage;
x) Mock drill reports dated 11 February 2016 and 21 December 2015;
y) Social Monitoring Report by BCAS (February 2016);
z) Current status of implementation of livelihood restoration programme
shared by SBIIPCL;
aa) Stakeholder Engagement Plan;
bb) Socio-Economic Impact Assessment, Resettlement Action Plan and
Livelihood Restoration Framework Document, prepared for BCAS for IFC;
cc) HR Manual of the M/s. NEPCS (the Chinese contractor engaged for O&M
of the plant);
dd) Personal files, salary sheets of the employees and contract workers of M/s.
NEPCS;
ee) Legal Register, Human Resources (HR) Policy and Procedures of Summit
Group;
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
6
ff) Hazard Identification and Risk Assessment (HIRA) analysis
gg) Grievance Management Process and Records
Site Visits and Physical Verification
The EPC Contractor has recently completed the necessary construction works
regarding operation of combined cycle power generation – only minor
accessory construction related activities are now being done. Single cycle
operation of the power plant commenced from 6th June 2015 with COD for
combined cycle operations being declared on 28th December 2015. For
operations SBIIPCL has engaged China Northeast Electric Power Engineering
and Services Co. Ltd (NEPC-S) as the Operations and Maintenance (O&M)
Contractor.
The ERM team accompanied by the representatives of the project team
undertook site visits of the key project components to assess the status and
compliance with respect to EHS and social/labour issues and legal
obligations. During the site visit, the team made physical and visual
inspection/verification of the minor construction activities and on site
management of EHS and labour issues related to operations. This was
followed by visits to the operation areas and the consultations with the project
affected communities. The different activities undertaken during the course of
site visits included:
1. Discussions and Interviews: The team conducted detailed discussions
and interviews with the site personnel, contractor representatives, and the
operations workers to understand the on-site management of EHS issues,
compliance to labour laws, working conditions and facilities available at
site to these workers and satisfaction levels (of the workers and
contractors) or any issues/concerns at the site. Discussions were also
undertaken with the relevant personnel of the O&M contractor (China
Northeast Electric Power Engineering & Service Co. Ltd. or NEPC-S) and
sub-contractors employed to understand and assess the environmental,
health and safety and labour compliance and its management at the site.
2. Detailed Discussion with the communities and Community
Development Officer (CDO) of SBIIPCL: The ERM team had discussions
with the PAPs who were imparted LRP trainings, the NGO (IDEA) hired
for implementation of LRP and other local community members. The
discussions included the following:
a) Perception of the project affected families (PAFs) on the
implementation of LRP programme, seed money distribution,
compensation package, rehabilitation measures, other welfare
initiatives and issues surrounding them, if any;
b) Any legacy issues or open issues surrounding land acquisition,
resettlement etc.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
7
c) Community engagement activities by the CDO and perception of the
locals on these engagement interventions;
d) Progress on livelihood restoration related intervention carried out by
the project and CDO for the project affected families;
e) Understanding vulnerability of the project affected persons;
Close Out Meeting
A close out meeting was held on 28th February 2016 with the Senior
Management Team at SBIIPCL Corporate office in Dhaka. ERM briefed the
Senior Management with the key observations and findings based on the site
visit, discussions with the site personnel and contractors and review of the
relevant documents and sought their responses to the observations/findings.
The CAP and ESAP compliance status, identified gaps and actions required to
close the gaps identified were also discussed during this meeting with the
Senior Management. Some of the newly identified issues, associated with
project operations were also briefed during the closing meeting.
Reporting
Information from various sources and direct observations made by ERM have
been collated and compared against the reference framework.
1.6 LIMITATION
The report is based on information provided to ERM before, during the site
visit and post the site visit. The findings and observations made herein are
based on application of professional judgement. The findings should be
viewed in the context of the applicable scope and objectives of the study and
the limitation on time and resources made available to the consultants for the
successful completion of the study. The Compliance Assessment was based on
readily available information/ documentation, visual reconnaissance, and
management interviews in course of site visit. Kindly also note that the scope
of work did not include any sampling, analysis of environmental media,
collection of primary data, engineering design or development of technical
specifications or cost estimates among others.
ERM is not engaged in consulting or reporting for the purpose of advertising,
sales promotion, or endorsement of any client interests, including raising
investment capital, recommending investment decisions, or other publicity
purposes. Client acknowledges this report has been prepared for their and
their clients’ exclusive use and agrees that ERM reports or correspondence
will not be used or reproduced in full or in part for such purposes, and may
not be used or relied upon in any prospectus or offering circular. Client also
agrees that none of its advertising, sales promotion, or other publicity matter
containing information obtained from this assessment and report will mention
or imply the name of ERM.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
8
Nothing contained in this report shall be construed as a warranty or
affirmation by ERM that the site and property described in the report are
suitable collateral for any loan or that acquisition of such property by any
lender through foreclosure proceedings or otherwise will not expose the
lender to potential environmental or social liability.
1.7 LAYOUT OF THIS REPORT
The report has been prepared in the following layout:
Section 1: (this section) provides a background of the assignment,
objectives and scope of work, approach and methodology
along with limitation of the review and report.
Section 2: Project Appreciation and Current Status of the Project
Section 3: Summary of Key Observations
Section 4: Compliance Status of the CAP & ESMMP and IFC ESAP
Section 5: EHS&S Regulatory Compliance Assessment
Section 6: Social Audit Compliance Status
Annex A Photo Documentation
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
9
2 PROJECT APPRECIATION AND CURRENT STATUS OF THE PROJECT
2.1 THE PROJECT
The project of 341 MW gas-fired Combined Cycle Power Station, is being
developed by Summit Bibiyana II Power Company Limited (SBIIPCL) by
installing one Gas Turbine (GT), one Heat Recovery Steam Generator (HRSG)
and one Steam Turbine (ST). Gas supply for the Project will be from Bibiyana
Gas Field and will be supplied by the Gas Supplier (i.e. JGTDSL). Power
generated by the Project will be evacuated through an existing 230 kV
transmission line of the PGCB.
A Request for Proposal (RFP) was issued by Power Cell (the Power
Division of the GoB Ministry of Power, Energy and Mineral Resources) on
3rd May 2010 (and subsequently amended on 2nd September 2010) for a
sponsor to develop a 330-450 MW Combined Cycle Gas Technology
(CCGT) power station at Bibiyana on a ‘build, own and operate’ basis. The RFP was signed by SBIIPCL on 6th September 2010 and in May 2011
SBIIPCL signed:
o Implementation Agreements (IAs)with the GoB and the Power Grid
Company of Bangladesh (PGCB);
o Power Purchase Agreements (PPAs) with the BPDB;
o Land Lease Agreements (LLAs) with the BPDB; and Gas Supply
Agreements (GSAs) with the Jalalabad Gas Transmission and
Distribution System Limited (JGTDSL).
In addition, an Engineering, Procurement and Construction (EPC) contract
was signed by SBIIPCL with a joint venture comprising the First Northeast
Electrical Power Engineering Co. and Northeast China International
Electric Power Corporation (herein referred to as ‘the EPC Contractor’) on 14th November 2012 and full notice to proceed (FNTP) was given on 25th
January 2013.
2.2 PROJECT DEVELOPER
The project developer for the Bibiyana II Gas Power Project is Summit
Bibiyana II Power Company Limited (SBIIPCL), which was incorporated in
Bangladesh on 21st December 2010, as a joint venture of Summit Corporation
Limited (SCL), which was formerly known as Summit Industrial and
Mercantile Corporation (Pvt.) Ltd.) and GE Energy LLC, a wholly owned
subsidiary of General Electric Company. SCL is part of the Summit Group, an
established financial entity and is experienced in the efficient management,
operation and maintenance of similar facilities in Bangladesh. Summit Group
is one of the largest Bangladeshi conglomerates and the industries under this
conglomerate include communication, trading, energy, power and shipping.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
10
2.3 CURRENT PROJECT STATUS
2.3.1 Main Project component
The current status of the project can be summarized as follows:
The single cycle operation of the power plant commenced from 6th June
2015.
Since 28th December 2015, combined cycle COD was achieved.
In the meantime, SBIIPCL hired China Northeast Electric Power
Engineering and Services Co. Ltd (NEPC-S) as the Operations and
Maintenance (O&M) Contractor. O&M Contractor will start activities after
handing over the responsibilities to them by the EPC Contractor.
EPC Contractor is still responsible for completion of any pending work
under the EPC contract as well as to operate the plant for two more years
as part of construction guarantee/warranty with limited staffs.
Table 2.1 below depicts important dates and timelines for SBIIPCL Project:
Table 2.1: Key Timelines – SBIIPCL Project
S. No. Particular Date
1 Date of signing Implementation Agreement (IA) 12th May 2011
2 Date of signing Power Purchase Agreement (PPA) 12th May 2011
3 Date of signing Gas Supply Agreement (GSA) 12th May 2011
4 Date of Signing Land Lease Agreement (LLA) 12th May 2011
5 Contract effective date 12th May 2011
6 Implementation period as per contract 31 Mar 2013 - 31 Dec 2015
7 Required Simple Cycle Operation Date (RSCOD) 31 Dec 2014
8 Simple Cycle Operation Date 06 June 2015
9 Date of Financial Closure 08 July 2015
10 Required Commercial Operation Date 31 Dec 2015
11 Combined Cycle COD 28 Dec 2015
Source: SBIIPCL
2.3.2 Associated project facilities
Regarding work progress on the project associated facilities (not being
constructed or financed by SBIIPCL) viz. gas pipeline, switchyard, access road,
transmission line etc. an update has been provided in Table 2.2 for reference.
However, as clearly specified by the Borrower, the construction as well as
operation and maintenance of these components rests with other parties (i.e.
government entities).
Table 2.2 Project Associated Facilities – Status
S. No Facility* Area (acres) Responsibility Status (Work Completed)
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
11
S. No Facility* Area (acres) Responsibility Status (Work Completed)
1 Switchyard 26.0 PGCB 07 March 2015
2 Site Access Road 2.0 BPDB 29 November 2014
3 Gas Pipeline 8.5 JGTDSL 12 April 2015
4 Construction Laydown
Area
14.0 BPDB/SBIIPCL August 2013
5 Transmission Line 70 meters to
switchyard
PGCB 28 February 2015
*Components not under financing by Lenders
Source: SBIIPCL and BCAS
The details of the project operational status and EHS performance for January
2016 have been presented in Table 2.3 and 2.4 respectively.
Table 2.3 Operational Performance – January 2016
S. No. Particular Month to Date Year to date
1 Gross Generation, (MWH) 151060.19 151060.19
2 Auxiliary Consumption (MWH) 5127.803 5127.803
3 Total Export, (MWH) 146407.6 146407.6
4 Total Import, (MWH) 475.167 475.167
5 Natural Gas Consumption (As per GT’s RMS meter) (MSCF)
985292536 985292536
6 Availability (%) 73.48 73.48
7 Equivalent Forced Outage Factor (EFOF) (%) 4.858 4.858
8 Capacity Factor (%) 61.53 61.53
9 DM production (m3) 4659 4659
10 Clarified water production (m3) 152438 152438
Source: NEPC-S Monthly Report for January 2016
Table 2.4: EHS Performance – January 2016
S. No. Particular Month to Date Year to date
A Environment
1 Quantity of NOx Emission (kg) 425.78 425.78
2 Quantity of CO Emission (kg) 861.35 861.35
3 Quantity of effluent (m3) 5461 5461
4 Quantity of sludge (m3) 0 0
5 Quantity of Oily waste (liters) 0 0
7 Generation of medical waste (kg) 2 2
B Health & Safety
1 Fatality 0 0
2 Lost Time Accident 0 0
3 First Aid Cases 0 0
4 Near Miss 0 0
Source: NEPC-S Monthly Report for January 2016
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
12
3 SUMMARY OF KEY OBSERVATIONS
The COD for combined cycle operations declared as on December 2015, efforts
have been made by the ERM audit team to assess project EHSS performance
for operations stage and also to verify compliance status of any pending EHSS
related actions from construction stage. The EHSS observations/findings
made in this regard have been summarized in the subsequent sections below.
3.1 ENVIRONMENTAL, HEALTH & SAFETY
The observations made by the ERM audit team with respect to the project
environmental, health and safety aspects as outlined in the CAP, ESMMP,
ESAP and applicable local and national regulations have been tabulated under
the various sub-sections below.
3.1.1 Legal Register
The Environmental, Health, Safety and Social Compliance Audit Report
prepared by ERM dated November 2014 suggested development of a legal
register for both construction and operations phases. SBIIPCL has prepared a
legal register for ensuring timely approval or renewal of all legal compliances
of the project with respect to both construction and operations. Table 3.1
below provides status of the various permits/licenses as applicable for
construction and operational phase of SBIIPCL.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
13
Table 3.1 EHS License/Permit Compliance Status for Construction & Operations Phase
S. No. Permit/License Issuing Authority Issue date Valid until Status
1 Trade License Aushkandi Union Parishad 1st July’15 30th June’16 In compliance
2 License for use of river water/
foreshore/jetty
Bangladesh Inland Water
Transport Authority (BIWTA)
7th Oct’15 28th Aug’16 In compliance
3 Site Clearance Certificate Department of Environment
(DOE)
25th Jun’14 28th May’15 No renewal required as the project has
already obtained Environmental Clearance
(EC) certificate from Department of
Environment (DoE), Bangladesh.
4 Environment Clearance
Certificate
Department of Environment
(DOE)
17th June’15 16th June’16 In compliance
5 Permission for acid and alkali
storage
Department of Explosives
(DOEXP)
9th June’15 30th Jun’16 In Compliance
6 Fire Permit Fire Service and Civil Defence 8th June’15 30th June’16 In compliance.
7 License for storage of Carbon
Dioxide
Department of Explosives
(DOEXP) 18th June’15 31st Dec’17 In compliance
8 License for Diesel Storage
(4KL capacity)
Department of Explosives
(DOEXP) 18th June’15 31st Dec’17 In compliance
9 License for Diesel Storage
(1.36 KL capacity)
Department of Explosives
(DOEXP)
- - SBIIPCL is yet to obtain license for the
additional diesel storage of 1.36 KL near the
fire pump house.
10 License for generation of
Hydrogen and storage of
Hydrogen inside plant
Department of Explosives
(DOEXP) 18th June’15 31st Dec’17 In compliance
11 License for installation of
High pressure Gas pipeline
inside power plant
Department of Explosives
(DOEXP) 13th May’15 Entire project life
cycle
In compliance
12 License of Boiler (IP, HP & LP
Drum & Auxiliary Boiler )
Office of the Chief Inspector of
Boilers (CIB)
14th June’15 13th June’16 In compliance.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
14
S. No. Permit/License Issuing Authority Issue date Valid until Status
13 Permission for Stack Erection Bangladesh Air Traffic Services
(BATS)
16th Jun’14 Entire project life
cycle
In compliance.
14 License for Power Generation Bangladesh Energy Regulatory
Commission (BERC)
29th June’15 28th June’16 Provisional license obtained for generation
of 349 MW power (gross) [GT 228 MW & ST
121 MW] in combined cycle mode.
15 Factories License Deputy Chief Inspector of
Factories
21st July’15 30th June’17 In compliance.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
3.1.2 Environment Linked Observations
Some of the key observations linked to the Environmental performance of the
project are mentioned below:
A legal register for the project has been prepared by SBIIPCL covering
both construction and operational EHSS requirements.
o However updation of the legal register or a separate tracking
mechanism to include the conditions specified in the relevant
permits/license and applicable regulations are still pending.
o It is considered to be important, with the project now in operational
stage and requirement of effectively tracking and complying with the
legal requirements for this phase.
A two day bird survey has been undertaken by SBIIPCL in December 2015
by engaging a third party expert. The study focused on five Beels (water
bodies) within the project study area with a total of 43 species being
recorded.
o The study report does not indicate any change/disruption of
migratory bird movement or habitat due to the project;
o The report further recommends that an annual monitoring is
undertaken to comprehensively assess the potential impact on
migratory bird habitat, if any throughout the lifecycle of the project.
o The subsequent surveys to be undertaken to be focusing on the
transmission line stretch (~70m) and outcome utilised for development
of an Avifauna Management Plan, if required, based on the assessment
of any impact on the avifauna due to the transmission lines.
ESMMP – Operations Phase prepared as part of the ESIA study has been
shared with NEPC-S.
o The periodic compliance monitoring/verification of ESMMP
implementation yet to be initiated by SBIIPCL.
SBIIPCL has installed and is operating a Continuous Emission Monitoring
System (CEMS) to continuously monitor pollutant (CO, NOx, PM10, SO2)
concentration in flue gas emissions.
o The results were found to be in compliance with emissions standards
(well within the limits) as specified in the IFC EHS Guidelines for
Thermal Power Plants and Bangladesh ECR, 1997. However in most
cases the pollutant concentration were not found to be expressed in
units referred in the aforesaid standards. Same was communicated to
the CEMS in-charge and corrective action been taken.
No provision of CO2 emission monitoring is available in CEMS and hence
actual CO2 emission monitoring and annual reporting is not possible. This
was discussed during the closing meeting and the SBIIPCL management
had mentioned that GHG emissions will not be monitored but calculated
and based on the fuel consumption and plant performance.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
SBIIPCL has installed 3 continuous ambient air quality monitoring stations
(CAAQMS), which are installed on the top of dormitory, cooling water
pump house and cooling tower.
o The system is operational since December 2015. Review of the
monitoring results indicated that the SO2 concentrations are observed
in the range of 40 to 80 µg/m3 and PM2.5 levels are higher than PM10
levels in all the locations, which are not matching with the testing done
during the calibration period. Furthermore the levels of SO2 during the
conventional monitoring were in the range of 10 – 18 µg/m3. Re-
calibration of the CAAQMS is required.
With project in operation from December 2015 ambient air and noise
quality monitoring at the village locations were found to be pending. As
per the Operations ESMMP such monitoring is required to be undertaken
within three months of combined cycle of operations. In house monitoring
of noise is undertaken by NEPC-S at 8 locations within the project
premises and the results found to be in compliance with the Bangladesh
ECR, 1997 standards.
For treated effluent, in-house monitoring by NEPC-S is done for pH,
conductivity and temperature prior to its discharge into the Khusiyara
River. The results were found to be in conformance to the Bangladesh
ECR, 1997 discharge standards; however analysis of other key parameter
viz. BOD, TSS, TDS and Oil & Grease were not being performed due to
limitations with respect to the availability of appropriate analytical
equipment at the NEPC-S project laboratory at this stage. Quarterly
monitoring of treated effluent is also being done by engaging a third party
laboratory; however it does not encompass all parameters as outlined in
the Inland Water Discharge Standard of Bangladesh ECR, 1997. It was
further confirmed by the Summit Management that all other parameters
will be covered through third party monitoring.
SBIIPCL has not made any provision of installation of oil water separators
for storm water drainage system. This is assessed to be justified based on
the fact that the project hazardous material and waste storages are covered
with any waste/chemical spillages being channelized through a dedicated
underground drainage system to a waste water collection basin for
subsequent treatment.
For operations SBIIPCL has developed a Waste Management Procedure
for both hazardous and non-hazardous waste streams to be generated
during operations.
o Review indicates the procedure to be generic in nature and lacking
specific requirements with respect to storage, handling and disposal of
specific waste categories/streams.
o Also NEPC-S is supposed to commence with maintenance of a waste
inventory and deployment of authorized waste contractor for disposal
of hazardous waste streams to facilitate effective implementation of the
procedure. However, visit to the hazardous waste storage area, on the
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
back-side of cooling towers is not fulfilling this requirement. The
hazardous waste storage area is on top of the storm water drainage
network and there is no secondary containment for capturing any
spillage from this area. Currently there are a number of openings
provided in this area, and any spillage from this area can directly reach
to the storm water drainage and can directly reach to the River.
