Estimating | BOQs | Feasibility Studies | Life Cycle Costing | Post Contract Management | M&E
Cost Estimate Report
Lower Lee Flood Relief Scheme
Detailed cost estimate report based on the proposed Lower Lee Flood Relief Scheme as
published by OPW, Cork City Council & Cork County Council.
V1 – 25.04.2018
![Page 2: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/2.jpg)
Executive Summary The OPW have published a Capital Cost estimate of €108m for their preferred Flood Relief Scheme (FRS) option of walls and embankments for Cork City. MMC estimate that the published scheme will conservatively cost €204m to build and to extend the scheme to protect the Docklands would cost €295m. All figures relate to Capital Costs only and are exclusive of operation and maintenance costs.
The Stakeholder group, Save Cork City, engaged MMC Quantity Surveyors to produce a detailed cost estimate for the OPW ‘Walls Scheme’ and to provide an Order of Magnitude Cost for the longitudinal and vertical extension of the ‘Walls Scheme’ to provide a level of flood defence that would be comparable with a Tidal Barrier at Little Island – a significant portion of this cost will be in protecting the City and Tivoli Docklands.
On review of the OPW estimate, a clear disparity was observed between the level of detail on the published drawings and the published cost estimate breakdown. OPW cost estimates are aggregations of the proposals illustrated on the drawings, where several items are accounted for in a single rate. MMC have undertaken a more detailed cost estimate based on the published drawings – a detailed explanation of the methodology is included in this report.
MMC’s cost estimate indicates that the OPW Walls Scheme costs have been significantly underestimated by 61%. Applying the OPW cost estimation methodology to the revised estimate for the measured items would result in a Capital Cost Total of approximately €176m for the Walls Scheme. However, this methodology does not include Construction Tender Price Inflation which is considered critical for a Scheme which is programmed to be completed over a 10 year period. MMC have taken an inflation rate of 3% per annum and assumed an even distribution in expenditure over 10 years. MMC propose a more realistic estimate of the Capital Cost Total to be in excess of €204m.
The MMC estimate is based on the information provided in the OPW published drawings for the scheme. The 20% allowance in the OPW Methodology for ‘Unmeasured Items’ [‘Design Development’ in MMC Methodology] is considered conservative as there have been numerous subsequent changes to the published scheme which have a significant cost implication. These additions include inter-alia: the requirement for a groundwater pumping system; back-up generators for resilience to two pumping systems; cut limestone finish to walls; retrofit of flat deck bridges; etc. It is recommended that these decisions be reflected in revised drawings to facilitate the development of cost estimates.
The report of the Cork Docklands Development Forum (2008), chaired by G.T. Wrixon, estimates that flood protection to the City Docks alone would cost the exchequer €47m. MMC estimates that flood protection to Tivoli Docks would cost an additional €39m. By including an allowance of just €5m for future raising of walls in line with sea level rises, the total cost of flood protection to the City under the Walls Scheme would be approximately €295m. The cost of flood protection to areas identified by the OPW at risk of coastal flooding – the Jack Lynch Tunnel, parts of Mahon, Rochestown, Douglas etc are not included in the report and would see the figure exceed €300m. It is noted that HR Wallingford and TU Delft have estimated the capital cost of a tidal barrier at Little Island at €140m and €187m respectively.
This report does not provide a Quantitative Assessment of the disruption to transport and commerce in the City Centre for the duration of the works. An Economic Impact Assessment of the OPW Walls scheme is recommended to provide a true cost comparison with the Tidal Barrier option. It is noted that the OPW Project Team similarly underestimated the nearby Douglas FRS at €6.8m, significantly lower than the publicised tender price of €13m, and that the cost estimate for Walls and Embankments proposed for Cork City is significantly lower than the cost per km on projects previously delivered by the OPW.
![Page 3: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/3.jpg)
1
Table of Contents
1.0. Background ................................................................................................................................. 2
2.0. Observations on the OPW Cost Estimates ................................................................................... 2
3.0. MMC Cost Estimate Methodology .............................................................................................. 2
3.1. Design Information .................................................................................................................. 2
3.2. Measurement .......................................................................................................................... 2
3.3. Quantifying Cost ...................................................................................................................... 4
4.0. OPW/ MMC Cost Estimate Comparative ..................................................................................... 8
5.0. Design Development/ Contingency ............................................................................................. 9
6.0. Archaeology & Environment ..................................................................................................... 10
7.0. Construction Inflation ................................................................................................................ 10
8.0. Raising Walls .............................................................................................................................. 10
9.0. Docklands Flood Protection ....................................................................................................... 10
10.0. References ............................................................................................................................. 12
10.1. Works Cited ....................................................................................................................... 12
Table of Figures
Figure 1: Measurement Take-Off Example .............................................................................................. 3
Figure 2: Schedule of Work (LL_201) ....................................................................................................... 4
Figure 3: Rate Breakdown Example ......................................................................................................... 5
Figure 4: Embankment Sectional Drawing (UWW-1) .............................................................................. 5
Figure 5: Rated Schedule of Work (LL_201) ............................................................................................ 6
Figure 6: Cost Estimate Summary - Proposed Construction Work .......................................................... 7
Figure 7: OPW/ MMC Cost Estimate Comparison (OPW Methodology) ................................................. 8
Figure 8: OPW / MMC Estimate Cost Comparison (MMC Methodology) ................................................ 9
Figure 9: City Centre, North, South & Tivoli Docks Flood Relief Costs ................................................... 11
![Page 4: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/4.jpg)
2
1.0. Background
MMC Quantity Surveyors (MMC) have been engaged by the group Save Cork City to review the cost
estimate prepared on behalf of the office of Public Works (OPW) for a proposed scheme involving
walls, embankments, pumping systems and demountable barriers (the walls scheme) to provide flood
relief to Cork City Centre.
2.0. Observations on the OPW Cost Estimates
On review of the OPW’s estimate, MMC found that there was a disparity between the level of detail
on the drawings and the detail on the estimate.
The items in the OPW report seemed to be aggregations of the work shown on the drawings where
several items of work are accounted for in a single rate.
One of the main items of difference is the rate for the pumping chambers. In the OPW’s estimate,
there is €75,000 allowance per chamber.
MMC have based their estimate on an actual pump chamber design (included in the detailed report)
and includes for sheet piling, excavation, concrete work, services diversions, mechanical and electrical
allowances for pumping. It does not include for a filter drain network. The total cost estimated per
chamber is €381,000. This results in a net difference of €14.4m on this item alone.
3.0. MMC Cost Estimate Methodology
3.1. Design Information
MMC completed their detailed cost estimate based on the drawings made publicly available on the
OPW Lower Lee Flood Relief Scheme website, see references section (OPW, 2017).
The set of drawings are split into 6 series. Series 2 (proposed plans) and Series 3 (proposed sections)
were mainly used for extracting quantities of the proposed work elements, while the remain series
were used for reference.
3.2. Measurement
A detailed quantity take-off was completed on each Series 2 plan drawing for all proposed work at
that location, see below example of this process. Figure 1 illustrates extracted quantities from
drawing ref. LL_201, such as flood embankments, grounds to be regraded and new storm water
drainage.
![Page 5: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/5.jpg)
3
Figure 1: Measurement Take-Off Example
These quantities were then carried forward to a workbook, creating a schedule of work, see Figure 2.
This schedule of work lists all works deemed necessary to complete the proposed design.
![Page 6: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/6.jpg)
4
Figure 2: Schedule of Work (LL_201)
3.3. Quantifying Cost
The next stage of the cost estimate was to apply rates to the schedule of work. These rates were
developed by assembling all labour, material and plant costs associated with each individual item of
work. Figure 3 shows an example a rate breakdown. In this example, the rate breakdown shows costs
![Page 7: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/7.jpg)
5
associated with constructing a 17.00m wide flood defence embankment, as per Figure 2 work
schedule item 1.2, see Figure 4 for sectional drawing of this work item.
Figure 3: Rate Breakdown Example
Figure 4: Embankment Sectional Drawing (UWW-1)
The letter reference shown in ‘Column A’ of Figure 3 refers to labour (L), material (M) and plant (P).
‘Column C’ calculates the quantity of each work element required per linear meter, see below
example.
Cell C:1 (15m3)
= 17m wide x 0.90m high (average between highest point 1.80m, and lowest point 0.00m
high) = 15.00m3
Rates included in ‘Column E’ were ascertained using Spon’s Civil Engineering and Highway Works Price
Book, 2018 (AECOM, 2018), and benchmarked with market rates from current projects. ‘Column F’
factors waste allowance on certain material items. These rates are exclusive of contractors profit, 8%
profit margin has been across rates.
Similar rate calculations were completed for all work schedule items and applied accordingly to
provide a total cost per Series 2 plan drawing, see Figure 5.
![Page 8: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/8.jpg)
6
Figure 5: Rated Schedule of Work (LL_201)
This process was repeated for all Series 2 plan drawings, each combining to form the total estimated
cost for proposed construction works, Figure 6.
![Page 9: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/9.jpg)
7
Figure 6: Cost Estimate Summary - Proposed Construction Work
![Page 10: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/10.jpg)
8
4.0. OPW/ MMC Cost Estimate Comparative
MMC’s cost estimate indicates that the walls scheme costs have been significantly underestimated. The measured items quantified in the OPW Options Report total €49,451,108. MMC’s cost estimate, based on the same proposed drawings, result in a comparison total of €81,097,622, an approximate increase of 61%. Figure 7 presents a comparison of projected costs for delivering the walls scheme using the OPW methodology (ARUP, 2017), table 16: Summary of Costs, Section 13.2, page 158
Figure 7: OPW/ MMC Cost Estimate Comparison (OPW Methodology)
This comparison shows cost estimate variances on a like-for-like basis following the OPW’s
methodology, however, the percentage allowances for items outside measured works are extremely
optimistic. Figure 8 presents a more realistic estimate of project capital costs. The rationale for these
alterations are explained further in the following sections of this report.
