executive summary - aeso · executive summary project overview ... existing transmission system in...
TRANSCRIPT
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 1 Public
R3-2015-07-01
Executive Summary
Project Overview
ENMAX Power Corporation (EPC), in its capacity as the legal owner of an electric distribution
system (DFO), has submitted a request for system access service to the Alberta Electric
System Operator (AESO), to reliably serve load growth within the City of Calgary.
The DFO’s request for system access service includes a request for a Rate DTS, Demand
Transmission Service, contract capacity increase of 5 MW, from 35 MW to 40 MW, for the
system access service provided at the existing SS-7 substation,1 and a request for transmission
development (collectively, the Project). Specifically, the DFO requested upgrades to the existing
SS-7 substation.
The requested in-service date (ISD) for the Project is December, 2018.
This report details the engineering studies undertaken to assess the impact of the Project on the
performance of the Alberta interconnected electric system (AIES).
Existing System
Geographically, the Project is located in the AESO planning area of Calgary (Area 6), which is
part of the AESO Calgary Planning Region. Calgary (Area 6) is adjacent to the planning areas
of Seebe (Area 44), Airdrie (Area 57), Strathmore / Blackie (Area 45), and High River (Area 46).
From a transmission system perspective, Calgary (Area 6) consists primarily of 138 kV and
240 kV transmission systems. The existing SS-7 substation is a point-of-delivery (POD)
substation, which is connected to the AIES by two existing 138 kV transmission lines:
138 kV transmission line 7.82L, which connects the SS-7 substation to Sarcee 42S
substation; and,
138 kV transmission line 7.84L, which connects the SS-7 substation to SS-36 substation.
The existing constraints in the Calgary Planning Region are managed in accordance with the
procedures set out Section 302.1 of the ISO Rules, Real Time Transmission Constraint
Management (TCM Rule).
Study Summary
Study area for the Project
The Study Area for the Project consists of Calgary (Area 6), including the tie lines connecting
Calgary (Area 6) to the rest of the AIES. All transmission facilities within the Study Area were
studied and were monitored to assess the impact of the Project on the performance of the AIES,
including any violations of the Reliability Criteria (as defined in Section 2.1.1).
1 The SS-7 substation is also referred to as the No. 7 Substation.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 2 Public
R3-2015-07-01
Studies performed for the Project
Power flow studies were performed for the 2018 winter peak (2018 WP) and the 2019 summer
peak (2019 SP) pre-Project and post-Project scenarios.
Voltage stability studies were performed for the 2018 WP post-Project scenario.
Results of the Pre-Project Studies
No Reliability Criteria violations were observed under the Category A condition. A thermal
criteria violation was observed under Category B conditions. No voltage criteria violations were
observed under Category B conditions.
Connection Alternatives
The AESO, in consultation with the DFO and the legal owner of transmission facilities (TFO)
examined three connection alternatives to meet the DFO’s request for system access service:
Alternative 1- Replace Two Transformers at SS-7 Substation
Alternative 1 involves upgrading the existing SS-7 substation, including replacing both of the
existing 138/25 kV transformers with two 138/25 kV transformers of higher capacity.
Alternative 1 also involves adding one 138 kV circuit breaker, and associated equipment. In
addition, Alternative 1 involves adding a new 25 kV distribution feeder, approximately 5 km in
length.
Alternative 2- Add a Third Transformer at SS-7 Substation
Alternative 2 involves upgrading the existing SS-7 substation, including adding one 138/25 kV
transformer. Alternative 2 also involves adding one 138 kV circuit breaker, four 25 kV feeder
circuit breakers and associated equipment. To complete the required upgrades, the TFO has
advised the AESO that expansion and/or modification of the 138 kV and 25 kV busses would be
required. In addition, Alternative 2 involves adding a total of approximately 14 km of 25 kV
distribution feeders.
