environmental assessment report...the environmental impact assessment is a document of the borrower....

315
The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “Terms of Use” section of this website.” Environmental Assessment Report Full Environmental Impact Assessment Report Project Number: 41627-05 June 2011 IND: Himachal Pradesh Clean Energy Development Investment Program – Tranche 4 Prepared by WAPCOS Limited for Himachal Pradesh Power Corporation Ltd.

Upload: others

Post on 19-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “Terms of Use” section of this website.”

Environmental Assessment Report

Full Environmental Impact Assessment Report Project Number: 41627-05 June 2011

IND: Himachal Pradesh Clean Energy Development Investment Program – Tranche 4

Prepared by WAPCOS Limited for Himachal Pradesh Power Corporation Ltd.

Page 2: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

WAPCOS Centre for Environment

TABLE OF CONTENTS

CHAPTER-1: INTRODUCTION 1.1 GENERAL 1-1

1.2 NEED FOR THE PROJECT 1-1

1.3 POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK 1-4

1.4 SCOPE OF THE EIA STUDY 1-4

1.5 STAGES IN AN EIA STUDY 1-4

1.6 OUTLINE OF THE REPORT 1-5

CHAPTER-2: PROJECT DESCRIPTION 2.1 GENERAL 2-1

2.2 ALTERNATIVES CONSIDERED 2-1

2.3 PROJECT FEATURES 2-2

2.4 PROJECT DESCRIPTION 2-6

2.5 OTHER WORKS 2-9

2.6 LAND REQUIREMENT 2-10

2.7 CONSTRUCTION EQUIPMENT 2-11

2.8 CONSTRUCTION MATERIAL REQUIREMENT 2-11

2.9 YEAR WISE CONSTRUCTION WORKERS 2-12

2.10 CONSTRUCTION PERIOD 2-14

CHAPTER-3: METHODOLOGY ADOPTED FOR THE EIA STUDY 3.1 INTRODUCTION 3-1

3.2 STUDY AREA 3-1

3.3 SCOPING MATRIX 3-1

3.4 DATA COLLECTION 3-2

3.5 SUMMARY OF DATA COLLECTION 3-8

3.6 IMPACT PREDICTION 3-8

3.7 ENVIRONMENTAL MANAGEMENT PLAN AND COST ESTIMATES 3-9

3.8 RESETTLEMENT AND REHABILITATION PLAN 3-9

3.9 CATCHMENT AREA TREATMENT PLAN 3-9

3.10 ENVIRONMENTAL MONITORING PROGRAM 3-10

CHAPTER-4 BASELINE SETTING FOR PHYSICO-CHEMICAL ASPECTS 4.1 GENERAL 4-1

4.2 METEOROLOGY 4-1

4.3 GEOLOGY 4-2

4.4 SEISMOLOGY 4-3

4.5 LAND USE PATTERN 4-5

Page 3: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

4.6 SOILS 4-7

4.7 WATER RESOURCES 4-9

4.8 WATER QUALITY 4-11

4.9 AMBIENT AIR QUALITY 4-14

4.10 NOISE ENVIRONMENT 4-19

Chapter 5: BASELINE SETTING FOR ECOLOGICAL ASPECTS 5.1 GENERAL 5-1

5.2 TERRESTRIAL ECOLOGY 5-1

5.3 AQUATIC ECOLOGY AND FISHERIES 5-16

CHAPTER – 6: SOCIO-ECONOMIC ASPECTS 6.1 INTRODUCTION 6-1

6.2 STUDY APPROACH 6-1

6.3 SOCIO-ECONOMIC PROFILE OF THE STUDY AREA 6-3

6.4 SOCIO-ECONOMIC PROFILE OF THE PROJECT 6-16

6.5 ACTIVITIES UNDERTAKEN UNDER R&R PLAN DURING 2009-2010 6-25

6.6 BUDGETS FOR RESETTLEMENT & REHABILITATION 6-27

CHAPTER-7: PREDICTION OF IMPACTS 7.1 GENERAL 7-1

7.2 IMPACTS ON WATER ENVIRONMENT 7-3

7.3 IMPACTS ON AIR ENVIRONMENT 7-8

7.4 IMPACTS ON NOISE ENVIRONMENT 7-10

7.5 IMPACTS ON LAND ENVIRONMENT 7-13

7.6 IMPACTS ON BIOLOGICAL ENVIRONMENT 7-23

7.7 IMPACTS ON SOCIO-ECONOMIC ENVIRONMENT 7-28

7.8 IMPACTS DUE TO CONSTRUCTION OF ROADS 7-30

Page 4: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

WAPCOS Centre for Environment

ABBREVIATIONS AND ACRONYMS

AAQM - Ambient Air Quality Monitoring

CAT - Catchment Area Treatment

CEIA - Comprehensive Environmental Impact Assessment CHC - Community Health Centre

DEM - Digital Elevation Model DPR - Detailed Project Report

EC - Electrical conductivity EIA - Environmental Impact Assessment

EIMU - Environmental Impact Management Unit EMP - Environmental Management Plan

FCC - False Color Composite

FRL - Full Reservoir Level

PFR - Pre-Feasibility Report GIS - Geological Information System

GHNP - Great Himalayan National Park

GOI - Government of India

GPP - Gross Primary Productivity

HEP - Hydroelectric Project

HRT - Head Race TunnelHPSEB - Himachal Pradesh State Electricity Board

IDC - Interest During Construction IMD - India Meteorological Department

MDDL - Minimum Draw Down Level

MOEF - Ministry of Environment and Forests MOWR - Ministry of Water Resources MOU - Memorandum of Understanding

MU - Million Units

MW - Mega Watt NOC - No Objection Certificate NOx - Nitrogen Oxides NPRR - National Policy for Resettlement & Rehabilitation PAP - Project Affected People

PAF - Project Affected Families NRSA - National Remote Sensing Agency

Page 5: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

PHC - Primary Health Centre

ROR - Record of Rights

R&R - Resettlement & RehabilitationRPM - Respirable Particulate Matter

SAV - Study Area Village

SPCB - State Pollution Control Board

SPL - Sound Pressure LevelSPM - Suspended Particulate Matter

SPSS - Statistical Package for Social Sciences SO2 - Sulphur dioxide

STP - Sewage Treatment Plant

SYI - Silt Yield Index

TRT - Tail Race Tunnel

TDS - Total Dissolved Solids

WAPCOS - Water and Power Consultancy Services (I) Limited

Page 6: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 1-1

CHAPTER-1

INTRODUCTION

1.1 GENERAL The Kinner Kailash Power Corporation Limited (KKPCL) promoted by Himachal Pradesh State Electricity Board (HPSEB) has been renamed as Himachal Pradesh Power Corporation Limited (HPPCL). The HPPCL is the joint venture between the Government of Himachal Pradesh (GoHP) and Himachal Pradesh State Electricity Board (HPSEB). The HPPCL proposes to develop the Shongtong–Karchham Hydro Electric Project on river Satluj in district Kinnaur of Himachal Pradesh. The project is envisaged as a run-of-river (RoR) Scheme on river Satluj in district Kinnaur, Himachal Pradesh. The barrage site is located near village Powari and the power house is proposed to be located near village Ralli on left bank of river Satluj near confluence of river Bapsa with river Satluj. The installed capacity of Shongtong-Karchham hydro-electric project shall be 450 MW. The barrage site is located near village Powari and the power house is proposed to be located near village Ralli on NH-22 about 200 km from Shimla. The project location map along with revenue village’s boundaries and population outline enclosed as Figure-1.1. 1.2 NEED FOR THE PROJECT The installed power generation capacity in India was 1,362 MW in 1947 which increased to 64,729 MW in 1990. In spite of the significant growth, power demand has always outstripped the supply. At the end of the 10th plan, shortfall in energy availability on an all India basis is given as per Table 1.1. Table 1.1: 10th Plan, shortfall in energy availability on an all India basis Year Requirement Availability Surplus(+)/

Shortage (-) Surplus/Shortage %

Peak (MW) 2006-07 100,715 86,818 -13,897 -13.8 Energy (MU) 2006-07 690,587 624,495 -66,092 -9.6

Source: Data Management and Load Forecasting (DMLF) Division, Central Electricity Authority Based on 10th Plan actual capacity addition of 21,180 MW, a capacity addition of 78,577 MW comprising of 39,865 MW (50.7%) in central sector, 27,952 MW (35.6%) in State sector and 10,760 MW (13.7%) in private sector has been proposed during 11th Plan. Table 1.2 gives the capacity addition proposed during 11th five year plan. Table 1.2: Capacity addition proposed during 11th five year Plan Hydro Thermal Thermal Breakup Nuclear Total

Coal Lignite Gas A. Projects Commissioned Central Sector 0 0 0 0 0 220 220 ALL-INDIA 0 0 0 0 0 220 220 B. Projects Under Construction Central Sector 8,565 12,680 11,190 750 740 3,160 24,405 State Sector 3,075 13,947 12,735 450 762 0 17,022 Private Sector 2,791 4,737 2,700 0 2,037 0 7,528

Page 7: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 1-2

Hydro Thermal Thermal Breakup Nuclear Total Coal Lignite Gas

ALL-INDIA 14,431 31,364 26,625 1,200 3,539 3,160 48,955 C. Committed Projects (Orders yet to be placed) Central Sector 1,120 14,120 13,120 250 750 0 15,240 State Sector 530 10,400 10,400 0 0 0 10,930 Private Sector 472 2,760 2,760 0 0 0 3,232 ALL-INDIA 2,122 27,280 26,280 250 750 0 29,402 D. Total Central Sector 9,685 26,800 24,310 1,000 1,454 3380 39,865 State Sector 3,605 24,347 23,135 450 762 0 27,952 Private Sector 3,263 7,497 5,460 0 2,037 0 10,760 ALL-INDIA 16,553 58,644 52,905 1,450 4,289 3,380 78,577

Source: DMLF Division, Central Electricity Authority Status of Hydro Projects in 11th Plan; The status of Hydro Projects totaling to 16,553 MW included in 11th Plan is as under: • 14,431 MW (87%) are under construction. • 1,537 MW (9.5%) have been accorded concurrence by Central Electricity Authority

(CEA)/State Government and are awaiting investment decision/work award. • 585 MW (3.5%) the DPR is ready and concurrence by CEA/State Government is

awaited. Besides capacity addition, a strong inter-state and inter regional transmission system has also been planned not only to evacuate the planned generation capacity but also to provide open access for transfer of power from surplus to deficit area. The hydro power potential of Himachal Pradesh is surplus for its own requirement. The surplus power is made available to meet the power and energy requirements in other parts of the country, through northern grid. Therefore, it is necessary to look into energy and power requirements of the northern region while planning hydropower development in Himachal Pradesh. The All India region wise generating installed capacity (MW) of power utilities including allocated shares in joint and central sector utilities are given in Table-1.3. Table 1.3: Captive generating capacity (As on 31.01.2010)

Sl. No.

Region Thermal Nuclear Hydro R.E.S @ (MNRE)

Total Coal Gas Diesel TOTAL Renewable

1 Northern 23,620.00 3,813.26 12.99 27,446.25 1,620.00 13,622.75 2,777.32 45,466.32

2 Western 29,290.50 8,143.81 17.48 37,451.79 1,840.00 7,447.50 4,918.28 51,657.57 3 Southern 19,172.50 4,690.78 939.32 24,802.60 1,100.00 1,1260.03 8,517.55 45,680.18 4 Eastern 17,635.38 190.00 17.20 17,842.58 0.00 3,882.12 344.41 22,069.11 5 North

Eastern 60.00 787.00 142.74 989.74 0.00 1,116.00 223.32 2,329.06

6 Islands 0.00 0.00 70.02 70.02 0.00 0.00 6.10 76.12 7 All India 89,778.38 17,624.85 1,199.75 108,602.98 4,560.00 37,382.40 16,786.98 167,278.36

Captive generating capacity connected to the Grid (MW) = 19,509 Source: DMLF Division, Central Electricity Authority. @ R.E.S = Renewable Energy Sources includes Small Hydro Power Projects, Biomass Gas, Biomass Power, Urban and industrial waste power and Wind Energy.

Page 8: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 1-3

Chenab, Ravi, Beas, Satluj and Yamuna are the five major rivers of western Himalaya which pass through the Himachal Pradesh, having total hydel potential of 23,000 MW. The Satluj basin has the hydel potential of around 11,104 MW, followed by the Beas basin with 4,902 MW, the Chenab basin of 3,045 MW, the Ravi Basin with 3,105 MW and the Yamuna basin with 842 MW. Included within this is the 1,427 MW potential is under Himurja where projects, 267 MW by IPPs and 2,069 MW by HPSEB. The breakup of the total estimated Hydro Power Potential of Himachal Pradesh upto year 2025 is given in Table 1.4. Table 1.4: Hydro Power Potential of Himachal Pradesh

River Basin Assessed Potential (MW) Additional Potential identified by Total Potential

(MW) HIMURJA IPP HPSEB

Yamuna 598 201 43 - 842

Satluj 9,995 324 148 636 11,104

Beas 3,652 472 76 700 4,902

Ravi 2,284 366 - 453 3,105

Chenab 2,703 61 - 280 3,045

Total 19,235 1,427 267 2069 23,000 Source: HPPTCL Master Plan 2010. Transmission System The transmission system in the country at the end of 10th Plan (as on 31.03.2007) at 220 kV and above was 198,089 circuit km (Ckm) of transmission lines, 251,439 MVA of EHV substation capacities and 8,200 MW of HVDC. Voltage level wise details are given in Table 1.5.

Table 1.5: Summary of Transmission Capacity as on 31.03.2007

Transmission Lines Unit Quantity 765 kV Ckm 1,704 HVDC + 500 kV Ckm 5,872 HVDC Ckm 162 400 kV Ckm 75,722 230/220 kV Ckm 114,629 Total Transmission Line Ckm 198,089 Substations MW / MVA HVDC BTB MW 3,000 HVDC Bipole + Monopole MW 5,200 Total – HVDC Terminal Capacity MW 8,200 765 kV MVA 2,000 400 kV MVA 92,942 230/220 kV MVA 156,497 Total – EHV Substation Capacity MVA 251,439

Page 9: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 1-4

1.3 POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK A Comprehensive Environmental Impact Assessment (CEIA) report is prerequisite for obtaining Environmental Clearance. HPPCL has awarded the work for Environmental Impact Assessment Study for the above mentioned project to Water and Power Consultancy Services (India) Limited (WAPCOS), a Government of India Undertaking vide letter No KKPCL /DP/ SHONGTONG-KARCHHAM /EIA & EMP- CONTRACT /Vol-II/07-1979-1800 dated 29/12/07. The Agreement for implementation of the study was signed on 30.01.2007. The principal Environmental Regulatory Agency in India is the Ministry of Environment and Forests (MOEF), Government of India. MOEF formulates environmental policies and accords environmental clearance for the projects. The State Pollution Control Board (SPCB) accords No Objection Certificate (NOC) for Consent to Establish and Consent to Operate for the projects. As per the guidelines pertaining to Environmental clearance issued by Ministry of Environment and Forests (MoEF) dated September 14, 2006, the Terms of Reference (TOR) for the EIA study to be approved by MoEF. In this connection Form-I along with TOR in the prescribed format was submitted to MoEF. The same was reviewed by the Environmental Appraisal Committee of River Valley Projects of MoEF, and the TOR for the EIA study was approved. A copy of the approved Terms of Reference for the CEIA study is enclosed as Annexure-1.1. 1.4 SCOPE OF THE EIA STUDY The brief scope of EIA study includes: • Assessment of the existing status of physico-chemical, ecological and socio-economic

aspects of environment. • Identification of potential impacts on various environmental components due to activities

envisaged during construction and operation phases of the proposed hydro-electric project. • Prediction of significant impacts on major environmental components using appropriate

mathematical/simulation models. • Delineation of Environmental Management Plan (EMP) outlining measures to minimize

adverse impacts during construction and operation phases of the proposed project. • Formulation of Resettlement and Rehabilitation (R&R) Plan. • Formulation of Catchment Area Treatment (CAT) Plan. • Formulation of environmental quality monitoring programmes for implementation during

construction and operation phases. • Estimation of Cost for implementation of Environmental Management Plan, Resettlement &

Rehabilitation Plan, Catchment Area Treatment Plan and Environmental Monitoring Program.

1.5 STAGES IN AN EIA STUDY The purpose of this section is to enumerate the steps involved in an Environmental Impact Assessment (EIA) study, which are described in the following paragraphs. Scoping : An exhaustive list of all likely impacts drawing information from as many sources as possible was prepared. The next step was to select a manageable number of attributes which were likely to be affected as a result of the proposed project. The various criteria applied for selection of the important impacts were follows: • Magnitude; • Extent; and • Significance.

Page 10: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 1-5

Description of Environment: Before the start of the project, it is essential to ascertain the baseline levels of appropriate environmental parameters which could be significantly affected by the implementation of the project. The baseline status assessed as a part of CEIA study for the proposed Shongtong-Karchham hydroelectric project involved both field work and review of data collected from various secondary sources. Prediction of Impacts: is essentially a process to forecast the future environmental conditions of the project area that might be expected to occur as a result of the construction and operation of the proposed Shongtong-Karchham hydroelectric project. An attempt was made to forecast future environmental conditions quantitatively to the extent possible. However, for intangible impacts, qualitative assessment has been made so that planners and decision-makers were aware of their existence as well as their possible implications. Environmental Management Plan: the approach for formulation of an Environmental Management Plan (EMP) is to maximize the positive environmental impacts and minimize the negative ones. The steps suggested as a part of EMP include modifications of plans, engineering designs, construction schedules and techniques, as well as operational and management practices. After selection of suitable environmental mitigation measures, cost required for implementation of various management measures has also been estimated as a part of the present study. Environmental Monitoring Program: An Environmental Monitoring Programme for monitoring of critical parameters during project construction and operation phases has been prepared as a part of the CEIA study to oversee the environmental safeguards, to ascertain the agreement between prediction and reality. The monitoring programme also helps in suggestion of remedial measures not foreseen during the planning stage but arising during construction and operation phases. The exercise will also generate data for future use and serve as a reference for assessment of impacts of hydropower projects in similar settings. 1.6 OUTLINE OF THE REPORT The document for the Comprehensive EIA study for the proposed Shongtong hydroelectric project has been presented in two volumes. Volume-I presents the Environmental Impact Assessment (EIA) study and Volume-II delineates the Environmental Management Plan. The present document (Volume-I) outlines the findings of the EIA study for the proposed Shongtong Karchham hydroelectric project. The contents of the document are organized as follows: Chapter - 1. The Chapter gives an overview of the need for the project. The policy, legal and

administrative framework for environmental clearance has been summarized. The objectives and need for Comprehensive EIA study too have been covered.

Chapter - 2. Gives a brief description of the proposed Shongtong Karchham hydroelectric project.

Chapter - 3. Outlines the methodology adopted for conducting the Comprehensive EIA study for the proposed Shongtong hydroelectric project.

Chapter - 4. Covers, the environmental baseline conditions physico-chemical and biological aspects of the area. The baseline study involved both field work and review of

Page 11: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 1-6

existing documents, which are necessary for identification of data which may already have been collected for other purposes.

Chapter - 5. Presents the biological aspects of environment. The study is based on collection of data from various secondary data sources. As a part of the Comprehensive EIA study, detailed ecological survey was conducted for three seasons. The findings of the ecological survey were analysed and ecological characteristics of the study area have been covered in this Chapter.

Chapter - 6. Delineates the pre-project environmental baseline conditions vis-a-vis socio-economic aspects of environment. The baseline study involved data collection using primary as well as secondary sources.

Chapter - 7 Describes the anticipated positive and negative impacts as a result of the construction and operation of the proposed Shongtong-Karchham hydro-power project. It is essentially a process to forecast the future environmental conditions of the project area that might be expected to occur as a result of the construction and operation of the proposed project. An attempt has been made to forecast future environmental conditions quantitatively to the extent possible. But for certain parameters, which cannot be quantified, qualitative assessment has been done so that planners and decision-makers are aware of their existence as well as their possible implications.

Page 12: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 1-7

Figure – 1.1: Project Location with village boundary map

Page 13: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board
Page 14: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board
Page 15: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board
Page 16: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board
Page 17: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board
Page 18: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board
Page 19: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-1

CHAPTER-2

PROJECT DESCRIPTION

2.1 GENERAL The Shongtong-Karchham Hydro Electric Project is proposed to be commissioned on river Satluj in district Kinnaur of Himachal Pradesh. The project envisages as a run-of-river Scheme on Satluj River in district Kinnaur of Himachal Pradesh. The proposed barrage site is near village Powari and the power house is proposed to be located near village Ralli on left bank of river Satluj near confluence of river Bapsa with Satluj. The Shongtong-Karchham hydro-electric project is proposed to generate 450 MW of energy. The L – section and list of other hydroelectric projects in Satluj basin are shown in Figure 2.1 and 2.2. The details of Associated Hydro power projects which are downstream of Shongtong-Karchham 450 MW HEP on river Satluj are Baspa-II (300 MW) and Karchham-Wangtoo HEP (1000 MW) for which appropriate environment clearances have been taken by project promoter which are enclosed as Annexure 2.1. The salient feature of Thopan–Powari HEP which is immediate u/s of the Shongtong - Karchham Project is enclosed as Annexure 2.2. These are as per the PFR prepared following CEA requirement under the PM’s 50,000 MW initiative program. 90% dependable series for the project is also enclosed as Annexure 2.3. 2.2 ALTERNATIVES CONSIDERED As per the Preliminary Master Plan studies carried out for harnessing the hydel potential of Satluj river between Shongtong and Karchham, two dam sites were identified at Shongtong (bridge). However as per the Revised Master Plan studies carried out in association with Swed Power of Sweden under assistance from Swedish Government, it was pointed out that a bigger Earth and Rockfill dam is feasible just upstream of confluence of Tangling khad with Satluj river. Various alternative proposals studied for the project are described in the following paragraphs. Alternative-I In this alternative, the dam site was proposed near Shongtong bridge. Though this was the ideal site from engineering point of view, the same had to be abandoned due to administrative problems. The site was located close to the defense installation; as a result, the site was abandoned. Alternative-II Left bank alternative with dam site just near the confluence of Tangling khad with Satluj river. At this site, there is a well defined vertical rock on the left bank but no rock exposures on the left bank of the river, but the exposures are at higher elevations. To know the depth of rock one drill hole was drilled, which showed a overburden of more than 50 m. In view of the presence of more than 50 m thickness of overburden in the valley, presence of large landslides overlooking the site on the left abutment, and occurrence of large debris fan just downstream of dam axis on the left flank which could interfere with the alignment of HRT and other appurtenant structures, the site was abandoned and the possibility of locating a dam upstream was explored.

Page 20: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-2

Alternative-III A dam site just downstream of steel truss bridge where there is a vertical left bank and exposure of rock on the right bank was selected for a suitable dam. This proposal envisaged a location of water conductor system of the right bank of the river as gives the shortest length of the system. The sub-surface explorations carried out at the site through four drill holes along the dam axis indicated the depth of bedrock in the river bed varies between 16.5 to 66.5 m. The bed rock is buried deeper on the right bank. Therefore, this site was not found suitable for a high dam and the possibility of a barrage as a diversion structure was studied. In order to assess the thickness of overburden and limit of slumping on right bank, subsurface explorations, comprising one exploratory drift and one drill hole on the right bank was drilled. The explorations indicated that the limit of slumping falls beyond RD 60 m in the drift. The drill hole drilled, indicated the presence of overburden down to 42 m depth. The results of these explorations indicated that the right bank is not suitable for locating intake structure, approach tunnel to Desilting chamber and Desilting chamber itself. Alternative-IV Present proposal consists of intake/sedimentation chamber, HRT and power house located on the left bank of the river. The alternatives studied have been given in Figure 2.3. 2.3 PROJECT FEATURES 2.3.1 Salient feature of the Project The Shongtong-Karchham Hydro Electric Project has been envisaged with the purpose of exploiting the potential in the Satluj River between villages Powari and Ralli. The project envisages the construction of:

• Diversion barrage, intake structure with 4 intake bays with gates and four intake tunnels passing through four sedimentation chambers.

• Head Race Tunnel 8.02 km long culminating in open surface surge shaft. • Three circular steel lined underground pressure shafts to convey water to 3 francis

turbines to generate (3 x 150 MW) 450 MW of power in an underground power house. Earlier it was envisaged for 402 MW generation capacity, however, as per approved hydrology and advice of CEA the install capacity has been revised to 450 MW taking into consideration the hydrology more efficient turbine and generator improved flow with in project component and revised power studies. This does not entail any chance in levels, relocation of any component site, project component sizes requirement of land, other natural sources including felling of trees and generation of any additional muck, as such, the capacity enhancement achieved without any additional environmental impact.

• Tail Race Tunnel of 10.0 m dia and 90 m length to discharge flow into river Satluj near village Ralli.

The salient features of the project are given in Table-2.1.

Page 21: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-3

TABLE-2.1: Salient features of Shongtong-Karchham hydro-electric project Location State Himachal Pradesh District Kinnaur River Satluj Location Diversion barrage site near village Powari Power House site near village Ralli on NH-22

about 200 km from Shimla Hydrology Catchment area at barrage axis 47,132 sq km Maximum observed average 10 1,666 cumecs Daily discharge Design flood 6,819 cumecs Firm discharge for 90% availability 67.39cumecs 50% availability 131.88 cumecs Diversion Barrage Type Sloping Glacis Size 122.6m long at top of barrage Water Bay 87.0 m Top level of Barrage El. 1,958.00 m Full Reservoir Level (FRL) El. 1,956.00 m Maximum Pond Level El. 1,956.00 m Mean Draw Down Level (MDDL) El. 1,945.50 m Crest level El. 1,937.00 m Live storage 431 Ha m. Peaking 3.6 hrs River Bed Level at Barrage axis + El. 1,934.000 m Length of stilling basin 55.00 m Diversion Tunnel Type Circular concrete lined Size 10.0 m dia Length 1658.72 m Bed Slope 1 : 553 Intake structure No. of intake bays 4 Width of each bay 17.17 m Discharge through each bay 101.80 cumecs Crest level 1,938.00 m Minimum water level u/s El. 1,945.50 m No. of Intake Gates 4 Size 6.40m x 6.40 m Intake Tunnels No. of Intake Tunnels 4 Type Modified horse shoe Size 6.4 m Design discharge 487.2 cumecs Velocity 2.41 m/sec Sedimentation Chambers No. of sedimentation chambers 4 Width 15 m

Page 22: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-4

Depth 31 m Length 530 m Particle size to be arrested +0.20 mm Design discharge 487.2 cumecs Flow through velocity 0.22 m/s Silt Flushing Tunnels No. of tunnels from the sedimentation Chambers connected with main silt Flushing tunnel

4

Type D-shaped Diameter 3.0 m Length 70 m Main Silt Flushing Tunnel Type D-shaped, concrete lined Diameter 6.00 m Length 2010.00 m Design discharge 81.2 cumecs Head Race Tunnel Type Circular concrete lined Diameter 10.00 m finished Length 8,042.69 m Design discharge 406 cumecs Bed slope 1:280.61 Velocity 5.17 m/sec Adits No. of Adits 3 Type D-shaped Size 7.5 m Length 368.00 m (max.) Surge Shaft No. One Type Restricted Orifice (Underground) Diameter 35.0 m Orifice Dia. 5.54 Elevation of centre line of HRT 1905.00 m Elevation at invert of surge shaft 1900.00 m Top elevation 1,982.00 m Maximum upsurge level 1,978.00 m Minimum down surge level 1,919.34 m Pressure Shaft No. 3 Type Circular steel lined (Underground) Diameter 5.80 m (Finished) Length 240.00 m each Power House/Transformer Hall cavity Type Underground Installed capacity 450 MW (3 x 150 MW) Size of machine Hall 120m (L) x 19 m (W) x 40.10 m (H) Size of transformer Hall 120 m (L) x 18 m (W) x 28 m (H) Approach adit to machine hall 8.5 m D-shaped 218.95 m long

Page 23: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-5

Average gross head 142.50 m Net head 124.01 m Tail Race Tunnel Size & Type 10.00 m dia. Circular shape Length 99.66 m Normal tail water level 1,804.65 m Maximum tail water level 1,810.12 m Power Generation Installed capacity 450 MW Annual generation : 90% dependable Year 1,653.13 GWh 50% dependable year 1,887.23 GWh COST ESTIMATE (Rs. In Crores) Civil Works Rs. 1,455.65 Electro-Mechanical Works Rs. 823.51 Total base cost of Project Rs. 2,279.16 Crores (Dec, 2010 Price Level) Financial Aspects Cost per MW of installed capacity Rs. 3.77 crores Sale rate per unit (at bus bar) First year Rs. 3.31 per unit Tenth year Rs. 2.33 per unit Average for 10 years Rs. 2.82 per unit

2.3.2 Minimum Environmental Flow The length of river that have low flow will be 8.602 km. The project is expected to provide annual energy generation of about 1,735.5 MU in a 90% dependable year. Shongtong-Karchham (150 X 3 MW) HEP is run of the river scheme having three turbines of 150 MW each. It has peaking capability during low flow season i.e. in winter. This Lean flow season is considered between December to February. All turbines will operate 24 hours during high flow season from mid May to mid September. During low flow season, the project has been planned for a diurnal peaking of 3.40 hrs i.e 1.70 hrs in the morning and 1.70 hrs during evening peak hours. During lean season, turbines will operate only in the above mentioned peaking time. Only 8.88% of total generation is expected during three lean season months. During rest of the year, two turbines will normally operate with the third one also becoming occasionally operational. As per GoHP, Hydropower Policy 2007 (Annexure - 2.4), it has been made mandatory to release minimum flow of 15 percent (of average of the lean season flows) water immediately down-stream of the diversion structures to address issues concerning riparian rights, drinking water, health, aquatic life, wild life, fisheries, silt and even to honor the sensitive religious issues like cremation and other religious rites etc. on the river banks. Thus, it will be available between diversion structure and tailrace outlet, which gets augmented by contribution from the tributaries in the stretch of the river as shown in Figure - 2.4. The diagram also provides information on contribution by each tributary and cumulative discharge at confluence. The downstream discharge of 15 % (24 hours X 365 days) will be maintained at all times throughout the year. Downstream discharge will be maintained even while storing water for peaking purpose. Table 2.2 provides cumulative minimum environmental discharge in the river.

Page 24: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-6

Table 2.2 Cumulative Minimum Environmental Discharge in the River S. No Flow measurement point Progressive Discharge

(cumecss) Cumulative flow (cumecss)

1 Barrage axis 10.31 10.31 2 Tangling Khad 1.414 11.724 3 Shyang Khad 0.607 12.331 4 Meber Khad 0.152 12.483 Total Cumulative environmental flow 12.483 Cumecss A separate study has been commissioned by HPPCL to determine environment flow and HPPCL is committed to maintain the same, if it is higher than 15% downstream discharge. If it is lower than 15%, HPPCL shall maintain 15% discharge i.e. whichever is higher. The task has been assigned to the National Institute of Hydrology, Roorkee with following details. 1. The specific study under reference involves an estimation of environment flow required to

be released downstream of the point of diversion for maintaining aquatic life in the river. 2. The study will estimate Environment Flow Requirement (EFR) using hydrological methods

(Flow duration and modification) and make suitable recommendation for minimum environmental Flow.

3. Completion of environmental flow assessment study will take one year from the date of award of work, which has been awarded to NIH Roorkee on 30.09.2010. The results of the study will be submitted by December 2011.

Assessment of environmental flow was not a part of the approved ToR for EIA for this project. Assessed environmental flow is to be released during operation phase of the project. During operation phase there will be no flow obstruction only diversion of water through diversion tunnel. HPPCL commits to release the environmental flow as would be assessed by the NIH or 15% of lean-season discharge, whichever is higher. Findings of this study related to Environmental flow will be fed to designing aspect which cannot be done concurrently. Fish pass will be appropriately design suited for fish movement keeping the findings also in view. 2.3.3 Power Transmission As per the (CERC) Central Electricity Regulatory Commission norms, the hydropower generated from the HEP ≥ 250 MW has to be evacuated only by Power Grid Corporation of India Ltd (PGCIL) right from its powerhouse/switchyard. As per the new master plan 2010 for this basin (Figure – 2.5), to save the only available corridor, the 400 kV common line from Jangi 400/220 kV Pooling Station will now LILO on one circuit to the STKHEP (Shongtong-Karchham HEP) switchyard and then carry on to Sherpa Colony pooling point. This PGCIL transmission line coming from Jangi will carry power from other upstream projects like Chango-Yangthang HEP, Yangthang-Khab HEP, Jangi-Thopan HEP and Thopan-Powari HEP etc. This common line will be constructed by PGCIL at its own cost and STKHEP will pay only wheeling charges decided by CERC. Since the work for transmission lines has to be executed by Power Grid Corporation India Ltd. at their own cost. The budget provision for transmission line has been excluded from project cost.

Page 25: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-7

2.4 PROJECT DESCRIPTION The proposed Shongtong-Karchham hydropower project comprises of the following components:

• Diversion works. • Diversion barrage. • Intake & Sedimentation chamber. • Head Race Tunnel. • Surge tank. • Pressure shaft and Penstock. • Power house Complex. • Tail race works. • Hydraulic gates and valves. • Power house. • Sediment Flushing Tunnel.

The above components are briefly described in the following paragraphs.

i . Diversion works Keeping in view that there is overburden of more than 50 m in the river bed, and relatively moderately wide gorge, it is considered necessary to construct a diversion tunnel to permit uninterrupted construction of the barrage in its entire length during non-monsoon period. The diversion tunnel will be 10.00 m finished dia and 1,658.72 m in length. The upstream coffer dam will be 16 m high while downstream coffer dam will be 12 m high. Both the coffer dams will be of rock fill type with impervious core. Grouting will be carried out to make cut-offs up to the bed rock for both the upstream and downstream coffer dams in view of the permeability of the overburden material.

i i . Diversion barrage The diversion barrage is proposed about 100 m downstream of Foot Bridge on river Satluj. The top of barrage has been kept at EI 1,958.00 m while the deepest level will be at EI 1,919.00 m. The maximum and minimum pond levels have been kept at EI 1,956.00 m and EI 1,945.5 m respectively. The total storage available between these pond levels is 431ha m. as against requirement of 432 Ha m. for 3.6 hour peaking.

i i i . Intake and Sedimentation chamber Intake works have been proposed on the left bank. The intake has been designed for 487.2 cumecs discharge, 406 cumecs for power generation and 81.2 cumecs for flushing the sediment as the HRT and power house complex are located on this bank. There will be four intake bays with four corresponding sedimentation chambers. The intake will have its invert at EI 1938.00 m which is 1.5 m above the crest of under sluices.

i v . Head Race Tunnel (HRT) The length of HRT from exit end of sedimentation chambers and upto junction with surge shaft is 8042.69 meter. Based on optimization studies, tunnel size has been kept as 10.00 m dia

Page 26: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-8

circular tunnel. The maximum velocity in the tunnel will be 5.17 m/sec. For construction of HRT, two intermediate adits apart from adit at inlet end and adit at surge shaft end, have been provided. The length of adits varies between 100 m and 600 m.

v . Surge Tank A restricted orifice type open to sky surge shaft has been proposed at the end of HRT. The top of surge shaft has been kept at EI 1,982.00 m. The surge shaft will be of 5.54 m dia. up to EI 1,919.34 m and 35 m dia above this elevation. The orifice area required is 24.11 sq m which will be provided by an opening of 5.54 m dia in the centre. The surge shaft will be provided with reinforced concrete lining.

v i . Pressure Shafts and Penstock

The power house will be fed by 3 pressure shafts of 5.80 m dia. each. Each pressure shaft will negotiate a head of 128.5 m between centerline of HRT (1905.00m) and centre line of machine at El1, 814.65 m. The length of each pressure shaft will be 240.0m. The pressure shafts will be provided with steel liners in the entire length, the thickness of plate varying from 14 mm to 35 mm. The elevation of Pressure shaft at top level will be EL. 1905.80m.

v i i . Power House Complex

The powerhouse and transformer hall cavities are located on the left bank of river Satluj near village Ralli. The access to the machine hall and transformer hall will be through 8.5 m D-shaped adit of 218.95 m length. The powerhouse cavity will be 19 m wide, 40.10 m high and 120 m long. The powerhouse will have three vertical axis Francis turbines. The transformer hall cavity will be 18 m wide, 28m high, and 120 m long and will be parallel to PH Cavity. It will house the single phase transformers at El.1818.50 m and 400 kV GIS equipment at the floor at EI 1,828.50 m. The elevation of Power house at top level will be EL. 1834.65m.

v i i i . Tailrace Works The tailrace works will consist of a 99.66 m long tailrace tunnel of 10.00 m dia, Circular shape. An outlet structure with provision of gates has been provided at the exit end so that the tailrace works can be isolated when river is in high flood and power station is closed. The operation of draft tube gates at the junction of unit draft tubes and tail race tunnel will be carried out from a transformer hall cavity at EI 1,810.12 m.

i x . Flushing Tunnel Flushing works will consist of a 450 m long flushing tunnel of 5.00 m dia, Circular shape. Sediment flushing is to be done when we have sufficient discharge like during post-spring and during monsoon season. During monsoon season the sediment flushing will be done throughout the day as the silt quantity in river Satluj is very high. During, lean season the sediment flushing will be done once or twice in the week depending upon the discharge and silt. Since the discharge through flushing tunnel will be very less, no artificial flood like situation is likely to arise. Moreover, this river is not used for bathing or washing purposes. Habitations are located on the slopes well above the river and there are natural water springs and streams that cater to the need of people.

Page 27: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-9

x. Turbines The turbine shall be vertical shaft Francis type with adequate capacity to provide 153.061 MW at generator terminals and 10% continuous overload. Each turbine shall be provided with suitable oil pressure unit, electro hydraulic governor and other requisite control equipments. Shongtong Karchham H.E.P is located on river Satluj and its water carries high silt content during peak season, as experienced in case of Nathpa - Jhakri H.E.P which is also located on the same river.

In view of high silt contents and possibility of erosion of underwater parts, the optimum speed of the turbine has been selected as 166.67 rpm with suction head 4 meters below the minimum tail water level. The weighted average efficiency of turbine shall be 93%. The speed rise and pressure rise shall not be more than 35% of synchronous speed and 20% of maximum static head respectively. The runner shall be integrally forged or forged fabricated made of stainless steel having 13% chromium and 4% Nickel with maximum carbon content of 0.06% and minimum desired strength of 80 kg/sq mm. Runner and underwater parts shall be provided with suitable hard coating against hydro abrasion to ensure high reliability and long life. 2.5 OTHER WORKS The following components are to be constructed for the project purpose. The components are as follows. i) Improvement of existing national highway Realignment or relocation of the National Highway which was originally envisaged, is no longer needed as it has already been taken up by the agency concerned as part of their own departmental program which covers the whole length of the National Highway and not just the portion falling in the project area. As of today, this work is already underway and it is not to be done as part of project activity. Therefore, EIA of the proposed project not address this issue. Approach roads to Project components along with widening of road will be done in a stretch of 10.44 km. with a width of 5/7meters within the project area of 3 sq. km. The widening of road will help in smooth movement of traffic which will take care of increase in traffic due to project activity. The details are given in Table 2.3. Table 2.3: Approach roads to Project components Description and Name of Road Length Approx in km Widening of existing HPPWD road to 5/7 m. Wide from Shongtong bridge to Powari junction village

4.44

Approach road 5/7 m. Wide from Ralli village road to top and bottom of surge shaft, proposed explosive magazine site, temporary staff quarters, site office, Adit to bottom of pressure shaft and pot head yard and approach road to Adit-3 from NH-22

5.0

Approach road to quarry site at Powari 1.0

Land required for approach roads is going to be taken in possession after the forest clearance of the project. There will be no resettlement of local population due to construction or widening of these roads as these roads are project specific no adjoining settlement. Thus, no social impact is envisaged.

Page 28: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-10

Table 2.4: The proposed detail of vehicular movement Name of Project Component Distance from closest village (km) No. of vehicles/day* Barrage & Intake ½ 8 Adit-1 ½ 6 Adit-2 2 6 Adit-3 3.5 6 P/H Complex 4.0 8 TRT 5.0 4 Surge Shaft 5.0 5 Labor Camp-1 ½ 3 Labor Camp-2 5.0 3 Others 0-12 11 TOTAL 60 *All the vehicles are pollution norm compliant/pollution under control. The total no. of vehicles movement during construction phase will be 60 vehicles/day in whole project area, i.e. in a stretch of 12 km. These vehicle movements will not be at a single point source but will be at different places in the entire project area. ii) Construction of temporary bridge over river Satluj A 70 R bridge for crossing over to right bank of river Satluj will be constructed near barrage site. iii) Project headquarters, offices, colonies The availability of facilities viz., schools and college education, hospitals, market and recreation at Karchham, Bhabanagar and Reckong Peo, shall enable the staff posted on the project in the beginning to speed up the construction of project roads, buildings and also enable to start the main civil works of the project in the 1st year itself. Suitable colony sites for construction of residential and non-residential buildings have been finalized near village Ralli and Karchham respectively. The main residential and non-residential colony will be at Ralli. The building will be permanent and temporary depending upon the use to which they are likely to be put during and after construction. 2.6 LAND REQUIREMENT The total land required for the project is 77.3326 Ha. The component-wise details of land required are given in Table - 2.5. TABLE-2.5: Land required for the proposed Shongtong-Karchham, HE. Project Type Quantity (Ha) Forest 63.5015 Private 13.8311 Total 77.3326

Page 29: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-11

2.7 CONSTRUCTION EQUIPMENT The lists of major equipment to be used during construction phase are:

• Crushers • Batching plant • Aggregate processing plant • Dumpers • Transit Mixer • Excavator • Loader • Dozer • DG Sets • Compressors • Concrete pump • Ventilation Blower

2.8 CONSTRUCTION MATERIAL REQUIREMENT In all a total quantity of 0.375 million cubic meters concrete is estimated to be placed in diversion barrage, Intake structure, Intake tunnels, Sedimentation chambers, feeder tunnels to HRT, Flushing tunnel,. Diversion tunnel, Head race tunnel, Surge shaft, Pressure shaft, valve chamber, Power house complex, Tail race tunnel, Outfall and Building works. Table 2.5 gives detail of availability of adequate quantities of raw material (Coarse/Fine aggregate) per year construction of Shongtong – Karchham HEP. Part of requirement of material for backfill and protection works will be met from the muck generated during excavation for underground components. Table 2.6: Detail of annual availability of adequate quantities of raw material Site No.

Name of Quarry Site Quantity (cubic meters)

1. 25 m D/S of Drift to Desanding chamber 24,241.00 2. 25 m U/S of Drift to Desanding chamber 17,622.75 3. At Barrage 8,891.25 4. At Barrage 39,337.50 5. Near Stone Crusher at Powari 30,137.25 6. U/S of Discharge site 9,975.00 7. U/S of Discharge site 17,672.00 8. Near Tangling Jhula 9,265.00 TOTAL 157,141.75 say

(157,142.00 Cu. m.) Since all the sites are in river bed thus they will replenish themselves every year. So for the 5½ years of construction phase it will comes out to be: = 157,142 x 5½ = 864,279.625 cubic meters = 0.86 million cubic meters In case the required material fall short of demand, then HPPCL will use its already existing quarry of Kashang Project at Jangi. The estimated 0.297 million cum of coarse aggregate and 0.150 million cum of fine aggregate will be required as detail hereunder. Detail of Proposed

Page 30: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-12

location of Quarry site along with submergence area are shown in Figure 2.6: Table 2.7: Requirement of Fine and Coarse aggregate Description of Component Coarse Aggregate(cum) Fine Aggregate(cum) Diversion Barrage 25,000 12,500 Intake structure 7,000 35,000 Intake tunnels & Sedimentation chambers

38,250 19,125

feeder tunnels to HRT 15,225 7,500 Flushing tunnel, Diversion tunnel, gate galleries, Head race tunnel and its Adits

180,170 80,665

Surge shaft & its Adits 15,310 7,754 valve chamber & its Adit 915 0.01 Pressure shaft& its Adits 11,622 6,011 Power house complex 10,952 5,800 Tail race tunnel &Outfall 5,000 2,500 Building works 19,430 9,914 Total 297,000 150,000 Since the quarry site near the barrage lies in submergence area, thus the river bed mining material (RBM) will replenish itself annually in monsoon season. Since no gangue or mine spoil will be generated (RBM has 100% utilization rate) therefore there is no need for disposal. The quarried material (RBM) will be stacked at leveled Dumping site. As per our Muck Management Plan, excess capacity for dumping is available. The necessary approval of quarry sites will be taken after acquisition of land. The NOC/approval from the mining department will be provided. 2.9 Year wise number of construction workers. Year wise number of construction workers proposed at sites for construction camps and workers residential areas. Also distance to nearest villages, population of economic activity at these villages, summary provided in Table 2.10. Table 2.8: Year wise distribution of construction workers, starting from the year of commencement (say 2011-2012) of civil works.

Year No. of Workers No. of Dependents Total

2010-2011 80 160 240 2011-2012 650 1,300 1,950 2012-2013 1,000 2,200 3,200 2013-2014 1,000 2,200 3,200 2014-2015 1,000 2,200 3,200 2015-2016 1,000 2,200 3,200 2016-2017 1,000 2,200 3,200 2017 onwards 150 300 450

Page 31: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-13

Table 2.9: Year wise distribution of construction workers, starting from the year of commencement (say 2011-2012) of civil works at different working sites Year No. of workers at

Barrage, sedimentation chamber and Adit -1

No. of workers at Adit -2

No. of workers at Power House Complex

Total

2010-2011 40 2 38 80 2011-2012 288 64 288 650 2012-2013 400 200 400 1,000 2013-2014 400 200 400 1,000 2014-2015 400 200 400 1,000 2015-2016 400 200 400 1,000 2016-2017 400 200 400 1,000 2017 onwards 75 0 75 150

Table 2.10: Proposed sites for construction camps and its distances from nearest Village S. No. Powari Tangling

(Population – 967) Barang (Population. – 1,399)

Ralli (Population. – 459)

Khawangi (Population. – 803)

Aerial (km)

R D (km)

Aerial (km)

R D (km)

Aerial (km)

R D (km)

Aerial (km)

R D (km)

Aerial (km)

R D (km)

Camp -1 (300 labor)

½ ½ ½ ½ 2½ 6 5 11 1 8

Camp-2 (700 labor)

5½ 6 4½ 5 2 9 3 8 5 11

R.D = Road Distance Table 2.11: Proposed sites for construction camps and its distances from Project Components S. No. Barrage and

Intake Adit-1 Adit-2 Adit-3 P/H Complex

Aerial (km)

R D (km)

Aerial (km)

R D (km)

Aerial (km)

R D (km)

Aerial (km)

R D (km)

Aerial (km)

R D (km)

Camp -1 0 0 0 ½ 2 3 3 4½ 4½ 5 Camp-2 5 6 4½ 5 1 2 ½ 1 1 2

R.D = Road Distance Table 2.12: Elevation (EL) of Project components, Labor Camps along with Project Affected Villages S. No. Project Component/Village Elevation (EL) in meters 1 Camp 1 1950 2 Camp 2 1860 3 Barrage 1958 4 Adit 1 1942 5 Adit 2 1896 6 Adit 3 1867 7 MAT 1828 8 Power House 1789 9 TRT outfall 1808 10 Barang Village 2600 11 Powari Village 2000 12 Khawangi Village 2150

Page 32: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-14

S. No. Project Component/Village Elevation (EL) in meters 13 Tangling Village 1955 14 Ralli Village 2300 15 Mebar Village 1942.50

The main area of economic activity within the vicinity of project area nearest to camps is at Reckong-Peo which is at approx 8 km from camps. As seen from the Table 2.12 above, the villages, project components, and the labor camps are situated farther apart with nearly minimal contact due to distances involved. 2.10 CONSTRUCTION PERIOD The project is proposed to be completed within a time frame of about 66 months.

Page 33: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-15

Figure 2.1: L section of Satluj River from Khab HEP to Bhakra Dam

Page 34: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-16

Figure – 2.2: Other Hydro Projects on River Satluj

Page 35: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-17

Figure – 2.3: Alternatives examined for project location

Page 36: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-18

Figure – 2.4: Progressive discharge in River Satluj from barrage to outfall

Page 37: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-19

Figure – 2.5: Power Evacuation Master Plan of Satluj Basin

Page 38: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-20

Figure 2.6: Proposed location of Quarry site along with submergence area

Page 39: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-21

Annexure 2.1 Details of Associated Projects downstream to Shongtong – Karchham HEP on river

Satluj BASPA – II HEP (300 MW) - Jaypee Group MoU Signing with GoHP November 1991

Implementation Agreement October 1992

Environment Clearance J-12011/1/87-1A-1, Dated 24 May, 2000

Forest Clearance 8-224/89/FC, Dated 08 Nov. 1993

Techno-Economic Clearance April 1994

Power Purchase Agreement June 1997

Commercial Generation of Power May 2003

KARCHHAM - WANGTOO HEP (1000 MW) - Jaypee Group MOU Signing with GOHP 28 August, 1993

In-Principal Clearance by CEA March, 1996

Implementation Agreement 18 November, 1999

Addendum to Implementation Agreement 28 May, 2001

Environment & Forest Clearance

J-12011/47/2005-1A-1, Dated 09/11/2005 F. No. 8-5/2002-FC, Dated 06/07/2006

Techno-Economic Clearance 31 March, 2003 Consent to establish HP SEP & PCB/ J.P. Karchham Wangtoo HEP – Kinnaur/ 2005-9127-34, Dt. 08/08/2005 and EP & PCB/ J.P. (Karchham Wangtoo HEP) Vol - III/ 2004-9236 - 43, Dt. 12/08/2005

Page 40: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-22

Annexure 2.2

Details of Project Up stream to Shongtong – Karchham HEP

SALIENT FEATURES OF THOPAN-POWARI HEP

LOCATION State Himachal Pradesh District Kinnaur River Satluj Vicinity Diversion dam site near village Thopan &

Power House site near village Powari on NH-22 about 215 km from Shimla (HP)

HYDROLOGY Catchment area at diversion site. 46730 Sqkm Average runoff in 90% dependable year 5712 Mm3 Average runoff in 50% mean year 8354 Mm3

DIVERSION DAM Type Concrete Gravity Full reservoir level EL 2130.00 m. Maximum pond level EL 2133.00 m. MDDL EL 2120.00 m River Bed Level at Dam site ±EL. 2080.00 m.

SEDIMENTATION CHAMBERS No. of sedimentation chambers 3 Width 15m. Depth 27.50m. Length 530m. Particle size to be arrested +0.25 mm. Design discharge 412.50 cumecss. Flow through velocity 0.3 m/s

HEAD RACE TUNNEL Type Circular concrete lined Diameter 9.35 m finished. Length 5,840 m. Design discharge 330 cumecss.

SURGE SHAFT No One Type Restricted Orifice (Underground) Diameter 31.00 m Orifice Dia. 550 m

PRESSURE SHAFTS No. 3 Type circular steel lined(underground) Diameter 4.75 m ( Finished)

Page 41: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-23

Length 320.00 m each Type ASTM - 537 Thickness varies from 15 to 35 mm

POWER HOUSE / TRANSFORMER HALL CAVITY Type Underground installed capacity 480 MW (3 x 160 MW) Size of machine hail 90 m (L) X 20 m (W)x 51 m (H) Size of transformer hall 72 m (L) X l5.5 m (W)x 25 m (H) Normal tail water elevation 1,956.00 m Average head 171.92 m Net head at 330 cumecss tunnel discharge 161.14 m

ELECTRO- MECHANICAL EQUIPMENT TURBINES No. and type 3 Francis turbines

Page 42: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-24

Annexure 2.3 (90% dependable flow series of Thopan- Powari HEP)

Page 43: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-25

Annexure 2.4

Himachal Pradesh Hydro Power Policy (2007) The State Policy is in consonance with National Water Policy of 2002. It makes a clear statement of objectives. Some of the statements in this policy document relevant from social and environmental viewpoint are:

• Promotion of a participatory approach and involvement of local communities and stakeholders, including women, in the management of water resources, in an effective and decisive manner in various aspects of planning, design, development and management of the water related schemes.

• Ensure ecological and environmental balance while developing water resources • Promotion of equity and social justice among individuals and groups of users in water

resource allocation and management • Ensure self-sustainability in water resources development • Provision of a well-developed information system, for water related data for resource

planning. A standardized state information system should be established with a network of data banks and data bases, integrating the State and Central level agencies and improving the quality of data collection and analysis

• Effective monitoring of policy implementation Among the important provisions included in this policy document are:

• Non-Conventional methods for augmenting availability of water such as artificial recharge of ground water and traditional water conservation practices like rainwater harvesting, including roof-top rainwater harvesting and use of such water through dual plumbing systems in all buildings need to be promoted. Pilot projects will be supported for demonstration effect. Research and development in these areas shall also be supported.

• Water resource development projects should as far as possible be planned and developed as multipurpose projects but provision for drinking water shall be a primary consideration.

• There should be an integrated and multi-disciplinary approach to the planning, formulation, clearance and implementation of projects, including catchment area treatment and management, environmental and ecological aspects, the rehabilitation of affected people and command area development. Besides, in projects for hydropower generation involving impounding of water, adequate water shall be released round the year to meet the needs of downstream users. The sustainability evaluation of the Project shall determine.

• “Environmental Discharge” to be prescribed for the Project, which shall not be less than 15% of the available discharge at any given time. In forest areas the extraction of water shall be planned keeping in view the needs of the flora and fauna of the area. The involvement and participation of beneficiaries and other stakeholders will be encouraged at the project planning stage itself.

• All water resources projects should be examined from ecological and environmental considerations and remedial measures wherever needed should form a part of the project itself and implemented along with it. A minimum flow in the natural streams should be allowed.

• Water Harvesting should be given consideration in planning water resources. Viable projects, especially in scarce ground water areas, should be investigated and

Page 44: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 2-26

implemented to increase the surface water availability would also help in recharging the ground water.

• All the water resources projects shall give due regard to the “ecological health” and other needs for which adequate provision shall be made on priority basis.

Page 45: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 3-1

CHAPTER-3

METHODOLOGY ADOPTED FOR THE EIA STUDY

3.1 INTRODUCTION

Standard methodologies of Environment Impact Assessment were followed for conducting the Comprehensive EIA study for the proposed Shongtong-Karchham hydroelectric project. A brief account of the methodologies and matrices followed in the present study is given below under different headings. All the methods were structured for the identification, collection and organization of environmental impact data. The information thus gathered has been analyzed and presented in the form of a number of visual formats for easy interpretation and decision-making.

3.2 STUDY AREA

The study area covered as a part of the EIA study is as below (Refer Figure 3.1).

• Land to be acquired for various project appurtenances including reservoir submergence and project colony at Dakho near Kalpa.

• 10 km on either side from the periphery of reservoir submergence. • Downstream of the barrage site 10 km on either side of various project

appurtenances. • Catchment area intercepted at barrage site.

3.3 SCOPING MATRIX

Scoping is a tool which gives direction for selection of impacts due to the project activities on the environment. As a part of the study, scoping exercise was conducted selecting various type of impacts which can accrue due to hydroelectric project. Based on the project features, site conditions, various parameters to be covered as a part of the CEIA study were selected. The results of scoping analysis are presented in Table-3.1.

TABLE-3.1: Scoping Matrix for CEIA study for the proposed Shongtong-Karchham hydroelectric Project Aspects of Environment Likely Impacts Land Environment Construction phase • Increase in soil erosion

• Pollution by construction spoils • Acquisition of land for labour colonies - Solid waste from

labour camps/colonies. Operation phase • Acquisition of land for various project appurtenances

• Loss of agricultural and forest land due to submergence Water resources & water quality Construction phase • - Increase in turbidity of nearby receiving water bodies

• - Degradation of water quality due to disposal of wastes from labour, colony and construction sites

Operation phase • Modification of hydrologic regime Aquatic Ecology Construction phase • Increased pressure on riverine fisheries as a result of

indiscriminate fishing by the labour population. • Reduced productivity due to increase in turbidity levels as a

result of disposed off effluents from construction sites. Operation phase • Impacts on spawning and breeding grounds

• Degradation of riverine ecology

Page 46: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 3-2

Aspects of Environment Likely Impacts • Impacts on migratory fish species - Impact on aquatic

ecology due to drying of the river stretch Terrestrial Ecology Construction phase • Increased pressure from labour to meet their fuel wood

requirements • Adverse impacts on flora and fauna due to increased

accessibility in the area and increased influx of human population

• Loss of forest due to construction of road and other project appurtenances

Operation phase • Loss of forests in the submergence area • Impacts on wildlife movement - Impacts on wildlife habitats

Socio-Economic Aspects Construction phase • Increased employment potential during the project

construction phase • Development of allied sectors leading to greater

employment • Pressure on existing infrastructure facilities. • Cultural conflicts and law and order issues due to

migration of labour population Operation phase • Loss of lands

• Loss of private properties • Impacts on archaeological and cultural monuments, if any • Impacts on mineral reserves, if any

Air Pollution Construction Phase • Impacts due to fuel combustion in various construction

equipment • Impacts due to increased vehicular movement • Fugitive emissions from various sources • Impacts due to emissions of DG sets

Noise Pollution Construction Phase • Noise due to operation of various construction equipment

• Noise due to increased vehicular movement • Impacts due to blasting • Increased noise levels due to operation of DG sets

Public Health Construction Phase • Increased incidence of water related diseases

• Transmission of diseases by immigrant labour population Operation phase • Increased incidence of vector borne diseases

Based on Scoping matrix, the environmental baseline data has been collected. The project details have been superimposed on environmental baseline conditions to understand the beneficial and deleterious impacts due to the construction and operation of the proposed project.

3.4 DATA COLLECTION

Detailed field studies were conducted various aspects as a part of data collection of CEIA study. Primary surveys were started in February 2008 and field studies were conducted for three seasons to collect data on flora, fauna, aquatic ecology, water quality, soil, ambient air quality and soil quality. The details are being given in Chapters -3, 4 and 5 of the EIA report. During these surveys data and information was collected on physico-chemical, biological and socio-economic aspects of the study area. In addition, detailed surveys and studies were also conducted for understanding bio-diversity in the study area.

Page 47: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 3-3

3.4.1 Physico-chemical aspects

Geology

The regional geology around the project area highlighting geology, stratigraphy and structural features were based on the existing information on these aspects contained in Detailed Project Report (DPR) of the project.

Hydrology

Hydrological data for river Satluj as available in the Detailed Project Report (DPR) was collected and suitably incorporated in the Comprehensive EIA study.

Land use pattern

Land use pattern of the study area as well as the catchment area was carried out by standard methods of analysis of remotely sensed data and followed by ground truth collection and interpretation of satellite data. For this purpose digital satellite data was procured from National Remote Sensing Agency (NRSA), Hyderabad, IRS-P6, LISS-IV. The data was processed through ERDAS software package available with WAPCOS.

Soil

The soil quality was monitored at various locations in the catchment area. Soil sampling was done at five locations in the study area. The monitoring was conducted for three seasons namely winter (February 2008), summer (May 2008) and post-monsoon (October 2008). The parameters monitored were:

• pH • Electrical Conductivity • Organic Matter • Sodium • Phosphates • Potassium • Nitrates • Cation Exchange Capacity • Sulphates • Chlorides • Ammonical Nitrogen • Particle Size Distribution

Water Quality

The existing data on water quality has been collected to evaluate river water quality on upstream and downstream of the project site. The water quality was monitored for three seasons listed as below:

• Winter season February 2008 • Summer season May 2008 • Post-monsoon season October 2008

The water samples were collected from various locations in the study area and analyzed for physico-chemical parameters. The list of various parameters analyzed is given in Table-3.2.

Page 48: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 3-4

TABLE-3.2: Water quality parameters analyzed as a part of the field studies

pH Zinc Electrical Conductivity Cadmium TDS Magnesium Sulphates Lead Chlorides Mercury Nitrates Manganese Phosphates Hardness Sodium DO Potassium BOD Calcium COD Copper Chromium Iron Total Coliform

Ambient air quality

Ambient air quality monitoring has been carried out with a frequency of two samples per week at three locations for three seasons. The monitoring was conducted for the following seasons:

• Winter : February-March 2008 • Summer : May-June 2008 • Post-monsoon : October-November 2008

The baseline data of ambient air environment has been generated for the mentioned parameters as given below:

• Suspended Particulate Matter (SPM) • Respirable Particulate Matter (RPM) • Sulphur dioxide (SO2) • Oxides of Nitrogen (NOx).

Instruments used for sampling

Respirable Dust Samplers APM-451 of Envirotech Instruments are being used for monitoring Suspended Particulate Matter (SPM), Respirable fraction (<10 microns) and gaseous pollution like SO2 and NOx.

Sampling and Analysis Techniques

SPM and RPM present in ambient air is sucked through the cyclone. Coarse and non-respirable dust is separated from the air stream by centrifugal forces acting on the solid particles. The separated particulates fall through the cyclone’s conical hopper and are collected in the sampling cap placed at the bottom. The fine dust (<10 micros) forming the respirable fraction of the SPM passes the cyclone and is retained by the filter paper. A tapping is provided on the suction side of the blower to provide suction for air sampling through a set of impinges.

SPM and RPM have been estimated by gravimetric method. Modified West and Gacke Method (IS-5182 Part-II, 1962) have been adopted for estimation of SO2. Jacobs

Page 49: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 3-5

Hochheiser method (IS 5182 Part-II, 1975) has been adopted for estimation of NOx.

Ambient Noise level

Baseline noise data has been measured using a weighted sound pressure level meter. The survey was carried out in calm surrounding. Sound Pressure Level (SPL) measurement in the outside environment was made using sound pressure level meter. Hourly noise meter readings were taken at different sites. The survey for winter season was conducted in February 2008, likewise the survey for summer and post- monsoon seasons were conducted in the months of May 2008 and October 2008 respectively.

Noise monitoring was conducted at five locations. The noise levels were monitored continuously from 6 AM to 9 PM at each location and hourly equivalent noise level was measured. Sound Pressure Level (SPL) measurement in the ambient environment was made using sound pressure level meter. Based on the hourly ambient noise levels monitored for winter, summer and post monsoon seasons, day time equivalent noise levels was estimated.

3.4.2 Ecological Aspects

Terrestrial Ecology

Various sampling sites were identified in the project area keeping in view the various points: the area to be adversely affected by the activities of submergence; catchment area; area within 10 km from reservoir periphery; the land to be acquired for power house; and the site of dumping of excavated tunnel materials. The sampling sites for terrestrial ecological survey are listed as below:

• T-1: In the sub-mergence area and close to the dumping site 2 and 3 on the Satluj River (1,945 m above MSL.)

• T-2: was identified close to the barrage site near the village Powari (1,940 m above MSL.).

• T-3: was identified near the dumping site 4 on right bank (1,810 m above MSL.). • T-4: was identified near the dumping site 5 on left bank (1,810 m above MSL.). • T-5: was identified near the site of power house and close to the village Ralli on NH-

22 (1,810 m above MSL.).

As a part of the CEIA study, a detailed Ecological survey was conducted for three seasons namely winter, summer and monsoon seasons. The field study for winter, summer and monsoon seasons was conducted in the months of February 2008, May 2008 and July 2008 respectively. The objective of the study of terrestrial ecosystem was to prepare an inventory of flora, listing of rare, endangered of economically important and medicinal plant species and to determine frequency, abundance and density of different vegetation components. Considering the difficult terrain, quadrate method was used for sampling of the vegetation. Taking into consideration, the size of the vegetation patches, 25 random quadrates of 10m X 10 m size were laid to study the trees and shrubs, and 25 random quadrates of 1 m X 1 m size were laid to study the herbaceous component at each sampling site. During the survey, numbers of plants of different species in each quadrate were counted and identified. The height of individual tree was estimated using Abney level/ Binocular and the DBH of all trees having height more than 8m was measured. Based on the quadrate data, frequency, density and cover (basal area) of each species were calculated. The Importance Value Index (IVI) values for different trees species were determined based on the relative density, relative frequency and relative

Page 50: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 3-6

cover value. The relative density and relative frequency values were used to calculate the IVI of shrubs and herbs. The volume of wood for trees was estimated using the data on DBH (measured at 1.5 m above the ground level) and height. The volume was estimated using the formula: π r2 h, where r is the radius and h is the estimated height of the bole of the tree. The data on density and volume were presented in per hectare (ha). Species diversity indices (Shannon Wiener Index) of general diversity ( H ) was computed using the following formula:

Shannon Wiener Diversity Index ( H ) = -nN

nN

i i

l

s ⎛⎝⎜

⎞⎠⎟

⎛⎝⎜

⎞⎠⎟−

∑ log21

where, H = Shannon Wiener index of diversity; ni= total no. of individuals of a species; and N= total no of individuals of all species. During the vegetation survey, herbaria were prepared for those plants which had flowers. The Red Data Book of India and other available literature, floral herbaria pertaining to the rare/ endangered species were considered to identify the endemic, rare and other threatened categories of plants. Wildlife

The wild animals were identified by direct observation during field survey and signs of their pellets, scats, pugmarks and claw marks were also considered. A binocular (10X50X) was used for bird watching and the important features were noted. The identification of avian fauna was made on the basis of available literature (Ali 1962, Gasten 1978 and Grimmett et al 2000) Interviews with the villagers and local people were also made to generate information about wild animals and avian fauna. The secondary data and reported list of wild life were also consulted. On the basis of on-site observations as well as secondary data, a check list of wild animals was prepared. The ecological status of the wild animals was categorized following IUCN Red Data Book, 1994.

Aquatic Ecology

Aquatic ecological analysis of Satluj River was made following the methods outlined in Wetzel and Likens (1991) and APHA (1998). Periphyton was collected using a timed scrapping technique following Ward (1974) with the help of a sharp knife for each replicate sample. The upper surfaces of at least cobble sized rocks were scrapped using a five-minute period. For enumeration of plankton population, bulk water samples were collected in polythene jars. For obtaining, net plankton from the water sample, 150 ml of bulk water was filtered through a 50 µm net and was centrifuged at 1500 rpm for 10-minute period. The sediment of the centrifuge tubes was made to concentrate and was used for enumeration of zooplankton population. A plankton chamber of 0.5 ml capacity was used for counting of plankton under the Inverted Compound Microscope. The total number of planktons present in a litre of water sample was calculated using the following formula:

Number of plankton (units l-1) = Number of plankters in 0.5 ml aliquot X 0.5 X 10 Volume of sediment concentrate X Volume of water centrifuged Primary productivity of periphyton-phytoplankton of Satluj River was determined by the 1.93 litre molded Polysterene Chamber Method in situ measurement of the rate of primary production. Three replicates were maintained for each sampling site. The experimental chamber was kept for 4 hrs under incubation in the Satluj River. The modified Winkler’s method was used for determination of oxygen in the light and dark chambers. The

Page 51: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 3-7

calculation of primary production of phytoplankton-periphyton was made following the methods outlined in Strickland and Parsons (1960) and Benton and Werner Jr. (1972).