OPW Options Report Estimate MMC Cost Estimate
Ref. Description Total € Total €
1.0 Measured Items 49,451,108 81,097,622
2.0 Preliminaries (17.5%) 8,653,944 14,192,084
3.0 Unmeasured Items (20%) 9,890,222 16,219,524
4.0 Sub-Total 67,995,274 111,509,230
5.0 Archaeology & Environmental (10%) 6,799,527 11,150,923
6.0 Basel ine Construction Cost Total 74,794,801 122,660,153
7.0 Contingency/ Optimisim Bias (20%) 14,958,960 24,532,031
8.0 Construction Cost Total 89,753,761 147,192,184
9.0 Fees & Supervision (9%) 8,077,838 13,247,297
10.0 Construction & Fees Total 97,831,600 160,439,480
11.0 Land Acquisition (10%) 8,975,376 14,719,218
12.0 Art (1% cap at €64,000) 64,000 64,000
13.0 Site Investigation & Surveys 1,200,000 1,200,000
14.0 Capital Cost Total 108,070,976 176,422,699
![Page 11: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/11.jpg)
9
Figure 8: OPW / MMC Estimate Cost Comparison (MMC Methodology)
5.0. Design Development/ Contingency
Both OPW & MMC’s cost estimates are limited by the lack of detail contained within the published
proposal. The 20% provisional allowance for ‘unmeasured work’ as outlined in the OPW’s estimate
can be seen as extremely optimistic given the requirement to make provision for inter alia the
following project elements:
(i.) The proposal as bridge locations: There is a suggestion that there will be walls
constructed between footpaths and carriageway on flat deck bridges with demountable
barriers erected at footpaths.
(ii.) The extent of the back-of-wall drainage network including non-return valve chambers.
(iii.) The relocation of existing services at areas of proposed work.
(iv.) The make-up of the groundwater pumping system, outlined as a necessity in the OPW
Supplementary Report (ARUP, 2017).
(v.) A network of back-up generators with associated ducting and cabling to the pump
chambers. OPW agents have indicated that this is the preferred method to protect
against coincidental flood & power outage as a result of a storm event (ARUP, 2017).
The OPW’s 20% allowance for unmeasured works and 20% allowance for contingency / optimistic bias
remains in MMC’s estimate methodology, renamed as design development & unforeseen item
contingencies.
OPW Options Report Estimate MMC Cost Estimate
Ref. Description Total € Total €
1.0 Measured Items 49,451,108 81,097,622
2.0 Preliminaries (20%) 9,890,222 16,219,524
3.0 Design Development (20%) 11,868,266 19,463,429
3.0 Unforeseen Items Contingency (20%) 14,241,919 23,356,115
3.0 Tender Price Inflation (3% P.A.) 8,939,750 14,660,793
4.0 Sub-Total 94,391,265 154,797,484
5.0 Archaeology & Environmental Risk (15%) 14,158,690 23,219,623
6.0 Construction Cost Total 108,549,954 178,017,107
9.0 Fees & Supervision (9%) 9,769,496 16,021,540
10.0 Construction & Fees Total 118,319,450 194,038,646
11.0 Land Acquisition 9,000,000 9,000,000
12.0 Art (1% cap at €64,000) 64,000 64,000
13.0 Site Investigation & Surveys 1,200,000 1,200,000
14.0 Capital Cost Total 128,583,450 204,302,646
![Page 12: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/12.jpg)
1
0
6.0. Archaeology & Environment
Similarly, the allowance for archaeology and environmental impact can be seen as very optimistic due
to the river bank location in one of Ireland’s oldest cities.
An allowance for traffic management would be recommended given the rolling closure of city centre
quay roadways and bridges necessitated to accommodate proposed works.
It is for these reasons that MMC have increased the OPW’s 10% allowance for archaeology and
environment to 15%.
7.0. Construction Inflation
As the projected project programme is indicated to take up to 10 years to complete, an allowance of
construction tender price inflation would also be required. MMC have split the estimated
construction costs evenly over the 10 years and have allowed 3% inflation per annum.
8.0. Raising Walls
The OPW’s plan envisages the raising of the walls by 1.00m in the event of rising sea and flood levels.
While there are many technical and political challenges to realising this plan, they have not been
addressed here.
We have assessed a €5m figure based on 15km of walls at €200/m plus contingency, preliminaries
and fees.
9.0. Docklands Flood Protection
The project extends from the Lee Fields, west of the city centre, to the downstream confluence of the
North and South Channels of the River Lee at the Customs House and Bonded Warehouses, however,
there are also further flood defence works that will need to be completed to keep Cork City flood
free.
The planned redevelopment of Cork Docklands will also require substantial flood protection and
mitigation. The report of the Cork Docklands Development Forum, chaired by G.T. Wrixon, estimates
that the cost of flood walls and embankments to protect the City Docklands would cost the exchequer
€47m (Cork Docklands Development Forum, 2008), based on figures supplied by the Cork City
Council.
It is also noted that Cork City Council are developing a Local Area Plan for the Tivoli Docklands in light
of the planned relocation of Port of Cork activities to Ringaskiddy. Assuming the 61.5 hectare
![Page 13: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/13.jpg)
1
1
(615,000m2) site is raised a conservative 1.80m for flood protection, using imported hardcore fill, this
would incur costs of approximately €39m (615,000m2 x 1.80m x €35/m3 fill).
Figure 9 shows these costs in addition to the proposed Lower Lee Flood Relief Scheme, to present a
total flood relief cost for the City Centre, North, South & Tivoli Docks.
Figure 9: City Centre, North, South & Tivoli Docks Flood Relief Costs
These costs do not include for tidal flood protection to Douglas, Jacob’s Island, Rochestown or Harty’s
Quay, which would be provided by an alternative flood defence strategy.
OPW Options Report Estimate MMC Cost Estimate
Ref. Description Total € Total €
1.0 Measured Items 49,451,108 81,097,622
2.0 Preliminaries (20%) 9,890,222 16,219,524
3.0 Design Development (20%) 11,868,266 19,463,429
3.0 Unforeseen Items Contingency (20%) 14,241,919 23,356,115
3.0 Tender Price Inflation (3% P.A.) 8,939,750 14,660,793
4.0 Sub-Total 94,391,265 154,797,484
5.0 Archaeology & Environmental Risk (15%) 14,158,690 23,219,623
6.0 Construction Cost Total 108,549,954 178,017,107
9.0 Fees & Supervision (9%) 9,769,496 16,021,540
10.0 Construction & Fees Total 118,319,450 194,038,646
11.0 Land Acquisition 9,000,000 9,000,000
12.0 Art (1% cap at €64,000) 64,000 64,000
13.0 Site Investigation & Surveys 1,200,000 1,200,000
14.0 Capital Cost Total 128,583,450 204,302,646
15.0 Flood Protection of South Docks 47,000,000 47,000,000
16.0 Flood Protection of Tivoli Docks 39,000,000 39,000,000
17.0 Raise Level of Walls 1.00m 5,000,000 5,000,000
18.0Total Capital Cost: City Centre,
North, South & Tivol i Docks219,583,450 295,302,646
![Page 14: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/14.jpg)
1
2
10.0. References
10.1. Works Cited
AECOM. (2018). Spon's Civil Engineering and Highway Works Pricebook. Oxford: CRC Press.
ARUP. (2017). Lower Lee (Cork City) Drainage Scheme - Options Report (4.04.03-05). Cork: OPW.
Cork Docklands Development Forum. (2008). Publications: housing.gov.ie. Retrieved from Department
of Housing, Planning and Local Government Website:
http://www.housing.gov.ie/sites/default/files/migrated-
files/en/Publications/DevelopmentandHousing/Planning/FileDownLoad%2C25187%2Cen.pdf
OPW. (2017, January 20). Index of Assets / Lee Valley / Documents. Retrieved from Lower Lee (Cork
City) Flood Relief Scheme Web Site:
http://www.lowerleefrs.ie/assets/lee_valley/docs/LL%20Full%20Drawing%20Set%20Final.pdf
![Page 15: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/15.jpg)
Estimating | BOQs | Feasibility Studies | Life Cycle Costing | Post Contract Management | M&E
Detailed Cost Estimate
Lower Lee Flood Relief Scheme
Detailed cost estimate based on the proposed Lower Lee Flood Relief Scheme as published by OPW, Cork City Council & Cork County Council.
