ETCS L2 On-Board
Retrofit
SUPERVISION SERVICES
(Consulting, Inspection & Testing)
NTP1 + NTP2 + OPTIONAL WORKS
SCOPE OF WORK
2
1 General……………………………………………………………………………………………………………………….3
2 Scope of Services ................................................................................................. 3
2.1 Technical Consultancy ................................................................................... 3
2.2 Shops Inspection & Quality Control ................................................................. 5
2.3 Software Development Quality Control ........................................................... 6
2.4 FAIs & Factory Acceptance Tests ..................................................................... 6
2.5 Lab Tests, Installation Tests, Odometry Tests and Final Acceptance Tests ............ 6
3 Project Management Activities.............................................................................. 7
4 Tests Description ................................................................................................. 8
4.1 General ....................................................................................................... 8
4.2 On-Board Factory Acceptance Tests ................................................................ 8
4.2.1 OB Sub-Systems Description .................................................................... 8
4.2.2 Sub-Systems Inspection & OB Factory Acceptance Tests ............................. 8
4.3 On-Board System ........................................................................................ 12
4.3.1 OB Systems Description ........................................................................ 12
4.3.2 OB Systems Inspection ......................................................................... 12
5 Schedule Baseline .............................................................................................. 15
5.1 General Design per Vehicle Type (Ongoing 2019-2022) ................................... 15
5.2 NTP1 – Approximate Timeline ...................................................................... 15
5.2.1 Vossloh Euro 3200 ............................................................................... 15
5.2.2 Bombardier DD-PC ............................................................................... 15
5.2.3 Vossloh JT42 BW .................................................................................. 15
5.3 NTP2 – Approximate Timeline ...................................................................... 16
5.3.1 Siemens SD-PP ..................................................................................... 16
5.3.2 Alstom SD-PP Error! Bookmark not defined.
5.3.3 Vossloh Euro 4000 ............................................................................... 16
5.3.4 IC3 ............................................................. Error! Bookmark not defined.
5.3.5 Vossloh JT42 CW .................................................................................. 16
5.4 Optional Works – Timeline TBD .................................................................... 16
5.4.1 Proto .................................................................................................. 17
5.4.2 Serial .................................................................................................. 17
6 List of Attachments ............................................................................................ 18
3
1 General The ISR Project Manager (IPM) seeks to retain Consulting, Inspection, Supervision & Test
Services from a Rolling Stock expert specializing in Rolling Stock ATP & ETCS Systems, for the
support of the design, manufacturing, inspecting, testing, commissioning & operations /
maintenance of ETCS-L2 Installations in rolling stock, in 3 stages as follows:
NTP (Stage) 1
3 prototypes and 133 serial vehicles as follows:
Vossloh Euro 3200 Passenger Diesel Locomotives – 1 Prototype + 23 Serial
Bombardier 64 Double Deck Passenger Coaches – 1 Prototype + 63 Serial
Vossloh JT428W Passenger Diesel Locomotives – 1 Prototype + 47 Serial
Plasser Crane Yellow Machine – 1 Prototype
NTP (Stage) 2
5 prototypes and 51 serial vehicles as follows:
Bombardier 22 Double Deck Passenger Coaches –22 Serial
Siemens Single Deck Passenger Coaches – 1 Prototype + 13 Serial
Vossloh Euro 4000 Freight Diesel Locomotives – 1 Prototype + 14 Serial
Vossloh JT42CW Freight Diesel Locomotives – 1 Prototype + 6 Serial
Note: Scope of this Call-Off may change
Optional Works
5 prototypes and 29 serial vehicles as follows:
Yellow Machines as Follows:
o Geismar Ballast Regulators – 1 Prototype + 1 Serial
o Plasser & Theurer Rail Tamping Machine – 1 Prototype + 2 Serial
o Plasser & Theurer Measuring Vehicle – 1 Prototype
o Geismar Weed Killing Track Motorcars – 1 Prototype
o Plasser & Theurer Vehicles – 1 Prototype + 6 Serial
The following specification describes the general guidelines for the Supervision Company's
Scope of Work for all Stages - NTP1, NTP2 and Optional Works.