Respiration (R) = O2 consumed = O2 at start (-) O2 at end in dark chamber.

Gross Primary Productivity (Pg) = O2 contents of light chamber (-) O2 contents of dark chamber.

Net Primary Productivity (Pn) = Pg (-) R

Macro-zoo-benthos colonizing the substrate were collected with the help of the Surber Sampler (0.50 mm mesh net) and by hand picking from stones. Quantitative estimation of macro-zoo-benthos was based on numerical counting (individual m-2). The surface area of the stones of the sampled area was estimated by using following formula:

S = n/3(LW+LH+WH)

Where, L = length; W = width; H = height of each stone to the nearest of 0.5 cm.

An in-depth survey for fish and fisheries in the project area was done interacting with the local inhabitants, professional anglers, casual fisherman and the officials of the Department of Fisheries, GoHP. The secondary data were also collected in addition to the interview with the above section of the society. An experimental fishing was also performed for ascertaining the facts related with the fish diversity and the potential of the fisheries in the project area.

3.4.3 Socio-economic Aspects

Demography

The demographic and socio-economic characteristics of the submergence area as well as the study area have been studied through primary as well secondary sources. Detailed socio-economic census survey was conducted in all the affected villages due to the proposed project. Collection of data was completed at two levels - at village/ block and individual household level. The socio-economic survey at the village/ block level was aimed at finding out the status and extent of amenities and resources at the disposal of villages/ blocks. The household surveys were conducted with the main aim of evolving and preparing compensatory and rehabilitation packages for families who would be rendered houseless, landless and whose part of land would be acquired for various project activities. Based on the assessment of demographic profile of Project Affected Families (PAFs), Resettlement and Rehabilitation Plan using guidelines and norms as per Policy laid down for R& R Scheme for Project Affected Families (PAFs) of Shongtong-Karchham hydroelectric project was formulated.

Page 52: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 3-8

3.5 SUMMARY OF DATA COLLECTION

The summary of the data collected from various sources is outlined in Table-3.3.

TABLE-3.3: Summary of data collected from various sources

Aspect Mode of Data collection

Parameters monitored

Frequency Source

Meteorology Secondary Temperature, humidity, rainfall

- India Meteorological Department (IMD)

Water Resources

Secondary Flow, Design hydrograph and design flood hydrograph

- Detailed Project Report (DPR)

Water Quality Primary Physico- chemical and bacteriological parameters

Three seasons

Field studies for winter, summer and post-monsoon seasons

Ambient air quality

Primary RPM, SPM, SO2 and NOx

Three seasons

Field studies for winter, summer and post-monsoon seasons

Noise Primary Hourly noise level Three seasons

Field studies for winter, summer and post-monsoon seasons

Land use Primary and secondary

Land use pattern - NRSA and Ground truth Studies

Geology Secondary Geological characteristics of study area

- Detailed Project Report (DPR )

Soils Physico- chemical parameters

Three seasons

Field studies for winter, summer and post-monsoon seasons

Terrestrial Ecology

Primary and secondary

Floral and faunal diversity

Three seasons

Field studies for winter, monsoon seasons. Secondary data as available with the Forest and Wild life Department

Aquatic Ecology Primary and Secondary

Presence and abundance of various species

Three seasons

Field studies for winter, summer and monsoon seasons. Secondary data as available with the Fisheries Department

Socio- economic aspects

Primary and secondary

Demographic and socio - economic, Public health cultural aspects

- Field studies for PAFs, Secondary data collection from Revenue Department and literature review.

3.6 IMPACT PREDICTION

Prediction is essentially a process to forecast the future environmental conditions of the project area that might be expected to occur because of implementation of the project. Impact of project activities has been predicted using mathematical models and overlay technique (super-imposition of activity on environmental parameter). For intangible impacts qualitative assessment has been done. The environmental impacts predicted are as follows:

Page 53: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 3-9

• Loss of land; • Displacement of population due to acquisition of private and community properties; • Impacts on hydrologic regime; • Impacts on water quality; • Increase in incidence of water-related diseases including water borne and vector-

borne diseases; • Effect on riverine fisheries including migratory fish species; • Increase in air pollution and noise level during project construction phase; • Impacts due to sewage generation from labour camps; • Impacts due to acquisition of forest land; and • Impacts due to increase in terrestrial and aquatic ecology due to increased human

interferences during project construction and operation phases.

3.7 ENVIRONMENTAL MANAGEMENT PLAN AND COST ESTIMATES

Based on the environmental baseline conditions and project inputs, the adverse impacts were identified and a set of measures have been suggested as a part of Environmental Management Plan (EMP) for their amelioration. The management measures have been suggested for the following aspects:

• Compensatory afforestation and bio-diversity conservation plan; • Catchment Area Treatment; • Fisheries Management Plan; • Public health delivery system; • Environmental management in labour camp; • Muck Management Plan; • Restoration of quarry sites and landscaping of construction sites; • Management of Impact due to construction of roads; • Greenbelt development plan; • Control of Air Pollution; • Measure for noise control; • Water pollution control; and • Resettlement and Rehabilitation Plan.

The expenditure required for implementation of these management measures has also been estimated as a part of the EMP study. 3.8 RESETTLEMENT AND REHABILITATION PLAN

As a part of the CEIA study, a socio-economic survey of project affected families was conducted. As a part of the survey, information on family profile, occupational profile, income, land holding, crop grown, assets owned, etc. was collected. Based on the findings of the survey and the norms of outlined in R&R Scheme for Project Affected.

Families of Shongtong Hydroelectric Project, a Resettlement and Rehabilitation Plan have been formulated.

3.9 CATCHMENT AREA TREATMENT PLAN

As a part of the CEIA study, a catchment area treatment plan for the catchment area intercepted at the project site has been formulation. Various sub-watersheds have been categorized into different erosion categories, as per Silt Yield Index (SYI) method. For

Page 54: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 3-10

high and very high erosion categories a catchment area treatment plan comprising of engineering and biological measures has been formulated.

3.10 ENVIRONMENTAL MONITORING PROGRAM

It is necessary to continue monitoring of certain parameters to verify the adequacy of various measures outlined in the Environmental Management Plan (EMP) and to assess the implementation of mitigative measures. An environmental monitoring program for critical parameters has been suggested for implementation during project construction and operation phases. The staff, necessary equipment and agencies to be involved for implementation of the Environmental Monitoring Program and costs have also been indicated.

Page 55: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 3-11

Figure 3.1 Study Area Map

Page 56: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-1

CHAPTER-4

BASELINE SETTING FOR PHYSICO-CHEMICAL ASPECTS 4.1 GENERAL

Before start of any Environmental Impact Assessment study, it is necessary to identify the baseline levels of relevant environmental parameters which are likely to be affected as a result of the construction and operation of the proposed project. A similar approach has been adopted for conducting the EIA study for the proposed Shongtong-Karchham hydroelectric Project. A Scoping Matrix as outlined in Table-3.1 of Chapter-3 was formulated to identify various issues likely to be affected as a result of the proposed project. Based on the specific inputs likely to accrue in the proposed project, aspects to be covered in the EIA study were identified. The other issues as outlined in the Scoping Matrix were then discarded. Thus, planning of baseline survey commenced with the short listing of impacts and identification of parameters for which the data needs to be collected. The baseline status has been divided into following three categories:

• Physico-chemical aspects; • Ecological aspects; and • Socio-Economic aspects. The baseline setting for physico-chemical aspects have been covered in this Chapter.

4.2 METEOROLOGY

The climate of the project area is characterized by cool and dry climate. Meteorologically, the year can be divided into three distinct seasons. Winter season sets in from the month of October and continues up to February, followed by summer season from March to June. The area receives rainfall under the influence of south-west monsoons over a period of three months from July to September.

Temperature

Temperature rises rapidly after March and the month of July is the hottest month of the year with mean daily maximum temperature going up to 23.0 °C. With the withdrawal of monsoons, by the end of October, there is a sharp decrease in temperature. The months of January and February are the coolest months of the year, with mean daily minimum temperature as low as -2.3 °C. The month wise temperature variations are depicted in Figure-4.1.

Rainfall

The total annual rainfall is about 766.5 mm per annum. The maximum rainfall is received in the months from January to March. About 55% of the rainfall is received during winter season. A part of the rainfall received during winter months is in the form of snow. The rainfall as received in various months of the year is given in Figure-4.2.

Humidity

The average `humidity’ observed in the project area is about 50% Apart from the monsoon months. Humidity is generally low from 35 to 54.2%. In monsoon months, humidity is more than 80%.

Page 57: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-2

Cloud cover

In the winter season months from July to September, skies are generally heavily clouded. Heavy cloud cover persists in short spells during the winter months when the area is affected by the passing western disturbances.

The nearest meteorological station is Kalpa. The detailed data on various meteorological aspects was collected for Kalpa station. The average meteorological conditions are summarized in Table 4.1.

TABLE-4.1: Average Meteorological conditions in the Project Area

Month Mean Temp. Daily (°C) Rainfall (mm) Relative Humidity (%)

Max. Min. At 0830 hrs At 1730 hrs January 88.6 51.2 39.6 February 6.7 -2.5 121.9 54.2 45.4 March 10.7 0.2 208.7 49.6 42.4 April 17.6 4.9 60.2 44.6 37.6 May 21.7 7.9 36.3 51.6 42.6 June 22.6 10.9 42.3 67.6 54.2 July 23.0 13.3 41.2 81.4 64.2 August 22.3 12.9 39.7 83.8 68.6 September 21.1 9.5 33.6 72.0 60.8 October 19.7 5.0 2.5 45.6 40.2 November 14.7 1.9 63.2 40.4 35.4 December 10.0 -1.1 28.3 45.4 36.0 Average 16.4 5.1 57.3 47.3 Total 766.5 Source: India Meteorological Department (IMD), Kapla station average of 5 year data.

Wind Direction

Seasonal (summer, winter and monsoon) two year period wind direction based on the nearest representative meteorological station (Aerial distance of 350 meters) the wind rose diagram of project area from November 2008 to December 2010 are given in Figure 4.3. It is to be noted that project is located in a steep river gorge with cliffs and very Steep Mountain slopes on both sides of the river. Wind can thus move in only two directions (either upstream (u/s) or downstream (d/s)). However, there are no houses situated up to at least 500 m (vertical distance) from the project sites.

HPPCL, as per its corporate policy is going to install its own project specific metrological station in the project area.

4.3 GEOLOGY

Regional Geology

The project area and its surroundings expose one of the oldest stack of rocks in the core Himalayas (Central Crystalines). This metamorphic sequence is characterised by polyphase regional metamorphism varying from green schists facies to amphibolite facies. These rocks in this part of Himalayas have been categorized in to Vakirata Group comprising of felspathic gneiss, quartzite, high grade schists and magmatites, which are exposed in an accurate

Page 58: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-3

pattern. This rest over the rocks belonging to the Jutogh, Salkhala and Rampur Groups along Vakirata Thrust.

These rocks are intruded by Rakcham and Nako granites. The Vakirata Group of rocks extends towards NE along Satluj and Spiti valleys up to Shipki La and Sumdo. The Vakirata Group has further been divided in to three formations, viz- Kharo, Morang and Shiasu, of which the rocks belonging to Kharo Formations are exposed in the area around the proposed project.

Geology of Project Area

Barrage Site

The river Satluj near barrage site flows towards south through a moderately wide valley having moderately sloping right bank and steep left flank. Along the barrage axis, riverine deposits mixed with slope wash deposits are present from river bed level (+1,932 m elevation) to + 1950 m elevation. Between El +1,950 m and El + 2,050 m quartz biotite gneisses belonging to Kharo formation of Vakirata groups of rocks is exposed along a precipitous rocky slope. The rock strikes, in general, in N 25° to 300 W-S 25° to 300 E with 40° to 45°dips towards NE. The rocks are moderately jointed and some of the joints are observed to be extending for more than 100 m. These rocks are traversed by five sets of joints which include foliation joints.

Head Race Tunnel (HRT)

The HRT will have to negotiate two major drainages, i.e. Tangling and Shyong. Keeping in huge thickness of Tangling fan and presence of thick fluviglacial deposit in view, it is apprehended that there are chances of these being encountered in HRT. The fan deposits consists of big boulders of granite gneiss and quartzite, probably brought down by palaeo landslide and glaciers.

Power House

In view of steep valley slopes in this reach, unstable slopes at frequent interval and problem of avalanches, an underground power house site near village Ralli on the left bank of river Satluj has been selected. At this site thinly foliated quartzites with thin schist band trending in N 400 to N 65°W-S400E, S65°E and dipping at 200 to 450 in a NE direction i.e.; upstream are exposed along a steep slope. The site for power house has been selected downstream of the nallah so that it does not block the approach or the tail race tunnel outlet of the underground power house site. The elevation of Power house at top level will be EL. 1834.65m.

The quarzites at this location are thinly foliated and are closely jointed. The quartzites are exposed for a distance of 110 m upstream and 260 m downstream of the proposed power house location along the National Highway-22. Further downstream the area on the left abutment is covered with thick slide debris material. The quartzites are interlaced with thin schist bands and are schistose at places

4.4 SEISMOLOGY

The project area is located in Shimla Seismo Tectonic Block of Western Himalayas. This block is bounded by Sundernagar Fault in West and Kaurik Sumdo Fault in the east. Historical data indicates that largest earthquake experienced in this block is Kinnaur earthquake of January 1975 (M= 6.8).

Page 59: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-4

Apart from seismic events that have occurred in this seismic block, major earthquakes like Kangra Earthquake of April 1905 (M= +8), earthquake of 1916 (M=7.5), earthquake of 1966 (M= 7 and the Uttarkashi Earthquake of 1991 (M=6.5) have been recorded in adjoining seismic blocks within a distance of 200 km of the project site. The origin of these seismic events has been attributed to various tectonic features, which extend in to this seismic block. The location of various tectonic features like Kaurik Sumdo Fault, Raura Fault, Vakirata thrust and Jutogh thrust in the vicinity of the project area and categorisation of the project area in zone-IV, of siesmic zoning map of India indicate that necessary seismic coefficient has to be incorporated in the designs of various structures of the project. Detailed evaluation of seismic status of the area becomes more necessary due to its location in the category having highest seismic risk.

The project area falls under seismic zone-IV, as per the seismic zoning Map of India given in IS: 1894: 2002 i.e. highest seismic zone in Western Himalayas. In the past, the region has been affected with a number of strong earthquakes. Since year 1720, 17 nos. of earthquakes of intensity greater than 5 on Richter scale have been reported in the area. The most devastating earthquake recorded in the region, is the Kangra earthquake of 1905, which caused considerable damage to life and property in district Kangra. Other major earthquakes are Chamba-1945, 1947, 1950 (M=6.5, 6.6, & 5.5); Dharamshala 1978, 1986 (M= 5 & 5.7) and Kathua-1980 (M=5.3). The major earthquake causing considerable damage in last 100 years in the region are given in Table- 4.2.

TABLE-4.2 List of major earthquakes in the region in last 100 years

Year Earthquake Magnitude 1905 Kangra 7.8 1906 Kullu 6.4 1930 Sultanpur 6.0 1945 Chamba 6.0 1947 Chamba 6.0 1950 Chamba 6.0 1951 Chamba-Udhampur 6.0 1955 Lahual-Spiti 6.0 1962 Chamba-Udhampur 6.0 1975 Kinnaur 6.8 1978 Dharamshala 5.0 1980 Kathua 5.3 1986 Dharamshala 5.7 1986 Uttarkashi 6.6 2004 Kangra 5.1

Source: Amateur Seismic Centre, Pune, 2007

The important earthquakes within 200 km of the proposed Shongtong-Karchham Hydroelectric site are given below in Table-4.3.

Page 60: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-5

TABLE-4.3 Important Earthquake Within 200 km from Shongtong-Karchham Hydro-Electric project Site

Date Epicenter Magnitude Latitude (N) Longitude (E)

05.03.1842 30.00 78.00 6.5 16.06.1902 31.00 79.00 6.0 04.04.1905 32.25 76.25 8.0 13.06.1906 31.00 79.00 6.0 28.02.1908 32.00 77.00 7.0 20.10.1937 31.10 78.00 6.0 12.05.1939 32.50 78.00 6.3 22.06.1945 32.80 76.90 6.5 10.06.1947 32.60 75.90 6.0 27.06.1955 32.50 78.50 6.0 12.04.1963 32.00 78.79 6.0 19.01.1975 32.35 78.76 6.8 20.01.1991 30.75 78.86 6.6 (mb) 7.1 (ms)

In order to monitor impact of blasting, Seismograph at an appropriate location will be established and monitoring done in association with representatives of Gram Panchayat. Water resources and houses in all villages and their vicinity shall be inventorized by HPPCL to develop a baseline in case of any claim. Damages occurring subsequently as may be attributed to project construction shall be either restored or compensated at project cost. A Dam break analysis along with inundation map is under process.

4.5 LAND USE PATTERN The land utilization for the Kinnaur district is given in Table-4.4 and total land requirement of the project is summarized in Table-4.5.

TABLE-4.4: Land utilization for the district Kinnaur S. No. Land Utilization Area (Ha) 1. Geographical area by village papers 623,742 2. Forests 37,579 3. Net available for cultivation

i. Barren & un-culturable land 130,859 ii. Land put to non-agriculture Uses 124,602

4. Other cultivated land i. Permanent pastures and other grazing land 317,697 ii. Culturable waste 3,610 iii. Land under misc. tree crops and graves not

included in net area sown 84

5. Fallow land i. Current fallows 1,770 ii. Other fallows 57

6. Net area sown 7,484 7. Total cropped area 8,745 8. Area sown more than once 1,261 9. Intensity of cropping 116.85%

Source: Directorate of Land Records, Himachal Pradesh

Page 61: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-6

TABLE-4.5 Land required for various project appurtenances

S. No.

Name of Components of Project

Ownership-wise land requirement Total land required (Perm/Temp) Area of forest land (ha) Area of private land (ha) Grand

Total Temporary Permanent Total

Temporary Permanent Sub- Total Temporary Permanent Sub- Total

1 Diversion barrage, diversion tunnel and supporting structure

3.0000 30.221 33.221 - 0.7498 0.7498 33.9708 3.0000 30.9708 33.9708

2 Head Race Tunnel and Adits

1.5426 9.7449 11.2875 - - - 11.2875 1.5426 9.7449 11.2875

3 Surge shaft and associate structures

- 1.2125 1.2125 - - - 1.2125 - 1.2125 1.2125

4 Pressure shaft (U/G)

- 0.3608 0.3608 - - - 0.3608 - 0.3608 0.3608

5 Power House, tail race tunnel and associate structure

0.5000 0.9470 1.4470 - - - 1.4470 0.5000 0.9470 1.4470

6 6 nos. Dumping Area

5.1000 - 5.1000 3.1944 - 3.1944 8.2944 8.2944 - 8.2944

7 Approach Roads - 4.3416 4.3416 - - - 4.3416 - 4.3416 4.3416 8 Job facilities and

other requirement 2.0970 8.1073 10.2043 - 9.5038 9.5038 19.7081 2.0970 17,6111 19.7081

9. Quarry 1.8500 - 1.8500 - - - 1.8500 1.8500 - 1.8500 Total 14.0896 54.9351 69.0247 3.1944 10.2536 13.4480 82.4727 17.2840 65.1887 82.4727

Unit-Ha

Page 62: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-7

The project area has a typical mountainous terrain with moderate to high relief. The altitude varies from 1500 to over 3000 m from the mean sea level. There are no habitations along the river from Diversion structure to TRT. The national highway-22 follows the river, and otherwise it is too steep for habitation.

Forests are the major land use category. As a part of EIA study, digital satellite data of the area is being procured from National Remote Sensing Agency (NRSA), Hyderabad for assessing the land use pattern. The data is processed in house using sophisticated image processing software like ERDAS-Imagine to study the land use, land cover and forest details. Ground truth verification studies are to be undertaken to verify the signatures of various land use category which then will be used to classify the satellite imagery. The FCC and the classified imagery of the study area are given in Figures 4.4 and 4.5 respectively. The land use pattern of the study area is described in Table-4.6.

TABLE - 4.6: Land use pattern of the study area based on satellite data Type of land Area in Ha (%) Dense vegetation 13,577 (25.93) Open Vegetation 10,133 (19.35) Alpine Pasture 5,793 (11.06) Barren land 13,712 (26.19) Snow cover 7,454 (14.24) Agriculture 846 (1.62) Settlements 235 (0.45) Water bodies 605 (1.16) Total 52,355 (100.0)

The major land use category of land in the study area is forest land as it accounts for 45.26% of the study area. Area under agriculture is only 1.62% of the total study area. Pasture account for about 11.06% of the study area. Settlements and snow cover account for about 0.45% and 14.24%, respectively of the total study area.

4.6 SOILS

Soil is the product of geological, chemical and biological interactions. The soils in the region vary according to altitude and climate. The soil in the project area and study area are young like any other region of Himalayas. The vegetal cover is one of the most important influencing factors characterizing the soil types in a region. Soil on the slope above 30o, due to erosion and mass wasting processing, are generally shallow and usually have very thin surface horizons. Such soils have medium to coarse texture. Residual soils are well developed on level summits of lesser Himalayas, Subsoil are deep and heavily textured.

As a part of field studies, soil depth at various locations in the catchment area have been collected during winter, summer and post-monsoon seasons, which were then analyzed. The sampling stations are shown in Figure - 4.6. The results of the analysis of soil samples for the winter (February 2008), summer (May 2008) and post - monsoon (October 2008) seasons are given in Tables 4.7 to 4.9 respectively.

Page 63: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-8

TABLE - 4.7: Results of soil sampling analysis of study area in winter season

Parameter S1 S2 S3 S4 S5

pH 7.30 7.65 7.17 7.15 7.80 Electrical Conductivity µomhs/cm 46.90 23.90 35.40 49.80 70.50 Organic matter (%) 1.60 0.45 2.14 0.87 0.38 Nitrates (mg/kg) 6.20 5.30 8.50 7.50 13.00 Sodium (mg/kg) 110.88 82.31 47.63 99.98 103.76 Magnesium (mg/kg) 247.41 480.70 184.40 78.90 291.80 Chlorides (mg/kg) 168.00 199.50 94.50 136.50 126.00 Sulphates (mg/kg) <0.1 <0.1 <0.1 <0.1 <0.1 Phosphates (mg/kg) 704.24 418.02 564.80 259.15 693.41 Copper (mg/kg) 6.04 15.96 6.45 1.59 12.92 Manganese (mg/kg) 137.86 94.28 29.04 20.00 42.75 Chromium (mg/kg) 21.68 26.89 18.79 15.82 20.75 Barium (mg/kg) 58.44 55.37 48.53 45.66 47.34 Potassium (mg/kg) 3791.02 4100.37 1994.30 1228.61 2254.82 Lead (mg/kg) 18.03 29.98 30.00 20.00 6.19 Cyanide (mg/kg) ND ND ND ND ND

TABLE - 4.8: Results of soil sampling analysis of study area in summer season

Parameter S1 S2 S3 S4 S5 pH 7.46 7.53 7.62 7.31 7.45 Electrical Conductivity µomhs/cm 73.70 56.60 86.90 89.60 76.5 Organic matter (%) 0.29 0.31 5.04 0.32 0.30 Nitrates (mg/kg) 7.10 8.30 8.70 9.70 8.80 Sodium (mg/kg) 139.17 38.55 144.99 173.82 96.31 Magnesium (mg/kg) 621.30 107.80 373.90 541.60 187.60 Chlorides (mg/kg) 105.00 157.00 168.00 115.50 105.00 Sulphates (mg/kg) <0.1 <0.1 <0.1 <0.1 <0.1 Phosphates (mg/kg) 601.42 329.06 559.97 874.62 446.11 Copper (mg/kg) 56.17 3.89 20.80 23.01 4.69 Manganese (mg/kg) 251.10 85.39 108.50 38.86 160.68 Chromium (mg/kg) 30.97 17.63 24.20 24.25 19.61 Barium (mg/kg) 50.21 43.04 49.55 50.19 51.90 Potassium (mg/kg) 5,715.99 1,113.50 4,444.78 3,259.95 1,107.78 Lead (mg/kg) 59.05 16.00 22.40 22.16 24.30 Cyanide (mg/kg) ND ND ND ND ND

TABLE - 4.9: Results of soil sampling analysis of study area in post-monsoon season Parameter S1 S2 S3 S4 S5 pH 7.32 7.42 7.51 7.29 7.34 Electrical Conductivity µomhs/cm 67.80 48.65 79.85 84.50 79.5 Organic matter (%) 0.32 0.33 5.60 0.52 0.40 Nitrates (mg/kg) 6.70 9.30 8.90 9.80 9.20 Sodium (mg/kg) 145.12 46.15 156.46 165.57 89.45 Magnesium (mg/kg) 616.20 105.60 358.70 518.40 168.50 Chlorides (mg/kg) 105.00 157.00 168.00 115.50 105.00 Sulphates (mg/kg) <0.1 <0.1 <0.1 <0.1 <0.1

Page 64: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-9

Parameter S1 S2 S3 S4 S5 Phosphates (mg/kg) 601.42 329.06 559.97 874.62 446.11 Copper (mg/kg) 56.17 3.89 20.80 23.01 4.69 Manganese (mg/kg) 251.10 85.39 108.50 38.86 160.68 Chromium (mg/kg) 30.97 17.63 24.20 24.25 19.61 Barium (mg/kg) 50.21 43.04 49.55 50.19 51.90 Potassium (mg/kg) 5,715.99 1,113.50 4,444.78 3,259.95 1,107.78 Lead (mg/kg) 59.05 16.00 22.40 22.16 24.30 Cyanide (mg/kg) ND ND ND ND ND

The pH of soil at various sites lies within neutral range. The levels of NPK indicate moderate to high soil productivity. The sodium levels do not indicate any potential for soil salinization or adverse impacts on soil productivity.

In a hydroelectric project, no significant impact on soil quality is expected barring, soil pollution at local level due to disposal of construction waste. For amelioration of such impacts appropriate management measures are recommended.

4.7 WATER RESOURCES

4.7.1 Water Resources

Shontong-Karchham Hydro Electric Project is a run of river scheme project on River Satluj with all the project components proposed to be located on the left bank of Satluj river to harness the available hydel potential of the river. The river Satluj rises near Rakas Tal which is fed by Mansarovar Lake at an altitude of 4,570 m above mean sea level and passes through the Tibetan province of `Nari Khorsam'. The principal source i.e. lake Mansarovar is fed by glaciers of Ganglung, Gaungni. The southern glaciers of Kailash, Peak Kamer and Peak Riva Phargul also feed the river. The river then traverses through plateau between Zakhar and Ladakh ranges. The river flows through a very deep (915 m) channel and is fed by glaciers. The river Satluj is joined by several tributaries in `Nari Khorsam' which include Zangchu, Drama Yankti, Chonak, Manglan, Trunsaco, Sumna, Trape, etc. The banks in the Tibetan portion are less eroded because the activities of geological agents like surface runoff, water, snow, etc. are limited. There is no vegetation in the area and when the snow melts, deep channels are formed on the surface. The river Satluj enters India near Shipkila after traversing a distance of 320 km in the Tibetan province of Nari Khorsam. On entering the Indian portion, river takes a south-westerly direction and traverses for a distance of 320 km to reach Bhakra gorge, crossing which, it enters the plains of Punjab.

The principal tributaries of river Satluj below Shipkila i.e. in India are Spiti, Kashming, Baspa, Bhaba, Nogli, Kurpan, Nauli, Sholding, Seer, Bharari, Ali and Gambher Khad, river Spiti which confluences at Namgia, at 14 km upstream of Pooh is the biggest tributary.

The total catchment area intercepted up to Shongtong barrage site is 47,132 km2. The altitude in the catchment area drained by river Spiti varies from 3,048 m to 4,570 m. The rainfall in the area is scarce. The area is devoid of vegetation and melting snow forms deep flow channels. Majority of the silt carried by the river comes mainly from the Spiti area, where due to degraded status of the catchment, high soil erosion rates are observed. The catchment area from Namgia to Shongtong dam site is bounded hills of moderate height and the altitude varies from 1,936 m to 3,048 m. The area has little rainfall but witnesses heavy snow fall. The runoff due to melting of snow is the chief source of water. At higher elevations `Chilgoza' plantations are observed. The

Page 65: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-10

area has steep slopes with little vegetal cover and very little rain. The river is perennial in nature as it is fed by snow melt. About one-fourth of the catchment is under snow. The final series as approved by CWC (Central Water Commission) for the project planning along with Power potential studies using the above approved series as submitted to CEA (Central Electricity Authority) is enclosed as Annexure 4.1. Initially installed capacity of the project is 402 MW as approved by CEA vide letter copy enclosed as per Annexure 4.1.

As per the Project Report 2002, the design flood has been estimated using various methods for flood frequency analysis is given in Table-4.10.

TABLE-4.10: Design Flood estimated for the Shongtong hydroelectric Project Return period year Maximum flood average Inst. Flood 1.15 time of maximum

flood 5 1,785.81 2,053.68 10 2,163.47 2,488.00 20 2,525.83 2,904.71 50 2,995.37 3,444.67 100 3,346.38 3,848.34 200 3,472.27 3,993.11 500 3,849.94 4,427.43

1,000 4,479.39 5,151.30 Source: Project Report 2002. 4.7.2 Water resources study The Water Sources inventory for Shongtong–Karchham HEP was carried out to assess the total discharge in river Satluj from different water sources, a study of major and minor waterfalls flowing in to Satluj River was carried out in different villages in the catchment area of the project. The study includes photography and measurement of discharge per minute for each of these water sources. This study will help in comparing pre-project and post-project scenario of the water resources of the catchment area of the project. The above mentioned inventory for project is attached as Annexure 4.2. 4.7.3 Climate Change At present there are no studies available to show the effect of climate change on flow regime, including during the next decade or so and consequent effect of the same on generation capacity. However, the ecological flow downstream is related with inflow; as such, 15% of average lean months’ flow shall always be maintained downstream during the life of the project. Recently a draft report (still under finalization) has been made available through a separate study of ADB called Integrated Water Resource Management {ADB RSC-C00666 (IND)}. The said report assesses the impact of climate change in short, medium and long term. As per this report, there is no serious adverse impact on the project in the medium term (up to 30 years). Even after this, the hydrology is apparently not going to change much. Moreover, as a climate change adaptation measure, a storage project at the top of the catchment (within Indian territory) has been planned to arrest silt and to make assured regulated water availability for all the downstream projects in a cascade.

Page 66: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-11

4.7.4 Water use

As such there is no population dependent on the water flow of the river to be diverted except for washing of remains of cremation (as per Hindu rights) which takes 100 litre/body. This requirement can be easily met from 15% of lean season discharge.

The major sources of water in the project area are rivers and nallahs, which flow adjacent to the habitations. These are used to meet the major water requirements in the project as well as study area. The water is conveyed to the point of consumption, i.e. habitations, through open channels, which is then utilized for meeting domestic consumption. The water of river Satluj in the intervening catchment is not used for meeting domestic requirements.

Majority of the cropped area is rain fed. The study area in general, depends on rainfall for irrigation. Rainwater and snow are absorbed within the soil, which then percolates through pores and crevices and reappears in the form of springs. During monsoons, number and discharge of the springs increases. The supply of water in the perennial springs gets reduced in winter and summer seasons. Spring water is generally collected in a tank and stored for irrigation during the periods of scarcity. The spring water is also used for meeting domestic requirements in many areas. The water is carried through surface channels called `gools' into the fields located at lower levels.

4.8 WATER QUALITY

The major sources of water in the project area are river and nallahs, which flows adjacent to the habitation. These are used to meet the major water requirement in the project area as well as study area. The water is conveyed to the point of consumption i.e. habitations and agriculture field through open channel, then utilized for meeting various requirement. There are no major industries in the catchment. Likewise, pollution load from domestic sources is also insignificant.

As a part of the field studies, water samples from river Satluj and other tributaries from various locations were collected and analysed for various physico-chemical parameters. The various sampling locations are shown in Figure-4.6 and are listed as below:

W1- About 100m upstream of proposed barrage site; W2- About 500 m downstream to the barrage site; W3- Near Tangl ing Khad; W4- Near proposed Power house site; and W5- Drinking water at Powari village.

The water sampling results for three seasons namely winter (February 2008), summer (May 2008) and post-monsoon (October 2008) are given in Tables-4.12 to 4.14 respectively. The drinking water quality standards are enclosed as Annexure-II.

TABLE-4.12: Water quality in the study area in winter season

Parameter W1 W2 W3 W4 W5 pH 7.5 7.4 7.4 7.3 7.5 Electrical conductivity (µs/cm) 451 210 290 203 263 Total Dissolved Solids, mg/l 279 130 179 125 163 Total Suspended Solids, mg/l 844 466 60 558 80 Total alkalinity (CaCO3), mg/l 196.8 98.4 118 118 118

Page 67: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-12

Parameter W1 W2 W3 W4 W5 Carbonates, mg/l Nil Nil Nil Nil Nil D.O., mg/l 9.7 10.2 9.2 9.6 10.1 BOD, mg/l 2.3 3.2 2.1 2.7 13.2 COD, mg/l 13.8 18.4 13.8 18.5 27.6 Nitrate as NO3, mg/l BDL BDL BDL BDL BDL Phosphate as PO4, mg/l 0.28 0.28 BDL 0.16 0.40 Fluoride as F, mg/l BDL BDL BDL 0.2 BDL Chloride as Cl, mg/l 7.9 7.9 7.9 7.9 7.9 Sulphate as SO4, mg/l 46 45.3 56 49 86 Sodium as Na, mg/l 13 11 11 8 9 Potassium as K, mg/l 1 1 2 1 1 Calcium as Ca, mg/l 48.2 34.7 44.2 28.4 38.7 Magnesium as Mg, mg/l 18.3 1.9 1.9 4.8 3.3 Oil & Grease, mg/l BDL BDL BDL BDL BDL Phenolic Compound BDL BDL BDL BDL BDL Manganese, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Copper, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Zinc, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Chromium, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Cyanides, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Total Coliforms, MPN/100 ml 14 21 21 21 12

TABLE-4.13: Water quality in the study area in summer season Parameter W1 W2 W3 W4 W5 pH 7.8 7.3 7.5 7.3 7.6 Electrical conductivity (µs/cm) 380 230 310 240 267 Total Dissolved Solids, mg/l 285 150 210 150 172 Total Suspended Solids, mg/l 854 475 70 558 80 Total alkalinity (CaCO3), mg/l 208 97 120 128 121 Carbonates, mg/l Nil Nil Nil Nil Nil D.O., mg/l 9.5 10.0 9.0 9.3 9.8 BOD, mg/l 2.5 2.7 2.1 2.8 3.2 COD, mg/l 13.3 18.4 12.6 17.5 17.2 Nitrate as NO3, mg/l BDL BDL BDL BDL BDL Phosphate as PO4, mg/l 0.28 0.25 BDL 0.17 0.31 Fluoride as F, mg/l BDL BDL BDL 0.2 BDL Chloride as Cl, mg/l 7.8 7.8 7.8 7.8 7.8 Sulphate as SO4, mg/l 47 43 57 49 75 Sodium as Na, mg/l 13 14 12 9 10 Potassium as K, mg/l 1 1 2 1 1 Calcium as Ca, mg/l 49.2 35.7 45.3 30.4 39.7 Magnesium as Mg, mg/l 2.3 2.4 2.5 5.2 4.3 Oil & Grease, mg/l BDL BDL BDL BDL BDL Phenolic Compound BDL BDL BDL BDL BDL Manganese, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Copper, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Zinc, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Chromium, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Cyanides, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Total Coliforms, MPN/100 ml 18 29 31 32 15

Page 68: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-13

TABLE-4.14: Water quality in the study area in post-monsoon season Parameter W1 W2 W3 W4 W5 pH 7.6 7.4 7.45 7.2 7.5 Electrical conductivity (µs/cm) 410 236 315 229 258 Total Dissolved Solids, mg/l 292 158 219 142 168 Total Suspended Solids, mg/l 814 464 82 578 92 Total alkalinity (CaCO3), mg/l 203 94 115 127 114 Carbonates, mg/l Nil Nil Nil Nil Nil D.O., mg/l 9.3 9.8 9.1 9.4 9.7 Parameter W1 W2 W3 W4 W5 BOD, mg/l 2.4 2.8 2.3 2.9 2.1 COD, mg/l 12.7 19.4 13.8 16.8 18.4 Nitrate as NO3, mg/l BDL BDL BDL BDL BDL Phosphate as PO4, mg/l 0.26 0.24 BDL 0.19 0.36 Fluoride as F, mg/l BDL BDL BDL 0.1 BDL Chloride as Cl, mg/l 7.8 7.8 7.8 7.8 7.8 Sulphate as SO4, mg/l 49 44 59 49 79 Sodium as Na, mg/l 15 13 14 11 12 Potassium as K, mg/l 1 1 2 1 1 Calcium as Ca, mg/l 47.4 39.8 48.4 32.6 41.2 Magnesium as Mg, mg/l 2.4 2.5 2.6 4.9 4.5 Oil & Grease, mg/l BDL BDL BDL BDL BDL Phenolic Compound BDL BDL BDL BDL BDL Manganese, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Copper, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Zinc, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Chromium, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Cyanides, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Total Coliforms, MPN/100 ml 12 22 32 33 12

The total alkalinity in various water samples were varies from 98.4 to 196.8 mg/l, 97.0 to 208.0 mg/l and 94 to 203 mg/l in winter, summer and post-monsoon seasons respectively. The low calcium and magnesium levels are responsible for soft nature of water. The non-carbonate hardness accounts for the balance hardness. Normally non-carbonate hardness can be removed by boiling. The calcium values in the three seasons covered as a part of the study ranges from 29 to 49 mg/l. The calcium values were below the permissible limit of 75 mg/l and cause for rejection limit of 200 mg/l for drinking water purposes. The calcium hardness ranges from 70 to 124 mg/l and the total hardness ranges from 85 to 140 mg/l. The hardness values were below the permissible limit of 200 mg/l (Annexure 4.3) and cause for rejection limit of 600 mg/l for drinking water purposes. Thus, it is concluded that hardness values are low. The low Electric Conductivity (EC) and Total Dissolve Solids (TDS) values indicate the lower concentration of cations and anions. The concentration of TDS level ranged from 125 to 279 mg/l, 150 to 285 mg/l and 142 to 292 mg/l in winter, summer and post-monsoon seasons respectively, which is much lower than the permissible limit of 500 mg/l specified for domestic use. This is also reflected by the fact that the concentration of most of the cations and anions are well within the permissible limit. The fluorides level was lower than the permissible limit (1mg/l) for drinking purposes. Use of water with such fluorides level could lead to dental curies.

The BOD values are well within the permissible limits, which indicate the absence of organic pollution loading. This is mainly due to the low population density and absence of industries in

Page 69: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-14

the area. The low COD values also indicate the absence of chemical pollution loading in the area. The marginal quantity of pollution load, which enters river Satluj, gets diluted. In fact, even for the minimum flow, there is more than adequate water available for dilution. Level of heavy metal in the water of the project area is below the permissible limit used for drinking purposes. The Total Coliform count is very low and it ranges from 12-21, 15-32 and 12-33 in winter season, summer season and post monsoon seasons respectively in the study area. The Water Quality Standards prescribed by Bureau of Indian Standards for Class-A Surface waters, i.e., Water that can be used for domestic purpose without any conventional treatment, except for disinfection is 50 MPN/100 ml. Hence, it has been concluded that water quality in the area is quite good.

4.9 AMBIENT AIR QUALITY

The ambient air quality with respect to the study area around the proposed site forms the baseline information. The study area represents rural environment. The sources of air pollution in the region are vehicular traffic, dust arising from unpaved village roads and domestic fuel burning. The prime objective of the baseline air quality study was to establish the existing ambient air quality of the area.

Selection of Sampling Locations

The baseline status of the ambient air quality has been established through a scientifically designed ambient air quality monitoring network and is based on the following considerations:

- Meteorological conditions on synoptic scale; - Representatives of regional background air quality for obtaining baseline status - Representation of likely affected area.

Three Ambient Air Quality Monitoring (AAQM) locations were selected taking care of above-mentioned points.

Detail methodology for study of ambient air quality is given in Chapter -3.

Instruments used for sampling

Respirable Dust Samplers APM-451 of Envirotech Instruments are being used for monitoring Suspended Particulate Matter (SPM), Respirable fraction (<10 microns) and gaseous pollution like SO2 and NOx.

Sampling and Analysis Techniques

SPM and RPM present in ambient air is sucked through the cyclone. Coarse and non-respirable dust is separated from the air stream by centrifugal forces acting on the solid particles. The separated particulates fall through the cyclone’s conical hopper and are collected in the sampling cap placed at the bottom. The fine dust (<10 micros) forming the respirable fraction of the SPM passes the cyclone and is retained by the filter paper. A tapping is provided on the suction side of the blower to provide suction for air sampling through a set of impinges.

SPM and RPM have been estimated by gravimetric method. Modified West and Gacke Method (IS-5182 Part-II, 1962) have been adopted for estimation of SO2. Jacobs Hochheiser method (IS 5182 Part-II, 1975) has been adopted for estimation of NOx.

Page 70: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-15

Result of Ambient Air Quality Monitoring

The summary of result of ambient air quality monitoring conducted for various seasons are given in Tables-4.15 to 4.17. The summary of findings of ambient air quality monitoring survey is given in Table-4.18 to 4.20. The ambient air quality standards are given in Annexure-4.4.The results of Air Quality of Kashang HEP has been attached as Annexure-4.5 for reference.

TABLE-4.15: Results of ambient air quality monitoring for winter season

Station Date of Monitoring

SPM RPM SO2 NOx

21.02.08 to < 5 < 5 22.02.08 124.3 41

25.02.08 to < 5 < 5 Det Ralli 26.02.08 102.3 31.7 01.03.08 to < 5 < 5 02.03.08 128 42.0 06.03.08 to < 5 < 5 07.03.08 116.7 35.1 Power 21.02.08 to < 5 < 5 House 22.02.08 131 45.3 25.02.08 to < 5 < 5 26.02.08 121.6 38.0 01.03.08 to < 5 < 5 02.03.08 127.3 41.6 06.03.08 to < 5 < 5 07.03.08 114.3 39.2 21.02.08 to < 5 < 5 22.02.08 125.3 43.4 25.02.08 to < 5 < 5 Near 26.02.08 137.6 48.4 Barrage 01.03.08 to < 5 < 5 02.03.08 136.2 48.2 06.03.08 to < 5 < 5 07.03.08 133.7 41.2

Unit: (µg/m3)

TABLE- 4.16: Results of ambient air quality monitoring for summer season Unit: (µg/m3)

Station Date of Monitoring

SPM RPM SO2 NO,

22.05.08 to

23.05.08 135 46.2 < 5 < 5

26.05.08 to Det Ralli 27.05.08 98.3 30.3 < 5 < 5 31.05.08 to 01.06.08 145.1 48.3 < 5 < 5 05.06.08 to

Page 71: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-16

Station Date of Monitoring

SPM RPM SO2 NO,

06.06.08 112.7 35.1 < 5 < 5 22.05.08 to 23.05.08 132.5 45.7 < 5 < 5 26.05.08 to Power 27.05.08 115.6 35.1 < 5 < 5 House 31.05.08 to 01.06.08 134.3 43.2 < 5 < 5 05.06.08 to 06.06.08 112.3 35.1 < 5 < 5 22.05.08 to 23.05.08 122.6 38.0 < 5 < 5 26.05.08 to Near 27.05.08 135.1 45.8 < 5 < 5 Barrage 31.05.08 to 01.06.08 140.4 49.2 < 5 < 5 05.06.08 to 06.06.08 131.2 42.1 < 5 < 5

TABLE-4.17: Results of ambient air quality monitoring for post monsoon season

Station Date of Monitoring

SPM RPM SO2 NOx

22.10.08 to

23.10.08 126 44.2 < 5 < 5

26.10.08 to Det Ralli 27.10.08 97.4 31.4 < 5 < 5 31.10.08 to 01.11.08 123.2 45.6 < 5 < 5 05.11.08 to 06.11.08 111.4 33.2 < 5 < 5 22.10.08 to 23.10.08 129.4 48.2 < 5 < 5 26.10.08 to Power 27.10.08 113.9 35.7 < 5 < 5 House 31.10.08 to 01.11.08 124.6 42.1 < 5 < 5 05.10.08 to 06.10.08 119.4 34.2 < 5 < 5 22.10.08 to 23.10.08 128.6 41.8 < 5 < 5 26.10.08 to Near 27.10.08 124.2 42.3 < 5 < 5 Barrage 31.10.08 to 01.11.08 122.6 42.4 < 5 < 5 05.11.08 to

Page 72: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-17

Station Date of Monitoring

SPM RPM SO2 NOx

06.11.08 128.8 45.0 < 5 < 5 Unit: (µg/m3)

TABLE-4.18: Summary of ambient air quality monitoring in the study area for winter season

Station Average Maximum Minimum

RPM Det Ralli 37.45 42.0 31.7 Power House 41.03 45.3 38.0 Near Barrage 45.3 48.4 41.2 SPM Det Ralli 117.83 128.0 102.3 Power House 123.55 131.0 114.3 Near Barrage 133.2 137.6 125.3 SO2 Det Ralli < 5 < 5 < 5Power House < 5 < 5 < 5Near Barrage < 5 < 5 < 5NOx Det Ralli < 5 < 5 < 5Power House < 5 < 5 < 5Near Barrage < 5 < 5 < 5

Source: Primary survey (Unit: µg/m3)

TABLE-4.19: Summary of ambient air quality monitoring in the study area for summer season

Station Average Maximum Minimum RPM Det Ralli 39.98 48.3 30.3 Power House 39.78 45.7 35.1 Near Barrage 43.78 49.2 38.0 SPM Det Ralli 122.78 145.1 98.3 Power House 123.67 134.3 112.3 Near Barrage 132.32 140.4 122.6 SO2 Det Ralli < 5 < 5 < 5 Power House < 5 < 5 < 5 Near Barrage < 5 < 5 < 5 Nox Det Ralli < 5 < 5 < 5 Power House < 5 < 5 < 5 Near Barrage < 5 < 5 < 5

(Unit: µg/m3)

Page 73: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-18

TABLE-4.20: Summary of ambient air quality monitoring in the study area for post-monsoon season Station Average Maximum Minimum RPM Det Ralli 38.6 45.6 31.4 Power House 40.05 48.2 34.2 Near Barrage 42.87 45 41.8 SPM

Det Ralli 114.5 126.0 97.4 Power House 121.82 129.4 113.9 Near Barrage 126.05 128.8 122.6 SO2 Det Ralli < 5 < 5 < 5 Power House < 5 < 5 < 5 Near Barrage < 5 < 5 < 5 Nox Det Ralli < 5 < 5 < 5 Power House < 5 < 5 < 5 Near Barrage < 5 < 5 < 5

(Unit: µg/m3)

Observations on NOx levels

As a part of ambient air quality survey, it was seen that in all the stations the NOx level was below detectable limit. i.e it was < 5 µg/m3. The NOx level observed at various sampling stations was well below the permissible limit of 80 µg/m3 for residential and rural areas.

Observation on ambient SO2 levels

As a part of ambient air quality survey, it was seen that in all the stations the SO2 level was below detectable limit. i.e. it was < 5 µg/m3. The SO2 level observed at various stations was well below the permissible limit of 80 µg/m3 specified for residential and rural areas.

Observations on ambient SPM levels

The maximum SPM level observed in survey conducted during the survey was observed to be 145.1 µg/m3 in summer season near Det Ralli. The average SPM level at various monitoring stations ranged from 102.3 µg/m3 to 137.6 µg/m3, 98.3 µg/m3 to 145.1 µg/m3 and 97.4 µg/m3 to129.4 µg/m3 in winter season, summer season and post monsoon season respectively. The minimum SPM level was observed 97.4 µg/m3 at the station near Det Ralli in post-monsoon season, which is much below the permissible limit of 200 µg/m3 specified for residential, rural and other areas at various stations covered during the survey. But in some station SPM level is above the permissible limit.

Observations on ambient RPM levels

The average RPM levels as observed at various stations in the study area ranged from 31.7 µg/m3 to 48.4 µg/m3, 30.3 µg/m3 to 49.2 µg/m3 and 31.4 µg/m3 to 48.2 µg/m3 in winter season,

Page 74: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-19

summer season and post monsoon season respectively. The highest RPM value was recorded as 49.2 µg/m3 at near Barrage in summer season. The highest values of RPM monitored during the field survey were above the permissible limit of 100 µ g/m3 for residential and rural areas.

Conclusions

Based on the findings of the ambient air quality survey conducted it can be concluded that the ambient air quality is quite good in the area. The values of various parameters were well below the permissible limits specified for residential, rural and other areas.

4.10 NOISE ENVIRONMENT

The hourly ambient noise levels monitored for winter, summer and post monsoon seasons are given in Tables-4.21 to 4.23 respectively. The day time equivalent noise levels estimated are given in Table-4.24. The noise standards for various categories are given in Annexure-4.6. Detail methodology for study of ambient Noise levels is given in Chapter -3.

TABLE-4.21: Hourly equivalent noise levels in the study area for winter season Time Det Ralli Power House Powari Near

suspension bridge

Near Barrage

8 -9 A.M. 35 36 37 35 34 9-10 A.M. 37 37 35 36 32 10-11 A.M. 35 38 40 38 31 11 AM - 12 Noon 36 36 37 35 36 1 –2 PM 37 36 38 34 37 2 – 3 PM 36 35 34 35 38 3 – 4 PM 35 38 32 36 36 4 – 5 PM 37 36 34 36 37 5 – 6 PM 37 39 34 35 37 6 – 7 PM 36 36 36 36 32 7 – 8 PM 36 35 33 36 34 8 – 9PM 36 37 33 34 33

(Unit: dB(A))

TABLE-4.22: Hourly equivalent noise levels in the study area for summer season Time Det Ralli Power House Powari Near

suspension bridge

Near Barrage

8 - 9 AM 36 34 38 35 32 9 - 10 A M 32 32 38 33 34 10 - 11 AM 31 31 40 36 32 11 AM - 12 Noon 34 36 37 34 32 1 –2 PM 35 37 38 32 32 2 – 3 PM 32 38 34 32 32 3 – 4 PM 31 36 32 34 32 4 – 5 PM 34 37 34 35 32 5 – 6 PM 32 34 34 35 31 6 – 7 PM 31 32 36 36 36

Page 75: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-20

7 – 8 PM 30 30 30 34 31 8 – 9 PM 30 30 30 30 31

(Unit: dB (A))

TABLE-4.23: Hourly equivalent noise levels in the study area for Post monsoon season Time Det Ralli Power

House Powari Near

suspension bridge

Near Barrage

8 -9 A M 35 33 37 36 33 9-10 A M 31 31 38 32 35 10-11 A M 32 32 39 35 33 11 AM - 12 Noon 33 35 36 34 34 1 –2 PM 34 36 38 33 32 2 – 3 PM 33 37 34 32 32 3 – 4 PM 32 37 32 34 32 4 – 5 PM 35 36 33 34 33 5 – 6 PM 31 33 35 34 32 6 – 7 PM 31 31 33 36 35 7 – 8 PM 30 30 30 33 31 8 – 9 PM 30 30 30 30 31

(Unit: dB(A))

TABLE-4.24 Day time equivalent noise level at various sampling locations

S. NO. Location Zone Lday (dB(A)) Winter Det Ralli Rural 35.2 Power House Rural 35.8 Powari Rural 34.9 Near suspension bridge Rural 34.6 Near Barrage Rural 34.3 Summer Det Ralli Rural 31.8 Power House Rural 33.8 Powari Rural 35.1 Near suspension bridge Rural 33.2 Near Barrage Rural 31.5 Post monsoon Det Ralli Residential 31.6 Power House Residential 33.2 Powari Residential 34.5 Near suspension bridge Residential 32.9 Near Barrage Residential 31.9

The day time equivalent noise level in winter and summer seasons at various sampling stations ranged from 34 to 36 dB(A), 31 to 36 dB(A). Likewise, day time equivalent noise level in post-

Page 76: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-21

monsoon season ranged from 31 to 35 dB(A) at various sampling stations which were well within the permissible limit specified for rural area (Refer Annexure 4.5).

Page 77: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-22

Page 78: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-23

Page 79: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-24

Figure 4.3: Wind rose diagram of project area from November 2008 to December 2010

Page 80: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-25

Figure 4.4 Satellite Imagery of the Study Area

Page 81: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-26

Figure 4.5 Land use classification of the Study Area

Page 82: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-27

Figure 4.6 Project Layout

Page 83: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-28

Final Approved Hydrological Series by CWC

Page 84: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-29

Page 85: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-30

Page 86: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-31

Page 87: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-32

Page 88: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-33

Computed Discharge data of Satluj river at Shongtong w.e.f. 6/1972 to 5/ 2006 (34 years data)

Period 1972-73 1973-74 1974-75 1975-76 1976-77 I 358.89 747.32 255.30 565.67 665.43 II 502.32 1408.55 407.74 941.33 479.86 III 667.30 1208.69 341.80 927.68 363.46 I 708.19 1033.39 389.37 623.43 650.41 II 657.18 1062.94 833.09 1014.98 898.20 III 770.13 870.47 833.15 866.46 1022.46 I 684.17 750.82 842.28 956.26 635.63 II 601.19 767.60 832.84 1037.52 528.09 III 477.00 782.01 568.45 691.06 425.48 I 408.42 734.18 403.45 465.88 370.90 II 282.48 476.65 269.46 326.30 237.61 III 175.15 354.54 215.44 244.79 191.48 I 151.64 203.35 139.07 198.62 156.55 II 132.49 156.89 125.28 171.52 126.46 III 110.88 136.55 104.21 147.36 118.58 I 100.58 116.05 94.72 132.39 107.33 II 92.23 104.51 85.95 116.11 97.81 III 84.66 89.40 71.43 97.65 90.14 I 79.12 79.76 70.98 85.87 77.18 II 72.05 71.81 68.29 77.81 68.78 III 70.59 70.51 63.54 77.03 67.88 I 68.29 69.13 60.71 71.50 67.11 II 66.13 67.06 62.01 68.90 65.16 III 65.45 67.90 66.71 67.72 60.98 I 65.24 65.90 73.54 67.20 62.52 II 66.46 63.33 76.83 67.56 60.34 III 66.33 63.46 77.86 70.98 64.33 I 67.01 70.51 91.88 77.19 70.81 II 70.61 72.82 106.26 75.76 73.81 III 111.14 90.30 109.43 84.71 74.50 I 139.38 101.07 141.62 87.47 83.40 II 179.47 118.30 143.54 112.97 81.58 III 501.28 151.84 220.06 219.25 90.74 I 985.59 197.40 271.08 218.87 90.07 II 447.39 191.38 501.32 287.00 102.93 III 620.25 152.07 425.48 396.44 201.95

5543.91 8952.46 5470.74 7617.37 5713.74 3886.57 2255.09 2862.25 2719.65 1900.98 9430.48 11207.55 8332.99 10337.02 7614.72

1977-78 1978-79 1979-80 1980-81 1981-82 317.35 657.94 269.40 582.44 357.22 215.20 539.64 698.50 718.61 377.41 484.48 942.35 1579.68 985.07 799.05 1073.20 1054.57 1112.73 964.69 682.78 1148.86 924.74 1280.84 1098.78 883.02 906.76 899.33 1042.73 1006.45 1072.23 1188.16 1183.86 933.39 1045.39 1121.24 742.50 1026.72 872.28 655.72 950.53

Page 89: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-34

576.47 628.13 655.39 543.65 618.87 517.17 586.04 516.79 445.86 427.99 379.47 433.20 305.20 346.58 301.22 262.73 289.61 193.78 259.52 241.51 184.29 217.58 177.16 202.16 162.08 153.76 181.65 155.75 155.83 132.81 138.49 158.71 138.49 135.78 121.87 126.11 128.65 131.01 116.68 118.58 114.62 118.47 114.15 104.61 100.08 106.80 110.08 110.62 93.75 89.69 100.79 98.12 96.75 83.15 83.97 94.19 90.00 84.48 76.85 78.32 86.75 84.14 79.14 75.33 72.69 76.82 77.60 73.97 71.28 72.89 71.96 78.15 71.90 66.43 69.65 72.30 79.74 71.75 69.64 67.09 72.41 76.92 71.49 68.02 66.41 71.71 78.65 72.64 68.01 71.50 72.50 85.23 74.36 67.16 70.18 74.44 83.35 73.63 70.39 71.54 83.39 98.48 65.68 71.26 72.19 88.20 111.69 88.09 77.62 80.08 92.42 152.35 98.90 83.52 123.74

138.28 197.72 121.74 139.77 136.82 153.04 239.37 166.96 182.44 188.30 288.80 306.28 246.31 360.83 283.30 453.83 281.46 291.79 395.14 226.63 491.79 230.00 355.06 498.71 286.31 6877.43 8050.88 8320.08 7609.30 6913.21 3007.18 2956.61 2669.61 2942.97 2501.44 9884.61 11007.49 10989.70 10552.27 9414.65

1982-83 1983-84 1984-85 1985-86 1986-87 534.78 714.76 815.00 434.35 219.12 1059.96 585.28 619.13 506.73 674.23 845.05 842.40 603.70 595.50 1196.61 1114.23 873.77 657.04 594.08 790.13 1087.46 584.57 399.56 646.27 945.59 1121.94 1081.06 645.14 699.26 1171.22 1049.55 1124.80 581.73 549.05 908.99 1008.71 906.28 646.47 667.99 762.41 596.84 983.61 628.40 577.29 544.15 401.41 722.60 451.03 446.78 426.38 340.36 521.02 254.80 284.11 250.16 232.14 295.32 147.45 219.77 193.30 162.12 261.30 111.06 167.51 141.42 150.07 187.56 94.70 174.72 123.54 134.12 160.60 84.70 126.59 105.55 121.33 136.99 73.91 105.11 94.47 107.64 119.92 64.52 91.46 87.47 95.90 97.59 59.59 80.80 81.91 85.60 93.38 55.86 71.08 78.24

Page 90: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-35

81.82 84.13 53.52 65.11 75.66 77.04 77.06 50.39 61.17 71.33 71.75 72.52 48.23 55.55 67.61 72.51 69.52 45.06 52.33 64.92 73.66 65.44 45.80 50.62 63.13 69.99 64.64 43.41 52.60 61.98 67.91 64.65 42.87 53.81 63.42 71.43 65.57 44.34 53.70 64.33 70.66 70.71 50.87 59.65 65.41 84.88 85.94 55.99 67.08 75.28 92.80 100.22 60.57 68.59 89.48 104.27 101.45 64.19 76.94 102.93 115.01 108.58 78.38 118.54 96.97 150.43 155.29 100.68 158.81 145.96 256.73 191.79 136.79 200.42 156.05 483.16 300.78 158.10 335.23 145.63 495.06 471.21 429.63 174.27 256.98

8262.87 8157.01 5681.86 5484.89 7130.62 2916.55 2834.57 1823.98 2210.81 2100.93

11179.42 10991.58 7505.84 7695.71 9231.54

1987-88 1988-89 1989-90 1990-91 1991-92 613.76 491.70 749.01 648.46 892.66 528.45 489.97 549.40 522.37 1104.51 617.08 860.59 554.58 1118.07 959.96 883.64 840.06 614.08 939.90 1242.73 772.70 897.48 887.23 797.16 1078.20 897.26 979.82 1009.61 692.89 1003.00 674.80 898.98 592.85 753.06 784.77 613.19 752.88 606.66 751.85 561.48 579.01 519.91 595.78 620.03 603.56 477.53 391.51 388.97 503.70 520.18 343.77 286.97 268.40 386.78 381.67 279.08 319.98 226.70 288.05 249.89 184.16 194.66 165.43 214.80 212.16 145.36 154.66 134.23 176.68 160.23 128.95 129.32 122.08 142.98 151.30 106.75 117.26 111.63 126.62 158.15 106.11 110.47 100.93 120.86 129.71 96.66 101.98 94.75 114.09 122.03 90.89 94.33 89.09 106.41 123.77 85.11 89.88 83.88 101.62 115.06 78.92 87.62 82.59 95.56 129.83 78.93 83.13 73.75 77.98 109.24 77.94 79.11 73.48 74.68 111.24 74.42 77.24 73.49 74.83 106.44 64.79 74.79 74.60 75.35 106.39 58.30 73.49 74.50 75.91 99.73 58.14 72.66 73.38 76.45 111.12 62.46 76.29 73.94 79.34 99.32 68.24 79.69 78.73 85.42 109.54

Page 91: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-36

73.99 88.39 140.59 107.33 115.01 84.08 92.08 100.75 155.47 114.75 202.07 98.94 123.65 135.99 140.31 268.38 100.28 174.95 163.61 171.29 384.27 119.33 250.75 261.56 213.63 459.29 222.81 737.62 385.96 330.96 474.92 426.20 639.21 486.04 302.57 6417.11 6807.57 6223.46 7044.19 8244.74 3096.75 2514.71 3316.56 3108.84 3111.86 9513.86 9322.29 9540.02 10153.02 11356.59

1992-93 1993-94 1994-95 1995-96 1996-97 373.84 364.94 508.52 482.59 415.53 587.40 507.75 437.85 659.49 806.58 791.37 413.85 847.56 373.65 1198.16 461.99 494.50 1005.00 553.51 540.57 687.95 649.10 858.40 594.81 677.97 857.62 447.48 1066.42 598.87 669.69 704.55 505.34 1083.50 680.98 687.42 611.12 417.08 720.94 619.60 861.86 561.43 385.46 741.33 547.20 452.41 475.54 335.73 574.06 476.62 378.09 322.11 314.31 324.61 307.89 306.56 203.57 204.70 203.04 217.96 215.95 195.41 172.92 181.53 158.79 177.37 159.81 136.97 160.26 144.40 143.09 133.82 122.70 138.17 122.44 125.80 128.22 120.28 129.28 109.89 117.25 114.63 110.73 123.47 105.62 108.50 116.38 110.76 117.11 99.69 103.63 105.33 100.97 111.43 94.54 98.29 101.36 99.14 106.38 90.26 91.19 92.52 90.29 102.87 87.71 86.90 97.39 85.19 98.44 84.87 82.93 90.39 84.46 92.94 77.82 73.98 89.02 82.43 87.83 75.55 73.35 90.20 81.15 87.05 75.42 73.74 94.87 81.06 90.68 76.29 73.53 97.33 81.38 90.39 77.05 72.99 94.14 81.93 90.72 79.67 74.56 95.70 91.89 87.51 90.58 79.76

100.14 99.17 101.48 94.09 77.28 97.01 105.05 96.20 98.89 80.18

121.20 98.98 104.07 158.11 91.74 187.07 106.47 126.10 244.66 115.80 355.37 168.57 173.83 272.21 154.64 206.90 203.07 371.46 252.99 107.23 325.61 427.26 312.75 382.70 162.36 5857.70 4426.39 7388.22 5380.34 6326.63 2889.32 2599.21 2805.34 2777.50 2146.00 8747.01 7025.60 10193.56 8157.85 8472.64

Page 92: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-37

1997-98 1998-99 1999-2000 2000-01 2001-02 222.42 515.55 278.18 247.38 204.20 330.38 406.41 515.43 363.94 285.62 465.45 995.48 620.00 406.26 258.98 462.14 1069.93 695.60 389.30 353.55 591.68 907.58 686.33 494.89 438.47 587.12 664.21 765.63 661.02 461.37 525.25 712.38 1183.77 676.04 412.01 526.79 730.86 745.26 449.91 446.43 376.68 506.76 662.15 376.85 344.38 273.84 337.99 349.22 333.51 258.93 235.80 284.81 285.61 228.79 171.40 144.05 299.83 230.86 161.77 120.14 97.90 208.65 163.66 118.37 96.28 73.29 185.52 134.22 108.53 89.23 60.68 169.63 120.02 101.37 83.33 64.98 136.18 109.48 98.22 80.33 74.72 125.02 101.42 93.79 73.15 117.50 114.56 92.99 86.50 63.92 107.79 109.46 87.43 80.58 57.34 101.63 102.16 82.81 73.55 53.47 93.61 98.14 78.29 72.14 51.05 64.77 93.11 77.09 68.73 49.70 59.93 88.81 75.75 66.72 47.98 53.95 87.36 76.21 66.14 46.65 54.16 86.18 74.77 62.99 46.95 54.16 82.59 74.37 63.61 48.80 54.35 82.06 73.05 64.16 48.66 58.06 82.94 75.31 64.84 55.90 64.57 84.59 77.78 63.32 62.40 67.45 86.10 81.42 69.04 69.24 86.27 120.22 91.86 73.74 77.72 92.61 151.64 101.89 79.48 92.56 159.64 267.92 112.49 86.29 126.59 215.51 273.15 130.10 117.20 179.80 235.92 329.89 284.95 176.42 550.74 573.40 379.32 306.66 147.31 359.63 4179.64 6521.78 6186.37 4227.52 3314.03 2385.03 3126.57 2363.36 1845.15 2213.90 6564.67 9648.35 8549.72 6072.67 5527.92

2002-03 2003-04 2004-05 2005-06 480.44 820.86 214.03 227.52 656.89 746.85 336.37 377.18 547.27 669.02 352.65 816.52 620.15 687.18 460.15 874.15 550.08 605.68 377.40 898.93 460.24 591.61 402.48 766.16 484.47 551.79 443.94 720.01 504.29 436.47 445.57 546.81 420.84 362.45 311.37 423.02 290.44 328.89 226.84 374.55

Page 93: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-38

242.82 242.22 235.73 275.96 152.13 198.35 159.99 206.55 112.86 135.72 115.07 127.56 98.26 104.09 99.10 103.63 90.32 92.30 88.12 87.20 83.42 84.62 82.90 78.18 79.06 77.82 70.98 74.29 74.56 66.58 62.47 73.68 72.69 61.74 56.55 68.83 68.92 57.44 52.56 60.14 56.85 54.69 50.61 60.04 42.21 53.93 48.57 57.62 33.85 54.04 48.11 55.81 34.41 43.12 44.73 58.73 49.06 43.64 47.09 56.13 51.29 49.26 50.57 55.41 51.34 50.30 50.79 64.25 59.47 52.45 56.78 63.81 59.53 57.20 64.82 64.29 84.22 63.39 70.15 63.37 84.46 61.76 75.23 71.43

