environmental monitoring report...the environmental monitoring report is a document of the borrower....
TRANSCRIPT
The environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
Environmental Monitoring Report
Project Number: 37530 October 2012
Republic of Tajikistan: Rural Development Project
Prepared by Rural Development Project - Management Unit, Ministry of Agriculture of the Republic of Tajikistan for the Asian Development Bank (ADB).
INFRASTRUCTURE SUBPROJECTS ENVIRONMENTAL MONITORING REPORT
January - September 2012
ABBREVIATIONS
ADB Asian Development Bank ALMGC Committee (ex Agency) for Land Management, Geodesy and Cartography CACILM Central Asian Initiative for Land Management CBO Community Based Organization CIS Community of Independent States EA Executing Agency GEF Global Environmental Facility GoT Government of Tajikistan HR Human Resources IA Implementing Agency IEE Initial Environmental Examination LPDP Livestock and Pasture Development Project (IFAD) MoA Ministry of Agriculture M & E Monitoring and Evaluation NGO Non Governmental Organization PMU Project Management Unit PPMS Project Performance Monitoring System RDP Rural Development Project RRP Report and Recommendations of the President of ADB SES Sanitary and Epidemic Station SLM Sustainable Land Management component (= Contract 3) TA Technical Assistance TJS Tajik Somoni TL Team Leader TORs Terms of Reference UN United Nations USD United States Dollar WB World Bank WUA Water Users Association
CONTENTS
PROJECT SYNOPSIS
I. INTRODUCTION
II. STATUS OF INFRASTRUCTURE SUBPROJECTS
1. Commissioned infrastructures
2. Sub projects under construction
3. Sub projects just contracted
4. Sub projects tendered
5. Sub projects designed to be submitted to ADB
6. Sub projects under design
7. Sub projects under PMU investigations and evaluation
8. Sub projects implementation schedule
III. SCHEDULE OF INTERVENTIONS OF THE ENVIRONMENTAL MONITORING SPECIALIST
IV. ENVIRONMENTAL AND RESETTLEMENT STATUS OF INFRASTRUCTURE SUBPROJECTS
1. Reporting documentation
2. Key features of the environmental and resettlement status of the subprojects
APPENDIXES: 1 STATUS OF INFRASTRUCTURE SUBPROJECTS AS AT END SEPTEMBER 2012 2 ENVIRONMENTAL MONITORING AND MANAGEMENT FIELD TRIPS ((January to
September 2012) 3 INFRASTRUCTURE SUB PROJECTS ENVIRONMENTAL MONITORING SHEETS
PROJECT SYNOPSIS Prepared in 2005-2006 and designed to be implemented during the 2007-2014 period, the Rural
Development Project (RDP) targets five hilly to mountainous raions not producing cotton, north and close to Dushanbe.
Indicator Varzob Rogun Faizabod Vahdat Rudaki TOTAL % Country
Population 2005 (000 inhab)
58 33 75 252 301 719 10,0
Area (sq. km) 1 630 660 870 3 670 1 520 8 350 5,8
Arable land (sq km) 30 24 85 150 69 358 4,9
Irrigated land (% arable)
13,3 12,5 44,7 70,7 53,6 52,5 3,7
Pastures (sq km) 865 487 467 880 800 3 499 9,3
Altitude agricultural land (mini/maxi) (m)
900 2 500
1 000 2 500
1 000 2 500
750 2 000
650 1 200
650 2 500
300 2 500
Rainfalls (mm/year) 1 189 767 797 704 585 - -
Jamoats (number) 5 2 9 10 13 39 10,6
Rayon Proper Budget 2009 (Million TJS)
10,4 11,0 12,0 25,0 32,0 90,4 -
State-subsidised budget (%)
13 80 58 17 0 23,6 -
Taking a holistic and coordinated approach of rural development and economy, the RDP global
objective is to increase the farm and non-farm incomes of rural households, through an enhanced productivity of individual and cooperative dekhan farms, households and rural enterprises, within an environmentally sustainable management framework.
Structured into five components
Policy and Institutional Development and Reform,
Sustainable Land Management (Pasture, Arable, and Forest),
Agriculture and Rural Business Support,
Rural Infrastructure Development,
Project Management (through a PMU), the RDP is implemented under the responsibility of the Ministry of Agriculture (MoA) as Executing Agency (EA), the Agency for Land Management, Geodesy and Cartography (ALMGC - formerly the State Land Committee) being an Implementing Agency (IA) of the second component.
A multi-institutional Steering Committee headed by a representative from the Executing Agency (MoA) endorses the RDP strategy and relevant proposals prior to any submission and agreement with the Asian Development Bank.
The co-financing scheme involves the Tajik Government, the Asian Development Bank (Loan
and Grant of Special Operations effective since 14/09/2007 and expiring on 31/03/2014), the Global Environment Facility (Grant signed on 08/05/2009, expiring on 31/03/2014) and the Beneficiaries:
Investment Plan (USD million) Financing Plan (USD million)
Item Cost % Source Cost %
Base Cost 1. Policy and Institutional Development and Reform 2.10 9,01 1. Government 1.65 7.10 2. Sustainable Land Management 4.17 17,90 2. ADB 3. Agriculture and Rural Business Support 6.27 26,91 Loan 8.80 37.80 4. Rural Infrastructure Improvement 6.18 26,52 Grant 8.30 35.60 5. Project Management 3.05 13,09 3. GEF Grant 3.50 15.00 Sub total Base Cost 21.77 93,43 4. Beneficiaries 1.05 4.50
Contingencies 1.16 4,98
Financing charges during implementation 0.37 1,59
TOTAL 23.30 100.00 TOTAL 23.30 100.00
Initially envisaged, the allocation of an additional separate ADB Grant (USD 0,6 million) to develop capacity for planning and budgeting in local government has been cancelled in March 2010 by the ADB in order to avoid overlaps with interventions from other funding institutions.
I. INTRODUCTION
Issue 52 of the March/April 2012 ADB review mission report introduced the ADB requirement for
biannual environmental reports (April and October) on each infrastructure subproject. The present report is the first specific environmental report produced by the Project and covers the January-September 2012 period. Further reporting will be implemented according to the routine recommended by ADB.
At the end of the reporting period, the status of the infrastructure subprojects envisaged through two different criteria is the following:
Progress Number of
subprojects Profile
Number of subprojects
Completed: 4 Water supply in villages 15
Under construction 7 Bridge rehabilitation 7
Contract awarded 3 Road rehabilitation 4
Tendered 3 Irrigation network rehabilitation
3
Project documentation preparation
3 Small hydro electric power plant
1 Under identification and design
10
TOTAL 30 TOTAL 30
The relevant environmental monitoring and management interventions of the project are implemented according to the following plan:
o Preparation: definition of environmental impact and of safeguards to be included in the contract and of eventual resettlement issues,
o Construction: monitoring of the fulfillment of requirements by contractors until commissioning,
o Maintenance: environmental monitoring of interventions from those in charge of maintenance (public institutions for roads and bridges, communities for others) and training of these targets.
During the reporting period, PMU staffing (environmental monitoring specialist) has been maintained but its financing has been shifted from the ADB Grant to the ADB Loan (03/08/2012) to control the exhaustion risk of Grant funding allocated to local staffing. Issue 34 of the March/April 2012 ADB review mission report specifies 30/03/2013 as a dead line for ADB approval of any infrastructure sub project. The intervention schedule of the environmental monitoring specialist is designed accordingly.
ADB headquarters provided support to the Project through a mission of an environment specialist twinned with a social development specialist (07-11/05/2012). Field visits of infrastructures with the PMU relevant staff and working sessions led to adjustments in the reporting forms to be used.
II. STATUS OF INFRASTRUCTURE SUBPROJECTS
The status of the 30 infrastructure subprojects on which the Project is working is detailed in Appendix 1.
Annex 1 shows a classification / numbering / reference of subprojects which is used in the whole present document and its annexes.
Out of 30 identified subprojects, 4 are completed, 7 are under construction, 3 are contracted (September 2012), 3 approved and advertised for the tendering process, 3 at the stage of sending for ADB approval, 7 at the stage of investigations by Design Institutes, and 3 at the stage of PMU Specialist evaluation.
The profiles of these 30 subprojects are distributed as follows:
Profile Number Subprojects ref. in the present report
Water supply in villages 15 2, 3,8,13,19,20,21,22,23,24,25,26,27,28,29
Bridge rehabilitation 7 5,7,9,10,11,12,13
Road rehabilitation 4 4,6,16,17
Irrigation network rehabilitation 3 1,18,30
Small hydro electric power plant 1 15
TOTAL 30 -
Subprojects linked to roads, bridges and irrigation are rehabilitation of existing infrastructure whilst water catchments/supply and mini power plants are new infrastructure. The cost and profiles of beneficiaries of the 17 (from “completed” to “advertised”) subprojects are summarized as follows: Indicators Faizabad Rudaki Rogun Varzob Vahdat Total
1. Number 3 4 2 2 6 17
2. Total Amount (USD) 338,312 566,955 383,435 230,130 1,094,628 2,613,461
3. Persons beneficiaries (expected)
10192 36738 6084 10969 14861 78844
4. % Female benefited 52% 48% 54% 53% 49% 51%
5. % Ethnic Minorities benefited
Not Applicable
46% Not
Applicable 29% 28% 34%
6. Households beneficiaries (expected)
1,456 6,123 1,014 1,567 2,123 12,283
1. Commissioned infrastructures
4 subprojects are already operational
Project name Rayon Jamoat Status Sub-sector Cost (USD)
1. Reconstruction of Dashti-Bed canal
Vahdat Abdulvosiev Commissioned
15/09/2011 Irrigation 105,724
2. Construction of TahtiAlif drinking water supply
Faizabad Chasmasor Commissioned
26/09/2011 Water supply 43,300
3. Supply of clean drinking water for Lohur village
Rudaki Lohur Commissioned
18/04/2012 Water supply 42,649
4. Reconstruction of road between Chorburgh- Chormagsakoni Uzbek
Varzob Chorbog Commissioned
27/09/2012 Bridge/road 48,736
TOTAL 240,409
BENEFICIARIES
Raion Name of the Completed subprojects
Location of the sub-project
Beneficiaries (Households)
Beneficiaries (Persons)
Number and % of Women
Beneficiaries
Number and % of Ethnic
Minorities
Vahdat Restoration of in-farm canal Dashtibed
Abdulvosiev jamoat, Navobod village
1 149 8 043 4 535 (57%)
2 413 (30%)
Faizabad Construction of water supply system
Chashmasor jamoat, Takhti Alif village
87 520 274
(53%) Not
Applicable
Rudaki Drinking water supply
Lohur jamoat, Lohur village
773 4 250 2 150 (51%)
103 (3%)
Varzob Restoration of transport bridge
Chorbog jamoat, Chormagzakoni Uzbek village
788 4 725 2 362 (50%)
1 400 (30%)
TOTAL 2 796 17 538 9 321 (53%) 3 916 (22%)
2. Sub projects under construction
7 subprojects are under construction.
Project name Rayon Jamoat Status Sub-sector Cost (USD)
5. Bridge construction at Shurmanka village
Rudaki Esanboy 70 % built Bridge/road 202,277
6. Restoration of road in Javoni village
Rogun Kadi-ob 75 % built Bridge/road 231,876
7. Rehabilitation of bridge in Takob-Dehmalik village
Varzob Dehmalic 75 % built Bridge/road 205,585
8. Construction of water network in Kulobiyon-Sari Chinor villages
Faizabad Javonon 80 % built Water supply 196,902
9. Reconstruction of bridge in Shaykhon village
Rudaki Rohati 80 % built Bridge/road 173,893
10. Rehabilitation of bridge in Tilloobod village jamoat Lohur of Rudaki rayon
Rudaki Lohur 85 % built Bridge/road 177,648
11. Rehabilitation of Dorob village bridge
Faizabad KalaiDasht 70 % built Bridge/road 123,533
TOTAL 1,311,624
3. Sub projects just contracted
3 subprojects are just contracted.
Project name Rayon Jamoat Status Sub-sector Cost (USD)
12. Rehabilitation of bridge in Kadiob village
Rogun Kadiob ADB approval Sep
2012 Contracted 20/09/2012
Bridge/road 204,650
13. Construction of additional water supply system in Geshi village, Jamoat Chorsu of Vahdat city
Vahdat Chorsu ADB approval Sep
2012. Contracted 20/09/2012
Water supply 71,875
14. Reconstruction of bridge over Naidara river
Vahdat Dusti ADB approval Sep
2012 Contracted 20/09/2012
Bridge/road 249,419
TOTAL 525,944
4. Sub projects tendered
3 subprojects are just tendered (02/10/2012).