The SUPERVISION COMPANY shall provide CONSULTING, INSPECTION, TEST & SUPERVISION
services which ISR may require on a non-exclusive basis in the field of design, manufacturing,
testing, commissioning, delivering & operations / maintenance of the ETCS-L2 for the
vehicles described above. All works have to be carried out in accordance with the
norms/standards/specifications specified in Agreement No.91944 between ISR and Supplier,
Alstom Belgium, and as detailed hereafter but not limited to the items listed below. If there
are other deliverables the bidder would provide in this context, please include them in the
Proposal as well, in the form of an optional non-binding extension to the Offer.
2 Scope of Services
2.1 Technical Consultancy The scope of work includes, but not limited to, the following activities:
4
Design Appraisal in all relative disciplines (electrical, software, mechanical)
System Review & Assessment
Preparation of relative deviation reports
Preparation of the working procedures and checklists as base to perform inspections
and quality control
Technical consultancy on issues & matters arising during the execution of the Project
beginning from ETCS-L2 system design, through manufacturing, installations &
integrations, testing, commissioning, final acceptance and up to successful delivery
and operations / maintenance
Appraisal of technical documentation (Interfaces, RAMS, Quality (Assurance &
Control), Conformity to Railway Industry Standards, Design, Survey Reports, "As-
Build" Documentation, Testing etc.)
Appraisal of training packages (operation, maintenance etc.)
Check for Compliance with the Specification, the Approved Design and Purchase
Order Specification
Assessment and approval of Factory Acceptance Tests (FAT) / First Article Inspection
(FAI) for selected modules or components (e.g. EVC, EDOR, DMI, TCC, JRU, RADAR,
WHEEL SENSOR, RMR, INDUZI I60R, EUROBALISE ANTENNA, GSM-R ANTENNA, GSM-
R & GPS ANTENNA, JRU, I60-R etc.)
Actively participate in all Technical Milestones as required – Design Reviews,
Manufacturing Quality Control Gates, First Article Inspection (FAI), Prototype Tests
as well as Acceptance Tests for Serial Units, and issue corresponding Reports as
required
Review & Provide Remarks regarding Minutes of Meetings
Monitor Manufacturing Milestones & issue the Corresponding Reports & Punch-Lists
including Blocking points
Witness all Final Acceptance Tests (Prototype & Serial) & issue the Corresponding
Tests Reports & Punch-Lists including Blocking points
Organization and performance of the Final Design Review ("Design Freeze") with the
contractor
Assess the Test program at different manufacturing levels, the completeness of the
entire test program and the content of the individual test procedures
Approve the detailed Inspection and Test Plan for Type Tests & Serial Acceptance
Tests
Study of the Quality Plan of the examination of the Type Test and Routine Test
Specification of the contractor and its subcontractors
Approval of Type Test and Routine Test specifications of the contractor and its sub-
contractors
Software
o Verify Software Inter-operability with System Components
o Check Software Testing Management
o Verify Software Versions Control & Traceability
Cyber & Security
o Check conformity to Security and Safety requirements for Software (reports)
o Check all Cyber Security aspects in the Train IT (reports)
5
2.2 Shops Inspection & Quality Control The scope of work includes, but not limited to, the following activities:
Performance of shop inspection during the ETCS Retrofit process in the facilities or
on the premises of the suppliers & sub-contractors; Assess manufacturer & sub-
supplier authorities
Note: Inspection may be required in multiple shops, in up to 3 different sites
Development of the inspection plan and the working procedures and checklists,
which are defining the tasks and responsibilities of the supervisor inspectors (to be
submitted to the ISR project manager of the employer for approval)
Issue of Inspection, Quality Control & Deviation Reports
Issue respective certificates after the project milestones have been achieved (e.g.