143.89 63.25 85.29 80.36 171.74 72.90 136.27 137.15 193.87 90.46 238.32 305.46 404.60 179.50 203.06 431.63 559.15 223.40 152.65 610.46 4750.07 5474.58 3488.47 5724.64 2451.20 1668.37 1802.46 2583.90 7201.27 7142.95 5290.94 8308.54

Power Studies for Shongtong HEP Year wise Computations for Unrestricted Energy In GWH NET HEAD = 124.01 m EFFICIENCY= 0.9114

Month Period 1972-73 1973-74 1974-75 1975-76 1976-77 I 95.50 198.86 67.94 150.52 177.07 June II 133.67 374.82 108.50 250.49 127.69 III 177.57 321.63 90.95 246.86 96.72 I 188.45 274.99 103.61 165.90 173.07 July II 174.88 282.85 221.68 270.09 239.01 III 225.42 254.80 243.87 253.62 299.28 I 182.06 199.79 224.13 254.46 169.14 Aug. II 159.98 204.26 221.62 276.08 140.52 III 139.62 228.90 166.39 202.28 124.54 I 108.68 195.37 107.36 123.97 98.70 Sept. II 75.17 126.84 71.70 86.83 63.23 III 46.61 94.34 57.33 65.14 50.95 I 40.35 54.11 37.01 52.85 41.66 Oct. II 35.26 41.75 33.34 45.64 33.65 III 32.46 39.97 30.50 43.13 34.71 I 26.76 30.88 25.21 35.23 28.56 Nov. II 24.54 27.81 22.87 30.90 26.03 III 22.53 23.79 19.01 25.98 23.99

Page 94: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-39

I 21.05 21.22 18.89 22.85 20.54 Dec. II 19.17 19.11 18.17 20.71 18.30 III 20.66 20.64 18.60 22.55 19.87 I 18.17 18.39 16.16 19.03 17.86 Jan. II 17.60 17.84 16.50 18.34 17.34 III 19.16 19.87 19.53 19.82 17.85 I 17.36 17.54 19.57 17.88 16.64 Feb. II 17.69 16.85 20.44 17.98 16.06 III 14.12 13.51 16.57 17.00 13.69 I 17.83 18.76 24.45 20.54 18.84 March II 18.79 19.38 28.28 20.16 19.64 III 32.53 26.43 32.03 24.79 21.81 I 37.09 26.90 37.69 23.28 22.19 April II 47.76 31.48 38.20 30.06 21.71 III 133.39 40.40 58.56 58.34 24.15 I 262.27 52.53 72.14 58.24 23.97 May II 119.05 50.93 133.40 76.37 27.39 III 181.55 44.51 124.54 116.04 59.11 TOTAL ENERGY 2904.74 3452.05 2566.73 3183.94 2345.48 OCT. TO MAY N/M 1197.14 694.60 881.64 837.70 585.54 JUNE TO SEPT.M 1707.60 2757.45 1685.09 2346.24 1759.94

1977-78 1978-79 1979-80 1980-81 1981-82 1982-83 1983-84 84.45 175.08 71.69 154.99 95.06 142.31 190.20 57.27 143.60 185.87 191.22 100.43 282.06 155.74

128.92 250.76 420.35 262.13 212.63 224.87 224.16 285.58 280.62 296.10 256.70 181.69 296.50 232.51 305.71 246.07 340.83 292.39 234.97 289.37 155.55 265.42 263.24 305.22 294.60 313.85 328.40 316.44 316.17 315.03 248.37 278.18 298.36 279.29 299.31 197.58 273.21 232.12 174.49 252.94 268.42 241.16 168.74 183.86 191.84 159.13 181.15 174.70 287.91 137.62 155.95 137.52 118.64 113.89 106.81 192.29 100.98 115.27 81.21 92.22 80.15 90.57 138.64 69.91 77.06 51.56 69.06 64.27 61.77 78.58 49.04 57.90 47.14 53.79 43.13 43.14 69.53 40.91 48.34 41.45 41.47 35.34 39.93 49.91 40.54 46.46 40.54 39.74 35.67 39.26 47.01 33.56 34.23 34.86 31.05 31.56 32.29 36.45 30.50 31.53 30.37 27.84 26.63 28.64 31.91 28.42 29.29 29.44 24.95 23.87 25.52 25.97 26.82 26.11 25.74 22.13 22.34 22.78 24.85 25.06 23.95 22.48 20.45 20.84 21.77 22.39 25.39 24.63 23.17 22.05 21.28 22.55 22.56 20.44 20.65 19.68 18.97 19.40 19.09 19.30 19.15 20.80 19.13 17.68 18.53 19.29 18.50 21.16 23.34 21.00 20.38 19.64 21.56 19.15 19.27 20.47 19.02 18.10 17.67 18.62 17.20 19.08 20.93 19.33 18.10 19.03 18.07 17.20 15.43 18.14 17.81 14.30 14.94 15.21 15.70 19.81 22.18 19.59 18.73 19.04 18.80 18.82 22.19 26.20 17.48 18.96 19.21 22.59 22.87

Page 95: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-40

25.82 32.69 25.78 22.72 23.44 27.16 29.33 24.59 40.54 26.32 22.23 32.93 27.75 27.00 36.80 52.61 32.40 37.19 36.41 30.60 28.89 40.72 63.70 44.43 48.55 50.11 40.03 41.32 76.85 81.50 65.54 96.02 75.39 68.31 51.04

120.77 74.90 77.64 105.15 60.31 128.57 80.04 143.95 67.32 103.93 145.98 83.81 144.91 137.93 3044.63 3388.16 3386.97 3250.26 2899.88 3441.52 3387.37 926.28 908.40 824.28 906.51 770.49 896.46 874.87 2118.34 2479.75 2562.69 2343.75 2129.39 2545.07 2512.51

1984-85 1985-86 1986-87 1987-88 1988-89 1989-90 1990-91 1991-92 216.87 115.58 58.31 163.32 130.84 199.31 172.56 237.54 164.75 134.84 179.41 140.62 130.38 146.19 139.00 293.91 160.65 158.46 318.42 164.21 229.00 147.57 297.52 255.45 174.84 158.08 210.25 235.14 223.54 163.41 250.11 330.69 106.32 171.97 251.62 205.62 238.82 236.09 212.12 286.91 188.84 204.68 342.83 262.64 286.80 295.52 202.82 293.59 154.80 146.10 241.88 179.56 239.22 157.76 200.39 208.83 172.03 177.75 202.88 163.17 200.34 161.43 200.07 149.41 183.94 168.98 159.28 169.48 152.18 174.39 181.49 176.67 120.02 118.89 113.46 127.07 104.18 103.51 134.03 138.42 67.80 75.60 66.57 91.48 76.36 71.42 102.92 101.56 39.24 58.48 51.44 74.26 85.15 60.32 76.65 66.49 29.55 44.57 37.63 49.01 51.80 44.02 57.16 56.45 25.20 46.49 32.87 38.68 41.15 35.72 47.01 42.64 24.79 37.05 30.89 37.75 37.85 35.73 41.85 44.29 19.67 27.97 25.14 28.41 31.20 29.70 33.69 42.08 17.17 24.34 23.28 28.24 29.40 26.86 32.16 34.52 15.86 21.50 21.80 25.72 27.14 25.21 30.36 32.47 14.86 18.91 20.82 24.19 25.10 23.71 28.31 32.94 14.24 17.32 20.13 22.65 23.92 22.32 27.04 30.62 14.75 17.90 20.88 23.10 25.65 24.18 27.97 38.00 12.83 14.78 17.99 21.00 22.12 19.62 20.75 29.07 11.99 13.92 17.28 20.74 21.05 19.55 19.87 29.60 13.41 14.82 18.48 21.78 22.61 21.51 21.90 31.16 11.55 14.00 16.49 17.24 19.90 19.85 20.05 28.31 11.41 14.32 16.88 15.51 19.56 19.83 20.20 26.54 9.44 11.43 13.69 13.92 15.47 15.62 16.28 26.61

13.54 15.87 17.40 16.62 20.30 19.68 21.11 26.43 14.90 17.85 20.03 18.16 21.21 20.95 22.73 29.15 17.73 20.08 26.19 21.66 25.87 41.15 31.42 33.67 17.08 20.47 27.39 22.37 24.50 26.81 41.37 30.53 20.86 31.54 25.80 53.77 26.33 32.90 36.19 37.34 26.79 42.26 38.84 71.42 26.68 46.55 43.54 45.58 36.40 53.33 41.52 102.25 31.75 66.72 69.60 56.85 42.07 89.21 38.75 122.22 59.29 196.28 102.70 88.07 125.76 51.01 75.22 139.01 124.75 187.10 142.27 88.57 2311.94 2370.40 2841.76 2931.98 2871.43 2938.53 3125.23 3500.94 561.85 680.96 645.41 955.41 774.60 1021.59 955.55 961.47 1750.09 1689.43 2196.35 1976.57 2096.83 1916.94 2169.68 2539.47

Page 96: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-41

1992-93 1993-94 1994-95 1995-96 1996-97 1997-98 1998-99 99.48 97.11 135.32 128.42 110.57 59.19 137.19 156.31 135.11 116.51 175.49 214.63 87.92 108.15 210.58 110.13 225.54 99.43 318.83 123.86 264.90 122.94 131.59 267.43 147.29 143.85 122.98 284.71 183.07 172.73 228.42 158.28 180.41 157.45 241.51 251.03 130.98 312.15 175.29 196.03 171.86 194.42 187.48 134.47 288.32 181.21 182.92 139.77 189.57 162.62 110.98 191.84 164.87 229.34 140.18 194.48 164.34 112.83 217.00 160.17 132.43 110.26 148.33 126.54 89.34 152.76 126.83 100.61 72.87 89.94 85.71 83.64 86.38 81.93 81.58 62.75 75.79 54.17 54.47 54.03 58.00 57.46 38.33 79.79 52.00 46.01 48.31 42.25 47.20 26.05 55.52 42.52 36.45 42.64 38.43 38.08 19.50 49.37 39.17 35.91 40.44 35.84 36.82 17.76 49.65 34.12 32.01 34.40 29.24 31.20 17.29 36.24 30.50 29.47 32.86 28.11 28.87 19.88 33.27 30.97 29.47 31.16 26.53 27.58 31.27 30.48 28.03 26.87 29.65 25.16 26.16 28.68 29.13 26.97 26.38 28.31 24.02 24.27 27.04 27.19 27.08 26.43 30.11 25.67 25.44 27.40 28.73 25.92 22.67 26.19 22.58 22.07 17.23 24.78 24.05 22.47 24.73 20.71 19.69 15.95 23.63 26.06 24.13 25.71 22.12 21.47 15.79 25.57 24.00 21.59 23.17 20.07 19.62 14.41 22.93 25.24 21.57 24.13 20.30 19.57 14.41 21.98 20.72 17.33 19.24 18.45 15.54 11.57 17.47 25.05 21.80 24.14 21.20 19.84 15.45 22.07 25.46 24.45 23.29 24.10 21.22 17.18 22.51 29.31 29.03 29.71 27.54 22.62 19.74 25.20 25.82 27.95 25.60 26.32 21.34 22.96 31.99 32.25 26.34 27.69 42.07 24.41 24.64 40.35 49.78 28.33 33.56 65.10 30.81 42.48 71.29 94.56 44.86 46.26 72.44 41.15 57.35 72.69 55.06 54.04 98.85 67.32 28.53 62.78 87.78 95.31 125.06 91.55 112.02 47.52 167.84 111.03

2694.24 2164.00 3137.38 2514.80 2609.67 2022.06 2969.62 889.97 800.63 861.68 857.58 661.01 734.67 960.85 1804.27 1363.37 2275.70 1657.22 1948.66 1287.39 2008.77

1999-2000 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 74.02 65.83 54.34 127.85 218.43 56.95 60.54

137.16 96.84 76.00 174.80 198.74 89.51 100.37 164.98 108.11 68.91 145.63 178.03 93.84 217.28 185.10 103.59 94.08 165.02 182.86 122.45 232.61 182.63 131.69 116.68 146.38 161.17 100.43 239.21 224.11 193.49 135.05 134.72 173.17 117.81 224.26 315.00 179.89 109.64 128.92 146.83 118.13 191.60 198.31 119.72 118.79 134.19 116.14 118.57 145.51 193.82 110.31 100.80 123.18 106.09 91.14 123.82 92.93 88.75 68.90 77.29 87.52 60.36 99.67

Page 97: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-42

76.00 60.88 45.61 64.62 64.46 62.73 73.43 61.43 43.05 31.97 40.48 52.78 42.57 54.96 43.55 31.50 25.62 30.03 36.12 30.62 33.94 35.72 28.88 23.75 26.15 27.70 26.37 27.58 35.13 29.67 24.39 26.44 27.02 25.79 25.52 29.13 26.14 21.37 22.20 22.52 22.06 20.80 26.99 24.96 19.47 21.04 20.71 18.89 19.77 24.74 23.02 17.01 19.84 17.72 16.62 19.61 23.27 21.44 15.26 19.34 16.43 15.05 18.32 22.04 19.57 14.23 18.34 15.28 13.99 16.00 22.92 21.11 14.94 16.64 16.01 14.82 17.57 20.51 18.29 13.22 11.23 14.35 12.92 15.33 20.16 17.75 12.77 9.01 14.38 12.80 14.85 22.31 19.36 13.66 10.07 12.62 13.09 17.19 19.90 16.76 12.49 13.05 11.61 12.53 14.94 19.79 16.93 12.98 13.65 13.11 13.46 14.74 17.49 13.66 10.36 12.30 12.05 10.81 13.68 20.04 17.25 14.88 15.82 13.96 15.11 16.98 20.70 16.85 16.61 15.84 15.22 17.25 17.11 23.83 20.21 20.27 24.65 18.55 20.53 18.55 24.45 19.62 20.68 22.48 16.43 20.02 19.01 27.11 21.15 24.63 38.29 16.83 22.70 21.38 29.93 22.96 33.69 45.70 19.40 36.26 36.50 34.62 31.19 47.85 51.59 24.07 63.42 81.28 75.82 46.95 146.55 107.66 47.77 54.03 114.86 89.76 43.12 105.27 163.67 65.39 44.68 178.69

2635.41 1870.49 1702.71 2218.10 2201.45 1628.32 2557.46 729.91 568.34 681.93 755.03 515.24 553.83 794.20 1905.50 1302.15 1020.78 1463.07 1686.22 1074.49 1763.26

SHONGTONG HYDRO- ELECTRIC PROJECT SUMMARY

Year

Annual Inflow

Mons Inflow

Non-Mons Inflow

Annual Energy

Non-Mons Energy Mons Energy

Total June- Sept. Oct. - May Total Oct. - May June- Sept. Mcum Mcum Mcum GWH GWH GWH

1972-73 9430.48 5543.91 3886.57 2904.74 1197.14 1707.60 1973-74 11207.55 8952.46 2255.09 3452.05 694.60 2757.45 1974-75 8332.99 5470.74 2862.25 2566.73 881.64 1685.09 1975-76 10337.02 7617.37 2719.65 3183.94 837.70 2346.24 1976-77 7614.72 5713.74 1900.98 2345.48 585.54 1759.94 1977-78 9884.61 6877.43 3007.18 3044.63 926.28 2118.34 1978-79 11007.49 8050.88 2956.61 3388.16 908.40 2479.75 1979-80 10989.70 8320.08 2669.61 3386.97 824.28 2562.69 1980-81 10552.27 7609.30 2942.97 3250.26 906.51 2343.75 1981-82 9414.65 6913.21 2501.44 2899.88 770.49 2129.39 1982-83 11179.42 8262.87 2916.55 3441.52 896.46 2545.07 1983-84 10991.58 8157.01 2834.57 3387.37 874.87 2512.51 1984-85 7505.84 5681.86 1823.98 2311.94 561.85 1750.09 1985-86 7695.71 5484.89 2210.81 2370.40 680.96 1689.43 1986-87 9231.54 7130.62 2100.93 2841.76 645.41 2196.35 1987-88 9513.86 6417.11 3096.75 2931.98 955.41 1976.57 1988-89 9322.29 6807.57 2514.71 2871.43 774.60 2096.83

Page 98: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-43

1989-90 9540.02 6223.46 3316.56 2938.53 1021.59 1916.94 1990-91 10153.02 7044.19 3108.84 3125.23 955.55 2169.68 1991-92 11356.59 8244.74 3111.86 3500.94 961.47 2539.47 1992-93 8747.01 5857.70 2889.32 2694.24 889.97 1804.27 1993-94 7025.60 4426.39 2599.21 2164.00 800.63 1363.37 1994-95 10193.56 7388.22 2805.34 3137.38 861.68 2275.70 1995-96 8157.85 5380.34 2777.50 2514.80 857.58 1657.22 1996-97 8472.64 6326.63 2146.00 2609.67 661.01 1948.66 1997-98 6564.67 4179.64 2385.03 2022.06 734.67 1287.39 1998-99 9648.35 6521.78 3126.57 2969.62 960.85 2008.77

1999-2000 8549.72 6186.37 2363.36 2635.41 729.91 1905.50 2000-01 6072.67 4227.52 1845.15 1870.49 568.34 1302.15 2001-02 5527.92 3314.03 2213.90 1702.71 681.93 1020.78 2002-03 7201.27 4750.07 2451.20 2218.10 755.03 1463.07 2003-04 7142.95 5474.58 1668.37 2201.45 515.24 1686.22 2004-05 5290.94 3488.47 1802.46 1628.32 553.83 1074.49 2005-06 8308.54 5724.64 2583.90 2557.46 794.20 1763.26

COMPUTATIONS FOR DEPENDABLE YEAR ON THE BASIS OF RUNOFF

90% dependable year=0.9x34= 30.6 31

50% dependable year=0.5x34= 17 17

S. No.

ANNUAL RUNOFF

RUNOFF IN Mcum IN

REMARKSDescending Order % DEP.

YEAR YEAR IN Mcum. YEAR IN Mcum. 1 1972-73 9430.48 11356.59 2.86 2 1973-74 11207.55 11207.55 5.71 3 1974-75 8332.99 11179.42 8.57 4 1975-76 10337.02 11007.49 11.43 5 1976-77 7614.72 10991.58 14.29 6 1977-78 9884.61 10989.70 17.14 7 1978-79 11007.49 10552.27 20.00 8 1979-80 10989.70 10330.84 22.86 9 1980-81 10552.27 10193.56 25.71 10 1981-82 9414.65 10153.02 28.57 11 1982-83 11179.42 9884.61 31.43 12 1983-84 10991.58 9648.35 34.29 13 1984-85 7505.84 9540.02 37.14 14 1985-86 7695.71 9513.86 40.00 15 1986-87 9231.54 9430.48 42.86 16 1987-88 9513.86 9414.65 45.71 17 1988-89 9322.29 1988-89 9322.29 48.57 50% 18 1989-90 9540.02 9231.54 51.43 mean 19 1990-91 10153.02 8747.01 54.29 year 20 1991-92 11356.59 8549.72 57.14 21 1992-93 8747.01 8472.64 60.00 22 1993-94 7025.60 8339.77 62.86 23 1994-95 10193.56 8308.54 65.71

Page 99: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-44

24 1995-96 8157.85 8157.85 68.57 25 1996-97 8472.64 7695.71 71.43 26 1997-98 6564.67 7614.72 74.29 27 1998-99 9648.35 7505.84 77.14 28 1999-2000 8549.72 7201.27 80.00 29 2000-01 6072.67 7142.95 82.86 30 2001-02 5527.92 7025.60 85.71 31 2002-03 7201.27 1997-98 6564.67 88.57 90% 32 2003-04 7142.95 6072.67 91.43 mean 33 2004-05 5290.94 5527.92 94.29 year 34 2005-06 8308.54 5290.94 97.14

SHONGTONG HYDRO- ELECTRIC PROJECT COMPUTATIONS FOR DEPENDABLE YEAR ON THE BASIS OF ENERGY

90% dependable year=0.9x34= 30.6 31

50% dependable year=0.5x34= 17 17

S.No. ANNUAL ENERGY ENERGY IN GWH

REM-ARKS DESCENDING ORDER YEAR IN GWH. YEAR IN GWH.

1 1972-73 2904.74 3500.94 2 1973-74 3452.05 3452.05 3 1974-75 2566.73 3441.52 4 1975-76 3183.94 3388.16 5 1976-77 2345.48 3387.37 6 1977-78 3044.63 3386.97 7 1978-79 3388.16 3250.26 8 1979-80 3386.97 3183.94 9 1980-81 3250.26 3137.38 10 1981-82 2899.88 3125.23 11 1982-83 3441.52 3044.63 12 1983-84 3387.37 2969.62 13 1984-85 2311.94 2938.53 14 1985-86 2370.40 2931.98 15 1986-87 2841.76 2904.74 16 1987-88 2931.98 2899.88 17 1988-89 2871.43 1988-89 2871.43 50% 18 1989-90 2938.53 2841.76 mean. 19 1990-91 3125.23 2694.24 year. 20 1991-92 3500.94 2635.41 21 1992-93 2694.24 2609.67 22 1993-94 2164.00 2566.73 23 1994-95 3137.38 2557.46 24 1995-96 2514.80 2514.80 25 1996-97 2609.67 2370.40 26 1997-98 2022.06 2345.48 27 1998-99 2969.62 2311.94 28 1999-2000 2635.41 2218.10 29 2000-01 1870.49 2201.45 30 2001-02 1702.71 2164.00 31 2002-03 2218.10 1997-98 2022.06 90% 32 2003-04 2201.45 1870.49 Dep.

Page 100: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-45

33 2004-05 1628.32 1702.71 year. 34 2005-06 2557.46 1628.32

SHONGTONG HYDRO- ELECTRIC PROJECT Discharges of 90%dep.& 50% dependable year.Year

MONTH PERIOD 90% dep.yr 50% dep. yr

1997-98 1988-89 I 222.42 491.70

JUN II 330.38 489.97 III 465.45 860.59 I 462.14 840.06

JUL II 591.68 897.48 III 587.12 979.82 I 525.25 898.98

AUG II 526.79 752.88 III 376.68 519.91 I 273.84 391.51

SEP II 235.80 286.97 III 144.05 319.98 I 97.90 194.66

OCT II 73.29 154.66 III 60.68 129.32 I 64.98 117.26

NOV II 74.72 110.47 III 117.50 101.98 I 107.79 94.33

DEC II 101.63 89.88 III 93.61 87.62 I 64.77 83.13

JAN II 59.93 79.11 III 53.95 77.24 I 54.16 74.79

FEB II 54.16 73.49 III 54.35 72.66 I 58.06 76.29

MAR II 64.57 79.69 III 67.45 88.39 I 86.27 92.08

APR II 92.61 98.94 III 159.64 100.28 I 215.51 119.33

MAY II 235.92 222.81 III 573.40 426.20

SHONGTONG HYDRO- ELECTRIC PROJECT POWER & ENERGY GENERATION IN 90% DEP. YEAR

Net Head = 124 mtr Efficiency. = 0.9114 inc. in MW = 25.00 MW

Average discharge in lean period= 71.59

Page 101: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-46

MONTH PERIOD 90% Dep.

Less water releases

15% of the average of

lean period

discharge

Net disch. in

90% Dep. Year

Un-Restricted Restricted Disch. 1997-

98 Power Energy Power Energy MW GWH MW GWH

275 I 222 10.74 211.68 234.70 56.33 234.70 56.33

JUN II 330 10.74 319.64 354.41 85.06 261.25 62.70 III 465 10.74 454.71 504.16 121.00 261.25 62.70 I 462 10.74 451.40 500.49 120.12 261.25 62.70

JUL II 592 10.74 580.94 644.12 154.59 261.25 62.70 III 587 10.74 576.38 639.06 168.71 261.25 68.97 I 525 10.74 514.51 570.47 136.91 261.25 62.70

AUG II 527 10.74 516.06 572.18 137.32 261.25 62.70 III 377 10.74 365.94 405.74 107.12 261.25 68.97 I 274 10.74 263.10 291.71 70.01 261.25 62.70

SEP II 236 10.74 225.06 249.54 59.89 249.54 59.89 III 144 10.74 133.31 147.81 35.47 147.81 35.47 I 98 10.74 87.16 96.64 23.19 96.64 23.19

OCT II 73 10.74 62.55 69.35 16.64 69.35 16.64 III 61 10.74 49.94 55.37 14.62 55.37 14.62 I 65 10.74 54.24 60.14 14.43 60.14 14.43

NOV II 75 10.74 63.98 70.94 17.02 70.94 17.02 III 117 10.74 106.76 118.37 28.41 118.37 28.41 I 108 10.74 97.05 107.60 25.82 107.60 25.82

DEC II 102 10.74 90.89 100.77 24.19 100.77 24.19 III 94 10.74 82.87 91.89 24.26 91.89 24.26 I 65 10.74 54.03 59.90 14.38 59.90 14.38

JAN II 60 10.74 49.19 54.54 13.09 54.54 13.09 III 54 10.74 43.21 47.91 12.65 47.91 12.65 I 54 10.74 43.42 48.14 11.55 48.14 11.55

FEB II 54 10.74 43.42 48.14 11.55 48.14 11.55 III 54 10.74 43.61 48.35 9.28 48.35 9.28 I 58 10.74 47.32 52.47 12.59 52.47 12.59

MAR II 65 10.74 53.83 59.68 14.32 59.68 14.32 III 67 10.74 56.71 62.88 16.60 62.88 16.60 I 86 10.74 75.53 83.75 20.10 83.75 20.10

APR II 93 10.74 81.87 90.78 21.79 90.78 21.79 III 160 10.74 148.91 165.10 39.62 165.10 39.62 I 216 10.74 204.77 227.04 54.49 227.04 54.49

MAY II 236 10.74 225.18 249.67 59.92 249.67 59.92 III 573 10.74 562.66 623.85 164.70 261.25 68.97

TOTAL ENERGY 1917.75 1298.03 PLANT LOAD FACTOR 0.54 INC. INCREASE IN ENERGY 0.00 GWH / MW 4.72 % AGE UTILISATION 67.69 PLF (LEAN- SEASON) 0.25 95% availibilty of 261.25

Page 102: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-47

Power

SHONGTONG HYDRO- ELECTRIC PROJECT POWER & ENERGY GENERATION IN 90% DEP. YEAR

Net Head = 124 m Eff. = 0.9114 inc. in MW = 25.00 MW349.35

Restricted Restricted Restricted Restricted

Power Energy Power Energy Power Energy Power Energy MW GWH MW GWH MW GWH MW GWH 300 325 350 375

234.70 56.33 234.70 56.33 234.70 56.33 234.70 56.33 285.00 68.40 308.75 74.10 332.50 79.80 354.41 85.06 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 75.24 308.75 81.51 332.50 87.78 356.25 94.05 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 75.24 308.75 81.51 332.50 87.78 356.25 94.05 285.00 68.40 291.71 70.01 291.71 70.01 291.71 70.01 249.54 59.89 249.54 59.89 249.54 59.89 249.54 59.89 147.81 35.47 147.81 35.47 147.81 35.47 147.81 35.47 96.64 23.19 96.64 23.19 96.64 23.19 96.64 23.19 69.35 16.64 69.35 16.64 69.35 16.64 69.35 16.64 55.37 14.62 55.37 14.62 55.37 14.62 55.37 14.62 60.14 14.43 60.14 14.43 60.14 14.43 60.14 14.43 70.94 17.02 70.94 17.02 70.94 17.02 70.94 17.02

118.37 28.41 118.37 28.41 118.37 28.41 118.37 28.41 107.60 25.82 107.60 25.82 107.60 25.82 107.60 25.82 100.77 24.19 100.77 24.19 100.77 24.19 100.77 24.19 91.89 24.26 91.89 24.26 91.89 24.26 91.89 24.26 59.90 14.38 59.90 14.38 59.90 14.38 59.90 14.38 54.54 13.09 54.54 13.09 54.54 13.09 54.54 13.09 47.91 12.65 47.91 12.65 47.91 12.65 47.91 12.65 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.35 9.28 48.35 9.28 48.35 9.28 48.35 9.28 52.47 12.59 52.47 12.59 52.47 12.59 52.47 12.59 59.68 14.32 59.68 14.32 59.68 14.32 59.68 14.32 62.88 16.60 62.88 16.60 62.88 16.60 62.88 16.60 83.75 20.10 83.75 20.10 83.75 20.10 83.75 20.10 90.78 21.79 90.78 21.79 90.78 21.79 90.78 21.79

165.10 39.62 165.10 39.62 165.10 39.62 165.10 39.62 227.04 54.49 227.04 54.49 227.04 54.49 227.04 54.49 249.67 59.92 249.67 59.92 249.67 59.92 249.67 59.92 285.00 75.24 308.75 81.51 332.50 87.78 356.25 94.05

TOTAL ENERGY 1356.74 1411.36 1464.37 1516.94 PLANT LOAD FACTOR 0.52 0.50 0.48 0.46 INC.INCREASE IN ENERGY 58.71 54.62 53.01 52.57

Page 103: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-48

GWH / MW 4.52 4.34 4.18 4.05 % AGE UTILISATION 70.75 73.59 76.36 79.10 PLF (LEAN- SEASON) 0.23 0.21 0.19 0.18

285.00 308.75 332.50 356.25

SHONGTONG HYDRO- ELECTRIC PROJECT POWER & ENERGY GENERATION IN 90% DEP. YEAR

Net Head = 124 mtr Eff. = 0.9114 inc. in MW = 25.00 MW

Restricted Restricted Restricted Restricted

Power Energy Power Energy Power Energy Power Energy MW GWH MW GWH MW GWH MW GWH 400 425 450 475

234.70 56.33 234.70 56.33 234.70 56.33 234.70 56.33 354.41 85.06 354.41 85.06 354.41 85.06 354.41 85.06 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 100.32 403.75 106.59 427.50 112.86 451.25 119.13 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 100.32 403.75 106.59 405.74 107.12 405.74 107.12 291.71 70.01 291.71 70.01 291.71 70.01 291.71 70.01 249.54 59.89 249.54 59.89 249.54 59.89 249.54 59.89 147.81 35.47 147.81 35.47 147.81 35.47 147.81 35.47 96.64 23.19 96.64 23.19 96.64 23.19 96.64 23.19 69.35 16.64 69.35 16.64 69.35 16.64 69.35 16.64 55.37 14.62 55.37 14.62 55.37 14.62 55.37 14.62 60.14 14.43 60.14 14.43 60.14 14.43 60.14 14.43 70.94 17.02 70.94 17.02 70.94 17.02 70.94 17.02

118.37 28.41 118.37 28.41 118.37 28.41 118.37 28.41 107.60 25.82 107.60 25.82 107.60 25.82 107.60 25.82 100.77 24.19 100.77 24.19 100.77 24.19 100.77 24.19 91.89 24.26 91.89 24.26 91.89 24.26 91.89 24.26 59.90 14.38 59.90 14.38 59.90 14.38 59.90 14.38 54.54 13.09 54.54 13.09 54.54 13.09 54.54 13.09 47.91 12.65 47.91 12.65 47.91 12.65 47.91 12.65 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.35 9.28 48.35 9.28 48.35 9.28 48.35 9.28 52.47 12.59 52.47 12.59 52.47 12.59 52.47 12.59 59.68 14.32 59.68 14.32 59.68 14.32 59.68 14.32 62.88 16.60 62.88 16.60 62.88 16.60 62.88 16.60 83.75 20.10 83.75 20.10 83.75 20.10 83.75 20.10 90.78 21.79 90.78 21.79 90.78 21.79 90.78 21.79

165.10 39.62 165.10 39.62 165.10 39.62 165.10 39.62 227.04 54.49 227.04 54.49 227.04 54.49 227.04 54.49 249.67 59.92 249.67 59.92 249.67 59.92 249.67 59.92 380.00 100.32 403.75 106.59 427.50 112.86 451.25 119.13

TOTAL ENERGY 1564.25 1611.56 1653.13 1694.17 PLANT LOAD 0.45 0.43 0.42 0.41

Page 104: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-49

FACTOR INC.INCREASE IN ENERGY 47.31 47.31 41.57 41.04 GWH / MW 3.91 3.79 3.67 3.57 % AGE UTILISATION 81.57 84.03 86.20 88.34 PLF (LEAN- SEASON) 0.17 0.16 0.15 0.14

380.00 403.75 427.50 451.25

SHONGTONG HYDRO- ELECTRIC PROJECT POWER & ENERGY GENERATION IN 90% DEP. YEAR

Net Head = 124 mtr Eff. = 0.9114 inc. in MW = 25.00 MW

Restricted Restricted Restricted Restricted Restricted

Power Energy Power Energy Power Energy Power Energy Power Energy MW GWH MW GWH MW GWH MW GWH MW GWH 500 525 550 575 600

234.70 56.33 234.70 56.33 234.70 56.33 234.70 56.33 234.70 56.33 354.41 85.06 354.41 85.06 354.41 85.06 354.41 85.06 354.41 85.06 475.00 114.00 498.75 119.70 504.16 121.00 504.16 121.00 504.16 121.00 475.00 114.00 498.75 119.70 500.49 120.12 500.49 120.12 500.49 120.12 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 570.00 136.80 475.00 125.40 498.75 131.67 522.50 137.94 546.25 144.21 570.00 150.48 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 570.00 136.80 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 570.00 136.80 405.74 107.12 405.74 107.12 405.74 107.12 405.74 107.12 405.74 107.12 291.71 70.01 291.71 70.01 291.71 70.01 291.71 70.01 291.71 70.01 249.54 59.89 249.54 59.89 249.54 59.89 249.54 59.89 249.54 59.89 147.81 35.47 147.81 35.47 147.81 35.47 147.81 35.47 147.81 35.47 96.64 23.19 96.64 23.19 96.64 23.19 96.64 23.19 96.64 23.19 69.35 16.64 69.35 16.64 69.35 16.64 69.35 16.64 69.35 16.64 55.37 14.62 55.37 14.62 55.37 14.62 55.37 14.62 55.37 14.62 60.14 14.43 60.14 14.43 60.14 14.43 60.14 14.43 60.14 14.43 70.94 17.02 70.94 17.02 70.94 17.02 70.94 17.02 70.94 17.02

118.37 28.41 118.37 28.41 118.37 28.41 118.37 28.41 118.37 28.41 107.60 25.82 107.60 25.82 107.60 25.82 107.60 25.82 107.60 25.82 100.77 24.19 100.77 24.19 100.77 24.19 100.77 24.19 100.77 24.19 91.89 24.26 91.89 24.26 91.89 24.26 91.89 24.26 91.89 24.26 59.90 14.38 59.90 14.38 59.90 14.38 59.90 14.38 59.90 14.38 54.54 13.09 54.54 13.09 54.54 13.09 54.54 13.09 54.54 13.09 47.91 12.65 47.91 12.65 47.91 12.65 47.91 12.65 47.91 12.65 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.35 9.28 48.35 9.28 48.35 9.28 48.35 9.28 48.35 9.28 52.47 12.59 52.47 12.59 52.47 12.59 52.47 12.59 52.47 12.59 59.68 14.32 59.68 14.32 59.68 14.32 59.68 14.32 59.68 14.32 62.88 16.60 62.88 16.60 62.88 16.60 62.88 16.60 62.88 16.60 83.75 20.10 83.75 20.10 83.75 20.10 83.75 20.10 83.75 20.10 90.78 21.79 90.78 21.79 90.78 21.79 90.78 21.79 90.78 21.79

165.10 39.62 165.10 39.62 165.10 39.62 165.10 39.62 165.10 39.62

Page 105: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-50

227.04 54.49 227.04 54.49 227.04 54.49 227.04 54.49 227.04 54.49 249.67 59.92 249.67 59.92 249.67 59.92 249.67 59.92 249.67 59.92 475.00 125.40 498.75 131.67 522.50 137.94 546.25 144.21 570.00 150.48

TOTAL ENERGY 1735.21 1776.25 1807.60 1837.24 1866.88 Plant load factor 0.40 0.39 0.38 0.36 0.36 INC. Increase in Energy 41.04 41.04 31.36 29.64 29.64 GWH / MW 3.47 3.38 3.29 3.20 3.11 % AGE UTILISATION 90.48 92.62 94.26 95.80 97.35 PLF (LEAN- SEASON) 0.14 0.13 0.12 0.12 0.11

475.00 498.75 522.50 546.25 570.00

SHONGTONG HYDRO- ELECTRIC PROJECT ENERGY AT 95% AVAILABILITY IN 90% DEP. YEAR

MONTH PERIOD 90% Dep. Power Energy Net Dis. MW GWH at 95%m/c

1997-98 450 Availability I 211.68 234.70 56.33

JUN II 319.64 354.41 85.06 III 454.71 427.50 102.60 I 451.40 427.50 102.60

JUL II 580.94 427.50 102.60 III 576.38 427.50 112.86 I 514.51 427.50 102.60

AUG II 516.06 427.50 102.60 III 365.94 405.74 107.12 I 263.10 291.71 70.01

SEP II 225.06 249.54 59.89 III 133.31 147.81 35.47 I 87.16 96.64 23.19

OCT II 62.55 69.35 16.64 III 49.94 55.37 14.62 I 54.24 60.14 14.43

NOV II 63.98 70.94 17.02 III 106.76 118.37 28.41 I 97.05 107.60 25.82

DEC II 90.89 100.77 24.19 III 82.87 91.89 24.26 I 54.03 59.90 14.38

JAN II 49.19 54.54 13.09 III 43.21 47.91 12.65 I 43.42 48.14 11.55

FEB II 43.42 48.14 11.55 III 43.61 48.35 9.28 I 47.32 52.47 12.59

MAR II 53.83 59.68 14.32 III 56.71 62.88 16.60 I 75.53 83.75 20.10

Page 106: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-51

APR II 81.87 90.78 21.79 III 148.91 165.10 39.62 I 204.77 227.04 54.49

MAY II 225.18 249.67 59.92 III 562.66 427.50 112.86 TOTAL ENERGY= 1653.13

SHONGTONG HYDRO- ELECTRIC PROJECT POWER & ENERGY GENERATION IN 50% DEP. YEAR

Net Head = 124 mtr Efficiency = 0.9114 inc. in MW = 25.00 MW

Average discharge in lean period= 81.36

MONTH PERIOD 50% Dep.

Less water releases 15%

of the average of lean period discharge

Net disch.in

90% Dep. Year

Un-Restricted Restricted Disch.

1988-89 Power Energy Power Energy MW GWH MW GWH 275

I 492 12.20 479.50 531.64 127.59 261.25 62.70 JUN II 490 12.20 477.77 529.73 127.13 261.25 62.70

III 861 12.20 848.39 940.65 225.76 261.25 62.70 I 840 12.20 827.86 917.89 220.29 261.25 62.70

JUL II 897 12.20 885.28 981.56 235.57 261.25 62.70 III 980 12.20 967.62 1072.85 283.23 261.25 68.97 I 899 12.20 886.78 983.22 235.97 261.25 62.70

AUG II 753 12.20 740.68 821.23 197.10 261.25 62.70 III 520 12.20 507.70 562.91 148.61 261.25 68.97 I 392 12.20 379.30 420.55 100.93 261.25 62.70

SEP II 287 12.20 274.76 304.64 73.11 261.25 62.70 III 320 12.20 307.77 341.24 81.90 261.25 62.70 I 195 12.20 182.45 202.29 48.55 202.29 48.55

OCT II 155 12.20 142.45 157.95 37.91 157.95 37.91 III 129 12.20 117.11 129.85 34.28 129.85 34.28 I 117 12.20 105.06 116.48 27.96 116.48 27.96

NOV II 110 12.20 98.26 108.95 26.15 108.95 26.15 III 102 12.20 89.77 99.54 23.89 99.54 23.89 I 94 12.20 82.13 91.06 21.85 91.06 21.85

DEC II 90 12.20 77.68 86.13 20.67 86.13 20.67 III 88 12.20 75.41 83.61 22.07 83.61 22.07 I 83 12.20 70.93 78.64 18.87 78.64 18.87

JAN II 79 12.20 66.91 74.19 17.80 74.19 17.80 III 77 12.20 65.04 72.11 19.04 72.11 19.04 I 75 12.20 62.58 69.39 16.65 69.39 16.65

FEB II 73 12.20 61.29 67.95 16.31 67.95 16.31 III 73 12.20 60.45 67.03 12.87 67.03 12.87 I 76 12.20 64.08 71.05 17.05 71.05 17.05

MAR II 80 12.20 67.49 74.83 17.96 74.83 17.96 III 88 12.20 76.19 84.47 22.30 84.47 22.30 I 92 12.20 79.87 88.56 21.25 88.56 21.25

APR II 99 12.20 86.73 96.17 23.08 96.17 23.08 III 100 12.20 88.08 97.65 23.44 97.65 23.44

Page 107: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-52

I 119 12.20 107.12 118.77 28.50 118.77 28.50 MAY II 223 12.20 210.60 233.50 56.04 233.50 56.04

III 426 12.20 414.00 459.02 121.18 261.25 68.97

Total energy 2752.89 1408.42Plant load factor 0.58 Increase in energy 0.00 GWH / MW 5.12 % Utilisation 51.16 PLF (Lean- Season) 0.28 95% Availability of Power 261.25

Restricted Restricted Restricted Restricted

Power Energy Power Energy Power Energy Power Energy MW GWH MW GWH MW GWH MW GWH 300 325 350 375

285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 75.24 308.75 81.51 332.50 87.78 356.25 94.05 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 75.24 308.75 81.51 332.50 87.78 356.25 94.05 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 304.64 73.11 304.64 73.11 304.64 73.11 285.00 68.40 308.75 74.10 332.50 79.80 341.24 81.90 202.29 48.55 202.29 48.55 202.29 48.55 202.29 48.55 157.95 37.91 157.95 37.91 157.95 37.91 157.95 37.91 129.85 34.28 129.85 34.28 129.85 34.28 129.85 34.28 116.48 27.96 116.48 27.96 116.48 27.96 116.48 27.96 108.95 26.15 108.95 26.15 108.95 26.15 108.95 26.15 99.54 23.89 99.54 23.89 99.54 23.89 99.54 23.89 91.06 21.85 91.06 21.85 91.06 21.85 91.06 21.85 86.13 20.67 86.13 20.67 86.13 20.67 86.13 20.67 83.61 22.07 83.61 22.07 83.61 22.07 83.61 22.07 78.64 18.87 78.64 18.87 78.64 18.87 78.64 18.87 74.19 17.80 74.19 17.80 74.19 17.80 74.19 17.80 72.11 19.04 72.11 19.04 72.11 19.04 72.11 19.04 69.39 16.65 69.39 16.65 69.39 16.65 69.39 16.65 67.95 16.31 67.95 16.31 67.95 16.31 67.95 16.31 67.03 12.87 67.03 12.87 67.03 12.87 67.03 12.87 71.05 17.05 71.05 17.05 71.05 17.05 71.05 17.05 74.83 17.96 74.83 17.96 74.83 17.96 74.83 17.96 84.47 22.30 84.47 22.30 84.47 22.30 84.47 22.30 88.56 21.25 88.56 21.25 88.56 21.25 88.56 21.25 96.17 23.08 96.17 23.08 96.17 23.08 96.17 23.08 97.65 23.44 97.65 23.44 97.65 23.44 97.65 23.44

118.77 28.50 118.77 28.50 118.77 28.50 118.77 28.50

Page 108: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-53

233.50 56.04 233.50 56.04 233.50 56.04 233.50 56.04 285.00 75.24 308.75 81.51 332.50 87.78 356.25 94.05

TOTAL ENERGY 1484.23 1559.05 1629.16 1695.67 PLANT LOAD FACTOR 0.56 0.55 0.53 0.52 INC.INCREASE IN ENERGY 75.81 74.82 70.11 66.51 GWH / MW 4.95 4.80 4.65 4.52 % AGE UTILISATION 53.92 56.63 59.18 61.60 PLF (LEAN- SEASON) 0.26 0.24 0.22 0.21

285.00 308.75 332.50 356.25

Restricted Restricted Restricted Restricted

Power Energy Power Energy Power Energy Power Energy MW GWH MW GWH MW GWH MW GWH 400 425 450 475

380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 100.32 403.75 106.59 427.50 112.86 451.25 119.13 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 100.32 403.75 106.59 427.50 112.86 451.25 119.13 380.00 91.20 403.75 96.90 420.55 100.93 420.55 100.93 304.64 73.11 304.64 73.11 304.64 73.11 304.64 73.11 341.24 81.90 341.24 81.90 341.24 81.90 341.24 81.90 202.29 48.55 202.29 48.55 202.29 48.55 202.29 48.55 157.95 37.91 157.95 37.91 157.95 37.91 157.95 37.91 129.85 34.28 129.85 34.28 129.85 34.28 129.85 34.28 116.48 27.96 116.48 27.96 116.48 27.96 116.48 27.96 108.95 26.15 108.95 26.15 108.95 26.15 108.95 26.15 99.54 23.89 99.54 23.89 99.54 23.89 99.54 23.89 91.06 21.85 91.06 21.85 91.06 21.85 91.06 21.85 86.13 20.67 86.13 20.67 86.13 20.67 86.13 20.67 83.61 22.07 83.61 22.07 83.61 22.07 83.61 22.07 78.64 18.87 78.64 18.87 78.64 18.87 78.64 18.87 74.19 17.80 74.19 17.80 74.19 17.80 74.19 17.80 72.11 19.04 72.11 19.04 72.11 19.04 72.11 19.04 69.39 16.65 69.39 16.65 69.39 16.65 69.39 16.65 67.95 16.31 67.95 16.31 67.95 16.31 67.95 16.31 67.03 12.87 67.03 12.87 67.03 12.87 67.03 12.87 71.05 17.05 71.05 17.05 71.05 17.05 71.05 17.05 74.83 17.96 74.83 17.96 74.83 17.96 74.83 17.96 84.47 22.30 84.47 22.30 84.47 22.30 84.47 22.30 88.56 21.25 88.56 21.25 88.56 21.25 88.56 21.25 96.17 23.08 96.17 23.08 96.17 23.08 96.17 23.08

Page 109: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-54

97.65 23.44 97.65 23.44 97.65 23.44 97.65 23.44 118.77 28.50 118.77 28.50 118.77 28.50 118.77 28.50 233.50 56.04 233.50 56.04 233.50 56.04 233.50 56.04 380.00 100.32 403.75 106.59 427.50 112.86 451.25 119.13

TOTAL ENERGY 1760.08 1824.49 1887.23 1945.94 PLANT LOAD FACTOR 0.50 0.49 0.48 0.47 INC.INCREASE IN ENERGY 64.41 64.41 62.74 58.71 GWH / MW 4.40 4.29 4.19 4.10 % AGE UTILISATION 63.94 66.28 68.55 70.69 PLF (LEAN- SEASON) 0.19 0.18 0.17 0.16

380.00 403.75 427.50 451.25

Restricted Restricted Restricted Restricted

Power Energy Power Energy Power Energy Power Energy MW GWH MW GWH MW GWH MW GWH 500 525 550 575

475.00 114.00 498.75 119.70 522.50 125.40 531.64 127.59 475.00 114.00 498.75 119.70 522.50 125.40 529.73 127.13 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 475.00 125.40 498.75 131.67 522.50 137.94 546.25 144.21 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 475.00 125.40 498.75 131.67 522.50 137.94 546.25 144.21 420.55 100.93 420.55 100.93 420.55 100.93 420.55 100.93 304.64 73.11 304.64 73.11 304.64 73.11 304.64 73.11 341.24 81.90 341.24 81.90 341.24 81.90 341.24 81.90 202.29 48.55 202.29 48.55 202.29 48.55 202.29 48.55 157.95 37.91 157.95 37.91 157.95 37.91 157.95 37.91 129.85 34.28 129.85 34.28 129.85 34.28 129.85 34.28 116.48 27.96 116.48 27.96 116.48 27.96 116.48 27.96 108.95 26.15 108.95 26.15 108.95 26.15 108.95 26.15 99.54 23.89 99.54 23.89 99.54 23.89 99.54 23.89 91.06 21.85 91.06 21.85 91.06 21.85 91.06 21.85 86.13 20.67 86.13 20.67 86.13 20.67 86.13 20.67 83.61 22.07 83.61 22.07 83.61 22.07 83.61 22.07 78.64 18.87 78.64 18.87 78.64 18.87 78.64 18.87 74.19 17.80 74.19 17.80 74.19 17.80 74.19 17.80 72.11 19.04 72.11 19.04 72.11 19.04 72.11 19.04 69.39 16.65 69.39 16.65 69.39 16.65 69.39 16.65 67.95 16.31 67.95 16.31 67.95 16.31 67.95 16.31 67.03 12.87 67.03 12.87 67.03 12.87 67.03 12.87 71.05 17.05 71.05 17.05 71.05 17.05 71.05 17.05 74.83 17.96 74.83 17.96 74.83 17.96 74.83 17.96 84.47 22.30 84.47 22.30 84.47 22.30 84.47 22.30 88.56 21.25 88.56 21.25 88.56 21.25 88.56 21.25

Page 110: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-55

96.17 23.08 96.17 23.08 96.17 23.08 96.17 23.08 97.65 23.44 97.65 23.44 97.65 23.44 97.65 23.44 118.77 28.50 118.77 28.50 118.77 28.50 118.77 28.50 233.50 56.04 233.50 56.04 233.50 56.04 233.50 56.04 459.02 121.18 459.02 121.18 459.02 121.18 459.02 121.18

TOTAL ENERGY 2000.43 2052.87 2105.31 2150.28 Plant load factor 0.46 0.45 0.44 0.43 Inc. increase in energy 54.49 52.44 52.44 44.97 Gwh / mw 4.00 3.91 3.83 3.74 % Age utilisation 72.67 74.57 76.48 78.11 PLF (lean- season) 0.15 0.15 0.14 0.13

475.00 498.75 522.50 546.25 SHONGTONG HYDRO- ELECTRIC PROJECT

ENERGY AT 95% AVAILABILITY IN 50% MEAN YEAR

MONTH PERIOD 50% Mean. Power Energy Net Dis. MW GWH at 95%m/c

1988-89 450 Availability I 491.70 427.50 102.60

JUN II 489.97 427.50 102.60 III 860.59 427.50 102.60 I 840.06 427.50 102.60

JUL II 897.48 427.50 102.60 III 979.82 427.50 112.86 I 898.98 427.50 102.60

AUG II 752.88 427.50 102.60 III 519.91 427.50 112.86 I 391.51 420.55 100.93

SEP II 286.97 304.64 73.11 III 319.98 341.24 81.90 I 194.66 202.29 48.55

OCT II 154.66 157.95 37.91 III 129.32 129.85 34.28 I 117.26 116.48 27.96

NOV II 110.47 108.95 26.15 III 101.98 99.54 23.89 I 94.33 91.06 21.85

DEC II 89.88 86.13 20.67 III 87.62 83.61 22.07 I 83.13 78.64 18.87

JAN II 79.11 74.19 17.80 III 77.24 72.11 19.04 I 74.79 69.39 16.65

FEB II 73.49 67.95 16.31 III 72.66 67.03 12.87 I 76.29 71.05 17.05

MAR II 79.69 74.83 17.96 III 88.39 84.47 22.30 I 92.08 88.56 21.25

APR II 98.94 96.17 23.08 III 100.28 97.65 23.44

Page 111: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-56

I 119.33 118.77 28.50 MAY II 222.81 233.50 56.04

III 426.20 427.50 112.86 TOTAL ENERGY= 1887.23

Page 112: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-57

Letter from CEA for capacity up gradation of STKHEP

Page 113: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-58

Annexure 4.2

List of water sources in the project affected area of Shongtong Karchham HEP, 450 MW

Name of Source Discharge Time Gram Panchayat Mebar

Date 19.11.2010Potharng Nala 72 l \ minute 4:30 pm Koyato Nala 100 L\ minute 4:30 pm Listi 180 L\ minute 4:32 pm Langthelu (Dharangche Nala) 1500 L\ minute 5:55 pm

Date 20.11.2010Dhjarangche Nala 48 L\ minute 9:30am Shogaley 72 L\ minute 9:40am Nagaso 5 L\ minute 10:30am Shormo 51.4 L\ minute 11:20am Bulgar Nala 400 L\ minute 11:55am (Dakelach Nala Runing) 24 L\ minute 12:30 pm Gane Nagas 90 L\ minute 12:50 pm Kusum Nala 45 L\ minute 12:55 pm Kulang Khad 180 L\ minute 4:30 pm

Date 21.11.2010Jhakharang Nala 72 L\ minute 5:30 pm Baspa garang (Jagat Bahadur) Damang Chango 9 L\ minute 9:30am Damang Chango (Bal Bahadur) 0.16 L\ minute 9:40am Damang Dhank 6 L\ minute 10:00am Yotch Garang (Parmeshwar Negi) 48 L\ minute 10:30am Yotch Garang (Bhupinder Negi) Fayang Chaden (Bhupinder Negi) 8 L\ minute 10:40am Limkate (Baspa Nala) 90 L\ minute 12:05 pm Baro (Surjeet Negi) 20 L\ minute 12:30 pm

Ralli Village

Yanpiyang 2.5 L\ minute 4:30am

Gram Panchayat Barang

Date 23.11.2010Nalo Nagas (Mangal Sen) 0.33 L\ minute 11:15am Kare (Madan) 1 L\ minute 11:47am Batuka (Raj Mohan) 2\1\2 L\ minute 12:25 pm Kanka (Near School) 2 L\ minute 12:55 pm Konka-1 (Near School) 1 L\ minute 1:00 pm Leparang (Kalam Sukh) 1\2 L\ minute 2:05 pm Ramo (Derta land) 10.5 L\ minute 2:35 pm Ramo (Prem Lal) 2 L\ minute 2:40 pm Ramo (Vidya Krishan) 2 L\ minute 2:50 pm Ramo ( Near Ranbir House) 5 L\ minute 3:00 pm Ramo (Ranbir Singh) 1\2 L\ minute 3:10 pm Choko Nala (IPH) 144 L\ minute 3:40 pm

Date 24.11.2010Choko Nala (Om Prakash) 600 L\ minute 12:05 pm

Page 114: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-59

Name of Source Discharge Time Choko Nala (Om Prakash) 36 L\ minute 12:10 pm Kholanka Nagas 216 L\ minute 12:40 pm Reyang Sho (Jawahri Lal) 216 L\ minute 2:05 pm Reyang Sho (Jawahri Lal) 72 L\ minute 2:08 pm Reyang Sho (Agya Ram) 108 L\ minute 2:10 pm Reyang Sho (Jawahri Lal) 192 L\ minute 3:25 pm Choko Nala (Jiyu lal 12 L\ minute 3:45 pm Gotangden (Prem Kumar) 2 L\ minute 4:15 pm Gotangden (Manning) 120 L\ minute 4:50 pm Teg Running (Lambardar) 120 L\ minute 5:30 pm

Date 22.11.2010Dumte Nagas-1 (Sashi) 600 L\ minute 1:00 pm Dumte Nagas-2 (Sashi) 200 L\ minute 1:10 pm Dumte Nagas-3 (Hoshiar Singh) 60 L\ minute 1:30 pm Dumte Nagas-4 (Sashi) 4 L\ minute 2:06 pm Dumte Nagas-5 (Sashi) 5 L\ minute 2:10 pm Golpang (Agya Ram) 1 L\ minute 2:30 pm Kare Nagas (Near Roop Singh House) 1 L\ minute 2:45 pm Tinchpa-1 (Bhajan Dass) 4 L\ minute 3:15 pm Tinchpa-2 (Bhajan Dass) 12 L\ minute 3:25 pm Kuta (Vimal) 0.3 L\ minute 3:50 pm Kuta Saring (Raghunath) 0.5 L\ minute 4:30 pm

Date 02.12.2010Konke (Sunder Lal) 0.25 L\ minute 11:30am Khiyawang (Rameshwar Singh) 1 L\ minute 11:45am Soling (Ashok Negi) 4 L\ minute 1:40 pm Kholanka (Ram Singh) 2 L\ minute 1:50 pm Kholanka (Burgur Sen) 3 L\ minute 2:05 pm Kholanka (Jawal Sen) 3.6 L\ minute 2:30 pm Kholanka (On path) 135 L\ minute 2:40 pm Soling (Murthu Devi) 0.16 L\ minute 2:50 pm Skamlinge (Bhajan Das) 0.05 L\ minute 3:30 pm Seryo (Sanjeev) 0.025 L\ minute 3:35 pm

Date 06.12.2010Marua (Chhetan Nargu) 16 L\ minute 12:15 pm Deksho (Rajmohan & Sandeep) 120 L\ minute 12:55 pm Nagaso (Sandeep) 900 L\ minute 1:15 pm Nagaso-II (Sandeep) 5,400 L\ minute 1:25 pm Labale (Shakti Devi) 60 L\ minute 1:35 pm Tangnal Labale 450 L\ minute 2:00 pm Sharmi (Shashibhushan 12 L\ minute 2:25 pm &Naresh Mehta) Nalo (Jigu Lal) 60 L\ minute 3:15 pm

Date 10.12.2010Ticharothen (Shashi Negi) 2 L\ minute 1:30 pm Liche Nala 2400 L\ minute 4:30 pm Date 11-12-10

Raldhang Nala

2:36 pm

Page 115: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-60

Name of Source Discharge Time Gram Panchayat Powari

Date 14.12.2010

Rocknagas Kangrang (Krishan Dev)

10 L\ minute 12:10 pm

Shonchaden 5 L\ minute 12:50 pm Kangrang garang 5400 L\ minute 3:15 pm Kangrang garang 336 L\ minute 3:15 pm Varoo Nala 72 L\ minute 3:30 pm

Date 16.12.2010Gotangden Nagasti (Lafan Chand 2 L\ minute 12:05 pm & Uma Singh) Gotangden Nagasti (Lafan Chand 1 L\ minute 12:15 pm Baleyo (Hukum Singh) 24 L\ minute 1:05 pm Panugo (Sudesh Kumar) 36 L\ minute 1:30 pm Panugo Kuwang (Govt. Land) 16 L\ minute 1:55 pm Dakho (Rajender Singh) 25 L\ minute 2:10 pm Fore (Kedar Chand) 8 L\ minute 3:30 pm Fore (Lafan Chand) 6 L\ minute 3:35 pm Salich Runing-I (Sahi Ram) 1 L\2 minute 4:20 pm Salich Runing-II (Sahi Ram) 12 L\ minute 4:22 pm Ankalangti (Govt. Land) 48 L\ minute 4:35 pm Salich Runing-III (Sahi Ram) 5 L\ minute 4:40 pm

Date 20.12.2010Palesti (Sartal Singh) 60 L\ minute 12: 05 pm Dumchader (Krishan Gopal) 15 L\ minute 12: 20 pm Guthuden (Krishan Gopal) 60 L\ minute 12: 45 pm Guthuden (Prakash Thangi) 4 L\ minute 12: 55 pm Kholangden 45 L\ minute 1: 05 pm Khawangra (Veerbhadra) 30 L\ minute 1: 45 pm Wazeer bawdi 18 L\ minute 2: 45 pm Kulizar 32 L\ minute 3: 00 pm Homticho 8 L\ minute 3: 30 pm Khogruden 6 L\ minute 3: 50 pm Homticho-II 10 L\ minute 4: 05 pm

Date 21.12.2010Kholgaden-I (Hira Singh) 120 L\ minute 11: 45am Kholgaden-II (Govt. Land) 180 L\ minute 12: 05 pm Thithrioden 24 L\ minute 3: 00 pm Chamansho 2 L\ minute 3: 30 pm

Gram Panchayat Khawangi

Date 18.02.2011Pickicho (Yashwant Singh) 36 L\ minute 10:40AM Pichicho-II -do- 30 L\ minute 10:45AM Chona-I (Bupender Singh) 12 L\ minute 11:30am Chona-II -do- 60 L\ minute 11:35am Chona-III 18 L\ minute 11:40am Chona-iv 24 L\ minute 11:50am Chona Nagas-I 225 L\ minute 12:10 pm Balgarang-I (Mahesh) 52 L\ minute 1:20 pm Balgarang-II -do- 42.8 L\ minute 1:25 pm

Page 116: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-61

Name of Source Discharge Time Balgarang-III -do- 60 L\ minute 1:28 pm Jangnaloo (Baldev Singh) 78 L\ minute 2:35 pm Thawabayo (Sujan Singh) 20 L\ minute 3:45 pm Bansi Niwas (Suraj Bansi) 6 L\ minute 3:55 pm Jawangai (Baldev Singh) 21.6 L\ minute 4:05 pm Dolingche (Anit Negi) 3 L\ minute 4:07 pm Bargarang (Narender) 2 L\ minute 4:10 pm Bargarang (Rattan Prakash) 2 L\ minute 4:15 pm

Date 19.02.2011Danicho Saring-I (Virender) 3 L\ minute 12:15 pm Danicho Saring-II (Virender) 11 L\ minute 12:20 pm Kimrang (Gori Shanker) 22 L\ minute 12:40 pm Shaksho-I (Arun Bandhari) 8 L\ minute 1:20 pm Shaksho-II (Arun Bandhari) 4 L\ minute 1:25 pm Shaksho-III (Arun Bandhari) 30 L\ minute 1:30 pm Shaksho-IV (Arun Bandhari) 30 L\ minute 1:40 pm Ontrang 70 L\ minute 2:05 pm Darro (Near Old School) 13 L\ minute 2:15 pm Changrang (Dinesh Negi) 24 L\ minute 3:00 pm

Date 20.02.2011Baruat 25 L\ minute 11.30am Kharshang-II (Sher Singh) 96 L\ minute 11.45am Kabare-II (Surinder Kumar) 48 L\ minute 12.05 pm Kabare (Cheering) 36 L\ minute 12.08 pm Kabare-I (Surinder Negi) 12 L\ minute 12.15 pm KabareMain (Surinder Singh) 2 L\ minute 12.25 pm Kabare-IV (Bhag Singh) 25 L\ minute 01.05 pm Kharshang-I (Praveen Kumar) 30 L\ minute 1.30 pm Ontrang-II (Vijay Kumar) 8 L\ minute 1:55 pm Ontrang-Main (Sukh Path) 120 L\ minute 2:00 pm Ontrang (Narsum Devi) 8 L\ minute 2:05 pm Kamantang (Mohan Kumari) 16 L\ minute 2:30 pm Sutre (Gori Shankar) 24 L\ minute 2:40 pm Domrya (Rattan Prakash) 6 L\ minute 3:05 pm Yalcharang 90 L\ minute 3:20 pm Khomto (Dev Raj) 12 L\ minute 3:30 pm Khane Rim (Bhajan Singh) 10 L\ minute 3:40 pm Khawangi Khas (Devta Sahib) 10 L\ minute 4:10 pm

Date: 21.02.2011Kabre-V (Keshvi Nand) 2 L\ minute 11:20am Kabre-VI (Dil Bhadhur) 16 L\ minute 11:25am Tainalang-I (Bupender Singh) 8 L\ minute 11:40am Tainalang-II (Bupender Singh) 50 L\ minute 11:45am Shakuthang (Sukh Path) 120 L\ minute 12:05 pm Tainalang-III (Jai Dev) 12 L\ minute 12:15 pm Tainalang-IV (Rishi Ram) 96 L\ minute 12:30 pm Tainalang-V (Lal Chand) 50 L\ minute 12:45 pm Tainalang-VI (Vidya Basker) 48 L\ minute 12:55 pm Tainalang-VII (Vidya Basker) 72 L\ minute 1:05 pm Markaging Nagas 450 L\ minute 1:30 pm Durga Nagas 850 L\ minute 1:55 pm Pangshu Nagas (Budh Raj) 300 L\ minute 2:10 pm Dakho (Rishi Ram) 6 L\ minute 2:15 pm Kagrah (Rattan Singh) 5 L\ minute 2:30 pm

Page 117: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-62

Name of Source Discharge Time Kagrah (Public) 3 L\ minute 2:35 pm Kagrah-I (Manjeet) 5 L\ minute 2:40 pm Powari 50 L\ minute 3.00 pm Powari-I 4 L\ minute 3.05 pm Torti (Kanta Devi) 72 L\ minute 3.15 pm Torti-I (Bhisham Lal) 50 L\ minute 3.30 pm Ralo 5 L\ minute 3.45 pm Ralo-I 10 L\ minute 3.50 pm Ralo-II 10 L\ minute 4.00 pm

Page 118: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-63

Annexure-4.5

Page 119: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-64

Page 120: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-65

Page 121: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-66

Page 122: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-67

Page 123: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-68

Page 124: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-69

Page 125: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-70

Page 126: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-71

Page 127: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-72

Page 128: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-73

Page 129: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-1

CHAPTER-4

BASELINE SETTING FOR PHYSICO-CHEMICAL ASPECTS 4.1 GENERAL

Before start of any Environmental Impact Assessment study, it is necessary to identify the baseline levels of relevant environmental parameters which are likely to be affected as a result of the construction and operation of the proposed project. A similar approach has been adopted for conducting the EIA study for the proposed Shongtong-Karchham hydroelectric Project. A Scoping Matrix as outlined in Table-3.1 of Chapter-3 was formulated to identify various issues likely to be affected as a result of the proposed project. Based on the specific inputs likely to accrue in the proposed project, aspects to be covered in the EIA study were identified. The other issues as outlined in the Scoping Matrix were then discarded. Thus, planning of baseline survey commenced with the short listing of impacts and identification of parameters for which the data needs to be collected. The baseline status has been divided into following three categories:

• Physico-chemical aspects; • Ecological aspects; and • Socio-Economic aspects. The baseline setting for physico-chemical aspects have been covered in this Chapter.

4.2 METEOROLOGY

The climate of the project area is characterized by cool and dry climate. Meteorologically, the year can be divided into three distinct seasons. Winter season sets in from the month of October and continues up to February, followed by summer season from March to June. The area receives rainfall under the influence of south-west monsoons over a period of three months from July to September.

Temperature

Temperature rises rapidly after March and the month of July is the hottest month of the year with mean daily maximum temperature going up to 23.0 °C. With the withdrawal of monsoons, by the end of October, there is a sharp decrease in temperature. The months of January and February are the coolest months of the year, with mean daily minimum temperature as low as -2.3 °C. The month wise temperature variations are depicted in Figure-4.1.