Project name Rayon Jamoat Status Sub-sector Est. Cost
(USD)
15. Construction of small power plant in Kokhu village of Romit jamoat
Vahdat Romit Tendered on 02/10/2012
Small power plant
252,520
16. Rehabilitation of road Zargar-Chaman of Abdulvosiev jamoat
Vahdat Abdulvosiev Tendered on 02/10/2012
Road 215,130
17. Rehabilitation of road Mehrgon-Shirinchashma of B.Burunov jamoat
Vahdat B.Burunov Tendered on 02/10/2012
Road 215,410
TOTAL 683,060
5. Sub projects designed to be submitted to ADB
3 subprojects are designed and ready to be submitted to ADB
Project name Rayon Jamoat Status Sub-sector Est. Cost
(USD)
18. Construction of irrigation system in Duoba village of Chorbog jamoat
Varzob Chorbog Submission expected
end October 201 Irrigation 52,980
19. Construction of water supply line in Chashmai Kulo village of Kadi Ob jamoat
Rogun Kadi Ob Submission expected begin October 2012
Water supply 245,780
20. Construction of water supply line in Kuliyo – Yumsurok villages of Simiganch jamoat
Vahdat Simiganch Submission expected
end October 201 Water supply 122,840
TOTAL 421,600
6. Sub projects under design
7 subprojects are under design by design institutes
Project name Rayon Jamoat Status Sub-sector Est. Cost
(USD)
21. Construction of water supply line in Kengeli village of Faizabad jamoat
Faizabad Faizabad 65 % design done Water supply 157,560
22. Construction of water supply line in Chukurak village of Faizabad jamoat
Faizabad Faizabad 65 % design done Water supply 168,060
23. Construction of water supply line in Fathobod village of Miskinobod jamoat
Faizabad Miskinobod 45 % design done Water supply 178,570
24. Construction of water supply line in Gulteppa village of Miskinobod jamoat
Faizabad Miskinobod 45 % design done Water supply 147,060
25. Construction of water supply line in Sultonobod village of Sultonobod jamoat
Rudaki Sultonobod 45 % design done Water supply 178,570
26. Construction of water supply line in Zafar-2 village of Choryakkoron jamoat
Rudaki Choryakkoron 45 % design done Water supply 189,080
27. Construction of water supply line in Totshikobob village, Zainabobod Jamoat
Rudaki Zainabobod 45 % design done Water supply 168,070
TOTAL 1,186,970
7. Sub projects under PMU investigations and evaluation
3 subprojects are under PMU investigations and evaluation
Project name Rayon Jamoat Status Sub-sector
28. Construction of water supply line Kandak village, Obi Garm Jamoat
Rogun Obi Garm Selection with Rayon
Committee in August 2012 Water supply
29. Construction of water supply line in Kharangon village, Aini Jamoat
Varzob Kharangon Selection with Rayon
Committee on 20 Sept 2012 Water supply
30. Rehabilitation of irrigation canal in Mavlonoi Kukhna, Jamoat Guliston
Rudaki Guliston Selection with Rayon
Committee on 20 Sept 2012 Irrigation
TOTAL
8. Sub projects implementation schedule
The March 2012 ADB Review Mission (Issue 8 – parag 34 of the mission report) fixed March 31 2013 as the dead line for the approval of infrastructure subproject in order to complete the full sub project cycle before the project completion date (end March 2014).
III. SCHEDULE OF INTERVENTIONS OF THE ENVIRONMENTAL MONITORING SPECIALIST
During the reporting period, targeted field trips have been implemented as described in Appendix 2: ADB headquarters provided support to the Project through a mission of an environment specialist twinned with a social development specialist (07-11/05/2012). Field visits of infrastructures with the PMU relevant staff and working sessions led to adjustments in the reporting forms to be used.
IV. ENVIRONMENTAL AND RESETTLEMENT STATUS OF INFRASTRUCTURE SUBPROJECTS
For each subproject, a full package of information is available in Annex 3.
1. Reporting documentation
1.1. The detailed environmental status of infrastructure subprojects is described in Annex 3, referring to two forms:
Sheet 1: “System of environmental assessment and monitoring of the effectiveness of activities” (one page) gathering key data,
Sheet 2: Four pages form describing the environmental status through: o General information on the project and site, o Information on security measures, o Impact mitigation measures, o Monitoring plan.
Historically, the PMU started activities with a free form evaluation, then shifted to Sheet 1 in March 2011 (recommendation of international monitoring and evaluation expert) and finally shifted to Sheet 2 at subproject 13 evaluation stage (April 2012), with a transition period when both sheets were used. Sheets 1 and 2 are available as follows in Annex 3:
Subproj 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Sheet1 X X X X X X X X X X X X X X X X X X X X
Sheet2 X X X X X X X X X X X
Subproj 21 22 23 24 25 26 27 28 29 30
Sheet1 None – On field identification Sheet2 X X X X X X X
1.2. In addition, a presentation of the status of the 30 subprojects in terms of progress regarding civil works implementation (identification, tendering, construction,…) and in terms of environmental status and relevant action at end September 2012 is shown in Annex 3 for each of these subprojects. 1.3. The package linked to each subproject in Annex 3 is accordingly structured as follows and in the following order:
Subproject construction status at the end of September 2012 (progress of the civil work implementation)
Sheet 1 and / or Sheet 2
Subproject environmental status at the end of September 2012 1.4. Resettlement issues are not relevant to the subprojects implemented by the Rural Development Project.
2. Key features of the environmental and resettlement status of the subprojects:
No resettlement, flora and fauna irreversible destruction or soil pollution issue affects any of
the subprojects.
Main potential concerns are linked to:
o Soil erosion (landslides, etc…) controlled through training of the beneficiaries, saplings/trees planting (all subprojects), river bank protection and subproject comprehensive drainage (roads and bridges),
o air pollution during works (dust) controlled through water aspersion of the sites with risks,
o water quality (water supply in villages) controlled through training of the beneficiaries, biannual water testing by the Sanitary and Epidemic Station and routine chlorination..
All subprojects are relevant to category D1 of the checklist (no essential impact on the
environment)
APPENDIXES
APPENDIX 1
STATUS OF INFRASTRUCTURE SUBPROJECTS AS AT END SEPTEMBER 2012
№ Name of the project Raion Contractor Contract # Contract
cost (TJS)
Contract signing
date
Duration of works
according to the
contract
Completion date
according to the
contract
Working committee
Commissioning
Date of project acceptance
1
Restoration of in-farm canal Dashtibed in Navobod village of Abdulvosiev jamoat
Vahdat LLC "Gidroenergoservis",
Director Muminov A.
PMU/CW/NCB/01-2010
446,178.00 15.12.2010 23.06.2011 15.09.2011
2
Construction of water supply network in Takhti Alif village of Chashmasor jamoat
Faizabad LLC "MIF", Director Azizov K.
PMU/CW/NCB/03-2010
188,164.00 13.01.2011 26.09.2011 26.09.2011
3 Drinking water supply in Lohur village of Lohur jamoat
Rudaki LLC "Sari Khosor ", Director Gulomov S.
PMU/CW/NCB/04-2010
180,721.90 11.11.2011 18.04.2012 18.04.2012
4
Restoration of transport bridge on 4 km road Chorbog-Chormagzakon of Chorbog jamoat, Varzob raion
Varzob LLC "Sadr", Director Madzhidov A. Sh.
PMU/CW/NCB/02-2011
217,098.00 07.09.2012 27.09.2012
5
Rehabilitation of a bridge in Shurmanka village of Esanboy jamoat on the 32 km of Rudaki raion
Rudaki LLC "Sadr", Director Madzhidov A. Sh.
PMU/CW/NCB/05-2011
928,518.00 26.09.2011 5 months Feb. 11
6 Reconstruction of road Javonon-Safedoron, Rogun
Rogun LLC "Avtorem", Director Pirov M.
PMU/CW/NCB/06-2012
894,789.96 10.05.2012 6 months Nov. 12
7
Rehabilitation of a bridge in Dehmalik village of Dehmalik jamoat, Varzob raion
Varzob LLC "Davron", Director Temurov M.
PMU/CW/NCB/07-2012
887,526.21 10.05.2012 6 months Nov. 12
8
Construction of water supply line in Kulobiyon-Sari Chinor villages of Javonon jamoat, Faizabad raion
Faizabad LLC "Rasul Sohtmon", Director Kurbonov S.
PMU/CW/NCB/08-2012
826,779.92 11.06.2012 6 months Dec. 12
9
Rehabilitation of a bridge in Shaykhon village of Rohati jamoat, Rudaki raion
Rudaki LLC "Bodoma", Director Boboazizov A.
PMU/CW/NCB/09-2012
800,296.27 10.05.2012 6 months Nov. 12 08.09.2012
10
Rehabilitation of a bridge in Tiloobod village of Lohur jamoat, Rudaki raion
Rudaki LLC "Sahib", Director Sohibov Y.
PMU/CW/NCB/10-2012
811,849.84 10.05.2012 6 months Nov. 12 06.09.2012
11
Rehabilitation of a bridge through Elok river in Dorob village of Kalai Dasht jamoat, Faizabad raion
Faizabad LLC "Sari Khosor", Director Gulomov S.
PMU/CW/NCB/11-2012
560,104.69 10.05.2012 6 months
Nov. 12
12 Restoration of a bridge through river Kadi Ob of Kadi Ob jamoat
Rodun LLC "Korkhonai sohtmoni tekhniki "
PMU/CW/NCB/12-2012
945,699.83
13 Construction of additional water supply line in Geshi village
Vahdat LLC "Mirzob" PMU/CW/NCB/13-2012
345,000.00
14 Rehabilitation of a bridge through Naydara river of Dusti jamoat
Vahdat SMU-1 PMU/CW/NCB/14-2012
1,211,696.26
15 Construction of small power plant in Kokhu village of Romit jamoat
Vahdat Tender announced 1,202,000000
16 Rehabilitation of road Zargar-Chaman of Abdulvosiev jamoat
Vahdat Tender announced 1,024,000.00
17 Rehabilitation of road Mehrgon-Shirinchashma of B.Burunov jamoat
Vahdat Tender announced 1,025,340.00
18 Construction of irrigation system in Duoba village of Chorbog jamoat
Varzob On translation 252,190.00
19
Construction of water supply line in Chashmai Kulo village of Kadi Ob jamoat
Rogun On translation 1,169,921.00
20
Construction of water supply line in Kuliyo – Yumsurok villages of Simiganch jamoat
Vahdat On translation 584 720,00
Total until end 2012 (TJS) 14,502, 593.88
21 Construction of water supply line in Kengeli village of Faizabad jamoat
Faizabad Design institute work 750 000,00
22
Construction of water supply line in Chukurak village of Faizabad jamoat
Faizabad Design institute work 800 000,00
23
Construction of water supply line in Fathobod village of Miskinobod jamoat
Faizabad Design institute work 850 000,00
24
Construction of water supply line in Gulteppa village of Miskinobod jamoat
Faizabad Design institute work 700 000,00
25
Construction of water supply line in Sultonobod village of Sultonobod jamoat
Rudaki Design institute work 850 000,00
26
Construction of water supply line in Zafar-2 village of Choryakkoron jamoat
Rudaki Design institute work 900 000,00
27
Construction of water supply line in Totshikobob village, Zainabobod Jamoat
Rudaki Design institute work 800 000,00
28 Construction of water supply line Kandak village, Obi Garm Jamoat
Rogun Field investigations
29 Construction of water supply line in Kharangon village, Aini Jamoat
Varzob Field investigations
30 Rehabilitation of irrigation canal in Mavlonoi Kukhna, Jamoat Guliston
Rudaki Field investigations
Total 2013 (TJS) 5,650,000.00
TOTAL (TJS) 20,152,593.88
TOTAL (USD) 4 198,457
APPENDIX 2
ENVIRONMENTAL MONITORING AND MANAGEMENT FIELD TRIPS (January to September 2012)
Raion Date Conducted works Number of
participants
RUDAKI
Rehabilitation of a bridge in Tillioobod village of Lohur jamoat
(Subproject 10)
05 Feb Meeting and discussion with the population on environmental protection
18
14 June
Meeting and discussion with the contractors on better safety measures during civil works and environmental protection (disposal of wastes, dust, dirt, equipment and others)
11
Rehabilitation of a bridge in Shaykhon village of Rohati jamoat
(Subproject 9)
09 Apr Meeting and discussion with the population on the construction of a bridge
21
10 Aug Meeting and discussion with the contractor 14
15 Sep Use of construction materials and machinery during the works
VARZOB
Rehabilitation of a bridge in Takob village of Dehmalik jamoat
(Subproject 7)
7 Apr Meeting and discussion with the population on the sub-project, environmental protection and its economic and social benefits
23
Construction of irrigation system in Duoba village of Chorbog jamoat
(Subproject 18)
14 July Meeting and discussion with jamoat and village representatives on the sub-project, its economic and social benefits and environmental protection during civil works
27
6 Aug 17
VAHDAT
Rehabilitation of road in Chamai village of Abdulvosiev jamoat
(Subproject 16)
13 Mar Meeting and discussion with the population on the benefits and harms of the sub-project
15
4 May Discussion with the workers of environmental protection department of the raion
5
Construction of water supply line in Yumsurok village of Simiganch jamoat
(Subproject 20)
9 July
Meeting and discussion with the population of the village on benefits of the compliance with the environmental protection requirements (cleaning of water, chlorination, rational use of water)
14
Rehabilitation of road in Shirinchashma village of B.Burunov jamoat (Subproject 17)
11 Apr Discussion with the population of the village on the construction of the road, economic and social benefits from it 23
9 July Meeting and discussion with the specialists from road, environmental and land department
FAIZABAD
Construction of water supply line in Sari Chinor village of Javoni jamoat (Subproject 8)
7 May Meeting with the village population on the construction, questions and answers and discussion on the benefits from the project
31
3 Sep Meeting with the jamoat and raion representatives
27
Construction of water supply line in Kangeli village of Faizobod jamoat (Subproject 23)
10 June Meeting and discussion with the population on the sub-project and environmental protection
19
6 Sep Meeting with jamoat representatives on the appropriate and rational use of water in the village
13
ROGUN
Rehabilitation of a bridge in Kadi-Ob village of Kadi-Ob jamoat (Subproject 12)
11 Apr
Discussion with the village population on the sub-project, environmental protection, economy and health, decrease of mortality among people and livestock
31
8 June Meeting with the specialists of the road, environmental and land departments
12
Drinking water supply in Chashmai Kulo village of Kadi Ob jamoat (Subproject 19)
11 May
Meeting and discussion with jamoat and village representatives on the harmless supply of drinking water, its rational use, environmental protection and infectious diseases
33
9 Aug
Meeting with the raion specialists: sanitary department, department on environmental protection, construction, land tenure and standardization
14
APPENDIX 3 INFRASTRUCTURE SUB PROJECTS ENVIRONMENTAL MONITORING SHEETS
Note: Subprojects numbering in this appendix is similar to subprojects numbering in appendixes 1 and 2.