"Certificate of Completion")
Check material identification and certification
Assess procedures specifications, qualification records & certificates
Verify correctness of storage procedures (including shelf-life of consumables)
Verify compliance & conformity to Technical Standards as defined in the Technical
Specification
Random inspections of material preparation & fit-ups throughout the project
Check & approve Test and Installation Equipment
Final visual examination & inspection
Check application of identification marks and inscriptions
Check packing and marking
Issue of acceptance certificates for components and system-wide
Issue Release Notes and Reports (summarize the carried out activities in the
Monthly Report including Manufacturing QA Reports)
Verification of Manufacturing Employees Qualifications & Certifications for the
required works
Check for Compliance with the Specification, the Approved Design and Purchase
Order Specification
Participate in Technical Meetings with the Manufacturer and the Sub-Supplier &
Review the Minutes of Meetings
Assess and approve of Factory Acceptance Tests (FAT) / First Article Inspection (FAI)
for selected modules, which shall be defined after the completion of the Design
Review
Check for correct assembly & installation of all components and their secure
interoperability with existing systems as well as attachment to the structure
(Mechanical installation), and issue Corresponding Reports
6
2.3 Software Development Quality Control Software
o Software interoperability with system components
o Software Quality Assurance:
Check software testing management
Software versions control & traceability
Cyber & Security
o Check conformity to security and safety requirements for Software (reports)
o Check all cyber security aspects in the train IT (reports)
2.4 FAIs & Factory Acceptance Tests The scope of work includes, but not limited to, the following activities:
Assess Type Test Procedure & Certificates
Assess and approve of Factory Acceptance Tests (FAT) / First Article Inspection (FAI)
Reports
Verify compliance & conformity to Technical Standards as defined in the Technical
Specification
Verify conformity with Technical & Homologation requirements determined by
Israel Ministry of Transport
Administration work, documentation and reporting to ISR
Verify results of tests against predetermined test criteria and other supporting
technical documents to be provided by the manufacturer; issue corresponding
reports to ISR for its Acceptance
Issue of Inspection, Quality Control & Deviation Reports
2.5 Lab Tests, Installation Tests, Odometry Tests and Final Acceptance Tests The scope of work includes, but not limited to, the following activities:
Verify, witness and supervise all System-Level Serial Acceptance Test &
Commissioning
Approve the detailed Inspection and Test Plan for Serial Acceptance Tests
Appraisal and approval of Serial Acceptance Tests for selected modules, which shall
be defined after the completion of the Design Review
Assess the Serial Acceptance Test program at different levels, the completeness of
the entire test program and the content of the individual test procedures
Verify compliance & conformity to Technical Standards as defined in the Technical
Specification
Administration work, documentation and reporting to ISR
Witnessing of the routine tests on each trainset; issue of the related certificates
related to project milestones
Issue of Inspection, Quality Control & Deviation Reports
Verify results of tests against predetermined test criteria and other supporting
technical documents to be provided by the manufacturer & issue corresponding
reports to ISR for its Final Acceptance
Assess Serial Acceptance Tests Procedure & Certificates
Assess and approve of Serial Acceptance Test Reports
Check & Approve Test Equipment
7
Participate in Technical Meetings with the Manufacturer and the Sub-Supplier &
Review of Minutes of Meetings
Verify conformity with Technical & Homologation requirements determined by
Israel Ministry of Transport
Confirm Final Test Results and issue the Final Approval / Rejection
Recommendations
Issue Final Test Reports
Issue Punch-Lists including Blocking Issues with agreed dates for their correction by
the manufacturer
Check for correct assembly & installations of all components and their secure
interoperability with existing systems as well as attachment to the structure, and
issue Corresponding Reports
Software
o Software interoperability with system components
o Check software testing management
o Software versions control & traceability
Cyber & Security
o Check conformity to security and safety requirements for Software (reports)
o Check all cyber security aspects in the train IT (reports)
Take any measures necessary to ensure successful delivery of the Serial Units & their
Handover to Operations / Maintenance
Preparation and presentation of Final Acceptance Report per trainset to ISR Project
Manager for Approval
3 Project Management Activities The scope of work includes, but not limited to, the following activities:
Overall Supervision Project Management Responsibility
Interface with Project Management of ISR
Technical risk identification & recommendation to ISR Project Manager for remedial
actions
Definition of the interface with the contractor; Establishment of the inspectors'
office at the contractors' site
Management meetings with ISR and the contractor
Supervision of inspectors & technical experts in Supervision Team
Planning of supervision activities and personnel
Organization of regular meetings with the employer
Organization and conducting design reviews on technical milestones (e.g. "Design
Freeze"), preparation of the reports
Conducting the project progress meetings with contractor
Scheduling shop inspections with contractor
Organization of the witnessing program for the type tests
Release of monthly progress reports, inspection reports and type test reports to ISR
Project Managers
Release of Final Reports
8
4 Tests Description
4.1 General This section covers a general description, definition and logical order of the tests
required for accepting a system, including the following:
Factory Acceptance Test & On-Board sub-systems (EVC, BTM, Radio, JRU etc.)