Rainfall

The total annual rainfall is about 766.5 mm per annum. The maximum rainfall is received in the months from January to March. About 55% of the rainfall is received during winter season. A part of the rainfall received during winter months is in the form of snow. The rainfall as received in various months of the year is given in Figure-4.2.

Humidity

The average `humidity’ observed in the project area is about 50% Apart from the monsoon months. Humidity is generally low from 35 to 54.2%. In monsoon months, humidity is more than 80%.

Page 130: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-2

Cloud cover

In the winter season months from July to September, skies are generally heavily clouded. Heavy cloud cover persists in short spells during the winter months when the area is affected by the passing western disturbances.

The nearest meteorological station is Kalpa. The detailed data on various meteorological aspects was collected for Kalpa station. The average meteorological conditions are summarized in Table 4.1.

TABLE-4.1: Average Meteorological conditions in the Project Area

Month Mean Temp. Daily (°C) Rainfall (mm) Relative Humidity (%)

Max. Min. At 0830 hrs At 1730 hrs January 88.6 51.2 39.6 February 6.7 -2.5 121.9 54.2 45.4 March 10.7 0.2 208.7 49.6 42.4 April 17.6 4.9 60.2 44.6 37.6 May 21.7 7.9 36.3 51.6 42.6 June 22.6 10.9 42.3 67.6 54.2 July 23.0 13.3 41.2 81.4 64.2 August 22.3 12.9 39.7 83.8 68.6 September 21.1 9.5 33.6 72.0 60.8 October 19.7 5.0 2.5 45.6 40.2 November 14.7 1.9 63.2 40.4 35.4 December 10.0 -1.1 28.3 45.4 36.0 Average 16.4 5.1 57.3 47.3 Total 766.5 Source: India Meteorological Department (IMD), Kapla station average of 5 year data.

Wind Direction

Seasonal (summer, winter and monsoon) two year period wind direction based on the nearest representative meteorological station (Aerial distance of 350 meters) the wind rose diagram of project area from November 2008 to December 2010 are given in Figure 4.3. It is to be noted that project is located in a steep river gorge with cliffs and very Steep Mountain slopes on both sides of the river. Wind can thus move in only two directions (either upstream (u/s) or downstream (d/s)). However, there are no houses situated up to at least 500 m (vertical distance) from the project sites.

HPPCL, as per its corporate policy is going to install its own project specific metrological station in the project area.

4.3 GEOLOGY

Regional Geology

The project area and its surroundings expose one of the oldest stack of rocks in the core Himalayas (Central Crystalines). This metamorphic sequence is characterised by polyphase regional metamorphism varying from green schists facies to amphibolite facies. These rocks in this part of Himalayas have been categorized in to Vakirata Group comprising of felspathic gneiss, quartzite, high grade schists and magmatites, which are exposed in an accurate

Page 131: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-3

pattern. This rest over the rocks belonging to the Jutogh, Salkhala and Rampur Groups along Vakirata Thrust.

These rocks are intruded by Rakcham and Nako granites. The Vakirata Group of rocks extends towards NE along Satluj and Spiti valleys up to Shipki La and Sumdo. The Vakirata Group has further been divided in to three formations, viz- Kharo, Morang and Shiasu, of which the rocks belonging to Kharo Formations are exposed in the area around the proposed project.

Geology of Project Area

Barrage Site

The river Satluj near barrage site flows towards south through a moderately wide valley having moderately sloping right bank and steep left flank. Along the barrage axis, riverine deposits mixed with slope wash deposits are present from river bed level (+1,932 m elevation) to + 1950 m elevation. Between El +1,950 m and El + 2,050 m quartz biotite gneisses belonging to Kharo formation of Vakirata groups of rocks is exposed along a precipitous rocky slope. The rock strikes, in general, in N 25° to 300 W-S 25° to 300 E with 40° to 45°dips towards NE. The rocks are moderately jointed and some of the joints are observed to be extending for more than 100 m. These rocks are traversed by five sets of joints which include foliation joints.

Head Race Tunnel (HRT)

The HRT will have to negotiate two major drainages, i.e. Tangling and Shyong. Keeping in huge thickness of Tangling fan and presence of thick fluviglacial deposit in view, it is apprehended that there are chances of these being encountered in HRT. The fan deposits consists of big boulders of granite gneiss and quartzite, probably brought down by palaeo landslide and glaciers.

Power House

In view of steep valley slopes in this reach, unstable slopes at frequent interval and problem of avalanches, an underground power house site near village Ralli on the left bank of river Satluj has been selected. At this site thinly foliated quartzites with thin schist band trending in N 400 to N 65°W-S400E, S65°E and dipping at 200 to 450 in a NE direction i.e.; upstream are exposed along a steep slope. The site for power house has been selected downstream of the nallah so that it does not block the approach or the tail race tunnel outlet of the underground power house site. The elevation of Power house at top level will be EL. 1834.65m.

The quarzites at this location are thinly foliated and are closely jointed. The quartzites are exposed for a distance of 110 m upstream and 260 m downstream of the proposed power house location along the National Highway-22. Further downstream the area on the left abutment is covered with thick slide debris material. The quartzites are interlaced with thin schist bands and are schistose at places

4.4 SEISMOLOGY

The project area is located in Shimla Seismo Tectonic Block of Western Himalayas. This block is bounded by Sundernagar Fault in West and Kaurik Sumdo Fault in the east. Historical data indicates that largest earthquake experienced in this block is Kinnaur earthquake of January 1975 (M= 6.8).

Page 132: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-4

Apart from seismic events that have occurred in this seismic block, major earthquakes like Kangra Earthquake of April 1905 (M= +8), earthquake of 1916 (M=7.5), earthquake of 1966 (M= 7 and the Uttarkashi Earthquake of 1991 (M=6.5) have been recorded in adjoining seismic blocks within a distance of 200 km of the project site. The origin of these seismic events has been attributed to various tectonic features, which extend in to this seismic block. The location of various tectonic features like Kaurik Sumdo Fault, Raura Fault, Vakirata thrust and Jutogh thrust in the vicinity of the project area and categorisation of the project area in zone-IV, of siesmic zoning map of India indicate that necessary seismic coefficient has to be incorporated in the designs of various structures of the project. Detailed evaluation of seismic status of the area becomes more necessary due to its location in the category having highest seismic risk.

The project area falls under seismic zone-IV, as per the seismic zoning Map of India given in IS: 1894: 2002 i.e. highest seismic zone in Western Himalayas. In the past, the region has been affected with a number of strong earthquakes. Since year 1720, 17 nos. of earthquakes of intensity greater than 5 on Richter scale have been reported in the area. The most devastating earthquake recorded in the region, is the Kangra earthquake of 1905, which caused considerable damage to life and property in district Kangra. Other major earthquakes are Chamba-1945, 1947, 1950 (M=6.5, 6.6, & 5.5); Dharamshala 1978, 1986 (M= 5 & 5.7) and Kathua-1980 (M=5.3). The major earthquake causing considerable damage in last 100 years in the region are given in Table- 4.2.

TABLE-4.2 List of major earthquakes in the region in last 100 years

Year Earthquake Magnitude 1905 Kangra 7.8 1906 Kullu 6.4 1930 Sultanpur 6.0 1945 Chamba 6.0 1947 Chamba 6.0 1950 Chamba 6.0 1951 Chamba-Udhampur 6.0 1955 Lahual-Spiti 6.0 1962 Chamba-Udhampur 6.0 1975 Kinnaur 6.8 1978 Dharamshala 5.0 1980 Kathua 5.3 1986 Dharamshala 5.7 1986 Uttarkashi 6.6 2004 Kangra 5.1

Source: Amateur Seismic Centre, Pune, 2007

The important earthquakes within 200 km of the proposed Shongtong-Karchham Hydroelectric site are given below in Table-4.3.

Page 133: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-5

TABLE-4.3 Important Earthquake Within 200 km from Shongtong-Karchham Hydro-Electric project Site

Date Epicenter Magnitude Latitude (N) Longitude (E)

05.03.1842 30.00 78.00 6.5 16.06.1902 31.00 79.00 6.0 04.04.1905 32.25 76.25 8.0 13.06.1906 31.00 79.00 6.0 28.02.1908 32.00 77.00 7.0 20.10.1937 31.10 78.00 6.0 12.05.1939 32.50 78.00 6.3 22.06.1945 32.80 76.90 6.5 10.06.1947 32.60 75.90 6.0 27.06.1955 32.50 78.50 6.0 12.04.1963 32.00 78.79 6.0 19.01.1975 32.35 78.76 6.8 20.01.1991 30.75 78.86 6.6 (mb) 7.1 (ms)

In order to monitor impact of blasting, Seismograph at an appropriate location will be established and monitoring done in association with representatives of Gram Panchayat. Water resources and houses in all villages and their vicinity shall be inventorized by HPPCL to develop a baseline in case of any claim. Damages occurring subsequently as may be attributed to project construction shall be either restored or compensated at project cost. A Dam break analysis along with inundation map is under process.

4.5 LAND USE PATTERN The land utilization for the Kinnaur district is given in Table-4.4 and total land requirement of the project is summarized in Table-4.5.

TABLE-4.4: Land utilization for the district Kinnaur S. No. Land Utilization Area (Ha) 1. Geographical area by village papers 623,742 2. Forests 37,579 3. Net available for cultivation

i. Barren & un-culturable land 130,859 ii. Land put to non-agriculture Uses 124,602

4. Other cultivated land i. Permanent pastures and other grazing land 317,697 ii. Culturable waste 3,610 iii. Land under misc. tree crops and graves not

included in net area sown 84

5. Fallow land i. Current fallows 1,770 ii. Other fallows 57

6. Net area sown 7,484 7. Total cropped area 8,745 8. Area sown more than once 1,261 9. Intensity of cropping 116.85%

Source: Directorate of Land Records, Himachal Pradesh

Page 134: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-6

TABLE-4.5 Land required for various project appurtenances

S. No.

Name of Components of Project

Ownership-wise land requirement Total land required (Perm/Temp) Area of forest land (ha) Area of private land (ha) Grand

Total Temporary Permanent Total

Temporary Permanent Sub- Total Temporary Permanent Sub- Total

1 Diversion barrage, diversion tunnel and supporting structure

3.0000 30.221 33.221 - 0.7498 0.7498 33.9708 3.0000 30.9708 33.9708

2 Head Race Tunnel and Adits

1.5426 9.7449 11.2875 - - - 11.2875 1.5426 9.7449 11.2875

3 Surge shaft and associate structures

- 1.2125 1.2125 - - - 1.2125 - 1.2125 1.2125

4 Pressure shaft (U/G)

- 0.3608 0.3608 - - - 0.3608 - 0.3608 0.3608

5 Power House, tail race tunnel and associate structure

0.5000 0.9470 1.4470 - - - 1.4470 0.5000 0.9470 1.4470

6 6 nos. Dumping Area

5.1000 - 5.1000 3.1944 - 3.1944 8.2944 8.2944 - 8.2944

7 Approach Roads - 4.3416 4.3416 - - - 4.3416 - 4.3416 4.3416 8 Job facilities and

other requirement 2.0970 8.1073 10.2043 - 9.5038 9.5038 19.7081 2.0970 17,6111 19.7081

9. Quarry 1.8500 - 1.8500 - - - 1.8500 1.8500 - 1.8500 Total 14.0896 54.9351 69.0247 3.1944 10.2536 13.4480 82.4727 17.2840 65.1887 82.4727

Unit-Ha

Page 135: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-7

The project area has a typical mountainous terrain with moderate to high relief. The altitude varies from 1500 to over 3000 m from the mean sea level. There are no habitations along the river from Diversion structure to TRT. The national highway-22 follows the river, and otherwise it is too steep for habitation.

Forests are the major land use category. As a part of EIA study, digital satellite data of the area is being procured from National Remote Sensing Agency (NRSA), Hyderabad for assessing the land use pattern. The data is processed in house using sophisticated image processing software like ERDAS-Imagine to study the land use, land cover and forest details. Ground truth verification studies are to be undertaken to verify the signatures of various land use category which then will be used to classify the satellite imagery. The FCC and the classified imagery of the study area are given in Figures 4.4 and 4.5 respectively. The land use pattern of the study area is described in Table-4.6.

TABLE - 4.6: Land use pattern of the study area based on satellite data Type of land Area in Ha (%) Dense vegetation 13,577 (25.93) Open Vegetation 10,133 (19.35) Alpine Pasture 5,793 (11.06) Barren land 13,712 (26.19) Snow cover 7,454 (14.24) Agriculture 846 (1.62) Settlements 235 (0.45) Water bodies 605 (1.16) Total 52,355 (100.0)

The major land use category of land in the study area is forest land as it accounts for 45.26% of the study area. Area under agriculture is only 1.62% of the total study area. Pasture account for about 11.06% of the study area. Settlements and snow cover account for about 0.45% and 14.24%, respectively of the total study area.

4.6 SOILS

Soil is the product of geological, chemical and biological interactions. The soils in the region vary according to altitude and climate. The soil in the project area and study area are young like any other region of Himalayas. The vegetal cover is one of the most important influencing factors characterizing the soil types in a region. Soil on the slope above 30o, due to erosion and mass wasting processing, are generally shallow and usually have very thin surface horizons. Such soils have medium to coarse texture. Residual soils are well developed on level summits of lesser Himalayas, Subsoil are deep and heavily textured.

As a part of field studies, soil depth at various locations in the catchment area have been collected during winter, summer and post-monsoon seasons, which were then analyzed. The sampling stations are shown in Figure - 4.6. The results of the analysis of soil samples for the winter (February 2008), summer (May 2008) and post - monsoon (October 2008) seasons are given in Tables 4.7 to 4.9 respectively.

Page 136: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-8

TABLE - 4.7: Results of soil sampling analysis of study area in winter season

Parameter S1 S2 S3 S4 S5

pH 7.30 7.65 7.17 7.15 7.80 Electrical Conductivity µomhs/cm 46.90 23.90 35.40 49.80 70.50 Organic matter (%) 1.60 0.45 2.14 0.87 0.38 Nitrates (mg/kg) 6.20 5.30 8.50 7.50 13.00 Sodium (mg/kg) 110.88 82.31 47.63 99.98 103.76 Magnesium (mg/kg) 247.41 480.70 184.40 78.90 291.80 Chlorides (mg/kg) 168.00 199.50 94.50 136.50 126.00 Sulphates (mg/kg) <0.1 <0.1 <0.1 <0.1 <0.1 Phosphates (mg/kg) 704.24 418.02 564.80 259.15 693.41 Copper (mg/kg) 6.04 15.96 6.45 1.59 12.92 Manganese (mg/kg) 137.86 94.28 29.04 20.00 42.75 Chromium (mg/kg) 21.68 26.89 18.79 15.82 20.75 Barium (mg/kg) 58.44 55.37 48.53 45.66 47.34 Potassium (mg/kg) 3791.02 4100.37 1994.30 1228.61 2254.82 Lead (mg/kg) 18.03 29.98 30.00 20.00 6.19 Cyanide (mg/kg) ND ND ND ND ND

TABLE - 4.8: Results of soil sampling analysis of study area in summer season

Parameter S1 S2 S3 S4 S5 pH 7.46 7.53 7.62 7.31 7.45 Electrical Conductivity µomhs/cm 73.70 56.60 86.90 89.60 76.5 Organic matter (%) 0.29 0.31 5.04 0.32 0.30 Nitrates (mg/kg) 7.10 8.30 8.70 9.70 8.80 Sodium (mg/kg) 139.17 38.55 144.99 173.82 96.31 Magnesium (mg/kg) 621.30 107.80 373.90 541.60 187.60 Chlorides (mg/kg) 105.00 157.00 168.00 115.50 105.00 Sulphates (mg/kg) <0.1 <0.1 <0.1 <0.1 <0.1 Phosphates (mg/kg) 601.42 329.06 559.97 874.62 446.11 Copper (mg/kg) 56.17 3.89 20.80 23.01 4.69 Manganese (mg/kg) 251.10 85.39 108.50 38.86 160.68 Chromium (mg/kg) 30.97 17.63 24.20 24.25 19.61 Barium (mg/kg) 50.21 43.04 49.55 50.19 51.90 Potassium (mg/kg) 5,715.99 1,113.50 4,444.78 3,259.95 1,107.78 Lead (mg/kg) 59.05 16.00 22.40 22.16 24.30 Cyanide (mg/kg) ND ND ND ND ND

TABLE - 4.9: Results of soil sampling analysis of study area in post-monsoon season Parameter S1 S2 S3 S4 S5 pH 7.32 7.42 7.51 7.29 7.34 Electrical Conductivity µomhs/cm 67.80 48.65 79.85 84.50 79.5 Organic matter (%) 0.32 0.33 5.60 0.52 0.40 Nitrates (mg/kg) 6.70 9.30 8.90 9.80 9.20 Sodium (mg/kg) 145.12 46.15 156.46 165.57 89.45 Magnesium (mg/kg) 616.20 105.60 358.70 518.40 168.50 Chlorides (mg/kg) 105.00 157.00 168.00 115.50 105.00 Sulphates (mg/kg) <0.1 <0.1 <0.1 <0.1 <0.1

Page 137: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-9

Parameter S1 S2 S3 S4 S5 Phosphates (mg/kg) 601.42 329.06 559.97 874.62 446.11 Copper (mg/kg) 56.17 3.89 20.80 23.01 4.69 Manganese (mg/kg) 251.10 85.39 108.50 38.86 160.68 Chromium (mg/kg) 30.97 17.63 24.20 24.25 19.61 Barium (mg/kg) 50.21 43.04 49.55 50.19 51.90 Potassium (mg/kg) 5,715.99 1,113.50 4,444.78 3,259.95 1,107.78 Lead (mg/kg) 59.05 16.00 22.40 22.16 24.30 Cyanide (mg/kg) ND ND ND ND ND

The pH of soil at various sites lies within neutral range. The levels of NPK indicate moderate to high soil productivity. The sodium levels do not indicate any potential for soil salinization or adverse impacts on soil productivity.

In a hydroelectric project, no significant impact on soil quality is expected barring, soil pollution at local level due to disposal of construction waste. For amelioration of such impacts appropriate management measures are recommended.

4.7 WATER RESOURCES

4.7.1 Water Resources

Shontong-Karchham Hydro Electric Project is a run of river scheme project on River Satluj with all the project components proposed to be located on the left bank of Satluj river to harness the available hydel potential of the river. The river Satluj rises near Rakas Tal which is fed by Mansarovar Lake at an altitude of 4,570 m above mean sea level and passes through the Tibetan province of `Nari Khorsam'. The principal source i.e. lake Mansarovar is fed by glaciers of Ganglung, Gaungni. The southern glaciers of Kailash, Peak Kamer and Peak Riva Phargul also feed the river. The river then traverses through plateau between Zakhar and Ladakh ranges. The river flows through a very deep (915 m) channel and is fed by glaciers. The river Satluj is joined by several tributaries in `Nari Khorsam' which include Zangchu, Drama Yankti, Chonak, Manglan, Trunsaco, Sumna, Trape, etc. The banks in the Tibetan portion are less eroded because the activities of geological agents like surface runoff, water, snow, etc. are limited. There is no vegetation in the area and when the snow melts, deep channels are formed on the surface. The river Satluj enters India near Shipkila after traversing a distance of 320 km in the Tibetan province of Nari Khorsam. On entering the Indian portion, river takes a south-westerly direction and traverses for a distance of 320 km to reach Bhakra gorge, crossing which, it enters the plains of Punjab.

The principal tributaries of river Satluj below Shipkila i.e. in India are Spiti, Kashming, Baspa, Bhaba, Nogli, Kurpan, Nauli, Sholding, Seer, Bharari, Ali and Gambher Khad, river Spiti which confluences at Namgia, at 14 km upstream of Pooh is the biggest tributary.

The total catchment area intercepted up to Shongtong barrage site is 47,132 km2. The altitude in the catchment area drained by river Spiti varies from 3,048 m to 4,570 m. The rainfall in the area is scarce. The area is devoid of vegetation and melting snow forms deep flow channels. Majority of the silt carried by the river comes mainly from the Spiti area, where due to degraded status of the catchment, high soil erosion rates are observed. The catchment area from Namgia to Shongtong dam site is bounded hills of moderate height and the altitude varies from 1,936 m to 3,048 m. The area has little rainfall but witnesses heavy snow fall. The runoff due to melting of snow is the chief source of water. At higher elevations `Chilgoza' plantations are observed. The

Page 138: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-10

area has steep slopes with little vegetal cover and very little rain. The river is perennial in nature as it is fed by snow melt. About one-fourth of the catchment is under snow. The final series as approved by CWC (Central Water Commission) for the project planning along with Power potential studies using the above approved series as submitted to CEA (Central Electricity Authority) is enclosed as Annexure 4.1. Initially installed capacity of the project is 402 MW as approved by CEA vide letter copy enclosed as per Annexure 4.1.

As per the Project Report 2002, the design flood has been estimated using various methods for flood frequency analysis is given in Table-4.10.

TABLE-4.10: Design Flood estimated for the Shongtong hydroelectric Project Return period year Maximum flood average Inst. Flood 1.15 time of maximum

flood 5 1,785.81 2,053.68 10 2,163.47 2,488.00 20 2,525.83 2,904.71 50 2,995.37 3,444.67 100 3,346.38 3,848.34 200 3,472.27 3,993.11 500 3,849.94 4,427.43

1,000 4,479.39 5,151.30 Source: Project Report 2002. 4.7.2 Water resources study The Water Sources inventory for Shongtong–Karchham HEP was carried out to assess the total discharge in river Satluj from different water sources, a study of major and minor waterfalls flowing in to Satluj River was carried out in different villages in the catchment area of the project. The study includes photography and measurement of discharge per minute for each of these water sources. This study will help in comparing pre-project and post-project scenario of the water resources of the catchment area of the project. The above mentioned inventory for project is attached as Annexure 4.2. 4.7.3 Climate Change At present there are no studies available to show the effect of climate change on flow regime, including during the next decade or so and consequent effect of the same on generation capacity. However, the ecological flow downstream is related with inflow; as such, 15% of average lean months’ flow shall always be maintained downstream during the life of the project. Recently a draft report (still under finalization) has been made available through a separate study of ADB called Integrated Water Resource Management {ADB RSC-C00666 (IND)}. The said report assesses the impact of climate change in short, medium and long term. As per this report, there is no serious adverse impact on the project in the medium term (up to 30 years). Even after this, the hydrology is apparently not going to change much. Moreover, as a climate change adaptation measure, a storage project at the top of the catchment (within Indian territory) has been planned to arrest silt and to make assured regulated water availability for all the downstream projects in a cascade.

Page 139: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-11

4.7.4 Water use

As such there is no population dependent on the water flow of the river to be diverted except for washing of remains of cremation (as per Hindu rights) which takes 100 litre/body. This requirement can be easily met from 15% of lean season discharge.

The major sources of water in the project area are rivers and nallahs, which flow adjacent to the habitations. These are used to meet the major water requirements in the project as well as study area. The water is conveyed to the point of consumption, i.e. habitations, through open channels, which is then utilized for meeting domestic consumption. The water of river Satluj in the intervening catchment is not used for meeting domestic requirements.

Majority of the cropped area is rain fed. The study area in general, depends on rainfall for irrigation. Rainwater and snow are absorbed within the soil, which then percolates through pores and crevices and reappears in the form of springs. During monsoons, number and discharge of the springs increases. The supply of water in the perennial springs gets reduced in winter and summer seasons. Spring water is generally collected in a tank and stored for irrigation during the periods of scarcity. The spring water is also used for meeting domestic requirements in many areas. The water is carried through surface channels called `gools' into the fields located at lower levels.

4.8 WATER QUALITY

The major sources of water in the project area are river and nallahs, which flows adjacent to the habitation. These are used to meet the major water requirement in the project area as well as study area. The water is conveyed to the point of consumption i.e. habitations and agriculture field through open channel, then utilized for meeting various requirement. There are no major industries in the catchment. Likewise, pollution load from domestic sources is also insignificant.

As a part of the field studies, water samples from river Satluj and other tributaries from various locations were collected and analysed for various physico-chemical parameters. The various sampling locations are shown in Figure-4.6 and are listed as below:

W1- About 100m upstream of proposed barrage site; W2- About 500 m downstream to the barrage site; W3- Near Tangl ing Khad; W4- Near proposed Power house site; and W5- Drinking water at Powari village.

The water sampling results for three seasons namely winter (February 2008), summer (May 2008) and post-monsoon (October 2008) are given in Tables-4.12 to 4.14 respectively. The drinking water quality standards are enclosed as Annexure-II.

TABLE-4.12: Water quality in the study area in winter season

Parameter W1 W2 W3 W4 W5 pH 7.5 7.4 7.4 7.3 7.5 Electrical conductivity (µs/cm) 451 210 290 203 263 Total Dissolved Solids, mg/l 279 130 179 125 163 Total Suspended Solids, mg/l 844 466 60 558 80 Total alkalinity (CaCO3), mg/l 196.8 98.4 118 118 118

Page 140: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-12

Parameter W1 W2 W3 W4 W5 Carbonates, mg/l Nil Nil Nil Nil Nil D.O., mg/l 9.7 10.2 9.2 9.6 10.1 BOD, mg/l 2.3 3.2 2.1 2.7 13.2 COD, mg/l 13.8 18.4 13.8 18.5 27.6 Nitrate as NO3, mg/l BDL BDL BDL BDL BDL Phosphate as PO4, mg/l 0.28 0.28 BDL 0.16 0.40 Fluoride as F, mg/l BDL BDL BDL 0.2 BDL Chloride as Cl, mg/l 7.9 7.9 7.9 7.9 7.9 Sulphate as SO4, mg/l 46 45.3 56 49 86 Sodium as Na, mg/l 13 11 11 8 9 Potassium as K, mg/l 1 1 2 1 1 Calcium as Ca, mg/l 48.2 34.7 44.2 28.4 38.7 Magnesium as Mg, mg/l 18.3 1.9 1.9 4.8 3.3 Oil & Grease, mg/l BDL BDL BDL BDL BDL Phenolic Compound BDL BDL BDL BDL BDL Manganese, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Copper, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Zinc, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Chromium, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Cyanides, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Total Coliforms, MPN/100 ml 14 21 21 21 12

TABLE-4.13: Water quality in the study area in summer season Parameter W1 W2 W3 W4 W5 pH 7.8 7.3 7.5 7.3 7.6 Electrical conductivity (µs/cm) 380 230 310 240 267 Total Dissolved Solids, mg/l 285 150 210 150 172 Total Suspended Solids, mg/l 854 475 70 558 80 Total alkalinity (CaCO3), mg/l 208 97 120 128 121 Carbonates, mg/l Nil Nil Nil Nil Nil D.O., mg/l 9.5 10.0 9.0 9.3 9.8 BOD, mg/l 2.5 2.7 2.1 2.8 3.2 COD, mg/l 13.3 18.4 12.6 17.5 17.2 Nitrate as NO3, mg/l BDL BDL BDL BDL BDL Phosphate as PO4, mg/l 0.28 0.25 BDL 0.17 0.31 Fluoride as F, mg/l BDL BDL BDL 0.2 BDL Chloride as Cl, mg/l 7.8 7.8 7.8 7.8 7.8 Sulphate as SO4, mg/l 47 43 57 49 75 Sodium as Na, mg/l 13 14 12 9 10 Potassium as K, mg/l 1 1 2 1 1 Calcium as Ca, mg/l 49.2 35.7 45.3 30.4 39.7 Magnesium as Mg, mg/l 2.3 2.4 2.5 5.2 4.3 Oil & Grease, mg/l BDL BDL BDL BDL BDL Phenolic Compound BDL BDL BDL BDL BDL Manganese, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Copper, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Zinc, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Chromium, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Cyanides, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Total Coliforms, MPN/100 ml 18 29 31 32 15

Page 141: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-13

TABLE-4.14: Water quality in the study area in post-monsoon season Parameter W1 W2 W3 W4 W5 pH 7.6 7.4 7.45 7.2 7.5 Electrical conductivity (µs/cm) 410 236 315 229 258 Total Dissolved Solids, mg/l 292 158 219 142 168 Total Suspended Solids, mg/l 814 464 82 578 92 Total alkalinity (CaCO3), mg/l 203 94 115 127 114 Carbonates, mg/l Nil Nil Nil Nil Nil D.O., mg/l 9.3 9.8 9.1 9.4 9.7 Parameter W1 W2 W3 W4 W5 BOD, mg/l 2.4 2.8 2.3 2.9 2.1 COD, mg/l 12.7 19.4 13.8 16.8 18.4 Nitrate as NO3, mg/l BDL BDL BDL BDL BDL Phosphate as PO4, mg/l 0.26 0.24 BDL 0.19 0.36 Fluoride as F, mg/l BDL BDL BDL 0.1 BDL Chloride as Cl, mg/l 7.8 7.8 7.8 7.8 7.8 Sulphate as SO4, mg/l 49 44 59 49 79 Sodium as Na, mg/l 15 13 14 11 12 Potassium as K, mg/l 1 1 2 1 1 Calcium as Ca, mg/l 47.4 39.8 48.4 32.6 41.2 Magnesium as Mg, mg/l 2.4 2.5 2.6 4.9 4.5 Oil & Grease, mg/l BDL BDL BDL BDL BDL Phenolic Compound BDL BDL BDL BDL BDL Manganese, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Copper, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Zinc, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Chromium, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Cyanides, mg/l <0.01 <0.01 <0.01 <0.01 <0.01 Total Coliforms, MPN/100 ml 12 22 32 33 12

The total alkalinity in various water samples were varies from 98.4 to 196.8 mg/l, 97.0 to 208.0 mg/l and 94 to 203 mg/l in winter, summer and post-monsoon seasons respectively. The low calcium and magnesium levels are responsible for soft nature of water. The non-carbonate hardness accounts for the balance hardness. Normally non-carbonate hardness can be removed by boiling. The calcium values in the three seasons covered as a part of the study ranges from 29 to 49 mg/l. The calcium values were below the permissible limit of 75 mg/l and cause for rejection limit of 200 mg/l for drinking water purposes. The calcium hardness ranges from 70 to 124 mg/l and the total hardness ranges from 85 to 140 mg/l. The hardness values were below the permissible limit of 200 mg/l (Annexure 4.3) and cause for rejection limit of 600 mg/l for drinking water purposes. Thus, it is concluded that hardness values are low. The low Electric Conductivity (EC) and Total Dissolve Solids (TDS) values indicate the lower concentration of cations and anions. The concentration of TDS level ranged from 125 to 279 mg/l, 150 to 285 mg/l and 142 to 292 mg/l in winter, summer and post-monsoon seasons respectively, which is much lower than the permissible limit of 500 mg/l specified for domestic use. This is also reflected by the fact that the concentration of most of the cations and anions are well within the permissible limit. The fluorides level was lower than the permissible limit (1mg/l) for drinking purposes. Use of water with such fluorides level could lead to dental curies.

The BOD values are well within the permissible limits, which indicate the absence of organic pollution loading. This is mainly due to the low population density and absence of industries in

Page 142: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-14

the area. The low COD values also indicate the absence of chemical pollution loading in the area. The marginal quantity of pollution load, which enters river Satluj, gets diluted. In fact, even for the minimum flow, there is more than adequate water available for dilution. Level of heavy metal in the water of the project area is below the permissible limit used for drinking purposes. The Total Coliform count is very low and it ranges from 12-21, 15-32 and 12-33 in winter season, summer season and post monsoon seasons respectively in the study area. The Water Quality Standards prescribed by Bureau of Indian Standards for Class-A Surface waters, i.e., Water that can be used for domestic purpose without any conventional treatment, except for disinfection is 50 MPN/100 ml. Hence, it has been concluded that water quality in the area is quite good.

4.9 AMBIENT AIR QUALITY

The ambient air quality with respect to the study area around the proposed site forms the baseline information. The study area represents rural environment. The sources of air pollution in the region are vehicular traffic, dust arising from unpaved village roads and domestic fuel burning. The prime objective of the baseline air quality study was to establish the existing ambient air quality of the area.

Selection of Sampling Locations

The baseline status of the ambient air quality has been established through a scientifically designed ambient air quality monitoring network and is based on the following considerations:

- Meteorological conditions on synoptic scale; - Representatives of regional background air quality for obtaining baseline status - Representation of likely affected area.

Three Ambient Air Quality Monitoring (AAQM) locations were selected taking care of above-mentioned points.

Detail methodology for study of ambient air quality is given in Chapter -3.

Instruments used for sampling

Respirable Dust Samplers APM-451 of Envirotech Instruments are being used for monitoring Suspended Particulate Matter (SPM), Respirable fraction (<10 microns) and gaseous pollution like SO2 and NOx.

Sampling and Analysis Techniques

SPM and RPM present in ambient air is sucked through the cyclone. Coarse and non-respirable dust is separated from the air stream by centrifugal forces acting on the solid particles. The separated particulates fall through the cyclone’s conical hopper and are collected in the sampling cap placed at the bottom. The fine dust (<10 micros) forming the respirable fraction of the SPM passes the cyclone and is retained by the filter paper. A tapping is provided on the suction side of the blower to provide suction for air sampling through a set of impinges.

SPM and RPM have been estimated by gravimetric method. Modified West and Gacke Method (IS-5182 Part-II, 1962) have been adopted for estimation of SO2. Jacobs Hochheiser method (IS 5182 Part-II, 1975) has been adopted for estimation of NOx.

Page 143: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-15

Result of Ambient Air Quality Monitoring

The summary of result of ambient air quality monitoring conducted for various seasons are given in Tables-4.15 to 4.17. The summary of findings of ambient air quality monitoring survey is given in Table-4.18 to 4.20. The ambient air quality standards are given in Annexure-4.4.The results of Air Quality of Kashang HEP has been attached as Annexure-4.5 for reference.

TABLE-4.15: Results of ambient air quality monitoring for winter season

Station Date of Monitoring

SPM RPM SO2 NOx

21.02.08 to < 5 < 5 22.02.08 124.3 41

25.02.08 to < 5 < 5 Det Ralli 26.02.08 102.3 31.7 01.03.08 to < 5 < 5 02.03.08 128 42.0 06.03.08 to < 5 < 5 07.03.08 116.7 35.1 Power 21.02.08 to < 5 < 5 House 22.02.08 131 45.3 25.02.08 to < 5 < 5 26.02.08 121.6 38.0 01.03.08 to < 5 < 5 02.03.08 127.3 41.6 06.03.08 to < 5 < 5 07.03.08 114.3 39.2 21.02.08 to < 5 < 5 22.02.08 125.3 43.4 25.02.08 to < 5 < 5 Near 26.02.08 137.6 48.4 Barrage 01.03.08 to < 5 < 5 02.03.08 136.2 48.2 06.03.08 to < 5 < 5 07.03.08 133.7 41.2

Unit: (µg/m3)

TABLE- 4.16: Results of ambient air quality monitoring for summer season Unit: (µg/m3)

Station Date of Monitoring

SPM RPM SO2 NO,

22.05.08 to

23.05.08 135 46.2 < 5 < 5

26.05.08 to Det Ralli 27.05.08 98.3 30.3 < 5 < 5 31.05.08 to 01.06.08 145.1 48.3 < 5 < 5 05.06.08 to

Page 144: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-16

Station Date of Monitoring

SPM RPM SO2 NO,

06.06.08 112.7 35.1 < 5 < 5 22.05.08 to 23.05.08 132.5 45.7 < 5 < 5 26.05.08 to Power 27.05.08 115.6 35.1 < 5 < 5 House 31.05.08 to 01.06.08 134.3 43.2 < 5 < 5 05.06.08 to 06.06.08 112.3 35.1 < 5 < 5 22.05.08 to 23.05.08 122.6 38.0 < 5 < 5 26.05.08 to Near 27.05.08 135.1 45.8 < 5 < 5 Barrage 31.05.08 to 01.06.08 140.4 49.2 < 5 < 5 05.06.08 to 06.06.08 131.2 42.1 < 5 < 5

TABLE-4.17: Results of ambient air quality monitoring for post monsoon season

Station Date of Monitoring

SPM RPM SO2 NOx

22.10.08 to

23.10.08 126 44.2 < 5 < 5

26.10.08 to Det Ralli 27.10.08 97.4 31.4 < 5 < 5 31.10.08 to 01.11.08 123.2 45.6 < 5 < 5 05.11.08 to 06.11.08 111.4 33.2 < 5 < 5 22.10.08 to 23.10.08 129.4 48.2 < 5 < 5 26.10.08 to Power 27.10.08 113.9 35.7 < 5 < 5 House 31.10.08 to 01.11.08 124.6 42.1 < 5 < 5 05.10.08 to 06.10.08 119.4 34.2 < 5 < 5 22.10.08 to 23.10.08 128.6 41.8 < 5 < 5 26.10.08 to Near 27.10.08 124.2 42.3 < 5 < 5 Barrage 31.10.08 to 01.11.08 122.6 42.4 < 5 < 5 05.11.08 to

Page 145: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-17

Station Date of Monitoring

SPM RPM SO2 NOx

06.11.08 128.8 45.0 < 5 < 5 Unit: (µg/m3)

TABLE-4.18: Summary of ambient air quality monitoring in the study area for winter season

Station Average Maximum Minimum

RPM Det Ralli 37.45 42.0 31.7 Power House 41.03 45.3 38.0 Near Barrage 45.3 48.4 41.2 SPM Det Ralli 117.83 128.0 102.3 Power House 123.55 131.0 114.3 Near Barrage 133.2 137.6 125.3 SO2 Det Ralli < 5 < 5 < 5Power House < 5 < 5 < 5Near Barrage < 5 < 5 < 5NOx Det Ralli < 5 < 5 < 5Power House < 5 < 5 < 5Near Barrage < 5 < 5 < 5

Source: Primary survey (Unit: µg/m3)

TABLE-4.19: Summary of ambient air quality monitoring in the study area for summer season

Station Average Maximum Minimum RPM Det Ralli 39.98 48.3 30.3 Power House 39.78 45.7 35.1 Near Barrage 43.78 49.2 38.0 SPM Det Ralli 122.78 145.1 98.3 Power House 123.67 134.3 112.3 Near Barrage 132.32 140.4 122.6 SO2 Det Ralli < 5 < 5 < 5 Power House < 5 < 5 < 5 Near Barrage < 5 < 5 < 5 Nox Det Ralli < 5 < 5 < 5 Power House < 5 < 5 < 5 Near Barrage < 5 < 5 < 5

(Unit: µg/m3)

Page 146: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-18

TABLE-4.20: Summary of ambient air quality monitoring in the study area for post-monsoon season Station Average Maximum Minimum RPM Det Ralli 38.6 45.6 31.4 Power House 40.05 48.2 34.2 Near Barrage 42.87 45 41.8 SPM

Det Ralli 114.5 126.0 97.4 Power House 121.82 129.4 113.9 Near Barrage 126.05 128.8 122.6 SO2 Det Ralli < 5 < 5 < 5 Power House < 5 < 5 < 5 Near Barrage < 5 < 5 < 5 Nox Det Ralli < 5 < 5 < 5 Power House < 5 < 5 < 5 Near Barrage < 5 < 5 < 5

(Unit: µg/m3)

Observations on NOx levels

As a part of ambient air quality survey, it was seen that in all the stations the NOx level was below detectable limit. i.e it was < 5 µg/m3. The NOx level observed at various sampling stations was well below the permissible limit of 80 µg/m3 for residential and rural areas.

Observation on ambient SO2 levels

As a part of ambient air quality survey, it was seen that in all the stations the SO2 level was below detectable limit. i.e. it was < 5 µg/m3. The SO2 level observed at various stations was well below the permissible limit of 80 µg/m3 specified for residential and rural areas.

Observations on ambient SPM levels

The maximum SPM level observed in survey conducted during the survey was observed to be 145.1 µg/m3 in summer season near Det Ralli. The average SPM level at various monitoring stations ranged from 102.3 µg/m3 to 137.6 µg/m3, 98.3 µg/m3 to 145.1 µg/m3 and 97.4 µg/m3 to129.4 µg/m3 in winter season, summer season and post monsoon season respectively. The minimum SPM level was observed 97.4 µg/m3 at the station near Det Ralli in post-monsoon season, which is much below the permissible limit of 200 µg/m3 specified for residential, rural and other areas at various stations covered during the survey. But in some station SPM level is above the permissible limit.

Observations on ambient RPM levels

The average RPM levels as observed at various stations in the study area ranged from 31.7 µg/m3 to 48.4 µg/m3, 30.3 µg/m3 to 49.2 µg/m3 and 31.4 µg/m3 to 48.2 µg/m3 in winter season,

Page 147: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-19

summer season and post monsoon season respectively. The highest RPM value was recorded as 49.2 µg/m3 at near Barrage in summer season. The highest values of RPM monitored during the field survey were above the permissible limit of 100 µ g/m3 for residential and rural areas.

Conclusions

Based on the findings of the ambient air quality survey conducted it can be concluded that the ambient air quality is quite good in the area. The values of various parameters were well below the permissible limits specified for residential, rural and other areas.

4.10 NOISE ENVIRONMENT

The hourly ambient noise levels monitored for winter, summer and post monsoon seasons are given in Tables-4.21 to 4.23 respectively. The day time equivalent noise levels estimated are given in Table-4.24. The noise standards for various categories are given in Annexure-4.6. Detail methodology for study of ambient Noise levels is given in Chapter -3.

TABLE-4.21: Hourly equivalent noise levels in the study area for winter season Time Det Ralli Power House Powari Near

suspension bridge

Near Barrage

8 -9 A.M. 35 36 37 35 34 9-10 A.M. 37 37 35 36 32 10-11 A.M. 35 38 40 38 31 11 AM - 12 Noon 36 36 37 35 36 1 –2 PM 37 36 38 34 37 2 – 3 PM 36 35 34 35 38 3 – 4 PM 35 38 32 36 36 4 – 5 PM 37 36 34 36 37 5 – 6 PM 37 39 34 35 37 6 – 7 PM 36 36 36 36 32 7 – 8 PM 36 35 33 36 34 8 – 9PM 36 37 33 34 33

(Unit: dB(A))

TABLE-4.22: Hourly equivalent noise levels in the study area for summer season Time Det Ralli Power House Powari Near

suspension bridge

Near Barrage

8 - 9 AM 36 34 38 35 32 9 - 10 A M 32 32 38 33 34 10 - 11 AM 31 31 40 36 32 11 AM - 12 Noon 34 36 37 34 32 1 –2 PM 35 37 38 32 32 2 – 3 PM 32 38 34 32 32 3 – 4 PM 31 36 32 34 32 4 – 5 PM 34 37 34 35 32 5 – 6 PM 32 34 34 35 31 6 – 7 PM 31 32 36 36 36

Page 148: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-20

7 – 8 PM 30 30 30 34 31 8 – 9 PM 30 30 30 30 31

(Unit: dB (A))

TABLE-4.23: Hourly equivalent noise levels in the study area for Post monsoon season Time Det Ralli Power

House Powari Near

suspension bridge

Near Barrage

8 -9 A M 35 33 37 36 33 9-10 A M 31 31 38 32 35 10-11 A M 32 32 39 35 33 11 AM - 12 Noon 33 35 36 34 34 1 –2 PM 34 36 38 33 32 2 – 3 PM 33 37 34 32 32 3 – 4 PM 32 37 32 34 32 4 – 5 PM 35 36 33 34 33 5 – 6 PM 31 33 35 34 32 6 – 7 PM 31 31 33 36 35 7 – 8 PM 30 30 30 33 31 8 – 9 PM 30 30 30 30 31

(Unit: dB(A))

TABLE-4.24 Day time equivalent noise level at various sampling locations

S. NO. Location Zone Lday (dB(A)) Winter Det Ralli Rural 35.2 Power House Rural 35.8 Powari Rural 34.9 Near suspension bridge Rural 34.6 Near Barrage Rural 34.3 Summer Det Ralli Rural 31.8 Power House Rural 33.8 Powari Rural 35.1 Near suspension bridge Rural 33.2 Near Barrage Rural 31.5 Post monsoon Det Ralli Residential 31.6 Power House Residential 33.2 Powari Residential 34.5 Near suspension bridge Residential 32.9 Near Barrage Residential 31.9

The day time equivalent noise level in winter and summer seasons at various sampling stations ranged from 34 to 36 dB(A), 31 to 36 dB(A). Likewise, day time equivalent noise level in post-

Page 149: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-21

monsoon season ranged from 31 to 35 dB(A) at various sampling stations which were well within the permissible limit specified for rural area (Refer Annexure 4.5).

Page 150: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-22

Page 151: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-23

Page 152: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-24

Figure 4.3: Wind rose diagram of project area from November 2008 to December 2010

Page 153: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-25

Figure 4.4 Satellite Imagery of the Study Area

Page 154: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-26

Figure 4.5 Land use classification of the Study Area

Page 155: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-27

Figure 4.6 Project Layout

Page 156: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-28

Final Approved Hydrological Series by CWC

Page 157: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-29

Page 158: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-30

Page 159: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-31

Page 160: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-32

Page 161: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-33

Computed Discharge data of Satluj river at Shongtong w.e.f. 6/1972 to 5/ 2006 (34 years data)

Period 1972-73 1973-74 1974-75 1975-76 1976-77 I 358.89 747.32 255.30 565.67 665.43 II 502.32 1408.55 407.74 941.33 479.86 III 667.30 1208.69 341.80 927.68 363.46 I 708.19 1033.39 389.37 623.43 650.41 II 657.18 1062.94 833.09 1014.98 898.20 III 770.13 870.47 833.15 866.46 1022.46 I 684.17 750.82 842.28 956.26 635.63 II 601.19 767.60 832.84 1037.52 528.09 III 477.00 782.01 568.45 691.06 425.48 I 408.42 734.18 403.45 465.88 370.90 II 282.48 476.65 269.46 326.30 237.61 III 175.15 354.54 215.44 244.79 191.48 I 151.64 203.35 139.07 198.62 156.55 II 132.49 156.89 125.28 171.52 126.46 III 110.88 136.55 104.21 147.36 118.58 I 100.58 116.05 94.72 132.39 107.33 II 92.23 104.51 85.95 116.11 97.81 III 84.66 89.40 71.43 97.65 90.14 I 79.12 79.76 70.98 85.87 77.18 II 72.05 71.81 68.29 77.81 68.78 III 70.59 70.51 63.54 77.03 67.88 I 68.29 69.13 60.71 71.50 67.11 II 66.13 67.06 62.01 68.90 65.16 III 65.45 67.90 66.71 67.72 60.98 I 65.24 65.90 73.54 67.20 62.52 II 66.46 63.33 76.83 67.56 60.34 III 66.33 63.46 77.86 70.98 64.33 I 67.01 70.51 91.88 77.19 70.81 II 70.61 72.82 106.26 75.76 73.81 III 111.14 90.30 109.43 84.71 74.50 I 139.38 101.07 141.62 87.47 83.40 II 179.47 118.30 143.54 112.97 81.58 III 501.28 151.84 220.06 219.25 90.74 I 985.59 197.40 271.08 218.87 90.07 II 447.39 191.38 501.32 287.00 102.93 III 620.25 152.07 425.48 396.44 201.95

5543.91 8952.46 5470.74 7617.37 5713.74 3886.57 2255.09 2862.25 2719.65 1900.98 9430.48 11207.55 8332.99 10337.02 7614.72

1977-78 1978-79 1979-80 1980-81 1981-82 317.35 657.94 269.40 582.44 357.22 215.20 539.64 698.50 718.61 377.41 484.48 942.35 1579.68 985.07 799.05 1073.20 1054.57 1112.73 964.69 682.78 1148.86 924.74 1280.84 1098.78 883.02 906.76 899.33 1042.73 1006.45 1072.23 1188.16 1183.86 933.39 1045.39 1121.24 742.50 1026.72 872.28 655.72 950.53

Page 162: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-34

576.47 628.13 655.39 543.65 618.87 517.17 586.04 516.79 445.86 427.99 379.47 433.20 305.20 346.58 301.22 262.73 289.61 193.78 259.52 241.51 184.29 217.58 177.16 202.16 162.08 153.76 181.65 155.75 155.83 132.81 138.49 158.71 138.49 135.78 121.87 126.11 128.65 131.01 116.68 118.58 114.62 118.47 114.15 104.61 100.08 106.80 110.08 110.62 93.75 89.69 100.79 98.12 96.75 83.15 83.97 94.19 90.00 84.48 76.85 78.32 86.75 84.14 79.14 75.33 72.69 76.82 77.60 73.97 71.28 72.89 71.96 78.15 71.90 66.43 69.65 72.30 79.74 71.75 69.64 67.09 72.41 76.92 71.49 68.02 66.41 71.71 78.65 72.64 68.01 71.50 72.50 85.23 74.36 67.16 70.18 74.44 83.35 73.63 70.39 71.54 83.39 98.48 65.68 71.26 72.19 88.20 111.69 88.09 77.62 80.08 92.42 152.35 98.90 83.52 123.74

138.28 197.72 121.74 139.77 136.82 153.04 239.37 166.96 182.44 188.30 288.80 306.28 246.31 360.83 283.30 453.83 281.46 291.79 395.14 226.63 491.79 230.00 355.06 498.71 286.31 6877.43 8050.88 8320.08 7609.30 6913.21 3007.18 2956.61 2669.61 2942.97 2501.44 9884.61 11007.49 10989.70 10552.27 9414.65

1982-83 1983-84 1984-85 1985-86 1986-87 534.78 714.76 815.00 434.35 219.12 1059.96 585.28 619.13 506.73 674.23 845.05 842.40 603.70 595.50 1196.61 1114.23 873.77 657.04 594.08 790.13 1087.46 584.57 399.56 646.27 945.59 1121.94 1081.06 645.14 699.26 1171.22 1049.55 1124.80 581.73 549.05 908.99 1008.71 906.28 646.47 667.99 762.41 596.84 983.61 628.40 577.29 544.15 401.41 722.60 451.03 446.78 426.38 340.36 521.02 254.80 284.11 250.16 232.14 295.32 147.45 219.77 193.30 162.12 261.30 111.06 167.51 141.42 150.07 187.56 94.70 174.72 123.54 134.12 160.60 84.70 126.59 105.55 121.33 136.99 73.91 105.11 94.47 107.64 119.92 64.52 91.46 87.47 95.90 97.59 59.59 80.80 81.91 85.60 93.38 55.86 71.08 78.24

Page 163: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-35

81.82 84.13 53.52 65.11 75.66 77.04 77.06 50.39 61.17 71.33 71.75 72.52 48.23 55.55 67.61 72.51 69.52 45.06 52.33 64.92 73.66 65.44 45.80 50.62 63.13 69.99 64.64 43.41 52.60 61.98 67.91 64.65 42.87 53.81 63.42 71.43 65.57 44.34 53.70 64.33 70.66 70.71 50.87 59.65 65.41 84.88 85.94 55.99 67.08 75.28 92.80 100.22 60.57 68.59 89.48 104.27 101.45 64.19 76.94 102.93 115.01 108.58 78.38 118.54 96.97 150.43 155.29 100.68 158.81 145.96 256.73 191.79 136.79 200.42 156.05 483.16 300.78 158.10 335.23 145.63 495.06 471.21 429.63 174.27 256.98

8262.87 8157.01 5681.86 5484.89 7130.62 2916.55 2834.57 1823.98 2210.81 2100.93

11179.42 10991.58 7505.84 7695.71 9231.54

1987-88 1988-89 1989-90 1990-91 1991-92 613.76 491.70 749.01 648.46 892.66 528.45 489.97 549.40 522.37 1104.51 617.08 860.59 554.58 1118.07 959.96 883.64 840.06 614.08 939.90 1242.73 772.70 897.48 887.23 797.16 1078.20 897.26 979.82 1009.61 692.89 1003.00 674.80 898.98 592.85 753.06 784.77 613.19 752.88 606.66 751.85 561.48 579.01 519.91 595.78 620.03 603.56 477.53 391.51 388.97 503.70 520.18 343.77 286.97 268.40 386.78 381.67 279.08 319.98 226.70 288.05 249.89 184.16 194.66 165.43 214.80 212.16 145.36 154.66 134.23 176.68 160.23 128.95 129.32 122.08 142.98 151.30 106.75 117.26 111.63 126.62 158.15 106.11 110.47 100.93 120.86 129.71 96.66 101.98 94.75 114.09 122.03 90.89 94.33 89.09 106.41 123.77 85.11 89.88 83.88 101.62 115.06 78.92 87.62 82.59 95.56 129.83 78.93 83.13 73.75 77.98 109.24 77.94 79.11 73.48 74.68 111.24 74.42 77.24 73.49 74.83 106.44 64.79 74.79 74.60 75.35 106.39 58.30 73.49 74.50 75.91 99.73 58.14 72.66 73.38 76.45 111.12 62.46 76.29 73.94 79.34 99.32 68.24 79.69 78.73 85.42 109.54

Page 164: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-36

73.99 88.39 140.59 107.33 115.01 84.08 92.08 100.75 155.47 114.75 202.07 98.94 123.65 135.99 140.31 268.38 100.28 174.95 163.61 171.29 384.27 119.33 250.75 261.56 213.63 459.29 222.81 737.62 385.96 330.96 474.92 426.20 639.21 486.04 302.57 6417.11 6807.57 6223.46 7044.19 8244.74 3096.75 2514.71 3316.56 3108.84 3111.86 9513.86 9322.29 9540.02 10153.02 11356.59

1992-93 1993-94 1994-95 1995-96 1996-97 373.84 364.94 508.52 482.59 415.53 587.40 507.75 437.85 659.49 806.58 791.37 413.85 847.56 373.65 1198.16 461.99 494.50 1005.00 553.51 540.57 687.95 649.10 858.40 594.81 677.97 857.62 447.48 1066.42 598.87 669.69 704.55 505.34 1083.50 680.98 687.42 611.12 417.08 720.94 619.60 861.86 561.43 385.46 741.33 547.20 452.41 475.54 335.73 574.06 476.62 378.09 322.11 314.31 324.61 307.89 306.56 203.57 204.70 203.04 217.96 215.95 195.41 172.92 181.53 158.79 177.37 159.81 136.97 160.26 144.40 143.09 133.82 122.70 138.17 122.44 125.80 128.22 120.28 129.28 109.89 117.25 114.63 110.73 123.47 105.62 108.50 116.38 110.76 117.11 99.69 103.63 105.33 100.97 111.43 94.54 98.29 101.36 99.14 106.38 90.26 91.19 92.52 90.29 102.87 87.71 86.90 97.39 85.19 98.44 84.87 82.93 90.39 84.46 92.94 77.82 73.98 89.02 82.43 87.83 75.55 73.35 90.20 81.15 87.05 75.42 73.74 94.87 81.06 90.68 76.29 73.53 97.33 81.38 90.39 77.05 72.99 94.14 81.93 90.72 79.67 74.56 95.70 91.89 87.51 90.58 79.76

100.14 99.17 101.48 94.09 77.28 97.01 105.05 96.20 98.89 80.18

121.20 98.98 104.07 158.11 91.74 187.07 106.47 126.10 244.66 115.80 355.37 168.57 173.83 272.21 154.64 206.90 203.07 371.46 252.99 107.23 325.61 427.26 312.75 382.70 162.36 5857.70 4426.39 7388.22 5380.34 6326.63 2889.32 2599.21 2805.34 2777.50 2146.00 8747.01 7025.60 10193.56 8157.85 8472.64

Page 165: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-37

1997-98 1998-99 1999-2000 2000-01 2001-02 222.42 515.55 278.18 247.38 204.20 330.38 406.41 515.43 363.94 285.62 465.45 995.48 620.00 406.26 258.98 462.14 1069.93 695.60 389.30 353.55 591.68 907.58 686.33 494.89 438.47 587.12 664.21 765.63 661.02 461.37 525.25 712.38 1183.77 676.04 412.01 526.79 730.86 745.26 449.91 446.43 376.68 506.76 662.15 376.85 344.38 273.84 337.99 349.22 333.51 258.93 235.80 284.81 285.61 228.79 171.40 144.05 299.83 230.86 161.77 120.14 97.90 208.65 163.66 118.37 96.28 73.29 185.52 134.22 108.53 89.23 60.68 169.63 120.02 101.37 83.33 64.98 136.18 109.48 98.22 80.33 74.72 125.02 101.42 93.79 73.15 117.50 114.56 92.99 86.50 63.92 107.79 109.46 87.43 80.58 57.34 101.63 102.16 82.81 73.55 53.47 93.61 98.14 78.29 72.14 51.05 64.77 93.11 77.09 68.73 49.70 59.93 88.81 75.75 66.72 47.98 53.95 87.36 76.21 66.14 46.65 54.16 86.18 74.77 62.99 46.95 54.16 82.59 74.37 63.61 48.80 54.35 82.06 73.05 64.16 48.66 58.06 82.94 75.31 64.84 55.90 64.57 84.59 77.78 63.32 62.40 67.45 86.10 81.42 69.04 69.24 86.27 120.22 91.86 73.74 77.72 92.61 151.64 101.89 79.48 92.56 159.64 267.92 112.49 86.29 126.59 215.51 273.15 130.10 117.20 179.80 235.92 329.89 284.95 176.42 550.74 573.40 379.32 306.66 147.31 359.63 4179.64 6521.78 6186.37 4227.52 3314.03 2385.03 3126.57 2363.36 1845.15 2213.90 6564.67 9648.35 8549.72 6072.67 5527.92

2002-03 2003-04 2004-05 2005-06 480.44 820.86 214.03 227.52 656.89 746.85 336.37 377.18 547.27 669.02 352.65 816.52 620.15 687.18 460.15 874.15 550.08 605.68 377.40 898.93 460.24 591.61 402.48 766.16 484.47 551.79 443.94 720.01 504.29 436.47 445.57 546.81 420.84 362.45 311.37 423.02 290.44 328.89 226.84 374.55

Page 166: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-38

242.82 242.22 235.73 275.96 152.13 198.35 159.99 206.55 112.86 135.72 115.07 127.56 98.26 104.09 99.10 103.63 90.32 92.30 88.12 87.20 83.42 84.62 82.90 78.18 79.06 77.82 70.98 74.29 74.56 66.58 62.47 73.68 72.69 61.74 56.55 68.83 68.92 57.44 52.56 60.14 56.85 54.69 50.61 60.04 42.21 53.93 48.57 57.62 33.85 54.04 48.11 55.81 34.41 43.12 44.73 58.73 49.06 43.64 47.09 56.13 51.29 49.26 50.57 55.41 51.34 50.30 50.79 64.25 59.47 52.45 56.78 63.81 59.53 57.20 64.82 64.29 84.22 63.39 70.15 63.37 84.46 61.76 75.23 71.43

143.89 63.25 85.29 80.36 171.74 72.90 136.27 137.15 193.87 90.46 238.32 305.46 404.60 179.50 203.06 431.63 559.15 223.40 152.65 610.46 4750.07 5474.58 3488.47 5724.64 2451.20 1668.37 1802.46 2583.90 7201.27 7142.95 5290.94 8308.54

Power Studies for Shongtong HEP Year wise Computations for Unrestricted Energy In GWH NET HEAD = 124.01 m EFFICIENCY= 0.9114

Month Period 1972-73 1973-74 1974-75 1975-76 1976-77 I 95.50 198.86 67.94 150.52 177.07 June II 133.67 374.82 108.50 250.49 127.69 III 177.57 321.63 90.95 246.86 96.72 I 188.45 274.99 103.61 165.90 173.07 July II 174.88 282.85 221.68 270.09 239.01 III 225.42 254.80 243.87 253.62 299.28 I 182.06 199.79 224.13 254.46 169.14 Aug. II 159.98 204.26 221.62 276.08 140.52 III 139.62 228.90 166.39 202.28 124.54 I 108.68 195.37 107.36 123.97 98.70 Sept. II 75.17 126.84 71.70 86.83 63.23 III 46.61 94.34 57.33 65.14 50.95 I 40.35 54.11 37.01 52.85 41.66 Oct. II 35.26 41.75 33.34 45.64 33.65 III 32.46 39.97 30.50 43.13 34.71 I 26.76 30.88 25.21 35.23 28.56 Nov. II 24.54 27.81 22.87 30.90 26.03 III 22.53 23.79 19.01 25.98 23.99

Page 167: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-39

I 21.05 21.22 18.89 22.85 20.54 Dec. II 19.17 19.11 18.17 20.71 18.30 III 20.66 20.64 18.60 22.55 19.87 I 18.17 18.39 16.16 19.03 17.86 Jan. II 17.60 17.84 16.50 18.34 17.34 III 19.16 19.87 19.53 19.82 17.85 I 17.36 17.54 19.57 17.88 16.64 Feb. II 17.69 16.85 20.44 17.98 16.06 III 14.12 13.51 16.57 17.00 13.69 I 17.83 18.76 24.45 20.54 18.84 March II 18.79 19.38 28.28 20.16 19.64 III 32.53 26.43 32.03 24.79 21.81 I 37.09 26.90 37.69 23.28 22.19 April II 47.76 31.48 38.20 30.06 21.71 III 133.39 40.40 58.56 58.34 24.15 I 262.27 52.53 72.14 58.24 23.97 May II 119.05 50.93 133.40 76.37 27.39 III 181.55 44.51 124.54 116.04 59.11 TOTAL ENERGY 2904.74 3452.05 2566.73 3183.94 2345.48 OCT. TO MAY N/M 1197.14 694.60 881.64 837.70 585.54 JUNE TO SEPT.M 1707.60 2757.45 1685.09 2346.24 1759.94

1977-78 1978-79 1979-80 1980-81 1981-82 1982-83 1983-84 84.45 175.08 71.69 154.99 95.06 142.31 190.20 57.27 143.60 185.87 191.22 100.43 282.06 155.74

128.92 250.76 420.35 262.13 212.63 224.87 224.16 285.58 280.62 296.10 256.70 181.69 296.50 232.51 305.71 246.07 340.83 292.39 234.97 289.37 155.55 265.42 263.24 305.22 294.60 313.85 328.40 316.44 316.17 315.03 248.37 278.18 298.36 279.29 299.31 197.58 273.21 232.12 174.49 252.94 268.42 241.16 168.74 183.86 191.84 159.13 181.15 174.70 287.91 137.62 155.95 137.52 118.64 113.89 106.81 192.29 100.98 115.27 81.21 92.22 80.15 90.57 138.64 69.91 77.06 51.56 69.06 64.27 61.77 78.58 49.04 57.90 47.14 53.79 43.13 43.14 69.53 40.91 48.34 41.45 41.47 35.34 39.93 49.91 40.54 46.46 40.54 39.74 35.67 39.26 47.01 33.56 34.23 34.86 31.05 31.56 32.29 36.45 30.50 31.53 30.37 27.84 26.63 28.64 31.91 28.42 29.29 29.44 24.95 23.87 25.52 25.97 26.82 26.11 25.74 22.13 22.34 22.78 24.85 25.06 23.95 22.48 20.45 20.84 21.77 22.39 25.39 24.63 23.17 22.05 21.28 22.55 22.56 20.44 20.65 19.68 18.97 19.40 19.09 19.30 19.15 20.80 19.13 17.68 18.53 19.29 18.50 21.16 23.34 21.00 20.38 19.64 21.56 19.15 19.27 20.47 19.02 18.10 17.67 18.62 17.20 19.08 20.93 19.33 18.10 19.03 18.07 17.20 15.43 18.14 17.81 14.30 14.94 15.21 15.70 19.81 22.18 19.59 18.73 19.04 18.80 18.82 22.19 26.20 17.48 18.96 19.21 22.59 22.87

Page 168: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-40

25.82 32.69 25.78 22.72 23.44 27.16 29.33 24.59 40.54 26.32 22.23 32.93 27.75 27.00 36.80 52.61 32.40 37.19 36.41 30.60 28.89 40.72 63.70 44.43 48.55 50.11 40.03 41.32 76.85 81.50 65.54 96.02 75.39 68.31 51.04

120.77 74.90 77.64 105.15 60.31 128.57 80.04 143.95 67.32 103.93 145.98 83.81 144.91 137.93 3044.63 3388.16 3386.97 3250.26 2899.88 3441.52 3387.37 926.28 908.40 824.28 906.51 770.49 896.46 874.87 2118.34 2479.75 2562.69 2343.75 2129.39 2545.07 2512.51

1984-85 1985-86 1986-87 1987-88 1988-89 1989-90 1990-91 1991-92 216.87 115.58 58.31 163.32 130.84 199.31 172.56 237.54 164.75 134.84 179.41 140.62 130.38 146.19 139.00 293.91 160.65 158.46 318.42 164.21 229.00 147.57 297.52 255.45 174.84 158.08 210.25 235.14 223.54 163.41 250.11 330.69 106.32 171.97 251.62 205.62 238.82 236.09 212.12 286.91 188.84 204.68 342.83 262.64 286.80 295.52 202.82 293.59 154.80 146.10 241.88 179.56 239.22 157.76 200.39 208.83 172.03 177.75 202.88 163.17 200.34 161.43 200.07 149.41 183.94 168.98 159.28 169.48 152.18 174.39 181.49 176.67 120.02 118.89 113.46 127.07 104.18 103.51 134.03 138.42 67.80 75.60 66.57 91.48 76.36 71.42 102.92 101.56 39.24 58.48 51.44 74.26 85.15 60.32 76.65 66.49 29.55 44.57 37.63 49.01 51.80 44.02 57.16 56.45 25.20 46.49 32.87 38.68 41.15 35.72 47.01 42.64 24.79 37.05 30.89 37.75 37.85 35.73 41.85 44.29 19.67 27.97 25.14 28.41 31.20 29.70 33.69 42.08 17.17 24.34 23.28 28.24 29.40 26.86 32.16 34.52 15.86 21.50 21.80 25.72 27.14 25.21 30.36 32.47 14.86 18.91 20.82 24.19 25.10 23.71 28.31 32.94 14.24 17.32 20.13 22.65 23.92 22.32 27.04 30.62 14.75 17.90 20.88 23.10 25.65 24.18 27.97 38.00 12.83 14.78 17.99 21.00 22.12 19.62 20.75 29.07 11.99 13.92 17.28 20.74 21.05 19.55 19.87 29.60 13.41 14.82 18.48 21.78 22.61 21.51 21.90 31.16 11.55 14.00 16.49 17.24 19.90 19.85 20.05 28.31 11.41 14.32 16.88 15.51 19.56 19.83 20.20 26.54 9.44 11.43 13.69 13.92 15.47 15.62 16.28 26.61

13.54 15.87 17.40 16.62 20.30 19.68 21.11 26.43 14.90 17.85 20.03 18.16 21.21 20.95 22.73 29.15 17.73 20.08 26.19 21.66 25.87 41.15 31.42 33.67 17.08 20.47 27.39 22.37 24.50 26.81 41.37 30.53 20.86 31.54 25.80 53.77 26.33 32.90 36.19 37.34 26.79 42.26 38.84 71.42 26.68 46.55 43.54 45.58 36.40 53.33 41.52 102.25 31.75 66.72 69.60 56.85 42.07 89.21 38.75 122.22 59.29 196.28 102.70 88.07 125.76 51.01 75.22 139.01 124.75 187.10 142.27 88.57 2311.94 2370.40 2841.76 2931.98 2871.43 2938.53 3125.23 3500.94 561.85 680.96 645.41 955.41 774.60 1021.59 955.55 961.47 1750.09 1689.43 2196.35 1976.57 2096.83 1916.94 2169.68 2539.47

Page 169: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-41

1992-93 1993-94 1994-95 1995-96 1996-97 1997-98 1998-99 99.48 97.11 135.32 128.42 110.57 59.19 137.19 156.31 135.11 116.51 175.49 214.63 87.92 108.15 210.58 110.13 225.54 99.43 318.83 123.86 264.90 122.94 131.59 267.43 147.29 143.85 122.98 284.71 183.07 172.73 228.42 158.28 180.41 157.45 241.51 251.03 130.98 312.15 175.29 196.03 171.86 194.42 187.48 134.47 288.32 181.21 182.92 139.77 189.57 162.62 110.98 191.84 164.87 229.34 140.18 194.48 164.34 112.83 217.00 160.17 132.43 110.26 148.33 126.54 89.34 152.76 126.83 100.61 72.87 89.94 85.71 83.64 86.38 81.93 81.58 62.75 75.79 54.17 54.47 54.03 58.00 57.46 38.33 79.79 52.00 46.01 48.31 42.25 47.20 26.05 55.52 42.52 36.45 42.64 38.43 38.08 19.50 49.37 39.17 35.91 40.44 35.84 36.82 17.76 49.65 34.12 32.01 34.40 29.24 31.20 17.29 36.24 30.50 29.47 32.86 28.11 28.87 19.88 33.27 30.97 29.47 31.16 26.53 27.58 31.27 30.48 28.03 26.87 29.65 25.16 26.16 28.68 29.13 26.97 26.38 28.31 24.02 24.27 27.04 27.19 27.08 26.43 30.11 25.67 25.44 27.40 28.73 25.92 22.67 26.19 22.58 22.07 17.23 24.78 24.05 22.47 24.73 20.71 19.69 15.95 23.63 26.06 24.13 25.71 22.12 21.47 15.79 25.57 24.00 21.59 23.17 20.07 19.62 14.41 22.93 25.24 21.57 24.13 20.30 19.57 14.41 21.98 20.72 17.33 19.24 18.45 15.54 11.57 17.47 25.05 21.80 24.14 21.20 19.84 15.45 22.07 25.46 24.45 23.29 24.10 21.22 17.18 22.51 29.31 29.03 29.71 27.54 22.62 19.74 25.20 25.82 27.95 25.60 26.32 21.34 22.96 31.99 32.25 26.34 27.69 42.07 24.41 24.64 40.35 49.78 28.33 33.56 65.10 30.81 42.48 71.29 94.56 44.86 46.26 72.44 41.15 57.35 72.69 55.06 54.04 98.85 67.32 28.53 62.78 87.78 95.31 125.06 91.55 112.02 47.52 167.84 111.03

2694.24 2164.00 3137.38 2514.80 2609.67 2022.06 2969.62 889.97 800.63 861.68 857.58 661.01 734.67 960.85 1804.27 1363.37 2275.70 1657.22 1948.66 1287.39 2008.77

1999-2000 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 74.02 65.83 54.34 127.85 218.43 56.95 60.54

137.16 96.84 76.00 174.80 198.74 89.51 100.37 164.98 108.11 68.91 145.63 178.03 93.84 217.28 185.10 103.59 94.08 165.02 182.86 122.45 232.61 182.63 131.69 116.68 146.38 161.17 100.43 239.21 224.11 193.49 135.05 134.72 173.17 117.81 224.26 315.00 179.89 109.64 128.92 146.83 118.13 191.60 198.31 119.72 118.79 134.19 116.14 118.57 145.51 193.82 110.31 100.80 123.18 106.09 91.14 123.82 92.93 88.75 68.90 77.29 87.52 60.36 99.67

Page 170: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-42

76.00 60.88 45.61 64.62 64.46 62.73 73.43 61.43 43.05 31.97 40.48 52.78 42.57 54.96 43.55 31.50 25.62 30.03 36.12 30.62 33.94 35.72 28.88 23.75 26.15 27.70 26.37 27.58 35.13 29.67 24.39 26.44 27.02 25.79 25.52 29.13 26.14 21.37 22.20 22.52 22.06 20.80 26.99 24.96 19.47 21.04 20.71 18.89 19.77 24.74 23.02 17.01 19.84 17.72 16.62 19.61 23.27 21.44 15.26 19.34 16.43 15.05 18.32 22.04 19.57 14.23 18.34 15.28 13.99 16.00 22.92 21.11 14.94 16.64 16.01 14.82 17.57 20.51 18.29 13.22 11.23 14.35 12.92 15.33 20.16 17.75 12.77 9.01 14.38 12.80 14.85 22.31 19.36 13.66 10.07 12.62 13.09 17.19 19.90 16.76 12.49 13.05 11.61 12.53 14.94 19.79 16.93 12.98 13.65 13.11 13.46 14.74 17.49 13.66 10.36 12.30 12.05 10.81 13.68 20.04 17.25 14.88 15.82 13.96 15.11 16.98 20.70 16.85 16.61 15.84 15.22 17.25 17.11 23.83 20.21 20.27 24.65 18.55 20.53 18.55 24.45 19.62 20.68 22.48 16.43 20.02 19.01 27.11 21.15 24.63 38.29 16.83 22.70 21.38 29.93 22.96 33.69 45.70 19.40 36.26 36.50 34.62 31.19 47.85 51.59 24.07 63.42 81.28 75.82 46.95 146.55 107.66 47.77 54.03 114.86 89.76 43.12 105.27 163.67 65.39 44.68 178.69

2635.41 1870.49 1702.71 2218.10 2201.45 1628.32 2557.46 729.91 568.34 681.93 755.03 515.24 553.83 794.20 1905.50 1302.15 1020.78 1463.07 1686.22 1074.49 1763.26

SHONGTONG HYDRO- ELECTRIC PROJECT SUMMARY

Year

Annual Inflow

Mons Inflow

Non-Mons Inflow

Annual Energy

Non-Mons Energy Mons Energy

Total June- Sept. Oct. - May Total Oct. - May June- Sept. Mcum Mcum Mcum GWH GWH GWH

1972-73 9430.48 5543.91 3886.57 2904.74 1197.14 1707.60 1973-74 11207.55 8952.46 2255.09 3452.05 694.60 2757.45 1974-75 8332.99 5470.74 2862.25 2566.73 881.64 1685.09 1975-76 10337.02 7617.37 2719.65 3183.94 837.70 2346.24 1976-77 7614.72 5713.74 1900.98 2345.48 585.54 1759.94 1977-78 9884.61 6877.43 3007.18 3044.63 926.28 2118.34 1978-79 11007.49 8050.88 2956.61 3388.16 908.40 2479.75 1979-80 10989.70 8320.08 2669.61 3386.97 824.28 2562.69 1980-81 10552.27 7609.30 2942.97 3250.26 906.51 2343.75 1981-82 9414.65 6913.21 2501.44 2899.88 770.49 2129.39 1982-83 11179.42 8262.87 2916.55 3441.52 896.46 2545.07 1983-84 10991.58 8157.01 2834.57 3387.37 874.87 2512.51 1984-85 7505.84 5681.86 1823.98 2311.94 561.85 1750.09 1985-86 7695.71 5484.89 2210.81 2370.40 680.96 1689.43 1986-87 9231.54 7130.62 2100.93 2841.76 645.41 2196.35 1987-88 9513.86 6417.11 3096.75 2931.98 955.41 1976.57 1988-89 9322.29 6807.57 2514.71 2871.43 774.60 2096.83

Page 171: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-43

1989-90 9540.02 6223.46 3316.56 2938.53 1021.59 1916.94 1990-91 10153.02 7044.19 3108.84 3125.23 955.55 2169.68 1991-92 11356.59 8244.74 3111.86 3500.94 961.47 2539.47 1992-93 8747.01 5857.70 2889.32 2694.24 889.97 1804.27 1993-94 7025.60 4426.39 2599.21 2164.00 800.63 1363.37 1994-95 10193.56 7388.22 2805.34 3137.38 861.68 2275.70 1995-96 8157.85 5380.34 2777.50 2514.80 857.58 1657.22 1996-97 8472.64 6326.63 2146.00 2609.67 661.01 1948.66 1997-98 6564.67 4179.64 2385.03 2022.06 734.67 1287.39 1998-99 9648.35 6521.78 3126.57 2969.62 960.85 2008.77

1999-2000 8549.72 6186.37 2363.36 2635.41 729.91 1905.50 2000-01 6072.67 4227.52 1845.15 1870.49 568.34 1302.15 2001-02 5527.92 3314.03 2213.90 1702.71 681.93 1020.78 2002-03 7201.27 4750.07 2451.20 2218.10 755.03 1463.07 2003-04 7142.95 5474.58 1668.37 2201.45 515.24 1686.22 2004-05 5290.94 3488.47 1802.46 1628.32 553.83 1074.49 2005-06 8308.54 5724.64 2583.90 2557.46 794.20 1763.26

COMPUTATIONS FOR DEPENDABLE YEAR ON THE BASIS OF RUNOFF

90% dependable year=0.9x34= 30.6 31

50% dependable year=0.5x34= 17 17

S. No.

ANNUAL RUNOFF

RUNOFF IN Mcum IN

REMARKSDescending Order % DEP.