SUBPROJECT 1
Subproject construction status at the end of September 2012
1. Activity and progress:
Canal bed cleaned
Installation of water distribution gates
Installation of spillway facilities
Sub project commissioned on September 15, 2011 2. Change in project organization
Saplings planting and pluriannual grass seeding 3. Relations with contractors and other stakeholders:
Dashtibed water users association implements maintenance and operation
No particular problem with the contractor.and beneficiaries
SUBPROJECT 1
System of environmental assessment and monitoring of the effectiveness of activities
Date: _____07.2011_____________
Date/Month/Year
Watershed: District: Vahdat
JDC/JRC: Dashtibed Village: Navobod, jamoat A. Abdulvosiev
Subproject: Restoration of a canal Subproject Code: PMU/CW/NCB/01.2011 BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No
Anti-erosion works done
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
-
+
+
Planting of fruit, coniferous and bush trees.
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km) 3.1
Aftereffect:
area of afforested and bushed territories, (ha) 300
area (ha), of fixed slope land 0,3
Land areas improved and/or rehabilitated, (ha) -
increasing of biodiversity (yes-no), covering area +
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
+
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ___________Sanginova S.R._____________ ________________ First name/Last name signature
SUBPROJECT 1
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Restoration of Dashtibed canal in Navobod village of A.Abdulvosiev jamoat, Vahdat raion
4
Meeting with population, site observation and trainings
Trainings were conducted on environment, economic and moral parts of the project
Conduct anti-erosion works, planting of fruits and coniferous trees
No
Planting of coniferous trees: 20 Oct to 10 Nov 2011 Planting of fruit trees 25 Feb to 10 March 2011
Consultation on plants care (training) 10 & 11 Oct 2011. No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Restoration of Dashtibed canal in Navobod village of A.Abdulvosiev jamoat, Vahdat raion
Shore-protection works. Planting of fruit and building trees. Construction of mudflow installation during civil works.
All requirements fulfilled.
Care for plants, watering, fertilizing and processing of trees.
SUBPROJECT 2
Subproject construction status at the end of September 2012
1. Activity and progress:
Construction of captation
Installation of PVC pipe and dampers.
Construction of closed hood
Installation of reservoir and chlorination plant
Sub project commissioned on September 26, 2011 2. Change in project organization
The location of the captation has been changed 3. Relations with contractors and other stakeholders:
No particular problem with the contractor and beneficiaries
SUBPROJECT 2 System of environmental assessment and monitoring of the effectiveness of activities Date: _______08.2011___________
Date/Month/Year
Watershed: District: Faizobod
JDC/JRC: Takhti Alif Village: Takhti Alif
Subproject: Construction of water lines Subproject Code: PMU/CW/NCB/03.2011 BLOCK F
Subproject’s category: Processing production, local handicrafts, water and energy saving, improvement of potable water supply, mills, smithy, refrigerator, etc.
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
There is no negative impact on the environment: does not pollute soil and water, does not make worse land condition (salinity, erosion), and does not lead to long-term or irreversible destruction of local vegetation.
No
Sanitary protected spring area is created
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the
biological diversity, saving of rare
species of plants and animals
-
+
+
with water chlorination
Superfactor «-» (negative):
-
Output:
Energy resource economy (kilowatt\h\year) -
Water resource economy (m3\year) -
Aftereffect:
Land areas improved and/or rehabilitated, (ha) 30
fixed slope land areas, (ha) -
increasing of biodiversity (yes-no), covering area -
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
-
reduction of the number of pests +
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ______________Sanginova S.R.___________ ________________ First name/Last name signature
SUBPROJECT 2
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of water supply line Takhti Alif in Faizabad raion
5
Observation of the source and meeting with the population and workers of sanitary-epidemic station (SES)
Meeting with local specialists of Sanitary department, trainings were conducted on rational use of drinking water.
Conduct chlorination of water and twice a year identify quality of drinking water
No
Creation of sanitary-protected area (May 05 to 20 2011)
Consultations on effective use of drinking water. No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of water supply line Takhti Alif in Faizabad raion
Create a protection zone of the spring, water chlorination.
The requirement is fulfilled.
Twice a year identify the quality of water by SES and drinking water chlorination in accordance with the standards.
SUBPROJECT 3
Subproject construction status at the end of September 2012
1. Activity and progress:
Construction of captation
Installation of PVC pipe and dampers.
Installation of water distribution taps
Installation of reservoir and chlorination plant
Sub project commissioned on April 18, 2012 2. Change in project organization
No change 3. Relations with contractors and other stakeholders:
After sub-project completion, it was commissioned to the Water Users Association.
No particular problem with the contractor.and beneficiaries
-
SUBPROJECT 3
System of environmental assessment and monitoring of the effectiveness of activities
Date: ________25.04.2012___________
Date/Month/Year
Watershed: District: Rudaki
JDC/JRC: Village: Lohur village of Lohur jamoat
Subproject: Construction of water supply lines Subproject Code: PMU/CW/NCB/04.2010 BLOCK F
Subproject’s category: Processing production, local handicrafts, water and energy saving, improvement of potable water supply, mills, smithy, refrigerator, etc.
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
There is no negative impact on the environment: does not pollute soil and water, does not make worse land condition (salinity, erosion), and does not lead to long-term or irreversible destruction of local vegetation.
No
The sub-project has no impact on environment.
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the
biological diversity, saving of rare
species of plants and animals
-
+
+
The health conditions of the village people will improve and decreased number of diseases. Their livelihood will also improve
Superfactor «-» (negative):
-
Output:
Energy resource economy (kilowatt\h\year)
Water resource economy (m3\year)
Aftereffect:
Land areas improved and/or rehabilitated, (ha)
fixed slope land areas, (ha)
increasing of biodiversity (yes-no), covering area
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
reduction of the number of pests +
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ______________Sanginova S.R.___________ ________________ First name/Last name signature
SUBPROJECT 3
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Drinking water supply
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Drinking water supply
Describe the site location
Lohur village of Lohur jamoat, Rudaki Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Raion water user associations
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
The distance from the water spring to water supply is 4,1 km. Raion sanitary-epidemiological station (SES) is responsible for the quality of water. All the materials are safe and comply with international norms
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of local geologist, conclusion of the local sanitary-epidemiologic station on drinking water (SES).
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
25.04.2012 trainings with the local population and site observations were conducted. The site has no environmental impact.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [+] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
A. Reconstruction of buildings [ ] Yes [+] No Look Section A below
B. New small-scale construction [+]Yes [] No Look Section A below
C. Individual system on cleaning of foul water [+]Yes [ ] No Look Section B below
D. Historical building (s) and raions []Yes [ + ] No Look Section C below
E. Land acquisition1 []Yes [ + ] No Look Section D below
F. Dangerous or poisonous materials2 1> 3 <1 []Yes [ + ] No Look Section E below
G. Impact on forests and/or conservation zones []Yes [+ ] No Look Section F below
H. Processing / liquidation of wastes [] Yes [+ ] No Look Section G below
I. Movement and safety of the foot-passengers []Yes [+ ] No Look Section H below
1 Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to
suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land. 2 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, during the construction works is being fulfilled
(a) Local supervising body on construction and environment, as well as communities on the planned activities
(b) All the required permissive documents for construction and/or reconstruction are put into shape (c) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (d) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(e) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(f) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality (a) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(b) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(c) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(d) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(e) There must not be any open construction wastes burning and household wastes on the site
(f) There must not be any unused construction vehicles on the site Noise (a) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(b) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation
(a) The wastes are collected in special containers in the established place (b) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (c) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (d) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 3
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of drinking water line in Lohur village of Lohur jamoat, Rudaki raion
6 Meeting with population, site observation.
Training on effective use of water
Chlorination of water by raion SES
No Permanently
No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of drinking water line in Lohur village of Lohur jamoat, Rudaki raion
Controlling the cleanliness of water, chlorination and water quality identification in the spring.
All the requirements and measures fulfilled.
Chlorination and control of water quality.
SUBPROJECT 4
Subproject construction status at the end of September 2012
1. Activity and progress:
Strengthening of bridge footings
Asphalt covering of bridge approaches
Water spillway chutes installation
Additional strengthening of barrage in river bed
Sub project commissioned on September 27, 2012 2. Change in project organization
Bridge operation period extended
Improvement of bridge sustainability
Additional works are done under the contract 3. Relations with contractors and other stakeholders:
Subproject is commissioned to the State Enterprise on Road Maintenance and
Operation of Varzob
No particular problem with the contractor and beneficiaries
SUBPROJECT 4
System of environmental assessment and monitoring of the effectiveness of activities Date: _____08.2011_____________
Date/Month/Year
Watershed: District: Varzob
JDC/JRC: Village: Chormagzakoni Uzbek
Subproject: Rehabilitation of a bridge Subproject Code: PMU/CW/NCB/02.2011 BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No
Construction of dams for prevention
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
-
+
+
of soil erosion (river bed direction)
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km) 0,13
Aftereffect:
area of afforested and bushed territories, (ha)
area (ha), of fixed slope land 0,05
Land areas improved and/or rehabilitated, (ha) -
increasing of biodiversity (yes-no), covering area -
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
+
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ___________Sanginova S.R._____________ ________________ First name/Last name signature
SUBPROJECT 4
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Restoration of a bridge in Chormagzakoni Uzbek village of Varzob raion
5
Meeting with population, site observation and trainings on use of safety measures during the civil works
Training with the workers during civil works, meeting with local specialists (ecologist, engineers and local council members)
Construction of dams for prevention of erosion (river bed direction)
No
Construction of dams from August 01 to 30,.2011
Consultation on Timely removal of wastes, prevention of noise and dust during the civil works. No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Restoration of transport bridge in Chormagzakoni Uzbek village of Varzob raion.
Use of standard materials, shore-protection works and forest-protection works
All the requirements and measures are fulfilled.
Further bridge maintenance is the responsibility of State Enterprise on Maintenance and Operation of roads in Varzob raion.
SUBPROJECT 5
Subproject construction status at the end of September 2012
1. Activity and progress:
Monolithic base structure
Production and mounting of monolithic blocks.
Installation of monolithic reinforced concrete surface on blocks
Shore-protection works
Work progress at the end of September 2012: 70% 2. Change in project organization
It is necessary to install spillway pipes in the village.
Additional installation of retaining wall
Changes in contract cost 3. Relations with contractors and other stakeholders:
(Active) initiators for community and road departments and involved in designing of changes
No particular problem with the contractor and beneficiaries
SUBPROJECT 5
System of environmental assessment and monitoring of the effectiveness of activities Date: _____06.2012__________
Date/Month/Year
Watershed: District: Rudaki
JDC/JRC: Village: Shurmanka of Esanboy jamoat
Subproject: Restoration of a bridge Subproject Code: PMU/CW/NCB/05-2011 BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No
This sub-project has no impact on environment
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
No
Yes
No
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km) -
Aftereffect:
area of afforested and bushed territories, (ha) -
area (ha), of fixed slope land -
Land areas improved and/or rehabilitated, (ha) -
increasing of biodiversity (yes-no), covering area -
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
Yes
decreasing of animal morbidity Yes
decreasing of human morbidity Yes
Executor: ___________Sanginova S.R._____________ ________________ First name/Last name signature
SUBPROJECT 5
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Restoration of a bridge in
Shurmanka village of
Esanboy jamoat, Rudaki
raion
3
Meeting with
population, site
observation
Conducted trainings
with workers and the
village population on
environment and
further use of the
bridge.
No No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Restoration of a bridge in Shurmanka village of Esanboy jamoat, Rudaki raion.
Shore-protection works and protection from mudflows.
All the requirements and measures are fulfilled.
Further bridge maintenance is the responsibility of State Enterprise on Maintenance and Operation of roads in Rudaki raion.