V1 – 18.04.2018
![Page 16: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/16.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Total
LOWER LEE FLOOD RELIEF: CONSTRUCTION COSTS
DWG. REF;
1 LL_201 806,980.50
2 LL_202 856,102.67
3 LL_203 1,167,947.58
4 LL_204 57,834.00
5 LL_205 683,331.84
6 LL_206 2,642,401.84
7 LL_207 1,056,753.01
8 LL_208 688,306.22
9 LL_209 687,473.22
10 LL_210 851,083.42
11 LL_211 485,470.01
12 LL_212 1,375,868.36
13 LL_213 2,306,757.19
14 LL_214 6,145,460.50
15 LL_215 4,343,892.74
16 LL_216 3,535,417.79
17 LL_217 2,931,820.03
18 LL_218 6,172,496.52
19 LL_219 6,266,024.84
20 LL_220 (a & b) 3,928,545.28
21 LL_221 880,200.00
22 LL_222 4,713,310.29
23 LL_223 1,099,827.90
24 LL_224 4,490,405.18
25 LL_225 9,039,864.70
26 LL_226 (a & b) 7,349,582.56
27 LL_227 4,449,288.81
28 LL_228 2,085,174.80
TOTAL: CONSTRUCTION WORK 81,097,621.79
To Collection 162,195,244
18/04/2018 15:25:54 MMC Quantity Surveyors Page 1 of 2
![Page 17: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/17.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Total
29 PRELIMINARIES @ 20% 16,219,524.36
30 DESIGN DEVELOPMENT CONTINGENCY @ 20% 19,463,429.23
31 UNFORSEEN ITEMS CONTINGENCY @20% 23,356,115.08
32 TENDER PRICE INFLATION @3% PA 14,660,793.00
33 ARCHAEOLOGY & ENVIRONMENTAL RISK @ 15% 23,219,622.52
34 FEES & SUPERVISION @ 9% 16,021,539.54
35 LAND ACQUISITION 9,000,000.00
36 ART (1% CAP @ €64,000) 64,000.00
37 SITE INVESTIGATION 1,200,000.00
TOTAL: CAPITAL COST (LOWER LEE) 204,302,645.51
38 FLOOD PROTECTION OF SOUTH DOCKS 47,000,000.00
39 FLOOD PROTECTION OF TIVOLI DOCKS 39,000,000.00
40 RAISE LEVEL OF WALLS 1.00M 5,000,000.00
TOTAL: CAPITAL COST (LOWER LEE, NORTH & SOUTH DOCKS, TIVOLI DOCKS) 295,302,645.51
To Collection 713,810,315
18/04/2018 15:25:54 MMC Quantity Surveyors Page 2 of 2
![Page 18: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/18.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_201
LL_201
Demolition & Alterations;
1.1 Relocate existing shed 1.00 nr 648.00 648.00
Flood defence;
1.2 Flood defence embankment; 17.00m wide; 1.80m high (typical) 486.29 m 622.95 302,935.80
1.3 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
486.29 m 81.87 39,810.69
Drainage;
1.4 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
485.34 m 39.42 19,132.10
1.5 Extra over above for non‐return vlaves; provisional quantity 25 nr 1,350.00 33,750.00
1.6 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 1.00 nr 3,672.00 3,672.00
1.7 Pumping station 1.00 nr 381,040.72 381,040.72
1.8 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
26.51 m 56.43 1,495.96
Regrading ground levels;
1.9 Vehicle access ramp 275.71 m2 88.84 24,495.23
To Summary: 806,980
18/04/2018 MMC Quantity Surveyors Page 1 of 48
![Page 19: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/19.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_202
LL_202
Demolition & Alterations;
2.1 Existing acces to be extinguished 1.00 nr 540.00 540.00
Flood defence;
2.2 Flood defence embankment; 20.00m wide; 2.00m high (typical) 472.32 m 799.63 377,682.19
2.3 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
472.32 m 81.87 38,667.02
Drainage;
2.4 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
499.26 m 39.42 19,680.83
2.5 Extra over above for non‐return vlaves; provisional quantity 25 nr 1,350.00 33,750.00
2.6 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 1.00 nr 3,672.00 3,672.00
2.7 Pumping station 1.00 nr 381,040.72 381,040.72
2.8 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
18.96 m 56.43 1,069.91
To Summary: 856,103
18/04/2018 MMC Quantity Surveyors Page 2 of 48
![Page 20: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/20.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_203
LL_203
Flood defence;
3.1 Flood defence embankment; 17.00m wide; 2.00m high (typical) 864.74 m 679.69 587,752.71
3.2 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
864.74 m 81.87 70,792.94
Drainage;
3.3 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
882.92 m 39.42 34,804.71
3.4 Extra over above for non‐return vlaves; provisional quantity 30 nr 1,350.00 40,500.00
3.5 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 1.00 nr 3,672.00 3,672.00
3.6 Pumping station 1.00 nr 381,040.72 381,040.72
3.7 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
46.91 m 56.43 2,647.13
Regrading ground levels;
3.8 Vehicle access ramp 526.06 m2 88.84 46,737.37
To Summary: 1,167,948
18/04/2018 MMC Quantity Surveyors Page 3 of 48
![Page 21: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/21.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_204
LL_204
Flood defence;
4.1 Flood defence embankment; 8.00m wide; 0.80m high (typical) 68.44 m 205.59 14,070.51
4.2 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
68.44 m 81.87 5,602.92
Drainage
4.3 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
68.44 m 39.42 2,697.90
4.4 Extra over above for non‐return vlaves; assumed at every 20m 5 nr 1,350.00 6,750.00
Regrading ground levels;
4.5 Vehicle access ramp 323.18 m2 88.84 28,712.66
To Summary: 57,834
18/04/2018 MMC Quantity Surveyors Page 4 of 48
![Page 22: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/22.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_205
LL_205
Flood defence;
5.1 Flood defence embankment; 18.00m wide; 2.00m high (typical) 330.93 m 670.27 221,813.03
5.2 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
330.93 m 81.87 27,091.97
Drainage;
5.3 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
330.93 m 39.42 13,045.26
5.4 Extra over above for non‐return vlaves; provisional quantity 25 nr 1,350.00 33,750.00
5.5 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 1.00 nr 3,672.00 3,672.00
5.6 Pumping station 1.00 nr 381,040.72 381,040.72
5.7 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
21.60 m 56.43 1,218.89
5.8 Concrete pipe culvert; 0.9m diam.; constructed under proposedembankment; to tie into existing culvert
19.55 m 86.96 1,699.97
To Summary: 683,332
18/04/2018 MMC Quantity Surveyors Page 5 of 48
![Page 23: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/23.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_206
LL_206
Flood defence;
6.1 Flood defence wall; sheet pile wall and capping beam; avg height 1.50mabove ground level
395.87 m 3,353.40 1,327,510.46
6.2 Limestone cladding to wet side of flood defence wall 791.74 m2 324.00 256,523.76
6.3 Limestone cladding to dry side of flood defence wall 475.04 m2 237.60 112,870.45
Drainage;
6.4 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
395.87 m 39.42 15,605.20
6.5 Extra over above for non‐return vlaves; assumed at every 20m 30 nr 1,350.00 40,500.00
6.6 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 2.00 nr 3,672.00 7,344.00
6.7 Pumping station 2.00 nr 381,040.72 762,081.44
6.8 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
6.55 m 56.43 369.62
6.9 Concrete pipe culvert; 0.9m diam.; constructed under proposedembankment; to tie into existing culvert
25.05 m 86.96 2,178.23
Regrading ground levels;
6.10 Regrading; existing garden 941.60 m2 5.30 4,987.01
6.11 Regrading; existing pavement 962.46 m2 54.72 52,667.85
To Summary: 2,582,638
18/04/2018 MMC Quantity Surveyors Page 6 of 48
![Page 24: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/24.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_206 (Continued)
6.12 Reclaimed land; avg. 4.00m deep 503.09 m2 118.79 59,763.83
To Summary: 59,764
18/04/2018 MMC Quantity Surveyors Page 7 of 48
![Page 25: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/25.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_207
LL_207
Flood defence;
7.1 Flood defence embankment; 13.00m wide; 1.20m high (typical) 221.56 m 366.63 81,231.16
7.2 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
221.56 m 81.87 18,138.27
7.3 Flood defence wall; sheet pile wall and capping beam; avg height 1.50mabove ground level
117.55 m 3,353.40 394,192.17
7.4 Limestone cladding to wet side of flood defence wall 235.10 m2 324.00 76,172.40
7.5 Limestone cladding to dry side of flood defence wall 141.06 m2 237.60 33,515.86
Drainage;
7.6 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
340.00 m 39.42 13,402.80
7.7 Extra over above for non‐return vlaves; provisional quantity 10 nr 1,350.00 13,500.00
7.8 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 1.00 nr 3,672.00 3,672.00
7.9 Pumping station 1.00 nr 381,040.72 381,040.72
7.10 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
3.51 m 56.43 198.07
Regrading ground levels;
7.11 Regrading; existing road 374.08 m2 110.44 41,314.96
To Summary: 1,056,378
18/04/2018 MMC Quantity Surveyors Page 8 of 48
![Page 26: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/26.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_207 (Continued)
7.12 Regrading; existing garden 70.73 m2 5.30 374.61
To Summary: 375
18/04/2018 MMC Quantity Surveyors Page 9 of 48
![Page 27: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/27.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_208
LL_208
Demolition & Alterations;
8.1 Existing acces to be extinguished 1.00 nr 540.00 540.00
Flood defence;
8.2 Flood defence embankment; 13.00m wide; 1.00m high (typical) 648.46 m 323.25 209,613.26
8.3 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
648.46 m 81.87 53,086.93
Drainage;
8.4 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
653.11 m 39.42 25,745.60
8.5 Extra over above for non‐return vlaves; provisional quantity 10 nr 1,350.00 13,500.00
8.6 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 1.00 nr 3,672.00 3,672.00
8.7 Pumping station 1.00 nr 381,040.72 381,040.72
8.8 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
19.63 m 56.43 1,107.72
To Summary: 688,306
18/04/2018 MMC Quantity Surveyors Page 10 of 48
![Page 28: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/28.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_209
LL_209
Flood defence;
9.1 Flood defence embankment; 13.00m wide; 1.60m high (typical) 460.26 m 453.40 208,683.17
9.2 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
460.26 m 81.87 37,679.72
Drainage;
9.3 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
482.48 m 39.42 19,019.36
9.4 Extra over above for non‐return vlaves; provisional quantity 5 nr 1,350.00 6,750.00
9.5 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 1.00 nr 3,672.00 3,672.00