SBIIPCL has developed a hazardous materials handling procedure
(Caustic and Acid Handling Procedure) for operations, however it is
limited to only acids and alkali storages and does not cover other
chemicals like hydrazine, ammonia, etc. being used for operations.
During visit to the acid and alkali storage area it was observed that display
related to warning signages and usage of appropriate PPEs were found to
be lacking. Further there exists no provision for spill kits at the aforesaid
storage area to control any accidental spillage during loading of the acid
and alkali tanks. Periodic inspection of chemical emergency response
equipment like eye wash station and showers were also found to be
lacking.
Regarding disposal of hazardous waste particularly used/waste oil NEPC-
S is in discussion with Lafarge Cement facility at Chatak with a waste
disposal agreement/contract yet to be signed. Further no plans is
presently available to manage disposal of other notifiable hazardous waste
streams viz. ETP sludge, discarded chemical containers etc.
For operations NEPC-S has deployed only two vehicles for which valid
certificate of fitness is available from Bangladesh Road Transport
Authority (BRTA) as required per the relevant provision of Bangladesh
Environmental Conservation Rules, 1997 and Motor Vehicle Ordinance,
1983.
An aquatic survey has been conducted by SBIIPCL by engaging a third
party expert in November 2015 to assess the limnological and fisheries
conditions for the impact zone of project. A total of 34 species of fishes
have been recorded from the study site during both peak and lean season
fishing which is comparable to the baseline.
Green belt development for the project site is still under progress and need
to be finalised on a fast track basis for execution based on available areas
for plantation. With respect to green belt development outside the project
boundary, survival rate of the planted saplings is found to be affected.
This is assessed due to lack of proper upkeep and maintenance with
contract of Zara Enterprise (the green belt maintenance) being expired on
October 2015.
3.1.3 Health & Safety Linked Observations
Some of the key observations on the health and safety aspects are as follows:
As recommended in the ERM Audit report dated 19 November 2015 the
inclusion of Lock Out Tag Out (LOTO) checklist and PPE requirement is
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
still found to be absent in the work tickets being issued for electrical work.
This is important as NEPC is temporarily involved in project operations
till it is being handed over by SBIIPCL to the Operations & Maintenance
(O&M) contractor i.e. NEPC-S.
Reportedly the facility operates lifting equipment’s in the form of gantry cranes and overhead cranes for which NEPC is maintaining the inventory;
however, it does not cover all the lifting machineries/ equipment.
Furthermore, the aforesaid equipment has not been subjected to thorough
examination by a competent person and a register of such examination
maintained in prescribed format as required under relevant provision of
Bangladesh Labour Law, 2006. With respect to operations NEPC-S has already developed a training
calendar for 2016 encompassing the following components:
o Power Plant Safety Rules and Permit to Work;
o EHS Policy and Procedures;
o Site Risk Assessment and Prevention Spill;
o Fire Equipment Facility and Fire Emergency Response;
o Heavy Equipment Operation Safety;
o Basic Electrical Safety;
o Hot Work Training and Authorization;
o Lifting Operation & Work at Height
o Confined Space Work Safety
o Safety Awareness;
o Oil and Chemical Spillage Prevention;
o Hazardous Material and Waste Management Training;
o First Aid;
o PPE and Safety Equipment Use Training;
o Chemical and Flammable Material Handling; and
o Compressed Gas Cylinder Safety
As per the aforesaid calendar training on Power Plant Safety Rules; Permit
to Work and EHS Policies & Procedures were scheduled for January 2016.
However implementation of the said training programs is still found to be
pending.
SBIIPCL has prepared an Emergency Response Procedure (SBIIPCL-EHS-004)
for operations and shared the same with NEPC-S for implementation. The
procedure has identified response measures for the following emergencies
– fire and explosion, medical cases, earthquakes, bomb threat and severe
weather phenomenon. However review of the procedure indicates the
following key gaps/deficiencies:
o Roles and responsibilities of the Emergency Response Team (ERT) has
not been defined;
o Emergencies has not been classified according to the risk significance
including response flow for controlling each emergency type;
o Interfacing with offsite emergency responders lacking;
o Contact details of both onsite and offsite emergency responders have
not been incorporated in the procedure; and
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
o Details of resources available for emergency response and control;
o Requirements related to worker training; induction of new workers
and visitors not covered; and
o Disclosure of the potential emergencies from project operations
including control measures with the surrounding communities has not
been covered in the said procedure.
SBIIPCL along with NEPC-S need to update the Emergency Response
Procedure for operations to include the components related to emergency
classification; defining ERT roles and responsibilities; resource availability;
interfacing with offsite emergency responders; contact details of
emergency responders; induction for workers/visitors; training on
emergency response and community disclosure of potential
emergencies/risks.
SBIIPCL has identified the cooling tower, boiler area and central control
building as the area of concerns (AOCs); however preparation and
implementation of a safety action plan for the aforesaid AOCs is still
under progress. With project under operation from December 2015 the
SBIIPCL to ensure completion of the safety action plan for cooling tower,
boiler area and central control building on a fast track basis.
NEPC-S has commenced with monthly site safety inspection from
December 2015 with findings documented in a specific format. However
this report is not being shared with SBIIPCL.
Induction training to visitor and operations workforce has not been
undertaken by NEPC-S as required under the ESMMP. This is important
given the combined cycle operations have already commenced from
December 2015. It is reported that till now this is being done by SBIIPCL.
For project operations, NEPC-S – the O&M contractor has already
developed a set of about 45 management procedures and standards
including Site EHS Plan for the year 2016. This has been released by
NEPC-S for implementation vide letter dated 6 February 2016. However
NEPC-S is yet to develop a consolidated EHS plan for operations
encompassing EHS policy, objectives, procedures, training requirements,
performance indicators etc. to demonstrate compliance to the ESMMP
requirements.
In line with ESMMP requirements an EHS Committee has been formed
comprising representatives of both SBIIPCL and NEPC-S. The Committee
meeting is scheduled on a monthly basis and is being chaired by the
SBIIPCL Plant Manager.
Emergency mock drills are being periodically conducted by SBIIPCL in
coordination with NEPC-S; however drill records do not reveal full
participation of all the operations workers and personnel.
Review of health register of O&M staff indicates that initial medical
examination is limited to only 72 personnel as compared to the total
operational workforce comprising of 96 personnel.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
SBIIPCL has not initiated the Quantitative Risk Assessment (QRA) study
to assess and evaluate the operational risks/hazards associated with the
project, which was agreed to be completed within 3 months of the COD.
This is identified to be important taking into account the plant has
commenced operations in December 2015 and also given the output of the
study is to be utilised to formulate an Emergency Response Plan (ERP).
SBIIPCL has already engaged Life and Fire Safety Expert from NEPC-S in
September 2015 for assessing the fire safety preparedness and
subsequently develop a Corrective Action Plan (CAP) to address any
gaps/deficiencies. However based on discussion with NEPC-S it is
understood that fire safety review of the project is likely to commence by
end of March 2016. With COD for combined cycle already declared on Dec
2015 the assessment of project fire safety risks and preparedness need to be
undertaken by the Life and Fire Safety Expert on a fast track basis to meet the
suggested timeline. This is to be followed by preparation of a CAP in consistent
with the WB General EHS Guidelines.
3.1.4 EHS Regulatory Compliance Status
Environmental Performance Report (EPR) has been prepared and
submitted to DoE on 3 Feb 2016 and 4 Jan 2016 respectively. However
review of the reports indicates that the EPR though bear the EC conditions
however, the compliance status of the same has not been discussed and
elaborated.
The facility has developed a format for documenting the environmental
monitoring information for operations and the same has been submitted to
DOE Head Quarter in Dhaka and Sylhet Divisional Office on 4 January
2016. Review of the format reveals the following gaps viz. the ambient air
results not expressed in units; error in the PM10 and PM2.5 standards being
referred as part of Bangladesh ECR, 1997 etc.
As per the condition of boiler registration permit, boiler to be operated by
certified boiler operator. Compliance status still need to be assessed based
on availability and review of the certification copy of the personnel
involved in boiler operations at the plant. This matter was discussed
during the closing meeting and Summit has confirmed that no such
permission is required; however, as this is part of the condition imposed in
the permit, a clarification is required to be taken from the authority.
SBIIPCL is yet to establish a Worker Participation Fund and a Workers
Welfare Fund to comply with the provision of Bangladesh Labour Law
and condition specified in the Factories License.
Visual observation did not reveal the presence of any vent pipe or
approved relief valves for the HSD storage tanks to prevent any
generation of pressure from accumulation of dangerous vapour/fumes.
However this needs to be confirmed based on review of the design
document of the tanks.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
As reported the diesel storages at the facility is periodically refilled by
deploying a third party vehicle carrying diesel in bulk. To this regard the
O&M contractor has not verified the availability and validity of the license
issued by Department of Explosives to the vendor for such bulk
transportation of petroleum.
Diesel at the factory is being stored in 3 tanks (2 X 2KL capacity each and 1
X 1.35KL capacity); however the capacity has not been conspicuously
marked on the tankages.
Earthing was not available for the diesel storage tank of capacity 1.36KL
located near the fire pump house.
The facility currently operates five (5) overhead travelling cranes which
are being subjected to periodic internal examination by NEPC. The records
of such examination were found to be maintained in accordance to a
format specified in the project EHS Plan. However prior to putting these
machineries in use for first time in this facility no examination has been
performed by engaging a competent person for specifying the safe
working load. It was reported that all the equipments were commissioned
and checked by OEM, who manufactured this and after one year of
operation these will be due for inspection by competent people.
The facility operates eight (8) hoist and two (2) lifts which have not been
subjected to initial examination by a competent person prior to their first
time in use at the facility. No periodic examination is also being performed
for the aforesaid hoist and lifts as required under Bangladesh Labour Law
provisions. It was reported that all the equipments were commissioned
and checked by OEM, who manufactured this and after one year of
operation these will be due for inspection by competent people.
The first aid boxes at the facility were found to be kept in charge of
certified first aiders from SBIIPCL and EPC contractors. However with
project in operations from December 2015 no workers from the O&M team
has been identified and trained on first aid treatment as required under
the Bangladesh Labour Law provisions.
The facility operates pressure vessels in the form of air compressors,
boilers, hydrogen and carbon dioxide storage tanks. However since there
installation in 2015 these pressure vessels have not been subjected to
examination (both internal and external) including hydraulic testing by a
competent person and records maintained in prescribed format (Form No.
10). Further the metal plate on the air compressors near turbine building
were not found to bear the following information viz. design pressure and
date of first and subsequent hydrostatic testing. This is required under
Rule 6 of the Pressure Vessel Rules, 1995.
For operations a dedicated first aid room is available at the factory which
is being periodically visited by paramedical officer/male nurse in
comparison to qualified medical practitioner required as per Factories
regulation. Also as observed the first aid room is not found to be equipped
with resources as specified in the Factories Rules provisions. However, it
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
was confirmed by the management that there is a local doctor available on
call, who is also providing his services in the company supported
community health centre. There is no provision of a dedicated ambulance
at site; however it was confirmed that a dedicated vehicle will always be
available at site to address any serious case of accident or sickness to the
nearest medical facility.
Insulated rubber mats were not provided near the high/medium voltage
electrical panels at the turbine building, fire pump house and electrical
room of the CCB building to serve for protection against electric shock.
Further display of danger signages on the electrical panels and instruction
for restoration of persons suffering from electrical shock was lacking in the
CCB electrical room.
3.2 SOCIAL OBSERVATION
3.2.1 Manpower engagement
Present strength of workforce employed in SBIIPCL power plant could be classified under three types which include:
SBIIPCL’s own staff deployed at site; Employees and contractual workers engaged by M/s. NEPC – Contractor
hired for construction phase; and
Employees and contractual workers engaged by M/s. NEPCS – Operation & Maintenance Contractor
SBIIPCL Staff
Presently six staffs of SBIIPCL are posted at site that includes Project Head
(General Manager), Community Development Manager (CDM), Assistant
Manager (EHS), Operation Manager, Maintenance Manager and a Site Officer.
Workforce engaged by M/s. NEPC (EPC contractor for construction phase)
Workforce size of M/s. NEPC as on 27th Feb 2016 was reported to be 156. This includes all categories of the employees and workers engaged by M/s. NEPC.
Table 3.2 Breakup of manpower engaged in Plant by M/s. NEPC
S. No Worker category Number in ERM’s 3rd
EHS&S Compliance
Audit (Sept 2105)
Number in ERM’s 4th
EHS&S Compliance
Audit (27th Feb 2016)
1 Chinese staff of NEPC 146 65
2 NEPC contracted staff* 7 30
3 NEPC contracted workers 20 0
4 Labour supplied by M/s. Nation
Trade or Suhag (sub-contractor)
76 22
5 Labour supplied by M/s. Shotota
Enterprise (sub-contractor)
34 15
6 Labour supplied by M/s. Jui
Enterprise (sub-contractor)
32 11
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
S. No Worker category Number in ERM’s 3rd
EHS&S Compliance
Audit (Sept 2105)
Number in ERM’s 4th
EHS&S Compliance
Audit (27th Feb 2016)
7 Labour supplied by M/s. ISS
(security sub-contractor)
18
8 M/s. Raisa 3
9 M/s. Ali Enterprise 12
Total manpower 333 156
Source: NEPC and SBIIPCL site officials
Note: * NEPC contracted staff includes 14 security staff, 5 welder, 7 kitchen staff, 1
Translator, 1Doctor & 2 Driver
Workforce size engaged by NEPC in SBIIPCL plant has further reduced to 156
in ERM’s visit as on 27th Feb 2016. Key activities of construction phase are over
now. At present, plant is fully operational.
Workforce engaged by M/s. NEPCS (Operation & Maintenance Contractor)
Plant has become fully operational now and is being managed by a Chinese
Operation & Maintenance (O&M) contractor, M/s. NEPC. Current strength of
M/s. NEPC as on 27th Feb 2016 was reported to be 93 that consist of 36
Chinese employees and 57 Bangladeshi employees and workers.
3.2.2 Payment of minimum wage and overtime by EPC contractor
Third social monitoring report of BCAS was submitted to SBIIPCL in Feb
2016. In this report, BCAS have presented its findings regarding minimum
wage payment of the contractual workers hired by EPC contractor (M/s.
NEPC) based on review of the salary sheet of the contract workers for the
month of October, November and December 2015. Key observations of BCAS
were;
Minimum wage rate of the construction workers is Tk 375 per day as per
prevailing minimum wage notification issued by Minimum Wage Board of
Government of Bangladesh 2013;
The EPC contractor (M/s, NEPC) have started paying at the rate of Tk 375
per day to the construction workers instead of the earlier rate of Tk 330 per
day;
Mostly construction workers hired by M/s. NEPC, have been engaged
through labour supply contractors;
Service charge of Taka 60 is deducted from daily wage rate of the
construction workers, which is paid to the respective labour suppliers. So,
actual minimum daily wage received by the sub-contracted labourers (i.e.
construction workers) is 315, which is below the minimum wage fixed by
the government.
ERM observed the same status on payment of minimum wage by the EPC
contractor while having discussion with SBIIPCL site management. On
overtime payment issue, it was observed that there is no more requirements
for engaging any worker for extra hours by EPC contractor.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
This issue of minimum wage payment was raised to SBIIPCL corporate
management and their response was;
“In the month of December 2015, total 137 labors were mobilized by EPC contractor. Among them,
110 labors (80.29%) were paid atleast or above the threshold level (375 taka/day) and they were
directly engaged in construction work. The remaining 27 labors (19.71%), who were not attached to
construction works but doing some ancillary works, were paid below 375taka/day. In January 2016, 85 labors were present at the site; only 27 of them (31.76%) received payment atleast or above the threshold level (375 taka/day), and the remaining 58 labors (68.24%) were not paid minimum wage. According to HR dept. of NEPC (the EPC Contractor), up to the time till COD (28 December
2015), work load was more at the construction site. But, since January 2016, there remained
no construction work at site - the labours used to come at the site and staying for eight hours but
not doing much work which caused NEPC to pay payment less than the minimum wages. However,
the overtime does not exist after the construction was over.
Having said above, our conclusion is that we further talk to the EPC Contractor and make them
compensate the concerned labourers with the remaining payment to maintain the
minimum standard wage. In case they don't pay, we will locate the labourers and compensate
them with the due money to maintain the threshold (min. wage rate) and deduct the money from
the payables to EPC Contractor, or we expend the money from our Contingencies”.
Based on above mentioned observations, it could be concluded that the issue
of non-compliance w.r.t payment of minimum wage still persist.
3.2.3 Updated HR policy of SBIIPCL
ERM was shared an updated HR Policy document of SBIIPCL in the 2nd
EHS&S compliance audit visit (April 2015) which was reportedly undergoing
through the internal approval process then. The said policy had included the
additional provisions such as provision of non-tolerance of child labour &
forced labour, non-discrimination policy, anti-sexual harassment policy etc.; as
recommended in the initial EHSS Compliance Audit Report submitted by
ERM in November 2014. However in fourth E&S compliance Monitoring
visit, ERM was apprised that the updated HR policy document as shared in
the 2nd EHS&S compliance audit, has been declared redundant by SBIIPCL
management and it has adopted the HR policy of its parent company i.e.
Summit Industrial Mercantile Corporation (Pvt) Ltd. (SIMCPL) dated 11 June
2015. This matter was discussed during the closing meeting on 13th September 2015
with the Senior Management of SBIIPCL and ERM received an email confirmation
from the CEO of SBIIPCL on 28th September 2015 that the policy document will be
updated within 2 weeks with inclusion of all the above mentioned observations of
ERM.
ERM was apprised in 4th EHS&S compliance audit visit (Feb 2016) that
SBIIPCL has now adopted HR Policy of its parent company i.e. Summit
Industrial Mercantile Corporation (Pvt) Ltd, now called as Summit
Corporation Limited & Subsidiaries (SCL&S). Few additions have been made
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
in this HR policy manual document of SCL&S, based on ERM’s recommendation and this includes:
Policy on Non-employment of Adolescent & Children at Work;
Policy on Anti-harassment and Abuse at Work;
Anti-Discrimination Policy
HR Policy of O&M Contractor NEPCS
M/s. NEPCS has a defined HR policy in place. Key aspects of the policy cover
clarity on terms of employment which is defined in appointment letter of a
new employee, compensation and benefit policy, leave policy, Employee
transition policy, Grievance policy, Employee Training & Development Policy,
HIV/AIDS non-discrimination policy, Child & Forced Labour Prohibition
Policy, Non-discrimination policy, Anti-sexual harassment policy, Employees
Code of Conduct, Overtime Policy etc.
Manpower engaged by NEPCS could be classified into two categories.
The first category is of regular employee that includes their engineers and
other administration staff.
Another category is contract workers that include security guards, driver,
and kitchen staff. Review of appointment letter of these contract workers
indicates lack of clarity w.r.t. their terms of employment such as contract
period is not defined; leave detail is not properly described.
One of the clause in Overtime policy of NEPCS i.e. Clause no: 1.7.1.1 states
that ‘Company must compensate overtime by 1.5 times of the employees normal hourly basic salary for each hour worked’. This clause should be aligned with requirement of Bangladesh Labour law on overtime which
requires overtime hours to be paid @ twice of basic wage rate. Although
overtime payment to contract workers was observed to be aligned and being
paid @ double of basic wage rate.
3.2.4 R&R implementation status
The project required land for establishing power plant and associated facilities
which included construction laydown area, 2 km long access road, switchyard
area and an 8.8 km long gas pipe line.