SUBPROJECT 6
Subproject construction status at the end of September 2012
1. Activity and progress:
Mechanized surface planning
Road widening
Construction of water spillway pipes
Road surface leveling device
Road paving
Work progress at the end of September 2012: 75 % 2. Change in project organization
Needs identification for road drainage
Development of measures for liquidation rock erasing in curve
Changes in cost 3. Relations with contractors and other stakeholders:
(Active) initiators for community and road departments and involved in designing of
changes
No particular problem with the contractor and beneficiaries
SUBPROJECT 6
System of environmental assessment and monitoring of the effectiveness of activities
Date: _____20.02.2012___________
Date/Month/Year
Watershed: District: Vahdat
JDC/JRC: Village: Javonon, Safedoron villages of Kadi Ob jamoat
Subproject: Subproject Code: PMU/CW/NCB/06.2012 BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No
The sub-project has no impact on environment
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
The economic conditions of the village people will improve and decreased number of infectious diseases. The chlorination of water will take place
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km)
Aftereffect:
area of afforested and bushed territories, (ha)
area (ha), of fixed slope land
Land areas improved and/or rehabilitated, (ha)
increasing of biodiversity (yes-no), covering area
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
+
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ___________Sanginova S.R._____________ ________________ First name/Last name signature
SUBPROJECT 6
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Reconstruction of automobile road in Javonon-Safedoron villages of Kadi Ob jamoat, Rogun raion
4
Site observation, meeting with the population and jamoat authorities
Training on safety measures
Conduct shore-protection works.
No
During civil works
No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Reconstruction of automobile road in Javonon-Safedoron villages of Kadi Ob jamoat, Rogun raion
During civil works all the measures on cleanliness, wastes removal, noise and dust prevention are fulfilled. Schedule on the use of heavy machinery is complied with.
All the requirements and measures are fulfilled
Further road maintenance is the responsibility of State Enterprise on Maintenance and Operation of roads in Rogun raion
SUBPROJECT 7
Subproject construction status at the end of September 2012
1. Activity and progress:
Restoration of derivation canal
Bridge paving device
Restoration of bridge railing
Retaining wall device
Work progress at the end of September 2012: 75 % 2. Change in project organization
Bridge pass ability improved
Restoration of water spillway installations in the village 3. Relations with contractors and other stakeholders:
The beneficiaries and community groups actively participate in construction of the subproject
No particular problem with the contractor and beneficiaries
SUBPROJECT 7 System of environmental assessment and monitoring of the effectiveness of activities Date: _____10.10.2011__________
Date/Month/Year
Watershed: District: Varzob
JDC/JRC: Village: Dehmalik
Subproject: Rehabilitation of a bridge Subproject Code: PMU/CW/NCB/07.2012 BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No significant
impact on environment
During the civil works precaution works and discussions were conducted
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
-
+ -
The sub-project is referred to Category D1 – not significant impact on environment
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km) 0,1
Aftereffect:
area of afforested and bushed territories, (ha) 100 Near household lands
area (ha), of fixed slope land 0,2
Land areas improved and/or rehabilitated, (ha) 2
increasing of biodiversity (yes-no), covering area -
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
+
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ___________Sanginova S.R._____________ ________________ First name/Last name signature
SUBPROJECT 7
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Restoration of a bridge in Dehmalik village of Varzob raion
3
Meeting with population, site observation
Trainings on environment and use of safe materials during the civil works, complying with the standards
No No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Restoration of a bridge in Dehmalik village of Dehmalik jamoat, Varzob raion
During civil works all the measures on cleanliness, wastes removal, noise and dust prevention are fulfilled. Schedule on the use of heavy machinery is complied with.
Safety measures are followed. No negative impact on environment.
Further bridge maintenance is the responsibility of State Enterprise on Maintenance and Operation of roads in Varzob raion.
SUBPROJECT 8
Subproject construction status at the end of September 2012
1. Activity and progress:
Construction of captation
Installation of PVC pipe and dampers.
Installation of water distribution taps
Installation of reservoir and chlorination plant
Fencing of water reservoir territory
Work progress at the end of September 2012: 80 % 2. Change in project organization
Changes during civil works under the contract. 3. Relations with contractors and other stakeholders:
The beneficiaries actively participate in construction process
No particular problem with the contractor and beneficiaries
SUBPROJECT 8
System of environmental assessment and monitoring of the effectiveness of activities Date: ______11 05 2012___________
Date/Month/Year
Watershed: District: Faizobod
JDC/JRC: Village: Kulobiyon, Sari Chinor
Subproject: Drinking water supply Subproject Code: PMU/CW/NCB/08.2012 BLOCK F
Subproject’s category: Processing production, local handicrafts, water and energy saving, improvement of potable water supply, mills, smithy, refrigerator, etc.
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
There is no negative impact on the environment: does not pollute soil and water, does not make worse land condition (salinity, erosion), and does not lead to long-term or irreversible destruction of local vegetation.
No
Sanitary protected spring area is created
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the
biological diversity, saving of rare
species of plants and animals
-
+
+
with water chlorination prior its use and by conducting water analysis twice a year
Superfactor «-» (negative):
-
Output:
Energy resource economy (kilowatt\h\year) -
Water resource economy (m3\year) -
Aftereffect:
Land areas improved and/or rehabilitated, (ha) -
fixed slope land areas, (ha) -
increasing of biodiversity (yes-no), covering area -
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
-
reduction of the number of pests +
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ______________Sanginova S.R._____ ________________ First name/Last name signature
SUBPROJECT 8
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Drinking water supply
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Drinking water supply
Describe the site location
Kulobiyon –Sari Chinor village of Javoni jamoat, Faizabad raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge The State Institution on maintenance and operation of drinking water of Faizabad raion
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
The distance from the water spring to water supply is 10,2 km. Raion sanitary-epidemiological station (SES) is responsible for the quality of water. All the materials are safe and comply with international norms
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of local geologist, conclusion of the local sanitary-epidemiologic station on drinking water (SES)
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
15.09.2011 meeting with the village population was done and observation of the site. Trainings and consultations were conducted with the local population. Based on the approved table (checklist), the site was identified as D1 – no essential environmental impact
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [+] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
J. Reconstruction of buildings [+ ] Yes [] No Look Section A below
K. New small-scale construction []Yes [+] No Look Section A below
L. Individual system on cleaning of foul water [+]Yes [ ] No Look Section B below
M. Historical building (s) and raions []Yes [ + ] No Look Section C below
N. Land acquisition4 []Yes [ + ] No Look Section D below
O. Dangerous or poisonous materials5 1> 6 <1 []Yes [ + ] No Look Section E below
P. Impact on forests and/or conservation zones []Yes [+ ] No Look Section F below
Q. Processing / liquidation of wastes [+] Yes [ ] No Look Section G below
R. Movement and safety of the foot-passengers []Yes [+ ] No Look Section H below
4 Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to
suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land. 5 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, f during the construction works is being fulfilled
(g) Local supervising body on construction and environment, as well as communities on the planned activities
(h) All the required permissive documents for construction and/or reconstruction are put into shape (i) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (j) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(k) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(l) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(g) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(h) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(i) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(j) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(k) There must not be any open construction wastes burning and household wastes on the site
(l) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (c) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(d) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d,.
(e) The wastes are collected in special containers in the established place (f) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (g) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (h) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 8
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Drinking water supply in Kulobiyon-Sarichinor villages of Javonon jamoat, Faizabad raion
3
Site observation, meeting with the population and jamoat authorities
Training together with Sanitary Epidemic Station (SES) specialists on prevention of infectious diseases
Chlorination of water (raion SES)
No Permanently No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Drinking water supply in Kulobiyon-Sarichinor villages of Javonon jamoat, Faizabad raion
Regular water chlorination, spring area protection and identification of water quality by SES.
No negative impact on environment.
Chlorination and water quality identification by the SES specialists.
SUBPROJECT 9
Subproject construction status at the end of September 2012
1. Activity and progress:
Mechanized soil works
Monolithic and reinforced concrete base plate device.
Mounting of blocks
Monolithic surface device on blocks.
Monolithic retaining wall device
Work progress at the end of September 2012: 80 % 2. Change in project organization
Stockyard road improved
Rainfall water organized. 3. Relations with contractors and other stakeholders:
(Active) initiators for community and road departments and involved in designing of changes.
No particular problem with the contractor and beneficiaries.
SUBPROJECT 9 System of environmental assessment and monitoring of the effectiveness of activities Date: _____08.2012_____________
Date/Month/Year
Watershed: District: Rudaki
JDC/JRC: Village: Meykhon
Subproject: Rehabilitation of a bridge Subproject Code: PMU/CW/NCB/09.2012 BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No
Anti-mudflow works done
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
-
+
+
Improved spillway capacity of the river bed, as well as of cattle-driving roads
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km) 0,036
Aftereffect:
area of afforested and bushed territories, (ha) 30
area (ha), of fixed slope land 0,05
Land areas improved and/or rehabilitated, (ha) -
increasing of biodiversity (yes-no), covering area -
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
+
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ___________Sanginova S.R._____________ ________________ First name/Last name signature
SUBPROJECT 9
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Restoration of a bridge in Shaykhon village of Rohati jamoat, Rudaki raion
6 Meeting with population and site observation
Training with the workers during civil works.
Timely removal of wastes, prevention of noise, dust and river pollution
No
During civil works
No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Restoration of a bridge in Shaykhon village of Rohati jamoat, Rudaki raion
During civil works all the measures on cleanliness, wastes removal, noise and dust prevention are fulfilled. Schedule on the use of heavy machinery is complied with.
Safety measures are followed. No negative impact on environment.
Further bridge maintenance is the responsibility of State Enterprise on Maintenance and Operation of roads in Rudaki raion.
SUBPROJECT 10
Subproject construction status at the end of September 2012
1. Activity and progress:
Dismantling of the old bridge
Monolithic r/c bridge footing device
Mounting of metallic beams
Production and mounting of pavement plate
Shore-protection works
Work progress at the end of September 2012: 85 % 2. Change in project organization
Straightening of river bed
Metallic pipes device for rain water spillway
Asphalt covering of the bridge and its approaches. 3. Relations with contractors and other stakeholders:
(Active) initiators for community and road departments and involved in designing of changes
No particular problem with the contractor and beneficiaries.
SUBPROJECT 10
System of environmental assessment and monitoring of the effectiveness of activities Date:____09.2012_____________
Date/Month/Year
Watershed: District: Rudaki
JDC/JRC: Village: Tillobod, jamoat Lohur
Subproject: Rehabilitation of a bridge Subproject Code: PMU/CW/NCB/10.2012 BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No
Shore-protection works done
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
-
+ -
Spillway capacity of the river improved.
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km) 0,32
Aftereffect:
area of afforested and bushed territories, (ha) -
area (ha), of fixed slope land 0,9
Land areas improved and/or rehabilitated, (ha) -
increasing of biodiversity (yes-no), covering area -
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
+
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ___________Sanginova S.R._____________ ________________ First name/Last name signature
SUBPROJECT 10
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Restoration of a bridge in Tillobod village of Lohur jamoat, Rudaki raion
5 Site observation, meeting with the population
Training with contractors and population on “environment and soil erosion” (by the local land management specialist)
No river pollution, removal of wastes and use of construction materials according to the state standards
No
During civil works
No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Restoration of a bridge in Tillobod village of Lohur jamoat, Rudaki raion
Compliance with safety measures. Timely removal of wastes, watering of the construction area from dust, approval of work plan for heavy machinery with the population.
No negative impact on environment.
Further bridge maintenance is the responsibility of Raion State Enterprise on Maintenance and Operation of roads.
SUBPROJECT 11
Subproject construction status at the end of September 2012
1. Activity and progress:
Concrete supports device completed.
Shore-protection works on river bed and banks.
Preparation of supporting girder for mounting
Work progress at the end of September 2012: 70 % 2. Change in project organization
None 3. Relations with contractors and other stakeholders:
No particular problem with the contractor and beneficiaries.
SUBPROJECT 11
System of environmental assessment and monitoring of the effectiveness of activities
Date: _____02.05.2012__________
Date/Month/Year
Watershed: District: Faizabad
JDC/JRC: Village: Dorob of Kalai-Dasht jamoat
Subproject: Restoration of a bridge Subproject Code: PMU/CW/NCB/11-2012 BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No
This sub-project has no impact on environment
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
No
No
No
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km) 0,1
Aftereffect:
area of afforested and bushed territories, (ha) 180 Near household lands
area (ha), of fixed slope land 1,2
Land areas improved and/or rehabilitated, (ha) 3,2
increasing of biodiversity (yes-no), covering area -
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
Yes
decreasing of animal morbidity Yes
decreasing of human morbidity Yes
Executor: ___________Sanginova S.R._____________ ________________ First name/Last name signature
SUBPROJECT 11
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Restoration of a bridge through Elok river in Dorob village of Kalai Dasht jamoat, Faizabad raion
4
Meeting with village population and sub-project site observation
Training with contractor and workers on safety measures
Using of environmentally clean materials. Timely removal of wastes and safety measures compliance
No During civil works
No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Restoration of a bridge through Elok river in Dorob village of Kalai Dasht jamoat, Faizabad raion.