9.6 Pumping station 1.00 nr 381,040.72 381,040.72
9.7 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
31.38 m 56.43 1,770.77
Regrading ground levels;
9.8 Vehicle access ramp 324.81 m2 88.84 28,857.48
To Summary: 687,473
18/04/2018 MMC Quantity Surveyors Page 11 of 48
![Page 29: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/29.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_210
LL_210
Demolition & Alterations;
10.1 Remove existing footpath; dispose off‐site 130.00 m 59.94 7,792.20
10.2 Existing acces to be extinguished 1.00 nr 540.00 540.00
Flood defence;
10.3 Flood defence embankment; 15.00m wide; 1.80m high (typical) 532.95 m 561.57 299,289.47
10.4 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
532.95 m 81.87 43,630.57
Drainage;
10.5 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
532.95 m 39.42 21,008.89
10.6 Extra over above for non‐return vlaves; provisional quantity 10 nr 1,350.00 13,500.00
10.7 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 1.00 nr 3,672.00 3,672.00
10.8 Pumping station 1.00 nr 381,040.72 381,040.72
10.9 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
22.50 m 56.43 1,269.68
Regrading ground levels;
10.10 Vehicle access ramp 332.68 m2 88.84 29,556.68
10.11 Pedestrian walkway 1,033.31 m2 48.18 49,783.22
To Summary: 851,083
18/04/2018 MMC Quantity Surveyors Page 12 of 48
![Page 30: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/30.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_211
LL_211
Demolition & Alterations;
11.1 Existing acces to be extinguished 1.00 nr 540.00 540.00
Flood defence;
11.2 Flood defence embankment; 15.00m wide; 1.80m high (typical) 475.64 m 561.57 267,105.81
11.3 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
475.64 m 81.87 38,938.82
Drainage;
11.4 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
475.64 m 39.42 18,749.73
11.5 Extra over above for non‐return vlaves; provisional quantity 20 nr 1,350.00 27,000.00
Regrading ground levels;
11.6 Vehicle access ramp 300.07 m2 88.84 26,659.47
11.7 Pedestrian walkway 2,210.04 m2 48.18 106,476.18
To Summary: 485,470
18/04/2018 MMC Quantity Surveyors Page 13 of 48
![Page 31: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/31.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_212
LL_212
Flood defence;
12.1 Flood defence embankment; 17.00m wide; 1.60m high (typical) 391.00 m 566.22 221,391.52
12.2 Flood defence embankment; 12.00m wide; 0.90m high (typical) 104.00 m 285.03 29,643.31
12.3 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
493.19 m 81.87 40,375.57
12.4 Flood defence wall; reinforced concrete retaining wall at Lee Road; avgheight 2.00m
82.49 m 1,409.40 116,261.41
12.5 Limestone cladding to both sides of retaining wall at lee road 248.00 m2 324.00 80,352.00
12.6 Flood defence wall; reinforced concrete wall and capping beam; avg height1.00m above ground level
150.42 m 761.40 114,529.79
12.7 Limestone cladding to both sides of flood defence wall 300.84 m2 324.00 97,472.16
Drainage;
12.8 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
644.00 m 39.42 25,386.48
12.9 Extra over above for non‐return vlaves; provisional quantity 30 nr 1,350.00 40,500.00
12.10 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 1.00 nr 3,672.00 3,672.00
12.11 Pumping station 1.00 nr 381,040.72 381,040.72
12.12 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
38.31 m 56.43 2,161.83
To Summary: 1,152,787
18/04/2018 MMC Quantity Surveyors Page 14 of 48
![Page 32: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/32.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_212 (Continued)
Regrading ground levels;
12.13 Regrading; existing road 858.00 m2 110.44 94,761.10
12.14 Pedestrian walkway 2,622.00 m2 48.18 126,323.75
12.15 Regrading; existing lanscaping at proposed flood wall 377.00 m2 5.30 1,996.71
To Summary: 223,082
18/04/2018 MMC Quantity Surveyors Page 15 of 48
![Page 33: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/33.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_213
LL_213
Demolitions & alterations;
13.1 Remove existing footpath; dispose off‐site 62.00 m 59.94 3,716.28
13.2 Replace existing sluice gate at waterworks intake 1.00 Item 10,000.00 10,000.00
Flood defence;
13.3 Flood defence embankment; 11.00m wide; 1.00m high (typical) 417.00 m 284.55 118,656.12
13.4 Flood defence embankment; 20.00m wide; 2.00m high (typical) 304.00 m 784.32 238,434.19
13.5 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
721.00 m 81.87 59,025.50
13.6 Flood defence wall; reinforced concrete wall and capping beam; avg height3.00m above ground level
134.00 m 2,057.40 275,691.60
13.7 Flood defence wall; reinforced concrete wall and capping beam; avg height1.00m above ground level
282.00 m 761.40 214,714.80
13.8 Limestone cladding to both sides of flood defence wall 564.00 m2 324.00 182,736.00
13.9 Glass railing; 1.20m high 95.00 m 2,160.00 205,200.00
Drainage;
13.10 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
1,174.00 m 39.42 46,279.08
13.11 Extra over above for non‐return vlaves; provisional quantity 50 nr 1,350.00 67,500.00
To Summary: 1,421,954
18/04/2018 MMC Quantity Surveyors Page 16 of 48
![Page 34: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/34.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_213 (Continued)
13.12 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 2.00 nr 3,672.00 7,344.00
13.13 Pumping station 2.00 nr 381,040.72 762,081.44
13.14 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
19.16 m 56.43 1,081.20
13.15 Concrete pipe culvert; 0.9m diam.; constructed under proposedembankment; to tie into existing culvert
21.19 m 86.96 1,842.58
Regrading ground levels;
13.16 Pedestrian walkway/ vehicle access 501.36 m2 88.84 44,542.92
13.17 Regrading; roads at proposed flood wall (at Lee Road) 469.00 m2 110.44 51,798.32
13.18 Regrading; pedestrian walkway at proposed flood wall 283.00 m2 48.18 13,634.49
13.19 Regrading; existing lanscaping at proposed flood wall 468.00 m2 5.30 2,478.68
To Summary: 884,804
18/04/2018 MMC Quantity Surveyors Page 17 of 48
![Page 35: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/35.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_214
LL_214
Demolitions & alterations;
14.1 Demolish existing foot bridge 1.00 Item 48,600.00 48,600.00
14.2 Demolish existing kerb & railing (CIW_L02) 61.00 m 54.00 3,294.00
14.3 Demolish existing steps (UWW_G07 & G08)) 2.00 nr 1,620.00 3,240.00
14.4 Existing acces to be extinguished 1.00 nr 540.00 540.00
Flood defence;
14.5 Flood defence embankment; 20.00m wide; 2.00m high (typical) 111.05 m 784.32 87,099.07
14.6 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
111.05 m 81.87 9,091.24
14.7 Flood defence wall; sheet pile wall and capping beam; avg height 1.50mabove ground level
141.00 m 3,353.40 472,829.40
14.8 Limestone cladding to both sides of sheet pile flood defence wall 555.00 m2 324.00 179,820.00
14.9 Flood defence wall; reinforced concrete wall and capping beam; avg height3.00m above ground level
225.00 m 1,409.40 317,115.00
14.10 Flood defence wall; reinforced concrete wall and capping beam; avg height2.00m above ground level
418.00 m 1,409.40 589,129.20
14.11 Flood defence wall; reinforced concrete wall and capping beam; avg height1.00m above ground level
110.00 m 761.40 83,754.00
14.12 Limestone cladding to both sides of concrete flood defence wall 2,182.00 m2 324.00 706,968.00
To Summary: 2,501,480
18/04/2018 MMC Quantity Surveyors Page 18 of 48
![Page 36: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/36.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_214 (Continued)
14.13 Flood defence wall; reinforced concrete wall with textured concrete finish;avg height 2.50m
135.00 m 1,814.40 244,944.00
14.14 Railing; 1.20m high 264.00 m 702.00 185,328.00
14.15 Glass railing; 1.20m high 110.00 m 2,160.00 237,600.00
14.16 Steel flood wall (NNC_L14) approx. 22m 22.00 m 378.00 8,316.00
Drainage;
14.17 New storm drainage 939.00 m 205.20 192,682.80
14.18 Extra over above for non‐return vlaves; provisional quantity 50 nr 1,350.00 67,500.00
14.19 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 2.00 nr 3,672.00 7,344.00
14.20 Pumping station 2.00 nr 381,040.72 762,081.44
14.21 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
19.16 m 56.43 1,081.20
Regrading ground levels;
14.22 Pedestrian walkway/ vehicle access 2,801.00 m2 88.84 248,852.53
14.23 Regrading; pedestrian walkway at proposed flood wall 871.00 m2 48.18 41,963.38
14.24 Regrading; existing lanscaping at proposed flood wall 885.00 m2 5.30 4,687.24
14.25 Proposed steps (UWW_G05 & G09); complete with railings 1.00 nr 16,200.00 16,200.00
Bridges;
To Summary: 2,018,581
18/04/2018 MMC Quantity Surveyors Page 19 of 48
![Page 37: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/37.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_214 (Continued)
14.26 Proposed flow regulation structure 1.00 Item 1,296,000.00
1,296,000.00
14.27 Proposed footbridge 61.00 m2 5,400.00 329,400.00
To Summary: 1,625,400
18/04/2018 MMC Quantity Surveyors Page 20 of 48
![Page 38: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/38.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_215
LL_215
Demolitions & alterations;
15.1 Existing access gate reinstalled at proposed elevated footpath (CIW_G04) 1.00 Item 1,620.00 1,620.00
15.2 Demolish existing kerb & railing (CIW_L02) 345.00 m 54.00 18,630.00
Flood defence;
15.3 Flood defence embankment; 15.00m wide; 2.00m high (typical) 103.02 m 609.93 62,834.99
15.4 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
103.02 m 81.87 8,433.85
15.5 Flood defence wall; sheet pile wall and capping beam; avg height 1.50mabove ground level
356.00 m 3,353.40 1,193,810.40
15.6 Limestone cladding to both sides of sheet pile flood defence wall 1,470.00 m2 324.00 476,280.00
15.7 Flood defence wall; reinforced concrete wall with textured concrete finish;avg height 2.50m above ground level
275.00 m 1,676.70 461,092.50
15.8 Flood defence wall; reinforced concrete wall and capping beam; avg height2.50m above ground level
37.00 m 1,733.40 64,135.80
15.9 Limestone cladding to both sides of concrete flood defence wall 185.00 m2 324.00 59,940.00
15.10 Flood defence wall; reinforced concrete wall and capping beam; avg height1.50m above ground level
44.00 m 1,085.40 47,757.60