Alternative 3- Replace one Transformer at SS-7 Substation and Add a Transformer at SS-
28 Substation
Alternative 3 involves upgrading the existing SS-7 substation, including replacing one of the
existing 138/25 kV transformers with one 138/25 kV transformer of higher capacity and adding
one 138 kV circuit breaker and associated equipment. Alternative 3 also involves upgrading the
existing SS-28 substation, including adding one 138/25 kV transformer, one 138 kV circuit
breaker, four 25 kV circuit breakers and associated equipment. In addition, Alternative 3
involves adding a total of approximately 10 km of 25 kV distribution feeders.
Connection Alternative Selected for Further Examination
Alternative 1 was selected for further examination. Alternative 2 and Alternative 3 would both
involve increased transmission and distribution development, and hence overall increased cost
compared to Alternative 1. Therefore, these alternatives were not selected for further study.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 3 Public
R3-2015-07-01
Results of the Post-Project Studies
No Reliability Criteria violations were observed under the Category A condition. Identical to the
pre-Project studies, a thermal criteria violation was observed under Category B conditions. No
voltage criteria violations were observed under Category B conditions. The voltage stability
margin was met for all studied conditions.
Mitigation Measures
The thermal criteria violation, observed both pre-Project and post-Project, is currently being
managed by real time operational practices, and can continue to be managed by real time
operational practices in the future. This thermal criteria violation will be permanently mitigated
once the Downtown Calgary 138 kV Transmission Reinforcement Project is in service.
Conclusions and Recommendations
Based on the study results, Alternative 1 is technically viable. The connection assessment
identified a system performance issue, which was identical in pre-Project and post-Project
scenarios. Real-time operational practices can continue to be used to manage the identified
system performance issue, until the Downtown Calgary 138 kV Transmission Reinforcement
Project is in service.
It is recommended to proceed with the Project using Alternative 1 as the preferred option to
respond to the DFO’s request for system access service. It is also recommended to use real-
time operational practices to manage the identified system performance issue.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 4 Public
R3-2015-07-01
Contents
Executive Summary .................................................................................................................................... 1 1. Introduction ......................................................................................................................................... 5
1.1. Project............................................................................................................................................ 5 1.1.1. Project Overview .................................................................................................................... 5 1.1.2. Load Component ................................................................................................................... 5 1.1.3. Generation Component ......................................................................................................... 5
1.2. Study Scope .................................................................................................................................. 5 1.2.1. Study Objectives .................................................................................................................... 5 1.2.2. Study Area ............................................................................................................................. 6 1.2.3. Studies Performed ................................................................................................................. 8
1.3. Report Overview ............................................................................................................................ 8 2. Criteria, System Data, and Study Assumptions ............................................................................. 10
2.1. Criteria, Standards, and Requirements ....................................................................................... 10 2.1.1. AESO Standards and Reliability Criteria ............................................................................. 10 2.1.2. ISO Rules and Information Documents ............................................................................... 11
2.2. Study Scenarios .......................................................................................................................... 11 2.3. Load and Generation Assumptions ............................................................................................. 11
2.3.1. Load Assumptions ............................................................................................................... 11 2.3.2. Generation Assumptions ..................................................................................................... 12 2.3.3. Intertie Flow Assumptions ................................................................................................... 13 2.3.4. HVDC Power Order ............................................................................................................. 13
2.4. System Projects ........................................................................................................................... 14 2.5. Connection Projects .................................................................................................................... 14 2.6. Facility Ratings and Shunt Elements ........................................................................................... 14 2.7. Voltage Profile Assumptions ....................................................................................................... 17
3. Study Methodology ........................................................................................................................... 19 3.1. Connection Studies Carried Out .................................................................................................. 19 3.2. Power Flow Studies ..................................................................................................................... 19