Compliance with schedule on use of heavy machinery. No pollution of the river and shore-protection works.
All the measures are followed. No negative impact on environment.
Compliance with the requirements on use of machinery during the civil works.
SUBPROJECT 12
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Preparation of tendering documents
Tendering and awarding
Progress at the end of September 2012: Contracted on September 20, 2012 2. Change in project organization
None 3. Relations with contractors and other stakeholders:
The owners actively participate in selection of subproject
The contribution of beneficiaries is agreed.
SUBPROJECT 12
System of environmental assessment and monitoring of the effectiveness of activities Date: _____20.12.2011__________
Date/Month/Year
Watershed: District: Rogun
JDC/JRC: Village: Kadi-Ob jamoat, Kadi Ob village
Subproject: Restoration of automobile bridge Subproject Code: PMU/CW/NCB/12.2012 BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No
Plantation
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
Yes
Yes
Plantation
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km) 0,075
Aftereffect:
area of afforested and bushed territories, (ha)
area (ha), of fixed slope land 0.03
Land areas improved and/or rehabilitated, (ha)
increasing of biodiversity (yes-no), covering area -
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
Yes
decreasing of animal morbidity Yes
decreasing of human morbidity Yes
Executor: ___________Sanginova S.R._____________ ________________ First name/Last name signature
SUBPROJECT 12
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Restoration of a bridge through Kadi Ob village of Kadi Ob jamoat, Rogun raion
4
Meeting with the population and jamoat authorities. Site observation.
Training with the population and jamoat authorities on “effect of this subproject”
Comply with standards during civil works
No
During civil works
Recommendations on further use and maintenance of this bridge (Raion State Enterprise on Road Maintenance and Operation). No complaints.
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Restoration of a bridge through Kadi Ob village of Kadi Ob jamoat, Rogun raion
Removal of wastes during the works, noise and dust prevention, Shore-protection works, compliance with the safety measures.
No negative impact on environment.
Compliance with safety measures during civil works.
SUBPROJECT 13
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Preparation of tendering documents
Tendering and awarding
Progress at the end of September 2012: Contracted on September 20, 2012 2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Water Users Association exists
The beneficiaries actively participated in the selection of the subproject.
SUBPROJECT 13
System of environmental assessment and monitoring of the effectiveness of activities
Date: ________25.04.2011________
Date/Month/Year
Watershed: District: Vahdat
JDC/JRC: Village: Geshi village of Chorsu jamoat
Subproject: Drinking water supply Subproject Code: PMU/CW/NCB/13.2011 BLOCK F
Subproject’s category: Processing production, local handicrafts, water and energy saving, improvement of potable water supply, mills, smithy, refrigerator, etc.
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
There is no negative impact on the environment: does not pollute soil and water, does not make worse land condition (salinity, erosion), and does not lead to long-term or irreversible destruction of local vegetation.
No
The sub-project has no impact on environment.
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the
biological diversity, saving of rare
species of plants and animals
The economic conditions of the village people will improve and decreased number of infectious diseases. The chlorination of water will take place.
Superfactor «-» (negative):
-
Output:
Energy resource economy (kilowatt\h\year)
Water resource economy (m3\year)
Aftereffect:
Land areas improved and/or rehabilitated, (ha)
fixed slope land areas, (ha)
increasing of biodiversity (yes-no), covering area
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
reduction of the number of pests +
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ______________Sanginova S.R.___________ ________________
SUBPROJECT 13
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Drinking water supply
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Drinking water supply
Describe the site location
Geshi village of Chorsu jamoat, Vahdat
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Water user associations
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
The distance from the water spring to water supply is 8 km. Raion sanitary-epidemiological station (SES) is responsible for the quality of water. All the materials are safe and comply with international norms
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of local geologist, conclusion of the local sanitary-epidemiologic station on drinking water (SES).
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
25.04.2012 trainings with the local population and site observations were conducted. The site has no environmental impact.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [+] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
S. Reconstruction of buildings [ ] Yes [+] No Look Section A below
T. New small-scale construction [+]Yes [] No Look Section A below
U. Individual system on cleaning of foul water [+]Yes [ ] No Look Section B below
V. Historical building (s) and raions []Yes [ + ] No Look Section C below
W. Land acquisition7 []Yes [ + ] No Look Section D below
X. Dangerous or poisonous materials8 1> 9 <1 []Yes [ + ] No Look Section E below
Y. Impact on forests and/or conservation zones []Yes [+ ] No Look Section F below
Z. Processing / liquidation of wastes [] Yes [+ ] No Look Section G below
AA. Movement and safety of the foot-passengers []Yes [+ ] No Look Section H below
7 Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to
suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land. 8 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, during the construction works is being fulfilled
(m) Local supervising body on construction and environment, as well as communities on the planned activities
(n) All the required permissive documents for construction and/or reconstruction are put into shape (o) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (p) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(q) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(r) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality (m) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(n) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(o) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(p) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(q) There must not be any open construction wastes burning and household wastes on the site
(r) There must not be any unused construction vehicles on the site Noise (e) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(f) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation
(i) The wastes are collected in special containers in the established place (j) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (k) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (l) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 13
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of additional water supply system in Geshi village of Vahdat raion
4
Meeting with the population and jamoat authorities. Site observation. Meeting with raion environment specialist, SES, engineer and land management specialist
Training of the population on “chlorination and effective use of drinking water”.
Permanent compliance of clean drinking water (chlorination and identification of water quality, laboratory analysis by SES)
No
Permanently
Permanent clean water compliance. No complaints.
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of additional water supply system in Geshi village of Vahdat raion
Identify quality of water (by lab tests twice a year) and chlorination (permanently) SES.
No negative impact on environment.
Chlorination (permanently)and water analysis by SES.
SUBPROJECT 14
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Preparation of tendering documents
Tendering and awarding
Progress at the end of September 2012: Contracted on September 20, 2012 2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Raion road authorities and the population actively participate in project preparation process of estimate documentation.
SUBPROJECT 14
System of environmental assessment and monitoring of the effectiveness of activities Date: _____20.12.2011__________
Date/Month/Year
Watershed: District: Vahdat
JDC/JRC: Village: Naydara river of Dusti jamoat
Subproject: Restoration of a bridge Subproject Code: PMU/CW/NCB/14-2012 BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No
This sub-project has no impact on environment
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
No
No
No
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km) -
Aftereffect:
area of afforested and bushed territories, (ha)
area (ha), of fixed slope land
Land areas improved and/or rehabilitated, (ha)
increasing of biodiversity (yes-no), covering area
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
Yes
decreasing of animal morbidity Yes
decreasing of human morbidity Yes
Executor: ___________Sanginova S.R._____________ ________________ First name/Last name signature
SUBPROJECT 14
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Bridge reconstruction
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Bridge reconstruction
Describe the site location
Naydara river of Dusti, Vahdat raion Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge The State Enterprise on maintenance and operation of automobile roads of Vahdat raion
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
Reconstruction and restoration works with the account of bridge approach from two sides and shore-protection works.
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of the State Enterprise on maintenance and operation of automobile roads of Vahdat raion.
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
14.04 meeting was conducted and observation of the site. Trainings and consultations were conducted with the population. The site was identified as not having any impact on environment.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
BB. Reconstruction of buildings [ ] Yes [] No Look Section A below
CC. New small-scale construction []Yes [] No Look Section A below
DD. Individual system on cleaning of foul water []Yes [ ] No Look Section B below
EE. Historical building (s) and raions []Yes [ ] No Look Section C below
FF. Land acquisition10
[]Yes [ ] No Look Section D below
GG. Dangerous or poisonous materials11
1> 12 <1
[]Yes [ ] No Look Section E below
HH. Impact on forests and/or conservation zones []Yes [ ] No Look Section F below
II. Processing / liquidation of wastes [] Yes [ ] No Look Section G below
JJ. Movement and safety of the foot-passengers []Yes [ ] No Look Section H below
10
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
11 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, during the construction works is being fulfilled
(s) Local supervising body on construction and environment, as well as communities on the planned activities
(t) All the required permissive documents for construction and/or reconstruction are put into shape (u) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (v) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(w) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(x) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality. (s) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(t) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(u) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(v) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(w) There must not be any open construction wastes burning and household wastes on the site
(x) There must not be any unused construction vehicles on the site Noise (g) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(h) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation
(m) The wastes are collected in special containers in the established place (n) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (o) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (p) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 14
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Restoration of a bridge through Naydara river in Dusti jamoat, Vahdat raion
4
Meeting with village population and sub-project site observation
Training on “safety measures and use of natural resources”
Timely removal of wastes and use of quality materials during construction
No
During civil works
No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Restoration of a bridge through Naydara river in Dusti jamoat, Vahdat raion
Shore-protection works, compliance with safety measures.
No negative impact on environment.
Maintained by the local authorities.
SUBPROJECT 15
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Preparation of tendering documents
Progress at the end of September 2012: Ready to be tendered (tender launched on October 02, 2012)
2. Change in project organization
None 3. Relations with contractors and other stakeholders:
The beneficiaries are ready to fulfill 10% of expenses from the project total cost..
SUBPROJECT 15
System of environmental assessment and monitoring of the effectiveness of activities Date: ________05.05.2012________
Date/Month/Year
Watershed: District: Vahdat
JDC/JRC: Village: Kokhu village of Romit jamoat
Subproject: Electricity generation plants Subproject Code: BLOCK F
Subproject’s category: Processing production, local handicrafts, water and energy saving, improvement of potable water supply, mills, smithy, refrigerator, etc.
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
There is no negative impact on the environment: does not pollute soil and water, does not make worse land condition (salinity, erosion), and does not lead to long-term or irreversible destruction of local vegetation.
No
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the
biological diversity, saving of rare
species of plants and animals
The village people will be supplied with the electricity. Their livelihood will improve. The sub-project has no impact on environment.
Superfactor «-» (negative):
-
Output:
Energy resource economy (kilowatt\h\year) 80x24x365 700800
Water resource economy (m3\year)
Aftereffect:
Land areas improved and/or rehabilitated, (ha)
fixed slope land areas, (ha)
increasing of biodiversity (yes-no), covering area
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
reduction of the number of pests +
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ______________Sanginova S.R.___________ ________________ First name/Last name signature
SUBPROJECT 15
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Electricity supply system
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Small-scale hydro power plant
Describe the site location
Kokhu village of Romit jamoat, Vahdat raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Production Cooperative “Sohtmoni” of Vahdat city
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
The territory, where the village Kokhu is located, spreads for 2 km with the river Sardai Miyona by narrow line. Considering minimum land resources and convenient location of already existing water catchment, the power site was selected on the existing canal taking account geological and hydrological conditions.
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of local geologist, conclusion of the automobile roads operation specialist and warranty letter on O&M.
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
05.05.2012 meeting with the village population and raion administration was done. Based on the area observation and discussions with the local population, the site was identified as D1 – not essential environmental impact.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [+] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
KK. Reconstruction of buildings [+] Yes [] No Look Section A below
LL. New small-scale construction []Yes [+] No Look Section A below
MM. Individual system on cleaning of foul water
[]Yes [+] No Look Section B below
NN. Historical building (s) and raions []Yes [ + ] No Look Section C below
OO. Land acquisition13
[]Yes [ + ] No Look Section D below
PP. Dangerous or poisonous materials14
1> 15 <1 []Yes [ + ] No Look Section E below
QQ. Impact on forests and/or conservation zones
[]Yes [+ ] No Look Section F below
RR. Processing / liquidation of wastes [+] Yes [] No Look Section G below
SS. Movement and safety of the foot-passengers []Yes [+ ] No Look Section H below
13
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
14 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, f during the construction works is being fulfilled
(y) Local supervising body on construction and environment, as well as communities on the planned activities
(z) All the required permissive documents for construction and/or reconstruction are put into shape (aa) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (bb) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(cc) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(dd) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(y) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(z) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(aa) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(bb) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(cc) There must not be any open construction wastes burning and household wastes on the site
(dd) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (i) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(j) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d,.
(q) The wastes are collected in special containers in the established place (r) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (s) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (t) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S
SUBPROJECT 15
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of small power plant in Kokhu village of Rimot jamoat, Vahdat raion
6
Meeting with village population, sub-project site observation, meeting with the specialists (on energy, geology, environment, land management, engineer and designer)
Training on environmental protection of this sub-project (with the specialists of raion administration. Ecologist, energy specialist, geologist and land management specialist)
Use of standard materials complying with the state standards, timely removal of wastes and safety measures compliance
No
During civil works
No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of small power plant in Kokhu village of Romit jamoat, Vahdat raion
Comply with safety measures when using heavy machinery. Removal of wastes, cleaning of the site from fuel and prevent pollution of the river.
No negative impact on environment.