15.11 Limestone cladding to one side of concrete flood defence wall 65.00 m2 324.00 21,060.00
15.12 Flood defence wall; reinforced concrete wall with textured concrete finish;avg height 2.50m
245.00 m 1,814.40 444,528.00
To Summary: 2,860,123
18/04/2018 MMC Quantity Surveyors Page 21 of 48
![Page 39: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/39.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_215 (Continued)
15.13 Railing; 1.20m high 246.00 m 702.00 172,692.00
Drainage;
15.14 New storm drainage 784.00 m 205.20 160,876.80
15.15 Extra over above for non‐return vlaves; provisional quantity 50 nr 1,350.00 67,500.00
15.16 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 2.00 nr 3,672.00 7,344.00
15.17 Pumping station 2.00 nr 381,040.72 762,081.44
15.18 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
18.17 m 56.43 1,025.33
Regrading ground levels;
15.19 Pedestrian walkway/ vehicle access 991.00 m2 88.84 88,044.58
15.20 Pedestrian walkway/ vehicle access; raised avg. 1.00m 652.00 m2 108.27 70,591.34
15.21 Pedestrian walkway/ vehicle access; raised avg. 2.00m 744.00 m2 150.04 111,627.81
15.22 Regrading; existing lanscaping at proposed flood wall; raised avg. 2m 1,319.00 m2 31.83 41,986.30
To Summary: 1,483,770
18/04/2018 MMC Quantity Surveyors Page 22 of 48
![Page 40: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/40.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_216
LL_216
Demolitions & alterations;
16.1 Existing access gate to be relocated from existing to proposed ground level 1.00 Item 810.00 810.00
Flood defence;
16.2 Flood defence embankment; 8.00m wide; 1.00m high (typical) 189.00 m 255.93 48,370.93
16.3 Flood defence embankment; 19.00m wide; 2.50m high (typical) 61.56 m 947.48 58,327.07
16.4 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
249.69 m 81.87 20,441.16
16.5 Flood defence wall; sheet pile wall and capping beam 209.00 m 3,353.40 700,860.60
16.6 Limestone cladding to one side sheet pile flood defence wall 854.00 m2 324.00 276,696.00
16.7 Flood defence wall; reinforced concrete wall and capping beam; avg height1.50m
201.00 m 1,085.40 218,165.40
16.8 Limestone cladding to one side of concrete flood defence wall 301.00 m2 324.00 97,524.00
16.9 Flood defence wall; reinforced concrete wall and capping beam; avg height3.00m
66.00 m 2,057.40 135,788.40
16.10 Limestone cladding to one side of concrete flood defence wall 196.00 m2 324.00 63,504.00
16.11 Railing; 1.20m high 66.00 m 702.00 46,332.00
16.12 Glass railing; 1.20m high 295.00 m 2,160.00 637,200.00
Drainage;
To Summary: 2,304,020
18/04/2018 MMC Quantity Surveyors Page 23 of 48
![Page 41: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/41.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_216 (Continued)
16.13 New storm drainage 722.00 m 205.20 148,154.40
16.14 Extra over above for non‐return vlaves; provisional quantity 20 nr 1,350.00 27,000.00
16.15 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 2.00 nr 3,672.00 7,344.00
16.16 Pumping station 2.00 nr 381,040.72 762,081.44
16.17 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
17.55 m 56.43 990.35
Regrading ground levels;
16.18 Pedestrian walkway/ vehicle access; raised avg. 1.00m 1,095.00 m2 108.27 118,554.47
16.19 Pedestrian walkway/ vehicle access; raised avg. 2.00m 453.00 m2 150.04 67,966.93
16.20 Regrading; existing lanscaping at proposed flood wall 266.00 m2 5.30 1,408.82
16.21 Regrading; existing lanscaping at proposed flood wall; raised avg. 3.5m 114.00 m2 54.58 6,221.75
16.22 Reclaimed land; avg. 3.00m deep 468.58 m2 174.31 81,676.08
16.23 Reinstate existing tennis club balcony 1.00 Item 10,000.00 10,000.00
To Summary: 1,231,398
18/04/2018 MMC Quantity Surveyors Page 24 of 48
![Page 42: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/42.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_217
LL_217
Demolitions & alterations;
17.1 Remove existing track; dispose off‐site 20.00 m 59.94 1,198.80
Flood defence;
17.2 Flood defence embankment; 8.00m wide; 1.00m high (typical) 80.00 m 386.91 30,952.63
17.3 Flood defence embankment; 12.00m wide; 2.00m high (typical) 310.84 m 465.90 144,818.85
17.4 Flood defence embankment; 9.00m wide; 2.50m high (typical) 77.81 m 695.25 54,097.38
17.5 Flood defence embankment; 19.00m wide; 2.50m high (typical) 303.34 m 947.48 287,409.58
17.6 Flood defence embankment; 12.00m wide; 1.00m high (typical) 44.55 m 265.66 11,835.00
17.7 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
711.80 m 81.87 58,272.33
17.8 Flood defence wall; sheet pile wall and capping beam; typically 1.50m aboveground
173.00 m 3,353.40 580,138.20
17.9 Limestone cladding to both sides of sheet pile flood defence wall 690.00 m2 324.00 223,560.00
17.10 Flood defence wall; reinforced concrete wall and capping beam; avg height1m
99.00 m 761.40 75,378.60
17.11 Limestone cladding to both sides of concrete flood defence wall 197.00 m2 237.60 46,807.20
17.12 Palisade fencing; avg. 1.50m high 99.00 m 486.00 48,114.00
Drainage;
To Summary: 1,562,583
18/04/2018 MMC Quantity Surveyors Page 25 of 48
![Page 43: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/43.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_217 (Continued)
17.13 New storm drainage 983.00 m 205.20 201,711.60
17.14 Extra over above for non‐return vlaves; provisional quantity 50 nr 1,350.00 67,500.00
17.15 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 1.00 nr 3,672.00 3,672.00
17.16 Pumping station 1.00 nr 381,040.72 381,040.72
17.17 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
14.37 m 56.43 810.90
Regrading ground levels;
17.18 Pedestrian walkway/ vehicle access 420.00 m2 88.84 37,314.55
17.19 Reclaimed land; avg. 1.00m deep 628.00 m2 30.83 19,359.68
Bridges;
17.20 Proposed penstock and headwall 1.00 Item 540,000.00 540,000.00
17.21 Proposed footbridge 21.82 m2 5,400.00 117,828.00
To Summary: 1,369,237
18/04/2018 MMC Quantity Surveyors Page 26 of 48
![Page 44: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/44.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_218
LL_218
Demolitions & alterations;
18.1 Demolish stone parapet at quay walls; retain for salvage 707.00 m 270.00 190,890.00
18.2 Existing acces gate to be extinguished 2.00 nr 540.00 1,080.00
Flood defence;
18.3 Excavate trench at quay walls to allow grouting of existing foundations;backfilled with imported stone
3,871.00 m3 73.81 285,724.39
18.4 Excavate river bed to allow reclaiming of land 1,291.00 m2 92.19 119,015.74
18.5 Grouting to existing quay walls 361.00 m 2,160.00 779,760.00
18.6 Galvanised stitching bars to be grouted along full length in cord holes 130.00 m 2,160.00 280,800.00
18.7 Face of existing quay walls cleaned & repointed; stonework to be repaired 1,432.00 m2 162.00 231,984.00
18.8 Flood defence wall; reinforced concrete retaining wall at North Mall; avgheight 2.00m
15.80 m 1,625.40 25,681.32
18.9 Flood defence wall; sheet pile wall and capping beam; typically 1.20m aboveground
144.00 m 3,353.40 482,889.60
18.10 Limestone cladding to both sides of sheet pile flood defence wall 1,033.00 m2 324.00 334,692.00
18.11 Flood defence wall; reinforced concrete wall with concrete capping; avgheight 1m
10.00 m 761.40 7,614.00
18.12 Flood defence wall; reinforced concrete wall with concrete capping; avgheight 2m; quay walls
228.00 m 1,409.40 321,343.20
To Summary: 3,061,474
18/04/2018 MMC Quantity Surveyors Page 27 of 48
![Page 45: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/45.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_218 (Continued)
18.13 Flood defence wall; reinforced concrete wall with textured concrete finish;avg height 6m
80.00 m 4,860.00 388,800.00
18.14 Flood defence wall; reinforced concrete wall with textured concrete finish;avg height 1.5m; quay walls
133.00 m 1,117.80 148,667.40
18.15 Flood defence wall; reinforced concrete wall with textured concrete finish;avg height 1m
131.00 m 756.00 99,036.00
18.16 Limestone cladding to both sides of concrete flood defence wall 749.00 m2 324.00 242,676.00
18.17 Palisade fencing; avg. 1.20m high 131.00 m 162.00 21,222.00
18.18 Demountable flood gate 2.00 nr 11,880.00 23,760.00
18.19 Security fencing; including 1m high concrete retaining wall; avg. 2.1m highabove ground
120.00 m 1,317.60 158,112.00
Drainage;
18.20 New storm drainage 18.67 m 205.20 3,831.08
18.21 Extra over above for non‐return vlaves; provisional quantity 100 nr 1,350.00 135,000.00
18.22 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 2.00 nr 3,672.00 7,344.00
18.23 Pumping station 2.00 nr 381,040.72 762,081.44
18.24 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
6.48 m 56.43 365.67
Regrading ground levels;
18.25 Regrading roads 4,678.00 m2 110.44 516,657.85
To Summary: 2,507,553
18/04/2018 MMC Quantity Surveyors Page 28 of 48
![Page 46: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/46.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_218 (Continued)
18.26 Reclaimed land; avg. 4.5m deep; pedestrian finish 1,291.00 m2 225.69 291,371.41
18.27 Proposed steps (North Mall); complete with railings 1.00 nr 32,400.00 32,400.00
18.28 Pedestrian walkway/ vehicle access; raised avg. 1.00m; on exiting footbridge 107.00 m2 79.50 8,507.01
18.29 Regrading; existing lanscaping at proposed flood wall 131.00 m2 9.09 1,190.41
Bridges;
18.30 Proposed penstock and headwall 1.00 Item 270,000.00 270,000.00
To Summary: 603,469
18/04/2018 MMC Quantity Surveyors Page 29 of 48
![Page 47: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/47.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_219
LL_219
Demolitions & alterations;
19.1 Demolish stone parapet at quay walls; retain for salvage 890.00 m 270.00 240,300.00
19.2 Extinguish existing steps 1.00 nr 1,620.00 1,620.00
19.3 Extinguish river slipway; replace with access ladder 2.00 nr 2,700.00 5,400.00
Flood defence;
19.4 Excavate trench at quay walls to allow grouting of existing foundations;backfilled with imported stone
7,797.00 m3 63.75 497,085.88
19.5 Grouting to existing quay walls 780.00 m 2,160.00 1,684,800.00
19.6 Galvanised stitching bars to be grouted along full length in cord holes 132.00 m 2,160.00 285,120.00
19.7 Face of existing quay walls cleaned & repointed; stonework to be repaired 3,119.00 m2 162.00 505,278.00
19.8 Flood defence wall; reinforced concrete wall with concrete capping; avgheight 2m; quay walls
382.00 m 1,409.40 538,390.80