R&R implementation: ADB’s financed Project Component
ADB’s finance is limited to the Power Plant area. There are 31 Project Affected Households (PAHs) for the 11 acre land
acquired for the power plant establishment. There were total 14 land
owners on 11 acre private land acquired for the power plant
establishment. Besides this, ESIA study for this project had identified 6
sharecroppers and 11 agriculture labourers whose primary source of
livelihood were dependent upon the piece of land acquired for this project.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
Land compensation to 14 landowners has been paid by the concerned
government department. ADB had provisioned for providing one time
compensation of Tk 7,500 to each sharecropper PAH and Tk 8,000 to each
agriculture labour PAH to offset their economic loss. These payment have
been released by SBIIPCL already to all concerned sharecropper and
agriculture labour.
It was also provisioned to give Tk 2 lacs in addition to the land
compensation amount paid by government, to one of the PAH who
became landless after land acquisition for power plant. This amount was
disbursed in two instalments and it was informed that the affected
household invested the additional compensation amount in opening a
new grocery shop and was observed to be successfully running the shop at
present.
R&R implementation under IFC’s Financed Project Component
PAHs of the entire project components (including associated facilities) are
considered for Livelihood Restoration Programme as per Livelihood
Restoration Framework (LRF) of IFC.
SBIIPCL has got Livelihood Restoration Plan (LRP) prepared through an
external consultant and it was finalised after incorporating comments from
IFC. The details of the LRP, status of implementation of LRP and limitations, if
any are covered in Section below.
3.2.5 Livelihood Restoration Plan (LRP)
SBIIPCL has got a LRP study done by third party LRP Consultant. As reported
in ERM’s previous audit report, review of LRP reports indicates the following:
The document provides detail on the process of identifying & finalising
various trades suitable for skill enhancement training for the PAPs (Project
Affected Person); listing of the choice of 396 PAPs for different training
program;
Total 396 project affected persons (PAPs) from 514 PAHs were identified
for LRP;
21 PAHs out of the total PAHs (including PAHs of associated facilities)
didn’t opt for any livelihood training programme because they are economically well off Refer LRP Report prepared by external consultant for
SBIIPCL) for detail of 21 PAHs).
Listing of 14 PAHs & 58 Agriculture Labourers , who could not be traced
during the survey process;
The LRP covered listing of potential NGOs for LRP implementation
including key steps & strategies that are to be followed while
implementing LRP, key milestones of LRP implementation along with
proposed timeline etc.
Detailed review of listing of the PAPs for different training program
indicates that there was some problem in numbering of PAPs and hence 3
names were actually found to be missing. As the numbering was not
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
proper and hence the total number PAPs surveyed in LRP should be 393
instead of 396.
Cultivation over surface area along Gas pipeline route
LRP doesn’t cover the PAHs of Gas pipeline by citing their field observation that mostly landowners have resumed cultivation over the land where gas
pipeline is constructed. Remaining affected land owners will also start
cultivation as soon as water level on the field comes down.
As per SIA report, 168 land owners PAHs & 37 sharecroppers PAHs have
been affected by land acquisition for Gas pipeline.
Land owners PAHs have received compensation for their land loss and
allowing them to cultivate their land in post construction phase of Gas
pipeline will enable them to continue with their livelihood like before.
ERM visited the entire stretch of 8.8 km Gas pipeline route in current audit
period and observed that farmers have resumed cultivation over the
surface area of entire stretch of Gap pipeline route except for one location
(of about 200 to 250 meter long) in Manglapur Village and it was observed
that this portion of land was not properly levelled by the contractor who
was responsible for laying of pipeline and back filling the area. Based on
discussion with two farmers of Manglapur village and SBIIPCL, it was
noted that there were some protest by Manglapur farmers going on and
these farmers were not present at the time of back filling work by the
contractor. Now the concerned farmers of Manglapur village are expecting
this levelling work to be done by SBIIPCL, so that cultivation over this
land parcel could be resumed.
SBIIPCL management’s response to this issue was:
“Cost of levelling 200 m of length is not much of an issue for SUMMIT to undertake
such cost. As is already known, BPDB (Bangladesh Power Development Board) has
constructed the gas pipeline (including re-fill work) under supervision of JGTDSL
(Jalalabad Gas Transmission & Distribution Systems Ltd.) after acquisition of
required land and right-of-way. This is fully in knowledge of the people in and around
the gas pipeline track. The sensitivity here is - once we do such re-fill work in our
name, SBIIPCL will be exposed as an obligor and more people will ask for something
one way or the other. If we do the levelling work, we will have to do it by keeping
BPDB and/or JTDSL at the forefront as if they have done the levelling works before,
not SBIIPCL. So, the plan we have thought of is - we engage in dialog with BPDB and
JGTDSL and do the levelling work ourselves at our cost keeping them at the forefront
in case they are unable to do levelling work themselves (at their cost) for reasons
whatsoever. It can be done by the middle of April 2016, before the monsoon
starts”.
SBIIPCL have thus agreed for levelling work of remaining small portion of 8.8
km Gas Pipeline route in village Manglapur by keeping BPDB and/or JTDSL
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
at the forefront. Progress on implementation of this commitment will be
checked in next audit.
Progress on implementation of LRP training
One local NGO called as IDEA (Institute of Development Affairs) have been
appointed by SBIIPCL for LRP implementation.
13 feasible economic activities were identified in LRP and these includes
poultry and duck rearing, beef fattening, electrical house wiring, welding,
steed rod fabrication, snack food making and cooking, mobile servicing,
computer, business management, goat and sheep rearing,
agriculture/crop, vegetable and short duration fruit cultivation, tailoring
and masonry and house painting.
257 PAHs (Project affected households) have been covered under the
training programme completed so far Table 3.3 provides detail on
different training programmes attended by PAPs.
Table 3.3 Training completion status under LRP as on 15th March 2016
S. No Type of Training Number of
Participants
Training duration
1 Poultry
Batch 1 34 16th Nov 2015 to 25th Nov 2015 (10 days)
Batch 2 31 26th Nov 2015 to 5th Dec 2015 (10 days)
Batch 3 30 9th Dec 2015 to 19th Dec 2015 (10 days)
2 Sewing 7 16th Nov 2015 to 10th Dec 2015 (25 days)
3 Beef Fattening
Batch 1 26 7th Dec 2015 to 20th Dec 2015 (14 days)
Batch 2 30 22nd Dec 2015 to 31st Dec 2015 (10 days)
Batch 3 19 7th Feb 2016 to 17th Feb 2016 (10 days)
4 Agriculture 18 21st Dec 2015 to 31st Dec 2015 (11 days)
5 Computer 8 18th Jan 2016 to 17th Feb 2016( 1 month)
6 Business 25 28th Feb 2016 to 12th March 2016 (14 days)
Source: SBIIPCL site data
ERM had consultations with participants who were imparted livelihood
trainings by IDEA (NGO for LRP implementation). Key observations of the
consultations were as follows:
Maximum number of participants attended training on poultry and beef
fattening. These two activities are quite prevalent in these villages.
Training enabled the participants to manage poultry and beef fattening in
a better way. Participants learned about proper feeding process,
identification of disease and ways of tackling those diseases etc.;
There is no veterinary centre nearby the project area. In this scenario,
capacity building of the participants, especially in terms of identification of
disease and taking necessary action such as way of giving injection and
appropriate medicines etc, raised confidence among the participants for
poultry and beef rearing activity.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
For computer training, majority of the participants were students,
studying in inter college or degree college. One of the participants has his
own computer centre, being used commercially. This computer training
raised his confidence for offering other services in his centre like internet
surfing, data entry etc.;
Total 228 PAPs have been covered under different training programmes.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
30
provides summary of the training imparted by the NGO till Feb 2016.
Plan for remaining LRP training program
LRP training program for the remaining 172 PAPs is scheduled to be
completed by end of 2016. Proposed training calendar for the remaining PAPs,
is given in Table 3.5.
Table 3.4 Number of PAHs and PAPs covered under training programme conducted till
Feb 2016
PAH Type No. of
HHs as
per RAP,
LRF, SIA
No. of
HHs
covered
under LRP
HHs did not
participate in
LRP (not
interested/ not
traced)
No. of
HHs
covered
within
Decemb
er 2015
Number of HH
members
received
training within
December 2015
No. of HHs
covered
within March
2016
Numbe
HH me
receive
training
within
Februa
Landowners,
Sharecroppers,
Khasland
cultivators and
Resettlers
171 151 20 70 90 81 117
(These PAHs group
are eligible for Seed
Money)
Landown
ers: 86
(out of 171) (out of 171) (out of
151)
(out of 70 HHs) (out of 151
HHs)
(out of
HHs)
Khasland:
54
Sharecrop
pers: 16
Not Traced: 15
Resettlers:
15
Not Interested:
5
Agriculture labour 138 80 (out of
138)
58 (out of 138) 60 (out
of 80)
86 (out of 60
HHs)
76 (out of 80) 111 (out
(These PAHs group
are Not eligible for
Seed Money)
Total 294 205 89 130 176 157 228
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 3RD EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
31
Table 3.5 Tentative Work Plan for Remaining LRP training
S. No Activities Target Location 2016 Remarks
Fe
b
Ma
rch
Ap
ril
Ma
y
Jun
e
July
Au
gu
st
Se
p
Oct
o
No
v
De
c
1 Business training 10 days×1Batch Participant-25 Project office
2 Business training 10 days×2Batch Participant-30 Project office
3 Business training 10 days×3Batch Participant-33 Project office
4 Fishery training 1 Batch, Participant-7 Project office
5 Electric house wiring
training 25days×1Batch Participant-25 Sherpur
6 Masonry/house painting 25days×1Batch Participant-18 Sherpur
7 Mobile servicing training 25days×1Batch Participant-15 Sherpur
8 Welding training 25days×1Batch Participant-17 Sherpur
9 Snack food/cooking
training 25days×1Batch Participant-02 Sherpur
10 Follow up after training Trainees Project area Continuous
Source: SBIIPCL site data
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
32
Updated list of PAHs (who were not interested/not traced) in LRP
LRP document prepared by LRP consultant had identified 31 PAHs
who were either not interested (14) or could not traced (17) during
household survey for preparing LRP. These 31 PAHs were revisited
by the LRP implementation agency (IDEA) for tracking their interest
in LRP program. Table 3.6 highlights current status on this aspect.
Table 3.6 Reassessment of the PAHs who were either not interested or traced
SL ID HH Head Previous Status
June 2015 (LRP
Survey)
Present Status
March 2016
LR Activities Expected
Timeline
1 8 Ariful Bibi Not Interested Interested Foysol Miah: Fish
Culture
June 2016
2 10 Mina Begum Not Interested Interested Salik Miah: Fish
Culture
Alal Miah: Fish
Culture
June 2016
June 2016
3 21 Anayetullah Not Traced Not Traced NA NA
4 22 Sekondor
Ullah
Not Interested Interested Mozahid: Electrical
Zobayer: Welding
July 2016
October 2016
5 25 Rokeya Begum Not Traced Interested Rokeya Begum:
Sewing
NA
First Batch
completed
6 27 Anhar Miah Not Interested Interested Anhar Miah: Business April 2016
7 35 Moshahid
Miah
Not Interested Interested Moshahid Miah:
Business
April 2016
8 47 Porosh Bibi Not Interested Not Interested NA NA
9 69 Rahima
Khatun
Not Interested Interested Rahima Khatun:
Poultry
Received in
January 2016
10 76 Tokbir ullah Not Traced Not Traced NA NA
11 77 Rofique Ullah Not Traced Not Traced NA NA
12 79 Mosaddor Ali Not Interested Not Interested
Settled in UK
NA NA
13 101 Jahid Ullah Not Traced Not Traced NA NA
14 102 Dulal Not Interested Interested Abdur Rashid:
Computer
Received in
February 2016
15 105 Tajullah Not Traced Traced Aslomullah: Business
Sajlu Miah: Business
April 2016
16 106 Boshir Miah Not Interested Not Interested NA NA
17 108 Lesu Miah Not Traced Not Traced NA NA
18 109 Bozlu Miah Not Interested Interested Bozlu Miah: Business April 2016
19 111 Fozlur Rahman Not Traced Not Traced NA NA
20 137 Nozibullah Not Traced Not Traced NA NA
21 138 Hazi Satir
Miah
Not Traced Not Traced NA NA
22 139 Md. Ashiqur
Rahman
Not Traced Not Traced NA NA
23 142 Ashik Miah Not Interested Interested Ashik Miah: Business April 2016
24 144 Rustom Ali Not Traced Not Traced NA NA
25 145 Abdur Razzak Not Traced Not Traced NA NA
26 146 Kodorish Ali Not Traced Not Traced NA NA
27 152 Ator Ullah Not Interested Not Interested NA NA
28 153 Ismail Miah Not Traced Not Traced NA NA
29 158 Abdul Amin Not Traced Not Traced NA NA
30 163 Ruhel Miah Not Interested Not Interested NA NA
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
33
SL ID HH Head Previous Status
June 2015 (LRP
Survey)
Present Status
March 2016
LR Activities Expected
Timeline
31 369 Shahjon Miah Not Traced Not Traced NA NA
Source: SBIIPCL site data
Note: Results of the reassessment of 31 PAHs shows that 9 out 14
PAHs (who were earlier not interested) have now shown their interest
in different livelihood restoration activities. 2 out of 17 PAHs (who
were earlier not traced) have been traced and shown their interest in
livelihood restoration activity.
Old age pension scheme
As per the ‘SIA, RAP & LRF’ document of IFC, 57 old age and 11 widows were identified under vulnerable category during the SIA
survey process and they were made eligible for getting Tk 1000 per
month as pension under the RAP.
Reassessment of the vulnerable list was carried out by the IDEA (LRP
implementation agency). Key observations of the assessment were:
Total 49 persons under vulnerable category could be identified for
pension scheme. However ‘SIA, RAP & LRF’ document have budgetary provision for 68 candidates for pension scheme;
Total 24 Male could be identified till March 2016 for vulnerable
group pension. 21 were from the baseline list of ‘SIA, RAP & LRF’ document and 3 were newly identified;
25 Female were identified. This includes 3 new cases and rest of
them were from baseline list of ‘SIA, RAP & LRF’ document. SBIIPCL will provide them lifelong pension of BDT 1000/month
which will be started from April 2016.
For the verification and eligibility assessment, the candidates
should submit photocopies of their National ID card and passport
size photo.
SBIIPCL will maintain one register for the payment and the
candidates will give signatures upon receiving the monthly
stipend from the concerned person.
SBIIPCL thereafter, assumes that some eligible & interested
candidates for the pension scheme might appear while
distributing pension to the selected candidates.
SBIIPCL will assess the eligibility and vulnerability of the
upcoming candidates and include them for future considerations
if there are any suitable cases for inclusion;
Seed money distribution
LRP Training for 130 households were completed by December 2015.
Out of that 70 PAHs were entitled for seed money.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
34
67 out of the 70 PAHs had established bank accounts and shared
bank account detail with SBIIPCL.
Seed money is being released to entitled PAHs in three
instalments with the objective to ensuring utilisation of this
money for livelihood generation activity. First instalment for the
amount of 25000 BDT has been released to 65 PAHs out of the 67
PAHs whose bank detail was shared with SBIIPCL. Remaining
two cases were withheld for the time being, owing to certain valid
reason. One case was withheld due to non-accomplishment of
LRP training.
Monitoring indicators have been prepared to check utilisation of
first instalment and for releasing II instalment of seed money.
These indicators are linked to the training imparted the PAPs of
the eligible PAHs, are described below;
Also, it was mentioned that, 15 PAHs, who were shifted to the
resettlement colony area, were not entitled for seed money as per
the RAP, LRF and SIA document of IFC. However, these 15 cases
have now been considered for seed money benefit. For this group
SBIIPCL is planning to release the seed money payment along
with other 14 resettled PAHs in order to prevent any likely
concern among the resettled PAHs.
Table 3.7 Monitoring indicators for releasing second instalment of seed money
S.
No
Name of Training
imparted
Indicators for releasing II instalment
1 Beef Fattening Construction of sheds;
Purchase of calf/cow/ox.
2 Poultry/Duck rearing Purchase of seeds/fertilizer/inputs;
Leasing of additional parcel of land.
3 Agriculture Purchasing of computer/accessories
Renting of rooms/shops for business or
supportive items for initiating business.
4 Computer Purchasing of computer/accessories;
Renting of rooms/shops for business or
supportive items for initiating business.
5 Sewing Purchasing of sewing machines;
Purchasing of cloths/accessories
Source: SBIIPCL site data.
3.2.6 Stakeholder Engagement
Project has put in place different mechanism to engage project
affected and general community and provided them the opportunity
to register their concern.
Project presently has a dedicated Community Development
Officer (CDO) who was observed to be in regular touch with the
neighbouring community.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
35
Project has formed a Joint Committee for Community Relation
(JCCR) which is active and regular meeting of JCCR members is
organised by CDO.
A formal grievance redress mechanism (GRM) for the community
is also in place.
A copy of SEP and GRM in local language is shared with sizeable
number of PAHs. CDO also keeps local stakeholder including
PAHs informed about the process of raising grievances, if any.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
36
4 COMPLIANCE STATUS OF CAP & ESMMP AND IFC ESAP
The compliance status based on the site visit and review of documents as on February 2016 has been presented in Table 4.1 and Table 4.2. In order to define the status of various action items, colour
coding has been used for easy referencing, which is as follows:
Action Item Closed/ Complied Satisfactory Progress
Partially Complied Not Complied/ Delay
To be assessed during Operations/Decommissioning
Table 4.1 CAP & ESMMP Compliance Status
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
1 PS 1: Assessment and Management of Environmental and Social Risks and Impacts
1.1 Form a Construction Management Team (CMT) to
oversee EHS compliance of the Project during
construction phase
High SBIIPCL CMT Formation
Within 1 month of ‘date of deal closure’1 or November 2014, whichever is earlier
Complied Assessed and found to be in compliance by ERM during EHSS audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance Assessment Report.
1.2 Appoint a trained EHS Personnel for day to day
monitoring of the EHS Plan and ESMMP
implementation
High SBIIPCL EHS Officer for the Project
Within 1 month of date of deal closure or November 2014, whichever is earlier
Complied Assessed and found to be in compliance by ERM during EHSS audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance Assessment Report.
1.3 Ensure that all the records should also be made
available in local language/ English by the EPC
contractor
Review of all the records being maintained as
part of EHS Plan by the EPC contractor;
High SBIIPCL and EPC Contractor
Records Review and Corrective Actions
Within 2 months of date of deal closure or December 2014, whichever is earlier
Electrical permit recommendations are being followed. Inspection of lifting machines (hydraulic lift) and fall protection equipment (safety harness, lanyard etc.) are undertaken by NEPC in accordance to the frequency and format specified in the EHS Plan. Injury/illness log sheet in the EHS Plan has been updated through incorporation of occupational illness and man-hours worked data.
As recommended in the ERM Audit report dated 19 November 2015, the inclusion of Lock Out Tag Out (LOTO) checklist and PPE requirement is still found to be absent in the work tickets being issued for electrical work. This is important as NEPC is temporarily involved in project operations till it is being handed over by SBIIPCL to the Operations & Maintenance (O&M) contractor i.e. NEPC-S.
Reportedly the facility operates lifting equipment’s in the form of gantry cranes and overhead cranes for which no inventory is being maintained by NEPC.
Further the aforesaid equipment has not been subjected to thorough examination by a competent person and a register of such examination maintained in prescribed format as required under relevant provision of Bangladesh Labour Law, 2006.
Review of monthly injury and illness log maintained for the period Oct’15 to Jan’16 reveal that the same has been updated to include occupational illness and man-hours work related data. No injuries/illness has occurred during the said period.
NEPC to implement LOTO checklist integral to the work ticket being issued for electrical maintenance activities. NEPC to engage a competent person to perform periodic inspection of lifting machinery including lifting tools and tackles. Records of such examination to be maintained in format prescribed by the Bangladesh Labour Law.