Maintained by the Production Cooperation “Sohtmonchi”
SUBPROJECT 16
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Preparation of tendering documents
Progress at the end of September 2012: Ready to be tendered (tender launched on October 02, 2012)
2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Owners and the population are willing to actively participate during the civil works
SUBPROJECT 16
System of environmental assessment and monitoring of the effectiveness of activities
Date: _____20.02.2012___________
Date/Month/Year
Watershed: District: Vahdat
JDC/JRC: Village: Zargar, Chaman villages of Abdulvosiev jamoat
Subproject: Rehabilitation of a road Subproject Code: BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No
The sub-project has no impact on environment
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
- - -
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km)
Aftereffect:
area of afforested and bushed territories, (ha)
area (ha), of fixed slope land
Land areas improved and/or rehabilitated, (ha)
increasing of biodiversity (yes-no), covering area
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
+
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ___________Sanginova S.R._____________ ________________
First name/Last name signature
SUBPROJECT 16
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Reconstruction of a road
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Reconstruction of a road
Describe the site location
Zargar, Chaman villages of Abdulvosiev jamoat, Vahdat raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge The State Enterprise on maintenance and operation of automobile roads of Vahdat raion
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
Total road length is 7500 m. Out of which, 4500 m are rehabilitated. All the materials used are in compliance with the international norms.
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of local geologist, conclusion of the automobile roads operation specialist.
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
20.09.2011 meeting with the population and observation of the site were conducted. Trainings and consultations were conducted with the local population. Based on the area observation and discussions with the local population, the site was identified as D1 – not essential environmental impact.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
TT. Reconstruction of buildings [ ] Yes [+] No Look Section A below
UU. New small-scale construction []Yes [+ ] No Look Section A below
VV. Individual system on cleaning of foul water []Yes [+ ] No Look Section B below
WW. Historical building (s) and raions []Yes [ + ] No Look Section C below
XX. Land acquisition16
[]Yes [ + ] No Look Section D below
YY. Dangerous or poisonous materials17
1> 18 <1 []Yes [ + ] No Look Section E below
ZZ. Impact on forests and/or conservation zones []Yes [+ ] No Look Section F below
AAA. Processing / liquidation of wastes [] Yes [+ ] No Look Section G below
BBB. Movement and safety of the foot-passengers
[]Yes [+ ] No Look Section H below
16
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
17 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, f during the construction works is being fulfilled
(ee) Local supervising body on construction and environment, as well as communities on the planned activities
(ff) All the required permissive documents for construction and/or reconstruction are put into shape (gg) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (hh) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(ii) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(jj) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(ee) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(ff) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(gg) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(hh) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(ii) There must not be any open construction wastes burning and household wastes on the site
(jj) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (k) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(l) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d,.
(u) The wastes are collected in special containers in the established place (v) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (w) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (x) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 16
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Restoration of automobile road in Zargar-Chaman villages of Abdulvosiev jamoat, Vahdat raion
4
Meeting with jamoat population, sub-project site observation.
Meetings and trainings on “impact of this project on the economy, population and livelihood of the jamoat”.
Safety measures, cleanliness compliance and prevention of noise during works
No
During civil works
No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Restoration of automobile road in Zargar-Chaman villages of Abdulvosiev jamoat, Vahdat raion
Compliance with safety measures during civil works.
No negative impact on environment
Maintained by the local authorities
SUBPROJECT 17
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Preparation of tendering documents
Progress at the end of September 2012: Ready to be tendered (tender launched on October 02, 2012)
2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Owners and the population are willing to actively participate during the civil works
SUBPROJECT 17
System of environmental assessment and monitoring of the effectiveness of activities
Date: _____13.05.2012___________
Date/Month/Year
Watershed: District: Vahdat
JDC/JRC: Village: Shirinchashma of B.Burunov jamoat
Subproject: Rehabilitation of a road Subproject Code: BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No
The sub-project has no impact on environment
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
The livelihood of village people will improve
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km)
Aftereffect:
area of afforested and bushed territories, (ha)
area (ha), of fixed slope land
Land areas improved and/or rehabilitated, (ha)
increasing of biodiversity (yes-no), covering area
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
+
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ___________Sanginova S.R._____________ ________________
First name/Last name signature
SUBPROJECT 17
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Reconstruction of a road
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Reconstruction of a road
Describe the site location
Shirinchashma, Javoni of B.Burunov jamoat, Vahdat raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge The State Enterprise on maintenance and operation of automobile roads of Vahdat raion
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
Total road length is 10000 m. Out of which, 2700 m are rehabilitated. All the materials used are in compliance with the international norms.
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of local geologist, conclusion of the automobile roads operation specialist.
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
13.05.2009 meeting with the population and observation of the site were conducted. Trainings and consultations were conducted with the local population. Based on the area observation and discussions with the local population, the site was identified as D1 – not essential environmental impact.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [+] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
CCC. Reconstruction of buildings [ ] Yes [+] No Look Section A below
DDD. New small-scale construction []Yes [+ ] No Look Section A below
EEE. Individual system on cleaning of foul water
[]Yes [+ ] No Look Section B below
FFF. Historical building (s) and raions []Yes [ + ] No Look Section C below
GGG. Land acquisition19
[]Yes [ + ] No Look Section D below
HHH. Dangerous or poisonous materials20
1> 21 <1
[]Yes [ + ] No Look Section E below
III. Impact on forests and/or conservation zones []Yes [+ ] No Look Section F below
JJJ. Processing / liquidation of wastes [] Yes [+ ] No Look Section G below
KKK. Movement and safety of the foot-passengers
[]Yes [+ ] No Look Section H below
19
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
20 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, f during the construction works is being fulfilled
(kk) Local supervising body on construction and environment, as well as communities on the planned activities
(ll) All the required permissive documents for construction and/or reconstruction are put into shape (mm) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (nn) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(oo) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(pp) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(kk) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(ll) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(mm) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(nn) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(oo) There must not be any open construction wastes burning and household wastes on the site
(pp) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (m) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(n) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d,.
(y) The wastes are collected in special containers in the established place (z) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (aa) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (bb) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 17
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Restoration of automobile road in Rohi Mehrgon-ShirinChashma villages of Abdulvosiev jamoat, Vahdat raion
4
Meeting with the population, sub-project site observation
Training on impact of the project on knowledge level of the population and environment.
Removal of wastes during the civil works.
No
During civil works
No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Restoration of automobile road in Rohi Mehrgon-ShirinChashma villages of Abdulvosiev jamoat, Vahdat raion
Compliance with safety measures during civil works.
No negative impact on environment
Maintained by the local authorities
SUBPROJECT 18
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists
Project design is completed
All the necessary documents are collected and given for translation
Progress at the end of September 2012: Submission to ADB expected end October 2012
2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Water Users Association and the population are willing to actively participate during the civil works
SUBPROJECT 18
System of environmental assessment and monitoring of the effectiveness of activities
Date: _____07.2012__________
Date/Month/Year
Watershed: District: Varzob
JDC/JRC: Village: Duoba of Chorbog jamoat
Subproject: Water supply system Subproject Code: BLOCK G
Subproject’s category: Irrigation systems, restoration of irrigation canals, construction of dams, bridges, roads, pipelines
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
Does not bring on additional erosion or land underflooding, stable to impacts of environmental factors (landslides, mud flows, etc.), does not cause pollution of soil and water sources, and does not lead to long-term or irreversible destruction of local vegetation.
No
This sub-project has no impact on environment
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the biological
diversity, saving of rare species of
plants and animals
Yes
Yes
Superfactor «-» (negative):
-
Output:
Length of bank protection of rivers and canals (km) 0,075
Aftereffect:
area of afforested and bushed territories, (ha) 100
area (ha), of fixed slope land
Land areas improved and/or rehabilitated, (ha)
increasing of biodiversity (yes-no), covering area
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
Yes
decreasing of animal morbidity Yes
decreasing of human morbidity Yes
Executor: ___________Sanginova S.R._____________ ________________ First name/Last name signature
SUBPROJECT 18
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Construction of irrigation system
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Construction of irrigation system
Describe the site location
Duoba village of Chorbog jamoat, Varzob raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Water users Association
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
All the materials used are in compliance with the international norms.
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of local geologist
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
25.04.2012 meeting with the population was conducted. Trainings and site observation were conducted. The site was identified as not having any impact on environment.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [+] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
LLL. Reconstruction of buildings [ ] Yes [+] No Look Section A below
MMM. New small-scale construction [+]Yes [ ] No Look Section A below
NNN. Individual system on cleaning of foul water
[+]Yes [ ] No Look Section B below
OOO. Historical building (s) and raions []Yes [ + ] No Look Section C below
PPP. Land acquisition22
[]Yes [ + ] No Look Section D below
QQQ. Dangerous or poisonous materials23
1> 24 <1
[]Yes [ + ] No Look Section E below
RRR. Impact on forests and/or conservation zones
[]Yes [+ ] No Look Section F below
SSS. Processing / liquidation of wastes [] Yes [+ ] No Look Section G below
TTT. Movement and safety of the foot-passengers
[]Yes [+ ] No Look Section H below
22
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
23 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, f during the construction works is being fulfilled
(qq) Local supervising body on construction and environment, as well as communities on the planned activities
(rr) All the required permissive documents for construction and/or reconstruction are put into shape (ss) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (tt) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(uu) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(vv) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality (qq) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(rr) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(ss) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(tt) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(uu) There must not be any open construction wastes burning and household wastes on the site
(vv) There must not be any unused construction vehicles on the site Noise (o) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(p) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation
(cc) The wastes are collected in special containers in the established place (dd) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (ee) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (ff) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 18
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of irrigation
system in Duoba jamoat,
Varzob raion.
5
Meeting with jamoat
population, sub-
project site
observation
Training on gardening
on slope lands and
planting of coniferous
trees.
Use of engineer
calculations during
civil works and safety
norms compliance.
Shore protection
works to be done
No
During civil
works.
Care for planting,
watering and
fertilizing the
plants.
No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of irrigation system in Duoba village of Chorbog jamoat, Varzob raion.
Shore-protection works, temporary fencing of the territory during civil works.
No negative impact on environment
Maintained by the Raion Water Users Association
SUBPROJECT 19
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Project design and estimate completed
Translation of project documentation close to completion.
Progress at the end of September 2012: Submission to ADB expected begin October 2012
2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Water Users Association and the population are willing to actively participate during the civil works
SUBPROJECT 19
System of environmental assessment and monitoring of the effectiveness of activities Date: ________05.02.2012________
Date/Month/Year
Watershed: District: Rogun
JDC/JRC: Village: Chashmai Kulo of Kadi Ob jamoat
Subproject: Drinking water supply Subproject Code: BLOCK F
Subproject’s category: Processing production, local handicrafts, water and energy saving, improvement of potable water supply, mills, smithy, refrigerator, etc.
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
There is no negative impact on the environment: does not pollute soil and water, does not make worse land condition (salinity, erosion), and does not lead to long-term or irreversible destruction of local vegetation.
No
The sub-project has no impact on environment.
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the
biological diversity, saving of rare
species of plants and animals
The economic conditions of the village people will improve and decreased number of infectious diseases. The chlorination of water will take place.
Superfactor «-» (negative):
-
Output:
Energy resource economy (kilowatt\h\year)
Water resource economy (m3\year)
Aftereffect:
Land areas improved and/or rehabilitated, (ha)
fixed slope land areas, (ha)
increasing of biodiversity (yes-no), covering area
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
reduction of the number of pests +
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ______________Sanginova S.R.___________ ________________ First name/Last name signature
SUBPROJECT 19
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Drinking water supply
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Drinking water supply
Describe the site location
Chashmai Kulo village of Kadi Ob jamoat, Rogun city
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Water user associations
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
The distance from the water spring to water supply is 8 km. Raion sanitary-epidemiological station (SES) is responsible for the quality of water. All the materials are safe and comply with international norms
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of local geologist, conclusion of the local sanitary-epidemiologic station on drinking water (SES).
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
05.02.2012 meeting with the population of the village was done. Trainings were conducted with the local population and observations of the site. The site has no environmental impact.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [+] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
UUU. Reconstruction of buildings [ ] Yes [+] No Look Section A below
VVV. New small-scale construction [+]Yes [] No Look Section A below
WWW. Individual system on cleaning of foul water
[+]Yes [ ] No Look Section B below
XXX. Historical building (s) and raions []Yes [ + ] No Look Section C below
YYY. Land acquisition25
[]Yes [ + ] No Look Section D below
ZZZ. Dangerous or poisonous materials26
1> 27 <1
[]Yes [ + ] No Look Section E below
AAAA. Impact on forests and/or conservation zones
[]Yes [+ ] No Look Section F below
BBBB. Processing / liquidation of wastes [] Yes [+ ] No Look Section G below
CCCC. Movement and safety of the foot-passengers
[]Yes [+ ] No Look Section H below
25
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
26 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, f during the construction works is being fulfilled
(ww) Local supervising body on construction and environment, as well as communities on the planned activities
(xx) All the required permissive documents for construction and/or reconstruction are put into shape (yy) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (zz) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(aaa) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(bbb) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(ww) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(xx) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(yy) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(zz) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(aaa) There must not be any open construction wastes burning and household wastes on the site
(bbb) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (q) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(r) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d,.
(gg) The wastes are collected in special containers in the established place (hh) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (ii) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (jj) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 19
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of dringking water line in Kulo village of Kadi Ob jamoat, Rogun raion
4
Site observation, meeting with local environment specialist, engineer, land surveyor and workers of SES.