3.2.1. Contingencies Studied ......................................................................................................... 19 3.3. Voltage Stability Studies .............................................................................................................. 20
3.3.1. Contingencies Studied ......................................................................................................... 20 4. Pre-Project System Assessment ..................................................................................................... 21
4.1. Power Flow .................................................................................................................................. 21 4.1.1. Scenario 1: 2018 WP Pre-Project ........................................................................................ 21 4.1.2. Scenario 2: 2019 SP Pre-Project ......................................................................................... 21
5. Connection Alternatives ................................................................................................................... 22 5.1. Overview ...................................................................................................................................... 22 5.2. Connection Alternatives Identified ............................................................................................... 22
5.2.1. Connection Alternatives Selected for Further Studies ......................................................... 22 5.2.2. Connection Alternatives Not Selected for Further Studies .................................................. 23
6. Technical Analysis of the Connection Alternative ........................................................................ 24 6.1. Power Flow .................................................................................................................................. 24
6.1.1. Scenario 3: 2018 WP Post-Project ...................................................................................... 24 6.1.2. Scenario 4: 2019 SP Post-Project ....................................................................................... 24
6.2. Voltage Stability ........................................................................................................................... 24 6.2.1. Scenario 3: 2018 WP Post-Project ...................................................................................... 24
7. Mitigation Measures .......................................................................................................................... 26 8. Project Interdependencies ............................................................................................................... 27
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 5 Public
R3-2015-07-01
9. Conclusion and Recommendations ................................................................................................ 28
Attachments
Attachment A Pre-Project Power Flow Diagrams (Scenarios 1 & 2)
Attachment B Post-Project Power Flow Diagrams (Scenarios 3 & 4)
Attachment C Post-Project Voltage Stability Diagrams (Scenario 3)
Figures
Figure 1-1: Existing Transmission System in the Study Area ......................................................................................... 7
Tables
Table 2.1-1: Post Contingency Voltage Deviation Guidelines ...................................................................................... 11 Table 2.2-1: List of the Connection Study Scenarios ................................................................................................... 11 Table 2.3-1: Forecast Area Load (2016 LTO at Calgary Planning Region Peak) ........................................................ 12 Table 2.3-2: Existing Generator Dispatch in the Study Scenarios ................................................................................ 12 Table 2.3-3: HVDC Power Order by Scenario .............................................................................................................. 13 Table 2.4-1: System Projects in the Study Area ........................................................................................................... 14 Table 2.5-1: Connection Projects Included in the Studies ............................................................................................ 14 Table 2.6-1: Transmission Line Ratings in the Study Area .......................................................................................... 15 Table 2.6-2: Ratings of Key Transformers in the Study Area ....................................................................................... 16 Table 2.6-3: Details of Shunt Elements in the Study Area ........................................................................................... 17 Table 3.1-1: Engineering Studies Performed ............................................................................................................... 19 Table 4.1-1: Thermal Criteria Violations for the 2019 SP Pre-Project Scenario Under Category B Conditions ............ 21 Table 6.1-1: Thermal Criteria Violations for the 2019 SP Post-Project Scenario Under Category B Conditions .......... 24 Table 6.2-1: Voltage Stability Analysis Results for the 2018 WP Post-Project Scenario .............................................. 25
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 5 Public
R3-2015-07-01
1. Introduction
This report details the engineering studies conducted to assess the impact of the Project (as
defined below) on the performance of the Alberta interconnected electrical system (AIES).
1.1. Project
1.1.1. Project Overview
ENMAX Power Corporation (EPC), in its capacity as the legal owner of an electric distribution
system (DFO), has submitted a request for system access service to the Alberta Electric
System Operator (AESO), to reliably serve load growth within the City of Calgary.
The DFO’s request for system access service includes a request for a Rate DTS, Demand
Transmission Service, contract capacity increase of 5 MW, from 35 MW to 40 MW, for the
system access service provided at the existing SS-7 substation,2 and a request for transmission
development (collectively, the Project). Specifically, the DFO requested upgrades to the existing
SS-7 substation.
The requested in-service date (ISD) for the Project is December, 2018.