YEAR YEAR IN Mcum. YEAR IN Mcum. 1 1972-73 9430.48 11356.59 2.86 2 1973-74 11207.55 11207.55 5.71 3 1974-75 8332.99 11179.42 8.57 4 1975-76 10337.02 11007.49 11.43 5 1976-77 7614.72 10991.58 14.29 6 1977-78 9884.61 10989.70 17.14 7 1978-79 11007.49 10552.27 20.00 8 1979-80 10989.70 10330.84 22.86 9 1980-81 10552.27 10193.56 25.71 10 1981-82 9414.65 10153.02 28.57 11 1982-83 11179.42 9884.61 31.43 12 1983-84 10991.58 9648.35 34.29 13 1984-85 7505.84 9540.02 37.14 14 1985-86 7695.71 9513.86 40.00 15 1986-87 9231.54 9430.48 42.86 16 1987-88 9513.86 9414.65 45.71 17 1988-89 9322.29 1988-89 9322.29 48.57 50% 18 1989-90 9540.02 9231.54 51.43 mean 19 1990-91 10153.02 8747.01 54.29 year 20 1991-92 11356.59 8549.72 57.14 21 1992-93 8747.01 8472.64 60.00 22 1993-94 7025.60 8339.77 62.86 23 1994-95 10193.56 8308.54 65.71

Page 172: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-44

24 1995-96 8157.85 8157.85 68.57 25 1996-97 8472.64 7695.71 71.43 26 1997-98 6564.67 7614.72 74.29 27 1998-99 9648.35 7505.84 77.14 28 1999-2000 8549.72 7201.27 80.00 29 2000-01 6072.67 7142.95 82.86 30 2001-02 5527.92 7025.60 85.71 31 2002-03 7201.27 1997-98 6564.67 88.57 90% 32 2003-04 7142.95 6072.67 91.43 mean 33 2004-05 5290.94 5527.92 94.29 year 34 2005-06 8308.54 5290.94 97.14

SHONGTONG HYDRO- ELECTRIC PROJECT COMPUTATIONS FOR DEPENDABLE YEAR ON THE BASIS OF ENERGY

90% dependable year=0.9x34= 30.6 31

50% dependable year=0.5x34= 17 17

S.No. ANNUAL ENERGY ENERGY IN GWH

REM-ARKS DESCENDING ORDER YEAR IN GWH. YEAR IN GWH.

1 1972-73 2904.74 3500.94 2 1973-74 3452.05 3452.05 3 1974-75 2566.73 3441.52 4 1975-76 3183.94 3388.16 5 1976-77 2345.48 3387.37 6 1977-78 3044.63 3386.97 7 1978-79 3388.16 3250.26 8 1979-80 3386.97 3183.94 9 1980-81 3250.26 3137.38 10 1981-82 2899.88 3125.23 11 1982-83 3441.52 3044.63 12 1983-84 3387.37 2969.62 13 1984-85 2311.94 2938.53 14 1985-86 2370.40 2931.98 15 1986-87 2841.76 2904.74 16 1987-88 2931.98 2899.88 17 1988-89 2871.43 1988-89 2871.43 50% 18 1989-90 2938.53 2841.76 mean. 19 1990-91 3125.23 2694.24 year. 20 1991-92 3500.94 2635.41 21 1992-93 2694.24 2609.67 22 1993-94 2164.00 2566.73 23 1994-95 3137.38 2557.46 24 1995-96 2514.80 2514.80 25 1996-97 2609.67 2370.40 26 1997-98 2022.06 2345.48 27 1998-99 2969.62 2311.94 28 1999-2000 2635.41 2218.10 29 2000-01 1870.49 2201.45 30 2001-02 1702.71 2164.00 31 2002-03 2218.10 1997-98 2022.06 90% 32 2003-04 2201.45 1870.49 Dep.

Page 173: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-45

33 2004-05 1628.32 1702.71 year. 34 2005-06 2557.46 1628.32

SHONGTONG HYDRO- ELECTRIC PROJECT Discharges of 90%dep.& 50% dependable year.Year

MONTH PERIOD 90% dep.yr 50% dep. yr

1997-98 1988-89 I 222.42 491.70

JUN II 330.38 489.97 III 465.45 860.59 I 462.14 840.06

JUL II 591.68 897.48 III 587.12 979.82 I 525.25 898.98

AUG II 526.79 752.88 III 376.68 519.91 I 273.84 391.51

SEP II 235.80 286.97 III 144.05 319.98 I 97.90 194.66

OCT II 73.29 154.66 III 60.68 129.32 I 64.98 117.26

NOV II 74.72 110.47 III 117.50 101.98 I 107.79 94.33

DEC II 101.63 89.88 III 93.61 87.62 I 64.77 83.13

JAN II 59.93 79.11 III 53.95 77.24 I 54.16 74.79

FEB II 54.16 73.49 III 54.35 72.66 I 58.06 76.29

MAR II 64.57 79.69 III 67.45 88.39 I 86.27 92.08

APR II 92.61 98.94 III 159.64 100.28 I 215.51 119.33

MAY II 235.92 222.81 III 573.40 426.20

SHONGTONG HYDRO- ELECTRIC PROJECT POWER & ENERGY GENERATION IN 90% DEP. YEAR

Net Head = 124 mtr Efficiency. = 0.9114 inc. in MW = 25.00 MW

Average discharge in lean period= 71.59

Page 174: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-46

MONTH PERIOD 90% Dep.

Less water releases

15% of the average of

lean period

discharge

Net disch. in

90% Dep. Year

Un-Restricted Restricted Disch. 1997-

98 Power Energy Power Energy MW GWH MW GWH

275 I 222 10.74 211.68 234.70 56.33 234.70 56.33

JUN II 330 10.74 319.64 354.41 85.06 261.25 62.70 III 465 10.74 454.71 504.16 121.00 261.25 62.70 I 462 10.74 451.40 500.49 120.12 261.25 62.70

JUL II 592 10.74 580.94 644.12 154.59 261.25 62.70 III 587 10.74 576.38 639.06 168.71 261.25 68.97 I 525 10.74 514.51 570.47 136.91 261.25 62.70

AUG II 527 10.74 516.06 572.18 137.32 261.25 62.70 III 377 10.74 365.94 405.74 107.12 261.25 68.97 I 274 10.74 263.10 291.71 70.01 261.25 62.70

SEP II 236 10.74 225.06 249.54 59.89 249.54 59.89 III 144 10.74 133.31 147.81 35.47 147.81 35.47 I 98 10.74 87.16 96.64 23.19 96.64 23.19

OCT II 73 10.74 62.55 69.35 16.64 69.35 16.64 III 61 10.74 49.94 55.37 14.62 55.37 14.62 I 65 10.74 54.24 60.14 14.43 60.14 14.43

NOV II 75 10.74 63.98 70.94 17.02 70.94 17.02 III 117 10.74 106.76 118.37 28.41 118.37 28.41 I 108 10.74 97.05 107.60 25.82 107.60 25.82

DEC II 102 10.74 90.89 100.77 24.19 100.77 24.19 III 94 10.74 82.87 91.89 24.26 91.89 24.26 I 65 10.74 54.03 59.90 14.38 59.90 14.38

JAN II 60 10.74 49.19 54.54 13.09 54.54 13.09 III 54 10.74 43.21 47.91 12.65 47.91 12.65 I 54 10.74 43.42 48.14 11.55 48.14 11.55

FEB II 54 10.74 43.42 48.14 11.55 48.14 11.55 III 54 10.74 43.61 48.35 9.28 48.35 9.28 I 58 10.74 47.32 52.47 12.59 52.47 12.59

MAR II 65 10.74 53.83 59.68 14.32 59.68 14.32 III 67 10.74 56.71 62.88 16.60 62.88 16.60 I 86 10.74 75.53 83.75 20.10 83.75 20.10

APR II 93 10.74 81.87 90.78 21.79 90.78 21.79 III 160 10.74 148.91 165.10 39.62 165.10 39.62 I 216 10.74 204.77 227.04 54.49 227.04 54.49

MAY II 236 10.74 225.18 249.67 59.92 249.67 59.92 III 573 10.74 562.66 623.85 164.70 261.25 68.97

TOTAL ENERGY 1917.75 1298.03 PLANT LOAD FACTOR 0.54 INC. INCREASE IN ENERGY 0.00 GWH / MW 4.72 % AGE UTILISATION 67.69 PLF (LEAN- SEASON) 0.25 95% availibilty of 261.25

Page 175: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-47

Power

SHONGTONG HYDRO- ELECTRIC PROJECT POWER & ENERGY GENERATION IN 90% DEP. YEAR

Net Head = 124 m Eff. = 0.9114 inc. in MW = 25.00 MW349.35

Restricted Restricted Restricted Restricted

Power Energy Power Energy Power Energy Power Energy MW GWH MW GWH MW GWH MW GWH 300 325 350 375

234.70 56.33 234.70 56.33 234.70 56.33 234.70 56.33 285.00 68.40 308.75 74.10 332.50 79.80 354.41 85.06 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 75.24 308.75 81.51 332.50 87.78 356.25 94.05 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 75.24 308.75 81.51 332.50 87.78 356.25 94.05 285.00 68.40 291.71 70.01 291.71 70.01 291.71 70.01 249.54 59.89 249.54 59.89 249.54 59.89 249.54 59.89 147.81 35.47 147.81 35.47 147.81 35.47 147.81 35.47 96.64 23.19 96.64 23.19 96.64 23.19 96.64 23.19 69.35 16.64 69.35 16.64 69.35 16.64 69.35 16.64 55.37 14.62 55.37 14.62 55.37 14.62 55.37 14.62 60.14 14.43 60.14 14.43 60.14 14.43 60.14 14.43 70.94 17.02 70.94 17.02 70.94 17.02 70.94 17.02

118.37 28.41 118.37 28.41 118.37 28.41 118.37 28.41 107.60 25.82 107.60 25.82 107.60 25.82 107.60 25.82 100.77 24.19 100.77 24.19 100.77 24.19 100.77 24.19 91.89 24.26 91.89 24.26 91.89 24.26 91.89 24.26 59.90 14.38 59.90 14.38 59.90 14.38 59.90 14.38 54.54 13.09 54.54 13.09 54.54 13.09 54.54 13.09 47.91 12.65 47.91 12.65 47.91 12.65 47.91 12.65 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.35 9.28 48.35 9.28 48.35 9.28 48.35 9.28 52.47 12.59 52.47 12.59 52.47 12.59 52.47 12.59 59.68 14.32 59.68 14.32 59.68 14.32 59.68 14.32 62.88 16.60 62.88 16.60 62.88 16.60 62.88 16.60 83.75 20.10 83.75 20.10 83.75 20.10 83.75 20.10 90.78 21.79 90.78 21.79 90.78 21.79 90.78 21.79

165.10 39.62 165.10 39.62 165.10 39.62 165.10 39.62 227.04 54.49 227.04 54.49 227.04 54.49 227.04 54.49 249.67 59.92 249.67 59.92 249.67 59.92 249.67 59.92 285.00 75.24 308.75 81.51 332.50 87.78 356.25 94.05

TOTAL ENERGY 1356.74 1411.36 1464.37 1516.94 PLANT LOAD FACTOR 0.52 0.50 0.48 0.46 INC.INCREASE IN ENERGY 58.71 54.62 53.01 52.57

Page 176: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-48

GWH / MW 4.52 4.34 4.18 4.05 % AGE UTILISATION 70.75 73.59 76.36 79.10 PLF (LEAN- SEASON) 0.23 0.21 0.19 0.18

285.00 308.75 332.50 356.25

SHONGTONG HYDRO- ELECTRIC PROJECT POWER & ENERGY GENERATION IN 90% DEP. YEAR

Net Head = 124 mtr Eff. = 0.9114 inc. in MW = 25.00 MW

Restricted Restricted Restricted Restricted

Power Energy Power Energy Power Energy Power Energy MW GWH MW GWH MW GWH MW GWH 400 425 450 475

234.70 56.33 234.70 56.33 234.70 56.33 234.70 56.33 354.41 85.06 354.41 85.06 354.41 85.06 354.41 85.06 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 100.32 403.75 106.59 427.50 112.86 451.25 119.13 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 100.32 403.75 106.59 405.74 107.12 405.74 107.12 291.71 70.01 291.71 70.01 291.71 70.01 291.71 70.01 249.54 59.89 249.54 59.89 249.54 59.89 249.54 59.89 147.81 35.47 147.81 35.47 147.81 35.47 147.81 35.47 96.64 23.19 96.64 23.19 96.64 23.19 96.64 23.19 69.35 16.64 69.35 16.64 69.35 16.64 69.35 16.64 55.37 14.62 55.37 14.62 55.37 14.62 55.37 14.62 60.14 14.43 60.14 14.43 60.14 14.43 60.14 14.43 70.94 17.02 70.94 17.02 70.94 17.02 70.94 17.02

118.37 28.41 118.37 28.41 118.37 28.41 118.37 28.41 107.60 25.82 107.60 25.82 107.60 25.82 107.60 25.82 100.77 24.19 100.77 24.19 100.77 24.19 100.77 24.19 91.89 24.26 91.89 24.26 91.89 24.26 91.89 24.26 59.90 14.38 59.90 14.38 59.90 14.38 59.90 14.38 54.54 13.09 54.54 13.09 54.54 13.09 54.54 13.09 47.91 12.65 47.91 12.65 47.91 12.65 47.91 12.65 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.35 9.28 48.35 9.28 48.35 9.28 48.35 9.28 52.47 12.59 52.47 12.59 52.47 12.59 52.47 12.59 59.68 14.32 59.68 14.32 59.68 14.32 59.68 14.32 62.88 16.60 62.88 16.60 62.88 16.60 62.88 16.60 83.75 20.10 83.75 20.10 83.75 20.10 83.75 20.10 90.78 21.79 90.78 21.79 90.78 21.79 90.78 21.79

165.10 39.62 165.10 39.62 165.10 39.62 165.10 39.62 227.04 54.49 227.04 54.49 227.04 54.49 227.04 54.49 249.67 59.92 249.67 59.92 249.67 59.92 249.67 59.92 380.00 100.32 403.75 106.59 427.50 112.86 451.25 119.13

TOTAL ENERGY 1564.25 1611.56 1653.13 1694.17 PLANT LOAD 0.45 0.43 0.42 0.41

Page 177: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-49

FACTOR INC.INCREASE IN ENERGY 47.31 47.31 41.57 41.04 GWH / MW 3.91 3.79 3.67 3.57 % AGE UTILISATION 81.57 84.03 86.20 88.34 PLF (LEAN- SEASON) 0.17 0.16 0.15 0.14

380.00 403.75 427.50 451.25

SHONGTONG HYDRO- ELECTRIC PROJECT POWER & ENERGY GENERATION IN 90% DEP. YEAR

Net Head = 124 mtr Eff. = 0.9114 inc. in MW = 25.00 MW

Restricted Restricted Restricted Restricted Restricted

Power Energy Power Energy Power Energy Power Energy Power Energy MW GWH MW GWH MW GWH MW GWH MW GWH 500 525 550 575 600

234.70 56.33 234.70 56.33 234.70 56.33 234.70 56.33 234.70 56.33 354.41 85.06 354.41 85.06 354.41 85.06 354.41 85.06 354.41 85.06 475.00 114.00 498.75 119.70 504.16 121.00 504.16 121.00 504.16 121.00 475.00 114.00 498.75 119.70 500.49 120.12 500.49 120.12 500.49 120.12 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 570.00 136.80 475.00 125.40 498.75 131.67 522.50 137.94 546.25 144.21 570.00 150.48 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 570.00 136.80 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 570.00 136.80 405.74 107.12 405.74 107.12 405.74 107.12 405.74 107.12 405.74 107.12 291.71 70.01 291.71 70.01 291.71 70.01 291.71 70.01 291.71 70.01 249.54 59.89 249.54 59.89 249.54 59.89 249.54 59.89 249.54 59.89 147.81 35.47 147.81 35.47 147.81 35.47 147.81 35.47 147.81 35.47 96.64 23.19 96.64 23.19 96.64 23.19 96.64 23.19 96.64 23.19 69.35 16.64 69.35 16.64 69.35 16.64 69.35 16.64 69.35 16.64 55.37 14.62 55.37 14.62 55.37 14.62 55.37 14.62 55.37 14.62 60.14 14.43 60.14 14.43 60.14 14.43 60.14 14.43 60.14 14.43 70.94 17.02 70.94 17.02 70.94 17.02 70.94 17.02 70.94 17.02

118.37 28.41 118.37 28.41 118.37 28.41 118.37 28.41 118.37 28.41 107.60 25.82 107.60 25.82 107.60 25.82 107.60 25.82 107.60 25.82 100.77 24.19 100.77 24.19 100.77 24.19 100.77 24.19 100.77 24.19 91.89 24.26 91.89 24.26 91.89 24.26 91.89 24.26 91.89 24.26 59.90 14.38 59.90 14.38 59.90 14.38 59.90 14.38 59.90 14.38 54.54 13.09 54.54 13.09 54.54 13.09 54.54 13.09 54.54 13.09 47.91 12.65 47.91 12.65 47.91 12.65 47.91 12.65 47.91 12.65 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.14 11.55 48.35 9.28 48.35 9.28 48.35 9.28 48.35 9.28 48.35 9.28 52.47 12.59 52.47 12.59 52.47 12.59 52.47 12.59 52.47 12.59 59.68 14.32 59.68 14.32 59.68 14.32 59.68 14.32 59.68 14.32 62.88 16.60 62.88 16.60 62.88 16.60 62.88 16.60 62.88 16.60 83.75 20.10 83.75 20.10 83.75 20.10 83.75 20.10 83.75 20.10 90.78 21.79 90.78 21.79 90.78 21.79 90.78 21.79 90.78 21.79

165.10 39.62 165.10 39.62 165.10 39.62 165.10 39.62 165.10 39.62

Page 178: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-50

227.04 54.49 227.04 54.49 227.04 54.49 227.04 54.49 227.04 54.49 249.67 59.92 249.67 59.92 249.67 59.92 249.67 59.92 249.67 59.92 475.00 125.40 498.75 131.67 522.50 137.94 546.25 144.21 570.00 150.48

TOTAL ENERGY 1735.21 1776.25 1807.60 1837.24 1866.88 Plant load factor 0.40 0.39 0.38 0.36 0.36 INC. Increase in Energy 41.04 41.04 31.36 29.64 29.64 GWH / MW 3.47 3.38 3.29 3.20 3.11 % AGE UTILISATION 90.48 92.62 94.26 95.80 97.35 PLF (LEAN- SEASON) 0.14 0.13 0.12 0.12 0.11

475.00 498.75 522.50 546.25 570.00

SHONGTONG HYDRO- ELECTRIC PROJECT ENERGY AT 95% AVAILABILITY IN 90% DEP. YEAR

MONTH PERIOD 90% Dep. Power Energy Net Dis. MW GWH at 95%m/c

1997-98 450 Availability I 211.68 234.70 56.33

JUN II 319.64 354.41 85.06 III 454.71 427.50 102.60 I 451.40 427.50 102.60

JUL II 580.94 427.50 102.60 III 576.38 427.50 112.86 I 514.51 427.50 102.60

AUG II 516.06 427.50 102.60 III 365.94 405.74 107.12 I 263.10 291.71 70.01

SEP II 225.06 249.54 59.89 III 133.31 147.81 35.47 I 87.16 96.64 23.19

OCT II 62.55 69.35 16.64 III 49.94 55.37 14.62 I 54.24 60.14 14.43

NOV II 63.98 70.94 17.02 III 106.76 118.37 28.41 I 97.05 107.60 25.82

DEC II 90.89 100.77 24.19 III 82.87 91.89 24.26 I 54.03 59.90 14.38

JAN II 49.19 54.54 13.09 III 43.21 47.91 12.65 I 43.42 48.14 11.55

FEB II 43.42 48.14 11.55 III 43.61 48.35 9.28 I 47.32 52.47 12.59

MAR II 53.83 59.68 14.32 III 56.71 62.88 16.60 I 75.53 83.75 20.10

Page 179: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-51

APR II 81.87 90.78 21.79 III 148.91 165.10 39.62 I 204.77 227.04 54.49

MAY II 225.18 249.67 59.92 III 562.66 427.50 112.86 TOTAL ENERGY= 1653.13

SHONGTONG HYDRO- ELECTRIC PROJECT POWER & ENERGY GENERATION IN 50% DEP. YEAR

Net Head = 124 mtr Efficiency = 0.9114 inc. in MW = 25.00 MW

Average discharge in lean period= 81.36

MONTH PERIOD 50% Dep.

Less water releases 15%

of the average of lean period discharge

Net disch.in

90% Dep. Year

Un-Restricted Restricted Disch.

1988-89 Power Energy Power Energy MW GWH MW GWH 275

I 492 12.20 479.50 531.64 127.59 261.25 62.70 JUN II 490 12.20 477.77 529.73 127.13 261.25 62.70

III 861 12.20 848.39 940.65 225.76 261.25 62.70 I 840 12.20 827.86 917.89 220.29 261.25 62.70

JUL II 897 12.20 885.28 981.56 235.57 261.25 62.70 III 980 12.20 967.62 1072.85 283.23 261.25 68.97 I 899 12.20 886.78 983.22 235.97 261.25 62.70

AUG II 753 12.20 740.68 821.23 197.10 261.25 62.70 III 520 12.20 507.70 562.91 148.61 261.25 68.97 I 392 12.20 379.30 420.55 100.93 261.25 62.70

SEP II 287 12.20 274.76 304.64 73.11 261.25 62.70 III 320 12.20 307.77 341.24 81.90 261.25 62.70 I 195 12.20 182.45 202.29 48.55 202.29 48.55

OCT II 155 12.20 142.45 157.95 37.91 157.95 37.91 III 129 12.20 117.11 129.85 34.28 129.85 34.28 I 117 12.20 105.06 116.48 27.96 116.48 27.96

NOV II 110 12.20 98.26 108.95 26.15 108.95 26.15 III 102 12.20 89.77 99.54 23.89 99.54 23.89 I 94 12.20 82.13 91.06 21.85 91.06 21.85

DEC II 90 12.20 77.68 86.13 20.67 86.13 20.67 III 88 12.20 75.41 83.61 22.07 83.61 22.07 I 83 12.20 70.93 78.64 18.87 78.64 18.87

JAN II 79 12.20 66.91 74.19 17.80 74.19 17.80 III 77 12.20 65.04 72.11 19.04 72.11 19.04 I 75 12.20 62.58 69.39 16.65 69.39 16.65

FEB II 73 12.20 61.29 67.95 16.31 67.95 16.31 III 73 12.20 60.45 67.03 12.87 67.03 12.87 I 76 12.20 64.08 71.05 17.05 71.05 17.05

MAR II 80 12.20 67.49 74.83 17.96 74.83 17.96 III 88 12.20 76.19 84.47 22.30 84.47 22.30 I 92 12.20 79.87 88.56 21.25 88.56 21.25

APR II 99 12.20 86.73 96.17 23.08 96.17 23.08 III 100 12.20 88.08 97.65 23.44 97.65 23.44

Page 180: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-52

I 119 12.20 107.12 118.77 28.50 118.77 28.50 MAY II 223 12.20 210.60 233.50 56.04 233.50 56.04

III 426 12.20 414.00 459.02 121.18 261.25 68.97

Total energy 2752.89 1408.42Plant load factor 0.58 Increase in energy 0.00 GWH / MW 5.12 % Utilisation 51.16 PLF (Lean- Season) 0.28 95% Availability of Power 261.25

Restricted Restricted Restricted Restricted

Power Energy Power Energy Power Energy Power Energy MW GWH MW GWH MW GWH MW GWH 300 325 350 375

285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 75.24 308.75 81.51 332.50 87.78 356.25 94.05 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 75.24 308.75 81.51 332.50 87.78 356.25 94.05 285.00 68.40 308.75 74.10 332.50 79.80 356.25 85.50 285.00 68.40 304.64 73.11 304.64 73.11 304.64 73.11 285.00 68.40 308.75 74.10 332.50 79.80 341.24 81.90 202.29 48.55 202.29 48.55 202.29 48.55 202.29 48.55 157.95 37.91 157.95 37.91 157.95 37.91 157.95 37.91 129.85 34.28 129.85 34.28 129.85 34.28 129.85 34.28 116.48 27.96 116.48 27.96 116.48 27.96 116.48 27.96 108.95 26.15 108.95 26.15 108.95 26.15 108.95 26.15 99.54 23.89 99.54 23.89 99.54 23.89 99.54 23.89 91.06 21.85 91.06 21.85 91.06 21.85 91.06 21.85 86.13 20.67 86.13 20.67 86.13 20.67 86.13 20.67 83.61 22.07 83.61 22.07 83.61 22.07 83.61 22.07 78.64 18.87 78.64 18.87 78.64 18.87 78.64 18.87 74.19 17.80 74.19 17.80 74.19 17.80 74.19 17.80 72.11 19.04 72.11 19.04 72.11 19.04 72.11 19.04 69.39 16.65 69.39 16.65 69.39 16.65 69.39 16.65 67.95 16.31 67.95 16.31 67.95 16.31 67.95 16.31 67.03 12.87 67.03 12.87 67.03 12.87 67.03 12.87 71.05 17.05 71.05 17.05 71.05 17.05 71.05 17.05 74.83 17.96 74.83 17.96 74.83 17.96 74.83 17.96 84.47 22.30 84.47 22.30 84.47 22.30 84.47 22.30 88.56 21.25 88.56 21.25 88.56 21.25 88.56 21.25 96.17 23.08 96.17 23.08 96.17 23.08 96.17 23.08 97.65 23.44 97.65 23.44 97.65 23.44 97.65 23.44

118.77 28.50 118.77 28.50 118.77 28.50 118.77 28.50

Page 181: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-53

233.50 56.04 233.50 56.04 233.50 56.04 233.50 56.04 285.00 75.24 308.75 81.51 332.50 87.78 356.25 94.05

TOTAL ENERGY 1484.23 1559.05 1629.16 1695.67 PLANT LOAD FACTOR 0.56 0.55 0.53 0.52 INC.INCREASE IN ENERGY 75.81 74.82 70.11 66.51 GWH / MW 4.95 4.80 4.65 4.52 % AGE UTILISATION 53.92 56.63 59.18 61.60 PLF (LEAN- SEASON) 0.26 0.24 0.22 0.21

285.00 308.75 332.50 356.25

Restricted Restricted Restricted Restricted

Power Energy Power Energy Power Energy Power Energy MW GWH MW GWH MW GWH MW GWH 400 425 450 475

380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 100.32 403.75 106.59 427.50 112.86 451.25 119.13 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 91.20 403.75 96.90 427.50 102.60 451.25 108.30 380.00 100.32 403.75 106.59 427.50 112.86 451.25 119.13 380.00 91.20 403.75 96.90 420.55 100.93 420.55 100.93 304.64 73.11 304.64 73.11 304.64 73.11 304.64 73.11 341.24 81.90 341.24 81.90 341.24 81.90 341.24 81.90 202.29 48.55 202.29 48.55 202.29 48.55 202.29 48.55 157.95 37.91 157.95 37.91 157.95 37.91 157.95 37.91 129.85 34.28 129.85 34.28 129.85 34.28 129.85 34.28 116.48 27.96 116.48 27.96 116.48 27.96 116.48 27.96 108.95 26.15 108.95 26.15 108.95 26.15 108.95 26.15 99.54 23.89 99.54 23.89 99.54 23.89 99.54 23.89 91.06 21.85 91.06 21.85 91.06 21.85 91.06 21.85 86.13 20.67 86.13 20.67 86.13 20.67 86.13 20.67 83.61 22.07 83.61 22.07 83.61 22.07 83.61 22.07 78.64 18.87 78.64 18.87 78.64 18.87 78.64 18.87 74.19 17.80 74.19 17.80 74.19 17.80 74.19 17.80 72.11 19.04 72.11 19.04 72.11 19.04 72.11 19.04 69.39 16.65 69.39 16.65 69.39 16.65 69.39 16.65 67.95 16.31 67.95 16.31 67.95 16.31 67.95 16.31 67.03 12.87 67.03 12.87 67.03 12.87 67.03 12.87 71.05 17.05 71.05 17.05 71.05 17.05 71.05 17.05 74.83 17.96 74.83 17.96 74.83 17.96 74.83 17.96 84.47 22.30 84.47 22.30 84.47 22.30 84.47 22.30 88.56 21.25 88.56 21.25 88.56 21.25 88.56 21.25 96.17 23.08 96.17 23.08 96.17 23.08 96.17 23.08

Page 182: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-54

97.65 23.44 97.65 23.44 97.65 23.44 97.65 23.44 118.77 28.50 118.77 28.50 118.77 28.50 118.77 28.50 233.50 56.04 233.50 56.04 233.50 56.04 233.50 56.04 380.00 100.32 403.75 106.59 427.50 112.86 451.25 119.13

TOTAL ENERGY 1760.08 1824.49 1887.23 1945.94 PLANT LOAD FACTOR 0.50 0.49 0.48 0.47 INC.INCREASE IN ENERGY 64.41 64.41 62.74 58.71 GWH / MW 4.40 4.29 4.19 4.10 % AGE UTILISATION 63.94 66.28 68.55 70.69 PLF (LEAN- SEASON) 0.19 0.18 0.17 0.16

380.00 403.75 427.50 451.25

Restricted Restricted Restricted Restricted

Power Energy Power Energy Power Energy Power Energy MW GWH MW GWH MW GWH MW GWH 500 525 550 575

475.00 114.00 498.75 119.70 522.50 125.40 531.64 127.59 475.00 114.00 498.75 119.70 522.50 125.40 529.73 127.13 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 475.00 125.40 498.75 131.67 522.50 137.94 546.25 144.21 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 475.00 114.00 498.75 119.70 522.50 125.40 546.25 131.10 475.00 125.40 498.75 131.67 522.50 137.94 546.25 144.21 420.55 100.93 420.55 100.93 420.55 100.93 420.55 100.93 304.64 73.11 304.64 73.11 304.64 73.11 304.64 73.11 341.24 81.90 341.24 81.90 341.24 81.90 341.24 81.90 202.29 48.55 202.29 48.55 202.29 48.55 202.29 48.55 157.95 37.91 157.95 37.91 157.95 37.91 157.95 37.91 129.85 34.28 129.85 34.28 129.85 34.28 129.85 34.28 116.48 27.96 116.48 27.96 116.48 27.96 116.48 27.96 108.95 26.15 108.95 26.15 108.95 26.15 108.95 26.15 99.54 23.89 99.54 23.89 99.54 23.89 99.54 23.89 91.06 21.85 91.06 21.85 91.06 21.85 91.06 21.85 86.13 20.67 86.13 20.67 86.13 20.67 86.13 20.67 83.61 22.07 83.61 22.07 83.61 22.07 83.61 22.07 78.64 18.87 78.64 18.87 78.64 18.87 78.64 18.87 74.19 17.80 74.19 17.80 74.19 17.80 74.19 17.80 72.11 19.04 72.11 19.04 72.11 19.04 72.11 19.04 69.39 16.65 69.39 16.65 69.39 16.65 69.39 16.65 67.95 16.31 67.95 16.31 67.95 16.31 67.95 16.31 67.03 12.87 67.03 12.87 67.03 12.87 67.03 12.87 71.05 17.05 71.05 17.05 71.05 17.05 71.05 17.05 74.83 17.96 74.83 17.96 74.83 17.96 74.83 17.96 84.47 22.30 84.47 22.30 84.47 22.30 84.47 22.30 88.56 21.25 88.56 21.25 88.56 21.25 88.56 21.25

Page 183: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-55

96.17 23.08 96.17 23.08 96.17 23.08 96.17 23.08 97.65 23.44 97.65 23.44 97.65 23.44 97.65 23.44 118.77 28.50 118.77 28.50 118.77 28.50 118.77 28.50 233.50 56.04 233.50 56.04 233.50 56.04 233.50 56.04 459.02 121.18 459.02 121.18 459.02 121.18 459.02 121.18

TOTAL ENERGY 2000.43 2052.87 2105.31 2150.28 Plant load factor 0.46 0.45 0.44 0.43 Inc. increase in energy 54.49 52.44 52.44 44.97 Gwh / mw 4.00 3.91 3.83 3.74 % Age utilisation 72.67 74.57 76.48 78.11 PLF (lean- season) 0.15 0.15 0.14 0.13

475.00 498.75 522.50 546.25 SHONGTONG HYDRO- ELECTRIC PROJECT

ENERGY AT 95% AVAILABILITY IN 50% MEAN YEAR

MONTH PERIOD 50% Mean. Power Energy Net Dis. MW GWH at 95%m/c

1988-89 450 Availability I 491.70 427.50 102.60

JUN II 489.97 427.50 102.60 III 860.59 427.50 102.60 I 840.06 427.50 102.60

JUL II 897.48 427.50 102.60 III 979.82 427.50 112.86 I 898.98 427.50 102.60

AUG II 752.88 427.50 102.60 III 519.91 427.50 112.86 I 391.51 420.55 100.93

SEP II 286.97 304.64 73.11 III 319.98 341.24 81.90 I 194.66 202.29 48.55

OCT II 154.66 157.95 37.91 III 129.32 129.85 34.28 I 117.26 116.48 27.96

NOV II 110.47 108.95 26.15 III 101.98 99.54 23.89 I 94.33 91.06 21.85

DEC II 89.88 86.13 20.67 III 87.62 83.61 22.07 I 83.13 78.64 18.87

JAN II 79.11 74.19 17.80 III 77.24 72.11 19.04 I 74.79 69.39 16.65

FEB II 73.49 67.95 16.31 III 72.66 67.03 12.87 I 76.29 71.05 17.05

MAR II 79.69 74.83 17.96 III 88.39 84.47 22.30 I 92.08 88.56 21.25

APR II 98.94 96.17 23.08 III 100.28 97.65 23.44

Page 184: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-56

I 119.33 118.77 28.50 MAY II 222.81 233.50 56.04

III 426.20 427.50 112.86 TOTAL ENERGY= 1887.23

Page 185: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

Annexure 4.1

WAPCOS Centre for Environment 4-57

Letter from CEA for capacity up gradation of STKHEP

Page 186: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-58

Annexure 4.2

List of water sources in the project affected area of Shongtong Karchham HEP, 450 MW

Name of Source Discharge Time Gram Panchayat Mebar

Date 19.11.2010Potharng Nala 72 l \ minute 4:30 pm Koyato Nala 100 L\ minute 4:30 pm Listi 180 L\ minute 4:32 pm Langthelu (Dharangche Nala) 1500 L\ minute 5:55 pm

Date 20.11.2010Dhjarangche Nala 48 L\ minute 9:30am Shogaley 72 L\ minute 9:40am Nagaso 5 L\ minute 10:30am Shormo 51.4 L\ minute 11:20am Bulgar Nala 400 L\ minute 11:55am (Dakelach Nala Runing) 24 L\ minute 12:30 pm Gane Nagas 90 L\ minute 12:50 pm Kusum Nala 45 L\ minute 12:55 pm Kulang Khad 180 L\ minute 4:30 pm

Date 21.11.2010Jhakharang Nala 72 L\ minute 5:30 pm Baspa garang (Jagat Bahadur) Damang Chango 9 L\ minute 9:30am Damang Chango (Bal Bahadur) 0.16 L\ minute 9:40am Damang Dhank 6 L\ minute 10:00am Yotch Garang (Parmeshwar Negi) 48 L\ minute 10:30am Yotch Garang (Bhupinder Negi) Fayang Chaden (Bhupinder Negi) 8 L\ minute 10:40am Limkate (Baspa Nala) 90 L\ minute 12:05 pm Baro (Surjeet Negi) 20 L\ minute 12:30 pm

Ralli Village

Yanpiyang 2.5 L\ minute 4:30am

Gram Panchayat Barang

Date 23.11.2010Nalo Nagas (Mangal Sen) 0.33 L\ minute 11:15am Kare (Madan) 1 L\ minute 11:47am Batuka (Raj Mohan) 2\1\2 L\ minute 12:25 pm Kanka (Near School) 2 L\ minute 12:55 pm Konka-1 (Near School) 1 L\ minute 1:00 pm Leparang (Kalam Sukh) 1\2 L\ minute 2:05 pm Ramo (Derta land) 10.5 L\ minute 2:35 pm Ramo (Prem Lal) 2 L\ minute 2:40 pm Ramo (Vidya Krishan) 2 L\ minute 2:50 pm Ramo ( Near Ranbir House) 5 L\ minute 3:00 pm Ramo (Ranbir Singh) 1\2 L\ minute 3:10 pm Choko Nala (IPH) 144 L\ minute 3:40 pm

Date 24.11.2010Choko Nala (Om Prakash) 600 L\ minute 12:05 pm

Page 187: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-59

Name of Source Discharge Time Choko Nala (Om Prakash) 36 L\ minute 12:10 pm Kholanka Nagas 216 L\ minute 12:40 pm Reyang Sho (Jawahri Lal) 216 L\ minute 2:05 pm Reyang Sho (Jawahri Lal) 72 L\ minute 2:08 pm Reyang Sho (Agya Ram) 108 L\ minute 2:10 pm Reyang Sho (Jawahri Lal) 192 L\ minute 3:25 pm Choko Nala (Jiyu lal 12 L\ minute 3:45 pm Gotangden (Prem Kumar) 2 L\ minute 4:15 pm Gotangden (Manning) 120 L\ minute 4:50 pm Teg Running (Lambardar) 120 L\ minute 5:30 pm

Date 22.11.2010Dumte Nagas-1 (Sashi) 600 L\ minute 1:00 pm Dumte Nagas-2 (Sashi) 200 L\ minute 1:10 pm Dumte Nagas-3 (Hoshiar Singh) 60 L\ minute 1:30 pm Dumte Nagas-4 (Sashi) 4 L\ minute 2:06 pm Dumte Nagas-5 (Sashi) 5 L\ minute 2:10 pm Golpang (Agya Ram) 1 L\ minute 2:30 pm Kare Nagas (Near Roop Singh House) 1 L\ minute 2:45 pm Tinchpa-1 (Bhajan Dass) 4 L\ minute 3:15 pm Tinchpa-2 (Bhajan Dass) 12 L\ minute 3:25 pm Kuta (Vimal) 0.3 L\ minute 3:50 pm Kuta Saring (Raghunath) 0.5 L\ minute 4:30 pm

Date 02.12.2010Konke (Sunder Lal) 0.25 L\ minute 11:30am Khiyawang (Rameshwar Singh) 1 L\ minute 11:45am Soling (Ashok Negi) 4 L\ minute 1:40 pm Kholanka (Ram Singh) 2 L\ minute 1:50 pm Kholanka (Burgur Sen) 3 L\ minute 2:05 pm Kholanka (Jawal Sen) 3.6 L\ minute 2:30 pm Kholanka (On path) 135 L\ minute 2:40 pm Soling (Murthu Devi) 0.16 L\ minute 2:50 pm Skamlinge (Bhajan Das) 0.05 L\ minute 3:30 pm Seryo (Sanjeev) 0.025 L\ minute 3:35 pm

Date 06.12.2010Marua (Chhetan Nargu) 16 L\ minute 12:15 pm Deksho (Rajmohan & Sandeep) 120 L\ minute 12:55 pm Nagaso (Sandeep) 900 L\ minute 1:15 pm Nagaso-II (Sandeep) 5,400 L\ minute 1:25 pm Labale (Shakti Devi) 60 L\ minute 1:35 pm Tangnal Labale 450 L\ minute 2:00 pm Sharmi (Shashibhushan 12 L\ minute 2:25 pm &Naresh Mehta) Nalo (Jigu Lal) 60 L\ minute 3:15 pm

Date 10.12.2010Ticharothen (Shashi Negi) 2 L\ minute 1:30 pm Liche Nala 2400 L\ minute 4:30 pm Date 11-12-10

Raldhang Nala

2:36 pm

Page 188: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-60

Name of Source Discharge Time Gram Panchayat Powari

Date 14.12.2010

Rocknagas Kangrang (Krishan Dev)

10 L\ minute 12:10 pm

Shonchaden 5 L\ minute 12:50 pm Kangrang garang 5400 L\ minute 3:15 pm Kangrang garang 336 L\ minute 3:15 pm Varoo Nala 72 L\ minute 3:30 pm

Date 16.12.2010Gotangden Nagasti (Lafan Chand 2 L\ minute 12:05 pm & Uma Singh) Gotangden Nagasti (Lafan Chand 1 L\ minute 12:15 pm Baleyo (Hukum Singh) 24 L\ minute 1:05 pm Panugo (Sudesh Kumar) 36 L\ minute 1:30 pm Panugo Kuwang (Govt. Land) 16 L\ minute 1:55 pm Dakho (Rajender Singh) 25 L\ minute 2:10 pm Fore (Kedar Chand) 8 L\ minute 3:30 pm Fore (Lafan Chand) 6 L\ minute 3:35 pm Salich Runing-I (Sahi Ram) 1 L\2 minute 4:20 pm Salich Runing-II (Sahi Ram) 12 L\ minute 4:22 pm Ankalangti (Govt. Land) 48 L\ minute 4:35 pm Salich Runing-III (Sahi Ram) 5 L\ minute 4:40 pm

Date 20.12.2010Palesti (Sartal Singh) 60 L\ minute 12: 05 pm Dumchader (Krishan Gopal) 15 L\ minute 12: 20 pm Guthuden (Krishan Gopal) 60 L\ minute 12: 45 pm Guthuden (Prakash Thangi) 4 L\ minute 12: 55 pm Kholangden 45 L\ minute 1: 05 pm Khawangra (Veerbhadra) 30 L\ minute 1: 45 pm Wazeer bawdi 18 L\ minute 2: 45 pm Kulizar 32 L\ minute 3: 00 pm Homticho 8 L\ minute 3: 30 pm Khogruden 6 L\ minute 3: 50 pm Homticho-II 10 L\ minute 4: 05 pm

Date 21.12.2010Kholgaden-I (Hira Singh) 120 L\ minute 11: 45am Kholgaden-II (Govt. Land) 180 L\ minute 12: 05 pm Thithrioden 24 L\ minute 3: 00 pm Chamansho 2 L\ minute 3: 30 pm

Gram Panchayat Khawangi

Date 18.02.2011Pickicho (Yashwant Singh) 36 L\ minute 10:40AM Pichicho-II -do- 30 L\ minute 10:45AM Chona-I (Bupender Singh) 12 L\ minute 11:30am Chona-II -do- 60 L\ minute 11:35am Chona-III 18 L\ minute 11:40am Chona-iv 24 L\ minute 11:50am Chona Nagas-I 225 L\ minute 12:10 pm Balgarang-I (Mahesh) 52 L\ minute 1:20 pm Balgarang-II -do- 42.8 L\ minute 1:25 pm

Page 189: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-61

Name of Source Discharge Time Balgarang-III -do- 60 L\ minute 1:28 pm Jangnaloo (Baldev Singh) 78 L\ minute 2:35 pm Thawabayo (Sujan Singh) 20 L\ minute 3:45 pm Bansi Niwas (Suraj Bansi) 6 L\ minute 3:55 pm Jawangai (Baldev Singh) 21.6 L\ minute 4:05 pm Dolingche (Anit Negi) 3 L\ minute 4:07 pm Bargarang (Narender) 2 L\ minute 4:10 pm Bargarang (Rattan Prakash) 2 L\ minute 4:15 pm

Date 19.02.2011Danicho Saring-I (Virender) 3 L\ minute 12:15 pm Danicho Saring-II (Virender) 11 L\ minute 12:20 pm Kimrang (Gori Shanker) 22 L\ minute 12:40 pm Shaksho-I (Arun Bandhari) 8 L\ minute 1:20 pm Shaksho-II (Arun Bandhari) 4 L\ minute 1:25 pm Shaksho-III (Arun Bandhari) 30 L\ minute 1:30 pm Shaksho-IV (Arun Bandhari) 30 L\ minute 1:40 pm Ontrang 70 L\ minute 2:05 pm Darro (Near Old School) 13 L\ minute 2:15 pm Changrang (Dinesh Negi) 24 L\ minute 3:00 pm

Date 20.02.2011Baruat 25 L\ minute 11.30am Kharshang-II (Sher Singh) 96 L\ minute 11.45am Kabare-II (Surinder Kumar) 48 L\ minute 12.05 pm Kabare (Cheering) 36 L\ minute 12.08 pm Kabare-I (Surinder Negi) 12 L\ minute 12.15 pm KabareMain (Surinder Singh) 2 L\ minute 12.25 pm Kabare-IV (Bhag Singh) 25 L\ minute 01.05 pm Kharshang-I (Praveen Kumar) 30 L\ minute 1.30 pm Ontrang-II (Vijay Kumar) 8 L\ minute 1:55 pm Ontrang-Main (Sukh Path) 120 L\ minute 2:00 pm Ontrang (Narsum Devi) 8 L\ minute 2:05 pm Kamantang (Mohan Kumari) 16 L\ minute 2:30 pm Sutre (Gori Shankar) 24 L\ minute 2:40 pm Domrya (Rattan Prakash) 6 L\ minute 3:05 pm Yalcharang 90 L\ minute 3:20 pm Khomto (Dev Raj) 12 L\ minute 3:30 pm Khane Rim (Bhajan Singh) 10 L\ minute 3:40 pm Khawangi Khas (Devta Sahib) 10 L\ minute 4:10 pm

Date: 21.02.2011Kabre-V (Keshvi Nand) 2 L\ minute 11:20am Kabre-VI (Dil Bhadhur) 16 L\ minute 11:25am Tainalang-I (Bupender Singh) 8 L\ minute 11:40am Tainalang-II (Bupender Singh) 50 L\ minute 11:45am Shakuthang (Sukh Path) 120 L\ minute 12:05 pm Tainalang-III (Jai Dev) 12 L\ minute 12:15 pm Tainalang-IV (Rishi Ram) 96 L\ minute 12:30 pm Tainalang-V (Lal Chand) 50 L\ minute 12:45 pm Tainalang-VI (Vidya Basker) 48 L\ minute 12:55 pm Tainalang-VII (Vidya Basker) 72 L\ minute 1:05 pm Markaging Nagas 450 L\ minute 1:30 pm Durga Nagas 850 L\ minute 1:55 pm Pangshu Nagas (Budh Raj) 300 L\ minute 2:10 pm Dakho (Rishi Ram) 6 L\ minute 2:15 pm Kagrah (Rattan Singh) 5 L\ minute 2:30 pm

Page 190: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-62

Name of Source Discharge Time Kagrah (Public) 3 L\ minute 2:35 pm Kagrah-I (Manjeet) 5 L\ minute 2:40 pm Powari 50 L\ minute 3.00 pm Powari-I 4 L\ minute 3.05 pm Torti (Kanta Devi) 72 L\ minute 3.15 pm Torti-I (Bhisham Lal) 50 L\ minute 3.30 pm Ralo 5 L\ minute 3.45 pm Ralo-I 10 L\ minute 3.50 pm Ralo-II 10 L\ minute 4.00 pm

Page 191: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-63

Annexure-4.5

Page 192: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-64

Page 193: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-65

Page 194: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-66

Page 195: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-67

Page 196: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-68

Page 197: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-69

Page 198: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-70

Page 199: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-71

Page 200: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-72

Page 201: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-73

Page 202: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

i

ANNEXURE-II

Drinking water quality standards

Characteristics *Acceptable **Cause for Rejection

Turbidity (units on JTU scale) 2.5 10 Colour (Units on platinum cobalt scale) 5.0 25 Taste and Odour Unobjectionable Unobjectionable PH 7.0 to 8.5 <6.5 or >9.2 Total Dissolved Solids (mg/l) 500 1500 Total hardness (mg/l) (as CaCO3) 200 600

Chlorides as CD (mg/l) 200 1000 Sulphates (as SO4) 200 400 Fluorides (as F) (mg/l) 1.0 1.5 Nitrates (as NO3) (mg/l) 45 45 Calcium (as Ca) (mg/l) 75 200 Magnesium (as Mg) (mg/l) If there are 250 mg/l of sulphates, Mg content can be increased to a maximum of 125 mg/l with the reduction of sulphates at the rate of 1 unit per every 2.5 units of sulphates

30 150

Iron (as Fe) (mg/l) 0.1 1.0

Manganese (as Mn) (mg/l) 0.05 0.5 Copper (as Cu) (mg/l) 0.05 1.5 Zinc (as Zn) (mg/l) 5.0 15.0 Phenolic compounds (as phenol) (mg/l) 0.001 0.002 Anionic detergents (as MBAS) (mg/l) 0.2 1.0 Mineral Oil (mg/l) 0.01 0.3 Toxic materials

Arsenic (as As) (mg/l) 0.05 0.05 Cadmium (as Cd) (mg/l) 0.01 0.01 Chromium (as hexaalent Cr) (mg/l) 0.05 0.05 Cyanides (as CN) (mg/l) 0.05 0.05 Lead (as Pb) (mg/l) 0.1 0.1 Selenium (as Se) (mg/l) 0.01 0.01

Mercury (total as Hg) (mg/l) 0.001 0.001 Polynuclear aromatic hydrocarbons (PAH) 0.2 µg/l 0.2 µg/l Radio Activity

Gross Alpha activity 3p Ci/l 3p Ci/l Gross Beta activity Pci = pico curie

30p Ci/l 30p (Ci/l)

Govind Singh Rathore
Typewritten Text
Govind Singh Rathore
Typewritten Text
Govind Singh Rathore
Typewritten Text
A
Govind Singh Rathore
Typewritten Text
Annexure 4.3
Page 203: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

ii

Notes :- *1. The figures indicated under the column `Acceptable’ are the limits upto which water is generally acceptable to the consumers **2 Figures in excess of those mentioned under `Acceptable render the water

not acceptable, but still may be tolerated in the absence of alternative and better source but upto the limits indicated under column “Cause for Rejection” above which are supply will have to be rejected.

*3. It is possible that some mine and spring waters may exceed these radio

activity limits and in such cases it is necessary to analyse the individual radionuclides in order to assess the acceptability or otherwise for public consumption.

Page 204: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

iii

ANNEXURE-III

National Ambient Air Quality Standards (Unit: µµµµg/m3) Pollutants Time weighted

Average Industrial Area

Residential Area

Sensitive Area

SO2 Annual Average * 24 hours **

80 120

60 80

15 30

NOx Annual * 24 hours **

80 120

60 80

15 30

SPM Annual * 24 hours **

360 500

140 200

70 100

RSPM Annual * 24 hours **

120 150

60 100

50 75

* Annual Arithmetic mean of minimum 104 measurements in a year taken twice a week 24 hourly at uniform interval.

** 24 hourly/8hourly values should be met 98th percentile of the time in a year. However, 2% of the time, it may exceed but not on two consecutive days.

NOTE :

1. National Ambient Air Quality Standards: the levels of air quality with an adequate margin of safety, to protect the public health, vegetation and property.

2. Whenever and wherever two consecutive values exceeds the limit specified above for the respective category, it would be considered adequate reason to institute regular/continuous monitoring and further investigation.

Source : S.O. 384 (E), Air (Prevention & Control of Pollution) Act, 1981 dated April 11, 1994 and [EPA Notification : GSR 176 (E), April 2, 1996]

Govind Singh Rathore
Typewritten Text
Annexure 4.4
Page 205: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

iv

ANNEXURE-IV

Ambient Noise Standards ------------------------------------------------------------------------------------------------------------ Area Category Limits in dB(A)Leq Code of Area --------------------------------------------- Day time Night time ------------------------------------------------------------------------------------------------------------ A. Industrial Area 75 70 B. Commercial Area 65 55 C. Residential Area 55 45 D. Silence Zone 50 40 ------------------------------------------------------------------------------------------------------------ Note : 1. Day time 6 A.M. and 9 P.M.

2. Night time is 9 P.M. and 6 A.M. 3. Silence zone is defined as areas upto 100 meters around such

premises as hospitals, educational institutions and courts. The silence zones are to be declared by competent authority. Use of vehicular horns, loudspeakers and bursting of crackers shall be banned in these zones.

4. Environment (Protection) Third Amendment Rules, 2000 Gazette notification, Government of India, date 14.2.2000.

Govind Singh Rathore
Typewritten Text
Annexure 4.5
Page 206: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-63

Annexure 4.6

Page 207: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-64

Page 208: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-65

Page 209: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-66

Page 210: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-63

Annexure 4.6

Page 211: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-64

Page 212: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-65

Page 213: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-66

Page 214: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-63

Annexure 4.6

Page 215: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-64

Page 216: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-65

Page 217: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 4-66

Page 218: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-1

CHAPTER-5

BASELINE SETTING FOR ECOLOGICAL ASPECTS

5.1 GENERAL The baseline status has been divided into following three categories: • Physico-chemical aspects • Ecological aspects • Socio-Economic aspects. The baseline setting for ecological aspects are outlined in the present Chapter. The following section highlights floral and faunal diversity, based on the review of available information from secondary sources and primary data collection. 5.2 TERRESTRIAL ECOLOGY 5.2.1 Flora 5.2.1.1 Forest type The project site is surrounded by tall hills and remains under snow during winters. Hill slopes suffer from severe erosion from glacial flow. The vegetation along the slopes however remains sparse mainly owing to the severely cold temperature and largely rocky terrain. Major part of the catchment area is under permanent snow leading to sparse to no vegetation, whereas along the right bank of the river, there are steep slopes with sparse vegetation and few apple orchards. The forests of the project area falls under Dry climatic zone. Himalayan Dry Temperate Forest of Group13 observed in the study area, which has been classified into following different vegetation types as per the Champion and Seth classification: Group-13 Himalayan Dry Temperate Forest C-1 Dry broad leaved and coniferous Forests. C-2(a) Neoza Pine Forest (Pinus gerardiana) C-2(b) Dry Deodar Forest (Cedrus deodara) C-4 West Himalayan High level dry Blue Pine Forest (Pinus wallichiana) 5.2.1.2 Field Studies As a part of the CEIA study, a detailed Ecological survey was conducted for three seasons namely winter, summer and monsoon seasons. The field study for winter, summer and monsoon seasons was conducted in the months of February 2008, May 2008 and July 2008 respectively. The objective of the ecological survey were to • Prepare a checklist of flora in the study area. • Listing the rare/ endangered species economically important species. • Determine frequency abundance and density of different vegetation component.

Page 219: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-2

5.2.1.3 Floral diversity A total 115 plant species were recorded during the floristic survey in the project area. The floristic survey conducted for the winter season in the project area. The species observed are given in Annexure-IV. The number of plant species belonging to different group is summarized in Table 5.1.