Conducted training “Water is a source of life”
Cleaning of water: Chlorination and water analysis. SES
No Permanently No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of dringking water line in Chashmai Kulo village of Kadi Ob jamoat, Rogun raion
Guarding the spring territory, chlorination of drinking water
No negative impact on environment
Water quality identification and chlorination by SES
SUBPROJECT 20
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists
Project designi is completed
All the necessary documents are collected and given for translation
Progress at the end of September 2012: Submission to ADB expected end October 2012
2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Water Users Association and the population are willing to actively participate during the civil works
SUBPROJECT 20
System of environmental assessment and monitoring of the effectiveness of activities
Date: ________25.04.2011________
Date/Month/Year
Watershed: District: Vahdat
JDC/JRC: Village: Yumsurok, Kuli Ob villages of Simiganch jamoat
Subproject: Drinking water supply Subproject BLOCK F
Subproject’s category: Processing production, local handicrafts, water and energy saving, improvement of potable water supply, mills, smithy, refrigerator, etc.
Evaluation/
Output (yes/no; +/-)
Comment
Acce
pta
bili
ty
There is no negative impact on the environment: does not pollute soil and water, does not make worse land condition (salinity, erosion), and does not lead to long-term or irreversible destruction of local vegetation.
No
The sub-project has no impact on environment.
Superfactor «+» (affirmative):
Using of alternative energy sources
Contribute to improvement of soil,
water-saving, fixing of slope lands,
prevention of water and wind
erosion, subsidence, wettings
Contribute to increase the
biological diversity, saving of rare
species of plants and animals
Number of infectious diseases will decrease.
Superfactor «-» (negative):
-
Output:
Energy resource economy (kilowatt\h\year)
Water resource economy (m3\year)
Aftereffect:
Land areas improved and/or rehabilitated, (ha)
fixed slope land areas, (ha)
increasing of biodiversity (yes-no), covering area
Species of rare, endemic and endangered plants and animals, which is going to be rehabilitated (list, quantity, area of covering)
reduction of the number of pests +
decreasing of animal morbidity +
decreasing of human morbidity +
Executor: ______________Sanginova S.R.___________ ________________
SUBPROJECT 20
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Drinking water supply
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Drinking water supply
Describe the site location
Yumsurok, Kuli Ob village of Simiganch jamoat, Vahdat raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Water user associations
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
The distance from the water spring to water supply is 3,2 km. Raion sanitary-epidemiological station (SES) is responsible for the quality of water.
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of local geologist, conclusion of the local sanitary-epidemiologic station on drinking water (SES).
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
25.04.2012 a meeting with the population was conducted. Trainings were conducted with the local population. Based on the area observation, the site was identified as not having any impact on environment.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [+] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
DDDD. Reconstruction of buildings [ ] Yes [+] No Look Section A below
EEEE. New small-scale construction []Yes [+ ] No Look Section A below
FFFF. Individual system on cleaning of foul water
[]Yes [+ ] No Look Section B below
GGGG. Historical building (s) and raions []Yes [ + ] No Look Section C below
HHHH. Land acquisition28
[]Yes [ + ] No Look Section D below
IIII. Dangerous or poisonous materials29
1> 30 <1 []Yes [ + ] No Look Section E below
JJJJ. Impact on forests and/or conservation zones
[]Yes [+ ] No Look Section F below
KKKK. Processing / liquidation of wastes [] Yes [+ ] No Look Section G below
LLLL. Movement and safety of the foot-passengers
[]Yes [+ ] No Look Section H below
28
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
29 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, f during the construction works is being fulfilled
(ccc) Local supervising body on construction and environment, as well as communities on the planned activities
(ddd) All the required permissive documents for construction and/or reconstruction are put into shape (eee) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (fff) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(ggg) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(hhh) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(ccc) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(ddd) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(eee) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(fff) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(ggg) There must not be any open construction wastes burning and household wastes on the site
(hhh) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (s) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(t) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d,.
(kk) The wastes are collected in special containers in the established place (ll) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (mm) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (nn) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 20
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of water line in Kuliyo-Yumsurok villages of Simiganch jamoat, Vahdat raion
5
Meeting with the population and raion specialists, sub-project site observation
Meeting with raion specialists: ecologist, SES specialist on land management, geologist. Training on “clean water secures healthy life-style”.
Chlorination of water. Identification of water quality, rational use of drinking water.
No Permanently No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of water line in Kuliyo-Yumsurok villages of Simiganch jamoat, Vahdat raion
Analysis and identification of water quality (twice a year) by the SES specialists
No negative impact on environment
Chlorination by SES
SUBPROJECT 21
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Project design is underway
Progress at the end of September 2012: Design by Design Institute 65 % done 2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Water Users Association and the population are willing to actively participate during the civil works
SUBPROJECT 21
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Drinking water supply
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Drinking water supply
Describe the site location
Kangeli village of Faizabad jamoat, Faizabad raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Water user associations
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
The distance from the water spring to water supply is 10 km. Raion sanitary-epidemiological station (SES) is responsible for the quality of water. All the materials are safe and comply with international norms
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of local geologist, conclusion of the local sanitary-epidemiologic station on drinking water (SES).
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
30.07.2009 meeting with the population was done. Trainings were conducted with the local population and observations of the site. Based on the area observation and discussions with the local population, the site was identified as D1 – not essential environmental impact.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [+] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
MMMM. Reconstruction of buildings [ ] Yes [+] No Look Section A below
NNNN. New small-scale construction [+]Yes [] No Look Section A below
OOOO. Individual system on cleaning of foul water
[+]Yes [ ] No Look Section B below
PPPP. Historical building (s) and raions []Yes [ + ] No Look Section C below
QQQQ. Land acquisition31
[]Yes [ + ] No Look Section D below
RRRR. Dangerous or poisonous materials32
1> 33 <1
[]Yes [ + ] No Look Section E below
SSSS. Impact on forests and/or conservation zones
[]Yes [+ ] No Look Section F below
TTTT. Processing / liquidation of wastes [] Yes [+ ] No Look Section G below
UUUU. Movement and safety of the foot-passengers
[]Yes [+ ] No Look Section H below
31
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
32 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, f during the construction works is being fulfilled
(iii) Local supervising body on construction and environment, as well as communities on the planned activities
(jjj) All the required permissive documents for construction and/or reconstruction are put into shape (kkk) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (lll) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(mmm) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(nnn) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(iii) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(jjj) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(kkk) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(lll) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(mmm) There must not be any open construction wastes burning and household wastes on the site
(nnn) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (u) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(v) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d,.
(oo) The wastes are collected in special containers in the established place (pp) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (qq) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (rr) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 21
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of water supply line in Kengeli village of Faizabad jamoat, Faizabad raion
3
Meetings with the jamoat population. Subproject site observation
Training on “drinking water is: a) health, b) saving for the budget”
Water chlorination and effective use of drinking water
No No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of water supply line in Kengeli village of Faizabad jamoat, Faizabad raion
Chlorination of drinking water
No negative impact on environment
Chlorination and effective use of drinking water.
SUBPROJECT 22
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Project design is underway
Progress at the end of September 2012: Design by Design Institute 65 % done 2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Water Users Association and the population are willing to actively participate during the civil works
SUBPROJECT 22
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Construction of water supply line
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Construction of water supply line
Describe the site location
Chukurak village of Faizabad jamoat, Faizabad raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Water users Association
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
Raion Sanitary-Epidemic Station is responsible for the quality of water. All the materials used are in compliance with the international norms.
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of the SES
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
14.08 a meeting was conducted and observation of the site. Trainings and consultations were conducted with the local population. The site was identified as not having any impact on environment.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
VVVV. Reconstruction of buildings [ ] Yes [] No Look Section A below
WWWW. New small-scale construction []Yes [ ] No Look Section A below
XXXX. Individual system on cleaning of foul water
[]Yes [ ] No Look Section B below
YYYY. Historical building (s) and raions []Yes [ ] No Look Section C below
ZZZZ. Land acquisition34
[]Yes [ ] No Look Section D below
AAAAA. Dangerous or poisonous materials35
1> 36 <1
[]Yes [ ] No Look Section E below
BBBBB. Impact on forests and/or conservation zones
[]Yes [ ] No Look Section F below
CCCCC. Processing / liquidation of wastes [] Yes [ ] No Look Section G below
DDDDD. Movement and safety of the foot-passengers
[]Yes [ ] No Look Section H below
34
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
35 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, during the construction works is being fulfilled
(ooo) Local supervising body on construction and environment, as well as communities on the planned activities
(ppp) All the required permissive documents for construction and/or reconstruction are put into shape (qqq) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (rrr) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(sss) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(ttt) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(ooo) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(ppp) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(qqq) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(rrr) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(sss) There must not be any open construction wastes burning and household wastes on the site
(ttt) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (w) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(x) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d.
(ss) The wastes are collected in special containers in the established place (tt) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (uu) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (vv) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 22
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of water supply line in Chukurak village of Faizabad jamoat, Faizabad raion
3
Meetings with the jamoat population. Subproject site observation
Meeting with local specialists: ecologist, SES specialists, engineers and jamoat people
Protection of the spring zone. Chlorination of drinking water
No No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of water supply line in Chukurak village of Faizabad jamoat, Faizabad raion
Guarding the spring territory. Use of materials according to the standards (except asbestos)
No negative impact on environment
Chlorination of drinking water.
SUBPROJECT 23
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Project design is underway
Progress at the end of September 2012: Design by Design Institute 45 % done 2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Water Users Association and the population are willing to actively participate during the civil works
SUBPROJECT 23
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Construction of water supply line
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Construction of water supply line
Describe the site location
Fathobod village of Miskinobod jamoat, Faizabad raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Water users Association
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
Raion Sanitary-Epidemic Station is responsible for the quality of water. All the materials used are in compliance with the international norms and safe for use.
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of the SES
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
10.08 a meeting was conducted and observation of the site. Trainings and consultations were conducted with the local population. The site was identified as not having any impact on environment.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
EEEEE. Reconstruction of buildings [ ] Yes [] No Look Section A below
FFFFF. New small-scale construction []Yes [ ] No Look Section A below
GGGGG. Individual system on cleaning of foul water
[]Yes [ ] No Look Section B below
HHHHH. Historical building (s) and raions []Yes [ ] No Look Section C below
IIIII. Land acquisition37
[]Yes [ ] No Look Section D below
JJJJJ. Dangerous or poisonous materials38
1> 39 <1
[]Yes [ ] No Look Section E below
KKKKK. Impact on forests and/or conservation zones
[]Yes [ ] No Look Section F below
LLLLL. Processing / liquidation of wastes [] Yes [ ] No Look Section G below
MMMMM. Movement and safety of the foot-passengers
[]Yes [ ] No Look Section H below
37
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
38 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, during the construction works is being fulfilled
(uuu) Local supervising body on construction and environment, as well as communities on the planned activities
(vvv) All the required permissive documents for construction and/or reconstruction are put into shape (www) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (xxx) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(yyy) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(zzz) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(uuu) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(vvv) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(www) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(xxx) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(yyy) There must not be any open construction wastes burning and household wastes on the site
(zzz) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (y) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(z) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d.
(ww) The wastes are collected in special containers in the established place (xx) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (yy) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (zz) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova
SUBPROJECT 23
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of water supply line in Fathobod village of Miskinobod jamoat, Faizabad raion
3
Meetings with the jamoat population. Subproject site observation
Training on “clean water secures long life” with SES specialists
Chlorination of drinking water
No No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of water supply line in Fathobod village of Miskinobod jamoat, Faizabad raion.
Use of materials according to the standards. Water chlorination
No negative impact on environment.
Guarding the spring territory. Chlorination of drinking water.
SUBPROJECT 24
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Project design is underway
Progress at the end of September 2012: Design by Design Institute 45 % done 2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Water Users Association and the population are willing to actively participate during the civil works
SUBPROJECT 24
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Construction of water supply line
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Construction of water supply line
Describe the site location
Gulteppa village of Miskinobod jamoat, Faizabad raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Water users Association of Faizabad
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
Raion Sanitary-Epidemic Station is responsible for the quality of water. All the materials used are in compliance with the international norms and safe for use.
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of the SES.
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
10.09 a meeting was conducted and observation of the site. Trainings and consultations were conducted with the local population. The site was identified as not having any impact on environment.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
NNNNN. Reconstruction of buildings [ ] Yes [] No Look Section A below
OOOOO. New small-scale construction []Yes [ ] No Look Section A below
PPPPP. Individual system on cleaning of foul water
[]Yes [ ] No Look Section B below
QQQQQ. Historical building (s) and raions []Yes [ ] No Look Section C below
RRRRR. Land acquisition40
[]Yes [ ] No Look Section D below
SSSSS. Dangerous or poisonous materials41
1> 42 <1
[]Yes [ ] No Look Section E below
TTTTT. Impact on forests and/or conservation zones
[]Yes [ ] No Look Section F below
UUUUU. Processing / liquidation of wastes [] Yes [ ] No Look Section G below
VVVVV. Movement and safety of the foot-passengers
[]Yes [ ] No Look Section H below
40
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
41 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, during the construction works is being fulfilled
(aaaa) Local supervising body on construction and environment, as well as communities on the planned activities
(bbbb) All the required permissive documents for construction and/or reconstruction are put into shape (cccc) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (dddd) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(eeee) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(ffff) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(aaaa) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(bbbb) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(cccc) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(dddd) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(eeee) There must not be any open construction wastes burning and household wastes on the site
(ffff) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (aa) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(bb) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d.