1.4 Display and communicate environment and health
and safety policies of the company
High SBIIPCL Disclosure of company policies
Within 1 month of date of deal closure or December 2014, whichever is earlier
Complied. Assessed and found to be in compliance by ERM during EHSS
audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance
Assessment Report. 1.5 Develop a social policy of the Project with defined Medium SBIIPCL Social Policy Within 3 months of date of Complied. Assessed and found to be in compliance by ERM during EHSS
1Date of deal closure has been assumed the date on which the lender/s give/s assurance to SBIIPCL for providing project finance.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
37
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
objectives, principles and performance indicators. deal closure audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance
Assessment Report. 1.6 Develop and maintain legal register for all the Project
components
Medium Low
SBIIPCL and EPC Contractor SBIIPCL
Legal Register for Construction Legal Register for Operation Phase on Combined Cycle basis
Within 4months of date of deal closure for construction phase and quarterly review Within 3 months prior to the operation phase and half yearly review
SBIIPCL has updated the legal register through incorporating the conditions outlined in the applicable EHS permits and national regulations. SBIIPCL has also been monitoring and documenting the compliance status of this legal register on a monthly basis since October, 2015.
SBIIPCL has identified the applicable EHS permits/licenses (Refer Table 3.1) required during both construction and operational phases and their validity and approval status has been provided in Table 3.1.
As observed during the site visit SBIIPCL has not obtain necessary permit/license for storage of ~1362 litres of diesel for operating the generator set at the fire pump house. This is required under the relevant provision of Bangladesh Petroleum Act, 1934.
As recommended in the 19 Nov 2015 ERM Audit report, SBIIPCL is yet to prepare a legal register encompassing the conditions specified in the EHS licenses/permits (Refer Table 3.1) and relevant provisions of applicable regulations (Bangladesh Labour Act, Bangladesh Factories Rules etc.). The tracking of compliance status of the permit/license condition by SBIIPCL was also found to be pending. This is crucial as SBIIPCL has commenced with the combined cycles operation from December 2015 onwards.
SBIIPCL to obtain necessary permission for diesel storage in 1362 litres capacity tank as required under relevant provision of Bangladesh Petroleum Act, 1934. SBIIPCL to update the legal register to incorporate the conditions outlined in the applicable EHS permits and national regulations. SBIIPCL also need to monitor and document the compliance status of this legal register on a monthly basis.
1.7 Comply with the findings (not aligned) and
recommendations
High SBIIPCL and EPC Contractor
Legal compliance
Within 2 months of date of deal closure or December 2014, whichever is earlier
Complied. Refer Table 5.1 on Project EHS&S Regulatory Compliance Status
1.8 Develop the management plans as identified in the ESIA report and update the ESMMP with defined action items, responsibilities, monitoring indicators and review/ audit mechanisms
High SBIIPCL Management Plans as per ESIA requirement
Within 2months of date of deal closure or December 2014, whichever is earlier
SBIIPCL engaged a qualified Avifauna Management Expert. Bird survey has been conducted.
SBIIPCL has developed a Livelihood Restoration Plan and Public Relation Plan for the project in consultation with external agencies/experts.
Regarding development of the Avifauna Management Plan SBIIPCL has engaged Dr. Mohammad Firoj Jaman of Department of Zoology, University of Dhaka to conduct migratory bird survey for the project. The survey was conducted during 7th-8th December 2015 encompassing five Beels (water bodies) within the project study area. The two day survey recorded 43 bird species in Hakaluki Haor and Bara beel of which majority were identified to be as water birds. The study report does not indicate any change/disruption of migratory bird movement or habitat due to the project; however it is recommended in the report that an annual monitoring is undertaken to comprehensively assess the potential impact on migratory bird habitat, if any throughout the lifecycle of the project. The subsequent surveys to be undertaken to be focusing on the transmission line stretch (~70m) and outcome utilised for development of an Avifauna Management Plan, if required, based on the assessment of any impact on the avifauna due to the transmission lines.
1.9 Develop an organisational structure for the
construction and operation phase of the Project with
defined roles and responsibilities
High Low
SBIIPCL
Organisation Structure – Construction
Within 2months of date of deal closure or December 2014, whichever is earlier
Complied Assessed and found to be in compliance by ERM during EHSS audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance Assessment Report.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
38
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
Low SBIIPCL Organisation Structure – Operation on Combined Cycle basis
3 months prior to the operation phase
Complied Assessed and found to be in compliance by ERM during EHSS audit undertaken in September 2015. Refer ERM 3rd EHSS Compliance Assessment Report.
1.10 Training of SBIIPCL Staff and EHS team of EPC
Contractor on ESMMP
High
EPC Contractor
Training Calendar (Construction)
Within 2 months of date of deal closure or December 2014, whichever is earlier
Complied. Assessed and found to be in compliance by ERM during EHSS audit undertaken in September 2015. Refer ERM 3rd EHSS Compliance Assessment Report.
1.11 Training of SBIIPCL Staff and EHS team of EPC
Contractor on Operations ESMMP
Low SBIIPCL Training Calendar (Operation)
Within 2 months of Combined Cycle Operation
Already works are in process.
With respect to operations NEPC-S has already developed a training calendar for 2016 encompassing the following components:
Power Plant Safety Rules and Permit to Work;
EHS Policy and Procedures;
Site Risk Assessment and Prevention Spill;
Fire Equipment Facility and Fire Emergency Response;
Heavy Equipment Operation Safety;
Basic Electrical Safety;
Hot Work Training and Authorization;
Lifting Operation & Work at Height
Confined Space Work Safety
Safety Awareness;
Oil and Chemical Spillage Prevention;
Hazardous Material and Waste Management Training;
First Aid;
PPE and Safety Equipment Use Training;
Chemical and Flammable Material Handling; and
Compressed Gas Cylinder Safety As per the aforesaid calendar training on Power Plant Safety Rules; Permit to Work and EHS Policies & Procedures were scheduled for January 2016. However implementation of the said training programs is still found to be pending. NEPC-S to ensure thorough implementation of the training program in accordance to the annual training calendar prepared for the year 2016.
1.12 Mapping of training needs of SBIIPCL Staff and
development of training calendar
High SBIIPCL Training Calendar
Within 2 months of Combined Cycle Operation
- As discussed in Sl. No. 1.11 NEPC-S has developed a training calendar; however the same is not found to be based on a training need assessment study of the operational workforce. NEPC along with SBIIPCL to perform a training needs assessment study of the operational workforce and utilise the outcome to develop and implement the training calendar.
1.13 Develop an emergency response plan into a
consolidated document with:
Identification of, including risks associated with
all project components;
Key community and environmental sensitivities
(such as village settlements, ponds, etc.) and the
potential of offsite consequences along with
mitigation measures;
A common communication and emergency
response process flow for onsite emergencies as
well as their communication to authorities
offsite;
Disclosure to communities in the vicinity of the
project on the emergency readiness of the
Medium SBIIPCL Emergency Response Plan for Operation Phase
1 month prior to the date of Combined Cycle Operation
Prepared SBIIPCL has prepared an Emergency Response Procedure (SBIIPCL-EHS-004) for operations and shared the same with NEPC-S for implementation. The procedure has identified response measures for the following emergencies – fire and explosion, medical cases, earthquakes, bomb threat and severe weather phenomenon. However review of the procedure indicates the following key gaps/deficiencies:
Roles and responsibilities of the Emergency Response Team (ERT) has not been defined;
Emergencies has not been classified according to the risk significance including response flow for controlling each emergency type;
Interfacing with offsite emergency responders lacking;
Contact details of both onsite and offsite emergency
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
39
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
company in case of any incidents. responders have not been incorporated in the procedure; and
Details of resources available for emergency response and control;
Requirements related to worker training; induction of new workers and visitors not covered; and
Disclosure of the potential emergencies from project operations including control measures with the surrounding communities has not been covered in the said procedure.
SBIIPCL along with NEPC-S to update the Emergency Response Procedure for operations to include the components related to emergency classification; defining ERT roles and responsibilities; resource availability; interfacing with offsite emergency responders; contact details of emergency responders; induction for workers/visitors; training on emergency response and community disclosure of potential emergencies/risks.
1.14 Review the emergency preparedness and response
plan and include the necessary required emergencies
and implement the same at the earliest.
High EPC Contractor
ERP for construction phase
Within 1 month of date of deal closure or December 2014, whichever is earlier
Complied. Assessed and found to be in compliance by ERM during EHSS
audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance
Assessment Report. 1.15 Appoint a suitably qualified Emergency Coordinator
for the Project
Medium SBIIPCL Emergency Coordinator for the Project
Within 2 months of date of deal closure or January 2015, whichever is earlier
Complied. Assessed and found to be in compliance by ERM during EHSS
audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance
Assessment Report. 1.16 Develop a Commitment Register as a part of
stakeholder engagement process in order to
document the outcomes of public consultations and
respond to local community expectations, and ensure
that these are communicated back to stakeholders
and updates provided.
High SBIIPCL
Commitment Register (Construction) Commitment Register (Operation)
Within 2 months of date of deal closure Within 2 months of date of Combined Cycle Operation
Complied.
Assessed and found to be in compliance by ERM during EHSS audit undertaken in September 2015. Refer ERM 3rd EHSS Compliance Assessment Report. To be assessed during the first compliance monitoring of Operation Phase.
1.17 Consider preparing a detailed SEP with stakeholder
profiling, key concerns, expectations, impact and
influence, and risk rating of various stakeholder
groups. It should include details on engagement
strategy, disclosure, monitoring, reporting etc. The
SEP should be subsequently updated with
engagement records.
High SBIIPCL Updated SEP for the Project
Within 3 months of date of deal closure
Complied. Assessed and found to be in compliance by ERM during EHSS audit undertaken in May 2015. SEP document is prepared and disclosed with stakeholders. However, it requires certain modification. Refer S. No: 5.4 of this table for detail.
2. PS 2: Labour and Working Conditions
2.1 SBIIPCL while finalising its HR policy may consider
the following aspects for inclusion:
Roles and responsibilities associated with
various positions need to be mentioned;
Non-discrimination policy should be mentioned;
HIV/ AIDS non- discrimination should also be
spelt out;
Working with Suppliers and contractors and
non-employee workers may also be referred to;
Non-tolerance of child labour and forced labour
not only for employee, but for the non-
employee workers if any
Anti- Sexual Harassment Policy may be
explicitly captured;
All contractors and sub-contractors within the
consortium should be required to apply the
High SBIIPCL HR Policy and Procedures
Within 3 months of date of deal closure
Still pending SBIICPL has adopted the HR policy and Procedure of its parent
company i.e. SIMCL on 11th June 2015. ERM had reviewed the
SIMCL HR policy during the first EHSS audit in November 2014
and recommended for inclusion of following mentioned aspects:
Roles and responsibilities associated with various positions need to be mentioned;
Non-discrimination policy should be mentioned;
HIV/ AIDS non-discrimination should also be spelt out;
Working with Suppliers and contractors and nonemployee workers should also be referred to;
Non-tolerance of child labour and forced labour not only for employee, but for the non-employee workers, if any Anti- Sexual Harassment Policy should be explicitly captured;
ERM again reviewed the SIMCL HR policy which has been adopted by SBIIPCL and observed that above mentioned recommended aspects have not been integrated in the HR policy.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
40
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
principles of the SBIIPCL HR Policy document and
also ensure that their internal procedures follow local
and international standards.
This matter was discussed during the closing meeting on 13th September 2015 with the Senior Management of SBIIPCL and ERM received an email confirmation from the CEO of SBIIPCL on 28th September 2015 that the policy document will be updated within 2 weeks with inclusion of all the above mentioned observations of ERM. ERM will review the updated HR policy document during the next compliance audit. ERM was apprised in 4th EHS&S compliance audit visit (Feb
2016) that SBIIPCL has now adopted HR Policy of its parent
company i.e. Summit Industrial Mercantile Corporation (Pvt)
Ltd, now called as Summit Corporation Limited & Subsidiaries
(SCL&S). Few additions have been made in this HR policy
manual document of SCL&S, based on ERM’s recommendation and this includes;
Policy on Non-employment of Adolescent & Children at
Work;
Policy on Anti-harassment and Abuse at Work;
Anti-Discrimination Policy
2.2 HR Policy of the EPC contractor should comply
with the provisions of SBIIPCL HR Policy.
EPC contractor’s local staffs’ terms and
conditions of employment to be put in
compliance with SBIIPCL HR policy.
The EPC contractor to provide contracts or clear
terms and conditions highlighting the terms of
employment. Or the same could be possibly
hired through sub- contractors.
Workers to be provided clear terms and
conditions of employment.
High EPC Contractor
HR Policy and Procedures of EPC Contractor
Within 2 months of date of deal closure or December 2014, whichever is earlier
Salary Sheet analysis of
EPC Contractor for the
months of October,
November and December
of 2015 reveals that the
construction workers who
used to receive Taka 330
previously are now
receiving Taka 375 per
day. But it is to be noted
that most of these
construction workers are
deployed by the labor
suppliers, and hence,
service charge of Taka 60
has been deducted from
their daily wage, which is
paid to the labor suppliers.
So, actual minimum daily
wage received by the sub-
contracted laborers is 315,
which is below the
minimum wage fixed by
the government.
EPC Contractor has
revised the OT payment of
the workers. However, out
of the 43 workers who
received OT payment for
the month of November
2015, 10 workers have been
found to be receiving OT
payment at the rate less
than double to their wage
rates.
EPC contractor has prepared a separate HR policy for this
project that is observed to be in line with provisions of HR
policy of SBIIPCL. However the policy was not signed by
management of EPC contractor.
BCAS’s observation on paying minimum wage and paying overtime hours at twice of the ordinary wage is still intact.
Current wage rate of the workers is less than minimum wage
rate and payment of overtime hours is still equivalent to
ordinary wage rate.
The Site Management of NEPC Bibiyana II Project had given a
confirmation email on 17th September 2015 to SBIIPCL management
that they will maintain paying daily wage workers minimum wage
according to prevailing Bangladesh Labour Act; and the overtime
payment will be made at the rate of twice of wage rate for over-time
hours. Furthermore, same will be implemented with immediate effect.
Implementation of these actions will be further reviewed during the
next compliance audit.
The issue of paying minimum wage still persist as observed in
ERM’s in 4th EHS&S compliance audit. Refer section 3.2.2 for
detail.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
41
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
2.3 Improve the conditions of the migrant workers-
better accommodation and clearly articulated terms
and conditions of employment
High EPC Contractor
Improved workers’ accommodation
November 2014 The labour camp is in same condition.
Approx. 30 workers are reportedly staying in the labour colony
as reported during site visit. Almost 50% of them, are security
guards, and rest are construction workers, drivers etc. Basic
facilities like ventilation, lighting arrangement, sanitation, water
supply is being provided. Separate place for cooking with
adequate ventilation, is being maintained. Overall living
condition in labour colony seems to be at satisfactory level.
2.4 Clear labour construction camp guidelines to be
formulated and shared with SPCBL II. The
guidelines should take into consideration
observations highlighted in the report.
High EPC Contractor
Labour construction camp guidelines
Within 1 month of date of deal closure or November 2014, whichever is earlier
Complied. Assessed to be in compliance by ERM during EHSS audit undertaken in September 2015. Refer ERM 3rd EHSS Compliance Assessment Report.
2.5 Ensure that the principles on non-discrimination and
equal opportunity are included in the HR Policy
Statement and that the EPC Contractor abides by the
same while engaging local sub-contractor or contract
workers.
High SCBPL II HR Policy of SCBPL II
Within 3 months of date of deal closure
Complied. Assessed to be in compliance by ERM during EHSS audit
undertaken in May 2015. Refer ERM 2nd EHSS Compliance
Assessment Report.
2.6 The Project should establish channels for
management and workers to communicate and for
the workers to place their concerns as well as
suggestions.
The grievance process should be made accessible for
construction workforce and should enable workforce
to raise anonymous complaints. The grievance
records should be properly documented, tracked and
reviewed for redressal of the Grievances.
High SCBPL II EPC Contractor
Grievance redressal mechanism
Within 1 month of date of deal closure or November 2014, whichever is earlier
Till date, there is no incidence on labour dispute and conflict between groups and there are no legal disputes. Besides, query on labour grievance over the current monitoring period (from August, 2015 to January, 2016) reveals no grievance from the labours. This illustrates harmonious relationship among the reduced EPC Contractor personnel and labourers.
Assessed to be in compliance by ERM during EHSS audit undertaken in May 2015. Grievance redressal mechanism is prepared and disclosed to the stakeholders including workers. However it was observed that workers still prefer to register their grievances verbally to their supervisors and line managers. Workers grievances are majorly related to the request for providing PPEs which are addressed on time.
2.7 The EPC contractor’s position on non-employment of
child, forced or bonded labour has to be clearly
stipulated more specifically to the sub-contractors
and their associated workforce. There should be
proper checks and verification systems in place for
the workforce to ensure no cases of child labour or
forced labour are not allowed within the site
premises.
High EPC Contractor
HR Policy and Procedures of EPC Contractor
Within 1 month of date of deal closure or November 2014, whichever is earlier
Complied Project specific HR policy of the EPC contractor, does include provision around prohibition of child labour and forced labour. National ID card and age proof document is obtained from each worker at the time of recruitment. Worker below 18 years are not employed by the EPC contractor.
2.8 Develop a site specific health and safety manual
including SOPs and work permits required to protect
the construction manpower (including
subcontractors’ personnel) from injuries.
High EPC Contractor
SOPs for EHS Plan
Within 1 month of date of deal closure or November 2014, whichever is earlier
Complied Assessed and observed to be in compliance by ERM during EHSS audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance Assessment Report.
2.9 Develop a work permit system to carry out non
routine jobs at the construction site.
High EPC Contractor
SOP for work permit system
Within 1 month of date of deal closure or November 2014, whichever is earlier
Complied. Assessed and observed to be in compliance by ERM during EHSS audit undertaken in September 2015. Refer ERM 3rd EHSS Compliance Assessment Report.
2.10 Prepare a Job hazard analysis for all the construction
activity and same should be communicated to all the
workers.
High EPC Contractor
Job hazard analysis
Within 1 month of date of deal closure or November 2014, whichever is earlier
JHA has been updated with the given recommendation. JHA related trainings have been imparted to the construction workforce as part of site EHS inspections and documents
Based on ERM Audit report recommendation NEPC has updated the Job Hazard Analysis (JHA) as prepared earlier to cover the following activities:
Hot Work;
Confined Space; and
Material Lifting
Documentation review indicates that JHA related trainings are
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
42
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
are available related to this.
being provided to workers by NEPC; however documentation review indicates that the such training is only limited to the following – driver and vehicles safety, material lifting and work at height. No training has been imparted to the workers on job safety aspects associated with electrical work. NEPC to impart JHA related training to workers engaged in electrical work and maintain records for the same.
2.11 Prepare a pre-use inspection checklist (activity and
equipment specific) and same should be performed
and attach with every permit before starting of
activity.
High EPC Contractor
Activity and equipment specific checklist
Within 1 month of date of deal closure or November 2014, whichever is earlier
NEPC is now implementing pre-use inspection checklist for critical work activities such as hot work, confined space entry, material lifting and work at height.
In line with the earlier ERM audit report recommendation NEPC has implemented pre-use inspection checklist for hot work and material lifting activities undertaken as part of construction activities and records of the same found to be maintained.
2.12 Conduct train the trainer program to increase the
knowledge of the safety department.
Medium EPC Contractor
Training Records
Within 2 months of date of deal closure
Complied. Assessed and observed to be in compliance by ERM during EHSS audit undertaken in September 2015. Refer ERM 3rd EHSS Compliance Assessment Report.
2.13 Recruit a qualified doctor to work at first aid centre High EPC Contractor
Qualified doctor at site clinic
Within 2 months of date of deal closure
Complied Assessed and observed to be in compliance by ERM during EHSS audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance Assessment Report.
2.14 Prepare an Accident & Investigation register to
include the information related to the accident.