On-Board System Tests - including Laboratory Tests, Installations (Electrical
and Mechanical), EMC / EMI Tests, Odometry Tests, and Final Acceptance
Tests. The FA (Final Acceptance) tests gather all the related to test each LRU
Interfacing with each other and/or the train. This includes On-board +
Wayside Equipment Tests, where the ETCS system (On-Board) is tested
interfacing with the wayside system, as a full system (ERTMS).
Each type of test includes where the tests area carried out and quantity of units that
are required to be tested by the supervision company.
This section draws the BASELINE for the tests & inspections the Supervision
Company shall carry out. ISR Expects the Supervision Company to create a
COMPLETE & FINAL TESTS & INSPECTIONS DOCUMENTS based on the guidelines set-
forth in this section.
4.2 On-Board Factory Acceptance Tests
4.2.1 OB Sub-Systems Description
OB Sub-System #
GSM / GPS Antenna 1
GSM Antenna 2
Doppler Radar 3
Balise Antenna 4
Wheel Speed Sensor 5
ETCS Enclosure (EVC + Other) 6
EDOR 7
JRU 8
DMI 9
4.2.2 Sub-Systems Inspection & OB Factory Acceptance Tests
4.2.2.1 OB Sub-Systems Inspection
Inspection:
As all sub-systems are COT (Commercial Out of Shelf), certificates / documentation check as
described under 2.4 above are sufficient
Where:
Manufacturer's Facilities
Quantity:
1 Sub-System Inspection per sub-system defined under 4.2.1 above - Total of 9 Sub-System
Inspections
9
4.2.2.2 OB Factory Acceptance Tests
Inspection:
Tests that are targeted for Verification of quality standards, specifications, size and
other intrinsic characteristics of the equipment.
The Factory Acceptance Tests include, but not limited to Electrical & Mechanical
aspects as follows: Shock and Vibration, Environmental, EMC/EMI, Continuity
checks, Power supply, cabling, insulation, among others.
Factory Acceptance Tests are USUALLY carried out following a list like the following
EXAMPLE:
Ref. First Article Inspection - Criteria Required
(Yes / No)
Reference
Documents /
Evidence / Actions
Status
(OK /
NOK)
01 Completed and signed copy of
Quality, Environmental, Safety &
Health (QUENSH) Contract Conditions
Menu.
02 Drawing Pack (Confirmation of
Approval signatures and record
document Number / revision).
03 Specification (Confirmation of
Approval signatures and record
document number / revision).
04 Compliance Document (Clause by
clause statement confirming how
each of the approved Specification /
Drawing requirements and specified
QUENSH menus have been met).
05 In-house Production Drawings – If
applicable (Must include indication of
approval sign off / acceptance of
current revision and record Doc.
No./Rev.)
06 Bill of Materials (Record latest Doc.
No./Rev.)
07 In process Mechanical / Dimensional /
Electrical Test / Inspection Results for
1st Production sample (To verify
10
Ref. First Article Inspection - Criteria Required
(Yes / No)
Reference
Documents /
Evidence / Actions
Status
(OK /
NOK)
compliance with approved
Specification & Drawing
requirements).
08 All required / specified Type Testing
certificates (Temperature / Humidity
/ Vibration / Shock / EMC / IP /
Acoustics / etc.).
09 Completed Factory Acceptance Test
(FAT), to approved Test Specification
/ Procedure, with applicable Test
Results for: Test & Commissioning;
Visual Inspection; Wire counts; Power
connections; Voltage continuity & Bell
checks; Ground Bonding &
Meggaring; etc.
10 Completed Test & Commissioning -
TC2 Records & Results, relating to 1st
off sample, as defined in the FAT
Specification / Procedure.
11 Evidence of valid staff qualification (if
applicable).
12 Calibration records (For Electrical /
Mechanical measuring equipment
used on 1st off sample).
13 Material data sheets / Certificates of
Conformity for ALL flammable /
combustible materials / Low Smoke
Zero Halogen (LSZH).
14 1 x 1st off Production Sample must be
available for inspection (For
Dimension / Tolerance checks; to
demonstrate functionality; and for
electrical testing, where applicable).