1.1.2. Load Component
The Project includes a load component:
The existing Rate DTS contract capacity for the system access service provided at the existing SS-7 substation is 35 MW.
The DFO requested a Rate DTS contract capacity of 40 MW on December, 2018
The project load was studied assuming a 0.9 power factor (pf) lagging.
Load type: residential and commercial loads.
1.1.3. Generation Component
There is no generation component associated with the Project.
1.2. Study Scope
1.2.1. Study Objectives
The objectives of the studies are as follows:
Assess the impact of the Project on the performance of the AIES.
2 The SS-7 substation is also referred to as the No. 7 Substation.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 6 Public
R3-2015-07-01
Identify any violations of the relevant AESO criteria, standards or requirements, both pre-Project and post-Project.
Recommend mitigation measures, if required, to reliably connect the Project to the AIES.
1.2.2. Study Area
1.2.2.1. Study Area Description
Geographically, the Project is located in the AESO planning area of Calgary (Area 6), which is
part of the AESO Calgary Planning Region. Calgary (Area 6) is adjacent to the planning areas
of Seebe (Area 44), Airdrie (Area 57), Strathmore / Blackie (Area 45), and High River (Area 46).
From a transmission system perspective, Calgary (Area 6) consists primarily of 138 kV and
240 kV transmission systems. The existing SS-7 substation is a point-of-delivery (POD)
substation, which is connected to the AIES by two existing 138 kV transmission lines:
138 kV transmission line 7.82L, which connects the SS-7 substation to Sarcee 42S
substation; and,
138 kV transmission line 7.84L, which connects the SS-7 substation to SS-36
substation.
The Study Area for the Project consists of Calgary (Area 6), including the tie lines connecting
Calgary (Area 6) to the rest of the AIES. All transmission facilities within the Study Area were
studied and were monitored to assess the impact of the Project on the performance of the AIES,
including any violations of the Reliability Criteria (as defined in Section 2.1.1).
Figure 1-1 shows the existing transmission system in the Study Area.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 7 Public
R3-2015-07-01
Figure 1-1: Existing Transmission System in the Study Area
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 8 Public
R3-2015-07-01
1.2.2.2. Existing Constraints
The existing constraints in the Calgary Planning Region are managed in accordance with the
procedures set out Section 302.1 of the ISO Rules, Real Time Transmission Constraint
Management (TCM Rule).
1.2.2.3. AESO Long-Term Transmission Plan
The AESO 2015 Long-term Transmission Plan (2015 LTP) 3 includes the following system
transmission developments in the Study Area in the near term (to 2020):4
Build new 240 kV line from East Calgary substation in Highfield industrial area to SS-8 substation in northwest corner of downtown Calgary
Convert SS-8 to 240/138 kV substation
Add new 138 kV line between SS-47 substation north of Calgary airport and SS-36substation in northwest Calgary
Add new 138 kV line from SS-22 substation south of Calgary airport to SS-23 substation in Valleyfield industrial area of Calgary
Build 240 kV double-circuit line to connect Beddington (SS-162) substation in northeast Calgary to one of the 240 kV lines between Red Deer and Calgary in an in/out configuration
The above developments were not included in the system topology for the pre-Project and post-
Project studies because these transmission developments are not expected to be in service
before the scheduled Project ISD.
1.2.3. Studies Performed
The following studies were performed for the pre-Project scenarios:
Power flow studies
The following studies were performed for the post-Project scenarios:
Power flow studies
Voltage stability studies
1.3. Report Overview
The Executive Summary provides a high-level summary of the study and its conclusions.