19.9 Flood defence wall; reinforced concrete wall with textured concrete finish;avg height 1.5m; quay walls
146.00 m 1,117.80 163,198.80
19.10 Limestone cladding to both sides of concrete flood defence wall 1,032.00 m2 324.00 334,368.00
19.11 Flood defence steel plate; at existing bridge; architectural finish 28.00 m 1,350.00 37,800.00
19.12 Steel demountable flood defence gate 2.00 nr 11,880.00 23,760.00
Drainage;
To Summary: 4,317,121
18/04/2018 MMC Quantity Surveyors Page 30 of 48
![Page 48: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/48.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_219 (Continued)
19.13 New storm drainage 22.30 m 205.20 4,575.96
19.14 Extra over above for non‐return vlaves; provisional quantity 100 nr 1,350.00 135,000.00
19.15 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 3.00 nr 3,672.00 11,016.00
19.16 Pumping station 3.00 nr 381,040.72 1,143,122.16
19.17 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
8.37 m 56.43 472.32
Regrading ground levels;
19.18 Regrading roads 3,190.00 m2 110.44 352,316.92
19.19 Extra over for kerbs & road gullies 1.00 Item 21,600.00 21,600.00
19.20 Proposed steps (Popes Quay); complete with railings (access to existingsteps
1.00 nr 10,800.00 10,800.00
Bridges;
19.21 Proposed penstock and headwall 1.00 Item 270,000.00 270,000.00
To Summary: 1,948,903
18/04/2018 MMC Quantity Surveyors Page 31 of 48
![Page 49: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/49.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_220 (a & b)
LL_220a
Demolitions & alterations;
20.1 Demolish stone parapet at quay walls; retain for salvage 302.00 m 270.00 81,540.00
20.2 Existing acces to be extinguished 1.00 nr 540.00 540.00
20.3 Existing river acces to be extinguished 1.00 nr 1,080.00 1,080.00
Flood defence;
20.4 Excavate trench at quay walls to allow grouting of existing foundations;backfilled with imported stone
3,418.00 m3 63.75 217,909.39
20.5 Excavate trench at quay walls to allow grouting of existing foundations;backfilled with mass concrete
573.00 m3 158.81 91,000.42
20.6 Grouting to existing quay walls 426.00 m 2,160.00 920,160.00
20.7 Galvanised stitching bars to be grouted along full length in cord holes 58.00 m 2,160.00 125,280.00
20.8 Face of existing quay walls cleaned & repointed; stonework to be repaired 1,984.00 m2 162.00 321,408.00
20.9 Flood defence wall; reinforced concrete wall with concrete capping; avgheight 0.25m; quay walls
245.00 m 275.40 67,473.00
20.10 Flood defence wall; reinforced concrete wall with textured concrete finish;avg height 1.5m; quay walls
58.00 m 1,117.80 64,832.40
20.11 Railing; 600m high 58.00 m 540.00 31,320.00
20.12 Glass railing; 1.20m high 90.00 m 2,160.00 194,400.00
To Summary: 2,116,943
18/04/2018 MMC Quantity Surveyors Page 32 of 48
![Page 50: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/50.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_220 (a & b) (Continued)
20.13 Flood defence steel plate; at existing bridge; architectural finish 43.00 m 1,350.00 58,050.00
Drainage;
20.14 New storm drainage 52.31 m 205.20 10,734.01
20.15 Extra over for non‐return vlaves; provisional quantity 100 nr 1,350.00 135,000.00
20.16 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 4.00 nr 3,672.00 14,688.00
20.17 Pumping station 4.00 nr 381,040.72 1,524,162.87
20.18 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
11.38 m 56.43 642.17
Regrading ground levels;
20.19 Pedestrian walkway 1,194.00 m2 48.18 57,525.00
20.20 Extra over for kerbs 1.00 Item 10,800.00 10,800.00
To Summary: 1,811,602
18/04/2018 MMC Quantity Surveyors Page 33 of 48
![Page 51: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/51.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_221
LL_221
Demolitions & alterations;
21.1 Grout existing foundation walls; ensuring water tight seal 160.00 m 1,620.00 259,200.00
21.2 Provisional allowance for alterations to existing building services; ensuringno potential routes for water ingress
1.00 Item 54,000.00 54,000.00
21.3 Reseal & grout existing concrete bridge access; steel railings to be replacedwith concrete flood defense walls;
3.00 nr 5,400.00 16,200.00
21.4 Existing double windows to have local defenses fitted externally 3.00 nr 5,400.00 16,200.00
21.5 Existing timber bridge access to be replaced with new concrete bridge; siderailings replaced with concrete flood defense walls; with 900mm railing
4.00 nr 54,000.00 216,000.00
21.6 Existing concrete bridge access to be strucutrally assessed; side railingsreplaced with concrete flood defense walls; with 900mm railing
2.00 nr 21,600.00 43,200.00
Flood defence;
21.7 Flood defence steel plate; architectural finish 204.00 m 1,350.00 275,400.00
To Summary: 880,200
18/04/2018 MMC Quantity Surveyors Page 34 of 48
![Page 52: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/52.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_222
LL_222
Demolitions & alterations;
22.1 Demolish stone parapet at quay walls; retain for salvage 771.00 m 270.00 208,170.00
22.2 Existing river acces to be extinguished 3.00 nr 1,080.00 3,240.00
Flood defence;
22.3 Excavate trench at quay walls to allow grouting of existing foundations;backfilled with imported stone
6,522.00 m3 63.75 415,800.20
22.4 Grouting to existing quay walls 398.00 m 2,160.00 859,680.00
22.5 Face of existing quay walls cleaned & repointed; stonework to be repaired 2,586.00 m2 162.00 418,932.00
22.6 Flood defence wall; reinforced concrete wall with textured finish; avg height1.00m; quay walls
566.00 m 756.00 427,896.00
22.7 Flood defence wall; reinforced concrete wall with textured concrete finish;avg height 0.50m; quay walls
97.00 m 378.00 36,666.00
22.8 Flood defence wall; reinforced concrete wall with textured concrete finish;avg height 0.75m; quay walls
109.00 m 567.00 61,803.00
22.9 Railing; 600m high 566.00 m 540.00 305,640.00
22.10 Flood defence steel plate; at existing bridge; architectural finish 125.00 m 1,350.00 168,750.00
22.11 Steel demountable flood defence gate 4.00 nr 11,880.00 47,520.00
Drainage;
To Summary: 2,954,097
18/04/2018 MMC Quantity Surveyors Page 35 of 48
![Page 53: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/53.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_222 (Continued)
22.12 New storm drainage 66.80 m 205.20 13,707.36
22.13 Extra over for non‐return vlaves; provisional quantity 100 nr 1,350.00 135,000.00
22.14 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 4.00 nr 3,672.00 14,688.00
22.15 Pumping station 4.00 nr 381,040.72 1,524,162.87
22.16 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
18.17 m 56.43 1,025.33
Regrading ground levels;
22.17 Pedestrian walkway 1,466.00 m2 48.18 70,629.53
To Summary: 1,759,213
18/04/2018 MMC Quantity Surveyors Page 36 of 48
![Page 54: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/54.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_223
LL_223
Demolitions & alterations;
23.1 Demolish stone parapet at quay walls; retain for salvage 256.00 m 270.00 69,120.00
Flood defence;
23.2 Excavate trench at quay walls to allow grouting of existing foundations;backfilled with imported stone
296.00 m3 63.75 18,871.03
23.3 Grouting to existing quay walls 37.00 m 2,160.00 79,920.00
23.4 Face of existing quay walls cleaned & repointed; stonework to be repaired 148.00 m2 162.00 23,976.00
23.5 Flood defence wall; reinforced concrete wall with textured finish; avg height1.00m; quay walls
37.00 m 756.00 27,972.00
23.6 Flood defence wall; reinforced concrete wall with textured concrete finish;avg height 0.50m; quay walls
219.00 m 378.00 82,782.00
23.7 Railing; 600m high 219.00 m 540.00 118,260.00
23.8 Flood defence steel plate; at existing bridge; architectural finish 20.00 m 1,350.00 27,000.00
Drainage;
23.9 Non‐return vlaves; provisional quantity 50 nr 1,123.20 56,160.00
Regrading ground levels;
23.10 Pedestrian walkway 74.00 m2 48.18 3,565.20
23.11 Regrading roads 5,362.00 m2 110.44 592,201.67
To Summary: 1,099,828
18/04/2018 MMC Quantity Surveyors Page 37 of 48
![Page 55: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/55.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_224
LL_224
Demolitions & alterations;
24.1 Demolish stone parapet at quay walls; retain for salvage 286.00 m 270.00 77,220.00
24.2 Demolish existing crash barrier; dispose off‐site 210.00 m 270.00 56,700.00
24.3 Demolish existing wharf at Alberts Quay; dispose off‐site 1.00 Item 216,000.00 216,000.00
24.4 Existing river acces to be extinguished 2.00 nr 1,080.00 2,160.00
Flood defence;
24.5 Excavate trench at quay walls to allow grouting of existing foundations;backfilled with imported stone
826.00 m3 63.75 52,660.37
24.6 Grouting to existing quay walls 104.00 m 2,160.00 224,640.00
24.7 Face of existing quay walls cleaned & repointed; stonework to be repaired 413.00 m2 162.00 66,906.00
24.8 Flood defence wall; sheet pile wall and capping beam; Albert Quay West 91.00 m 3,353.40 305,159.40
24.9 Limestone cladding to one side of sheet pile flood defence wall 363.00 m2 324.00 117,612.00
24.10 Flood defence wall; reinforced concrete wall with textured finish; avg height2.00m; quay walls
313.00 m 1,512.00 473,256.00
24.11 Flood defence wall; reinforced concrete wall with textured finish; avg height1.00m; quay walls
183.00 m 756.00 138,348.00
24.12 Flip up flood defence barrier; at existing boardwalk; 54.00 m 3,240.00 174,960.00
24.13 Glass railing; 1.20m high 55.00 m 2,160.00 118,800.00
To Summary: 2,024,422
18/04/2018 MMC Quantity Surveyors Page 38 of 48
![Page 56: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/56.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_224 (Continued)
24.14 Railing; 600mm high 495.00 m 540.00 267,300.00
24.15 Flood defence steel plate; at existing bridge; architectural finish 114.00 m 1,350.00 153,900.00
24.16 Steel demountable flood defence gate 9.00 nr 11,880.00 106,920.00
Drainage;
24.17 New storm drainage 32.35 m 205.20 6,638.22
24.18 Extra over for non‐return vlaves; provisional quantity 100 nr 1,123.20 112,320.00
24.19 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 3.00 nr 2,633.63 7,900.89
24.20 Pumping station 3.00 nr 381,040.72 1,143,122.16
24.21 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
13.26 m 37.89 502.37
Regrading ground levels;
24.22 Reinstate existing paving at lapps quay 540.00 m2 56.79 30,669.10
24.23 Regrading roads 5,765.00 m2 110.44 636,710.67