15 Configuration Log for production 1st
off sample (and for all Line
11
Ref. First Article Inspection - Criteria Required
(Yes / No)
Reference
Documents /
Evidence / Actions
Status
(OK /
NOK)
Replacement Units that make up the
asset, including: Part No.; Item
Change Status; Serial No.; Batch No.;
and Bar Code No.)
16 Certificate of Conformity for FAI
sample (In-line with QUENSH CofC
criteria and to ref. “Manufactured in
accordance with: Specification No. /
Rev.; Drawing No. / Rev.; etc.).
17 Certificates of Conformance and
CofC’s for Commercial Off The Shelf
(COTS) Line Replacement Units
(LRU’s).
18 Hardcopy and Softcopy of entire FAI
evidence pack (all above documents)
available and ready for handover at
FAI.
19 Inspection Test Plan agreed
20 Packing revision
Where:
Manufacturer's Facilities
Quantity:
Factory Acceptance Tests are generic (for all prototypes) and therefore are carried-out only
once in the project.
12
4.3 On-Board System
4.3.1 OB Systems Description
Total QTY OB System NTP
24 Vossloh Euro 3200 NTP1
64 Bombardier DD-PC
48 Vossloh JT-42 BW
1 Plasser Crane Yellow Machine
22 Bombardier DD-PC NTP2
14 Siemens SD_PP
15 Vossloh Euro 4000
7 Vossloh JT 42 CW
2 Giesmar-Ballast Regulator Optional
3 P&T Rail Tamping Machine
1 P&T Measuring Vehicle
1 Geismar – Weed Killing Track Motorcar
7 P&T – Yellow Vehicles
4.3.2 OB Systems Inspection
4.3.2.1 Lab Tests
Inspection:
Controlled Tests using specific HW and SW for the ISR Project
Where:
Manufacturer's Laboratories
Quantity:
Lab Tests are generic (for all prototypes) and therefore are carried-out only once in the
project.
4.3.2.2 Installation Test
Inspection:
Installation Acceptance Tests shall include, but not limited to, the following:
Mechanical - Torque settings marks, cable routing, cable and looms fixation,
maximum radius of cable, installation certificates, measurement of
mechanical parts and installation of fixings, brackets, others.
Electrical – Continuity check on new Cables or harnesses, Indentation checks
(Label of cables and pins), Megger tests (Insulation resistance), Earth bonding
tests
Where:
In Depot. Access to undercarriage equipment (Pit) and roof may be required.
Quantity:
Proto – Installation Tests will be conducted per OB System Prototype defined under
4.3.1 above - Total of 13 OB-System Inspections
13
Serial – Sample 30% (total of 63 Tests for all types of vehicles altogether)
4.3.2.3 Electromagnetic Field Measurements (EMC/EMI)
Inspection:
The measurements are intended to demonstrate pertaining EMC/EMI EN requirements.
Where:
On Depot
Quantity:
Proto Only – EMC / EMI Tests will be conducted per OB System Prototype defined
under 4.3.1 above - Total of 13 OB-System Inspections
4.3.2.4 Odometry Test
Inspection:
As described in Odometry Test Documentation by the Manufacturer.
Where:
On "Test Tracks"
Quantity:
Proto Only – Odometry Tests will be conducted per OB System Prototype defined
under 3.14. above - Total of 13 OB-System Inspections
4.3.2.5 Final Acceptance Test
Inspection:
These tests comprehend all the required tests prior for commissioning the equipment, and
include STATIC TESTS and DYNAMIC TESTS as follows:
Static Tests
Tests of individual on-board equipment working together in a static environment,
while equipment and train are powered up.
Testing equipment is required, including but not limited to the following:
Computers and cables (to read logs), Multimeter, VSWR reader, breakout boxes, Test
rigs (to simulate signals), measuring tape, bubble or electronic level, laser distance
meter, etc.
Tests may include, but are not limited to, the following:
Verify Rack Installation and Cable Connections
Verify Balise Antenna and BTM
14
Verify Train Power Supplies
Verify Accelerometer
Verify Radio Antenna Installation (GPS/GSM and GSM)
Verify Doppler Radar
Verify Operation of cabin control
Verify Emergency Break (EB) Interface
Verify Availability of EVC (2oo3)
Verify Tachometer Movement
Verify Operation of the DMI
Verify EDOR
Verify GSM-Voice
Verify JRU
Dynamic Tests
Tests of the on-board equipment working together in a dynamic environment,
including interface testing between on-board and wayside equipment.