Section 1 provides an introduction to the Project and provides a high-level description of the
study scope. Section 2 describes the criteria, system data, and other assumptions used in the
studies. Section 3 describes the study methodology. Section 4 discusses the pre-Project studies
results. Section 5 presents the alternatives examined and selected for further study. Section 6
3 The 2015 LTP document is available on the AESO website.
4 The 2015 LTP identifies the transmission developments in the City of Calgary sub-region on page 36.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 9 Public
R3-2015-07-01
provides post-Project studies results. Section 7 discusses the mitigation measures, if any,
required to enable the reliable connection of the Project to the AIES. Section 8 identifies any
dependencies the Project may have. Section 9 presents the conclusions and recommendations
of this assessment.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 10 Public
R3-2015-07-01
2. Criteria, System Data, and Study Assumptions
2.1. Criteria, Standards, and Requirements
2.1.1. AESO Standards and Reliability Criteria
The Transmission Planning (TPL) Standards, which are included in the Alberta Reliability
Standards, and the AESO’s Transmission Planning Criteria – Basis and Assumptions
(collectively, the Reliability Criteria) were applied to evaluate system performance under
Category A system conditions (i.e., all elements in-service) and following Category B
contingencies (i.e., single element outage) prior to and following the studied alternatives. Below
is a summary of Category A and Category B system conditions.
Category A, often referred to as the N-0 condition, represents a normal system with no
contingencies and all facilities in service. Under this condition, the system must be able to
supply all firm load and firm transfers to other areas. All equipment must operate within its
applicable rating, voltages must be within their applicable range, and the system must be stable
with no cascading outages.
Category B events, often referred to as an N-1 or N-G-1 with the most critical generator out of
service, result in the loss of any single specified system element under specified fault conditions
with normal clearing. These elements are a generator, a transmission circuit, a transformer, or a
single pole of a DC transmission line. The acceptable impact on the system is the same as
Category A. Planned or controlled interruptions of electric supply to radial customers or some
local network customers, connected to or supplied by the faulted element or by the affected
area, may occur in certain areas without impacting the overall reliability of the interconnected
transmission systems. To prepare for the next contingency, system adjustments are permitted,
including curtailments of contracted firm (non-recallable reserved) transmission service electric
power transfers.
The Alberta Reliability Standards include the Transmission Planning (TPL) standards that
specify the desired system performance under different contingency categories with respect to
the Applicable Ratings. The transmission system performance under various system conditions
is defined in Appendix 1 of the TPL standards. For the purpose of applying the TPL standards to
this study, the Applicable Ratings shall mean:
Seasonal continuous thermal rating of the line’s loading limits.
Highest specified loading limits for transformers.
For Category A conditions: Voltage range under normal operating condition per the
AESO Information Document # 2010-007RS007RS General Operating Practices –
Voltage Control (ID #2010-007RS). ID #2010-007RS relates to Section 304.4 of the ISO
rules, Maintaining Network Voltage. For the busses not listed in ID#2010-007RS, Table
2-1 in the Transmission Planning Criteria – Basis and Assumptions applies.
For Category B conditions: The extreme voltage range values per Table 2-1 in the
Transmission Planning Criteria – Basis and Assumptions.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 11 Public
R3-2015-07-01
Desired post-contingency voltage change limits for three defined post event timeframes as provided in Table 2.1-1.
Table 2.1-1: Post Contingency Voltage Deviation Guidelines
Parameter and reference point
Time Period
Post Transient (up to 30 sec)
Post Auto Control (30 sec to 5 min)
Post Manual Control (Steady
State)
Voltage deviation from steady state at POD low voltage bus.
±10% ±7% ±5%
2.1.2. ISO Rules and Information Documents
ID #2010-007RS will be applied to establish pre- contingency voltage profiles in the Study Area.
The TCM Rule was followed in setting up the study scenarios and assessing the impact of the
Project. In addition, due regard was given to the AESO’s Connection Study Requirements
document and the AESO’s Generation and Load Interconnection Standard.
2.2. Study Scenarios
The scheduled ISD of the Project is December, 2018. Therefore, the studies were performed
using the 2018 winter peak (WP) and 2019 summer peak (SP) and scenarios.
Table 2.2-1 provides a list of the study scenarios. This connection assessment will assume a
pf of 0.9 lagging for the load associated with the Project.