To Summary: 2,465,983
18/04/2018 MMC Quantity Surveyors Page 39 of 48
![Page 57: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/57.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_225
LL_225
Demolitions & alterations;
25.1 Demolish stone parapet at quay walls; retain for salvage 1,101.00 m 270.00 297,270.00
Flood defence;
25.2 Excavate trench at quay walls to allow grouting of existing foundations;backfilled with imported stone
6,806.00 m3 63.75 433,906.18
25.3 Grouting to existing quay walls 851.00 m 2,160.00 1,838,160.00
25.4 Galvanised stitching bars to be grouted along full length in cord holes 306.00 m 2,160.00 660,960.00
25.5 Face of existing quay walls cleaned & repointed; stonework to be repaired 3,298.00 m2 162.00 534,276.00
25.6 Flood defence wall; reinforced concrete wall with concrete capping; avgheight 2m
27.00 m 1,738.80 46,947.60
25.7 Flood defence wall; reinforced concrete wall with textured finish; avg height2.00m; quay walls
306.00 m 1,512.00 462,672.00
25.8 Flood defence wall; reinforced concrete wall with textured finish; avg height1.00m; quay walls
796.00 m 756.00 601,776.00
25.9 Glass railing; 1.20m high 110.00 m 2,160.00 237,600.00
25.10 Railing; 600m high 992.00 m 540.00 535,680.00
25.11 Works to Trinity Bridge; new concret deck on new horizontally braced steelbeams on existing deck; c/w downstand concrete beams and parapetrailings
1.00 Item 540,000.00 540,000.00
Drainage;
To Summary: 6,189,248
18/04/2018 MMC Quantity Surveyors Page 40 of 48
![Page 58: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/58.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_225 (Continued)
25.12 New storm drainage 24.46 m 205.20 5,019.19
25.13 Extra over for non‐return vlaves; provisional quantity 200 nr 1,350.00 270,000.00
25.14 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 3.00 nr 3,672.00 11,016.00
25.15 Pumping station 3.00 nr 381,040.72 1,143,122.16
25.16 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
20.00 m 56.43 1,128.60
Regrading ground levels;
25.17 Pedestrian walkway 1,110.00 m2 48.18 53,478.02
25.18 Regrading roads 6,197.00 m2 110.44 684,422.55
25.19 Proposed steps (Georges Quay); complete with railings (access to existingsteps
1.00 nr 10,800.00 10,800.00
25.20 Stone paving finishes to Morrisons Island plazas & streets 3,099.00 m2 129.60 401,630
Fittings
25.21 Street furniture & Artwork 1 Item 270,000.00 270,000
To Summary: 2,850,617
18/04/2018 MMC Quantity Surveyors Page 41 of 48
![Page 59: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/59.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_226 (a & b)
LL_226 (a & b)
Demolitions & alterations;
26.1 Demolish stone parapet at quay walls; retain for salvage 413.00 m 270.00 111,510.00
Flood defence;
26.2 Excavate trench at quay walls to allow grouting of existing foundations;backfilled with imported stone
5,662.00 m3 63.75 360,972.20
26.3 Grouting to existing quay walls 708.00 m 2,160.00 1,529,280.00
26.4 Galvanised stitching bars to be grouted along full length in cord holes 233.00 m 2,160.00 503,280.00
26.5 Face of existing quay walls cleaned & repointed; stonework to be repaired 3,007.00 m2 162.00 487,134.00
26.6 Flood defence wall; sheet pile wall and capping beam 207.00 m 3,353.40 694,153.80
26.7 Limestone cladding to one side of sheet pile flood defence wall 825.00 m2 324.00 267,300.00
26.8 Reinforced concrete benching; reinforced concrete wall with textured finish;timber bench finish; avg height 0.50m above ground level; 1m wide
35.00 m 1,620.00 56,700.00
26.9 Flood defence wall; reinforced concrete wall with textured finish; avg height2.00m; quay walls
58.00 m 1,512.00 87,696.00
26.10 Flood defence wall; reinforced concrete wall with textured finish; avg height0.50m; quay walls
354.00 m 378.00 133,812.00
26.11 Flood defence wall; reinforced concrete wall with concrete capping; avgheight 0.50m; quay walls
233.00 m 437.40 101,914.20
26.12 Limestone cladding to both sides of flood defence wall 233.00 m2 237.60 55,360.80
To Summary: 4,389,113
18/04/2018 MMC Quantity Surveyors Page 42 of 48
![Page 60: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/60.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_226 (a & b) (Continued)
26.13 Railing; 1000m high 354.00 m 648.00 229,392.00
26.14 Railing; 600m high 233.00 m 540.00 125,820.00
26.15 Railing; 600m high; w/ capping to existing walls 149.00 m 653.40 97,356.60
26.16 Flip up flood defence barrier; at existing boardwalk; 80.00 m 3,240.00 259,200.00
26.17 Privacy railing; 2.00m high 58.00 m 810.00 46,980.00
26.18 Steel demountable flood defence gate 7.00 nr 11,880.00 83,160.00
26.19 Local raising of window cills by approx 150mm; damp proof membranebelow; finish to match existing
37.00 m 1,620.00 59,940.00
Drainage;
26.20 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
41.06 m 39.42 1,618.59
26.21 Extra over for non‐return vlaves; provisional quantity 200 nr 1,350.00 270,000.00
26.22 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 3.00 nr 3,672.00 11,016.00
26.23 Pumping station 3.00 nr 381,040.72 1,143,122.16
26.24 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
17.89 m 56.43 1,009.53
Regrading ground levels;
26.25 Pedestrian walkway/ vehicle access; raised avg. 500mm 1,983.00 m2 99.29 196,884.71
26.26 Reclaimed land; avg. 4.00m deep 471.52 m2 191.83 90,449.97
To Summary: 2,615,950
18/04/2018 MMC Quantity Surveyors Page 43 of 48
![Page 61: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/61.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_226 (a & b) (Continued)
26.27 New boardwalk; 3m wide; with steel plate fixed to underside of cantilever &1.20m high railing
58.00 m 5,940.00 344,520.00
To Summary: 344,520
18/04/2018 MMC Quantity Surveyors Page 44 of 48
![Page 62: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/62.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_227
LL_227
Demolitions & alterations;
27.1 Demolish stone parapet at quay walls; retain for salvage 245.00 m 270.00 66,150.00
27.2 Repairs to existing culvert; Provisional 1.00 Item 108,000.00 108,000.00
Flood defence;
27.3 Excavate trench at quay walls to allow grouting of existing foundations;backfilled with imported stone
1,454.00 m3 63.75 92,697.56
27.4 Excavate trench at quay walls to allow grouting of existing foundations;backfilled with mass concrete
505.00 m3 158.81 80,201.07
27.5 Grouting to existing quay walls 245.00 m 2,160.00 529,200.00
27.6 Galvanised stitching bars to be grouted along full length in cord holes 451.00 m 2,160.00 974,160.00
27.7 Face of existing quay walls cleaned & repointed; stonework to be repaired 1,886.00 m2 162.00 305,532.00
27.8 Flood defence wall; sheet pile wall and capping beam 120.00 m 3,353.40 402,408.00
27.9 Limestone cladding to one side of sheet pile flood defence wall 480.00 m2 324.00 155,520.00
27.10 Flood defence wall; reinforced concrete wall with concrete capping; avgheight 1.50m; quay walls
245.00 m 1,085.40 265,923.00
27.11 Limestone cladding to both sides of flood defence wall 672.00 m2 237.60 159,667.20
27.12 Glass railing; 1.20m high 26.00 m 2,160.00 56,160.00
27.13 Railing; 600m high 64.00 m 540.00 34,560.00
To Summary: 3,230,179
18/04/2018 MMC Quantity Surveyors Page 45 of 48
![Page 63: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/63.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_227 (Continued)
27.14 Railing; 600m high; w/ capping to existing walls 120.00 m 653.40 78,408.00
Drainage;
27.15 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
6.81 m 39.42 268.45
27.16 Extra over for non‐return vlaves; provisional quantity 200 nr 1,350.00 270,000.00
27.17 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 1.00 nr 3,672.00 3,672.00
27.18 Pumping station 2.00 nr 381,040.72 762,081.44
27.19 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
20.00 m 56.43 1,128.60
Regrading ground levels;
27.20 Pedestrian walkway/ vehicle access; raised avg. 500mm 823.00 m2 99.29 81,712.62
27.21 Reclaimed land; avg. 2.00m deep 180.08 m2 121.27 21,838.88
To Summary: 1,219,110
18/04/2018 MMC Quantity Surveyors Page 46 of 48
![Page 64: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/64.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_228
LL_228
Demolitions & alterations;
28.1 Remove & reinstate railings at proposed flood defense wall 105.00 m 270.00 28,350.00
Flood defence;
28.2 Flood defence embankment; 17.00m wide; 2.00m high (typical) 139.36 m 679.69 94,721.21
28.3 Flood defence embankment; key to existing trench; 4.00m wide; 500mmhigh (typical)
139.36 m 81.87 11,408.87
28.4 Excavate trench at quay walls to allow grouting of existing foundations;backfilled with imported stone
269.00 m3 63.75 17,149.69
28.5 Grouting to existing quay walls 34.00 m 2,160.00 73,440.00
28.6 Galvanised stitching bars to be grouted along full length in cord holes 34.00 m 2,160.00 73,440.00
28.7 Face of existing quay walls cleaned & repointed; stonework to be repaired 101.00 m2 162.00 16,362.00
28.8 Flood defence wall; sheet pile wall and capping beam 172.00 m 3,353.40 576,784.80
28.9 Limestone cladding to one side of sheet pile flood defence wall 719.00 m2 324.00 232,956.00
28.10 Flood defence wall; reinforced concrete wall with concrete capping; avgheight 1.00m; quay walls
144.00 m 1,085.40 156,297.60
28.11 Limestone cladding to both sides of flood defence wall 288.00 m2 324.00 93,312.00
28.12 Railing; 600m high 40.00 m 540.00 21,600.00
Drainage;
To Summary: 1,395,822
18/04/2018 MMC Quantity Surveyors Page 47 of 48
![Page 65: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/65.jpg)
DETAILED ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Estimate of proposed flood relief works as
published by OPW, Cork City Council & Cork
County Council
Code Description Quantity Unit Rate Total
LL_228 (Continued)
28.13 Drain; surface water; toe drain; not exceeding 500mm deep; backfilled withexcavated material
7.40 m 39.42 291.71
28.14 Extra over for non‐return vlaves; provisional quantity 200 nr 1,350.00 270,000.00
28.15 Manhole; surface water; 3.00 deep (assumed); 1200mm diameter 1.00 nr 3,672.00 3,672.00
28.16 Pumping station 1.00 nr 381,040.72 381,040.72
28.17 Pumped rising main; surface water; not exceeding 500mm deep; backfilledwith excavated material
10.00 m 56.43 564.30
Regrading ground levels;
28.18 Pedestrian walkway/ vehicle access; raised avg. 500mm 105.00 m2 99.29 10,425.06