TABLE -5.1: Plant diversity of the project area Groups No. of Species Angiosperm & Gymnosperms • Trees 27 • Shrubs 18 • Herbs 39 • Grasses 8 Pteridophytes 8 Bryophytes 6 Lichens 3 Fungi 6 Total 115

5.2.1.4 Economically Important Species The conifers are the dominant species. The broad leaved tree have stunted height and occur either scattered among the conifer or forming more or less pure patches. The list of major floral species observed in the project area, alongwith their economic importance are given in Table-5.2. TABLE - 5.2: Floral species observed in the study area

S. No

Botanical Name Vernacular Name Status Economic Importance

Angiosperms/ Gymnosperms Trees

1. Alnus nitida Kosh, Kunish, Nyun Common Nitrogen fixing, soil binder 2. Aialanthus excelsa Arua Common Medicinal 3. Cedrella toona Tun Common Timber 4. Cedrus deodara. Deodar Common Timber 5. Celtis australis Kharik Common Fodder 6. Douglas fir 7. Ficus hispida Fedu Common Fodder 8. Ficus palmata Fagda/Bedu Common Fodder, edible fruits, medicinal 9. Fraxinus micrantha Angu Rare Medicinal 10. Juglans regia Khor, Akhrot Common Timber, dye and medicine 11. Melia azadirachta Drek Common Medicinal, fodder 12. Pinus gerardiana Chilgoza /Neoza Rare Timber, fruits edible, medicine

13. Pinus roxburghii Chir Common Wood used for construction, resin for varnish and paint

14. P. wallichiana Kail Common Timber, medicinal ,fuel 15. Pyrus communis Nashpati Common Fruits edible 16. P.malus Seb, Seo Common Fruits edible 17. P.pashia Melu common Fruits edible 18. Quercus leucotrichophora Ban] Common Timber, Fuel, fodder, medicinal 19. Quercus semicarpifolia Kharsu, Ban] Common Fuel, Timber 20. Querus ilex Bray Common Fuel, Timber 21. Robinia pseudoacacia Rubinia Common Timber, fuel 22. Salix babylonica Weeping willow Common Agricultural implements, bee-forage

Shrubs 1. Artemisia nilagirica Kun]aa Common Medicinal

Page 220: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-3

S. No

Botanical Name Vernacular Name Status Economic Importance

2. Berberis aristata Kingore Common Medicinal 3. Berberis lycium Kingor Common Fruits edible,medicinal 4. Cannabis sativa Bhang Common Fibre, fuel, medicinal 5. Cotoneaster acuminatus Cham-ruins Common Fuel, bee-forage 6. Girardinia diversifolia Kandali Common Ropes, Medicinal 7. Hypericum podocarpoides Basanti Rare Medicinal, fodder 8. Pyracantha crenulata Bakeel Common Soil binder 9. Rosa brunonii Kun]a Common Medicinal 10. Salix tetrasperma Gad-bhains Common Fodder, medicinal 11. Sinarundinaria anceps Ringal Common Fodder 12. Sorbaria tomentosa Bhiloka/Kathi Common Ornamental, medicinal 13. Viburunum Moliya Common Medicinal 14. Zanthoxylum armatum Timra Common Medicinal

Herbs 1. Ajuga bracteosa Neelkanthi Common Medicinal 2. Anaphalis sp - Common Medicinal 3. Arabis amplexicaulis Ban-Sarsaun Common Edible 4. Arisaema flavum Meen Common Medicinal 5. Bidens pilosa Kumur Common Fodder, medicinal 6. Centella asiatica Brahmi buti Common Medicinal 7. Circium arvense - Common Medicinal 8. Cotula hemispherica Common Medicinal 9. Cyanodon dactylon Dubla Common Medicinal, Used in religious, ceremonies 10. Cyperus sp Motha Common Medicinal 11. Dioscorea bublifera. Genthi Common Edible, medicinal 12. Euphorbia sp Duddhi Common Medicinal 13. Eupatorium adenophorum Kharna Common Fodder, medicinal 14. Gnaphalium sp Buglaya Common Fodder, medicinal 15. Galium aparine Khuskusa Common Medicinal 16. Hyptis suaveolens. Vilayti Tulsi Common Medicinal, local beverage 17. Launaea sp Dudhalu Common Medicinal 18. Leucas aspera Gumba Common Medicinal 19. Nepeta leucophylla Karda Common Medicinal, bee - forage 20. Plantago lanceolata Luhuriya Common Medicinal 21. Pilea scripta Chailu Common Medicinal 22. Potentilla sp Bajardanti Common Medicinal 23. Roripa indica Piria Common Medicinal 24. Rumex dentatus Jangali Palak Common Edible 25. Scutellaria scandens Kutlaphul Common Medicinal, bee- forage 26. Scutellaria grossa Kutlaphul Common Bee-forage 27. Solanum nigrum Makoi Common Medicinal 28. Thalictrum raditum Kirmoli Common Medicinal 29. Vicoa indica - Common Medicinal

Grasses 1. Arundinella setosa Ringal Common Used for brooms 2. Cymbopogon sp Tintyra Common Medicinal 3. Festuca gigantea - Common Ropes made from the leaves, also fodder 4. Poa pratensis Ghas Common Fodder

5. Poa annua Annual Meadow grass

Common Fodder

6. Pogonatherum saccharoideum

- Common Fodder

7. Tripogon filiformis - Common Fodder

Page 221: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-4

In the catchment area, major vegetation covers under Himalayan moist temperate forest. Under this category there are two sub-types i.e. Upper West Himalayan temperate forest and Alder forest. The upper west Himalayan temperate forests are dominating in this area. 1.2.1.6.1 Dominance of various floral species The sampling site T1 is in the submergence area (1,945 m above m.s.l.) of the Shongtong –Karchham HEP. NH-22 is passing along the right bank of the Satluj River. The forest cover at the right bank is very scanty. However, the left bank has some vegetation cover. The dumping sites 2 and 3 are located in the area of sampling site T1. The sampling site T2 is identified close to the barrage site (1,940 m above m.s.l.) near the village Powari. The right bank of the site has a considerable forest cover of Alnus nitida, Pinus gerardiana and Querus ilex. However, the left bank side has no forest cover except some scattered trees, shrubs and herbs. The sampling site T3 is the site (1,810 m above m.s.l.) of Power House. This is located in a narrow valley of high mountains on the left bank of Satluj River close to the village Ralli. Due to high slopes of the mountains on both the side of the mountains, no tree is available at this sampling site. Only shrubs and herbs are present. The frequency, density, abundance, basal area and importance value index (IVI) of the trees, herbs and shrubs at barrage site and submergence area between proposed barrage and power house and in power house area during summer and post-monsoon seasons have been presented in Tables 5.3 to 5.11. A perusal of the data on the ecological analysis revealed that the most dominant tree species were Pinus gerardiana (IVI:144.53), Cedrus deodara (IVI:52.87) and Alnus nitida (IVI 47.75). The shrubs were dominantly represented by the species of Salix tetrasperma (IVI: 65.39) followed by Vibrunum mullaha (IVI:36.81) and Sorbaria tomentosa (IVI: 34.44). The dominant herbs were the species of Solanum nigrum (IVI: 57.05), Nepeta leucophylla (IVI: 46.20) and Rumex dentatus (IVI: 37.62). At sampling site T2, dominant tree species include Alnus nitida (IVI: 132.14), Pinus gerardiana (IVI: 120.55) and Querus ilex (IVI:47.32). However, the shrubs were dominated by three species of Salix tetrasperma (IVI: 67.82), Sorbaria tomentosa (IVI 37.13) and Rosa brunonii (IVI:31.55). The herbs were dominantly represented by the species of Nepeta leucophylla (IVI: 74.57), Rumex dentatus (IVI: 54.48) and the species of Scutellaia grossa (IVI:41.80). At the sampling site T3, dominant by the shrub species are Salix tetrasperma (IVI:72.34), Cotoneaster acuminatus (IVI: 44.91), Vibrunum mullaha (IVI:43.75) and Sorbaria tomentosa (IVI: 41.97). The herbs at this site were dominantly represented by the species of Nepeta leucophylla (IVI:81.13), Rumex dentatus (IVI:69.67) and the species of Cynadon dactylon (IVI:46.28). Pinus gerardiana was observed at various sampling sites covered as a part of the Ecological survey. The details are given in Table-5.3.

Page 222: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-5

TABLE-5.3: Details of availability of Pinus gerardiana in the study area S. No. Sampling site Density of Pinus

gerardiana (No./Ha) T1 In the sub-mergence area and close to the

dumping site 2 and 3 on the Satluj River 330

T2 Close to the barrage site near the village Powari 90 T3 Near the dumping site 4 on right bank 30 T4 Near the dumping site 5 on left bank 70 T5 Near power house site close to the village Ralli -

• At site-T1, dominant tree species were Pinus gerardiana (IVI:144.53), Cedrus deodara

(IVI:52.87) and Alnus nitida (IVI 47.75). • At sampling site T2, dominant tree species include Alnus nitida (IVI: 132.14), Pinus

gerardiana (IVI: 120.55) and Querus ilex (IVI:47.32). • At sampling site T3, dominant tree species include Alnus nitida (IVI: 144.10), Pinus

gerardiana (IVI: 100.02) and Querus ilex (IVI:55.88). • At sampling site T4, dominant tree species include Pinus gerardiana (IVI: 142.20), Alnus

nitida (IVI: 107.63), and Querus ilex (IVI:50.17). • At sampling site T5, Pinus gerardiana wasnot observed.

TABLE -5.4 Frequency, density, abundance, basal area and importance value index (IVI) of plant species at sampling location T1 (submergence area) during winter Season

Plants Frequency (%)

Density (ind./Ha)

Abundance

Basal area (Ha)

IVI Diversity index (ShannonWiener)

Trees Alnus nitida 50 60 1.200 0.980 47.75 0.363

Aialanthus excelsa 20 20 1.000 0.500 20.16 0.183Cedrus deodara 50 60 1.200 1.280 52.87 0.363

Fraxinus micrantha 20 20 1.000 0.180 14.69 0.183Ficus hispida 10 10 1.000 0.259 10.24 0.111

Ficus palmata 10 10 1.000 0.231 9.76 0.111Pinus gerardiana 100 330 3.300 2.420 144.53 0.406

Total 510 1.722Shrubs

Cannabis sativa 50 60 1.2 0.039 23.23 0.345Cotoneaster acuminatus 50 60 1.2 0.180 27.35 0.345

Girardinia diversifolia 50 70 1.4 0.051 25.36 0.375Hypericum

podocarpoides 60 70 1.2 0.039 27.28 0.375Pyracantha crenulata 40 40 1.0 0.115 19.61 0.272

Rosa brunonii 30 60 2.0 0.180 22.80 0.345Salix tetrasperma 60 80 1.3 1.280 65.39 0.401

Sinarundinaria anceps 40 40 1.0 0.051 17.73 0.272

Sorbaria tomentosa 40 60 1.5 0.500 34.44 0.345Vibrunum mullaha 20 20 1.0 0.980 36.81 0.172

Total 560 3.248Herbs

Anaphalis 40 40 1.00 0.000072 25.05 0.352Cynadon dectylon 50 60 1.20 0.000032 32.63 0.431Hyptis suaveolens 40 40 1.00 0.000098 25.71 0.352

Page 223: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-6

Plants Frequency (%)

Density (ind./Ha)

Abundance

Basal area (Ha)

IVI Diversity index (ShannonWiener)

Nepeta leucophylla 40 50 1.25 0.0008 46.20 0.396 Rumex dentatus 30 30 1.00 0.0008 37.62 0.299 Scutellaria scandens 40 40 1.00 0.000032 24.04 0.352 S. grossa 40 40 1.00 0.000128 26.46 0.352 Solanum nigrum 20 20 1.00 0.0018 57.05 0.232 Vicoa indica 30 40 1.33 0.0002 25.25 0.352 Total 360 3.118

TABLE - 5.5: Frequency, density, abundance, basal area and importance value index (IVI) of plant species at sampling location T2 (close to barrage site) during winter season

Plants Frequency (%)

Density (ind./Ha)

Abundance

Basal area (Ha)

IVI Diversity index (Shannon Weinner)

TreesAlnus nitida ` 180 2.25 1.411 132.1 0.442

Pinus gerardiana

90 90 1 2.000 120.5 0.521

Querus ilex 30 30 1 0.980 47.32 0.332Total 300 1.295

ShrubsCannabis

sativa 40 50 1.25 0.039 22.73 0.348

Cotoneaster acuminatus 50 50 1 0.157 29.38 0.348

Girardinia diversifolia 40 50 1.25 0.045 22.93 0.348

Hypericum podocarpoide

s 50 60 1.2 0.029 27.18 0.383Pyracantha

crenulata 20 30 1.5 0.115 15.72 0.257

Rosa brunonii 50 60 1.2 0.157 31.55 0.383Salix

tetrasperma 50 70 1.4 1.155 67.82 0.413

Sinarundinaria anceps 30 30 1 0.051 16.16 0.257

Sorbaria tomentosa 40 50 1.25 0.461 37.13 0.348

Vibrunum mullaha 10 10 1 0.720 29.39 0.120

Total 460 3.206Herbs

Anaphalis 30 30 1 0.000098 32.50 0.392Cynadon dectylon 30 30 1 0.000032 29.42 0.392

Hyptis suaveolens 20 20 1 0.000072 21.98 0.314

Nepeta leucophylla 40 40 1 0.0008 74.57 0.447

Rumex dentatus 20 20 1 0.000768 54.48 0.314

Page 224: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-7

Plants Frequency (%)

Density (ind./Ha)

Abundance

Basal area (Ha)

IVI Diversity index (Shannon Weinner)

Scutellaria scandens 20 30 2 0.000032 24.65 0.392

S. grossa 40 40 1 0.000098 41.80 0.447Vicoa indica 10 10 1 0.000242 20.60 0.203

Total 220 2.902 TABLE 5.6: Frequency, density, abundance, basal area and importance value index (IVI) of plant species at sampling location T3 (in proposed Power House area) during winter season

Plants * Frequency (%)

Density (ind./Ha)

Abundance Basal area (Ha)

IVI Diversity index (Shannon Weinner)

Shrubs Cannabis sativa 20 30 1.5 0.029 17.84 0.314

Cotoneaster acuminatus 50 60 1.2 0.205 44.91 0.447Girardinia diversifolia 20 40 2.0 0.051 21.69 0.369

Hypericum podocarpoides 40 50 1.3 0.039 31.97 0.412Salix tetrasperma 50 50 1.0 1.037 72.34 0.412

Sinarundinaria anceps 30 40 1.3 0.051 25.53 0.369Sorbaria tomentosa 30 40 1.3 0.500 41.97 0.369

Vibrunum mullaha 20 20 1.0 0.819 43.75 0.245Total 330 2.939

HerbsAnaphalis sp 20 20 1 0.00010 35.41 0.401

Cynadon dectylon 30 30 1 0.00003 46.28 0.476Hyptis suaveolens 20 20 1 0.00012 36.07 0.401

Nepeta leucophylla 20 30 1.5 0.00080 81.13 0.476Rumex dentatus 20 20 1 0.00072 69.67 0.401

Scutellaria scandems 20 20 1 0.00003 31.44 0.401Total 140 2.557

TABLE - 5.7: Frequency, density, abundance, basal area and importance value index (IVI) of plant species at sampling location T1 (submergence area) during summer Season

Plants Frequency (%)

Density (ind./Ha)

Abundance Basal area (Ha)

IVI Diversity index (Shannon Wiener)

Trees Alnus nitida 60 70 1.2 1.008 49.86 0.382

Aialanthus excelsa 20 20 1.0 0.500 18.75 0.176Cedrus deodara 60 70 1.2 1.280 54.41 0.382

Fraxinus micrantha 20 20 1.0 0.180 13.39 0.176Ficus hispida 10 10 1.0 0.259 9.53 0.107

Ficus palmata 10 10 1.0 0.231 9.06 0.107Pinus gerardiana

120 340 2.8 2.509 145.0

0 0.420Total 540 1.750

ShrubsArtemisia nilagirica 50 50 1.0 0.0018 17.02 0.277

Page 225: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-8

Plants Frequency (%)

Density (ind./Ha)

Abundance Basal area (Ha)

IVI Diversity index (Shannon Wiener)

Cannabis sativa 50 70 1.4 0.045 21.18 0.352Cotoneaster acuminatus 50 70 1.4 0.2048 25.69 0.338

Girardinia diversifolia 50 70 1.4 0.0512 21.35 0.338Hypericum podocarpoides 70 80 1.1 0.0512 26.67 0.363

Pyracantha crenulata 40 50 1.3 0.125 18.57 0.277Rosa brunonii 40 60 1.5 0.18 21.60 0.309

Salix tetrasperma 60 90 1.5 1.3122 61.81 0.386Sinarundinaria anceps 40 40 1.0 0.0512 15.02 0.240

Sorbaria tomentosa 40 70 1.8 0.5408 33.25 0.338Vibrunum mullaha 30 30 1.0 0.98 37.84 0.199

Total 680 3.402Herbs

Anaphalis 40 50 1.3 0.00007 20.23 0.325Arabis amplexicaulis 30 40 1.3 0.00007 16.13 0.285

Centella asiatica 50 40 0.8 0.00007 20.48 0.285Cynadon dectylon 50 60 1.2 0.00007 24.32 0.359

Hyptis suaveolens 40 40 1.0 0.00007 18.30 0.285Nepeta leucophylla 70 80 1.1 0.00007 32.52 0.415

Potentilla sp 30 20 0.7 0.00003 11.22 0.181Rumex dentatus 20 30 1.5 0.00080 31.39 0.237

Scutellaria scandems 40 40 1.0 0.00003 17.24 0.285S. grossa 40 40 1.0 0.00013 19.79 0.285

Solanum nigrum 20 30 1.5 0.00205 64.59 0.237Vicoa indica 30 50 1.7 0.00029 23.80 0.325

Total 520 3.504 TABLE - 5.8: Frequency, density, abundance, basal area and importance value index (IVI) of plant species at sampling location T2 (close to barrage site) during summer Season

Plants Frequency (%)

Density (ind./Ha)

Abundance

Basal area (Ha) IVI

Diversity index (Shannon Weinner)

Trees Alnus nitida 80 180 2.3 1.411 130.72 0.455

Pinus gerardiana 90 100 1.1 2.000 122.46 0.527Querus ilex 30 30 1.0 0.980 46.82 0.326

Total 310 1.308Shrubs

Artemisia nilagerica 50 40 0.8 0.002 17.98 0.275Cannabis sativa 40 60 1.5 0.045 20.91 0.349

Cotoneaster acuminatus 50 50 1.0 0.157 24.92 0.314

Girardinia diversifolia 40 50 1.3 0.051 19.30 0.314Hypericum

podocarpoides 60 60 1.0 0.029 24.63 0.349

Pyracantha crenulata 20 30 1.5 0.125 13.85 0.229Rosa brunonii 50 60 1.2 0.157 26.73 0.349

Salix tetrasperma 50 80 1.6 1.186 64.41 0.405Sinarundinaria anceps 30 30 1.0 0.051 13.53 0.229

Sorbaria tomentosa 60 70 1.2 0.500 42.04 0.379Vibrunum mullaha 20 20 1.0 0.720 31.71 0.174

Page 226: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-9

Plants Frequency (%)

Density (ind./Ha)

Abundance

Basal area (Ha) IVI

Diversity index (Shannon Weinner)

Total 550 3.365Herbs

Anaphalis 40 40 1.0 0.000104 24.38 0.328Arabis amplexicaulis s 40 30 0.8 0.000082 21.02 0.276

Centella 40 40 1.0 0.000072 23.04 0.328Cynadon dectylon 30 30 1.0 0.000032 16.36 0.276Hyptis suaveolens 20 30 1.5 0.000072 15.48 0.276

Nepeta leucophylla 60 60 1.0 0.000800 63.69 0.406Potentilla 30 20 0.7 0.000032 13.92 0.213

Rumex dentatus 30 40 1.3 0.000784 50.45 0.328Scutellaria scandems 20 30 1.5 0.000032 13.79 0.276

S. grossa 60 50 0.8 0.000116 32.44 0.370Vicoa indica 20 40 2.0 0.000251 25.44 0.328

Total 410 3.403 TABLE - 5.9: Frequency, density, abundance, basal area and importance value index (IVI) of plant species at sampling location T3 (in proposed Power House area) during summer season

Plants * Frequency (%)

Density (ind./Ha)

Abundance Basal area (Ha)

IVI Diversity index (Shannon Weinner)

Shrubs Cannabis sativa 20 40 2.0 0.039 18.54 0.328 Cotoneaster acuminatus 50 80 1.6 0.205 45.21 0.460 Girardinia diversifolia 30 50 1.7 0.051 25.10 0.370 Hypericum podocarpoides 40 50 1.3 0.051 28.80 0.370 Salix tetrasperma 50 60 1.2 1.095 71.54 0.406 Sinarundinaria anceps 30 40 1.3 0.051 22.66 0.328 Sorbaria tomentosa 30 50 1.7 0.541 42.26 0.370 Vibrunum mullaha 20 40 2.0 0.819 45.88 0.328 410 2.959

Herbs Anaphalis 20 30 1.5 0.00012 27.81 0.375 Arabis amplexicaulis 30 30 1 0.00010 32.27 0.375 Cynadon dectylon 40 40 1 0.00003 38.14 0.431 Hyptis suaveolens 20 20 1 0.00012 23.65 0.299 Nepeta leucophylla 20 30 1.5 0.00097 67.03 0.375 Potentilla 30 30 1 0.00004 29.28 0.375 Rumex dentatus 20 30 1.5 0.00077 57.85 0.375 Scutellaria scandems 20 30 1.5 0.00003 23.97 0.375

Total 240 2.980

Page 227: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-10

TABLE -5.10: Frequency, density, abundance, basal area and importance value index (IVI) of plant species at sampling location T1 (submergence area) during monsoon Season

Plants Frequency(%)

Density (ind./Ha)

Abundance Basal area (Ha)

IVI Diversity index(Sha

Trees Alnus nitida 60 70 1.2 1.020 49.51 0.379

Aialanthus excelsa 20 20 1.0 0.541 19.21 0.174Cedrus deodara 60 80 1.3 1.280 55.62 0.405

Fraxinus micrantha 20 20 1.0 0.190 13.43 0.174Ficus hispida 10 10 1.0 0.259 9.42 0.105

Ficus palmata 10 10 1.0 0.231 8.96 0.105Pinus gerardiana 120 340 2.8 2.554 143.86 0.429

Total 550 1.770Shrubs

Artemisia nilagirica 50 70 1.4 0.002 17.44 0.287Cannabis sativa 50 100 2.0 0.046 22.00 0.352

Cotoneaster acuminatus 50 80 1.6 0.218 24.50 0.310Girardinia diversifolia 50 80 1.6 0.051 19.91 0.310

Hypericum 70 100 1.4 0.054 26.05 0.352Pyracantha crenulata 40 70 1.7 0.125 18.91 0.287

Rosa brunonii 40 80 2.0 0.180 21.54 0.310Salix tetrasperma 60 120 2.0 1.325 61.38 0.388

Sinarundinaria anceps 40 60 1.5 0.051 15.77 0.260Sorbaria tomentosa 40 90 2.3 0.541 32.59 0.332

Vibrunum mullaha 30 50 1.7 1.037 39.89 0.232Total 900 3.421

HerbsAnaphalis 40 80 2.0 0.00013 20.55 0.308

Arabis amplexicaulis 30 70 2.3 0.00003 14.98 0.285Centella asiatica 50 70 1.4 0.00010 20.91 0.285

Cynadon dectylon 50 90 1.8 0.00003 21.53 0.330Hyptis suaveolens 40 70 1.7 0.00010 18.73 0.285

Nepeta leucophylla 70 110 1.6 0.00080 46.44 0.368Potentilla sp 30 60 2.0 0.00003 13.88 0.259

Rumex dentatus 20 80 4.0 0.00080 32.28 0.308Scutellaria scandems 40 70 1.7 0.00003 17.15 0.285

S. grossa 40 70 1.7 0.00013 19.45 0.285Solanum nigrum 20 60 3.0 0.00180 54.00 0.259

Vicoa indica 30 80 2.7 0.00020 20.10 0.308Total 910 3.564

Page 228: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-11

TABLE -5.11: Frequency, density, abundance, basal area and importance value index (IVI) of plant species at sampling location T2 (close to between proposed barrages) during monsoon Season Plants Frequency

(%) Density (ind./Ha)

Abundance Basal area (Ha)

IVI Diversity index (Shannon Weinner)

Trees Alnus nitida 70 170 2.4 1.472 126.16 0.464 Pinus gerardiana 90 100 1.1 2.000 125.06 0.528 Querus ilex 30 30 1.0 1.037 48.78 0.332 Total 300 1.325 Shrubs Artemisia nilagerica 50 60 1 0.003 15.91 0.280 Cannabis sativa 70 80 1 0.046 23.10 0.332 Cotoneaster acuminatus

50 60 1 0.205 22.20 0.280

Girardinia diversifolia 50 80 2 0.051 19.92 0.332 Hypericum podocarpoides

60 60 1 0.029 18.39 0.280

Pyracantha crenulata 40 60 2 0.125 18.05 0.280 Rosa brunonii 50 60 1 0.157 20.71 0.280 Salix tetrasperma 80 140 2 1.293 71.00 0.440 Sinarundinaria anceps 30 40 1 0.051 11.59 0.216 Sorbaria tomentosa 80 100 1 0.500 41.37 0.375 Vibrunum mullaha 40 60 2 0.759 37.75 0.280 800 3.377 Herbs Anaphalis 60 70 1.2 0.00012 26.47 0.322 Arabis amplexicaulis s 50 60 1.2 0.00009 22.13 0.294 Centella 40 70 1.8 0.00010 21.66 0.322 Cynadon dectylon 30 60 2.0 0.00003 15.55 0.294 Hyptis suaveolens 20 60 3.0 0.00007 15.16 0.294 Nepeta leucophylla 80 90 1.1 0.00080 61.49 0.370 Potentilla 30 50 1.7 0.00003 14.20 0.263 Rumex dentatus 50 70 1.4 0.00078 52.00 0.322 Scutellaria scandems 20 60 3.0 0.00003 13.51 0.294 S. grossa 70 80 1.1 0.00012 29.86 0.347 Vicoa indica 40 70 1.8 0.00025 27.97 0.322 Total 740 3.442 TABLE-5.12: Frequency, density, abundance, basal area and importance value Index (IVI) of plant species at sampling location T3 (in proposed power house station) during Monsoon season Plants * Frequency

(%) Density (ind./Ha)

Abundance Basal area (Ha)

IVI Diversity index (Shannon Weinner)

Shrubs Cannabis sativa 40 100 2.5 0.0403 29.26 0.398 Cotoneaster 50 140 2.8 0.2048 43.99 0.462 Girardinia diversifolia 30 80 2.7 0.0512 23.37 0.355 Hypericum 40 100 2.5 0.0512 29.63 0.398 Salix tetrasperma 50 100 2.0 1.1250 69.92 0.398

Page 229: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-12

Plants * Frequency (%)

Density (ind./Ha)

Abundance Basal area (Ha)

IVI Diversity index (Shannon Weinner)

Sinarundinaria anceps 40 80 2.0 0.0564 26.99 0.355 Sorbaria tomentosa 30 80 2.7 0.5408 40.17 0.355 Vibrunum mullaha 10 30 3.0 0.8450 36.67 0.193 Total 710 2.914 Herbs Anaphalis 50 60 1.2 0.00012 30.55 0.342 Arabis amplexicaulis 30 60 2 0.00010 24.12 0.342 Cynadon dectylon 40 100 2.5 0.00003 30.78 0.441 Hyptis suaveolens 20 50 2.5 0.00012 19.97 0.308 Nepeta leucophylla 80 120 1.5 0.00097 89.11 0.473 Potentilla 40 60 1.5 0.00004 24.07 0.342 Rumex dentatus 40 60 1.5 0.00077 57.64 0.342 Scutellaria scandems 40 60 1.5 0.00003 23.76 0.342 Total 570 2.931 * No tree was present at S3 as river passes through a narrow valley of high mountains. 5.2.1.7 Diversity Indices Species diversity index can be considered as a measure of environmental quality and indicates the well being of any ecosystem. The species diversity indices for various vegetation components is given in Table-5.13. TABLE-5.13 Species Diversity Indices at various sampling locations

Season Sampling location Trees Shrubs Herbs Winter season Submergence area 1.722 3.248 3.118

Barrage site 1.295 3.206 Power house site 2.939 2.557 1.750

Summer season Submergence area 1.750 3.402 3.504 Barrage site 1.308 3.365 3.403 Power house site 2.939 2.959 2.980

Monsoon season Submergence area 1.770 3.421 3.564 Barrage site 1.325 3.377 3.442 Power house site 2.939 2.914 2.931

Diversity indices of sampling site T1 were computed to be 1.722 for trees, 3.248 for shrubs and 3.118 for herbs during winter season, and 1.750 for trees, 3.402 for shrubs and 3.504 for herbs during summer season, however 1.770 for trees, 3.421 for shrubs and 3.564 for herbs during monsoon season. The values for all the three components of plants indicate a good environmental quality of the ecosystem at barrage site. Diversity index of sampling site T2 was found to be 1.295 for trees, 3.206 for shrubs and 2.902 for herbs during winter season, 1.308 for trees, 3.365 for shrubs and 3.403 for herbs during summer season, however 1.325 for trees, 3.377 for shrubs and 3.442 for herbs during monsoon season. This indicates that the T2 has a modrate biodiversity. Diversity indices of sampling site T3 were found to be 2.939 for shrubs and 2.557 for herbs during winter, 2.959 for shrubs and 2.980 for herbs during summer season however 2.914 for shrubs and 2.931 for herbs during monsoon season. The values for all the three components of plants indicate the poor diversity at this site.

Page 230: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-13

5.2.1.8 Wood loss The details of trees coming under submergence area have been given in Table 5.14. As per the enumeration of trees done by Divisional Forest Officer of Kinnaur division 131 trees are falling in submergence area at FRL. As per Forest depertment guidelines, trees falling between FRL and 4 m below FRL has to be spared. Thus the total trees to be felled one time during construction will be 98 (as per Table 5.15). The rest of 32 trees will not be felled and the wood loss of these 32 trees will be by natural causes only during monsoon or heavy snowfall. Table 5.14: (Detail of trees falling in submergence area at FRL) Species Diameter Class wise number of trees Total

V IV III IIA IIB IA IB IC ID IE Deodar 0 2 10 6 0 0 0 0 0 0 18 Neoza 14 19 32 17 12 8 4 1 1 0 108 Bray (Q. ilex)

0 0 0 0 0 0 0 0 0 0 0

Other B/L 3 0 0 0 1 1 0 0 0 0 5 Total 131

Table 5.15: (Detail of trees falling in submergence area between FRL and 4 meters below FRL) Species Diameter Class wise number of trees Total

V IV III IIA IIB IA IB IC ID IE Deodar 0 2 7 6 0 0 0 0 0 0 15 Neoza 14 15 24 12 8 8 4 1 1 0 87 Bray (Q. ilex)

0 0 0 0 0 0 0 0 0 0 0

Other B/L 2 0 0 0 1 1 0 0 0 0 4 Total 98

5.2.2. FAUNA

The state abounds in wildlife among which some rare species like the musk deer, ibex, thar, Himalayan brown bear and snow leopard are still found. The tract has considerable variation in elevation and climate and is endowed with varied fauna. The main wildlife species found in the area are snow leopard, Himalayan black bear, musk deer, ghoral, serrow, bharal, himalayan thar, and langoor and other smaller mammals. Among birds, five species of pheasants namely Western Trapogan, Cheer Pheasant, Monal, Koklash and white crested Kalij are also found in the valley. In addition to these, a number of reptiles, amphibian and smaller birds are also found.

Wildlife surveys carried out in the nearby sanctuaries, by the Forest Department, i.e. in Rupi Bhaba sanctuary has shown a rich population of herbivores and carnivores. Most of these species are also found in the catchment area. The forest area of the Shongtong-Karchham hydroelectric project is reported to serve as a good habitat for various wild fauna species. The list of reported wild life in the project area has been presented in Table 5.15. The total forest land requirement for the project is 63.5015 ha. During construction phase, large number of machinery and construction labor will have to be mobilized. The operation of various construction equipment and blasting is likely to generate noise. These activities can lead to some disturbance to wildlife population. Likewise, sitting of construction equipment, godowns, stores, labor camps, etc. can lead to adverse impacts on fauna in the area. No wildlife sanctuary or National Park exists either in the project area or in its proximity. The Rupi Bhaba sanctuary is about 40 Kms. from project area. Distance of Rupi-Bhawa Sancutary from project area is shown in figure 5.1.

Page 231: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-14

Figure 5.1: Location of nearest wild life sanctuary from the project location

5.2.2.1 Wildlife It is noticed that wildlife resides at very high reaches in the mountains much above the villages. Thus susceptibility to hunting and preying besides strong current of bank less river is minimal. The river is separated from wildlife by labor camps, villages and dense vegetation. The water sources used by wildlife are very high in mountains which are far from project area. It is also established that project area doesn’t fall within the vicinity of any wildlife sanctuary i.e. in 10 km radius of the project components (as per Figure 5.1). Hence any water holes etc. are not required. Worker colonies are being put up in designated areas and muck disposal sites. The camps are usually fenced though there is no wildlife near the project sites. The labor camps are separated from wildlife by villages and dense vegetation. The topographic conditions around project area are such that the impacts cannot spread far beyond project area as there are upstream projects and downstream projects in the immediate vicinity and the site is bound by high mountains on either side. The sampling locations are spread in the area of 10 km. radius and the impacts have been assessed for this whole area.

Rupi – Bhawa Sancutary

Shongtong – Karchham HEP

Page 232: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-15

TABLE - 5.16: Inventory of wild fauna reported in the vicinity of Shongtong-Karchham HEP area

S. No

Zoological Name

English Name

Local Name

Schedule (As per wildlife protection Act, 1972)

Within Project area.

Within 500 m from project area.

Within 10 Kms from project area.

Mammals 1. Herpestes

edwardsi Mongoose Neola

NIL

NIL

Present

2. Moschus chrysogaster

Musk deer Kastura Present

3. Ochotona royalei

Himalayan mouse hare

Rungata Present

4. Pseudois nayaur nayaur

Blue sheep

Bharal NIL

5. Ursus thibetanus

Himalayan black bear

Bhalu Present

6. Nemarhaedus ghural

Goral Gural NIL

Birds 1. Lophophorus

impejanus Himalayan pheasant

Monal Schedule-I

NIL

NIL

2. Alectoris chukar Chukar Partridge

Chakor Present

3. Cariornis meerolophas

Koklas pheasent

Koklas Present

4. Gyps bengalensis

White backed vulture

Gidh Schedule-I Present

5. Glaucidum cuculoides

Himalayan spotted owl

Uloo Present

6. Lophora leucomelana

Kaleej pheasant

Present

7. Catreus walichii (E)

Chir pheasant

Schedule-I Present

8. Tetraogallus himalayensis

Snow cock Ram Chakor

Present

9. Tragopan melanocephalus (E)

Western tragopan

Schedule-I NIL

Reptiles 1. Ancistrodon

himalaynus Himalayan pit viper

Saap Present Present Present

2. Agama tuberculata

Common lizard

Chhipkali

Butterflies 1 Parnassius

charltonisus Gray

Regal Apollo

2 Parnassius hardwickei Gray

Common Blue Apollo

Page 233: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-16

S. No

Zoological Name

English Name

Local Name

Schedule (As per wildlife protection Act, 1972)

Within Project area.

Within 500 m from project area.

Within 10 Kms from project area.

3 Gonepteryx aspasia Menetries

Lesser Brimstone

Present

Present

4 Argynnis childreni Gray

Large Silver Stripe

5 A. hyperbius Johanssen

Indian Fritillary

6 Polygonia c-album L.

Comma

7 Precis hierta lemonias L

Lemon Pansy

8 Lycaena phleas L.

Common copper

9 Zizeeria lysimon Hubner

Dark Grass Blue

5.3 AQUATIC ECOLOGY AND FISHERIES 5.3.1 Aquatic Ecology Biological parameters are very important in the aquatic ecosystem, since they determine the productivity of a water body. Primary productivity is an important indicator of pollution level in any aquatic ecosystem. Fish production is dependent on production of zooplanktons, which in turn is dependent on the phytoplankton production or primary productivity. All these are related to the physio-chemical characteristics of the water. The riverine ecology described in this Section is based on the review of available literature and findings of the field studies conducted by the Consultant during the course of the study. 5.3.1.1 Periphyton and Phytoplankton The Satluj River, a rhithronic stretch of the river, is dominated by the rapids, only a few pools were present in the stretch of the project area. Dominance of periphyton were present in the rapids, while, stray numbers of phytoplankton were present in the pools. Periphyton was represented by 21 members of the family of Bacillariophyceae, Chlorophyceae and Myxophyceae. However, only 14 members of phytoplankton were represented by the family of Bacillariophyceae, Chlorophyceae and Myxophyceae. The data on frequency, density, abundance and diversity indices of periphyton dwelling in the Satluj River have been presented in Tables-5.17 to 5.25. The total density of periphyton ranged from 1,696 ind./ m2 to 2,168 ind. m-2, which was dominated by the members of Bacillariophyceae. Diversity index (Shannon-Wiener) of periphyton ranged from 3.362 to 3.597, which shows the good quality of aquatic environment of Satluj River in the project area of ShongtongKarchham hydroelectric project.

Page 234: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-17

TABLE – 5.17: Frequency, density, abundance and diversity index (Shannon and Weiner) of periphyton in Satluj River at sampling site AQ1 during winter season

Periphyton Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 72 352 4.889 0.426 Diatoma vulgaris 80 112 1.400 0.221 Meridion circulare 64 104 1.625 0.210 Fragilaria inflata 80 424 5.300 0.460 Synedra ulna 80 72 0.900 0.163 Nitzschia 80 112 1.400 0.221 Navicula radiosa 88 128 1.455 0.241 Cocconeis placentula 24 32 1.333 0.090 Cymbella cistula 96 416 4.333 0.457 Gomphonema 16 8 0.500 0.030 Cyclotella 20 24 1.200 0.072 Stauroneis 72 32 0.444 0.090 Denticula 72 56 0.778 0.136 Gomphoneis 72 64 0.889 0.150 Astrionella 72 56 0.778 0.136

Chlorophyceae Closterium leibleinii 64 32 0.500 0.090 Zygnema 80 40 0.500 0.106 Ulothrix zonata 40 48 1.200 0.122 Spirogyra 8 16 2.000 0.052

Myxophyceae Phormidium 16 24 1.500 0.072 Oscillatoria tenuis 8 16 2.000 0.052 Total 2,168 3.597 TABLE-5.18: Frequency, density, abundance and diversity index (Shannon and Weiner) of periphyton in Satluj River at sampling site AQ1 during summer season

Periphyton Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 72 352 4.889 0.454 Diatoma vulgaris 80 128 1.600 0.265 Meridion circulare 64 104 1.625 0.232 Fragilaria inflata 80 368 4.600 0.462 Synedra ulna 80 32 0.400 0.101 Nitzschia 80 72 0.900 0.181 Navicula radiosa 88 72 0.818 0.181 Cocconeis placentula 24 16 0.667 0.059 Cymbella cistula 96 384 4.000 0.470 Gomphonema 16 8 0.500 0.034 Cyclotella 20 24 1.200 0.081 Stauroneis 72 32 0.444 0.101 Denticula 72 40 0.556 0.119 Gomphoneis 72 48 0.667 0.136 Astrionella 72 40 0.556 0.119

Chlorophyceae Closterium leibleinii 64 32 0.500 0.101 Zygnema 80 24 0.300 0.081 Ulothrix zonata 40 32 0.800 0.101 Spirogyra 8 16 2.000 0.059

Myxophyceae

Page 235: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-18

Periphyton Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Phormidium 16 24 1.500 0.081 Oscillatoria tenuis 8 16 2.000 0.059 Total 1,864 3.476 TABLE-5.19: Frequency, density, abundance and diversity index (Shannon and Weiner) of periphyton in Satluj River at sampling site AQ1 during monsoon season

Periphyton Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 64 272 4.3 0.470 Diatoma vulgaris 56 72 1.3 0.229 Meridion circulare 64 64 1.0 0.212 Fragilaria inflata 80 288 3.6 0.480 Synedra ulna 16 24 1.5 0.105 Nitzschia 32 40 1.3 0.153 Navicula radiosa 16 24 1.5 0.105 Cocconeis placentula 8 8 1.0 0.045 Cymbella cistula 96 328 3.4 0.500 Gomphonema 4 4 1.0 0.025 Cyclotella 16 16 1.0 0.077 Stauroneis 8 16 2.0 0.077 Denticula 24 32 1.3 0.130 Gomphoneis 24 24 1.0 0.105 Astrionella 24 24 1.0 0.105

Chlorophyceae Closterium leibleinii 8 16 2.0 0.077 Zygnema 8 16 2.0 0.077 Ulothrix zonata 16 24 1.5 0.105 Spirogyra 8 8 1.0 0.045

Myxophyceae Phormidium 8 8 1.0 0.045 Oscillatoria tenuis 8 8 1.0 0.045 Total 1,316 3.215 TABLE-5.20: Frequency, density, abundance and diversity index (Shannon and Weiner) of periphyton in Satluj River at sampling site AQ2 during winter season

Periphyton Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 72 416 5.778 0.454 Diatoma vulgaris 80 88 1.100 0.186 Meridion circulare 64 104 1.625 0.208 Fragilaria inflata 80 392 4.900 0.443 Synedra ulna 80 72 0.900 0.161 Nitzschia 80 128 1.600 0.239 Navicula radiosa 88 152 1.727 0.266 Cocconeis placentula 24 32 1.333 0.089 Cymbella cistula 96 408 4.250 0.451 Gomphonema 16 24 1.500 0.071 Cyclotella 20 24 1.200 0.071 Stauroneis 72 40 0.556 0.105 Ceratoneis arcus 72 56 0.778 0.135

Page 236: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-19

Periphyton Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Denticula 72 64 0.889 0.148 Gomphoneis 48 32 0.667 0.089

Chlorophyceae Closterium leibleinii 64 32 0.500 0.089 Zygnema 80 32 0.400 0.089 Ulothrix zonata 40 48 1.200 0.120 Spirogyra 8 16 2.000 0.052

Myxophyceae Phormidium 16 24 1.500 0.071 Oscillatoria tenuis 8 16 2.000 0.052 Total 2,200 3.590 TABLE-5.21: Frequency, density, abundance and diversity index (Shannon and Weiner) of periphyton in Satluj River at sampling site AQ2 during summer season

Periphyton Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 80 368 4.600 0.459 Diatoma vulgaris 80 136 1.700 0.273 Meridion circulare 64 112 1.750 0.241 Fragilaria inflata 80 368 4.600 0.459 Synedra ulna 72 32 0.444 0.099 Nitzschia 80 72 0.900 0.179 Navicula radiosa 80 64 0.800 0.165 Cocconeis placentula 24 16 0.667 0.058 Cymbella cistula 96 392 4.083 0.470 Gomphonema 16 8 0.500 0.033 Cyclotella 24 24 1.000 0.080 Stauroneis 72 32 0.444 0.099 Ceratoneis arcus 64 32 0.500 0.099 Denticula 72 48 0.667 0.134 Gomphoneis 72 40 0.556 0.117

Chlorophyceae Closterium leibleinii 64 40 0.625 0.117 Zygnema 80 24 0.300 0.080 Ulothrix zonata 40 32 0.800 0.099 Spirogyra 8 16 2.000 0.058

Myxophyceae Phormidium 16 24 1.500 0.080 Oscillatoria tenuis 4 16 4.000 0.058 Total 1,896 3.460 TABLE-5.22: Frequency, density, abundance and diversity index (Shannon and Weiner) of Periphyton in Satluj river at Sampling site AQ2 during monsoon season

Periphyton Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 80 288 3.6 0.461 Diatoma vulgaris 80 80 1.0 0.229 Meridion circulare 64 64 1.0 0.197 Fragilaria inflata 80 320 4.0 0.480 Synedra ulna 72 32 0.4 0.121 Nitzschia 80 32 0.4 0.121 Navicula radiosa 80 32 0.4 0.121

Page 237: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-20

Periphyton Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Cocconeis placentula 24 8 0.3 0.041 Cymbella cistula 96 392 4.1 0.509 Gomphonema 16 8 0.5 0.041 Cyclotella 24 16 0.7 0.071 Stauroneis 72 24 0.3 0.097 Ceratoneis arcus 64 24 0.4 0.097 Denticula 72 32 0.4 0.121 Gomphoneis 72 24 0.3 0.097

Chlorophyceae Closterium leibleinii 64 24 0.4 0.097 Zygnema 80 16 0.2 0.071 Ulothrix zonata 40 24 0.6 0.097 Spirogyra 8 8 1.0 0.041

Myxophyceae Phormidium 16 8 0.5 0.041 Oscillatoria tenuis 4 8 2.0 0.041 Total 1,464 3.193 TABLE – 5.23: Frequency, density, abundance and diversity index (Shannon and Weiner) of periphyton in Satluj River at sampling site AQ3 during winter season

Periphyton Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 72 328 4.556 0.458 Diatoma vulgaris 80 64 0.800 0.178 Meridion circulare 64 104 1.625 0.247 Fragilaria inflata 80 376 4.700 0.482 Synedra ulna 80 40 0.500 0.127 Nitzschia 80 72 0.900 0.193 Navicula radiosa 88 88 1.000 0.221 Cocconeis placentula 24 8 0.333 0.036 Cymbella cistula 96 360 3.750 0.475 Gomphonema 16 16 1.000 0.063 Cyclotella 20 16 0.800 0.063 Stauroneis 72 16 0.222 0.063 Ceratoneis arcus 72 32 0.444 0.108 Denticula 72 32 0.444 0.108 Gomphoneis 48 24 0.500 0.087

Chlorophyceae Closterium leibleinii 64 16 0.250 0.063 Zygnema 80 24 0.300 0.087 Ulothrix zonata 40 32 0.800 0.108 Spirogyra 8 16 2.000 0.063

Myxophyceae Phormidium 16 16 1.000 0.063 Oscillatoria tenuis 8 16 2.000 0.063 Total 1,696 3.362

Page 238: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-21

TABLE – 5.24: Frequency, density, abundance and diversity index (Shannon and Weiner) of periphyton in Satluj River at sampling site AQ3 during summer season

Periphyton Frequency (%)

Density (ind.m/2)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 72 288 4.000 0.460 Diatoma vulgaris 80 48 0.600 0.161 Meridion circulare 64 80 1.250 0.228 Fragilaria inflata 80 368 4.600 0.500 Synedra ulna 80 40 0.500 0.141 Nitzschia 80 48 0.600 0.161 Navicula radiosa 88 56 0.636 0.179 Cocconeis placentula 24 8 0.333 0.041 Cymbella cistula 96 304 3.167 0.470 Gomphonema 16 16 1.000 0.071 Cyclotella 20 16 0.800 0.071 Stauroneis 72 16 0.222 0.071 Ceratoneis arcus 72 24 0.333 0.097 Denticula 72 24 0.333 0.097 Gomphoneis 48 24 0.500 0.097

Chlorophyceae Closterium leibleinii 64 16 0.250 0.071 Zygnema 80 24 0.300 0.097 Ulothrix zonata 40 24 0.600 0.097 Spirogyra 8 16 2.000 0.071

Myxophyceae Phormidium 16 16 1.000 0.071 Oscillatoria tenuis 8 16 2.000 0.071 Total 1,472 3.323 TABLE – 5.25: Frequency, density, abundance and diversity index (Shannon and Weiner) of periphyton in Satluj River at sampling site AQ3 during monsoon season

Periphyton Frequency (%)

Density (ind.m/2)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 72 216 3.0 0.503 Diatoma vulgaris 80 16 0.2 0.108 Meridion circulare 64 32 0.5 0.179 Fragilaria inflata 80 232 2.9 0.512 Synedra ulna 80 16 0.2 0.108 Nitzschia 80 16 0.2 0.108 Navicula radiosa 88 20 0.2 0.128 Cocconeis placentula 24 8 0.3 0.064 Cymbella cistula 96 184 1.9 0.479 Gomphonema 16 8 0.5 0.064 Cyclotella 20 8 0.4 0.064 Stauroneis 72 8 0.1 0.064 Ceratoneis arcus 72 8 0.1 0.064 Denticula 72 24 0.3 0.146 Gomphoneis 48 8 0.2 0.064

Chlorophyceae Closterium leibleinii 64 8 0.1 0.064 Zygnema 80 4 0.1 0.037 Ulothrix zonata 40 4 0.1 0.037 Spirogyra 8 8 1.0 0.064

Page 239: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-22

Periphyton Frequency (%)

Density (ind.m/2)

Abundance Diversity index (Shannon Wiener)

Myxophyceae Phormidium 16 8 0.5 0.064 Oscillatoria tenuis 8 8 1.0 0.064 Total 844 2.983 The data on frequency, density, abundance and diversity index (Shannon Weiner) of phytoplankton of Satluj River have been presented in Tables 5.26 to 5.34. The population of phytoplankton was sparse (123 – 331 ind. /Ha) at all the sampling sites. The diversity index ranged from 3.123 to 3.597 in the stretch of the Satluj River under the area of Shongtong HEP. It also confirms the good quality of the water of Satluj TABLE- 5.26: Frequency, density, abundance and diversity index (Shannon and Weiner) of phytoplanktons in Satluj River at sampling site AQ1 during winter season Phytoplankton Frequency

(%) Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 48 22.4 2.333 0.270 Diatoma vulgaris 32 17.6 2.750 0.232 D. elongata 40 20.8 2.600 0.258 Fragilaria inflata 36 19.2 2.667 0.245 Nitzschia 28 19.2 3.429 0.245 Navicula radiosa 44 30.4 3.455 0.324 Cymbella cistula 32 44.8 7.000 0.399 Ceratoneis arcus 40 27.2 3.400 0.304 Astrionella 24 11.2 2.333 0.170 Denticula 32 15.2 2.375 0.210

Chlorophyceae Ulothrix zonata 32 41.6 6.500 0.385 Spirogyra 32 18.4 2.875 0.238

Myxophyceae Oscillatoria tenuis 44 28.8 3.273 0.314

Total 316.8 3.596 TABLE -5.27: Frequency, density, abundance and diversity index (Shannon and Weiner) of phytoplanktons in Satluj River at sampling site AQ1 during summer season Phytoplankton Frequency

(%) Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 48 19.2 2.000 0.252 Diatoma vulgaris 32 16 2.500 0.224 D. elongata 40 19.2 2.400 0.252 Fragilaria inflata 36 17.6 2.444 0.238 Nitzschia 28 19.2 3.429 0.252 Navicula radiosa 44 28.8 3.273 0.322 Cymbella cistula 32 41.6 6.500 0.393 Ceratoneis arcus 40 28.8 3.600 0.322 Astrionella 24 9.6 2.000 0.157 Denticula 32 11.2 1.750 0.175 Chlorophyceae

Page 240: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-23

Ulothrix zonata 32 41.6 6.500 0.393 Spirogyra 32 20.8 3.250 0.265 Myxophyceae Oscillatoria tenuis 44 30.4 3.455 0.332 Total 304 3.576 TABLE- 5.28: Frequency, density, abundance and diversity index (Shannon and Weiner) of phytoplanktons in Satluj River at sampling site AQ1 during monsoon season Phytoplankton Frequency

(%) Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 40 33.6 4.200 0.335 Diatoma vulgaris 40 36.8 4.600 0.352 D. elongata 40 17.6 2.200 0.225 Fragilaria inflata 52 43.2 4.154 0.383 Nitzschia 72 40 2.778 0.368 Navicula radiosa 36 28.8 4.000 0.306 Cymbella cistula 36 25.6 3.556 0.285 Cocconeis 36 9.6 1.333 0.148 Ceratoneis arcus 8 1.6 1.000 0.037 Astrionella 36 14.4 2.000 0.197 Denticula 24 11.2 2.333 0.165

Chlorophyceae Ulothrix zonata 36 22.4 3.111 0.263 Spirogyra 32 17.6 2.750 0.225

Myxophyceae Oscillatoria tenuis 72 28.8 2.000 0.306 Total 331.2 3.597 TABLE 5.29: Frequency, density, abundance and diversity index (Shannon and Weiner) of phytoplanktons in Satluj River at sampling site AQ2 during winter season Phytoplankton Frequency

(%) Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 40 32 4.000 0.337 Diatoma vulgaris 40 36.8 4.600 0.364 D. elongata 40 16 2.000 0.220 Fragilaria inflata 52 41.6 4.000 0.388 Nitzschia 72 40 2.778 0.380 Navicula radiosa 36 25.6 3.556 0.296 Cymbella cistula 36 22.4 3.111 0.273 Cocconeis 36 8 1.111 0.136 Ceratoneis arcus 8 1.6 1.000 0.039 Astrionella 36 9.6 1.333 0.155 Denticula 24 11.2 2.333 0.172

Chlorophyceae Ulothrix zonata 36 20.8 2.889 0.260 Spirogyra 32 17.6 2.750 0.234

Myxophyceae Oscillatoria tenuis 72 28.8 2.000 0.317 Total 312 3.570

Page 241: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-24

TABLE 5.30: Frequency, density, abundance and diversity index (Shannon and Weiner) of phytoplanktons in Satluj River at sampling site AQ2 during summer season

Phytoplankton Frequency (%)

Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 64 32 2.500 0.354 Diatoma vulgaris 60 27.2 2.267 0.324 D. elongata 72 25.6 1.778 0.312 Fragilaria inflata 64 43.2 3.375 0.413 Nitzschia 64 32 2.500 0.354 Navicula radiosa 68 33.6 2.471 0.364 Cymbella cistula 72 33.6 2.333 0.364 Cocconeis 24 4.8 1.000 0.099 Ceratoneis arcus 24 6.4 1.333 0.123 Astrionella 20 6.4 1.600 0.123 Denticula 40 6.4 0.800 0.123

Chlorophyceae Ulothrix zonata 24 16 3.333 0.233 Spirogyra 36 8 1.111 0.145

Myxophyceae Oscillatoria tenuis 32 9.6 1.500 0.165 Total 285 3.496

TABLE 5.31: Frequency, density, abundance and diversity index (Shannon and Weiner) of phytoplankton’s in Satluj River at sampling site AQ2 during monsoon season

Phytoplankton Frequency (%)

Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 40 27.2 3.4 0.454 Diatoma vulgaris 40 28.8 3.6 0.464 D. elongata 40 6.4 0.8 0.200 Fragilaria inflata 52 33.6 3.2 0.490 Nitzschia 16 4.8 1.5 0.164 Navicula radiosa 32 6.4 1.0 0.200 Cymbella cistula 32 8 1.3 0.232 Cocconeis 36 1.6 0.2 0.072 Ceratoneis arcus 8 1.6 1.0 0.072 Astrionella 8 3.2 2.0 0.122 Denticula 8 1.6 1.0 0.072 Chlorophyceae Ulothrix zonata 36 8 1.1 0.232 Spirogyra 32 6.4 1.0 0.200 Myxophyceae Oscillatoria tenuis 24 6.4 1.3 0.200 Total 144 3.172

Page 242: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-25

TABLE 5.32: Frequency, density, abundance and diversity index (Shannon and Weiner) of phytoplankton’s in Satluj River at sampling site AQ3 during winter season

Phytoplankton Frequency (%)

Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 64 33.6 2.625 0.349 Diatoma vulgaris 60 33.6 2.800 0.349 D. elongata 72 25.6 1.778 0.298 Fragilaria inflata 64 43.2 3.375 0.397 Nitzschia 64 35.2 2.750 0.358 Navicula radiosa 68 32 2.353 0.339 Cymbella cistula 72 36.8 2.556 0.366 Cocconeis 24 4.8 1.000 0.094 Ceratoneis arcus 24 6.4 1.333 0.116 Astrionella 20 6.4 1.600 0.116 Denticula 40 9.6 1.200 0.156 Chlorophyceae Ulothrix zonata 24 20 4.167 0.256 Spirogyra 36 9.6 1.333 0.156 Myxophyceae Oscillatoria tenuis 32 11.2 1.750 0.174 Total 308 3.524

TABLE -5.33: Frequency, density, abundance and diversity index (Shannon and Weiner) of phytoplanktons in SatlujRiver at sampling site AQ3 during summer season

Phytoplankton Frequency (%)

Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 64 32 2.500 0.354 Diatoma vulgaris 60 27.2 2.267 0.324 D. elongata 72 25.6 1.778 0.312 Fragilaria inflata 64 43.2 3.375 0.413 Nitzschia 64 32 2.500 0.354 Navicula radiosa 68 33.6 2.471 0.364 Cymbella cistula 72 33.6 2.333 0.364 Cocconeis 24 4.8 1.000 0.099 Ceratoneis arcus 24 6.4 1.333 0.123 Astrionella 20 6.4 1.600 0.123 Denticula 40 6.4 0.800 0.123 Chlorophyceae Ulothrix zonata 24 16 3.333 0.233 Spirogyra 36 8 1.111 0.145 Myxophyceae Oscillatoria tenuis 32 9.6 1.500 0.165 Total 285 3.496

Page 243: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-26

TABLE 5.34: Frequency, density, abundance and diversity index (Shannon and Weiner) of phytoplanktons in Satluj River at sampling site AQ3 during monsoon season

Phytoplankton Frequency (%)

Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Bacillariophyceae Tabellaria fenestris 64 20.8 1.6 0.433 Diatoma vulgaris 60 16 1.3 0.382 D. elongata 32 8 1.3 0.256 Fragilaria inflata 64 24 1.9 0.460 Nitzschia 64 19.2 1.5 0.418 Navicula radiosa 68 19.2 1.4 0.418 Cymbella cistula 8 3.2 2.0 0.137 Cocconeis 8 1.6 1.0 0.081 Ceratoneis arcus 8 1.6 1.0 0.081 Astrionella 8 1.6 1.0 0.081 Denticula 4 1.6 2.0 0.081

Chlorophyceae Ulothrix zonata 16 3.2 1.0 0.137 Spirogyra 8 1.6 1.0 0.081

Myxophyceae Oscillatoria tenuis 32 1.6 0.3 0.081 Total 123 3.129

5.3.1.3 Zooplanktons Zooplankton population in the torrential water current of river Satluj was very low (refer Tables 5.35 to 5.43). Zooplanktons were represented by the taxa of cladocera (01) and rotifera (03). Density of zooplankton was present in the range of 80 – 114 ind. /Ha. The diversity index ranged between 1.798– 1.969 at all the sites. It indicates the poor diversity of zooplankton in the Satluj River. TABLE -5.35: Frequency, density, abundance and diversity index (Shannon and Weiner) of zooplanktons in Satluj River at sampling site AQ1 during winter season

Zooplankton Frequency (%)

Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Cladocerans Daphnia 44 19.2 2.182 0.479

Rotifers Trichocera 48 30.4 3.167 0.530 Keratella 40 24 3.000 0.511 Asplanchna 40 14.4 1.800 0.427 Total 88 1.947

TABLE – 5.36: Frequency, density, abundance and diversity index (Shannon and Weiner) of zooplanktons in Satluj River at sampling site AQ1 during summer season

Zooplankton Frequency (%)

Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Cladocerans Daphnia 48 38.4 4.000 0.529

Rotifers Trichocera 72 22.4 1.556 0.462 Keratella 56 27.2 2.429 0.494 Asplanchna 68 25.6 1.882 0.484 Total 114 1.969

Page 244: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-27

TABLE – 5.37: Frequency, density, abundance and diversity index (Shannon and Weiner) of zooplanktons in Satluj River at sampling site AQ1 during monsoon season

Zooplankton Frequency (%)

Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Cladocera Daphnia 40 33.6 4.2 0.530

Rotifera Trichocera 56 16 1.4 0.447 Keratella 56 19.2 1.7 0.479 Asplanchna 64 19.2 1.5 0.479 Total 88 1.936

TABLE-5.38: Frequency, density, abundance and diversity index (Shannon and Weiner) of zooplanktons in Satluj River at sampling site AQ2 during winter season

Zooplankton Frequency (%)

Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Cladocerans Daphnia 48 17.6 1.833 0.455

Rotifers Trichocera 40 28.8 3.600 0.524 Keratella 72 33.6 2.333 0.531 Asplanchna 16 12.8 4.000 0.394 Total 92.8 1.904

TABLE -5.39: Frequency, density, abundance and diversity index (Shannon and Weiner) of zooplanktons in Satluj River at sampling site AQ2 during summer season

Zooplankton Frequency (%)

Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Cladocerans Daphnia 48 22.4 2.333 0.472

Rotifers Trichocera 40 35.2 4.400 0.528 Keratella 72 28.8 2.000 0.509 Asplanchna 16 20.8 6.500 0.459 Total 107 1.968

TABLE -5.40: Frequency, density, abundance and diversity index (Shannon and Weiner) of zooplanktons in Satluj River at sampling site AQ2 during monsoon season

Zooplankton Frequency (%)

Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Cladocera Daphnia 40 17.6 2.2 0.471

Rotifera Trichocera 40 32 4.0 0.531 Keratella 56 20.8 1.9 0.497 Asplanchna 16 14.4 4.5 0.434 Total 85 1.933

Page 245: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-28

TABLE -5.41: Frequency, density, abundance and diversity index (Shannon and Weiner) of zooplanktons in Satluj River at sampling site AQ3 during winter season Zooplankton Frequency

(%) Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Cladocerans Daphnia 48 36.8 3.833 0.515

Rotifers Trichocera 72 14.4 1.000 0.445 Keratella 56 8 0.714 0.332 Asplanchna 68 20.8 1.529 0.505 Total 80 1.798

TABLE -5.42: Frequency, density, abundance and diversity index (Shannon and Weiner) of zooplanktons in Satluj River at sampling site AQ3 during summer season Zooplankton Frequency (%) Density

(ind./Ha) Abundance Diversity index

(Shannon Wiener) Cladocerans Daphnia 44 20.8 2.364 0.475 Rotifers Trichocera 48 33.6 3.500 0.530 Keratella 40 25.6 3.200 0.506 Asplanchna 40 17.6 2.200 0.446 Total 98 1.957 TABLE -5.43: Frequency, density, abundance and diversity index (Shannon and Weiner) of zooplanktons in Satluj River at sampling site AQ3 during monsoon season

Zooplankton Frequency (%)

Density (ind./Ha)

Abundance Diversity index (Shannon Wiener)

Cladocera Daphnia 40 16 2.0 0.464 Rotifera Trichocera 40 32 4.0 0.529 Keratella 40 17.6 2.2 0.481 Asplanchna 40 14.4 1.8 0.445 Total 80 1.919

5.3.1.4 Macrozoobenthos Macrozoobenthos of Satluj River were represented by the members of Ephemeroptera (11), Trichoptera (02), Plecoptera (02) and Diptera (02). The contribution of Ephemeroptera was maximum to the total macrozoobenthos. It shows the good water quality in the project area. The density of macrozoobenthos was present in the range of 696 – 1,680 ind. m-2. A maximum density was observed at AQ2. The diversity index of macrozoobenthos ranged from 3.111 to 3.575 in Satluj River project area (Tables 5.44 to 5.52), which confirms the rich diversity of aquatic insects and good environmental quality of aquatic ecosystem. TABLE – 5.44: Frequency, density, abundance and diversity index (Shannon and Weiner) of benthos in Satluj River at sampling site AQ1 during winter season

Benthos Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Ephemeropterans Heptagenia 100 128 1.280 0.292 Baetis niger 100 48 0.480 0.152 B. muticus 84 192 2.286 0.368 B. rhodani 96 256 2.667 0.424

Page 246: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-29

Ecdynurus 60 120 2.000 0.281 Ameletus 0 0 0.000 0.000 Sipholonurus 84 72 0.857 0.202 Centroptilum 64 48 0.750 0.152 Ephemerella ignita 48 88 1.833 0.231 Ephemerella notata 64 88 1.375 0.231 Rithrogena 60 8 0.133 0.038

Trichopterans Rhyacophila 84 96 1.143 0.244 Hydropsyche 96 288 3.000 0.446 Plecoptera Perla 72 40 0.556 0.134 Isoperla 72 32 0.444 0.113

Dipterans Tendipes 84 88 1.048 0.231 Total 1,592 3.541

TABLE – 5.45: Frequency, density, abundance and diversity index (Shannon and Weiner) of benthos in Satluj River at sampling site AQ1 during summer season

Benthos Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Ephemeroptera Heptagenia 96 136 1.417 0.294 Baetis niger 96 56 0.583 0.164 B. muticus 88 192 2.182 0.358 B. rhodani 96 272 2.833 0.425 Ecdynurus 60 136 2.267 0.294 Sipholonurus 88 88 1.000 0.223 Centroptilum 56 56 1.000 0.164 Ephemerella ignita 48 96 2.000 0.236 Ephemerella notata 64 88 1.375 0.223 Rithrogena 64 16 0.250 0.064

Trichoptera Rhyacophila 88 96 1.091 0.236 Hydropsyche 96 288 3.000 0.436

Plecoptera Perla 72 40 0.556 0.128 Isoperla 72 32 0.444 0.109

Diptera Tendipes 88 88 1.000 0.223 Total 1,680 3.575

TABLE – 5.46: Frequency, density, abundance and diversity index (Shannon and Weiner) of benthos in Satluj River at sampling site AQ1 during monsoon season

Benthos Frequency (%)

Density (ind.m2)

Abundance Diversity index (Shannon Wiener)

Ephemeroptera Heptagenia 96 48 0.5 0.235 Baetis niger 24 32 1.3 0.178 B. muticus 88 88 1.0 0.339 B. rhodani 96 232 2.4 0.512 Ecdynurus 60 56 0.9 0.259 Sipholonurus 40 32 0.8 0.178 Centroptilum 24 24 1.0 0.146 Ephemerella ignita 48 32 0.7 0.178

Page 247: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-30

Ephemerella notata 40 32 0.8 0.178 Rithrogena 8 8 1.0 0.063

Trichoptera Rhyacophila 40 16 0.4 0.108 Hydropsyche 96 200 2.1 0.492

PlecopteraPerla 16 16 1.0 0.108 Isoperla 16 16 1.0 0.108

DipteraTendipes 32 16 0.5 0.108 Total 848 3.191

TABLE – 5.47: Frequency, density, abundance and diversity index (Shannon and Weiner) of benthos in Satluj River at sampling site AQ2 during winter season Benthos Frequency

(%) Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Ephemeropterans Heptagenia 100 112 1.120 0.269 Baetis niger 100 48 0.480 0.152 B. muticus 84 124 1.476 0.286 B. rhodani 96 256 2.667 0.423 Ecdynurus 60 88 1.467 0.231 Ameletus 0 0 0.000 0.000 Sipholonurus 84 72 0.857 0.202 Centroptilum 64 48 0.750 0.152 Ephemerella ignita 48 168 3.500 0.342 Ephemerella notata 64 104 1.625 0.257 Rithrogena 60 8 0.133 0.038 Trichopterans Rhyacophila 84 96 1.143 0.244 Hydropsyche 96 312 3.250 0.460

Plecoptera Perla 72 40 0.556 0.133 Isoperla 72 32 0.444 0.113

Dipterans Tendipes 84 88 1.048 0.231 Total 1,596 3.533 TABLE – 5.48: Frequency, density, abundance and diversity index (Shannon and Weiner) of benthos in Satluj River at sampling site AQ2 during summer season Benthos Frequency

(%) Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Ephemeroptera Heptagenia 100 128 1.280 0.284 Baetis niger 100 56 0.560 0.164 B. muticus 84 128 1.524 0.284 B. rhodani 96 264 2.750 0.420 Ecdynurus 60 88 1.467 0.224 Sipholonurus 84 72 0.857 0.195 Centroptilum 64 56 0.875 0.164 Ephemerella ignita 48 168 3.500 0.333 Ephemerella notata 64 104 1.625 0.249 Rithrogena 60 8 0.133 0.037 Trichoptera Rhyacophila 84 104 1.238 0.249

Page 248: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-31

Hydropsyche 96 312 3.250 0.452 Plecoptera Perla 72 48 0.667 0.147 Isoperla 72 40 0.556 0.129 Diptera Tendipes 84 96 1.143 0.237 Total 1,672 3.568 TABLE – 5.49: Frequency, density, abundance and diversity index (Shannon and Weiner) of benthos in Satluj River at sampling site AQ2 during monsoon season

Benthos Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Ephemeroptera Heptagenia 100 40 0.4 0.221 Baetis niger 24 24 1.0 0.155 B. muticus 40 88 2.2 0.356 B. rhodani 96 200 2.1 0.504 Ecdynurus 40 48 1.2 0.248 Sipholonurus 24 32 1.3 0.190 Centroptilum 40 24 0.6 0.155 Ephemerella ignita 48 24 0.5 0.155 Ephemerella notata 40 32 0.8 0.190 Rithrogena 8 8 1.0 0.068

Trichoptera Rhyacophila 40 16 0.4 0.115 Hydropsyche 96 200 2.1 0.504

Plecoptera Perla 16 8 0.5 0.068 Isoperla 16 16 1.0 0.115

Diptera Tendipes 24 16 0.7 0.115 Total 776 3.160

TABLE – 5.50: Frequency, density, abundance and diversity index (Shannon and Weiner) of benthos in Satluj River at sampling site AQ3 during winter season

Benthos Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Ephemeropterans Heptagenia 100 120 1.200 0.286 Baetis niger 100 32 0.320 0.116 B. muticus 84 128 1.524 0.298 B. rhodani 96 216 2.250 0.397 Ecdynurus 60 64 1.067 0.190 Ameletus 20 128 6.400 0.298 Sipholonurus 84 72 0.857 0.206 Centroptilum 64 48 0.750 0.156 Ephemerella ignita 48 80 1.667 0.221 Ephemerella notata 64 88 0.000 0.000 Rithrogena 60 8 0.133 0.039

Trichopterans Rhyacophila 84 96 1.143 0.249 Hydropsyche 96 296 3.083 0.457 Plecoptera Perla 72 40 0.556 0.137 Isoperla 72 32 0.444 0.116

Page 249: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-32

Dipterans Tendipes 84 96 1.143 0.249 Total 1,544 3.415

TABLE – 5.51: Frequency, density, abundance and diversity index (Shannon and Weiner) of benthos in Satluj River at sampling site AQ3 during summer season

Benthos Frequency (%)

Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Ephemeroptera Heptagenia 100 264 2.640 0.428 Baetis niger 100 48 0.480 0.151 B. muticus 84 152 1.810 0.322 B. rhodani 96 224 2.333 0.396 Ecdynurus 60 64 1.067 0.185 Ameletus 20 32 1.600 0.112 Sipholonurus 84 56 0.667 0.169 Centroptilum 64 56 0.875 0.169 Ephemerella ignita 48 56 1.167 0.169 Ephemerella notata 40 8 0.200 0.038 Rithrogena 60 16 0.267 0.066

Trichoptera Rhyacophila 84 104 1.238 0.256 Hydropsyche 96 360 3.750 0.483

Plecoptera Perla 72 48 0.667 0.151 Isoperla 72 32 0.444 0.112

Diptera Tendipes 84 88 1.048 0.229 Total 1,608 3.437

TABLE – 5.52: Frequency, density, abundance and diversity index (Shannon and Weiner) of benthos in Satluj River at sampling site AQ3 during monsoon season Benthos Frequency

(%) Density (ind./m2)

Abundance Diversity index (Shannon Wiener)

Ephemeroptera Heptagenia 100 24 0.2 0.168 Baetis niger 24 16 0.7 0.125 B. muticus 80 80 1.0 0.359 B. rhodani 96 160 1.7 0.488 Ecdynurus 24 40 1.7 0.237 Ameletus 4 8 2.0 0.074 Sipholonurus 32 24 0.8 0.168 Centroptilum 40 16 0.4 0.125 Ephemerella ignita 32 24 0.8 0.168 Ephemerella notata 8 32 4.0 0.204 Rithrogena 8 8 1.0 0.074 Trichoptera Rhyacophila 40 8 0.2 0.074 Hydropsyche 96 216 2.3 0.524 Plecoptera Perla 16 16 1.0 0.125 Isoperla 16 8 0.5 0.074 Diptera Tendipes 40 16 0.4 0.125 Total 696 3.111

Page 250: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-33

5.3.1.5 Primary Productivity Primary productivity of river Satluj was mainly contributed by periphytonphytoplatnkton assemblage. The data on gross primary productivity (Pg), net primary productivity (Pn) and P/R ratio have been presented in Tables 5.52 to 5.54 respectively. The data on Pg, Pn and P/R have been presented on terms of biomass (dry), g m-3, carbon value (g C m-3) and calories of energy (K cal m-3) per hour (hr) and per month. The photoperiod (sunshine value) during the month of February 2008 and May 2008 was 12 hours and during the month of July 2008 was 11 hours. The gross primary productivity (Pg) was in the range from 0.621 to 0.671 gCm-3 during February 2008,0.601 to 0.657g C m-3 /hr during May 2008, however 0.554 to 0.624 g C m-3/hr during July 2008. The net primary productivity (Pn) of Satluj River was estimated to be in the range from 0.017 to 0.026 C m-3/ hr during February 2008, 0.008 to 0.021 g C m-3 /hr during May 2008 however 0.008 to 0.014 g C m-3 /hr during July 2008. TABLE 5.53 Gross primary productivity (Pg), respiration (R), net primary productivity (Pn) per month and P/R ratio of aquatic periphyton and phytoplankton in Satluj River during winter season

Sites

Gross primary productivity (Pg)

Respiration (R) Net Primary Productivity (Pn)

P/R ratio

Biomass (dry) g m-3 hr-1

Carbonvalue g C m-3 hr 1

Calories of energy K Cal m-3 hr-1

Biomass (dry) g m-3 hr-1

Carbonvalue g C m-3 hr 1

Caloriesof energy K Cal m-3 hr-1

Biomass (dry) g m-3 hr-1

Carbon value g C m-3 hr-1

Calories of energy K Cal m-3 hr-1

AQ1 1.342 0.671 7.381 1.295 0.647 7.122 0.047 0.023 0.258 1.036AQ2 1.310 0.655 7.205 1.257 0.629 6.916 0.053 0.026 0.289 1.042AQ3 1.242 0.621 6.833 1.209 0.604 6.648 0.034 0.017 0.186 1.028 TABLE – 5.54: Gross primary productivity (Pg), respiration (R), net primary productivity (Pn) per hour and P/R ratio of aquatic periphyton and phytoplankton in Satluj River during summer season

Sites Gross primary productivity (Pg)

Respiration (R) Net Primary Productivity (Pn)

Bioma ss (dry) g m-3 hr-1

Carbon value g C m-3 hr-1

Calories of energy K Cal m- 3 hr-1

Biomass(dry) g m-3 hr-1

Carbonvalue 1 g C m-3 hr-1

Caloriesof energy K Cal m-3 hr-1

Bioma ss(dry) g m-3 hr-1

Carbon value g C m-3 hr-1

Calories ofenergy K Cal m-3 hr-1

P/R ratio

AQ1 1.314 0.657 7.226 1.276 0.638 7.019 0.038 0.019 0.206 1.029AQ2 1.280 0.640 7.040 1.239 0.619 6.813 0.041 0.021 0.227 1.0

AQ3 1.201 0.601 6.606 1.186 0.593 6.524 0.015 0.008 0.083 1.013

TABLE – 5.55: Gross primary productivity (Pg), respiration (R), net primary productivity (Pn) per hour and P/R ratio of aquatic periphyton and phytoplankton in SatlujRiver during monsoon season

Sites Gross primary productivity (Pg)

Respiration (R) Net Primary Productivity (Pn) P/Rratio

Bioma ss (dry) g m-3 hr-1

Carbo n value g C m- 3 hr-1

Calories of energy K Cal m-3 hr-1

Biomass (dry) g m-3 hr-1

Carbonvalue g C m-3 hr-1

Calories ofenergy K Cal m-3 hr-1

Biomas s (dry) g m-3 hr-1

Carbo n value g C m-3 hr-1

Calorie s of energy K Cal m-3 hr-1

AQ1 1.248 0.624 6.864 1.220 0.610 6.710 0.028 0.014 0.155 1.015 AQ2 1.107 0.554 6.090 1.089 0.544 5.987 0.019 0.009 0.103 1.018 AQ3 1.098 0.549 6.039 1.083 0.541 5.956 0.015 0.008 0.083 1.009

Page 251: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-34

5.3.1.6 Trophic Status of Satluj River The P/R ratio of Satluj River was estimated to be in the range from 1.028 to 1.042 during winter, 1.013 to 1.033 during summer and 1.009 to 1.015 during monsoon season. It shows that the primary productivity (Pg) is somewhat higher to community respiration, which is the indicator of autotrophic nature of the aquatic ecosystem. The higher P/R ratio (1.172) is the clear indication of better trophic status present at the sampling site AQ3. 5.3.1.7 Aquatic Macrophytes Some of the aquatic macrophytes were recorded along the bank of the Satluj River. These macrophytes were identified as Equisetum spp., Adiantum and Selaginella spp. Aquatic macrophytes were present in the wet area of riparian zone of Satluj River, where there is some anthropogenic activities. 5.3.2 Fisheries The fisheries constitute an important sector of national economy, because fish populationplay an important role in human economy. Therefore fisheries of Satluj river is asubject of study before commencement of Shongtong H E Project. As per information collected from the Fisheries Department, Satluj river at high reaches i.e. upstream of Bilaspur, harbored 51 species of cold water fishes including exotic trout, snow trout and several other species of hill stream fishes (refer Table-5.56). TABLE-5.56 Fish species reported by Fisheries Department on river Satlu Family Species Cyprinidae Barilius bendelisis, B.Vagra, B.barila, B.modestus, Oxygaster bacaila, Rasbora

daniconius, Carassius auratus, Cirrihinus reba, C.mrigala, Crossocheilus latius, Catla catla, Labeo dero, L.dyocheilus, L.bata, L.calbasu, L.rohita, Cyprinus carpio var. communic, C.carpio var nudus, C.carpio var specularis, Schizothorax richyardsonii*, S. plagiostomus, Ctenopharyngodon idella, Hypophthalmicthys molitrix, Tor putitora*, Garra gotyla gotyla, G. lanita, Punitus sarana, P. ticto, P. chola and P.sophore.