(aaa) The wastes are collected in special containers in the established place (bbb) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (ccc) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (ddd) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 24
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of water supply line in Gulteppa village of Miskinobod jamoat, Faizabad raion
3
Meetings with the village population. Subproject site observation
Meeting with SES specialists
Chlorination and water quality identification
No No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of water supply line in Gulteppa village of Miskinobod jamoat, Faizabad raion
Chlorination of drinking water
No negative impact on environment
Drinking water testing by SES
SUBPROJECT 25
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Project design is underway
Progress at the end of September 2012: Design by Design Institute 45 % done 2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Water Users Association and the population are willing to actively participate during the civil works
SUBPROJECT 25
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Construction of water supply line
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Construction of water supply line
Describe the site location
Sultonobod village of Sultonobod jamoat, Rudaki raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Water users Association of Rudaki
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
Raion Sanitary-Epidemic Station is responsible for the quality of water. All the materials used are in compliance with the international norms and safe for use.
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of the SES
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
20.08 a meeting was conducted and observation of the site. Trainings and consultations were conducted with the local population. The site was identified as not having any impact on environment.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
WWWWW. Reconstruction of buildings [ ] Yes [] No Look Section A below
XXXXX. New small-scale construction []Yes [ ] No Look Section A below
YYYYY. Individual system on cleaning of foul water
[]Yes [ ] No Look Section B below
ZZZZZ. Historical building (s) and raions []Yes [ ] No Look Section C below
AAAAAA. Land acquisition43
[]Yes [ ] No Look Section D below
BBBBBB. Dangerous or poisonous materials44
1> 45 <1
[]Yes [ ] No Look Section E below
CCCCCC. Impact on forests and/or conservation zones
[]Yes [ ] No Look Section F below
DDDDDD. Processing / liquidation of wastes [] Yes [ ] No Look Section G below
EEEEEE. Movement and safety of the foot-passengers
[]Yes [ ] No Look Section H below
43
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
44 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, during the construction works is being fulfilled
(gggg) Local supervising body on construction and environment, as well as communities on the planned activities
(hhhh) All the required permissive documents for construction and/or reconstruction are put into shape (iiii) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (jjjj) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(kkkk) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(llll) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(gggg) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(hhhh) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(iiii) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(jjjj) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(kkkk) There must not be any open construction wastes burning and household wastes on the site
(llll) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (cc) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(dd) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d.
(eee) The wastes are collected in special containers in the established place (fff) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (ggg) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (hhh) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 25
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of water supply line in Sultonobod village of Sultonobod jamoat, Rudaki jamoat
5
Site observation, meeting with the population and local specialists
Meeting with SES workers and raion ecologist
Water quality identification (twice a year analysis by the SES)
No No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of water supply line in Sultonobod village of Sultonobod jamoat, Rudaki jamoat
Analysis and identification of water quality and chlorination
No negative impact on environment
Drinking water chlorination by the raion SES
SUBPROJECT 26
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Project design is underway
Progress at the end of September 2012: Design by Design Institute 45 % done 2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Water Users Association and the population are willing to actively participate during the civil works
SUBPROJECT 26
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Construction of water supply line
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Construction of water supply line
Describe the site location
Zafar-2 village of Choryakkoron jamoat, Rudaki raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Water users Association of Rudaki raion
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
Raion Sanitary-Epidemic Station is responsible for the quality of water. All the materials used are in compliance with the international norms and safe for use.
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of the SES
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
23.08 a meeting was conducted and observation of the site. Trainings and consultations were conducted with the local population. The site was identified as not having any impact on environment.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
FFFFFF. Reconstruction of buildings [ ] Yes [] No Look Section A below
GGGGGG. New small-scale construction []Yes [ ] No Look Section A below
HHHHHH. Individual system on cleaning of foul water
[]Yes [ ] No Look Section B below
IIIIII. Historical building (s) and raions []Yes [ ] No Look Section C below
JJJJJJ. Land acquisition46
[]Yes [ ] No Look Section D below
KKKKKK. Dangerous or poisonous materials47
1> 48 <1
[]Yes [ ] No Look Section E below
LLLLLL. Impact on forests and/or conservation zones
[]Yes [ ] No Look Section F below
MMMMMM. Processing / liquidation of wastes [] Yes [ ] No Look Section G below
NNNNNN. Movement and safety of the foot-passengers
[]Yes [ ] No Look Section H below
46
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
47 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, during the construction works is being fulfilled
(mmmm) Local supervising body on construction and environment, as well as communities on the planned activities
(nnnn) All the required permissive documents for construction and/or reconstruction are put into shape (oooo) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (pppp) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(qqqq) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(rrrr) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(mmmm)During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(nnnn) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(oooo) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(pppp) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(qqqq) There must not be any open construction wastes burning and household wastes on the site
(rrrr) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (ee) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(ff) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d.
(iii) The wastes are collected in special containers in the established place (jjj) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (kkk) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (lll) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 26
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of water supply line in Zafar village of Choryakkoron jamoat, Rudaki raion
3
Meeting with village and jamoat population, site observation.
Discussion on effective use of drinking water
Chlorination of drinking water
No No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of water supply line in Zafar-2 village of Choryakkoron jamoat, Rudaki raion
Use of materials according to the standards. Water chlorination.
No negative impact on environment
Chlorination and area protection
SUBPROJECT 27
Subproject construction status at the end of September 2012
1. Activity and progress:
Study of the project by PMU specialists.
Project design is underway
Progress at the end of September 2012: Design by Design Institute 45 % done 2. Change in project organization
None 3. Relations with contractors and other stakeholders:
Water Users Association and the population are willing to actively participate during the civil works
SUBPROJECT 27
PART 1: GENERAL INFORMATION ON THE PROJECT AND SITE
INSTITUTIONAL AND ADMINISTRATIVE
Country Tajikistan
Project name Construction of water supply line
Project scope and activities
Increase of agricultural incomes, decreasing soil erosion, improvement of technical skills and healthcare of the population, livestock and pasturelands conditions.
Institutional measures
(Name and contacts)
ADB (Team Leader), working
in the project,
Project Management
PMU
Local partner and/or receiving party of the Community, jamoat committee and
committee members.
Implementation mechanism
(Name and contacts)
Control on ensuring security measures
available
Control made by the local partner
Control made by the local supervising
body
Contractor
SITE DESCRIPTION
Name of the site Construction of water supply line
Describe the site location
Tojikobod village of Zaynabobod jamoat, Rudaki raion
Appendix 1: Site map [ ] Yes [ ] No [ + ]
Owner of the bridge Raion Water users Association
Description of geographical,
physical, biological, geological, hydrologic and social-economic
context
Location and distance to the
sources of materials, in particular fillers, water and stones?
Raion Sanitary-Epidemic Station is responsible for the quality of water. All the materials used are in compliance with the international norms and safe for use.
LEGISLATION
Identify national and local legislation and
permissive documents referring to the project activity
The documents package includes: Decrees of local authorities, ecologist’s conclusion, the State Committee on land management and geodesy conclusion, conclusion of the SES
CONSULTATIONS WITH THE COMMUNITY
Indicate when / where the
consultations with community took place
10.09 a meeting was conducted and observation of the site. Trainings and consultations were conducted with the local population. The site was identified as not having any impact on environment.
INSTITUTIONAL CAPACITY BUILDING
Will there be any activities on capacity
building?
[ ] no or [] yes, if «yes» the raion and jamoat administration will establish effective maintenance system, as well as conduct studies and trainings on effective use of the site by the population.
PART 2: INFORMATION ON SECURITY MEASURES
ECOLOGICAL / SOCIAL SCREENING
Will the activities on the site include/enable any of the following??
Activities Status Initiated activities
OOOOOO. Reconstruction of buildings [ ] Yes [] No Look Section A below
PPPPPP. New small-scale construction []Yes [ ] No Look Section A below
QQQQQQ. Individual system on cleaning of foul water
[]Yes [ ] No Look Section B below
RRRRRR. Historical building (s) and raions []Yes [ ] No Look Section C below
SSSSSS. Land acquisition49
[]Yes [ ] No Look Section D below
TTTTTT. Dangerous or poisonous materials50
1> 51 <1
[]Yes [ ] No Look Section E below
UUUUUU. Impact on forests and/or conservation zones
[]Yes [ ] No Look Section F below
VVVVVV. Processing / liquidation of wastes [] Yes [ ] No Look Section G below
WWWWWW. Movement and safety of the foot-passengers
[]Yes [ ] No Look Section H below
49
Land acquisition includes resettlement of people, change of livelihood, infringement of private property. This refers to land acquired / transferred and thus leads to suffering of the people, living on it and /or unauthorized settlers and/or those having business and on the acquired land.
50 Toxic / dangerous material includes, but is not limited with this list, asbestos, toxic paint, poisonous dissolvent, removal of lead from paint, etc.
PART 3: IMPACT MITIGATION MEASURES
ACTIVITY CHARACTERISTICS CONTROL TABLE ON IMPACT MITIGATION MEASURES
0. General conditions Conduct seminars for dissemination of recommendations: on safety measures, use of quality construction materials during the construction
Informing and ensuring safety of working
clauses a, b, c, d, e, during the construction works is being fulfilled
(ssss) Local supervising body on construction and environment, as well as communities on the planned activities
(tttt) All the required permissive documents for construction and/or reconstruction are put into shape (uuuu) The contractor officially agreed to implement all the works in safely manner with ensuring
corresponding discipline for impact minimization on nearby population and environment. (vvvv) Personal protection of workers comply with internationally accepted methods of work production
(constant use of helmets and if necessary, masks and safety spectacles, safety belts and safety footwear).
(wwww) Corresponding pointers on the site must inform workers on main rules and instructions that must be followed.
(xxxx) Temporary (for the period of fulfillment of repairing and construction works) fencing of the adjacent to the site territory.
A. General activities on reconstruction and/or construction are followed according to clauses: a,b,e,f.
Air quality is followed according to clauses:
c,d.
(ssss) During the internal works on demolition and dismantling of houses channels must be used for removal of construction wastes
(tttt) Systematic watering of adjacent territory for decrease of dust produced from works on demolition and dismantling
(uuuu) During the pneumatic drilling / dismantling of walls, the dust on the site must be constant water spraying
(vvvv) In the surrounding area (on sidewalks, roads) there should not be construction wastes, and minimum dust
(wwww) There must not be any open construction wastes burning and household wastes on the site
(xxxx) There must not be any unused construction vehicles on the site Noise, clauses
followed a,b (gg) The noise from the construction must be limited in time frames (working hours from 7.00 to 20.00)
(hh) During the works, cover of the engine generators, air compressors and other power mechanical equipment shall be closed and the equipment should be located as far from houses
Wastes liquidation All clauses are
followed: a,b,c,d.
(mmm) The wastes are collected in special containers in the established place (nnn) Upon the filling of containers, construction and household wastes must be transported in special
covered sanitation cars to the city dump, located in the west part of Dushanbe city (ooo) The reporting should be organized on the wastes liquidation as a proof for its corresponding
liquidation. (ppp) Every time, upon opportunity, the contractor must repeatedly use and process the corresponding
materials that can be used extensively (except asbestos)
PART 4: MONITORING PLAN
Stage
What
(Is there a necessity to control the
parameter?)
Where
(Is there a necessity to control the
parameter?)
How
(Is there a necessity to control the
parameter?)
When
(Identify the frequency / or continuity?)
Why
(Is the parameter
controlled?)
Cost
(If not included in the project
budget)
Who
(is responsible for control?)
Construction
Indicators identified by the interested parties for cost calculation and incomes or results.
Structural questionnaire, neutral evaluators, surveys conducted in certain time and monitoring, periodically conducted by the PMU staff
Monitoring is usually conducted as a long process during the whole duration of the project, while the evaluation is conducted in certain time, for instance, in the middle or after completion of the project
In order to prepare the progress reports for the Direction and evaluation of project results
Project Management personnel, community committees, local administration and sanitary department
Environmental Monitoring specialist: Sanginova S.
SUBPROJECT 27
Subproject environmental status at the end of September 2012
1. Environmental Management Plan and Activities
Subproject
Supervision and Audit
Activities Amendments
made Discrepancy notification
Corrected action plan
Consultation and complaints
Number
Type of visits
Construction of water supply line in Tojikobod village of Zaynabobod jamoat, Rudaki raion
4 Meeting with the village population, site observation
Meeting and training with the population on environmental issues
Chlorination and water quality identification by SES
No - No complaints
2. Status at the end of September 2012
Subproject Requirements Actions as of end
Sept 2012 Required
actions/comments
Construction of water supply line in Tojikobod village of Zaynabobod jamoat, Rudaki raion
Drinking water chlorination
No negative impact on environment
Chlorination and area protection.