Medium EPC Contractor
Accident & investigation register
Within 1 month of date of deal closure or November 2014, whichever is earlier
Complied Assessed and observed to be in compliance by ERM during EHSS audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance Assessment Report.
2.15 Carryout hazard identification and risk assessment
(HIRA) for all construction and associated activities
and preparation of SOPs
High EPC Contractor
HIRA Register and SOPs
Within 2 months of date of deal closure or December 2014, whichever is earlier
HIRAC has been updated through identification of the potential hazards and risk assessment of activities related to fuel/chemical storage & handling, electrical work and confined space entry.
Based on the ERM audit report recommendation SBIIPCL along with NEPC has updated the Hazard & Risk Assessment & Control (HIRAC) document for construction phase particularly with respect to electrical work, confined space entry and hot work.
2.16 Carry out inspection for the potential hazards at the
facility and provide the risk control as per the
hierarchy of control.
High EPC Contractor
Risk control measures
Within 1 month of date of deal closure or November 2014, whichever is earlier
Complied Assessed and observed to be in compliance by ERM during EHSS audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance Assessment Report.
2.17 Provide training to workers, supervisors and
employees on importance and usage of PPEs for
different activities and organize PPE awareness
program.
High EPC Contractor
Training Calendar
As per Training Calendar Complied. Assessed and observed to be in compliance by ERM during EHSS audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance Assessment Report.
2.18 Prepare a PPE program for the facility and program
should cover the following essential elements:
Workplace Survey;
Selecting appropriate controls;
Training;
Maintenance;
Audit of the program.
High EPC Contractor
PPE Implementation Program
Within 1 month of date of deal closure or November 2014, whichever is earlier
A PPE inspection checklist has been prepared and regularly maintained by NEPC.
NEPC has developed a Checklist for Inspection of Personal Protective Equipment in accordance to the ERM audit report recommendation. However no documentary evidence could be made available to assess the onsite implementation of the checklist by NEPC. Further the checklist focusses on the availability and use of PPEs by workers but fails to assess and evaluate the condition of such PPEs in use. NEPC to update the PPE checklist to include provision for assessing and evaluating the condition of PPE in use by the workforce. The aforesaid checklist to be implemented and records maintained for verification.
2.19 Prepare training modules for job specific trainings
and identify workers required to undergo job
specific trainings.
High EPC Contractor
Training modules
Within 2 months of date of deal closure or December 2014, whichever is earlier
A register of workers based on their skill set and job profile has been prepared. Trainings are being imparted accordingly
With project in operations the O&M contractor has prepared training presentation comprising of the following aspects viz. Permit to Work, Fire Prevention & Protection; Injury & Illness Prevention; Pressure Vessel Safety; Power & Hand Tools Safety; Job Safety Analysis; Emergency Preparedness & Response; Material Lifting; PPE Use; Lock Out Tag Out; Confined Space Entry; and Machine Guarding.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
43
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
SBIIPCL to update the training presentation based on the training needs assessment study to be undertaken for operations.
2.20 Conduct the first aid training with the help of
qualified first aider and make sure that first aiders
are available at all times at facility.
High EPC Contractor
First aid trainings
Within 2 months of date of deal closure or December 2014, whichever is earlier
Complied Assessed to be in compliance by ERM during EHSS audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance Assessment Report.
2.21 Develop a standard operating procedure on incident
investigation with roles and responsibilities.
High EPC Contractor
Incident investigation SOP
Within 2 months of date of deal closure
Updated. The incident reporting process flow diagram incorporated in the Incident Investigation & Reporting Procedure is found to be generic and vague. Again the process flow also does not identify the role of both NEPC and SBIIPCL EHS personnel with respect to incident reporting and investigation. The Incident Reporting process flow diagram to be simplified and also updated to recognize the roles of both NEPC and SBIIPCL EHS personnel in the overall reporting and investigation process.
2.22 Start preparing the accident/ incident statistics for
each and every area and start identifying the area of
concerns and prepare an action plan to address the
issues by mean of alternate work procedure,
trainings, special attention to the high risk jobs,
increase in number of supervisor for high risk jobs.
Medium EPC Contractor
Statistical analysis of accident/ incident data and corrective action
Within 2 months of date of deal closure and monthly update of the same
Pending. SBIIPCL has identified the cooling tower, boiler area and central control building as the AOCs; however preparation and implementation of a safety action plan for the aforesaid AOCs is still under progress. With project under operation from December 2015 the SBIIPCL to ensure completion of the safety action plan for cooling tower, boiler area and central control building on a fast track basis.
2.23 SBIIPCL will need to put in place a formal contractor
management system to audit its contractors as well
as those of the EPC contractor. The management
system should include:
Compliance checklist against the Applicable
Standards;
Criterion on contractor selection to minimize
HSE or labour related risks and issues at the
time of engagement;
Monitoring and audit procedures; and
Further the EPC contractor and the sub-contractor
should be made responsible for the insurance of the
workers mobilised at the site.
High SBIIPCL Contractor Management System
Within 2months of date of deal closure or December 2014, whichever is earlier
O&M Contractor has done group insurance for the O&M staffs. However, SBIIPCL has not yet done any group insurance for the company’s staffs.
HSE In-charge of SBIIPLC deployed at site is accountable for ensuring compliances w.r.t the contractors and sub-contractors engaged at plant. Considering the nature & size of contract workers engaged at plant, provision of extending insurance is not applicable as per labour law of Bangladesh.
3 PS 3: Resource Efficiency and Pollution Prevention
3.1 Ensure that all the ESMMP implementation
requirements during construction phase are being
clearly provided to the EPC contractor and
implementation of mitigation measures along with
records should be reviewed by EHS Officer of the
SBIIPCL.
High SBIIPCL and EPC Contractor SBIIPCL
ESMMP implementation
As defined in ESMMP during construction phase
SBIIPCL has been preparing Monitoring Report on ESMMP Implementation since December, 2015.
Presently the project is in operations with COD for combined cycle operations declared in December 2015. Based on discussion with NEPC-S (O&M contractor) it is understood that the Operations Phase ESMMP has been shared by SBIIPCL with the former for implementation. However no verification checks/monitoring has been undertaken by SBIICL to check ESMMP implementation status on a periodic basis. SBIIPCL to perform monthly monitoring of the Operations ESMMP implementation with findings to be shared with NEPC-S as part of monthly EHS meetings for closure. The compliance status of ESMMP commitments for constructions has been tabulated below:
NEPC/ SBIIPCL have displayed 2-3 signages related to “no honking” and “Speed Limit” along the site access road.
With project now in full operation SBIIPCL is working towards engaging authorized waste contractor for disposal of the hazardous and non-hazardous waste streams to be generated from the facility. No open burning of waste was
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
44
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
observed at site and laydown area.
NEPC has performed river water quality validation in January 2016 by engaging Center for Research, Testing and Consultancy Department of Civil and Environmental Engineering Shahjalal University of Science and Technology.
Erosion monitoring is being performed based on visual observations, however a time series analysis is still found to be pending. Erosion was also observed during the site visit in February 2016 on the right bank of the Khusiyara River.
In order to improve emergency response preparedness SBIIPCL along with NEPC-S has organised emergency drills on 23 December 2015 and 11 February 2016 respectively. Review of the drill report indicates that participation is limited to only 20-30 personnel and does not encompass the entire operational workforce.
With project now in full operation efforts have been made by the ERM audit team to assess the compliance status of the ESMMP implementation for operations. A summary of the observations and recommendations made to this regard has been tabulated below: Management System Certification
SBIIPCL plans to obtain both ISO 14001 and OHSAS 18001
certification within 3 years of operations. Reportedly work to
this regard will commence following handover of project
operations to NEPC-S by SBIIPCL.
Flue Gas Emission
As specified in operational phase ESMMP, SBIIPCL has installed
and operating a Continuous Emission Monitoring System
(CEMS) to continuously monitor pollutant (CO, NOx, PM10,
SO2) concentration in stack emission. Review of the results for
the period Dec’15-Feb’16 for key pollutants viz. NOx (11.2-17.8
ppm) and PM10 (20.9-21.34 mg/m3) were found to be in
compliance with the standards specified in both IFC EHS
Guidelines for Thermal Power Plants and Bangladesh ECR,
1997. However the values for PM10 and NOx were not found to
be expressed in mg/Nm3 and ppm as required by the aforesaid
IFC Guidelines and Bangladesh environmental regulations.
NEPC-S to ensure the NOx and particulate matter values are
expressed in units specified in the emission standards of IFC
Guidelines and Bangladesh ECR, 1997.
Ambient Air Quality
SBIIPCL has not undertaken monitoring of NOx at the
surrounding villages Parkul, Bongaon and Paharpur as specified
in the operations phase ESMMP. SBIIPCL to perform quarterly
monitoring of NOx at Parkul, Bongaon and Paharpur quarterly basis
within 3 months of operation.
SBIIPCL has installed 3 continuous ambient air quality
monitoring stations (CAAQMS), which are installed on the top
of dormitory, cooling water pump house and cooling tower. The
system is operational since December 2015. Review of the
monitoring results indicated that the SO2 concentrations are
observed in the range of 40 to 80 µg/m3 and PM2.5 levels are
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
45
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
higher than PM10 levels in all the locations, which are not
matching with the testing done during the calibration period.
Furthermore the levels of SO2 during the conventional
monitoring were in the range of 10 – 18 µg/m3. Re-calibration of
the CAAQMS is required.
Noise Quality
NEPC-S has performed in house monitoring of ambient noise
quality in January 2016 at 8 locations within the project premises
viz. cooling water tower; water treatment area; dormitory; gas
station; generator yard; fuel engine room; boiler room and water
pumping station. Review of the results indicates compliance
with both day and night time noise standards specified for
industrial area under Bangladesh ECR, 1997. However the noise
values are recorded based on spot monitoring and does not
encompass the entire day (6AM to 9PM) and night (9PM to
6AM) time period (continuous monitoring) as specified in the
Bangladesh ECR, 1997.
With respect to ambient noise monitoring at surroundings
village locations the implementation of the same is found to be
pending by SBIIPCL. This is required under the Operation
Phase ESMMP.
NEPC-S to undertake continuous monitoring of noise levels (both day
and night time) to check compliance with ECR standards. SBIIPCL to
commence with ambient noise monitoring at Paharpur and Parkul
village locations on a quarterly basis as specified in the ESMMP.
Gas Supply & Quality
Review of the monthly operating details for January 2016
reveals consumption of 985292536 million standard cubic feet
(MSCF) of natural gas till date. No information was however
available on the quality of natural gas being supplied to the
project.
Effluent Discharge
Treated effluent from ETP and STP gets collected in a Common
Monitoring Basin (CMB) prior to its discharge into Khusiyara
River. All such discharges are being monitored by both SBIIPCL
by engaging a third part (M/s Adroit Consultants) and in-house
by NEPC-S. Review of in-house monitoring records for January
2016 reveals treated water discharges being monitored for pH,
temperature and conductivity (as specified in the operations
ESMMP) with results in all cases found to be in compliance to
Bangladesh ECR, 1997 inland water discharge standards. Reportedly
due to absence of necessary laboratory
infrastructure/equipment other key parameters like BOD, TSS,
TDS and Oil & Grease is not being monitored by NEPC-S. Hence
it is recommended that necessary efforts are made by NEPC-S to
improve on the laboratory infrastructure through procurement of
relevant analytical equipment/facilities for monitoring the key
environmental parameter as specified above.
For monitoring undertaken for treated waste water in December
2015 through third party agency, only 24 parameters were
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
46
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
found to be covered instead of 34 parameters as specified in
Schedule 10 of the Bangladesh ECR, 1997. The results though
found to be in conformance with the Bangladesh ECR, 1997,
SBIIPCL to conduct quarterly monitoring of all inland water discharge
parameters specified in Schedule 10 of the Bangladesh ECR, 1997 to
check for conformance and also to assess ETP performance.
During visit to the common effluent discharge point coloured
and oil bearing discharges into the Khusiyara River was
observed. Based on discussion with SBIIPCL and NEPC-S it is
understood such discharges has resulted from gas turbine (GT)
washing which were being directly released to the storm water
drain. In view of the above it is recommended that adequate
checks are in place by NEPC-S to monitor such unwarranted
discharges. Also a contingency plan needs to be developed to control
generation and discharge of GT wash water.
Surface Water Quality
SBIIPCL has engaged Centre for Research, Testing and Consultancy
Department of Civil and Environmental Engineering Shahjalal
University of Science and Technology to monitor Khusiyara river
water quality at 3 locations – near the project site and both 50 m
upstream and downstream of the project. Review of the
monitoring results for January 2016 reveals a total of 13
parameters being covered except for Dissolved Oxygen (DO)
and Total Coliform as referred in Schedule 3 – Standards for Inland
Surface Water of Bangladesh ECR, 1997. The results of the
parameters being monitored were found to be in compliance
with the aforesaid standards. SBIIPCL to include both DO and
Total Coliform as part of the quarterly monitoring of Khusiyara river
water quality.
Storm Water Management
SBIIPCL has not made any provision of installation of oil water
separators for storm water drainage system. This is assessed to
be justified based on the fact that the project hazardous material
and waste storages are covered along with necessary provision
made to channelize any waste/chemical spillages through
dedicated underground drainage system to a waste water
collection basin for subsequent treatment.
Waste Management
For the purpose of managing waste generated from operations
SBIIPCL has developed a Waste Management Procedure and same
shared with NEPC-S for implementation. Review of procedure
indicates it needs to be updated to include the various
hazardous waste stream and their storage, transportation,
recycling and disposal options. Maintenance of a waste
inventory by NEPC-S is also found to be lacking which is
necessary to adequately track the implementation of the waste
management procedure.
SBIIPCL has a designated and covered storage yard for
hazardous waste; however no provision for secondary
containment and spill kit was made available at the aforesaid
area to manage any accidental spillage during waste storage and
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
47
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
handling. The waste storage area was also found to be located
above the storm water drains thereby enhancing the potential
for hazardous waste releases to such drains in event of an
accident.
Regarding disposal of hazardous waste particularly used/waste
oil NEPC-S is in discussion with Lafarge Cement facility at
Chatak with a waste disposal agreement/contract yet to be
signed. Further no plans is presently available to manage
disposal of other notifiable hazardous waste streams viz. ETP
sludge, discarded chemical containers etc.
SBIIPCL along with NEPC-S to update the Waste Management
Procedure to include all notifiable hazardous waste streams and their
management measures. NEPC-S to regularly maintain a waste
inventory for all wastes identified in the Waste Management
Procedure. NEPC-S to execute a waste disposal contract/agreement
with Lafarge Chatak facility to facilitate disposal of used/waste oil.
Similarly NEPC-S to identify third party vendors for disposal of other
important hazardous waste streams; the vendors so identified to be
audited by NEPC-S prior to execution of any waste disposal contract.
SBIIPCL/NEPC-S to ensure provision of secondary containment and
spill kits at the designated hazardous waste storage area.
Hazardous Material Management
SBIIPCL has developed a Caustic & Acid Handling Procedure and
the same shared with NEPC-S for implementation during the
operations stage. However the review of the procedure reveals
that the procedure is limited to only caustic soda and
hydrochloric acid and is not extended to cover other hazardous
materials such as hydrazine, sulphuric acid, ammonia etc. which
are also being used. Further Material Safety Data Sheets (MSDS)
for the aforesaid chemicals has not been referred and/or
annexed to this procedure.
During visit to the acid and alkali storage area it was observed
that display related to warning signages and usage of
appropriate PPEs were found to be lacking. Further there exists
no provision for spill kits at the aforesaid storage area to control
any accidental spillage during loading of the acid and alkali
tanks. Periodic inspection of chemical emergency response
equipment like eye wash station and showers were also found
to be lacking.
SBIIPCL to update the Caustic & Acid Handling Procedure based on
the review of chemical usage requirements for operations. The updated
procedure to bear MSDS of chemicals to be stored and used for
operations. SBIIPCL to ensure provision of spill kits and display of
warning and PPE requirements at the acid and alkali storage areas.
Periodic inspection to be undertaken for all chemical emergency
response equipment and records maintained for verification.
Occupational Health & Safety
NEPC-S has commenced with monthly site safety inspection
from December 2015 with findings documented in a specific
format. However this report is not being shared with SBIIPCL.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
48
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
Induction training to visitor and operations workforce has not
been undertaken by NEPC-S as required under the ESMMP.
This is important given the combined cycle operations have
already commenced from December 2015.
For project operations, NEPC-S – the O&M contractor has
already developed a set of about 45 management procedures
and standards including Site EHS Plan for the year 2016. This
has been released by NEPC-S for implementation vide letter
dated 6 February 2016. However NEPC-S is yet to develop a
consolidated EHS plan for operations encompassing EHS policy,
objectives, procedures, training requirements, performance
indicators etc. to demonstrate compliance to the ESMMP
requirements.
In line with ESMMP requirements an EHS Committee has been
formed comprising representatives of both SBIIPCL and NEPC-
S. The Committee meeting is scheduled on a monthly basis and
is being chaired by the SBIIPCL Plant Manager. Additionally
monthly site safety inspections are being conducted by NEPC-S
along with monthly reporting on EHS performance to SBIIPCL.
Review of health register indicates that initial medical
examination is limited to only 72 personnel as compared to the
total operational workforce comprising of 96 personnel.
NEPC-S to share site inspection report with SBIIPCL on a monthly
basis and findings to be discussed in the monthly EHS Committee
meetings. NEPC-S to develop a consolidated EHS Plan for operations
and the same to be shared with all sub-contractors for agreement.
Induction training modules to be developed and implemented by
NEPC-S for both operational workforce and visitors. NEPC-S to
facilitate initial medical examination for the remaining operations
workforce (24 personnel) and fitness certificate issued to be maintained
for verification.
Emergency Preparedness & Response
For details refer to S. No. 1.13 of Table 4.1
In order to improve emergency response preparedness SBIIPCL
along with NEPC-S has organised emergency drills on 23
December 2015 and 11 February 2016 respectively. Review of
the drill report indicates that participation is limited to only 20-
30 personnel and does not encompass the entire operational
workforce.
Regarding maintenance of emergency response equipment’s
NEPC-S has developed and implemented a monthly inspection
checklist for fire extinguishers and fire hydrants with records
maintained. No inspection checklist is currently available to
check the performance of hose reels. Additionally during the
site visit at the cooling tower location the hydrant capping was
found to be locked with no hydrant valve spanner available to
open the same.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
49
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
SBIIPCL to ensure full participation of the operational workforce
during implementation of the quarterly mock drills being undertaken.
Further an inspection checklist to be developed and implemented by
NEPC-S for fire hose reels and records for the same maintained.
Green House Gas Emissions
No provision of CO2 emission monitoring is available in CEMS
and hence actual CO2 emission monitoring and annual reporting
is not possible. This was discussed during the closing meeting
and the SBIIPCL management had mentioned that GHG
emissions will not be monitored but calculated and based on the
fuel consumption and plant performance.
3.2 Undertake regular monitoring of air emissions, water
consumption, wastewater discharge, solid and
hazardous waste disposal, noise levels, in line with
the ESMMP
Low SBIIPCL ESMMP implementation
As defined in ESMMP during operation phase
Done both internally and externally by third party. SBIIPCL says that the oil-water separator is in-built with the ETP, and there is no possibility of mixing of waste water and sewage water (passing to the ETP) with the storm water. Hence, there is no necessity of another oil-water separator at the outfall point. CEMS is working.
For details please refer to S. No. 3.1- Ambient Air Quality; Waste Water Discharge; Waste Management and Ambient Noise Quality of Table 4.1.
3.3 Ensure that impacts associated with the
decommissioning phase are assessed and addressed
prior to eventual decommissioning.
Low SBIIPCL ESMMP for
decommissioni
ng phase.
1 to 2 years prior to
eventual
decommissioning.