Cobitidae Biota Dario, B. birdi, B. lohachata, Noemacheilus botia, N. rupicola, N. monatanus, N. Kangrae and N. horai

Bagridae Mystus seenghala and M. aor Schilbeidae Clupisoma garua Sisoridae Glyptothorax pectinopterus and G. cavia Belonidae Xenentondon cancila Ophicephalidae Channa gachua and C. punctatus Mastocembelidae Mastocembelus armatus armatus Salmonidae Salmo trutta fario*

Source : Himachal Pradesh Fisheries Department * Migratory fish The same was confirmed by referring to the thesis on “Ecology and Fisheries of Mountain Streams of the North-Western Himalayas”, KL Sehgal, ICAR, Nainital, and year 1988), which reported a large number of fish species mainly belonging to 13 taxonomical families (51 species) inhabited the Satluj river in Himachal region. The details are given in Table-5.57. TABLE-5.57: Fish species reported in river Satluj Name of species Family Local Name Notopterus chitala Notopteridae Pari N. notopterus Notopteridae Moh Barilius barila Cyprinidae - Barilius bendelisis Cyprinidae Patha

Page 252: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-35

Name of species Family Local Name Barilius vagra Cyprinidae Lohari Barilius shacra Cyprinidae Chilwa Danio devario Cyprinidae Parrandah Danio rerio Cyprinidae Kangi Esomus danricus Cyprinidae Makni Rasbora daniconius Cyprinidae Chindolachal Tor chilinoides Cyprinidae Tor putitora* Cyprinidae Mahseer chiniaru Catla catla Cyprinidae Theila Cirrhina mrigala Cyprinidae Mori Cirrhina reba Cyprinidae Sunni Crossocheilus latius punjabensis Cyprinidae Tiller Garra gotyla Cyprinidae Kurka Punitus chola Cyprinidae Chidu Punitus chonchonius Cyprinidae Chidu Punitus ticto Cyprinidae Punitus sophore Cyprinidae Labeo boga Cyprinidae Morah Labeo calbasu Cyprinidae Kalbasu Labeo dero Cyprinidae Gid Labeo dyocheilus Cyprinidae Kunni Labeo gonius Cyprinidae Labeo pangusia Cyprinidae Labeo rohita Cyprinidae Rohi Schizothorax rishardsonii* Cyprinidae Rohi Botia birdi Cobitidae Chipar Noemacheilus botia Cobitidae Sundal Noemacheilus botia aeurus Cobitidae Sunda Noemacheilus corica Cobitidae Talana Noemacheilus kangrae Cobitidae Ompak bimaculatus Siluridae Pallu Wallago attu Siluridae Mullae Mystus bleekri Bagridae Mystus vittatus Bagridae Kingra Mystus seenghala Bagridae Singhara Rita rita Bagridae Khagga Amblyceps mangois Amblycipitidae Sundal Glyptothorax conirostris Sisoridae Nao Glyptothorax pectinopterus Sisoridae Mochi nao Glyptothorax stoliczkae Sisoridae Naiya Clupisoma gaura Schilbeidae Bachwa Belone cancila Belonidae Takla Mugil cascasia Muglidae Buah Channa gachau Channidae Dauli Channa marulius Channidae Saul Mastacembalus armatus Mastocembelidae Bami Salmo trutta fario* Salmonidae Trout/Asla

Source : “Ecology and fisheries of Mountain streams of the North-western \ Himalayas”, K.L. Sehgal, ICAR, Nainital, 1988 Note : * Migratory species

Page 253: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-36

However, the above-mentioned thesis also mentions that as compared to other mountain streams of N-W Himalayas, the fish population in river Satluj, in upper most reaches, is very scanty. The probable reasons are as follows:

a) The flow regime in river Satluj is very turbulent. This makes the upper reaches, difficult habitats for fish. Frequent occurrence of spates makes conditions worse for breeding and propagation of cold-water fish.

b) Sometimes entire species type from the river body disappears due to devastating floods, as happened in case of river Ravi. The flood in 1947 caused complete removal of brown trout population in Ravi.

c) The above mentioned thesis also states that cold-water streams are inherently poor in biological productivity due to low temperature and scanty food. Most of the energy of cold-water fishes is utilized in maintaining their position in fast-flowing waters and hence they live under continuous physiological stress.

d) The current velocity and natural biota are also the factors inhibiting fisheries in the area. e) The hydrological factors also change the structure and consistency of the sub-strratum of

the river channel thus making less favorable for well-being and propagation of cold water fish.

f) According to the thesis, most of the energy of cold-water fishes is utilized in maintaining their position in fast-flowing waters and hence they live under continuous physiological stress and exhibit poor biological productivity.

5.3.2.1 Status of fisheries of the project area The commercial fisheries are non-existent in the project area. The primary productivity of river is very low hence it has poor fish occurrence. The nutrient and temperature levels are given in Table 5.58.

Table 5.58: Primary productivity of Satluj River

Parameters Site-1 Site-2 Site-3 Coordinates 31° 35’ 44” N

78° 17’ 54” E 31° 37’ 57” N 78° 25’ 54” E

31° 39’ 34” N 78° 26’ 42” E

Elevation 1982 2286 2300 Water temp (°C) 5 5.2 6.2 DO (mg/l) 10.2 10.2 10.0 pH 7.7 7.6 7.5 Free CO2 Nil Nil Nil Total Alkanity 44 28 28 Hardness 12 10 12 Nitrate 3.6 2.1 2.4 Phosphate ND ND ND TDS 36 36 40

Source: Directorate of Cold Water Fisheries Research (Indian Council for Agriculture research) Nainital, Uttrakhand (India)

Netting was done to ascertain the presence/ absence of fish fauna using cast net with 4 mm mesh size at all the stations. Repeated netting was done at least ten times, at each station to avoid the possibility of escape of fish, if present in the river. Meantime the water samples were also collected for the estimations of physicochemical parameters. The fish catch area has been shown in Figure 5.2. Cast Net Specification (a) Diameter (m):- 2.7 m (b) Mesh size (mm): I) Near center (mm):- 15 mm II) Towards circumference (mm):- 4 mm ( c) Sinkers: Numbers: 110 (Weight of each sinker: 25 gm).

Page 254: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-37

The major fish species reported in river Satluj and its tributaries are given in Table-5.59. TABLE-5.59: Major fish’s species reported in river Satluj and its tributaries

Scientific Name Local Name Schizothorax plagiostromus Snow Trout Schizothorax richardsonii* (M) Snow Trout Salmo trutta fario* (M) Brown trout Salmo gairdneri gairdnerii* Rain bow trout Barilius spp. - Nemacheilus spp. - Note: * Fish species were also observed during the fisheries survey as well.

Page 255: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-38

Figure - 5.2: Fish catch sampling locations

The Shongtong-Karchham hydroelectric project is located between the stretch of Powari and Ralli villages. This stretch (1,800 - 2,000 m above m.s.l.) was surveyed for the presence of fish and fisheries. This high altitude stretch (1,800 – 2,000 m above m.s.l.) does not support the development of fisheries. Only one Botia specie has been observed in the isolated pools beside the main Satluj River near Speilo, which is about 25Kms upstream of the Project barrage. The other two species (Salmo trutta fario; Salmo gairdneri gairdneri) are exotic which have been introduced in the Satluj River by the Department of Fisheries, GoHP, which can survive in this very cold water. The same situation has been reported by many workers that the indigenous species do not reach beyond Gangnani (1,856 m above m.s.l.) in Bhagirathi River and Joshimath (1,875 m above m.s.l.) in Alaknanda in Uttarakhand. The ecological conditions in these rivers are similar with that of Satluj River. Thus, the finding in field survey is corroborated by published studies. 5.3.2.2 Sport fisheries The sport fishery in the area constituted by brown trout (Salmo trutta fario) and Rainbow trout (Salmon gairdneri). The sport fishery is confined mainly in river Baspa and its tributary. The first transplantation in the Baspa was made in 1930 and subsequently to meet the ever increasing demand of transplants a medium sized farm was established at Sangla in 1962. The details of production of fry at Sangla and their transplantation in Baspa river system are given in Table-3.36. However, the details on number of anglers, licencing fees and the revenue earned are given in Tables-5.60.and 5.61.

Sampling Location -1, Name: Pangi nala, confluence with river Satluj Distance: 500 Mts. U/S of Barrage

Sampling Location -2 Name; Confluence of Kerang Khadd with river Satluj, Distance: 22 Kms. U/S of Barrage

Sampling Location -3 Name; Village Speilo on the banks of River Satluj, Distance: 25 km. U/S of Barrage

Page 256: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-39

TABLE-5.60: Production of trout seed at Sangla farm and their transplanting in Satluj river system*

Year No. of green eggs No. of Fry No. of fry transplants Rainbow trout Brown trout

1992-93 115,900 93,262 68,907 24,355 1993-94 102,270 54,570 31,096 11,737 1994-95 60,985 23,332 21,340 1,992 1995-96 69,180 35,509 35,509 - 1996-97 124,250 68,949 42,213 13,568 1997-98 75,700 23,631 - - 1998-99 80,800 3,000 827 57,612 1999-00 55,000 48,659 - 25,437 2000-01 88,000 57,200 - - 2001-02 102,000 72,267 44,082 - 2002-03 6,000 55,287 - - 2003-04 - 23,000 - - Source: Himachal Pradesh, Fisheries Department, Simla TABLE-5.61: Angling pressure, licencing fee and amount of revenue earned*

Year Number of anglers Daily licencing fee (Rs.) Revenue earned (Rs.) 1992-93 21 10 210

1993-94 23 10 230 1994-95 95 100 9,500 1995-96 87 100 8,700 1996-97 31 100 3,100 1997-98 53 100 5,300 1998-99 29 100 2,900 1999-00 39 100 3,900 2001-02 7 100 700 2002-03 7 100 700 2003-04 15 100 1,500 * Source: Himachal Pradesh Fisheries Department, Shimla, H.P. It is evident from the available data that the sport fisheries is poorly developed in the project area. It is due to difficult terrain and poor infrastructural facilities. The temperature current velocity and natural biota are also the factors inhibiting fisheries in the project area. Satluj Vidyut Jal Nigam has already given an amount of Rs. 160 lakhs for creating the necessary infrastructure facilities for production of stocking and brood stock through H.P.State Fisheries department. 5.3.2.3 Fish Migration Snow trout (Schizothorax richardsonii) is the only commercial species observed in river Satluj in the project area. This species in normal course of its life cycle undertakes long journey during winter months to migrate in the lower reaches in warmer waters. With the warming of water in the lower reaches, in summer season, the species migrates towards the upstream reaches. During its upstream movement, in the months of May and June, this species breeds in the several side streams. Despite no fish population, project is providing fish ladder in the barrage to facilitate possible fish migration (although not observed) to the upstream area of barrage with an eye on distant possibility of decommissioning of certain downstream projects besides being a channel for routing downstream discharge. Project is also funding a Fisheries Development Plan in conjunction with two other HEP’s. This Fisheries Development Plan will be executed by Department of fisheries of GoHP (attached in Chapter - 3 of EMP).

Page 257: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 5-40

5.3.2.4 Spawning and breeding grounds There is no specific spawning or breeding ground observed in the study area. However, the presence of fingerling in the catch near confluence of Baspa river indicate the possibility of breeding in the area.

Page 258: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-1

CHAPTER - 6

SOCIO-ECONOMIC ASPECTS

6.1 INTRODUCTION

As part of the comprehensive EIA study, a comprehensive assessment of socioeconomic aspects was undertaken. The objective of this study was to ascertain the overall socio-economic conditions prevailing in the study area, as well as among the project affected families. Further, impacts, both positive as well as negative, that are likely to occur during the construction and operation phase of the proposed project on the socio-economic aspects of the environment have also been assessed, which has been described in Chapter 7 of this report. A Resettlement and Rehabilitation (R&R) plan has been devised for the Project Affected Families (PAFs) who are likely to lose land, homestead or both due to land acquisition for various project appurtenances as a part of the present studies. The R&R plan has been prepared using the approved R&R plan of Himachal Pradesh Corporation Limited. The same has been outlined in Chapter 13 of the Environmental Management Plan (EMP) report, which is enclosed as a separate volume of this report.

This chapter also outlines the study approach and methodology adopted to carry-out the socio-economic assessment. The chapter outlines the overall socio-economic profile of the study area as well as that of the project affected families.

6.2 STUDY APPROACH

Most of the information required to assess the socio-economic profile and property enumeration for preparation of Resettlement and Rehabilitation Master Plan was collected with the help of a detailed quantitative 100% survey of the PAFs in the affected villages. For identification of PAFs, i.e., families likely to lose their lands and/or homesteads, extensive use of Record of Rights (ROR), viz., revenue records was made. The families thus identified were covered as a part of the socio-economic survey. The information on the following socio-economic parameters was collected:

• Transhumance • Demographic profile • Educational levels • Occupational Profile • Land holding pattern • Cropping pattern • Assets owned • Livestock and other socio-economic parameters etc. During the socio-economic survey, public consultations were also carried-out. The description of the public consultations has been elaborated in Chapter 3 of the EIA report under Section 3.4.3 Socio-economic Aspects.

Page 259: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-2

6.2.1 Preparation

Before the actual survey work started, collection of base-line information, mainly from the secondary sources was undertaken. Discussions with the project officials were held, and secondary data was collected, which included existing documents, reports and other publications relevant to the project. Thereafter, information and database was also collected from the Revenue authorities. This included Jamabandi (Right of Record) and khasra maps of the project affected villages. This data was computerized and based on the khasra numbers proposed to be acquired; a list of all the affected plots and land holders was prepared. The ownership of the affected plots was correlated with the ROR to ascertain the owners/shareholders of the affected/ to be acquired plots of land.

Based on our preliminary field investigations, and through literature review, a household level survey schedule was devised, to capture the overall socio-economic status of the PAFs. The survey schedule was formulated as a series of prompts, rather than a structured questionnaire, to allow the investigators to phrase queries according to the circumstance during interpersonal interviews with PAFs. This survey schedule was pretested in the field, prior to start of the socio-economic survey.

6.2.2 Field work

For the process of primary data collection, a survey team comprising of local investigators was put together. Members of the survey team (investigators/ surveyors) were local educated youths. Special care was taken about the investigators’ comprehension of Hindi language (as the schedules had to be filled-in this language) and at the same time that they are well versed with the local customs and language/dialect, while recruiting them. Training was imparted to the members of the survey team, wherein they were appraised about the purpose of the survey and on the method of interaction with the PAFs and to elicit required information and how to fill in the survey schedules. The survey team traversed the entire project area, including submergence area, barrage alignment and sites of other project appurtenances in each of the project affected villages. The survey team visited various villages in which land is proposed to be acquired. As per our assessment, based on ROR, about 158 project affected persons were identified, who are expected to lose land (agricultural/nonagricultural/homestead) in varying proportion. This list was verified during the survey work, and by the end of the work, the survey team had covered 143 Project Affected Families.

The Project Affected Families were identified using the revenue records. The revenue records of the villages, from where private land was likely to be acquired was procured and computerized. Thereafter, the plots proposed for acquisition were demarked. Thus, the corresponding owners/ tillers of the identified plots were listed-out. These formed the list of project affected families/ persons.

This list was used to locate the affected families in the respective villages and survey was undertaken for them. In all 158 affected families were identified. During the survey, it was observed that some of the project affected persons belonged to same households. Thus, at the end of the survey work, the survey team had contacted 143 families and covered all the 158 PAFs.

Page 260: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-3

The survey team coordinator scrutinized the filled-in survey schedules for internal discrepancies and missing information; which were eliminated in the field, in some cases by either going back to the concerned families, before it was coded for computerization.

6.2.3 Data compilation, Analysis and Reporting

The filled-in survey schedules were scrutinized at WAPCOS headquarters (Delhi) as well, before they were coded and computerized using database computer software. The raw data was then compiled and systematized before it was analyzed for various socioeconomic parameters. Data analysis was undertaken using Statistical Package for Social Sciences (SPSS) computer software. The analyzed outputs have been used in reporting the findings of the socio-economic survey.

6.2.4 Formulation of R&R Plan

The Resettlement and Rehabilitation Plan for the Project Affected Families of the proposed Shongtong-Karchham hydro-electric project has been prepared in line with the provisions and/or guidelines as given in the Resettlement and Rehabilitation Plan for the Project Affected Families of Shongtong-Karchham (Powari-Ralli) hydroelectric project, which has been prepared by the Himachal Pradesh Power Corporation Limited. This R&R Scheme has been prepared by taking into consideration the R&R Policy notified by Government of Himachal Pradesh, vide Notification No Rev(PD)F(5)-1/1999 dated 27-4- 06, the National Rehabilitation and Resettlement Policy 2007 and the National Hydro Policy 2008.

6.3 SOCIO-ECONOMIC PROFILE OF THE STUDY AREA

The Shongtong Hydro-Electric (SHEP) is proposed to be located in Kinnaur district of Himachal Pradesh. For the purpose of this study, a study area has been demarcated as per the guidelines of the Ministry of Environment and Forest (MoEF), which is about 10 km on either sides of the alignment of various project appurtenances. After demarcation of the study area, it is observed that the study area extends into four tehsils, viz., Morang, Kalpa, Nichar and Sangla.

As per our assessment made through the Census map there are 80 villages (11 villages in tehsil Morang, 37 in tehsil Kalpa, 10 in tehsil Nichar and 21 villages in tehsil Sangla) in the study area. The following sub-sections describe the overall socio-economic profile within the study area.

6.3.1 Demographic Profile

According to the Census of India – 2001, the total population residing in the study area is about 31,886 persons, while the total number of households reckons 7,442. The overall sex- ratio (i.e. number of females per 1000 males) is 875, while the overall average family size is about 4.0 persons per family. The demographic profile in the study area is summarized in Table 6.1.

Page 261: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-4

TABLE - 6.1: Demographic Profile of the Study area villages

Study Area Villages No. of HH

Total Population

Male Population

Female Population

Popn less than

Sex Ratio

Avg. Family

Size

Tehsil Morang (T) Sheelapur (34/6) 22 104 52 52 15 1000 4.7 Swaden (34/7) 26 125 62 63 16 1016 4.8 Rarang Khas (34/1) 154 770 395 375 89 949 5.0 Parga (40/2) 36 126 66 60 14 909 3.5 D.P.F-187 (42) 2 5 3 2 2 667 2.5 Kutian (40/3) 49 204 86 118 13 1372 4.2 Ribba Khas (40/1) 170 804 382 422 79 1105 4.7 Holdang (40/4) 146 721 430 291 91 677 4.9 Skiba (48/4) 81 297 162 135 32 833 3.7 Kurpo (40/5) 1 5 3 2 1 667 5.0 Sub-Total Tehsil Morang

(T) 687 3161 1641 1520 352 926 4.6

Tehsil Kalpa (T) Ragura (6/2) 41 210 110 100 28 909 5.1 Khwanta (6/6) 187 861 417 444 112 1065 4.6 Mebar (6/8) 1 4 2 2 1 1000 4.0 Panwa (13/5) 2 2 2 0 0 0 1.0 Boktu (6/7) 8 27 15 12 9 800 3.4 Pangi (6/1) 221 1047 526 521 111 990 4.7 Purbani Khas (42/1) 81 399 189 210 46 1111 4.9 Rawa (42/2) 10 53 30 23 4 767 5.3 Pawari (41/1) 84 461 276 185 42 670 5.5 Telingi (13/1) 41 241 124 117 23 944 5.9 Tarkhwa (13/3) 77 363 179 184 47 1028 4.7 Khwangi (14/1) 456 1648 934 714 228 764 3.6 Kothi (15/1) 324 1184 652 532 104 816 3.7 Duni (17/1) 125 501 261 240 49 920 4.0 Kashmir (15/2) 115 497 227 270 69 1189 4.3 Goli (17/3) 1 5 4 1 0 250 5.0 Dumdumka (19/2) 1 2 2 0 0 0 2.0 Radule (20/2) 38 200 92 108 29 1174 5.3 Kastyo (30/3) 2 5 3 2 0 667 2.5 Dakhaye (30/4) 19 72 39 33 5 846 3.8 Talangcho (30/2) 34 153 74 79 23 1068 4.5 Rogi (30/1) 60 314 148 166 49 1122 5.2

Page 262: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-5

Study Area Villages No. of HH

Total Population

Male Population

Female Population

Popn less than

Sex Ratio

Avg. Family

Size

Shuda Rang (20/4) 102 494 246 248 63 1008 4.8 Saryo (20/3) 70 353 185 168 39 908 5.0 Jangal Mehfuza

Mehduda C-242 (22) 23 88 41 47 9 1146 3.8

Kalpa (20/1) 290 1186 628 558 119 889 4.1 Brelingi (17/2) 135 576 305 271 68 889 4.3 Reckong Peo (18) 858 2968 1886 1082 306 574 3.5 Yuwaringi (19/1) 238 839 457 382 123 836 3.5 Raang (21) 88 351 170 181 37 1065 4.0 Yusaring (37/2) 130 574 278 296 69 1065 4.4 Rali (33/2) 70 382 183 199 46 1087 5.5 Phayag Choden (33/3) 2 3 1 2 0 2000 1.5 Mebar (33/1) 9 40 18 22 10 1222 4.4 Barang (37/1) 102 481 233 248 62 1064 4.7 Tangling (41/2) 108 465 231 234 50 1013 4.3 Sub-Total Tehsil Kalpa 4153 17049 9168 7881 1980 860 4.1 Tehsil Nichar (T) Rall Santhang (100/3) 5 28 17 11 5 647 5.6 Urni Khas (100/1) 126 608 305 303 95 993 4.8 Yulla Khas (102/1) 97 442 224 218 58 973 4.6 Kutano (100/2) 92 386 186 200 57 1075 4.2 Meeru Khas (104/1) 103 529 252 277 73 1099 5.1 Ghumaruning (104/3) 7 27 14 13 1 929 3.9 Runang Uperla (111) 2 6 3 3 0 1000 3.0 Runang Nichla (104/4) 30 113 60 53 15 883 3.8 Cholling (104/2) 72 456 349 107 29 307 6.3 Sub-Total Tehsil Nichar

(T) 534 2595 1410 1185 333 840 4.9

Tehsil Sangla (T) Thikru (2/2) 25 116 57 59 22 1035 4.6 Kilba Khas (2/1) 177 738 372 366 82 984 4.2 Kanahi-Khas (6/1) 92 286 176 110 38 625 3.1 Sapni Khas (13/1) 212 1078 509 569 147 1118 5.1 Shenan Den (13/2) 26 63 36 27 2 750 2.4 Baturi (13/3) 48 204 97 107 6 1103 4.3 Barua Khas (19/1) 195 846 403 443 105 1099 4.3 Dhar Wadang (26) 13 33 23 10 3 435 2.5

Page 263: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-6

Study Area Villages No. of HH

Total Population

Male Population

Female Population

Popn less than

Sex Ratio

Avg. Family

Size

Shobre Yanang (27/2) 2 5 2 3 2 1500 2.5 Nagassaring (19/2) 1 2 1 1 0 1000 2.0 Shaung Khas (27/1) 119 540 274 266 87 971 4.5 Limoden (32/2) 9 19 11 8 0 727 2.1 Chasu Khas (32/1) 112 495 241 254 78 1054 4.4 Jareyo (32/3) 90 650 607 43 9 71 7.2

Sangla (34/1) 463 2053 1020 1033 244 1013 4.4 Kupa (33/2) 119 473 227 246 46 1084 4.0 Kamru Khas (33/1) 239 960 482 478 124 992 4.0 Lachonden (33/4) 1 5 4 1 3 250 5.0 Goroden (33/5) 42 194 85 109 31 1282 4.6 Thapa Saring (34/2) 70 294 138 156 34 1130 4.2 Panpo Kanda (34/3) 13 27 18 9 3 500 2.1 Sub-Total Tehsil Sangla

(T)2068 9081 4783 4298 1066 899 4.4

Total 7442 31886 17002 14884 3731 875 4.3 Source: Census of India – 2001

6.3.2 Caste Profile

The caste profile of the study area is depicted in Table 6.2. As per this table, it is observed that the study area is a tribal dominated area. The total tribal population constitutes about 76.1% of the total population within the study area. The General caste category population is the second largest population group, accounting for about 16% of the total population within the study area. This is followed by the Scheduled caste population, which accounts for about 7.9% of the total population residing in the study area.

TABLE - 6.2 Caste profile in the study area villages

Study Area Villages Total Population

Total GeneralCaste

Population

Total Scheduled

Caste Population

Total Scheduled Tribe Population

Tehsil Morang (T) Sheelapur (34/6) 104 16 0 88 Swaden (34/7) 125 0 0 125 Rarang Khas (34/1) 770 25 0 745 Parga (40/2) 126 0 0 126 D.P.F-187 (42) 5 4 0 1 Kutian (40/3) 204 0 0 204 Ribba Khas (40/1) 804 0 0 804

Page 264: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-7

Study Area Villages Total Population

Total GeneralCaste

Population

Total Scheduled

Caste Population

Total Scheduled Tribe Population

Holdang (40/4) 721 253 12 456 Skiba (48/4) 297 58 0 239 Kurpo (40/5) 5 0 0 5 Sub-Total Tehsil Morang (T) 3161 356 12 2793 Tehsil Kalpa (T) Ragura (6/2) 210 13 0 197 Khwanta (6/6) 861 30 7 824 Mebar (6/8) 4 4 0 0 Panwa (13/5) 2 0 0 2 Boktu (6/7) 27 23 0 4 Pangi (6/1) 1047 6 0 1041 Purbani Khas (42/1) 399 10 0 389 Rawa (42/2) 53 1 0 52 Pawari (41/1) 461 159 8 294 Telingi (13/1) 241 9 0 232 Tarkhwa (13/3) 363 0 9 354 Khwangi (14/1) 1648 643 230 775 Kothi (15/1) 1184 309 165 710 Duni (17/1) 501 101 43 357 Kashmir (15/2) 497 51 191 255 Goli (17/3) 5 0 5 0 Dumdumka (19/2) 2 0 0 2 Radule (20/2) 200 4 0 196 Kastyo (30/3) 5 0 0 5 Dakhaye (30/4) 72 0 0 72 Talangcho (30/2) 153 4 33 116 Rogi (30/1) 314 19 0 295 Shuda Rang (20/4) 494 10 25 459 Saryo (20/3) 353 6 16 331 Jangal Mehfuza Mehduda C-242 (22) 88 0 3 85 Kalpa (20/1) 1186 156 53 977 Brelingi (17/2) 576 32 34 510 Reckong Peo (18) 2968 1511 217 1240 Yuwaringi (19/1) 839 209 0 630 Raang (21) 351 70 3 278 Yusaring (37/2) 574 10 268 296 Rali (33/2) 382 1 5 376 Phayag Choden (33/3) 3 0 0 3 Mebar (33/1) 40 31 0 9 Barang (37/1) 481 0 36 445 Tangling (41/2) 465 15 10 440 Sub-Total Tehsil Kalpa (T) 17049 3437 1361 12251

Page 265: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-8

Study Area Villages Total Population

Total GeneralCaste

Population

Total Scheduled

Caste Population

Total Scheduled Tribe Population

Tehsil Nichar (T) Rall Santhang (100/3) 28 0 0 28 Urni Khas (100/1) 608 6 251 351 Yulla Khas (102/1) 442 29 58 355 Kutano (100/2) 386 14 112 260 Meeru Khas (104/1) 529 13 161 355 Ghumaruning (104/3) 27 0 10 17 Runang Uperla (111) 6 0 0 6 Runang Nichla (104/4) 113 1 22 90 Cholling (104/2) 456 260 20 176 Sub-Total Tehsil Nichar (T) 2595 323 634 1638 Tehsil Sangla (T) Thikru (2/2) 116 0 9 107 Kilba Khas (2/1) 738 19 288 431 Kanahi-Khas (6/1) 286 73 24 189 Sapni Khas (13/1) 1078 26 0 1052 Shenan Den (13/2) 63 11 6 46 Baturi (13/3) 204 0 14 190 Barua Khas (19/1) 846 2 2 842 Dhar Wadang (26) 33 28 0 5 Shobre Yanang (27/2) 5 0 0 5 Nagassaring (19/2) 2 0 0 2 Shaung Khas (27/1) 540 2 5 533 Limoden (32/2) 19 0 0 19 Chasu Khas (32/1) 495 34 68 393 Jareyo (32/3) 650 513 42 95 Sangla (34/1) 2053 94 33 1926 Kupa (33/2) 473 57 8 408 Kamru Khas (33/1) 960 110 0 850 Lachonden (33/4) 5 0 0 5 Goroden (33/5) 194 0 0 194 Thapa Saring (34/2) 294 12 2 280 Panpo Kanda (34/3) 27 12 4 11 Sub-Total Tehsil Sangla (T) 9081 993 505 7583 Total 31886 5109 2512 24265

Source: Census of India – 2001

6.3.3 Literacy levels

The total, male and female literate population residing within the study area is depicted in Table 6.3. As per this table, it is observed that the overall literacy rate within the study area is about 68.4%. The male and female literacy rates are 76.9% and 58.6% respectively.

Page 266: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-9

TABLE - 6.3 Literate population within the study area villages

Study Area Villages Total Literates

Male Literates

Female Literates

Literacy Rate (%)

Tehsil Morang (T) Sheelapur (34/6) 71 38 33 68.3 Swaden (34/7) 87 48 39 69.6 Rarang Khas (34/1) 567 322 245 73.6 Parga (40/2) 70 43 27 55.6 D.P.F-187 (42) 1 1 0 20 Kutian (40/3) 108 55 53 529 Ribba Khas (40/1) 521 273 248 64.8 Holdang (40/4) 449 289 160 62.3 Skiba (48/4) 189 112 77 63.6 Kurpo (40/5) 2 1 1 40 Sub-Total Tehsil Morang (T) 2065 1182 883 65.3 Tehsil Kalpa (T) Ragura (6/2) 128 79 49 60.9 Khwanta (6/6) 570 311 259 66.2 Mebar (6/8) 1 1 0 25 Panwa (13/5) 1 1 0 50 Boktu (6/7) 7 4 3 25.9 Pangi (6/1) 695 404 291 66.4 Purbani Khas (42/1) 212 116 96 53.1 Rawa (42/2) 38 24 14 71.6 Pawari (41/1) 318 222 96 68.9 Telingi (13/1) 179 103 76 74.3 Tarkhwa (13/3) 249 128 121 68.6 Khwangi (14/1) 1128 723 405 68.4 Kothi (15/1) 920 544 376 77.7 Duni (17/1) 334 192 142 66.7 Kashmir (15/2) 267 140 127 53.7 Goli (17/3) 3 3 0 60 Dumdumka (19/2) 1 1 0 50 Radule (20/2) 129 63 66 64.5 Kastyo (30/3) 3 2 1 60 Dakhaye (30/4) 44 29 15 61.1 Talangcho (30/2) 89 54 35 58.2 Rogi (30/1) 173 95 78 55.1 Shuda Rang (20/4) 367 196 171 74.3 Saryo (20/3) 233 139 94 66.0

Page 267: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-10

Study Area Villages Total Literates

Male Literates

Female Literates

Literacy Rate (%)

Jangal Mehfuza Mehduda C-242 (22)

58 32 26 65.9

Kalpa (20/1) 857 506 351 72.1 Brelingi (17/2) 387 225 162 67.2 Reckong Peo (18) 2438 1630 808 82.1 Yuwaringi (19/1) 616 362 254 73.4 Raang (21) 214 132 82 60.9 Yusaring (37/2) 394 206 188 68.6 Rali (33/2) 260 139 121 68.1 Phayag Choden (33/3) 2 1 1 66.7 Mebar (33/1) 16 7 9 40 Barang (37/1) 309 167 142 64.2 Tangling (41/2) 296 178 118 63.6 Sub-Total Tehsil Kalpa (T) 11936 7159 4777 70.0 Tehsil Nichar (T) Rall Santhang (100/3) 17 15 2 60.7 Urni Khas (100/1) 418 229 189 68.9 Yulla Khas (102/1) 274 143 131 61.9 Kutano (100/2) 243 130 113 62.9 Meeru Khas (104/1) 291 158 133 55.0 Ghumaruning (104/3) 14 10 4 51.9 Runang Uperla (111) 2 2 0 33.3 Runang Nichla (104/4) 57 44 13 389 Cholling (104/2) 362 317 45 79.3 Sub-Total Tehsil Nichar (T) 1678 1048 630 61.6 Tehsil Sangla (T) Thikru (2/2) 81 42 39 69.8 Kilba Khas (2/1) 582 298 284 78.9 Kanahi-Khas (6/1) 198 141 57 69.2 Sapni Khas (13/1) 645 370 275 59.8 Shenan Den (13/2) 43 31 12 68.3 Baturi (13/3) 136 76 60 66.7 Barua Khas (19/1) 505 279 226 59.7 Dhar Wadang (26) 21 16 5 63.6 Shobre Yanang (27/2) 2 1 1 40 Nagassaring (19/2) 1 1 0 50 Shaung Khas (27/1) 330 201 129 61.1 Limoden (32/2) 8 7 1 42.1 Chasu Khas (32/1) 305 173 132 61.6

Page 268: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-11

Study Area Villages Total Literates

Male Literates

Female Literates

Literacy Rate (%)

Jareyo (32/3) 560 536 24 86.2 Sangla (34/1) 1387 782 605 67.6 Kupa (33/2) 344 178 166 73.6 Kamru Khas (33/1) 643 370 273 66.9 Lachonden (33/4) 2 1 1 40 Goroden (33/5) 118 58 60 60.8 Thapa Saring (34/2) 195 111 84 66.3 Panpo Kanda (34/3) 10 9 1 37.0 Sub-Total Tehsil Sangla (T) 6116 3681 2435 67.3 Total 21795 13070 8725 68.4

Source: Census of India – 2001

6.3.4 Occupational Profile

As per Census of India – 2001, about 59.16% of the total population in the study area is engaged in some form of vocational activity and is economically productive. On the other hand about 40.84% of the total population in the study area is dependent on those who are engaged in economically productive vocations. Among the working population, about 82.67% are categorized as Main Workers, while about 17.33% have been categorized as Marginal workers.

TABLE - 6.4: Working and Non-working Population in the study area villages

Study Area Villages Total Population

Total Working

Population

Main Workers

Marginal Workers

Non Working

Population

Tehsil Morang (T) Sheelapur (34/6) 104 62 60 2 42 Swaden (34/7) 125 76 76 0 49 Rarang Khas (34/1) 770 562 450 112 208 Parga (40/2) 126 107 78 29 19 D.P.F-187 (42) 5 3 2 1 2 Kutian (40/3) 204 173 137 36 31 Ribba Khas (40/1) 804 694 453 241 110 Holdang (40/4) 721 531 441 90 190 Skiba (48/4) 297 207 119 88 90 Kurpo (40/5) 5 3 2 1 2 Sub-Total Tehsil Morang (T) 3161 2418 1818 600 743 Tehsil Kalpa (T) Ragura (6/2) 210 160 109 51 50 Khwanta (6/6) 861 722 498 224 139

Page 269: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-12

Study Area Villages Total Population

Total Working

Population

Main Workers

Marginal Workers

Non Working

Population

Mebar (6/8) 4 2 2 0 2 Panwa (13/5) 2 2 2 0 0 Boktu (6/7) 27 16 15 1 11 Pangi (6/1) 1047 692 602 90 355 Purbani Khas (42/1) 399 228 124 104 171 Rawa (42/2) 53 29 16 13 24 Pawari (41/1) 461 238 236 2 223 Telingi (13/1) 241 218 155 63 23 Tarkhwa (13/3) 363 306 210 96 57 Khwangi (14/1) 1648 863 742 121 785 Kothi (15/1) 1184 691 530 161 493 Duni (17/1) 501 326 220 106 175 Kashmir (15/2) 497 267 126 141 230 Goli (17/3) 5 4 2 2 1 Dumdumka (19/2) 2 1 1 0 1 Radule (20/2) 200 122 53 69 78 Kastyo (30/3) 5 4 1 3 1 72 56 20 36 16 Talangcho (30/2) 153 116 42 74 37 Rogi (30/1) 314 214 89 125 100 Shuda Rang (20/4) 494 297 297 0 197 Saryo (20/3) 353 243 98 145 110 Jangal Mehfuza Mehduda C-242 (22)

88 50 35 15 38

Kalpa (20/1) 1186 715 468 247 471 Brelingi (17/2) 576 181 160 21 395 Reckong Peo (18) 2968 1465 1453 12 1503 Yuwaringi (19/1) 839 349 282 67 490 Raang (21) 351 210 201 9 141 Yusaring (37/2) 574 130 129 1 444 Rali (33/2) 382 196 193 3 186 Phayag Choden (33/3) 3 2 2 0 1 Mebar (33/1) 40 18 18 0 22 Barang (37/1) 481 344 261 83 137 Tangling (41/2) 465 238 177 61 227 Sub-Total Tehsil Kalpa (T) 17049 9715 7569 2146 7334 Tehsil Nichar (T) Rall Santhang (100/3) 28 20 17 3 8

Page 270: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-13

Study Area Villages Total Population

Total Working

Population

Main Workers

Marginal Workers

Non Working

Population

Urni Khas (100/1) 608 322 321 1 286 Yulla Khas (102/1) 442 255 249 6 187 Kutano (100/2) 386 178 146 32 208 Meeru Khas (104/1) 529 315 314 1 214 Ghumaruning (104/3) 27 15 15 0 12 Runang Uperla (111) 6 4 4 0 2 Runang Nichla (104/4) 113 72 72 0 41 Cholling (104/2) 456 349 348 1 107 Sub-Total Tehsil Nichar (T) 2595 1530 1486 44 1065 Tehsil Sangla (T) Thikru (2/2) 116 63 63 0 53 Kilba Khas (2/1) 738 503 406 97 235 Kanahi-Khas (6/1) 286 160 160 0 126 Sapni Khas (13/1) 1078 434 424 10 644 Shenan Den (13/2) 63 43 38 5 20 Baturi (13/3) 204 102 100 2 102 Barua Khas (19/1) 846 491 491 0 355 Dhar Wadang (26) 33 20 20 0 13 Shobre Yanang (27/2) 5 3 1 2 2 Nagassaring (19/2) 2 2 2 0 0 Shaung Khas (27/1) 540 329 76 253 211 Limoden (32/2) 19 19 19 0 0 Chasu Khas (32/1) 495 314 273 41 181 Jareyo (32/3) 650 609 596 13 41 Sangla (34/1) 2053 1077 1055 22 976 Kupa (33/2) 473 249 228 21 224 Kamru Khas (33/1) 960 488 476 12 472 Lachonden (33/4) 5 2 2 0 3 Goroden (33/5) 194 102 102 0 92 Thapa Saring (34/2) 294 167 167 0 127 Panpo Kanda (34/3) 27 23 22 1 4 Sub-Total Tehsil Sangla (T) 9081 5200 4721 479 3881 Total 31886 18863 15594 3269 13023 Source: Census of India – 2001

Page 271: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-14

6.3.5 Public Health

Public health is an important aspect in water resources and hydro power project. Since the pool of water created by reservoir may be potential sources of vector borne and water borne diseases.

Dysentery, Diarrhea and Jaundice are the commonly observed water borne disease in the study area. No cases of Malaria or Dengue have been reported in the study area. The major disease reported cough, cold, scabes, tuberculosis, lucoria and sexual transmission disease.

Proper medical facilities are not available in the study area. There are only three public health centres one of each at Tangling, Kilba and Tapri. No. of cases of various diseases reported in these PHCs are given in Table 6.5.

TABLE - 6.5 Major diseases reported in the project area district Kinnaur

Name of the Institution

Malaria Dysentery & Diarrhea

Eye disease

Injury Resp. disease

PHC Tangling 0 93 58 96 554 PHC Kilba 0 324 177 197 2272 PHC Tapri 0 1242 1263 1699 2530 Source: Chief Medical Officer, District-Kinnaur

The medical facilities present in the Project Affected Panchayat’s are given in Table 6.6

Table-6.6: Medical Facility in Project Affected Panchayat’s

Medical Facility

Infrastructure

Powari Barang Ralli/Mebar Khawangi

Location Distance (kms.)

Location Distance(kms.)

Location Distance (kms.)

Location Distance (kms.)

Hospital Reckong peo

10 Reckong peo

13 Reckongpeo

25 Reckongpeo

2

Primary Health Centre

Tangling 2.5 Barang 0 Ralli 0 Reckongpeo

2

Source: Office of Chief Medical Officer, Reckong-Peo

6.3.6 Agriculture

The low productivity in agriculture is due to the deteriorating soil cover. Crop cereals and millet crops include barley, wheat, phapra, ogla, some vegetables like potato, cabbage and fruits like apple and chulli are grown. In spite of poor soils and soil erosion, agriculture is practiced at high elevations between El 2000 m and El 3500 m. Grazing occurs at higher elevations in the alpine meadows. At lower elevations, rain fed channel systems irrigate the crops. In the elevated areas that receive no summer rains, the water channels (khuls) are supplied from natural springs and melting snow. The majority of the area is apple crop covering.

Page 272: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-15

The crops produced in the project area district for last 5 years is given in Table 6.7

TABLE - 6.7 Cropping pattern in the project area, district Kinnaur (Area: ha)

Year/ crops 2001-02 2002-03 2003-04 2004-05 2005-06 Wheat 399 347 349 361 300 Maize 387 338 428 264 - Jaw 1,394 1,188 1,133 1,187 - Potato 199 239 169 183 134 Pulses 959 1,539 1,788 1,970 1,990 vegetables 36 23 20 - 134 Source: statistical handbook 2007, district- Kinnaur

Cultivation is the main occupation of the people residing in the study area tehsils. The crop-wise and area-wise details of main crops cultivated within the study area tehsils are depicted in Table 6.8.

TABLE - 6.8 Crop-wise and Area-wise details of main crops cultivated within the study area tehsils

Name of crops Tehsil Morang Tehsil Kalpa Tehsil Sangla Tehsil Nichar

Food Grains Wheat 1 19 17 279 Maize 55 58 42 161 Paddy - - - 22 Jow 205 246 53 401 Other food grains 55 237 416 719 Total Food grains 316 560 528 1582 Pulses Mash - 7 - 1 Channa - - - - Rajmah 163 264 87 245 Other pulses 376 159 216 24 Total Pulses 539 430 303 270 Other crops Potato 2 14 39 70 Chillies - - - Oil seeds - - - 1 Jeera - - 27 2 Onion - - - - Total Other crops 2 14 66 73 Source: District Land Records, Statistical Abstract Handbook 2007, District Kinnaur (HP)

The main crops that are cultivated within the study area tehsils are food grains, pulses and other crops. Food grains include wheat, maize, paddy jow and other food grains. Pulses such as mash, channa, rajmah, etc., are also cultivated. Others crops include potato, onion,

Page 273: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-16

chillies, oilseeds, jeera, etc. it is observed that out of the total land under different crops, the land under food grains accounts for about 64% of the total area cultivated. About 33% and 3% of the total area under cropping within the study area tehsils are under pulses and other crops respectively.

In addition the farmers also cultivate fruits and nuts, such as apple, plum, peach, apricot, pear, cherry, kiwi, grapes, almonds, walnut, chestnut, hazelnut, etc. The Apple production in the Project Affected Area is given in Table 6.9

Table-6.9: Apple Production in Project Affected Panchayat’s Crop Powari Barang Ralli/Mebar Khawangi

Total Production of Apple (Quintals)

9324.20 16577.00 3825.60 12496.11

Per household value of crop (Rs. per farm)

2,22,004.76 2,05,507.44 2,25,035.29 2,65,377.00

Source: Horticulture Department, Reckong-Peo

6.4: SOCIO-ECONOMIC PROFILE OF THE PROJECT AFFECTED FAMILIES

Commissioning of development projects invariably brings about a number of desired and undesired impacts along with it. Most often, development projects are planned based on the availability of exploitable natural resources. Upon commissioning, these areas act as growth foci. This attracts flow of finances, investments, job and other livelihood opportunities, which brings in people from different cultural and social backgrounds. Such planned activities not only provide impetus to the local economy but also bring about a multi-dimensional social and cultural change in the once dormant area. Most often it has been observed, such development projects are commissioned in economically and socially backward areas, which are inhabited by some of the most indigenous populations.

The Shongtong - Karchham hydro-electric project is likely to be located in one of the backward regions of district Kinnaur, which thrives on the tourism industry. A detailed socio-economic study was undertaken in July 2008. The study was taken up to understand the overall social and economic status of the project affected families (PAFs) of this project, their life-style and to assess the likely impacts of the project in terms of loss of personal and community property of the PAFs. A total of 09 villages listed as below are likely to be affected as a result of land acquisition due to the proposed project:

Village Barang (village Panachayat: Barang) Village Kalpa (village Panachayat: Kalpa) Village Khwangi (village Panachayat: Khwangi) Village Powari (village Panachayat: Powari)

Village Ralli – Mebar (village Panachayat: Mebar) Village Tangling (village Panachayat: Powari) Village Yuvrangi (village Panachayat: Kalpa)

6.4.1 Demographic Profile of Affected Population

The detailed description of the socio-economic profile is highlighted in the following sub-sections, which gives an overall summary of the socio-economic conditions of the affected

Page 274: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-17

population residing in the project study area. Census survey covering 100% of the PAFs were conducted in 9 project affected villages that reckoned about 146 families. Amongst these 146 families with a total population of 436 persons was covered.

(A) Religious Affiliation

During survey it was observed that a large majority of the project affected families were Hindus, constituting about 89% of the total surveyed families. About 2% of the affected families practiced Buddhism. However, about 9% of the affected families did not disclose their religious affiliation. The distribution of affected families on the basis of religion is given in Table 6.10.

TABLE – 6.10 Distribution of affected/ survey families on the basis of Religion

Village Buddhist Hindu Data NAGrand Total

Barang 2 5 2 9 Kalpa 3 3 Khwangi 12 12 Powari 22 22 Raang 7 7 Ralli - Mebar 23 23 Talangpi 1 1 Tangling 1 47 11 59 Yuvrangi 7 7 Grand Total 3 127 13 143 Source: Primary Survey, July 2008

(B) Caste distribution of PAFs

The caste-wise distribution of population is outlined in Table 6.11.

TABLE 6.11: Distribution of affected/ survey families on the basis of Caste

Village General Caste

Scheduled Caste

Scheduled Tribe

Data NA Grand Total

Barang 7 2 9 Kalpa 3 3 Khwangi 6 6 12 Powari 3 19 22 Raang 1 6 7 Ralli - Mebar 23 23 Talangpi 1 1 Tangling 3 45 11 59 Yuvrangi 7 7 Grand Total 1 12 117 13 143

Page 275: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-18

Source: Primary Survey, July 2008

It is observed from the above table that about 82% of the total surveyed families belong to the Scheduled Tribe category. The Scheduled Caste category comprises of about 8.4% of the surveyed families, while only 1 family belonged to the General Caste Category. Meanwhile for about 9% of the surveyed families, their caste category could not be ascertained.

(C) Population Characteristics

The demographic profile of the project affected families is given in Table 6.12.

TABLE 6.12: Demographic profile of the surveyed project affected families

Village Females MalesData NA

Total Population

Sex Ratio

Avg. Family Size

Barang 26 22 48 1182 5 Kalpa 7 10 17 700 6 Khwangi 37 29 66 1276 6 Powari 66 58 2 126 1138 6 Raang 19 18 37 1056 5 Ralli –58 50 108 1160 5 Talangpi 3 3 6 1000 6 Tangling 142 150 6 298 947 5 Yuvrangi 5 12 17 417 2 Grand Total 363 352 8 723 1031 5

Source: Primary Survey, July 2008

As per our survey, the total affected population is of the order of 723 persons. Out of this population, males and females constitute about 48.68% and 50.20% of the total affected population. The gender of about 8 persons could not be ascertained. The overall sex ratio among the surveyed project affected families is 1031 females per 1000 males. However, female population in villages Kalpa, Tangling and Yuvrangi are less than 1000. Village Yuvrangi has an exceptionally low female ratio, which could be attributed to single males from other parts having settled here. The average family size is about 5 persons per family.

Information pertaining to the marital status of the affected population was also collected, which is depicted in Table 6.13.

TABLE 6.13: Marital status of the affected population

Village Divorced Married SingleWidow/ Widower DNA

Grand Total

Barang 20 26 2 48 Kalpa 11 6 17 Khwangi 25 38 3 66 Powari 66 55 3 2 126

Page 276: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-19

Raang 14 20 3 37 Ralli -Mebar

62 42 4 108

Talangpi 5 1 6 Tangling 145 137 10 6 298 Yuvrangi 1 6 10 17 Grand Total 1 354 335 25 8 723

Source: Primary Survey, July 2008

About 46.33% of the affected population is single or un-married. Married population constitutes about 48.96% of the total affected population. A small proportion of the affected population, about 3.46% is widows/widower. One person in village Yuvrangi was observed to be divorced. In addition, data pertaining to the marital status of certain affected persons could not be ascertained, which comprises of about 1.1% (8 individuals) of the total project affected population.

During primary data collection, information about resident and non-resident population was also collected from the project affected population (PAPs). The details of the same are given in Table 6.12. It is observed that about 90.6% of the surveyed population is the resident population, and lives in their respective villages. On the other hand, there are about 6 individuals amongst the surveyed population for whom their residential status could not be ascertained. Among the migrants, it was observed that about 35% have migrated for their vocations to various parts of Himachal Pradesh and other parts of the country including Delhi, Mumbai, Punjab, etc. About 57% have migrated to various parts of the country and Himachal Pradesh to pursue their education. The remaining are settled with their families who have migrated out.

TABLE 6.14: Resident and non-resident population amongst the PAFs

Village Data NA Residents Non-residents Total

Barang 46 2 48 Kalpa 17 17 Khwangi 57 9 66 Powari 122 4 126 Raang 27 10 37 Ralli - Mebar 86 22 108 Talangpi 6 6 Tangling 6 280 12 298 Yuvrangi 14 3 17 Grand Total 6 655 62 723

Source: Primary Survey, July 2008

Information on the physical wellbeing of the PAFs was also collected during the socio-economic survey. It was observed that one individual each from villages Kwangi and Tangling were physically challenged. The remaining persons are all physically well and are not challenged either physically or mentally.

Page 277: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-20

6.4.2 Educational profile

The educational profile among the surveyed population as collected through the primary survey is given in Table-6.13. As per the socio-economic survey, about 16.73% of the project-affected population is illiterate/not going to school. The remaining population (80.91%) is either literate or is presently continuing with their education. Thus, out of the total project affected population, persons educated upto or pursuing the primary school level is about 26.0% of the total surveyed population. The percentage of population educated or undergoing their education in middle school and high school is of the order of 13.97% and 29.74% respectively. Individuals who manage to complete school level and have taken-up higher education and who are presently undergoing/have completed graduate (includes BA, BCom, BSc) level comprise 7.88% of the total surveyed population respectively. In addition, about 2.76% of the total surveyed population has either completed or presently undergoing their post graduate level. There are no individuals who are pursuing or have completed traditional form of education.

TABLE 6.15: Educational Profile of the project affected population

Village Name

Illiterate Kinderga rden

Primary School

Middle School

High School

Graduate Post Graduate

Traditional

Barang 2 0 15 7 15 8 1 0Kalpa 5 1 1 5 3 2 0 0Khwangi 13 2 18 5 18 4 1 0Powari 19 0 46 16 34 8 1 0Raang 5 1 4 2 13 7 4 0

Ralli – Mebar

5 0 27 16 32 15 10 0

Talangpi 3 0 0 1 2 0 0 0Tangling 68 0 76 48 89 8 3 0Yuvrangi 1 0 1 1 9 5 0 0Total 121 4 188 101 215 57 20 0

Source: Primary Survey, July 2008

6.4.3 Occupational profile

The occupational profile of the affected population is shown in Table 6.14. As per our survey, it is observed that out of the total affected population about 27.25% are gainfully engaged in an economic activity. This group consists of persons engaged in cultivation, service sector, business, and traditional vocations, which constitute about 19.78%, 6.5%, 0.83%, and 0.14% respectively of the total surveyed population. About 0.69% of the population although does not work, but they have worked and presently draw a pension. About 68.74% of the surveyed population does not contribute economically or in monetary terms, but nevertheless is engaged in some activity. This group constitutes of persons engaged in household chores (primarily women folk) (23.79%) and students (34.02%) and those that do not work at all, which include aged persons and children/ infants (10.93%). The occupational status for about 24 persons could not be ascertained.

Page 278: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-21

TABLE 6.16 Occupational profile of PAPs Vi

llage

Not

Wor

king

Hou

se h

old

Chor

es

Stud

ent

Cul

tivat

ion

Serv

ice

Bus

ines

s

Sha

stri

Pen

sion

er

DN

A

Gra

nd T

otal

Barang 1 11 15 15 4 2 48 Kalpa 3 5 3 6 17 Khwangi 4 13 27 9 3 1 9 66 Powari 18 33 42 29 2 2 126 Raang 3 8 18 3 2 1 2 37 Ralli - Mebar

2 23 34 22 22 2 3 108

Talangpi 2 2 1 1 6 Tangling 43 75 104 54 10 3 1 8 298 Yuvrangi 3 2 3 4 3 2 17 Grand Total

79 172 246 14 47 6 1 5 24 723

Source: Primary Survey, July 2008

6.4.4 Livestock holding pattern

During the survey, it was observed that practically all the affected families reared domesticated animals for milk, meat, eggs and labor. The village-wise details of livestock holding pattern among the PAFs are shown in Table 6.15.

It is clear from Table 6.17 that amongst the livestock, cattle is the most dominant. Cows are mainly reared for their milk. It was observed that a few families owned He-buffalo. Goats and sheep also reared for their meat and wool. A few families reared pigs and poultry birds, for their by-products.

TABLE 6.17 Livestock Holding Pattern of the PAFs

Village Cow

Bull

Cal

f

He B

uffa

lo

She

Buffa

l o

Milc

h B

uffa

lo

Buffa

lo C

al f

Goa

t

Milc

h G

oat

Shee

p

Pig

Poul

tr y

Oth

ers

Barang 14 2 3 1 0 0 0 0 0 5 0 10 0 Kalpa 0 0 0 0 0 0 0 0 0 0 0 0 0 Khwangi 9 0 4 0 0 0 0 0 0 0 2 0 0 Powari 24 0 12 3 0 0 0 52 0 3 0 7 0 Raang 14 1 2 0 0 0 0 0 0 4 0 0 0 Ralli - Mebar 35 8 7 1 0 0 0 60 0 87 10 8 0 Salangpi 1 0 0 0 0 0 0 0 0 0 0 0 0 Tangling 38 1 13 2 0 0 0 0 0 0 0 8 0

Page 279: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-22

Yuvrangi 7 0 4 0 0 0 0 0 0 0 0 0 0 Grand Total 142 12 45 7 0 0 0 112 0 99 12 33 0 Source: Primary Survey, July 2008

6.4.5 Housing and equipment

Information regarding Housing details was also collected from the affected families during the socio-economic survey. Housing patterns vary from one region to the other within the district. In the lower Kinnaur, houses are two storeyed and built of stone and wood. These are either slated or flat roofed. The latter that is most often formed of layers of birch bark covered with earth. The houses are whitewashed with a shining kind of mica. The ground floor is used as cattle-shed and the upper level used for living purpose of its residents.

In the upper Kinnaur, the houses are usually built of stone, with flat roofs made of earth. It is observed that they are ill-made on account of scarcity of wood and stone cannot be cut. Here also the houses are two storeyed and whitewashed.

With the passage of time Traditional houses have been replaced by modern designs and building materials.

The residential unit served the purpose of housing one or many families (off-spring), including their cattle, fuel wood, and other material possessions of these families. It was observed that residential units, on an average have about 1 to 2 floors with about 5 rooms. The average number of floors and rooms in the houses of the PAFs is depicted in Table. 6.18.

TABLE 6.18: Average number of floors and rooms in the houses of the PAFs

Cattle-Shed Godown Kitchen Lavatory Others Residence

Average of Floors

1.0 1.0 1.0 1.0 1.8

Average of Rooms

1.4 1.0 1.0 1.0 1.0 4.9

Source: Primary Survey, July 2008

It was observed during socio-economic survey that about 41% of the residential units were electrified. It was further observed that about 78% of the kitchens, 45% of the lavatories, 19% of the cattle-sheds and about 11% of the godowns were electrified. It was observed that most of the houses had a defined space for housing cattle, with about one room for housing cattle on an average. A small percentage of the houses had provision for separate bathroom and toilet facilities. For sanitation purposes, drains and other means of water outlets were absent in most of the villages.

Page 280: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-23

6.4.6 Household Assets

Information on various material assets owned by the surveyed population was also collected. Usually, the Kinnauri households have some wooden chests for keeping grain and dried apricots. In addition, most of the houses have a separate wooden grain storage structures locally called as “kathar”. Kharcha is a mat for sitting purposes, which is made of goat’s hair. Pakpa, made of sheep, goat or any wild animal is often placed on the kharcha for sitting. Traditionally, the people made use brass and bronze utensils, but increased contact with the outside world, local people are fast adapting to china crockery and steel utensils.

It is clear that many PAFs, if not all, own some material assets. These assets include television sets, LPG cylinders, transistor radio sets, tape recorder sets, refrigerators, etc. Some PAFs also own two wheelers and four wheelers. In addition, some of the PAFs own agricultural implements such as, ploughs, cultivators, chaff cutters, threshers, pump sets, etc.