These tests are conducted with equipment and train powered up. Connection with
the RBC is also required.
The OCC (Operation Control Center) is also involved in the dynamic tests, as it
provides important inputs for Dynamic Test Scenarios (routes to test, platform
stopping points, stopping locations, level crossings etc.)
Where:
Static Tests - In Depot. Access to undercarriage equipment (Pit) and roof may be
required
Dynamic Tests - On "Test Tracks" fitted with ERTMS
Quantity:
Proto – Final Acceptance Test will be conducted per OB System Prototype defined
under 4.3.1 above - Total of 13 OB-System Inspections
Serial –
o Sample 30% (total of 63 Tests for all types of vehicles altogether)
o Each ERTMS area shall be tested
15
5 Schedule Baseline
5.1 General Design per Vehicle Type (Ongoing 2019-2022) Provide support throughout the Project, as needed, with the following design activities:
Generic ETCS System Engineering
Generic RAM studies
Generic V&V Engineering
Generic Safety Studies
Generic Installation Design
Generic Maintenance Engineering
Operation & Maintenance Deliverables
5.2 NTP1 – Approximate Timeline
5.2.1 Vossloh Euro 3200 Prototype:
Prototype Installation: November 2020
T&C + Installation Acceptance tests + SC (Safety Case): December. 2020
Serial:
Installation Acceptance Tests + Final Acceptance Tests + Handover, Sample
30% of fleet: June. 2021 – November 21
5.2.2 Bombardier DD-PC Proto:
Prototype Installation: October 2020
T&C + Installation Acceptance tests + SC (Safety Case): Nov. 20
Serial:
Installation Acceptance Tests + Final Acceptance Tests + Handover, Sample
30% of fleet: may. 21– March. 22
5.2.3 Vossloh JT42 BW Proto:
Prototype Installation: July. 21
T&C + Installation Acceptance tests + SC (Safety Case): august. 21
Serial:
Installation Acceptance Tests + Final Acceptance Tests + Handover, Sample 30% of fleet: Nov. 21 to jun. 22
16
5.2.4 Plasser obw10
Proto:
Prototype installation: spe.20
T&C + Installation Acceptance tests + SC (Safety Case) phase 1: oct.20
5.3 NTP2 – Approximate Timeline
5.3.1 Siemens SD-PP Proto:
Prototype Installation, one prototype: March. 22
T&C + Installation Acceptance tests + SC (Safety Case), one prototype: April 22 –
may. 22
Serial:
Installation Acceptance Tests + Final Acceptance Tests + Handover, Sample 30%
of fleet: Aug. 22 – Feb. 23
5.3.2 Vossloh Euro 4000 Proto:
Prototype Installation: aug. 22
T&C + Installation Acceptance tests + SC (Safety Case): spt. 22 – Oct. 22
Serial:
Installation Acceptance Tests + Final Acceptance Tests + Handover, Sample
30% of fleet: nuv.22 – Jun. 23
5.3.3 Vossloh JT42 CW Proto:
Prototype Installation: oct 22
T&C + Installation Acceptance tests + SC (Safety Case): nov.22 – Dec. 22
Serial:
Installation Acceptance Tests + Final Acceptance tests + Handover, Sample
30% of fleet: mar. 23 – May. 23
Note: Scope of this Call-Off may change
5.4 Optional Works – Timeline TBD 5 prototypes and 29 serial vehicles as follows:
17
5.4.1 Proto
1 Giesmar Ballast Regulator
1 Plasser & Theurer Rail Tamping Machine
1 Plasser "& Theurer Measuring Vehicle
1 Plasser & Theurer Geismar Weed Killing Track Motorcars
1 Plasser & Theurer Vehicles
5.4.2 Serial
1 Giesmar Ballast Regulator
2 Plasser & Theurer Rail Tamping Machines
6 Plasser & Theurer Vehicles
18
6 List of Attachments 1. Attachment A Technical Specification of ETCS On-Board
2. Attachment B Agreement No. 91944 for the ETCS On-Board
3. Attachment C Delivery Schedule of ETCS On-Board