- To be assessed during decommissioning phase for combined
cycle operations. With project now in operations the offices and
equipment’s utilised for constructions will be decommissioned by the EPC contractor following release of the Provisional
Acceptance Certificate by SBIIPCL. It is recommended that on
decommissioning of temporary site offices and equipment used for
constructions, SBIIPCL to perform a site assessment study to identify
any potential environmental issues/concerns and accordingly develop
an action plan for managing the same.
3.4 Complete an annual GHG emissions estimation based on the actual operations of the Project during the operational phase.
Low SBIIPCL GHG estimation and reporting.
Annually, after one year of COD
- No provision of CO2 emission monitoring is available in CEMS
and hence actual CO2 emission monitoring and annual reporting
is not possible. This was discussed during the closing meeting
and the SBIIPCL management had mentioned that GHG
emissions will not be monitored but calculated and based on the
fuel consumption and plant performance.
3.5 Develop the climate adaptation policy and procedures in line with the requirements specified in the ESMMP.
Low SBIIPCL Climate Change Adaptation Policy
Within 12 months of COD (Plant Operations
-
To be assessed during December 2016 – a year following the declaration of COD.
3.6 Provide organisational arrangements, capacity development and training measures and performance indicators for effective implementation of the ESMMP already developed for the Project.
High SBIIPCL Capacity building and setting up of performance indicators
1 month prior to COD SBIIPCL organized a training program with O&M Team on ESMMP implementation in operation phase.
Organogram for project operations is available for both SBIIPCL and NEPC-S however no interfacing was observed in the said organisational arrangements for both companies.
Also both SBIIPCL and NEPC-S are in the process of selection of performance indicators and developing a capacity building program to ensure effective implementation of Operations ESMMP.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
50
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
It is recommended that organogram for both SBIIPCL and NEPC-S are interlinked with performance indicators and training needs identified for implementation of ESMMP for operations.
3.7 Develop a Waste Management Plan for operation
phase.
Low SBIIPCL Waste
inventory and
disposal
options.
3months prior to start of
Combined Cycle
Operation
Hazardous waste storage
has been prepared for
operations phase.
DOE approved waste
collector is not available in
Sylhet. O&M Contractor
and SBIIPCL are searching
for DOE approved waste
collector.
SBIIPCL has developed a Waste Management Procedure (NEPCS-
O&M-P-EHS-001-09) and the same shared with NEPC-S for
implementation during the operations stage. The procedure
outlines the categories of wastes, PPE requirements; roles and
responsibilities and activities related to waste handling and
disposal.
Review indicates the procedure to be generic in nature and
lacking specific requirements with respect to management of
hazardous waste. Further procedure does not cover the
following hazardous waste streams viz. sludge generated from
effluent treatment plant; discarded chemical containers; used oil
etc. SBIIPCL to review and update the Waste Management Procedure
to encompass all hazardous waste streams likely to be generated during
operations. This should also include provision for a designated
hazardous waste storage area and evaluation of potential disposal and
recycling options as may be identified in discussion with Department
of Environment (DoE), Bangladesh.
It is understood based on discussion with SBIIPCL and NEPC-S
the volume of waste generation is presently quite low as the
plant has commenced operation only since December 2015.
Hence no waste inventory is currently being maintained by
NEPC-S for operations. It is recommended that NEPC-S
maintains an inventory for all waste streams related to their storage,
transportation, recycling and/or disposal during operations.
3.8 Develop a Hazardous Materials Management
(HMM) Plans.
High
EPC
Contractor
HMM Plan. –
Construction
phase
Within 2 months of date of
deal closure or December
2014, whichever is earlier
Complied Assessed to be in compliance by ERM during EHSS audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance Assessment Report.
Low SBIIPCL HMM Plan –
Operation
Phase
3 months prior to start of
Combine Cycle Operation
Complied.
Please see SBIIPCL-EHS-
003 including MSDSs
annexed to it.
SBIIPCL has developed a Caustic & Acid Handling Procedure
(NEPCS-O&M-P-EHS-001-03) and the same shared with NEPC-S
for implementation during the operations stage. The procedure
is intended to ensure safe handling of chemicals outlining the
measures to be adopted related to storage, handling, first aid
and accidental releases. .
However the review of relevant documentation reveals that the
procedure is limited to only caustic soda and hydrochloric acid
and is not extended to cover other hazardous materials such as
hydrazine, sulphuric acid, ammonia etc. which are also being
used. Further Material Safety Data Sheets (MSDS) for the
aforesaid chemicals has not been referred and/or annexed to
this procedure.
In this regard it is recommended that SBIIPCL update the Caustic
& Acid Handling Procedure based on the review of chemical usage
requirements for operations. The updated procedure to bear MSDS of
chemicals to be stored and used for operations.
3.9 Ensure that spillage kit is available at the HSD
storage area.
High EPC
Contractor
Spillage
management
Within 1 month of date of deal closure or December
Complied Assessed to be in compliance by ERM during EHSS audit undertaken in September 2015. Refer ERM 3rd EHSS Compliance
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
51
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
Provide drainage system to the HSD storage
shed to collect the rain water and waste water
generated after floor cleaning.
Prepare a procedure for the HSD loading &
unloading and spill control and trained workers
for the same.
Prepare a list of the authorised person and same
should be pasted outside the storage shed area
and access control system to be implemented.
plan 2014, whichever is earlier Assessment Report.
3.10 Develop a Standard Operating Procedure for Pest
Management for the Project.
Medium SBIIPCL Standard
Operating
Procedure for
Pest
Management.
Within 3 months of COD Not due Reportedly SBIIPCL has commenced with preparation of the Standard Operating Procedure (SOP) for Pest Management which is to be completed by end of March 2016. Necessary efforts need to be made by SBIIPCL to formulate the Pest Management SOP on a fast track basis in order to comply with the March end timeline.
3.11 Develop a Standard Operating Procedure on the use
of Ozone Depleting Substances (ODS), with the focus
being on no new systems or equipment use ODS.
Medium SBIIPCL Standard
Operating
Procedure on
the use of
Ozone
Depleting
Substances.
Within 3 months of COD
Not due Reportedly SBIIPCL has commenced with preparation of the Standard Operating Procedure (SOP) on the use of ODS which is likely to be completed by end of March 2016. Necessary efforts need to be made by SBIIPCL to formulate the ODS usage SOP on a fast track basis to comply with the March end timeline.
3.12 Ensure that emissions from on-road and off-road
vehicles should comply with Schedule 6 (Standards
for emissions from motor vehicles) of the
Environmental Conservation Rules, 1997 of GoB.
Medium SBIIPCL and
EPC
Contractor
Compliance
checks of on-
road and off-
road vehicles.
Within 2months of date of
deal closure or December
2014, whichever is earlier
(with quarterly
monitoring)
BRTA does not issue
fitness certificates for
foreign vehicles, which are
not registered in
Bangladesh. The rental
ambulance has been
changed.
For operations NEPC-S has deployed only two vehicles for
which valid certificate of fitness is available from Bangladesh
Road Transport Authority (BRTA) as required per the relevant
provision of Bangladesh Environmental Conservation Rules, 1997
and Motor Vehicle Ordinance, 1983.
3.13 Ensure no use of asbestos containing material is
specified in the design of the Project.
High SBIIPCL Written
confirmation
that no
asbestos will be
used in the
Project
development
from newly
purchased
materials.
Within 1 month of date of
deal closure
Complied Assessed to be in compliance by ERM during EHSS audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance Assessment Report.
3.14 Conduct air quality dispersion modelling study with
updated stack characteristics in the design
Medium SBIIPCL Updated air
quality
dispersion
modelling
Within March 2015 Complied Assessed to be in compliance by ERM during EHSS audit undertaken in September 2015. Refer ERM 3rd EHSS Compliance Assessment Report.
4 PS 4: Community Health, Safety and Security
4.1 Conduct a detailed QRA for the Project based on
actual design and formulate an emergency response
plan.
Medium SBIIPCL Quantitative Risk Assessment and Emergency Response Plan
3 months of COD Not due SBIIPCL has not initiated the Quantitative Risk Assessment (QRA) study to assess and evaluate the operational risks/hazards associated with the project. This is identified to be important taking into account the plant has commenced operations in December 2015 and also given the output of the study is to be utilised to formulate an Emergency Response Plan (ERP). It is recommended that SBIIPCL engages a qualified and experience agency/expert on a fast track basis to perform a QRA study of the project operational risks.
4.2 Develop a traffic management and logistics plan taking into consideration community safety
High EPC Contractor
Traffic management plan.
Within 1 month of date of deal closure or November 2014, whichever is earlier
Done. As per ERM recommendation from the earlier audit SBIIPCL in
coordination with NEPC has displayed “no honking” signage’s
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
52
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
along the site access road. However signage related to safe speed
limit is yet to be displayed along this road.
4.3 Undertake specific communication on health hazards and mitigation measures on an ongoing basis against new activities and associated health and safety risks to the local community.
Medium SBIIPCL Communication on health hazards and mitigation measures.
Within 3 months of COD Not due Considering the potential safety related risks on the nearby
communities from any operational failure/accidents it is
essential to communicate the same to these communities to
enhance risk preparedness. However no communication to this
regard has been done by SBIIPCL till date. It is recommended
that SBIIPCL develops a disclosure plan for communicating the
project operational risks/hazards to the nearby communities. Regular
dialogue to be maintained by SBIIPCL with the communities to apprise
them of the identified risks, appropriate control measures and response
actions.
4.4 Engage a suitably qualified professional to undertake a Life and Fire Safety (L&FS) review of the facility prior to commissioning and develop a Corrective Action Plan to address any identified deficiencies / gaps between the facility and the requirements of the WBG General EHS Guidelines.
Medium SBIIPCL Life and Fire Safety Review and Corrective Action Plan
1 month prior to the
commissioning of
combined cycle
Review work and
preparation of CAP is in
progress.
SBIIPCL has already engaged Life and Fire Safety Expert from
NEPC-S in September 2015 for assessing the fire safety
preparedness and subsequently develop a Corrective Action
Plan (CAP) to address any gaps/deficiencies. However based on
discussion with NEPC-S it is understood that fire safety review
of the project is likely to commence by end of March 2016.
With COD for combined cycle already declared on Dec 2015 the
assessment of project fire safety risks and preparedness need to be
undertaken by the Life and Fire Safety Expert on a fast track basis to
meet the suggested timeline. This is to be followed by preparation of a
CAP in consistent with the WB General EHS Guidelines.
4.5 Ensure any future security arrangements shall comply with PS4 requirements. The SBIIPCL Grievance Mechanism should include security within its scope.
Low SBIIPCL Compliance check against PS4 requirement.
1 months of COD Complied Security services are being provided through private security contractor. The O&M contractor i.e. M/s. NEPCS has entered into contract with the security agencies. Consultation with security personnel and review of their wage register indicate that payment to security guards are at par with minimum wage rate. Security personnel are being engaged in 3 shifts (8 hours each shift). Security contractor is held responsible for addressing grievances of the security personnel.
5 PS 5: Land Acquisition and Involuntary Resettlement
5.1 Ensure:
Preparation of the Livelihood restoration plan;
Documentation of the stakeholder engagement
records;
Maintaining proper records of the employment
and vendor opportunity provided to the PAFs
and the local community
Medium SBIIPCL Livelihood restoration plan and stakeholder engagement
Within 3 months of date of deal closure (and periodic review)
Complied. LRP has been rolled out and Project has hired an NGO called ‘IDEA’ for LRP implementation. Refer section 3.2.5 for current progress in LRP implementation.
5.2 Continued engagement and resettlement monitoring
by CDO.
Medium SBIIPCL Resettlement monitoring reports
Within 3 months of date of deal closure (and periodic review)
Complied CDO is observed to be in regular touch with the local community including PAHs. Key progress w.r.t. R&R aspects in the reporting period of this compliance audit period includes;
Appointment of NGO for LRP implementation;
Rolling out of LRP programme. Livelihood related training to eligible PAPs were initiated;
Disbursement of Seed money to eligible PAFs were initiated;
Accomplishment of above mentioned activities can be seen as an indicator of continued community engagement.
5.3 Establishment of a formal GRM for the PAFs and the
community;
Medium SBIIPCL GRM for PAFs Within 3 months of date of deal closure (and periodic review)
Complied Formal GRM is established. Process of registering grievances is documented in English and local language
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
53
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
and it has been disseminated with PAHs at individual level as well by CDO.
Records of grievances are maintained by CDO. Consultation with community and CDO indicates PAHs prefer sharing their grievances verbally either by calling CDO on his mobile or through meeting with CDO.
Grievances are recorded by CDO in grievances register. Thus GRM is considered to be in compliance by ERM.
5.4 Consider preparing a detailed SEP with stakeholder
profiling, key concerns, expectations, impact and
influence, and risk rating of various stakeholder
groups. It should include details on engagement
strategy, disclosure, monitoring, reporting etc. The
SEP should be subsequently updated with
engagement records.
Medium SBIIPCL Updated SEP for the Project
Within 3 months of date of deal closure (and periodic review)
SEP has not yet been updated following the recommendations.
SEP document was prepared by CDO and reviewed by SBIIPCL management. SEP document was also translated in local language and translated copies were shared with PAHs and other stakeholders. ADB has also reviewed SEP and suggested for following recommendations;
SEP should provide a strategy and timetable for sharing information and consulting with each of the groups identified
SEP should describe resources and responsibilities for implementing stakeholder engagement activities
SEP should describe how stakeholder engagement activities will be incorporated into the company’s management system
Insert a Summary of any Previous Stakeholder Engagement Activities
Add a section on Monitoring and Reporting - describing any plans to involve project stakeholders (including affected communities) or third-party monitors in the monitoring of project impacts and mitigation programs. Describe how and when the results of stakeholder engagement activities Will be reported back to affected stakeholders as well as broader stakeholder groups?
Insert the GRM procedure itself which describes the process by which people affected by the project (or company’s operations) can bring their grievances to the company for consideration and redress. Who will receive public grievances, how and by whom will they be resolved, and how will the response be communicated back to the complainant?
ERM had also recommended integrating these recommendations in SEP document. it was also recommend that copies of revised SEP, GRM, SIA etc. should be placed at CDO office, situated at community (located just across the power plant) for convenient access to wider range of stakeholders. Copies of GRM, SIA etc were observed to have been placed at CDO office for wider reach of stakeholders. Updating of SEP document with the ADB’s recommendations is in progress.
5.5 SBIIPCL should ensure payment of compensation to
sharecroppers in line with the resettlement action
plan and records should be maintained.
Medium SBIIPCL Records of compensation payment
After finalisation of CAP Complied. SBIIPCL has made payment to one pending agriculture labour. Payment of compensation stands completed now.
6 PS 6: Biodiversity Conservation and Sustainable Management of Living Natural Resources
6.1 Conduct six monthly construction phase monitoring
of terrestrial and aquatic organisms
High SBIIPCL Terrestrial and
aquatic
organism
monitoring
As defined in ESMMP
during construction
phase
Monitoring of terrestrial
and aquatic organisms
done. Reports have been
furnished as well.
As discussed during the earlier ERM audit report a terrestrial
floral and faunal study was undertaken for the project by Dr.
Md. Monirul Islam, Associate Professor, Department of Fisheries,
University of Dhaka in August 2015. As per this report no
potential change in species diversity and habitat has been noted
in the study area with respect to the SBIIPCL project.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
54
S.
No
Measures and/or Corrective Actions Significance Responsibility Deliverable Suggested Timelines for
Completion*
Status provided by BCAS
as on Jan-Feb 2016
Status ERM Observations (as on 28 Feb 2016)
A study was also conducted by engaging the aforesaid expert in
November 2015 to assess the limnological and fisheries
conditions for the impact zone of SBIIPCL project. A total of 34
species of fishes have been recorded from the study site
belonging to 27 genera, 14 families and 7 orders. As per the
report fish species recorded during both peak and lean season
fishing is assessed to be comparable to the baseline.
6.2 Develop greenbelt within the project boundary. Low SBIIPCL Greenbelt
Development
After completion of
construction activities.
Project site green belt has
not been ensured.
As discussed in the 3rd EHSS Compliance Assessment report
SBIIPCL had engaged M/s Zara Enterprise for maintenance of
nearly 2800 saplings planted under the Green Belt Development
Plan. However as observed during the site visit the current
survival rate of the planted saplings is only 65%-70%. One of the
primary reasons identified for such reduced survival rate is
possibly the lack of maintenance with contract of Zara
Enterprise expiring on October 2015. It is therefore
recommended that SBIIPCL engages a third party vendor under an
annual maintenance contract to improve green belt species survival
rate.
Regarding green belt development within the site it is
understood that formulation of such a plan is currently under
progress by SBIIPCL. With COD for combined cycle operations
declared in December 2015, SBIIPCL to get the Green Belt
Development Plan for project finalized on a fast track basis for
execution.
6.3 Include an invasive alien species management plan
in the ESMMP for the construction and operational
phases
Medium SBIIPCL and
EPC
Contractor
Invasive alien
species
management
plan.
Within 2 months of date of
deal closure
Complied Assessed to be in compliance by ERM during EHSS audit undertaken in May 2015. Refer ERM 2nd EHSS Compliance Assessment Report.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
55
Table 4.2 IFC ESAP Compliance Status
S.
No Measures and/or Corrective Actions Deliverable Schedule Status
ERM Observations
(as on 11 Sep 2015)
1 Upgrade the existing EHS Policy, EHS
Management Procedures and EHSS Plan in
accordance with the provision of IFC PSs, the
ESMMP and findings of the EHSS Audit, and
implement the EHS Management Procedure.
EHS Policy and EHSS Plan 31 Mar 2015 SBIIPCL has prepared an EHSS Policy for operations and the same has been shared with NEPC-S – the O&M contractor for adoption and implementation. Review of the policy reveals that it is effective from 15 June 2015 however it does not feature in the list of Company EHSS Rules and Procedures notified by NEPC-S to both SBIIPCL and the operations personnel vide letter dated 6 Feb 2016. Further the policy has also not been shared with the operations worker through display at a conspicuous location within the factory. As discussed above NEPC-S has notified a list of 45 EHS related procedures and rules which will be executed for project operations. However this list does not include the following plan and procedures being shared by SBIIPCL to NEPC-S for implementation viz. Permit to Work; Caustic and Acid Handling; Emergency Response; Electrical Safety; Environmental & Social Monitoring; Spill Prevention & Response; Spill & Release Reporting; Waste Management; Community Development; Grievance Redressal Mechanism; and Incident Investigation & Reporting. Further NEPC-S is yet to develop a consolidated EHS plan for operations encompassing objectives, procedures, training requirements, performance indicators etc. to demonstrate compliance to the legal, ESMMP and IFC PS requirements. Specific observations on the management plans for operations are given in S. No. 1.13, 3.1, 3.7, 3.8, 3.9, 3.10, 3.11 of Table 4.1.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
56
S.
No Measures and/or Corrective Actions Deliverable Schedule Status
ERM Observations
(as on 11 Sep 2015)
2 Obtain an Environmental, Occupational,
Health and Safety (EHS) Management System
(EHSMS) certified to ISO 18001 standards with
IFC Performance Standards appropriately
incorporated.
ISO 14001 and OHSAS 18001 certification
Within 2 years of COD
Please refer to S. No. 3.1 – “Management System Certification” of Table 4.1
3 Development and implementation of SBIIPCL
Human Resource Policy, Environmental Policy,
Social Responsibility Policy and Health &
Safety Policy/or Statement.
SBIIPCL Policies in place 31 Mar 2015 EHS, Social, and HR policies are in place. Specific observations on HR policy and manual are presented in S. No. 2.1 of Table 4.1.
4 Formation of SBIIPCL CMT and appointment
of SBIIPCL’s EHS Manager, CDO and Community Liaison Officer.
CMT. EHS Manager and CDO in place
15 February 2015 Assessed to be in compliance by ERM during EHSS audit undertaken in September 2015. Refer ERM 3rd EHSS Compliance Assessment Report.