28.19 Reclaimed land; avg. 2.00m deep 172.00 m2 121.27 20,858.99
28.20 Regrading; existing garden 472.00 m2 5.30 2,499.86
To Summary: 689,353
18/04/2018 MMC Quantity Surveyors Page 48 of 48
![Page 66: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/66.jpg)
Estimating | BOQs | Feasibility Studies | Life Cycle Costing | Post Contract Management | M&E
Pump Chamber Estimate
Lower Lee Flood Relief Scheme
Detailed cost estimate for proposed pumping station chamber
V1 – 18.04.2018
![Page 67: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/67.jpg)
PUMPING STATION ESTIMATE ‐ SUMMARY
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Total
PUMPING STATION
A SITE PREPARATION 60,000
B EXCAVATION & EARTHWORK 100,268
C CONCRETE WORK 64,797
D METALWORK 16,878
E MECHANICAL & ELECTRICAL INSTALLATIONS 110,872
TOTAL (Excl. VAT) 352,815.48
To Collection 352,815
18/04/2018 15:28:28 MMC Quantity Surveyors Page 1 of 1
![Page 68: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/68.jpg)
PUMPING STATION ESTIMATE
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Quantity Unit Rate Total
SITE PREPARATION
SITE PREPARATION
General site preparation works;
A.1 Services diversions 1 Sum 50,000.00 50,000
A.2 Road / Surfaces re‐instatement 1 Sum 10,000.00 10,000
To Summary: 60,000
18/04/2018 MMC Quantity Surveyors Page 1 of 12
![Page 69: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/69.jpg)
PUMPING STATION ESTIMATE
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Quantity Unit Rate Total
EXCAVATION & EARTHWORK
EXCAVATION & EARTHWORK; EXCAVATION
Excavation;
Reduce levels; starting at formation level; maximum depth stated
≤ 2.00m;
B.1 Control Kiosk 1 m3 22.40 22.40
Reduce levels; within cofferdam enclosure; starting at formation level;maximum depth stated
2.00m ‐ 4.00m;
B.2 Pump Station 23 m3 4.48 103.04
4.00m ‐ 6.00m;
B.3 Pump Station 237 m3 8.40 1,990.80
6.00m ‐ 8.00m;
B.4 Pump Station 59 m3 13.44 792.96
Extra on excavation items for;
Breaking up existing;
B.5 Rock; Provisional (10%) 32 m3 56.00 1,792.00
Working Space;
To Summary: 4,701
18/04/2018 MMC Quantity Surveyors Page 2 of 12
![Page 70: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/70.jpg)
PUMPING STATION ESTIMATE
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Quantity Unit Rate Total
EXCAVATION & EARTHWORK (Continued)
For reducing levels; backfilling with approved excavated material; maximumdepth stated
2.00m ‐ 4.00m;
B.6 Pump Station 18 m2 20.16 362.88
4.00m ‐ 6.00m;
B.7 Pump Station 112 m2 24.64 2,759.68
6.00m ‐ 8.00m;
B.8 Pump Station 82 m2 28.00 2,296.00
Disposal;
B.9 Ground water; PROVISIONAL 1 Item
B.10 Surface water; PROVISIONAL 1 Item
Excavated material; disposal off‐site
B.11 Excavated material 532 m3 28.00 14,896.00
Filling; material stated;
Approved imported fill to Clause 804 granular material of natural gravels orcrushed rock well graded and passing a 75 mm sieve deposited andcompacted in layers not exceeding 250 mm; to excavations
to excavations
B.12 Control Kiosk; 150mm 5 m3 50.40 252.00
To Summary: 20,567
18/04/2018 MMC Quantity Surveyors Page 3 of 12
![Page 71: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/71.jpg)
PUMPING STATION ESTIMATE
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Quantity Unit Rate Total
EXCAVATION & EARTHWORK (Continued)
EXCAVATION & EARTHWORK: UNDERPINNING
Excavation Support
Permanent sheet piling to allow works to pumping station
B.13 Placing Piling; including delivery to site, unloading, mobilisation andplacing piling
1 item 75,000.00 75,000.00
To Summary: 75,000
18/04/2018 MMC Quantity Surveyors Page 4 of 12
![Page 72: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/72.jpg)
PUMPING STATION ESTIMATE
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Quantity Unit Rate Total
CONCRETE WORK
CONCRETE WORK; IN‐SITU CONCRETE
In‐Situ Concrete; Blinding
C20/25 Concrete; poured earth against formwork
Blinding; 100mm
C.1 Pumping Station 7 m3 100.80 705.60
In‐Situ Concrete; Reinforced
Concrete shall conform to classification to I.S. EN 206‐1 : 2002; C30/37;reinforced; vibrated; poured against faces of excavations
Slabs; incl. thickenings
C.2 Pumping Station; 300mm thick 4 m3 184.80 739.20
C.3 Pumping Station; 450mm thick 32 m3 162.40 5,196.80
C.4 Control Kiosk; 120mm thick 1 m3 218.40 218.40
Slabs; suspended
C.5 Pumping Station; 300mm thick 21 m3 184.80 3,880.80
Benching;
C.6 Pumping Station; Avg. 75mm thick 4 m3 252.00 1,008.00
Walls; > 150mm
C.7 Walls; 300mm thick 5 m3 162.40 812.00
To Summary: 12,561
18/04/2018 MMC Quantity Surveyors Page 5 of 12
![Page 73: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/73.jpg)
PUMPING STATION ESTIMATE
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Quantity Unit Rate Total
CONCRETE WORK (Continued)
C.8 Walls; 400mm thick 62 m3 145.60 9,027.20
CONCRETE WORK; SUNDRIES
Designed joints; waterstops
PVC centre bulb waterstops; vertical
C.9 250mm wide 50 m 47.04 2,352.00
PVC external waterstops; horizontal
C.10 250mm wide PVC rearguard 8 m 47.04 376.32
Puddle Flanges
to Opes; sizes;
C.11 100mm diam. 3 nr 56.00 168.00
C.12 150mm diam. 2 nr 84.00 168.00
C.13 300mm x 300mm 2 nr 140.00 280.00
C.14 400mm x 400mm 4 nr 168.00 672.00
C.15 450mm x 450mm 5 nr 179.20 896.00
C.16 600mm x 600mm 2 nr 224.00 448.00
Labours;
To Summary: 14,388
18/04/2018 MMC Quantity Surveyors Page 6 of 12
![Page 74: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/74.jpg)
PUMPING STATION ESTIMATE
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Quantity Unit Rate Total
CONCRETE WORK (Continued)
Cutting or forming rebates; in roof slab
C.17 100mm x 100mm 28 m 13.44 376.32
Cutting or forming holes;
in Walls; 300mm thick;
C.18 100mm diameter 1 nr 39.20 39.20
C.19 150mm diameter 1 nr 50.40 50.40
C.20 400mm x 400mm 2 nr 140.00 280.00
in Walls; 400mm thick;
C.21 150mm diameter 1 nr 61.60 61.60
C.22 400mm x 400mm 2 nr 140.00 280.00
C.23 600mm x 600mm 2 nr 184.80 369.60
Recessed Pocket; for lifting davitt
C.24 100mm diameter 1 nr 50.40 50.40
CONCRETE WORK; REINFORCEMENT
Bar; straight or bent; 12 ‐ 25mm diameter
Slabs;
C.25 Storm Holding Tank; 187kg/m3 4.13 t 1,092.00 4,509.96
To Summary: 6,017
18/04/2018 MMC Quantity Surveyors Page 7 of 12
![Page 75: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/75.jpg)
PUMPING STATION ESTIMATE
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Quantity Unit Rate Total
CONCRETE WORK (Continued)
C.26 Valve Chamber; 140kg/m3 0.30 t 1,176.00 352.80
C.27 Pump Sump; 66kg/m3 0.10 t 1,176.00 117.60
C.28 Flow Meter Chamber; 66kg/m3 0.05 t 1,400.00 70.00
Slabs; Suspended
C.29 Pumping Station Roof; 80kg/m3 (provisional) 1.65 t 1,092.00 1,801.80
Walls;
C.30 300mm thick; 80kg/m3 0.36 t 1,176.00 423.36
C.31 400mm thick; 105kg/m3 6.47 t 1,092.00 7,065.24
CONCRETE WORK; FORMWORK
Formwork; class B finish
Edges of Beds;
C.32 > 250mm ≤ 500mm 70 m 21.00 1,470.00
Edges of Kickers;
C.33 ≤ 250mm 99 m 13.44 1,330.56
Edges of Suspended Slabs;
C.34 > 250mm ≥ 500mm 68 m 21.00 1,428.00
To Summary: 14,059
18/04/2018 MMC Quantity Surveyors Page 8 of 12
![Page 76: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/76.jpg)
PUMPING STATION ESTIMATE
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Quantity Unit Rate Total
CONCRETE WORK (Continued)
Soffits of Suspended Slabs;
Thickness; > 250mm ≤ 500mm
C.35 1500mm high; floor to u/side of slab 8 m2 50.40 403.20
C.36 3180mm high; floor to u/side of slab 49 m2 58.24 2,853.76
C.37 5900mm high; floor to u/side of slab 5 m2 72.80 364.00
Walls; Vertical
C.38 Height < 4.00m measured overall; to both sides 208 m2 39.20 8,153.60
C.39 Height > 4.00m measured overall; to both sides 130 m2 39.20 5,096.00
Edges of Openings
C.40 Area of opening; ≤ 1m2 3 nr 140.00 420.00
C.41 Area of opening; > 1m2 ≤ 5m2 2 nr 240.80 481.60
To Summary: 17,772
18/04/2018 MMC Quantity Surveyors Page 9 of 12
![Page 77: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/77.jpg)
PUMPING STATION ESTIMATE
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Quantity Unit Rate Total
METALWORK
METALWORK: NON‐STRUCTURAL
Composite items;
Heavy Duty Covers & Frames; CI Metal; to pump station roofs
D.1 900mm x 900mm 2 nr 1,848.00 3,696.00
D.2 1200mm x 1200mm 1 nr 1,960.00 1,960.00
D.3 1400mm x 2600mm 2 nr 2,800.00 5,600.00
Galvanised Ladders; to pump stations; to engineers approval
D.4 galvanised steel ladder: 6m long 1 item 2,800.00 2,800.00
Control Kiosk; as per drawing no. Y14301‐SKETCH‐04 and to engineersapproval; complete
D.5 Control kiosk 1 Item 2,822.40 2,822.40
To Summary: 16,878
18/04/2018 MMC Quantity Surveyors Page 10 of 12
![Page 78: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/78.jpg)
PUMPING STATION ESTIMATE
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Quantity Unit Rate Total
MECHANICAL & ELECTRICAL INSTALLATIONS
MECHANICAL & ELECTRICAL INSTALLATIONS; GENERALLY
Allow for the following works
E.1 2 x 7.5kw Pumps 1 Item 60,872.00 60,872
E.2 2 x Guide rail & Ped kits 1 Item Incl. 0.00
E.3 1 x Valve & Fittings 1 Item Incl. 0.00
E.4 1 x Manual Knife edge valve 1 Item Incl. 0.00
E.5 1 x Venture Mixer unit 1 Item Incl. 0.00
E.6 1 x Mag flow meter 1 Item Incl. 0.00
E.7 1 x Set of Float switches 1 Item Incl. 0.00
E.8 1 x Electric Knife valve 1 Item Incl. 0.00
E.9 2 x Ultra sonic units 1 Item Incl. 0.00
E.10 5 x Access covers 1 Item Incl. 0.00
E.11 2 x Kiosks 1 Item Incl. 0.00
E.12 1 x Main control panel 1 Item Incl. 0.00
E.13 1 x Kiosk Electrical works 1 Item Incl. 0.00
E.14 1 x ESB Mini pillar 1 Item Incl. 0.00
E.15 1 x Lighting works 1 Item Incl. 0.00
To Summary: 60,872
18/04/2018 MMC Quantity Surveyors Page 11 of 12
![Page 79: Estimating | BOQs | Feasibility Studies | Life Cycle ...savecorkcity.org/docs/Lower-Lee-Flood-Relief-Scheme-MMC-Report-25-04-2018.pdfRates included in ‘ olumn E’ were ascertained](https://reader033.vdocument.in/reader033/viewer/2022041908/5e6567d8e1cece29c756103a/html5/thumbnails/79.jpg)
PUMPING STATION ESTIMATE
Project: SAVE CORK CITY
Building: LOWER LEE FLOOD RELIEF SCHEME
Details: Pumping Station
Code Description Quantity Unit Rate Total
MECHANICAL & ELECTRICAL INSTALLATIONS (Continued)
E.16 1 x Emergency Fall arrest system 1 Item Incl. 0.00
Back‐up Generation
E.17 Allowance per pumping station for backup power and distribution 1 Item 50,000.00 50,000
To Summary: 50,000
18/04/2018 MMC Quantity Surveyors Page 12 of 12