Table 2.2-1: List of the Connection Study Scenarios
Scenario No.
Year/Season Load
Pre-Project/Post-
Project
Project Load (MW)
System Generation Dispatch
Conditions
1 2018 WP Pre-project 0
Zero inter-tie, zero wind
2 2019 SP Pre-project 0
3 2018 WP Post-Project 5 (total of 40)
4 2019 SP Post-Project 5 (total of 40)
2.3. Load and Generation Assumptions
2.3.1. Load Assumptions
The AESO planning area and region forecasts used for the studies are shown in Table 2.3-1
and are based on the AESO 2016 Long-term Outlook (2016 LTO) at Calgary Planning Region
peak. For the studies, when POD loads for the Alberta internal load (AIL) were modified to align
with the load forecast from the 2016 LTO, the active power to reactive power ratio in the base
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 12 Public
R3-2015-07-01
case scenarios was maintained. While the AESO has updated its regional forecasts since the
connection studies were performed, the use of the current AESO forecast, the AESO 2017
Long-term Outlook, would not materially alter the connection study results or affect the
conclusions and recommendations in this report.
Table 2.3-1: Forecast Area Load (2016 LTO at Calgary Planning Region Peak)
AESO Planning Area or Region
Year/Season Forecast
Peak Load (MW)
Calgary (Area 6) 2018 WP 1662
2019 SP 1692
Calgary Planning Region
2018 WP 1778
2019 SP 1800
2.3.2. Generation Assumptions
The generation assumptions for the studies are described in Table 2.3-2.The study identified the
gas turbine generator (CECGT) at the Calgary Energy Centre plant at Beddington SS-162
substation as the critical generator and it was turned off to represent the N-G study condition for
all studies. As a consequence of the CECGT being turned off in the study, the steam generator
(CECST) at the Calgary Energy Centre plant was also turned off in the study, as CECST is
dependent on CECGT.
Table 2.3-2: Existing Generator Dispatch in the Study Scenarios
Generating Facility Name/Type and Unit Code
Unit ID
Bus Number
AESO Planning
Area
Pmax (MW)
Unit Net Generation (MW)
a
2018 WP 2019 SP
Enmax Calgary Energy Center
CEC GT n/a 4187 6 320
N-Gb
CEC ST n/a 3187 N-Gb
Bow River Hydro
Spray G1 1 174
44
97 49.2 47.7 Spray G2 2A 190
Three S9 1 381 3 1.5 1.5
Kananas9 1 196
19 9.6 9.3 Kananas9 2 196
Kananas9 3 196
POCATEA9 1 214 13 6.6 6.4
Rundle H 1 479 48 24.4 23.5
Rundle G 2 197
GHOST G9 1 3181
58 29.4 28.4 GHOST A9 2 181
GHOST A9 3 181
GHOST G9 4A 181
HORS GEN 1 172 16 8.1 7.8
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 13 Public
R3-2015-07-01
Generating Facility Name/Type and Unit Code
Unit ID
Bus Number
AESO Planning
Area
Pmax (MW)
Unit Net Generation (MW)
a
2018 WP 2019 SP
HORS GEN 2 172
HORS GEN 3 172
HORS GEN 4 172
INTERLA9 1 377 5 2.5 2.4
BARRIER9 1 222 11 5.6 5.4
BEARSPWB 1 183 16 8.1 7.8
CASCADE9 1 176 34 17.3 16.6
CASCADE9 2 176
Shepard
SECCT1 2 774
6 860 444 454 SECCT2 3 775
SECST 1 773
Nexen Inc #1
BALZ 3 1 4290
6 120 28 24 BALZ 1&2 2 3290
BALZ 1&2 3 4290
a “Unit Net Generation” refers to gross generating unit output (MW) less unit service load.
b “N-G” indicates the critical generating unit that is assumed by the AESO to be offline to test the N-G
contingency condition
2.3.3. Intertie Flow Assumptions
Intertie assumptions are included for the British Columbia-Alberta (BC-AB), Saskatchewan-
Alberta (SK-AB), and Montana-Alberta Tie Line (MATL) interties. All interties were assumed to
have zero import and zero export for all study scenarios.