5 Undertake labour audit covering own and
subcontractor workers to assess compliance
with national laws and IFC PS2 requirements.
This will cover review of all HR Policies and
Practices.
Complete implementation of mitigation
measures based on audit findings including
those relevant to EPC contractor’s management of labour issues
Labour Audit Report 31 March 2015 May 2015
Labour Audit report was carried out by BCAS. Outcome of the audit report was mentioned in previous audit report. there were some major gaps identified like non-compliance w.r.t minimum wage payment, overtime payment etc. for contract workers by EPC contractor (NEPCS). SBIIPCL was recommended to take actions to close the issues identified in labour audit report. Section 3.2.2 of this report update on current status on compliance w.r.t minimum wage and overtime.
6 Develop, communicate and operationalise the
worker’s grievance mechanism
Grievance Mechanism in place and conveyed to all stakeholders
March 2015 SBIIPCL has complied with this action plan and it was mentioned in previous audit report as well.
7 Complete implementation of corrective actions
based on first EHSS audit findings as per the
audit action plan and submits an action taken
report.
Action taken report 31 March 2015 Implementation of corrective actions based on first EHSS audit findings are being audited internally by SBIIPCL through BCAS and are being verified by ERM during quarterly auditing. ERM’s observations on each of the action item are presented in Table 4.1. Overall there is satisfactory progress with respect to
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
57
S.
No Measures and/or Corrective Actions Deliverable Schedule Status
ERM Observations
(as on 11 Sep 2015)
implementation of corrective actions during construction; however with project now in operations there are certain action items, which further need to be implemented in line with the specific recommendations given in italics text in Table 4.1.
8 O&M stage I documentation for management
of environment, health and safety performance
appropriately incorporating IFC Performance
Standards and Good International Industry
Practices.
Completed EHSMS Manuals
1 month prior to Combined Cycle Operation
Please refer to S. No.1 of Table 4.2.
9 Duty of care procedures implementation in
relation to hazardous waste treatment and
disposal facility.
List of the identified hazardous waste facilities
28 February 2015 Please refer to S. No. 3.1 – “Waste Management” of Table 4.1
10 The Company will as part of its monitoring
program continue to monitor bird species
within the project area of influence
Half yearly compilation Ongoing for two years
SBIIPCL has engaged Dr. Mohammad Firoj Jaman of Department of Zoology, University of Dhaka to conduct migratory bird survey for the project. The survey was conducted during 7th-8th December 2015 encompassing five Beels (water bodies) within the project study area. The two day survey recorded 43 bird species in Hakaluki Haor and Bara beel of which majority were identified to be as water birds. The study report does not indicate any change/disruption of migratory bird movement or habitat due to the project; however it is recommended in the report that an annual monitoring is undertaken to comprehensively assess the potential impact on migratory bird habitat, if any throughout the lifecycle of the project. The subsequent surveys to be undertaken to be focusing on the transmission line stretch (~70m) and outcome utilised for development of an Avifauna Management Plan, if required, based on the assessment of any impact on the avifauna due to the transmission lines.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
58
S.
No Measures and/or Corrective Actions Deliverable Schedule Status
ERM Observations
(as on 11 Sep 2015)
11 Develop and implement Livelihood
Restoration Plan
LRP in place and finalised in consultation with community and detailed PAH level LRP prepared and implementation complete
May 2015 (LRP development) August 2015 (for LRP implementation)
LRP is prepared. An NGO called as IDEA is engaged for LRP implementation. Refer section 3.2.5 for status on LRP implementation
12 Develop and implement comprehensive
stakeholder engagement plan and a detailed
Grievance Mechanism for the community.
SEP in place and communicated to all stakeholders.
August 2015 SEP and GRM is prepared and disclosed with stakeholders. Refer section 3.2.6 of this report for detail.
13 Completion audit of the resettlement/
livelihood restoration activities demonstrating
compliance with IFC PS5 or, if necessary,
identifying any remaining gaps and
corresponding corrective actions
Completion audit report and action taken report, if necessary
December 2016 As LRP implementation got delayed and it was recommended in previous audit report that time schedule for completion of audit report should be shifted to August 2017, considering the timeframe of LRP implementation activities. So SBIIPCL should stick to revised schedule for LRP implementation and its completion audit report.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
59
5 EHS&S REGULATORY COMPLIANCE ASSESSMENT
In addition to the CAP & ESMMP compliance assessment the ERM team has performed an EHS&S compliance audit of the
project for construction and operations phase. The audit has been conducted to assess project compliance with respect to
applicable local and national regulations including key permit/license conditions and has been based on site visits, site personnel
interviews and document reviews with the findings/observations being presented in Table 5.1 for reference. In order to establish
the compliance status, a risk rating with appropriate colour coding has been used for easy referencing, which is as follows:
High Significant deviation/departure from EHS&S regulations/permit conditions leading to legal prosecution, imposition of hefty
fines/penalties and or both requiring senior management intervention
Medium Substantial deviation from EHS&S regulations/permit conditions resulting in limited legal liability managed through interventions at
site management level
Low Minor deviation from EHS&S regulations/permit conditions managed through intervention of project EHS manager/personnel
Information to be
provided
Pending information to be shared for assessing compliance status
Table 5.1 EHS&S Regulatory Compliance Status
S. No Regulatory Requirement Finding /Observation Risk Rating Recommendation
1 Conditions of Environmental Clearance Letter dated 17 June 2015
1.1 All parameters of effluent, gaseous emission,
noise, solid waste, hazardous waste, etc. shall be
within the limits in the Environment
Conservation Rules (ECR) 1997. In case of non-
coverage of ECR 1997 the World Bank
Environment, Health and Safety Guideline shall
be adhered to.
Refer to S. No. 3.1 – Stack Emissions; Effluent Discharge;
Waste Management; Noise Quality; Surface Water
Quality of Table 4.1.
Refer to S. No. 3.1 – Stack Emissions; Effluent
Discharge; Waste Management; Noise Quality;
Surface Water Quality of Table 4.1.
1.2 Comprehensive Environmental Performance
report shall be submitted on a monthly basis to
both the DOE offices.
Environmental Performance Report (EPR) has been
prepared and submitted to DoE on 3 Feb 2016 and 4
Jan 2016 respectively. However review of the reports
indicates that the EPR though bear the EC conditions
however, the compliance status of the same has not
Update the EPR to include discussion on
the compliance status of the EC conditions.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
60
S. No Regulatory Requirement Finding /Observation Risk Rating Recommendation
been discussed and elaborated.
1.3 There shall be specific format for Environment
Monitoring. Environmental Monitoring Reports
shall be made available simultaneously to DOE
Head Quarter in Dhaka and Sylhet Divisional
Office on a monthly basis during the construction
& operation stage of the power plant.
The facility has developed a format for documenting
the environmental monitoring information for
operations and the same has been submitted to DOE
Head Quarter in Dhaka and Sylhet Divisional Office
on 4 January 2016. Review of the format reveals the
following gaps viz. the ambient air results not
expressed in units; error in the PM10 and PM2.5
standards being referred as part of Bangladesh ECR,
1997 etc.
Continue with the submission of
environmental monitoring report to both
DOE Head Quarter in Dhaka and Sylhet
Divisional Office on a monthly basis.
Ensure correct reference to the Bangladesh
Air Quality Standards and ambient air
results to be expressed in units specified in
the aforesaid standards
1.4 The noise level of the Power Plant area shall not
exceed the standard for industrial area mentioned
in ECR, 1997.
SBIIPCL has performed in house monitoring of
ambient noise quality in January 2016 at 8 locations
within the project premises viz. cooling water tower;
water treatment area; dormitory; gas station;
generator yard; fuel engine room; boiler room and
water pumping station. Review of the results
indicates compliance with both day and night time
noise standards specified for industrial area under
Bangladesh ECR, 1997.
2 Conditions of Boiler Registration
2.1 Boiler to be operated by certified boiler operator As per the condition of boiler registration permit,
boiler to be operated by certified boiler operator.
Compliance status still need to be assessed based on
availability and review of the certification copy of the
personnel involved in boiler operations at the plant.
This matter was discussed during the closing
meeting and SBIIPCL has confirmed that no such
permission is required; however, as this is part of the
condition imposed in the permit, a clarification is
required to be taken from the authority.
Obtain clarification from the competent
authority regarding condition related to
boiler operator certification.
3 Conditions of Factories License
3.1 First Aid Boxes to bear photographs of first aid
responders
As recommended in the 19 November ERM audit
report SBIIPCL has displayed the photographs of
certified first aid responders near all first aid boxes
location.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
61
S. No Regulatory Requirement Finding /Observation Risk Rating Recommendation
3.2 The occupier of the factory is required to set up a
“Worker Participation Fund” and “Worker Welfare Fund” in accordance to the provisions of the Bangladesh Labour Law 2006.
SBIIPCL is yet to establish a Worker Participation
Fund and a Workers Welfare Fund to comply with
the provision of Bangladesh Labour Law and
condition specified in the Factories License.
Establish a Worker Participation Fund and
a Workers Welfare Fund to comply with
the factories license requirement and
Bangladesh Labour Law provision.
4 Conditions of HSD Storage License
4.1 The tank or tanks shall be supported on an
approved foundation and shall be surrounded by
a wall or embankment of substantial construction,
or shall be partially sunk in an excavation. The
enclosure thus formed shall contain only one of
the following classes of petroleum, shall be of
dimension sufficient to contain
the quantity of petroleum specified under the
class to be stored and shall be so constructed and
maintained as to prevent the escape therefrom of
any petroleum in the form of liquid, whether
under the action of fire or otherwise.
Proper embankments were found to have been
provided for HSD storage tanks for the emergency
DG set as well as for the one located in the fire pump
house
4.2 All tanks shall be fitted with a vent pipe leading
into the open air, the open end being covered
with fine copper or other non-corroding metal
wire gauze of mesh not less than 11 to the linear
centimetre and fitted with a hood or the tank shall
be fitted with an approved relief valve or other
approved means for preventing dangerous
internal or external pressures being produced.
Visual observation did not reveal the presence of any
vent pipe or approved relief valves for the HSD
storage tanks to prevent any generation of pressure
from accumulation of dangerous vapour/fumes.
However this needs to be confirmed based on review
of the design document of the tanks.
Share design document of HSD tanks to
assess the compliance status related to
provision of vent pipes/approved relief
valves.
4.3 The licensee to keep records and accounts of all
petroleum in stock and issues and shall exhibit
his stocks and records to the Inspector or a
Sampling Officer
The chemical inventory sheet being maintained by
SBIIPCL does not bear information of HSD storage
and supplies.
Update chemical inventory sheet to
include storage and supply details of HSD.
5 Bangladesh Petroleum Act, 1934 & Petroleum Rules, 1937
5.1 As per Section 7 of this Act any person is
required to obtain a license for the transport or
storage of class II petroleum if the total quantity
in his possession at any one place does not exceed
two thousand liters and none of it is contained in
a receptacles exceeding one thousand litres in
capacity.
As discussed in the ERM Audit Report of 19
November 2015 the factory has diesel storage of 4KL
being kept in two tanks of 2KL capacity each.
Necessary license for such storage is available from
Department of Explosives, Bangladesh with the same
being valid till 31 December 2017. However as
observed during this visit the O&M contractor is
having an additional diesel storage of 1.36 KL
Obtain license from Department of
Explosives, Bangladesh for additional
storage of 1.36KL of diesel within the
factory premises.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
62
S. No Regulatory Requirement Finding /Observation Risk Rating Recommendation
capacity to fuel the generator set at the fire pump
house during emergency. No license was available
for this additional storage as per the provisions of the
Petroleum Act, 1934.
5.2 77. Approval of vehicles for transport in bulk
necessary. (1) Petroleum in bulk shall not be
transported by land except under a licence
granted under these rule in a vehicle of a type
approved in writing by the Chief Inspector.
As reported the diesel storages at the facility is
periodically refilled by deploying a third party
vehicle carrying diesel in bulk. To this regard the
O&M contractor has not verified the availability and
validity of the license issued by Department of
Explosives to the vendor for such bulk transportation
of petroleum.
Obtain and check validity of license issued
by Department of Explosives, Bangladesh
for the vendor involved in bulk
transportation of diesel at the factory.
5.3 99. Marking of capacity of tanks: The capacity in
litres of every tank in an installation shall be
conspicuously marked on the tank.
Diesel at the factory is being stored in 3 tanks (2 X
2KL capacity each and 1 X 1.35KL capacity); however
the capacity has not been conspicuously marked on
the tankages.
Ensure the diesel storage tanks are
conspicuously marked with their capacity
as required under Petroleum Rules.
5.4 102. Earthing of tanks: All tanks or other
receptacles for the storage of petroleum in
bulk other than well-head tank or tanks or
receptacles of less than 45,000 litres capacity
containing class III petroleum, shall be electrically
connected with the earth in an efficient manner
by means of not less than two separate and
distinct connections placed at opposite
extremities of such tank or receptacle.
Earthing was not available for the diesel storage tank
of capacity 1.36KL located near the fire pump house
Ensure provision of effective electrical
connection for the diesel storage tank near
the fire pump house for earthing purpose
6 Bangladesh Labour Law 2006 (as amended 2013)/Bangladesh Factories Rules, 1979
6.1 68. Cranes and other lifting machinery : The
following provisions shall apply in-
(a) every part thereof, including the working gear,
whether fixed or movable, ropes and chains and
anchoring and fixing appliances shall be-
(i) of good construction, sound material and
adequate strength,
(ii) properly maintained,
(iii) thoroughly examined by a competent person
at least once in every period of twelve months
and a register shall be kept containing the
prescribed particulars of every such
examination;
The facility currently operates five (5) overhead
travelling cranes which are being subjected to
periodic internal examination by NEPC. The records
of such examination were found to be maintained in
accordance to a format specified in the project EHS
Plan. However prior to putting these machineries in
use for first time in this facility no examination has
been performed by engaging a competent person for
specifying the safe working load. It was reported that
all the equipment’s were commissioned and checked by OEM, who manufactured this and after one year
of operation these will be due for inspection by
competent person.
Engage a competent person to perform
examination of overhead travelling cranes
and records of such examination
maintained in Form 9. Ensure such
examination is undertaken for the lifting
machinery on an annual basis.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
63
S. No Regulatory Requirement Finding /Observation Risk Rating Recommendation
(b) no such machinery shall be loaded beyond the
safe working load which shall be plainly
marked thereon; and
€ while any person is employed or working on or
near the wheel-tract of a traveling crane in any
place, where he would be liable to be struck by
the crane, effective measures shall be taken to
ensure that crane does not approach within six
meter of that place.
6.2 69. Hoists and lifts : (i) In every establishment
every hoist and lift shall be- (a) of good
mechanical construction, sound material and
adequate strength, (b) properly maintained,
(c) shall be thoroughly examined by competent
person at least once in every period of six
months, and a register shall be kept containing
the prescribed particulars of every such
examination.
The facility operates eight (8) hoist and two (2) lifts
which have not been subjected to initial examination
by a competent person prior to their first time in use
at the facility. No periodic examination is also being
performed for the aforesaid hoist and lifts as required
under Bangladesh Labour Law provisions. It was
reported that all the equipment’s were commissioned and checked by OEM, who manufactured this and
after one year of operation these will be due for
inspection by competent people.
Engage a competent person to perform
examination of hoist and lifts in use at the
facility to specify the safe working loads.
Ensure such examination of lifting
equipment is undertaken on a six monthly
basis.
6.3 89. First-aid appliances : (1) there shall, in every
establishment be provided and maintained, so as
to be readily accessible during all working hours
first-aid boxes or cupboards equipped with the
contents prescribed by rules.
(3) Every first-aid box or cupboard shall be kept
in charge of a responsible person who is trained
in first-aid treatment and who shall always be
available during the working hours of the
establishment.
The first aid boxes at the facility were found to be
kept in charge of certified first aiders from SBIIPCL
and EPC contractors. However with project in
operations from December 2015 no workers from the
O&M team has been identified and trained on first
aid treatment as required under the Bangladesh
Labour Law provisions.
Identify and train at least 1/4th of the O&M
workforce on first aid treatment as per the
Bangladesh Labour Law provision.
6.4 79. Dangerous operations : (d) providing for the
protection of all persons employed in the
operation or in the vicinity of the places where it
is carried on and the use of any specified
materials or processes in connection with the
operation; and
€ notice specifying use and precautions regarding
use of any corrosive chemicals.
During the site walkthroughs absence spill kits were
observed at the following areas:
Acid and alkali storage area; and.
Hazardous Waste Storage Area
Additionally no secondary containment was
observed at the hazardous waste storage area.
Ensure display of provision of spill kits at
the designated storages for acid, alkalis
and hazardous waste. Provide secondary
containment at the hazardous waste
storage to control any accidental
spills/releases to the storm water drain
nearby.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
64
S. No Regulatory Requirement Finding /Observation Risk Rating Recommendation
6.5 6. Service Book: (1) Every employer shall, at his
own cost, provide a service book for every worker
employed by him.
Reportedly a total of 95 workers have been deployed
for factory operations however a service book is not
being maintained for each worker as required under
the provision of Bangladesh Labour Law, 2006.
Maintain a service book for all workers
containing the following particulars viz. (a) name of the worker, name of mother
and father and address of the worker; (b)
date of birth, (c) particulars necessary for
identification, (d) name and address of the
employer under whom previously
employed, if any, (e) period of
employment, (f) occupation or designation,
(g) wages and allowance, if any, (h) leave
availed, and (i) conduct of the worker.
6.6 9. Register of Workers: (1) The employer of every
establishment shall maintain a register of
workers, to be available to the Inspector at all
times during working hours.
The factory was not found to maintain a register for
all workers being engaged at the factory for the
operations stage.
Maintain a register of workers in Form 14
comprising the following viz. (a) the name
and date of birth of each worker in the
establishment; (b) date of appointment; (c)
the nature of his work; (d) the periods of
work fixed for him; (e) the intervals for rest
and meals to which he is entitled; (f) the
days of rest to which he is entitled; (g) the
group, if any, in which he is included; (h)
where his group works on shifts, the relay
to which he is allotted; and (i) such other
particulars as may be prescribed by rules.
6.7 90. Maintenance of safety Record Book: In every
establishment factory wherein more than twenty
five workers are employed, shall maintain
compulsorily, in the prescribed manner, a safety
record book and safety board.
The factory operating with nearly 95 O&M workers
presently does not maintain a safety record book and
safety board to comply with this legal requirement.
Maintain both safety record book and
safety board in prescribed format for
operations as specified in the Bangladesh
Labour Law.
6.8 111. Notice of periods of work for adults and
preparation thereof : There shall be displayed
and correctly maintained in every establishment
in accordance with the provisions of section 337, a
notice of periods of work for adult workers
showing clearly the periods which adult workers
may be required to work.
Notice of period of works for adult workers has not
been displayed at the factory as required under the
Bangladesh Labour Law provision.
Ensure display of notice depicting the
work period for workers operating at
factory.
6.9 205. Participation committee : (1) The employer
in an establishment in which fifty or more
workers are normally employed shall constitute
The factory with an O&M workforce of 95 personnel
has not constituted a Participation Committee
comprising representatives of both employer and
Constitute a Participation Committee with
equal representation from both employer
and workers. The Participation Committee
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
65
S. No Regulatory Requirement Finding /Observation Risk Rating Recommendation
in the prescribed manner workers. The function of the Participation Committee
is to work towards improvement and maintenance of
safety, occupational health, welfare and working
condition at the factory.
to meet at least once in every two months
with proceedings of every meeting to be
submitted to the Director of Labour within
seven days of such meeting.
6.10 337. Abstracts of the Act, Rules and Regulations
to be displayed: (1) The employer of every
establishment shall cause to be displayed in a
conspicuous and accessible place at or near the
main entrance of the place of work or the
establishment, as the case may be, a notice in
Bangla containing an abstract of the important
provisions of this Act and of the rules and
regulation.