6.4.7 Sources of Water

Information on sources of water for different uses by the villagers was also collected. It was observed that pipes and taps are used primarily by the PAFs to meet their drinking water requirement and for washing and cleaning purposes. Natural streams and river also contributed to their water requirement. For cattle, water requirements are met by pipe and taps, followed by natural streams and river. It was observed that PAFs made use of pipe and tap which is connected to a system of pipe network connected to taps which were either locally assembled or provided by the government. It includes a storage tanks near a source and connected through a network of pipelines, which is subsequently connected to tap dispensers.

6.4.8 Ownership of Trees

As a part of the survey, information regarding number of fruit bearing and other trees owned by the project affected families was also collected. The village-wise details of trees owned by all the affected families are given in Table 6.19.

TABLE 6.19: Village-wise details of ownership of trees

Village

Name/

Name of Trees Bar

ang

Kal

pa

Khw

angi

Pow

ari

Raa

ng

Ral

li —

Meb

ar

Sala

ngpi

Tang

ling

Yuvr

angi

Gra

nd T

otal

Adu 5 4 4 53 66 Akhrot 26 16 4 3 47 96 Angur (Grapes) 8 3 3 86 100

Baan 126 74 200 Badam (Almonds)

26 12 667 5 181 50 941

Baimi 2 1 3

Page 281: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-24

Bhu 10 10 Chauja 35 35 Chilgoza 10 6 48 64 Chuli (Aprikot) 55 93 121 35 81 10 245 45 685

Khurmani 2 1 2 2 66 73 Nashpati 30 81 51 13 5 138 10 328 Nyoja 71 5 94 170 Plum 10 2 9 21 Seb (Apple) 1730 120 798 2830 1050 3210 50 5239 1200 16227 Walnut 8 8 Grand Total 1876 120 1001 3904 1122 3294 79 6326 1305 19027Source: Primary Survey, July 2008

6.4.9 Loans and Grants

Information pertaining to the financial assistance received/ taken by the PAFs was also collected. As per our survey, about 38 individuals have taken loans for various purposes. It is observed from our survey that a large majority (about 24 individuals) have taken loan for agricultural purposes, including land reclamation. About 11 individuals have taken loans for household activities; for house renovation, household expenditure, repair/ installation of water supply and water heater, etc. About 2 individuals have taken loan for business purposes. A few individuals have also taken loan for purchase of new four wheeler vehicle. It was observed that these individuals had taken loan from government sources, while one individual has taken loan from a cooperative bank. It is observed that the average loan taken by these individuals is of the order of about Rs. 222,000; the least amount taken is about Rs. 2,500 and the largest loan component is about Rs. 1,300,000.

In addition, information about individuals who had received grants was also collected and it was found that, only one PAF had received a grant of Rs. 50,000 from the government.

6.4.10 Awareness about Project

As a part of the field studies, the information on awareness among the PAFs about the proposed project was also collected. It was observed that more than 75% of the PAFs were aware about the proposed Shongtong - Karchham hydro-electric power project.

Page 282: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-25

6.5 ACTIVITIES UNDERTAKEN UNDER R&R PLAN DURING 2009-2010 & 2010-11 Following activities Undertaken under R & R plan During Year 2010-11

Table 6.20: Training and Awareness Camps: S. N.

Name of Project

Allotted Targets (2010-11) Achievement

PAA PAZ Total

1. Shongtong Karchham HEP

4 1 5 3 achieved and 2 is in progress

PAA- Project Affected Area PAZ – Project Affected Zone Table 6.21. . Merit and Support Scholarship Scheme: S. N.

Grade of the school for which Scholarship is proposed

Project-wise target allotted Achievement Shongtong Karchham HEP

1. Matriculation (From 6th standard up to 10th standard)

17

2. Plus two (11th & 12th standard) 10 3. Vocational Training (ITI) 3 Achieved 4. Diploma in Engineering/

Pharmacy/Computer 3

5. Degree in Engineering/Medicine 3 Total 36 *Other then candidates sponsored by HPPCL under ITI Scheme Table 6.22. Self Employment Scheme Targets for the Year 2010-11:

S. N.

Name of Project Allotted Target 2010-11

Achievement

1. Shongtong-Karchham HEP

5 In progress

PAA - Project Affected Area; PAZ - Project Affected Zone Table 6.23: Project–wise Allotted Target for CBO, School Competition & Varshik Mela

S. N. Name of the Schemes Project–wise Allotted Target for CBO, School Competition & Varshik Mela

PAA Paz Total Achievement 1. No. of CBOs involve in

Awareness & Sensitization work

1 - 1 In progress

2. Proposed number for Organizing School Competition

2 1 3 2 Achieved and 1 is in progress

3. Annual Varshik Mela 1 - 1 In progress 4. Sports Tournament (one for

men & one for women) 2 - 2

In progress Total 6 1 7

Page 283: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-26

Following activities Undertaken under R&R plan During Year 2009-10

Table 6.24.: Training and Awareness Camps: S. N. Name of Project Allotted Targets (2009-10) Achievement

PAA/PAZ Total 1 1. Shongtong Karchham HEP 4 4

Table 6.25.: Merit and Support Scholarship Scheme: S. N. Grade of the school for which

Scholarship is proposed Allotted Targets (2009-10) Achievement Shongtong -Karchham HEP

Achieved

1. Matriculation (From 6th standard up to 10th standard)

15

2. Plus two (11th & 12th standard) 5 3. Vocational Training (ITI) 3 4. Diploma in Engineering/

Pharmacy/Computer 2

5. Degree in Engineering/Medicine 2 Total 27 *Other then candidates sponsored by HPPCL under ITI Scheme

S. N. Name of the Schemes Project–wise Allotted Target for CBO, School Competition & Varshik Mela

PAA/PAZ Total Achievement 1. No. of CBOs involve in

Awareness & Sensitization work

1

1 Achieved

2. Number for school competition to be organizing

2

2 1 Achieved

3. Annual Varshik Mela 1 1 Nil

4. Candidates nominated to ITI for Academic Session 2009-10

10 - 10 Achieved

Total 14 14

Page 284: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham hydroelectric project (450 MW)

WAPCOS Centre for Environment 6-27

6.6 BUDGETS FOR RESETTLEMENT & REHABILITATION A total budget of Rs. 39.3 million is required for implementation of Rehabilitation Plan. The details are given in Table 6.26.

TABLE 6.26: Budgetary estimate for implementation of R&R Plan S. No. R&R Components Tentative Cost

(Rs in millions) A Financial Assistance under standard R&R plan 16.5 B Funds for R&R scheme 7.8

C Contingencies including compensation for unforeseen damages etc. 15.0

Total Rs. 39.3 millions

Note: If Alternative land in any eventuality is to be given, cost of the same will be extra.

Cost for minor minerals will be extra.

Page 285: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-1

CHAPTER-7

PREDICTION OF IMPACTS

7.1 GENERAL Based on the project details and the baseline environmental status, potential impacts as a result of the construction and operation of the proposed Shongtong hydroelectric project have been identified. This Chapter addresses the basic concepts and methodological approach for conducting a scientifically based analysis of the potential impacts likely to accrue as a result of the proposed project. The Environmental Impact Assessment (EIA) for quite a few disciplines is subjective in nature and cannot be quantified. Wherever possible, the impacts have been quantified and otherwise, qualitative assessment has been undertaken. This Chapter deals with the anticipated positive as well as negative impacts due to construction and operation of the proposed project. The construction and operation phase comprises of various activities each of which is likely to have an impact on environment. Thus, it is important to understand and analyze each activity so as to assess its impact on environment. The key activities have been categorized for construction and operation phases. Construction Phase Activities • Site preparation including removal of trees; • Earthwork and excavation including controlled blasting and drilling; • Construction of a diversion barrage, intake structure with 4 intake bays with gates and

four intake tunnels passing through four sedimentation chambers; • HRT of 8.02 km length cultivating in open surface surge shaft; • Underground power house to generate (3x150) 450 MW of power; • Tail Race Tunnel of 10 m diameter and 90 m length to discharge flow into river Satluj; • Construction of a temporary bridge over river Satluj; • Project headquarter, offices and colonies (labour and staff); • Disposal of muck and construction wastes; • Transportation of construction material; • Operation and maintenance of construction equipment; • Civil and mechanical fabrication works for construction of various project components; • Operation of DG sets; • Disposal of pollutants from workshops, etc; and • Disposal of effluents and solid waste from labour camps and colonies. Operation Phase Activities

o Diversion of water from river Satluj for hydropower generation; o Equipment maintenance and equipment restoration; and o Sewage and solid waste generation from project colonies.

The various project activities and associated potential environmental impacts on various environmental parameters have been identified and summarized in a matrix and the same is outlined in Table-7.1.

Page 286: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-2

Table 7.1: Matrix for various project activities and associated potential Environmental Impact on various Environmental Parameters

S. No.

Project Activities Soil & Land

Geology Hydrology Water quality

Air quality

Noise Flora/ Fauna

Employment Socio- culture

A. Construction Phase

1. Site preparation including tree cutting √ √ √

2. Earthwork and excavation including blasting and drilling

√ √ √ √ √ √ √ √

3. Construction of Diversion barrage across river Satluj

√ √ √ √ √

4. Construction of head race tunnel √ √ √ 5. Construction of underground surge

shaft √ √ √

6. Construction of underground power house

√ √ √

7. Widening of approach roads √ √ √ √ √ 8. Disposal of muck and construction

wastes √ √ √ √ √

9. Transportation of construction materials

√ √ √ √

10. Operation and maintenance of construction equipment

√ √ √ √

11. Disposal of sewage and solid waste from labour camps

√ √

12. Acquisition of private land √ √ 13. Acquisition of forest land √ √ √ 14. Immigration of labour population √ √ √ √ √ √ √ B. Operation Phase Activities

1. Diversion of water for hydropower generation

√ √ √

2. Equipment maintenance √ √ √ √ 3. Disposal of sewage and solid waste

from project colony √ √

4. Mushrooming of allied activities √ √ √ √ √ √

Page 287: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-3

The impacts which have been covered in the present Chapter are categorized as below: • Impacts on Water Environment • Impacts on Air Environment • Impacts on Noise Environment • Impacts on Land Environment • Impacts on Biological Environment • Impacts on Socio-Economic Environment 7.2 IMPACTS ON WATER ENVIRONMENT The various aspects covered under water environment are: • Water quality; • Sediments; and • Water resources and downstream users. 7.2.1 Water quality a) Construction phase The major sources of surface water pollution during project construction phase are as

follows: • Sewage from labour camps/colonies; • Effluent from crushers; and • Effluents from other sources including muck disposal. i) Sewage from labour camps The project construction is likely to last for a period of 6 years. The peak labour strength likely to be employed during project construction phase is about 800 workers and 200 technical staff. The employment opportunities in the area are limited. Thus, during the project construction phase, some of the locals may get employment. It has been observed during construction phase of many of the projects; the major works are contracted out, who bring their own skilled labour. However, it is only in the unskilled category, that locals get employment. The construction phase, also leads to mushrooming of various allied activities to meet the demands of the immigrant labour population in the project area. The following assumptions have been made for assessing the immigrating population in the area. • 80% of workers and technical staff immigrating into the area are married; • In 80% of the family of workers both the husband and wife will work; • In 100% of the family of technical staff, only husband will work; • 2% of total migrating population has been assumed as service providers; • 50% of service providers will have families; and • Family size has been assumed as 5. Based on experience of similar projects and above referred assumptions, the increase in the population as a result of migration of labour population during construction phase is expected to be of the order of 3,200.

Page 288: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-4

The domestic water requirement has been estimated as 70 lpcd. Thus, total water requirements work out to 0.224 MLD. It is assumed that about 80% of the water supplied will be generated as sewage. Thus, total quantum of sewage generated is expected to be of the order of 0.18 MLD. The BOD load contributed by domestic sources will be about 144 kg/day. It is assumed that the sewage is discharged without any treatment for which, the minimum flow required for dilution of sewage is about 2 cumec. Detailed DO modeling was done using Streeter Phelp’s model. The DO level was estimated using the following equation:

KK1LA [10-K1t – 10-K 2t ]

Dt = ------------------------- + DA 10-K2t K2 – K1

Dt = DO deficit downstream at time t. K1 = Deoxygenation rate K2 = Reaeration rate LA = Ultimate upstream BOD DA = DO deficit upstream t = Time of stream flow upstream to point at which DO level is to be estimated The DO level in the river Satluj was taken as 8.0 mg/l (from Tables - 4.12 to 4.14). The minimum flow in the river Satluj was taken as 70 cumec (from Table - 4.6). The results of DO model are summarized in Table-7.2. TABLE-7.2: Levels of DO at different distance from outfall

Distance from outfall (km) DO (mg/l) 0.1 8.0 0.2 8.0 0.3 8.0 0.4 8.1 0.5 8.1 1.0 8.2

It can be observed from Table-7.2, that no impact is anticipated on river water quality, as a result of disposal of sewage from labour camps. Even though no impact is envisaged on water quality of river Satluj, as a result of disposal of untreated sewage, it is recommended to commission units for treatment of sewage generated from labour camps. In the proposed project, sewage is proposed to be treated through a sewage treatment plant, prior to disposal. ii) Effluent from crushers During construction phase, at least one crusher will be commissioned at the quarry site by the contractor involved in construction activities. It is proposed only crushed material would be brought at construction site. The total capacities of the two crushers are likely to be of the order of 120-150 (tons per hour) tph. Water is required to wash the boulders and to lower the temperature of the crushing edge. About 0.1 m3 of water is required per ton of material crushed. The effluent from the crusher would contain high-suspended solids. About 12-15 m3/hr of wastewater is expected to be generated from each crusher. The effluent, if disposed without treatment can lead to marginal increase in the turbidity levels

DO Modeling due to disposal of sewage from labour camps in river Satluj.

Page 289: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-5

in the receiving water bodies. The natural slope in the area is such that, the effluent from the crushers will ultimately find its way in river Satluj. This amounts to a discharge of 0.0033 to 0.0042 cumec. Even the lowest 10 day minimum flow in river Satluj is 2.18 cumec. The effluent from crusher will have suspended solids level of 3000-4000 mg/l. On the other hand, suspended solids as observed at various sampling locations, during water quality monitoring studies was observed to be <0.1 mg/l. The composite value of suspended solids would increase by 0.25 mg/l, which is insignificant. Thus, no adverse impacts are anticipated due to small quantity of effluent and large volume of water available in river Satluj for dilution. Even then, it is proposed to treat the effluent from crushers in settling tank before disposal so to ameliorate even the marginal impacts likely to accrue on this account. iii) Effluent from other sources Substantial quantities of water would be used in the construction activities. With regard to water quality, waste water from construction activities and runoff from construction site would mostly contain suspended impurities. Adequate care should be taken so that excess suspended solids in the wastewater are removed before discharge into water body. The effluent is proposed to be treated by collecting the waste water and runoff from construction sites and treating the same in settling tanks. b) Operation phase The major sources of water pollution during project operation phase include: • Effluent from project colony; • Impacts on reservoir water quality; • Eutrophication risks; and • Sediments.

i) Effluent from project colony During project operation phase, due to absence of any large-scale construction activity, the cause and source of water pollution will be much different. A combined colony is envisaged at Dakho for Shongtong-Karchham and Integrated Kashang hydroelectric projects. The number of O&M staff for these two projects will reside in a well-designed colony. The colony will have sewage treatment plant and other infrastructure facilities. Thus, problems of water pollution due to disposal of sewage from the labour camp are not anticipated. In the operation phase, about 100 families (total population of 500) will be residing in the project colony proposed to be developed at Dakho (Kalpa). About 0.23 to 0.27 MLD of sewage will be generated. The total BOD loading will be order of 68 to 81 kg/day. It is proposed to provide sewage treatment facilities including secondary treatment units for sewage so generated from the BOD load after treatment will reduce to 10 to 12 kg/day. It shall be ensured that sewage from the project colony be treated in a sewage treatment plant so as to meet the disposal standards for effluent. Thus, with commissioning of facilities for sewage treatment, no impact on receiving water body is anticipated. Thus, no impacts are anticipated as a result of disposal of effluents from the project colony.

Page 290: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-6

ii) Impacts on reservoir water quality The flooding of previously forest and agricultural land in the submergence area will increase the availability of nutrients resulting from decomposition of vegetative matter. Phytoplankton productivity can supersaturate the euphotic zone with oxygen before contributing to the accommodation of organic matter in the sediments. Enrichment of impounded water with organic and inorganic nutrients will be the main water quality problem immediately on commencement of the operation. However, this phenomenon is likely to last for a short duration of initial few years from the filling up of the reservoir. In the proposed project, most of the land coming under reservoir submergence is barren, with few patches of trees. These trees will be cleared before filling up of the reservoir. The proposed project is envisaged as a runoff the river scheme, with significant diurnal variations in water level. In such a scenario, significant re-aeration from natural atmosphere takes place, which maintains Dissolved Oxygen in the water body. Thus, in the proposed project, no significant reduction in DO level in reservoir water is anticipated. iii) Eutrophication risks Another significant impact observed in the reservoir is the problem of eutrophication, which occurs mainly due to the disposal of nutrient rich effluents from the agricultural fields. However, in the present case, fertilizer use in the project area is negligible, hence, the runoff at present does not contain significant amount of nutrients. Even in the post-project phase, use of fertilizers in the project catchment area is not expected to rise significantly. Another factor to be considered that the proposed project is envisaged as a run off the river scheme, with significant diurnal variations in reservoir water level. Thus, residence time would be of the order of few days, which is too small to cause any eutrophication. Thus, in project operation phase, problems of eutrophication, which is primarily caused by enrichment of nutrients in water, are not anticipated. 7.2.2 Sediments When a river flows along a steep gradient, it could carry a significant amount of sediment load, depending on the degradation status of the catchment. When a hydraulic structure is built across the river, it creates a reservoir, which tends to accumulate the sediment, as the suspended load settles down due to decrease in flow velocity. The proposed project is envisaged as a runoff the river scheme, with a barrage. At regular intervals, the gates of the barrage shall be opened to flush out the sediments. Thus, in the proposed project, sedimentation problems are not anticipated. 7.2.3 Water resources and downstream users The Shongtong-Karchham Hydro Electric Project is a run of river scheme project on river Satluj with all the project components proposed to be located on the left bank of Satluj river to harness the available Hydel potential of the river. The river Satluj in the project area flows through a gorge portion. In the intervening stretch, there are quite a few villages on either side of river bank. The residents of these villages do not use the water from river Satluj, as it would entail pumping with significant energy requirements. Normally those villagers use the water of streams flowing close to their villages. The water is conveyed through channels to the point of consumption under gravity.

Page 291: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-7

In the intervening stretch there are quite a few streams with perennial flows. The discharge of the streams has been collected from Him Urja. The river Tangling confluences with river Satluj about 0.3 km downstream of the dam site. Likewise, river Shyang confluences with river Satluj about 0.3 km downstream of the dam site. The 10 daily flow data for Tangling and Shyang streams is given in Table-7.3 and 7.4 respectively.

TABLE-7.3 Average ten daily discharge of Tangling stream

Month 1997 1998 2004 2005 2006 January-I 0.81 0.74 1.05 1.05 0.78 January-II 0.82 0.78 1.05 1.05 0.77 January-III 0.8 0.8 1.05 1.04 0.69 February-I 0.76 0.74 1.06 1.05 0.66 February-II 0.76 0.65 1.06 1.03 0.69 February-III 0.77 0.7 1.02 1.03 0.70 March-I 0.83 0.82 1.11 1.02 0.72 March-II 0.91 0.99 1.16 1.05 0.74 March-III 1.18 1.22 1.22 1.05 0.73 April-I 1.29 1.24 1.14 1.10 0.85 April-II 1.32 1.37 1.2 1.16 0.89 April-III 1.44 1.46 1.29 1.25 1.03 May-I 1.93 1.68 1.41 1.36 1.05 May-II 2.74 2.41 2.2 2.12 1.25 May-III 3.07 3.18 1.41 1.36 1.35 June-I 2.99 3.27 1.93 1.86 1.42 June-II 2.89 2.99 2.17 2.09 1.49 June-III 2.85 2.71 3.94 3.81 1.16 July-I 2.5 2.53 3.98 3.84 1.88 July-II 2.32 2.33 3.16 3.05 2.06 July-III 2.07 2.11 2.73 2.64 2.23 August-I 1.91 1.93 2.32 2.24 2.29 August-II 1.78 1.78 2.27 2.19 2.45 August-III 1.56 1.72 2.23 2.15 1.98 September-I 1.4 1.45 1.93 1.87 1.87 September-II 1.19 1.26 1.87 1.80 1.89 September-III 1.04 1.1 1.56 1.51 2.06 October-I 0.9 0.98 1.5 1.49 1.85 October-II 0.84 0.9 1.4 1.35 1.56 October-III 0.78 0.92 1.27 1.22 1.37 November-I 0.8 0.79 1.24 1.20 1.18 November-II 0.8 0.86 1.23 1.18 0.98 November-III 0.77 0.83 1.13 1.09 0.65 December-I 0.77 0.84 1.1 0.88 0.67 December-II 0.78 0.78 1.06 0.85 0.58 December-III 0.77 0.75 1.08 0.84 0.59

(Unit : cumec) TABLE-7.4 Average ten daily discharge of Shyang stream (Unit: cumec)

Month 1999 2000 2005 January-I 0.18 0.17 0.34 January-II 0.15 0.16 0.34 January-III 0.17 0.16 0.33 February-I 0.22 0.19 0.34 February-II 0.24 0.21 0.33 February-III 0.29 0.2 0.33 March-I 0.36 0.25 0.33

Page 292: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-8

Month 1999 2000 2005 March-II 0.39 0.42 0.34 March-III 0.44 0.45 0.34 April-I 0.53 0.49 0.36 April-II 0.59 0.58 0.39 April-III 0.65 0.71 0.43 May-I 0.96 0.65 0.48 May-II 1.01 0.52 0.82 May-III 1.12 0.55 0.48 June-I 1.45 0.48 0.7 June-II 1.48 0.42 0.8 June-III 1.22 0.79 1.56 July-I 1.13 0.95 1.58 July-II 1.02 1.2 1.23 July-III 0.95 1.26 1.04 August-I 0.89 1.45 0.87 August-II 0.92 1.59 0.85 August-III 0.83 2.3 0.83 September-I 0.65 1.8 0.7 September-II 0.61 1.21 0.67 September-III 0.59 0.85 0.54 October-I 0.58 0.71 0.53 October-II 0.42 0.6 0.48 October-III 0.33 0.52 0.42 November-I 0.28 0.41 0.41 November-II 0.21 0.22 0.4 November-III 0.18 0.18 0.36 December-I 0.17 0.15 0.34 December-II 0.12 0.14 0.33 December-III 0.11 0.16 0.34

The 10 daily flow in lean season (December to February) in Tangling river ranges from 0.78 to 1.08 cumecs. Similarly in Shyang stream, discharge in lean season (December to February) ranges from 0.11 to 1.34 cumec. Thus, a minimum flow of 0.7 cumec to 1.4 cumec will be contributed by the two streams, namely Tangling and Shyang. 7.3 IMPACTS ON AIR ENVIRONMENT a) Construction phase In a water resources project, air pollution occurs mainly during project construction phase. The major sources of air pollution during construction phase are: • Fuel combustion in various construction equipment; • Emissions from crusher; • Impacts due to vehicular movement; • Blasting operations; and • Dust emissions from muck disposal. i) Pollution due to fuel combustion in various equipment The operation of various construction equipment requires of combustion of fuel. Normally, diesel is used in such equipment. The major pollutant, which gets emitted as a result of diesel combustion, is SO2. The SPM emissions are minimal due to low ash content. Based

Page 293: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-9

on past experience in similar projects, SPM and SO2 are not expected to increase significantly. Thus, in the proposed project, no significant impact on ambient air quality is expected as a result of operation of various construction equipment. ii) Emissions from various crushers The operation of the crusher during the construction phase is likely to generate fugitive emissions (mainly dust), which can move even up to 1 km in predominant wind direction. During construction phase, one crusher each is likely to be commissioned at the barrage and powerhouse sites. During crushing operations, fugitive emissions comprising of the suspended particulate will be generated. There could be marginal impacts to settlements close to the sites at which crushers are commissioned. However, based on past experience, adverse impacts on this account are not anticipated. However, during finalizing the project layout, it should be ensured that the labour camps, colonies, etc. are located on the leeward side and outside the impact zone (about 1.5 to 2 km) of the crushers. In addition, an appropriate management measure has been suggested as a part of the Environmental Management Plan. iii) Impacts due to vehicular movement Since the project is located adjacent to National Highway – 22 the traffic density is already very high. And even at this traffic density, the values recorded during ambient air quality monitoring for EIA study are less than 5 µg/m³. Thus, it has been assumed that due to project activity, even if the traffic density doubles, the corresponding values for ambient air quality are not likely to exceed 10 µg/m³, which will still be far less than the permissible standard at 80 µg/m³ for applicable category. Modeling studies for hydrocarbon emissions were conducted and the results are given in Table-7.5.

TABLE-7.5: Increase in hydrocarbon concentration due to vehicular movement

Distance (m) Increase in HC concentration (µg/m3) 10 5 20 2.50 30 1.67 40 1.25 50 1.00 60 0.83 70 0.71 80 0.63 90 0.56

100 0.50 The increase in vehicular density is not expected to significant. In addition, these ground level emissions do not travel for long distances. Thus, the increase in traffic due to project activity will have negligible effect on the air quality of the project area (i.e. 3 sq km), which will be far below the permissible limit. Blasting Operations Blasting will result in vibration, which shall propagate through the rocks to various degrees and may cause loosening of rocks/boulders. The overall impact due to blasting operations

Page 294: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-10

will be restricted well below the surface and no major impacts are envisaged at the ground level. During tunneling operations, dust will be generated during blasting. Induced Draft (ID) blowers will be provided with dust handling system to capture and generated dust. The dust will settle on vegetation, in the predominant down wind direction. Appropriate control measures have been recommended to minimize the adverse impacts on this account. iv) Dust emission from muck disposal The loading and unloading of muck is one of the sources of dust generation. Since, muck will be mainly in form of small rock pieces, stone, etc., with very little dust particles. Significant amount of dust is not expected to be generated on this account. Thus, adverse impacts due to dust generation during muck disposal are not expected. Operation Stage During project operation phase, no major source of air pollution is expected apart for use of DG set of 1000 kVA to meet power requirement during emergencies. The combustion of fuel (mainly Light Diesel Oil (LDO)) is likely to cause air pollution on account of increase SO2 emissions. The emissions from the DG set are not expected to be significant to cause any major adverse impact on ambient air quality. Emissions from DG set will be discharged into the atmosphere through a stack of adequate height as per CPCB guidelines. The details are given in Environmental Management Plan, outlined as a separate volume of this Report. 7.4 IMPACTS ON NOISE ENVIRONMENT

a) Construction phase In a water resource projects, the impacts on ambient noise levels are expected only during the project construction phase, due to earth moving machinery, etc. Likewise, noise due to quarrying, blasting, vehicular movement will have some adverse impact on the ambient noise levels in the area. i) Impacts due to operation of construction equipment The noise level due to operation of various construction equipment is given under. TABLE-7.6: Noise level due to operation of various construction equipment

Equipment Noise level dB(A) Earth moving Compactors 70-72 Loaders and Excavator 72-82 Dumper 72-92 Tractors 76-92 Scrappers, graders 82-92 Pavers 86-88 Truck 84-94 Materials handling Concrete mixers 75-85 Movable cranes 82-84 Stationary

Page 295: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-11

Equipment Noise level dB(A) Pumps 68-70 Generators 72-82 Compressors 75-85 Equipment Noise level dB(A) Others Vibrators 69-81 Saws 74-81

Under the worst-case scenario, considered for prediction of noise levels during construction phase, it has been assumed that all these equipment generate noise from a common point. The increase in noise levels due to operation of construction equipments is given in Table-7.7. TABLE - 7.7: Increase in noise levels due to operation of various construction equipment

Distance (m) Ambient noise levels dB(A)

Projected noise level due to construction activities dB(A)

Net Increase in ambient noise level due to construction activities dB(A)

100 36 74 38 200 36 69 33 500 36 65 29

1,000 36 61 25 1,500 36 60 24 2,000 36 55 19 2,500 36 53 17 3,000 36 51 15

It would be worthwhile to mention here that in absence of the data on actual location of construction equipments, all the equipments have been assumed to operate at a common point. This assumption leads to over-estimation of the increase in noise levels. Since most of the construction machinery will work underground, it may be point source of noise but the impact outside MAT (Main Access Tunnel) and Adit’s will be small. As per project layout only Barrage and Adit - 1 are close to population (approx. ½ km). Whereas, the rest of project components namely Adit - 2 & 3, Power house complex and TRT are about 3-5 km away from any habitation so, any noise impacts due to construction machinery will be very minimal and will be confined to the construction workers only. The proposed increase in noise levels at various distances from sites is given in Table – 7.8. Table 7.8: Projected Noise Levels at various project components Distance/ Site (m)

Barrage & Intake Structure dB (A)

ADIT-I (U/G) dB (A)

ADIT-II (U/G) dB (A)

ADIT-III (U/G) dB (A)

P/H Complex (U/G) dB (A)

TRT dB (A)

100 65 60 60 60 62 65 200 58 54 54 54 55 56 500 31 30 30 30 33 32

1,000 26 24 24 24 25 25 2,000 20 18 18 18 20 19

Page 296: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-12

Distance/ Site (m)

Barrage & Intake Structure dB (A)

ADIT-I (U/G) dB (A)

ADIT-II (U/G) dB (A)

ADIT-III (U/G) dB (A)

P/H Complex (U/G) dB (A)

TRT dB (A)

2,500 16 14 14 14 13 15 3,000 12 8 8 8 9 10 Source: Field survey; (All the construction equipment have assumed to be operating)

During blasting in underground work there will be at least 10dB attenuation in noise levels due to increase in distance and rock cover. Also, it is a known fact that there is a reduction in noise level as the sound wave passes through a barrier. The transmission loss values for common construction materials are given in Table-7.9

TABLE-7.9: Transmission loss for common construction materials

Material Thickness of construction material (inches)

Decrease in noise level dB(A)

Light concrete 4 38 6 39

Dense concrete 4 40 Concrete block 4 32

6 36 Brick 4 33 Granite 4 40

Thus, the walls of various houses will attenuate at least 30 dB(A) of noise. In addition there are attenuation due to the following factors. • Air absorption; • Rain; • Atmospheric in homogeneities; and • Vegetal cover. Attenuation due to other barriers also occur like trees, fence walls and air column distance from blast site to local habitation (500 m). Moreover, as the work progress in underground, the distance as well as rock cover will increase significantly causing further decrease in felt noise level at the surface. Thus, no increase in noise levels is anticipated as a result of various activities, during the project construction phase. The noise generated due to blasting is not likely to have any effect on habitations. However, blasting can have adverse impact on wildlife, especially along the alignment of the tunnel portion. It would be worthwhile to mention that no major wildlife is observed in and around the project site. Hence, no significant impact is expected on this account. However, operation of various construction equipment, blasting, etc. could lead to discomfort to labour populations working in high noise areas, i.e. close to various construction equipment or blasting sites. These labours shall be provided with ear plugs and other protective equipment. In addition, the time of exposure to high noise shall be restricted as per the norms specified by occupational safety & Health Administration. The details are covered in volume-II which outlines the Environmental Management Plan. Impacts due to increased vehicular movement during construction phase, there will be significant increase in vehicular movement for transportation of construction material. At present, there is no vehicular movement near the barrage site. During construction phase,

Page 297: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-13

the increase in vehicular movement is expected to increase up to a maximum of 60 trucks/day (refer to Table – 2.3). As a part of CEIA study, impact on noise level due to increased vehicular movement was studied using Federal Highway Administration model. The results of modelling are outlined in Table-7.10.

TABLE-7.10: Increase in noise levels due to increased project vehicular movement Distance (m) Ambient noise level

dB(A) Projected noise level due to increased vehicular movement dB(A)

Net Increase in ambient noise level due to increased vehicular movement dB(A)

10 36 72 36 20 36 67 31 50 36 61 25 100 36 57 21 200 36 52 16 500 36 46 10

1,000 36 42 06 As mentioned earlier, there will be significant attenuation due to various factors, e.g. absorption by construction material, air absorption, atmospheric inhomogeneties, and vegetal cover. Also, the noise standard for Industrial area during day time is 75 dB (A) and during night time it is 70 dB (A). As per the baseline established during EIA study, the pre-project maximum noise level is 36 dB (A). If the noise level is doubled due to increase in traffic from project activities, even then the limits will be well within the noise standards as prescribed by Central Pollution Control Board (CPCB). Thus, no significant impact on this account is anticipated. appropriate measures have been suggested as a part of Environmental Management Plan (EMP) report to minimize impacts on wildlife. 7.5 IMPACTS ON LAND ENVIRONMENT a) Construction phase The major impacts anticipated on land environment during construction are as follows: • Quarrying operations • Operation of construction equipment • Soil erosion • Muck disposal • Acquisition of land

Page 298: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-14

Quarrying operations The details of construction material requirement are given in Table-7.11.

TABLE-7.11: Details of requirement of construction material S. No. Material Unit Quantity

1. Coarse aggregate lac m3 2.97 2. Fine aggregate lac m3 1.50 3. Cement MT 14,000 4. Structural steel MT 6,200 5. Reinforcement steel MT 20,323 6. High Tensile steel MT 12,824 The sand required for the project is proposed to be taken from Satluj river bank. An aggregate manufacturing equipment sand processing plant will be located at quarry site near village Upmahal Jungi. This quarry site was also used for Karchham-Wangchoo hydroelectric project site. The site is away from habitation. The impervious material required for cofferdam will be met locally. The material for riprap is available on the river banks at site. Attempts will be made to protect banks by mining out the islands first which gets replenished each monsoon or by snow melt in April/May each year. The cement will be transported from ACC Barmana and Ambuja cement factories. The steel transported from Jalandhar or Kalka by road. The quarrying operations are semi-mechanized in nature. Normally, in a hilly terrain like Himachal Pradesh, quarrying is done by cutting a face of the hill. A permanent scar is likely to be left, once quarrying activities are over. With the passage of time, the rock from the exposed face of the quarry under the action of wind and other erosion forces, get slowly weathered and after some time, they become a potential source of landslide. Thus it is necessary to implement appropriate slope stabilization measures to prevent the possibility of soil erosion and landslides in the quarry sites. Similarly, the proposed project would require significant amount of fine material, which can be met either by crushing the aggregates or by excavation from borrow areas. In the proposed project, large quantity of fines shall be required, which would entail excavation from borrow pits. Normally, such sites are left untreated after excavation of the construction material. The pit so created impedes the natural drainage, increases the potential for soil erosion and stores rain water and runoff. These pools of water can serve as habitats for proliferation of mosquitoes, which can lead to increased incidence of vector-borne diseases. ii) Operation of construction equipment During construction phase, various types of equipment will be brought to the site. These include crushers, batching plant, drillers, earthmovers, rock bolters, etc. The siting of this construction equipment would require significant amount of space. Similarly, space will be required for storing of various other construction equipment. In addition, land will also be temporarily acquired, i.e. for the duration of project construction for storage of quarried material before crushing, crushed material,cement, rubble, etc. Efforts must be made for proper siting of these facilities. The various criteria for selection of these sites would be: • Proximity to the site of use; • Sensitivity of forests in the nearby areas; • Proximity from habitations; and

Page 299: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-15

• Proximity to drinking water source. Efforts would be made to site the contractor’s working space in such a way that the adverse impacts on environment are minimal, i.e. to locate the construction equipment, so that impacts on human and faunal population is minimal. iii) Soil erosion The runoff from the construction sites will have a natural tendency to flow towards river Satluj or its tributaries. For some distance downstream of major construction sites, such as barrage, power house, etc. there is a possibility of increased sediment levels which will lead to reduction in light penetration, which in turn could reduces the photosynthetic activity to some extent of the aquatic plants as it depends directly on sunlight. This change is likely to have an adverse impact on the primary biological productivity of the affected stretch of river Satluj. Since, river Satluj has significant flow, hence, impacts on this account are not expected to be significant. However, runoff from construction sites, entering small streams would have significant adverse impact on their water quality. The runoff would increase the turbidity levels with corresponding adverse impacts on photosynthetic action and biological productivity. The impacts on these streams and rivulets thus, would be significant. Adequate measures need to be implemented as a part of EMP to ameliorate this adverse impact to the extent possible. iv) Muck disposal A large quantity of muck is expected to be generated as a result of tunneling operations, construction of roads, etc. The total quantity of muck to be generated is about 2.55 Mm3. Considering a swelling factor of 40%, the quantity of muck to be disposed is 3.57 Mm3. This includes 0.69 Mm3 of open excavation and 1.86 Mm3 of underground excavation. The component wise details of muck to be generated are given in Table-7.12 and details of consumptive use of muck is given in Table-7.13. The excess muck has to be dumped in low lying areas for which an area of 8.2944 Ha has been earmarked.

TABLE-7.12: Component wise details of muck to be generated S. No. Name of component Qty. of Muck (Excavated) (m3)

Open Excavation Underground Excavation

Total

1. River diversion works 99,600 121,450 221,0502. Diversion Barrage 431,175 - 431,1753. Intake, Sedimentation

chambers & flushing conduits

30,000 505,608 535,608

4. HRT & Construction Adits 10,810 943,313 954,1235. Surge Shaft 32,400 97,557 129,9576. Pressure Shaft & Valve

Chamber - 37,956 37,956

7. Power House Complex 21,000 134,808 155,8088. TRT & outfall works 4,700 17,531 22,2319. Road 60,000 - 60,000 Total 689,685 1,858,223 2,547,908

Page 300: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450 MW)

WAPCOS Centre for Environment 7-16

TABLE-7.13: Abstract of Consumptive Use of Muck

S. No.

Components Qty. of Muck Debris generated I/C 40% swelling factor (cum)

Quantity to be used as backfill (m3)

Quantity to be used in construction or protection works

1. River diversion works 309,470 61,984 77,368 2. Diversion Barrage 603,645 181,093 120,729 3. Intake, Sedimentation

chambers & flushing conduits

749,851 149,970 149,970

4. HRT & Construction Adits 1,335,772 - 534,309 5. Surge Shaft 181,940 - 72,776 6. Pressure Shaft & Valve

Chamber 53,138 - 21,255

7. Power House Complex 218,131 43,626 54,533 8. TRT & outfall works 31,123 4,668 7,781 9. Road 84,000 29,400 16,800 Total 3,567,070 470,651 105,552

Considering a swelling factor of 40%, the quantity of muck to be disposed is 3.57 Mm3. About 0.47 Mm3 of muck shall be used as backfill, while 1.05 Mm3 of muck shall be used as a construction material/protection works. The balance, i.e. (3.56; 0.47 and 1.05) 2.04 Mm3 of muck shall be disposed at designated sites. The details of muck disposal sites and component wise muck disposal is given in Table-7.14.

Page 301: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-17

TABLE-7.14 Component-wise Details Planning for Muck Disposal

S. No Location Area (Ha)

Capacity (CuM)

Distance Qty. of muck debris to be dumped from Addl. Capacity From

Barrage & Adit-I

From Adit - II

From Adit-III & PH

1 Powari village 1.1383 349,000 2 km 5.00 km 9.00 km Intake sedimentation chambers & flushing conduits.

330,000 19,000

2 Tangling village 3.5738 761,645 0.50 km 1.50 km 5.50 km River diversion works, Barrage intake, sedimentation chambers flushing conducts & upper half of HRT.

700,000 61,645

3 Near Shongtong bridge

0.8928 237,300 1.50 km 1.00 km 5.00 km Upper half of HRT & Diversion barrage.

225,000 12,300

4 Lal Dhank 1.2450 417,900 5.00 km 2.00 km 3.00 km Lower half of HRT & Diversion barrage.

400,000 17,900

5 Ralli Det 0.8626 115,750 7.00 km 2.00 km 2.00 km P/H Complex & TRT. 95,000 20,750 6 Ralli Det (I),

Utilization of muck

0.50 25,750 7.00 km 2.00 km 2.00 km P/H Complex & TRT. 20,000 5,750

7 Ralli Det (II), Utilization of muck

1.80 111,600 7.00 km 2.00 km 2.00 km P/H Complex & TRT. 96,000 15,600

8 P/H Site 0.5819 187,300 9.00 km 6.00 km 0.50 km Valve chamber outfall works Road & TRT.

175,000 11,300

Total 10.0944 2,178,973 Total 2,041,000 137,973

Page 302: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-18

Normally, muck is disposed in low-lying areas or depressions. Trees, if any, are cut before muck disposal, however, shrubs, grass or other types of undergrowth in the muck disposal at sites perish. The total area earmarked for muck disposal is 10.0944 Ha. The muck disposal sites will be suitably stabilized on completion of the muck disposal. The details of stabilization of muck disposal sites are outlined in Environmental Management Plan covered in Volume-II of this Report. v) Acquisition of land The total land to be acquired for the project is 77.3326 Ha. A part of this land is required for labour camps, quarry sites, muck disposal storage of construction material, siting of construction equipment, which will be required temporarily and returned once the construction phase is over. Permanent acquisition of land is required for barrage axis, submergence area, project colony, etc. The details of land required for various project appurtenances is given in Table-7.15. The item wise forest and private land to acquired is given in Tables-7.16 and 7.17 respectively.

TABLE-7.15: Land required for the proposed Shongtong-Karchham, HE Project

Type Quantity (Ha) Forest 63.5015 Private 13.8311 Total 77.3326

Appropriate plan for compensation of forest and private land to be acquired for the project has been formulated and is covered as a part of Environmental Management Plan outlined in Volume-II of this Report.

Page 303: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-19

TABLE-7.16: ITEM WISE BREAKUP OF FOREST LAND PROPOSED FOR THE DIVERSION S. No. Name of component of project Area of forest land (Ha) Legal status of forest land Remarks

1. Diversion Tunnel 1.1957 Under Ground Activity 2. Intake Tunnel 0.4917 Under Ground Activity 3. Transitions 0.1442 Under Ground Activity 4. Sedimentation Chambers 3.1500 Under Ground Activity 5. Silt Flushing Tunnel 0.0798 Under Ground Activity 6. Main Silt Flushing Tunnel 0.2520 Under Ground Activity 7. Feeder Tunnels to HRT 0.2957 Under Ground Activity 8. Gate Galleries 0.1012 Under Ground Activity 9. Head Race Tunnel 8.8215 Under Ground Activity 10. Adit-1 0.2835 Under Ground Activity 11. Adit-2 0.4698 Under Ground Activity 12. Adit-3 0.1701 Under Ground Activity 13. Surge Shaft 0.1640 Under Ground Activity 14. Adit to valve Chamber and top of Surge Shaft 0.3645 Under Ground Activity 15. Drainage Gallery 0.1840 Under Ground Activity 16. Pressure Shaft 0.3608 Under Ground Activity 17. Valve Chamber 0.1056 Under Ground Activity 18. Machine Hall 0.1911 Under Ground Activity 19. Transformer Hall 0.1175 Under Ground Activity 20. Approach Adit to Machine Hall 0.0801 Under Ground Activity 21. Cable Cum Ventilation Tunnel 0.1037 Under Ground Activity 22. Tail Race Tunnel 0.0990 Under Ground Activity 23. Diversion Barrage and Reservoir 27.107 UPF Surface Activity 24. Dumping Area-1 1.1888 UPF Surface Activity 25. Job Facility (Batching Plantes) 0.5970 UPF Surface Activity 26. Job Facility (Store/Shop etc.) 0.3510 UPF Surface Activity 27. Dumping Area-2 0.3792 UPF Surface Activity 28. Dumping Area-3 0.8926 UPF Surface Activity 29. Dumping Area-4 1.2450 UPF Surface Activity 30. Job facility for Power House 3.0426 UPF Surface Activity 31. Site office and Staff Quarters 0.2813 UPF Surface Activity 32. Dumping Area-5 0.8626 UPF Surface Activity 33. Road to Magazine & Top – Surge Shaft 0.5122 UPF Surface Activity 34. Surge Shaft, Working area & Road to Bottom 3.0216 UPF Surface Activity

Page 304: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-20

S. No. Name of component of project Area of forest land (Ha) Legal status of forest land Remarks

of Surge Shaft 35. Explosive Magazine 0.1800 UPF Surface Activity 36. Dumping Area-6 0.5819 UPF Surface Activity 37. Road to Surge Shaft Via Adit-3 and Working

Area 4.3292 UPF Surface Activity

38. Quarry 1.8500 UPF Surface Activity Total 63.8018

Page 305: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-21

TABLE-7.17: STATEMENT SHOWING NON-FOREST AREA (PRIVATE LAND) INVOLVED IN PROPOSAL S. No. District Sub-

Division Tehsil/Sub-Mohal Components of project Khasra No. Area of Non- Forest

land (Ha) Classification of land

1 Kinnaur Kalpa Kalpa/Powari Diversion, Barrage and Reservoir

389,390,394 0.3482 Kulahu Abbal

2 Kinnaur Kalpa Kalpa/Khawangi Diversion, Barrage and Reservoir

474,475,478,4 79, 480,483 0.2225 Banjar Kadim

3 Kinnaur Kalpa Kalpa/Khawangi Diversion, Barrage and Reservoir

481.482 0.0749 Kulahu Abbal

4 Kinnaur Kalpa Kalpa/Khawangi Diversion, Barrage and Reservoir

724 0.0247 Ghasni

5 Kinnaur Kalpa Kalpa/Khawangi Diversion, Barrage and Reservoir

1065 0.0016 Gharat

6 Kinnaur Kalpa Kalpa/Khawangi Diversion, Barrage and Reservoir

1060 0.0192 Bagicha Bakhal Neoja

7 Kinnaur Kalpa Kalpa/Khawangi Diversion, Barrage and Reservoir

722 0.0587 Kulahu Abbal

8 Kinnaur Kalpa Kalpa/Powari Job facility (Batching Plant) 812,813,815 0.2660 Kulahu Abbal 9 Kinnaur Kalpa Kalpa/Powari Job facility (Batching Plant) 814 0.0098 Gair Mumkin Doon

10 Kinnaur Kalpa Kalpa/Powari Job facility (Batching Plant) 818 1.2678 Bagicha Bakhal Neoja

11 Kinnaur Kalpa Kalpa/Powari Job facility 810 0.0015 Gair Mumkin Nalla

12 Kinnaur Kalpa Kalpa/Tangling Dumping Area-2

302, 303, 316, 317, 319, 321, 322, 325, 330, 335, 336, 337, 338, 649, 650, 651, 652, 653, 555, 664, 665, 666, 803, 804, 307

1.9331 Kulahu Abbal

13 Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 304 0.312 Gair Mumkin Khandar 14. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 305 0.229 Banjar Kadim 15. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 306 0.009 Dogri 16. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 307 0.0042 Kuhal 17. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 308 0.0010 Gharat 18. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 309 0.0028 Kuhal 19. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 310 0.0062 Gair Mumkin Khandar 20. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 311 0.0015 Great 21. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 312, 313, 314 0.2264 Bagicha Bakhal Seb 22. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 315 0.0227 Banjar Kadim 23. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 318 0.0036 Dogri 24. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 320 0.0139 Gair Mumkin Makan 25. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 323 0.0054 Gair Mumkin Makan

Page 306: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-22

S. No. District Sub- Division

Tehsil/Sub-Mohal Components of project Khasra No. Area of Non- Forest land (Ha)

Classification of land

26. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 324 0.0032 Gair Mumkin Makan 27. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 326 0.1293 Bagicha Bakhal Seb 28. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 327 0.0027 Gair Mumkin Makan 29. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 328 0.0004 Kuthar 30. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 329 0.0586 Bagicha Bakhal Seb 31. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 331 0.0009 Kuthar 32. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 332 0.0056 Rasta 33. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 333 0.0054 Gair Mumkin Makan 34. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 334 0.0070 Gair Mumkin Makan 35. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 654 0.0755 Banjar Kadam 36. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 656 0.0508 Banjar Kadam 37. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 657,658,659 0.0641 Gair Mumkin Darya 38. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 660 0.0138 Banjar Kadam 39. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 661 0.0074 Gair Mumkin Darya 40. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 662 0.0164 Banjar Kadam 41. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 663 0.0738 Bagicha Bakhal Seb 42. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 667,802 0.3172 Gair Mumkin Darya 43. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 801 0.0810 Banjar Kadam 44. Kinnaur Kalpa Kalpa/Tangling Dumping Area-2 806 0.0055 Gair Mumkin Makan 45. Kinnaur Kalpa Kalpa/Ralli Job facility for Power

House 295 0.2772 Banjar Kadam

46. Kinnaur Kalpa Kalpa/Ralli Job facility for Power House

299 0.0604 Banjar Kadam

47. Kinnaur Kalpa Kalpa/Ralli Job facility for Power House

296 0.0630 Gair Mumkin Dawar

48. Kinnaur Kalpa Kalpa/Ralli Site office and Temporary hutments

69,333,56, 332,56,334,56 0.2887 Ghasri

49. Kinnaur Kalpa Kalpa/Ralli Site office and Temporary hutments

70,67 0.0094 Gair Mumkin Dogan

50 Kinnaur Kalpa Kalpa/Rang Store at Barrage site 6 0.0987 Bagicha Bakhal Abbal Seb

51 Kinnaur Kalpa Kalpa/Rang Colony 61,94 6.9687 Bagicha Bakhal 52 Kinnaur Kalpa Kalpa/Rang Colony 657 0.0472 Bagicha Bakhal Doyam

53 Kinnaur Kalpa Kalpa/Rang Colony 656,59,733,66, 59,711,664,59 0.3927 Bagicha Kulahu Abbal

54 Kinnaur Kalpa Kalpa/Rang Colony 62 0.1533 Bagicha Bakhal Doyam Total 13.8311

Page 307: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-23

7.6 IMPACTS ON BIOLOGICAL ENVIRONMENT a) Construction phase 7.6.1 Impacts on Terrestrial flora i) Increased human interferences The direct impact of construction activity of any water resource project in a Himalayan terrain is generally limited in the vicinity of the construction sites only. As mentioned earlier, a large population (3,200) including technical staff, workers and other group of people are likely to congregate in the area during the project construction phase. It can be assumed that the technical staff will be of higher economic status and will live in a more urbanized habitat, and will not use wood as fuel, if adequate alternate sources of fuel are provided. However, workers and other population groups residing in the area may use fuel wood, if no alternate fuel is provided for whom alternate fuel could be provided. There will be an increase in population by about 3200 which would require fuel. * Average fuel wood consumption : 20 kg pcd * Average population size over project

construction phase : 2,500

* Average consumption per day : 500 quintals/day Or 182,500 quintals/year * For a construction period of 6 years : 1,095,000 quintals or 31,2857 m3. *One tree produces about 2.5 m3 of wood, thus, about 1.25 lakh trees will be cut to meet the fuel wood requirements to the labour population, over a construction phase of 6 years. Hence to minimize impacts, community kitchens have been recommended. These community kitchens shall use LPG or diesel as fuel. The details are covered in Environmental Management Plan covered in Volume-II of this Report. The other major impact on the flora in and around the project area would be due to increased level of human interferences. The workers may also cut trees to meet their requirements for construction of houses and other needs. Thus, if proper measures are not undertaken, adverse impacts on terrestrial flora is anticipated. Since, labour camps are proposed to be constructed by the contractor along with necessary facilities, such impacts are not envisaged. During construction of various components of the project, e.g., road, colony, dam axis, muck disposal, etc. trees will have to be cleared. The tree felling or clearing shall be done by the State Forest Corporation.

Impacts due to Vehicular movement and blasting Dust is expected to be generated during blasting, vehicle movement for transportation of construction material or construction waste. The dust particles shall settle on the foliage of trees and plants, thereby reduction in amount of sunlight falling on tree foliage. This may reduce the photosynthetic activity, although stomata are located on the underside of leaves in greater concentration. Based on experience in similar settings, the impact is expected to be localized up to a maximum of 50 to 100 m from the source. In addition, the area experiences rainfall for almost 8 to 9 months in a year. Thus, minimal deposition of dust is expected on flora. Thus, no significant impact is expected on this account.

Page 308: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-24

Acquisition of forest land During project construction phase, land will be required for location of construction equipment, storage of construction material, muck disposal, widening of existing roads and construction of new project roads. The total land requirement for the project is 77.3326 Ha of which 63.5015 Ha is forest land. The details are given in Table-7.18.

Page 309: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-25

TABLE-7.18: DETAILS OF FOREST AREA PROPOSED FOR DIVERSION S. No. District Forest Division Range/Teh./Sub. Mohal Khasra/Survey or

Compartment or km stone Forest area

proposed for diversion (Ha)

Legal status of forest area

Remarks

1. Kinnaur Kinnaur al R/Peo.

Kalpa/Kalpa/Rang 724/576/1,571/1 0-89-28 UPF For surface activity

2. Kinnaur Kinnaur al R/Peo.

Kalpa/Kalpa/Usaring 4/1 1-24-50 UPF For surface activity

3. Kinnaur Kinnaur al Kalpa/Kalpa/Powari 393,392,389,391,387,816, 13-09-81 UPF For surface R/Peo. 797,810,811,817,821 activity 4. Kinnaur Kinnaur al

R/Peo. Kalpa/Kalpa/Tangling 301,931/1,648,805 0-73-04 UPF For surface

activity 5. Kinnaur Kinnaur al Kalpa/Kalpa/Ralli 393294/1, 294/2, 51/1, 12-81-18 UPF For surface R/Peo. 29/1, 291/1, 291/2, 291/3, activity 24/1, 24/2, 293/1, 293/3, 293/2, 291/4, 297, 303/1, 298, 305/1, 200, 301, 303/2, 51/1 6. Kinnaur Kinnaur al

R/Peo. Kalpa/Kalpa/Khawangi 470, 725, 1056, 484, 15-64-79 UPF For surface

10,653 activity 7. Kinnaur Kinnaur al

R/Peo. Morang/Morang/Jangi 1032/1, 1032/2 1-85-00 UPF For surface

activity 8. Kinnaur Kinnaur al

R/Peo. Kalpa/Kalpa/Powari, Tangling, Usaring, Ralli,

- 17-22,55 - For U/G activity

Page 310: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-26

The forest in the area has already been degraded due to a large-scale human interference. Though the project area is located in an ecologically sensitive area, the forests in and around the project area are quite degraded. The tree density in the submergence area and power house area is about 510 and 330 trees/Ha respectively. Normally in a dense forest, tree density is of the order of 1,000-1,200 trees/Ha. Thus, in land to be acquired for the project, the tree density is low to moderate. Likewise, no rare and endangered species are observed in the forest to be acquired for the project. Thus, no adverse impacts are anticipated on this account. 7.6.2 Impacts on Terrestrial fauna i ) Disturbance to wildlife The total forest land requirement for the project is 63.5015 Ha. During construction phase, large number of machinery and construction labour will have to be mobilized. The operation of construction equipments and blasting is likely to generate noise. These activities can lead to some disturbance to wildlife population. Likewise, sitting of construction equipment, godowns, stores, labour camps, etc. can lead to adverse impacts on fauna in the area. No wildlife sanctuary or National Park exists either in the project area on its proximity. It is proposed that during construction phase, strict surveillance measures be adopted to minimize adverse impacts due to increased human interferences. Stray animals, however, may sometimes drift to the construction site. It should be ensured through stringent anti-poaching surveillance that the stray animals are not killed. Detailed measures for the same have been suggested in Environmental Management Plan covered in Volume-II of this Report. b) Operation phase i) Increased accessibility During the project operation phase, the accessibility to the area will improve due to construction of roads, which in turn may increase human interferences leading to marginal adverse impacts on the terrestrial ecosystem. The increased accessibility to the area can lead to increased human interferences in the form of illegal logging, lopping of trees, collection of non-timber forest produce, etc. Since significant wildlife population is not found in the region, adverse impacts of such interferences are likely to be marginal. The details of measures to improve the terrestrial ecology of the area are covered in separate volume of this Report. 7.6.3 Aquatic Flora a ) Construction phase During construction phase wastewater mostly from domestic source will be discharged mostly from various camps of workers actively engaged in the project area. Around 0.22 MLD of water is required for the workers during the peak construction phase out of which 80% (i.e. about 0.18 MLD) will be discharged back to the river as wastes, more or less as a point sources from various congregation sites where workers will reside. The average minimum flow during lean season is about 2.18 cumecs. However, sufficient water for dilution will be available in Satluj to keep the DO of the river to significantly high levels.

Page 311: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-27

b) Operation phase The completion of Shongtong Karchham hydroelectric Project would bring about significant changes in the riverine ecology, as the river transforms from a fast-flowing water system to a quiescent lacustrine environment. Such an alteration of the habitat would bring changes in physical, chemical and biotic life. Among the biotic communities, certain species can survive the transitional phase and can adapt to the changed riverine habitat. There are other species amongst the biotic communities, which, however, for varied reasons related to feeding and reproductive characteristics cannot acclimatize to the changed environment, and may disappear in the early years of impoundment of water. The micro-biotic organisms especially diatoms, blue-green and green algae before the operation of project, have their habitats beneath boulders, stones, fallen logs along the river, where depth is such that light penetration can take place. But with the damming of river, these organisms may perish as a result of increase in depth. However, no rare and endangered or threatened species is found in the area likely to be impacted. 7.6.4 Impacts on Aquatic Fauna a) Construction phase The construction of the proposed Shongtong Karchham hydroelectric would involve large-scale extraction of different types of construction material from the riverbed including boulders, stones, gravel, sand, etc. Extraction of gravel and sand causes considerable damage to fish stocks and other aquatic life by destabilizing the sub-stratum, increasing the turbidity of water, silting of the channel bottom and modifying the flow, which in turn may result in erosion of the river channel. These alterations upset the composition and balance of aquatic organisms. The material at the river sub-stratum like stones and pebbles often provide anchorage and home to the invertebrates that remain attached in a fast flowing stream. During fish spawning season, the fertilized eggs are laid amidst the gravel, where it is made sure, that eggs are not washed away in fast flowing stream. The eggs of almost all species are sticky in nature, which provide additional safety. The turbidity in excess of 100 ppm brought by suspended solids chokes the gills of young fish. Fine solids in concentration greater than 25 mg/l, adversely affects the development of fish eggs and fish. b) Operation phase Among the aquatic animals, it is the fish life, which would be most affected. The migratory fish species, e.g. snow trout’s are likely to be adversely affected due to obstruction created by the proposed barrage. With the completion of barrage, flow in the downstream stretch of the river would be reduced considerably more so during the lean period. The most important changes, which can be expected, are: • Reduced flow rate; • Increase in water temperature; • Reduction in availability of stano-thermal aquatic animals; and • Increase in population of euro-thermal species. Unless the desired flow is maintained downstream of the barrage, aquatic ecology in general and fisheries in particular would be adversely affected. The mitigative measures

Page 312: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-28

for minimizing these impacts have been covered in Volume-II of this Report. 7.7 IMPACTS ON SOCIO-ECONOMIC ENVIRONMENT A project of this magnitude is likely to entail both positive as well as negative impacts on the socio-cultural fabric of the area. During construction and operation phases, a lot of allied activities will mushroom in the project area. The detail Socio-economic effect due to project activities will be addressed in SIA report of the project. 7.7.1 Impacts due to influx of labour force During the construction phase a large labour force, including skilled, semi-skilled and Un-skilled labour force of the order of about 1,000 persons is expected to immigrate into the project area. As per GoHP Hydro Power Policy 2007, 70% of employment will be given to Himachal residents. However, it has been noticed in the project vicinity and in those executed by HPPCL the local people do not want to work as un-skilled labor in the project. Instead they want supervisory roles which are few and limited and depend upon skill level. As such there is no competition with the immigrants and consequent loss of employment opportunities. However, considering these facts HPPCL is sponsoring suitable persons from PAF for training in various technical courses and also providing scholarships to improve employability of local population. It is also giving assistance for self employment for PAF’s. The labour force would stay near to the project construction sites. 7.7.2 Location of Workers colony Worker colonies in downstream areas are/were created by JP Associates for Karchham-Wangtoo (1,000 MW) and Baspa II (300 MW), both of which are downstream projects. The experiences of these projects are given below:- The past experiences have shown that labor remains within the labor camp as the basic necessities/ amenities are provided to them in labor camp itself. The labor camps are situated at reasonable distance from local population. It has also been observed that local population don’t allow immigrant population to mix with them and are often busy in their own daily activities. It is also mentioned that arrival, stay and working by immigrants is not a new phenomenon to the area as they are almost invariably employed by the natives for assisting them in horticulture and agricultural activities. Besides, other organizations like Border Roads and other hydropower projects as also many other government departments to employ immigrant labor. The project area has its unique culture. The people of the area have distinct habits of food and clothing. They have deep religious faiths and celebrate the festivals with great enthusiasm in the presence of local deities. During construction phase of the project, migratory population is expected from other parts of the country having different culture and habits but very little chance of cultural conflict is foreseen due to migratory population as intermingling remains limited to business activities. Police post will be set up for any eventual law and order situation within the project area due to presence of labor force.

Page 313: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-29

The distance of the proposed labor camps from the Project Affected Villages are as under:

Table -7.19: Labor Camps Distance from Project Affected Villages S. No. Powari Tangling

Population - 967 Barang Population - 1399

Ralli Population - 459

Khawangi Population - 803

Aerial (Km)

R D (Km)

Aerial (Km)

R D (Km)

Aerial (Km)

R D (Km)

Aerial (Km)

R D (Km)

Aerial (Km)

R D (Km)

Camp -1 (300 labor)

½ ½ ½ ½ 2½ 6 5 11 1 8

Camp-2 (700 labor)

5½ 6 4½ 5 2 9 3 8 5 11

7.7.2 Economic impacts of the project Apart from direct employment, the opportunities for indirect employment will also be generated which would provide great impetus to the economy of the local area. Various types of business like shops, food-stall, tea stalls, etc. besides a variety of suppliers, traders, transporters will concentrate here and benefit immensely as demand will increase significantly for almost all types of goods and services. The business community as a whole will be benefited. The locals will avail these opportunities arising from the project and increase their income levels. With the increase in the income levels, there will be an improvement in the infrastructure facilities in the area. 7.7.3 Impacts due to land acquisition Another most important deleterious impact during construction phase will be that, pertaining to land acquisition. About 77.3326 Ha of land proposed to be acquired for the proposed Shongtong hydro-electric project. Of this about 13.8311 Ha is private land (un-irrigated land) while about 63.5015 Ha is forest land. The details of land acquisition, project appurtenances-wise and land-use wise, are depicted in Table-7.15 and 7.16 of this Chapter. It is observed that about 13.8311 Ha of private land is proposed to be acquired from 9 revenue villages. It is observed that about 158 PAFs are likely to lose land in varying proportions. No family is likely to lose homestead on account of land acquisition for the project. The details of PAPs losing land is depicted in Table – 7.20.

TABLE – 7.20: Village-wise details of project affected families

Village Name Village Panchayat

PAFs losing only land

PAFs losing only

homestead

PAFs losing land &

homestead

Total PAFs

Khwangi Khwangi 20 -- -- 20 Powari Powari 6 -- -- 6 Ralli-Mebar Nebar 31 -- -- 31 Tangling Powari 86 -- -- 86 Total 158 -- -- 158

Page 314: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-30

7.7.4 HIV/AIDS and other Diseases The construction activities that are taking place because of the hydropower project in the area will involve the engagement of a work force in the area, thus changing the population density and increasing the floating population during construction activities. The influx of people into the area is associated with an augmented risk of communicable diseases, including sexually transmitted diseases. However, intermixing of resident population with immigrants is not favored as natives do not allow such interactions. As regards, other diseases, deployment in project area will be done after health check. 7.7.5 Increased incidence of water-related diseases This influx of population will result in a change in the existing health scenario due to increased pressure on existing infrastructure i.e. water supply sources, sanitation, etc. The additional domestic sewage generated may cause increased contamination of river water. Also, the construction of a barrage would convert riverine ecosystem into a lacustrine ecosystem. The vectors of various diseases may breed in shallow parts of the impounded water. The magnitude of breeding sites for mosquitoes and other vectors in the impounded water is in direct proportion to the length of the shoreline. Since, this is a run-of river project in a mountainous region, increase in water spread area will be marginal and it would remain mostly confined in the gorge of the river, the increase in the incidence of water borne disease is not expected. Further, mosquitoes are normally observed up to a maximum elevation of about 2,000 m above mean sea level. The proposed project is located just above this elevation. 7.7.6 Impacts on cultural/religious/historical monuments Apart from village temple in the study area, monuments of cultural, religious, historical or archaeological importance are not reported in the project as well as the study area. Thus, no impact on such structures is envisaged. 7.8 IMPACTS DUE TO CONSTRUCTION OF ROADS Approach roads to Project components along with widening of road will be done in a stretch of 10.44 km with a width of 5/7meters within the project area of 3 sq km. The widening of road will help in smooth movement of traffic which will take care of increase in traffic due to project activity. The details are given in Table 7.20 The total number of vehicles movement during construction phase will be 60 vehicles/day in whole project area, i.e. in a stretch of 12 km. These vehicle movements will not be at a single point source but will be at different places in the entire project area. Table 7.21: Details of Widening/Construction of project roads Description and Name of Road Length Approx.

in km

Widening of existing HPPWD road to 5/7 m wide from Shongtong bridge to Powari junction village

4.44

Approach road 5/7 m wide from Ralli village road to top and bottom of surge shaft, proposed explosive magazine site, temporary staff quarters, site office, Adit to bottom of pressure shaft and pot head yard and approach road to Adit-3 from NH-22

5.0

Approach road to quarry site at Powari 1.0

Page 315: Environmental Assessment Report...The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board

HPPCL EIA study for Shongtong-Karchham H.E Project (450MW)

WAPCOS Centre for Environment 7-31

The construction of roads can lead to the following impacts:

• The topography of the project area has steep to precipitatuous slope, which descends rapidly into narrow valleys. The conditions can give rise to erosion hazards due to net downhill movement of soil aggregates.

• Removal of trees on slopes and re-working of the slopes in the immediate vicinity of roads can encourage landslides, erosion gullies, etc. With the removal of vegetal cover, erosive action of water gets pronounced and accelerates the process of soil erosion and formation of deep gullies. Consequently, the hill faces are bared of soil vegetative cover and enormous quantities of soil and rock can move down the rivers, and in some cases, the road itself may get washed out.

• Construction of new roads increases the accessibility of a hitherto undisturbed areas resulting in greater human interferences and subsequent adverse impacts on the ecosystem.

• Increased air pollution during construction phase.