The Abstract of key provisions of Bangladesh Labour
Law, 2006 has not been displayed by the factory in
local language i.e. Bangla at the main entrance.
Ensure display of abstract of the key
provisions of the Bangladesh Labour Law
2006 in Bangla at the main entrance of the
factory.
6.11 47. Pressure plant.- (1) Every plant or machinery
other than working cylinder of prime movers
used in a factory, and operated at a pressure
greater than atmospheric pressure, shall be- (a) of
good construction, sound material, adequate
strength and free from any patent defect; (b)
properly maintained in a safe condition; (c) fitted
with- a suitable safety valve,
a suitable pressure gauge, a suitable stop valve
and a suitable drain cock or valve and (d)
thoroughly examined by a competent person-
The facility operates pressure vessels in the form of
air compressors, boilers, hydrogen and carbon
dioxide storage tanks. However since there
installation in 2015 these pressure vessels have not
been subjected to examination (both internal and
external) including hydraulic testing by a competent
person and records maintained in prescribed format
(Form No. 10).
Further the metal plate on the air compressors near
turbine building were not found to bear the following
information viz. design pressure and date of first and
subsequent hydrostatic testing. This is required
under Rule 6 of the Pressure Vessel Rules, 1995.
Engage a competent person to perform
examination of pressure vessels as per the
following frequency: (a) externally, once in
every period of six months, and (b)
internally, once in every period of twelve
months; and (c) hydraulic testing, at
intervals not more than four years.
Signed copies all examination undertaken
by competent person to be maintained in
Form No.10 for verification by the
Inspector, as and when required.
Ensure information related to test pressure
and hydrostatic test (both initial and
subsequent) is marked on all pressure
vessels at the factory.
6.12 52. Firefighting apparatus and water supply:
(9) Every worker of the factory should, as far as
possible, be trained in the use of portable fire
extinguishers subject to a minimum of at least
one-fourth of the numbers engaged separately in
each section of the factory.
(11) The Manager of the factory shall prepare a
detailed 'Fire Safety Plan' for proper enforcement
Documentation review reveals that the O&M
contractor has prepared and implemented specific
checklist for inspection of both fire extinguishers and
fire hydrant systems installed at the factory.
However O&M workforce has not been trained on
the proper usage of portable fire extinguishers as
required under this Law.
As discussed in the earlier ERM audit report the
Ensure at least 1/4th of the operational
workforce is adequately trained on the
usage of portable fire extinguishers.
Ensure the Fire & Life Safety Expert of the
O&M contractor formulates a Fire Safety
Plan on a fast track basis based on a
detailed fire safety assessment of the
factory.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
66
S. No Regulatory Requirement Finding /Observation Risk Rating Recommendation
of fire safety rules and for actions to be taken, in
proper sequence, in the case of a fire in the
factory.
factory has engaged a Fire & Life Safety Expert for
carrying out a detailed fire safety assessment of the
building followed by preparation of a Fire Safety
Plan. However the same is found to be pending
during the ERM audit team visit.
6.13 56. Ambulance room. (1) The ambulance room or
dispensary shall be in charge of a qualified
medical practitioner assisted by at least one
qualified compounder and nurse and such
subordinate staff as the Chief Inspector may
direct. The medical practitioner shall always be
available on call during working hours.
(6) The occupier of every factory shall, for the
purpose of removing serious cases of accident or
sickness, provide in the premises and maintain in
good condition a suitable transport unless he has
made arrangements for obtaining such a
transport from a hospital.
For operations a dedicated first aid room is available
at the factory which is being periodically visited by
paramedical officer/male nurse in comparison to
qualified medical practitioner required as per
Factories regulation. Also as observed the first aid
room is not found to be equipped with resources as
specified in the Factories Rules provisions. However,
it was confirmed by the management that there is a
local doctor available on call, who is also providing
his services in the company supported community
health centre. There is no provision of a dedicated
ambulance at site, however it was confirmed that a
dedicated vehicle will always be available at site to
address any serious case of accident or sickness to the
nearest medical facility
Equip the first aid room with resources as
prescribed in the relevant provisions of the
Bangladesh Factories Rules, 1979.
Maintain dedicated vehicle at the factory
premises for removing any serious cases of
accident or sickness to the nearest medical
facility.
6.14 100. Register of accidents and dangerous
occurrence.- The Manager of every factory shall
maintain a Register of all accidents and
dangerous occurrences which occur in the factory
in Form No. 28
The factory does not maintain a register of accidents
in Form 28 as specified under relevant provision of
the Factories Rules.
Maintain a register of accidents in Form 28
to comply with the Factories Rule
provision.
8 Electricity Rules, 1937
8.1 Rule 42, 45 & 49 of the Electricity Rules, 1937
Insulated rubber mats were not provided near the
high/medium voltage electrical panels at the turbine
building, fire pump house and electrical room of the
CCB building to serve for protection against electric
shock. Further display of danger signages on the
electrical panels and instruction for restoration of
persons suffering from electrical shock was lacking in
the CCB electrical room.
Ensure provision of rubber mats near all
high/medium voltage electrical panels.
Danger signages to be also displayed on all
such panels.
Ensure display of instructions in English
and Bangla for the restoration of persons
suffering from electrical shock at
conspicuous places within the factory
particularly in the electrical rooms.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
67
6 CORRECTIVE ACTION ITEMS
The corrective action items identified based on the assessment undertaken with respect to ESSMP, CAP, IFC ESAP commitments and labour audit & social monitoring performed has been presented in Table 6.1. This table also outlines the tentative timelines for completion of each of the action item as specified by SBIIPCL.
Table 6.1 Corrective Action Items List
S.
No. Action Item Responsibility[1] Completion Timeline[2]
A CAP, ESMMP & IFC ESAP
1 Implement LOTO checklist integral to the work ticket being issued for electrical maintenance
activities.
NEPC-S May 2016
2 Update the legal register to incorporate the conditions outlined in the applicable EHS permits
and national regulations. Regularly monitor and document the compliance status of this legal
register on a monthly basis.
NEPC-S July 2016
3 Ensure future bird surveys are specifically focussed on the transmission line stretch (~70m) and
outcome utilised for development of an Avifauna Management Plan, if required.
NPEC-S December 2016
4 Ensure thorough implementation of the training program in accordance to the annual training
calendar prepared for the year 2016
NPEC-S June 2016
5 Perform a training needs assessment study of the operational workforce and utilise the outcome
to develop and implement the training calendar.
SBIIPCL & NEPC-S August 2016
6 Update the Emergency Response Procedure for operations to include the components related to
emergency classification; defining ERT roles and responsibilities; resource availability;
interfacing with offsite emergency responders; contact details of emergency responders;
induction for workers/visitors; training on emergency response and community disclosure of
potential emergencies/risks.
SBIIPCL & NEPC-S August 2016
7 Update the PPE checklist to include provision for assessing and evaluating the condition of PPE
in use by the workforce.
NEPC-S June 2016
8 Update the training presentation based on the training needs assessment study to be undertaken
for operations.
SBIIPCL July 2016
9 Simplify and update the Incident Reporting Process flow diagram to recognize the roles of both
NEPC and SBIIPCL EHS personnel in the overall reporting and investigation process.
SBIIPCL & NEPC-S July 2016
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
68
S.
No. Action Item Responsibility[1] Completion Timeline[2]
10 Perform monthly monitoring of the Operations ESMMP implementation with findings to be
shared with NEPC-S as part of monthly EHS meetings for closure
SBIIPCL July 2016
11 Perform quarterly monitoring of NOx at Parkul, Bongaon and Paharpur quarterly basis within 3
months of operation
SBIIPCL/NEPC-S June 2016
12 Undertake recalibration of the continuous ambient air quality monitoring stations (CAAQMS) NEPC-S August 2016
13 Commence with ambient noise monitoring at Paharpur and Parkul village locations on a
quarterly basis as specified in the ESMMP.
SBIIPCL/NEPC-S July 2016
14 Improve the laboratory infrastructure through procurement of relevant analytical
equipment/facilities for monitoring the key environmental parameters viz. BOD, TSS, TDS and
Oil & Grease.
NEPC-S July 2016
15 Conduct quarterly monitoring of all inland water discharge parameters specified in Schedule 10
of the Bangladesh ECR, 1997 to check for conformance and also to assess ETP performance
SBIIPCL/NEPC-S June 2016
16 Update the river water quality monitoring program to include DO and Total Coliform as
specified in Schedule 3 – Standards for Inland Surface Water of Bangladesh ECR, 1997
NEPC-S July 2016
17 Update the Waste Management Procedure to include all notifiable hazardous waste streams and
their management measures. Regularly maintain a waste inventory for all wastes identified in
the Waste Management Procedure.
SBIIPCL & NEPC-S June 2016
18 Execute a waste disposal contract/agreement with Lafarge Chatak facility to facilitate disposal
of used/waste oil. Identify third party vendors for disposal of other important hazardous waste
streams; audit the facilities of waste disposal vendors prior to executing a contract.
NEPC/SBIIPCL June 2016
19 Update the Caustic & Acid Handling Procedure based on the review of chemical usage
requirements for operations.
SBIIPCL June 2016
20 Document the visual checks for erosion monitoring in the form of a monthly report providing a
comparative time-series analysis.
SBIIPCL July 2016
21 Ensure provision of spill kits and display of warning and PPE requirements at the acid and
alkali storage areas. Periodic inspection to be undertaken for all chemical emergency response
equipment and records maintained for verification.
NEPC-S June 2016
22 Develop a consolidated EHS Plan for operations and the same to be shared with all sub-
contractors for agreement.
SBIIPCL/NEPC-S September 2016
23 Induction training modules to be developed and implemented for both operational workforce
and visitors.
NEPC-S July 2016
24 Facilitate initial medical examination for the remaining operations workforce and fitness
certificate issued to be maintained for verification.
NEPC-S July 2016
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
69
S.
No. Action Item Responsibility[1] Completion Timeline[2]
25 Ensure full participation of the operational workforce during implementation of the quarterly
mock drills being undertaken. Further an inspection checklist to be developed and implemented
for fire hose reels and records for the same maintained
SBIIPCL/NEPC-S June 2016
26 Perform a site assessment study to identify any potential environmental issues/concerns related
to decommissioning of temporary site offices and construction equipment and accordingly
develop an action plan for managing the same.
SBIIPCL December 2016
27 Organogram for both SBIIPCL and NEPC-S are interlinked with performance indicators and
training needs identified for implementation of ESMMP for operations.
SBIIPCL July 2016
28 Formulate a Pest Management SOP on a fast track basis in order to comply with the March end timeline specified in the ESAP.
SBIIPCL June 2016
29 Formulate a ODS usage SOP on a fast track basis in order to comply with the March end timeline
specified in the ESAP.
SBIIPCL June 2016
30 Engage a qualified and experience agency/expert on a fast track basis to perform a QRA study
of the project operational risks.
SBIIPCL July 2016
31 Develop a disclosure plan for communicating the project operational risks/hazards to the
nearby communities.
SBIIPCL July 2016
32 Undertake assessment of the project fire safety risks and preparedness for operations and the
outcome utilised for development of a Corrective Action Plan (CAP)
SBIIPCL June 2016
33 Finalise the green belt development for the project site on a fast track basis. SBIIPCL July 2016
34 Engage a third party vendor under an annual maintenance contract improve green belt species
survival rate.
SBIIPCL September 2016
B EHSS Legal Compliance
1 Update the EPR to include discussion on the compliance status of the EC conditions. SBIIPCL July 2016
2 Obtain clarification from the competent authority regarding condition related to boiler operator
certification.
SBIIPCL July 2016
3 Share design document of HSD tanks to assess the compliance status related to provision of vent
pipes/approved relief valves.
SBIIPCL July 2016
4 Update chemical inventory sheet to include storage and supply details of HSD. NEPC-S June 2016
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
70
S.
No. Action Item Responsibility[1] Completion Timeline[2]
5 Obtain license from Department of Explosives, Bangladesh for additional storage of 1.36KL of
diesel within the factory premises.
SBIIPCL June 2016
6 Obtain and check validity of license issued by Department of Explosives, Bangladesh for the
vendor involved in bulk transportation of diesel at the factory.
NEPC-S June 2016
7 Ensure the diesel storage tanks are conspicuously marked with their capacity as required under
Petroleum Rules.
NEPC-S July 2016
8 Ensure provision of effective electrical connection for the diesel storage tank near the fire pump
house for earthing purpose.
NEPC-S June 2016
9 Engage a competent person to perform annual examination of overhead travelling cranes and
maintain records of such examination in Form 9.
NEPC-S December 2016
10 Engage a competent person to perform examination of hoist and lifts in use at the facility to
specify the safe working loads. Ensure such examination of lifting equipment is undertaken on a
six monthly basis.
NEPC-S December 2016
11 Identify and train at least 1/4th of the O&M workforce on first aid treatment as per the
Bangladesh Labour Law provision.
NEPC-S May 2016
12 Ensure display of provision of spill kits at the designated storages for acid, alkalis and
hazardous waste. Provide secondary containment at the hazardous waste storage to control any
accidental spills/releases to the storm water drain nearby.
NEPC-S June 2016
13 Maintain a register of workers in Form 14 as prescribed in the Bangladesh Labour Law, 2006. NEPC-S July 2016
14 Maintain both safety record book and safety board in prescribed format for operations as
specified in the Bangladesh Labour Law. Ensure display of notice depicting the work period for
workers operating at factory.
NEPC-S Immediate
15 Engage a competent person to perform examination of pressure vessels as per the following
frequency: (a) externally, once in every period of six months, and (b) internally, once in every
period of twelve months; and (c) hydraulic testing, at intervals not more than four years.
Records of all examinations to be maintained in Form 10
NEPC-S December 2016
16 Display information related to test pressure and hydrostatic test (both initial and subsequent) is
marked on all pressure vessels at the factory.
NEPC-S September 2016
17 Ensure at least 1/4th of the operational workforce is adequately trained on the usage of portable
fire extinguishers.
NEPC-S July 2016
18 Ensure the Fire & Life Safety Expert of the O&M contractor formulates a Fire Safety Plan on a
fast track basis based on a detailed fire safety assessment of the factory.
NEPC-S July 2016
19 Equip the first aid room with resources as prescribed in the relevant provisions of the
Bangladesh Factories Rules, 1979.
NEPC-S July 2016
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
71
S.
No. Action Item Responsibility[1] Completion Timeline[2]
20 Maintain dedicated vehicle at the factory premises for removing any serious cases of accident or
sickness to the nearest medical facility.
NEPC-S July 2016
21 Ensure provision of rubber mats near all high/medium voltage electrical panels. Danger
signages to be also displayed on all such panels. Display of instructions in English and Bangla
for the restoration of persons suffering from electrical shock at conspicuous places within the
factory
NEPC-S July 2016
Note: [1] Overall responsibility of ensuring compliance to the action items associated with NEPC-S will be of SBIIPCL and SBIIPCL should communicate the action
items with NEPC-S as well as monitor the compliance on a regular basis. [2] Compliance timelines have been discussed with SBIIPCL and agreed.
ENVIRONMENTAL RESOURCES MANAGEMENT SUMMIT BIBIYANA II POWER COMPANY LIMITED (SBIIPCL)
#0265459/I10515 – 4TH EHS&S COMPLIANCE ASSESSMENT – CONSTRUCTION PHASE JUNE 2016
72
7 CONCLUSION
SBIIPCL has commenced with the single cycle operation on 6 June with COD
for combined cycle operations being declared on 28 December 2015. China
Northeast Electric Power Engineering and Services Co. Ltd (NEPC-S) has been
engaged as the Operations and Maintenance (O&M) Contractor. However,
EPC Contractor will still be responsible for all sorts of construction,
maintenance and operation of the power plant. O&M Contractor will
commence with their activities following handing over the project to them by
the EPC Contractor.
With project now in combined cycle operations, SBIIPCL compliance to
operational EHSS requirements has been assessed to be satisfactory. However,
continued efforts need to be made by SBIIPCL towards tracking regulatory
and operations ESMMP compliance on a regular basis, through development
of a register comprising of all permit and ESMMP conditions (particularly
with respect to environmental monitoring). For operations, other key focus
area for SBIIPCL includes - development of a dedicated fire safety plan and
community disclosure plan for operational risks, ensuring scientific disposal
of hazardous waste, performing QRA study and facilitating coverage of entire
operations workforce for initial medical examination.
With operations now in full swing, it is crucial for both SBIIPCL and its
contractors to apprise the workforce on the EHSS requirement for this phase
(particularly operations ESAP) and sustain with the efforts being made to stay
in compliance. The compliance status with respect to the corrective action
items as outlined in the earlier section will be verified during the next visit to
be undertaken by ERM.
Annex A
Photo-Documentation
Photo-documentation
ERM India Private Limited Building 10, 4th Floor, Tower A, DLF Cyber City
Gurgaon – 122 002, India Board: +91- 0124 4170300 Fax: + 91-0124 - 4170301
Photo 2:
0265459 – Fourth EHS&S Compliance Audit – Construction Phase (Bibiyana II)
Summit Bibiyana II Power Company Limited (SBIIPCL), Bangladesh
Photo 1: Insulated rubber mats absent in front of electrical panels at CCB building electrical room
Photo 2: Display of certified first aider details near first aid boxes
Photo 3: Display of emergency contact information at conspicuous places
Photo 4: Licensed CO2 storage installation Photo 5: DM Water Storage Tanks Photo 6: Metallic ropes used for lifting observed to be damaged
Project:
Client :
Photo-documentation
ERM India Private Limited Building 10, 4th Floor, Tower A, DLF Cyber City
Gurgaon – 122 002, India Board: +91- 0124 4170300 Fax: + 91-0124 - 4170301
Photo 2:
0265459 – Fourth EHS&S Compliance Audit – Construction Phase (Bibiyana II)
Summit Bibiyana II Power Company Limited (SBIIPCL), Bangladesh
Photo 7: Safe working load not displayed for lifting tools and tackles
Photo 8: Hydrogen storage installation Photo 9: Diesel Storage tank without proper labelling, containment and spill kit provision
Photo 10: Air compressor tanks lacking display of design pressure and hydrostatic test details
Photo 11: Eye wash stations installed and operating at the Alkali & Acid Storage area
Photo 12: Designated onsite Hazardous Waste Storage Shed
Project:
Client :
Photo-documentation
ERM India Private Limited Building 10, 4th Floor, Tower A, DLF Cyber City
Gurgaon – 122 002, India Board: +91- 0124 4170300 Fax: + 91-0124 - 4170301
Photo 2:
0265459 – Fourth EHS&S Compliance Audit – Construction Phase (Bibiyana II)
Summit Bibiyana II Power Company Limited (SBIIPCL), Bangladesh
Photo 13: Display of PPE requirement onsite Photo 14: Hazardous waste storage drums lacking containment and spill kit provision
Photo 15: Implementation of color coded bins for storage of designated waste
Photo 16: Fire Pump Room onsite Photo 17: Coloured discharges into the Khusiyara River from common effluent discharge point
Photo 18: Transformer Yard onsite
Project:
Client :
ERM consulting services worldwide www.erm.com
ERM has over 140 offices
Across the following
countries worldwide
Argentina Netherlands
Australia Peru
Belgium Poland
Brazil Portugal
China Puerto Rico
France Singapore
Germany Spain
Hong Kong Sweden
Hungary Taiwan
India Thailand
Indonesia UK
Ireland USA
Italy Venezuela
Japan Vietnam
Korea
Malaysia
Mexico
ERM India Private Limited
Building 10, 4th Floor
Tower A, DLF Cyber City
Gurgaon NCR – 122 002
India
Tel : 91-124-4170300 Fax: 91-124-4170301 Email: [email protected] www.erm.com