2.3.4. HVDC Power Order
The Western Alberta Transmission Line (WATL) and the Eastern Alberta Transmission Line
(EATL) are high-voltage direct current (HVDC) transmission lines. The HVDC power order
assumptions for the studies will be set to minimize losses for the pre-Project and post-Project
study scenarios, as shown in Table 2.3-3.
Table 2.3-3: HVDC Power Order by Scenario
Scenario No. Scenario Name WATL (MW) EATL (MW)
1 2018 WP Pre-Project 900 N S Blocked
2 2019 SP Pre- Project 800 N S Blocked
3 2018 WP Post - Project 900 N S Blocked
4 2019 SP Post- Project 800 N S Blocked
Notes: N S indicates that HVDC flow direction is North to South
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 14 Public
R3-2015-07-01
2.4. System Projects
Table 2.4-1 lists the system transmission projects that occur within the Study Area and indicates
whether they were included in the studies. The near-term system projects identified in the 2015
LTP (see Section 1.2.2.3) were not considered in the studies.
Table 2.4-1: System Projects in the Study Area
AESO Project
No. AESO Project Name
Scheduled ISD
AUC Decision
No.
AUC NID Approval
No.
Date of original
AUC approval
Included/ Excluded
from Studies
1354 Foothills Area Transmission Development - Third Circuit
Oct 20, 2017 3386-
D01-2016 3386-D02-
2016 Jan-12-2016 Included
1456 Downtown Calgary 138 kV
Transmission Reinforcement project
Q1 2021 21038-
D01-2016 21038-D02-
2016 Jun-1-2016 Excluded
2.5. Connection Projects
Connection projects that have passed Gate 2 of the AESO Connection Process as of June 2017
were modelled in the study scenarios based on their respective positions in the AESO
Connection Queue. Table 2.5-1 lists the connection projects that were included in the studies.
Information in this table is subject to change as projects progress.
Table 2.5-1: Connection Projects Included in the Studies
AESO Planning
Area
AESO Queue
Position*
Scheduled In-Service
Date AESO Project Name
AESO Project
No.
Project Gen (MW)
Project
Load (MW)
6 42 Nov 12,
2018 ENMAX No. 31 Substation 13 kV
Breaker Addition 1601 0 0
6 46 Mar 15,
2018 ENMAX 162 Substation 138/25
kV 2nd Transformer Addition 1644 0 14
6 51 Jul 1, 2019
Calgary Energy Centre Peaking Plant New Generator Capacity
1566 150 0
* Per the AESO Connection Queue posted in June 2017 The connection projects in the Study Area, if any, that have queue positions after the Project are not listed in this table and were not modelled in the study cases.
2.6. Facility Ratings and Shunt Elements
The legal owners of transmission facilities (TFOs) provided thermal ratings for the transmission
lines in the Study Area. The seasonal continuous ratings and short-term emergency ratings for
the transmission lines in the Study Area are shown in Table 2.6-1.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 15 Public
R3-2015-07-01
Table 2.6-1: Transmission Line Ratings in the Study Area
Line ID Line Description Voltage Class (kV)
Seasonal Continuous Rating (MVA)
Short-term Emergency Rating (MVA)
Summer Winter Summer Winter
936L East Calgary 5S -
Langdon 102S 240 481 581 577 697
937L East Calgary 5S -
Langdon 102S 240 481 581 577 697
1064L Langdon 102S - Janet
74S 240 974 1039 1039 1039
1065L Langdon 102S - Janet
74S 240 974 1208 1169 1247
916L East Calgary 5S - Sarcee
42S 240 408 494 593 490
1106L Foothills 237S - SS-65 240 971 1207 1071 1330
1107L Foothills 237S - SS-65 240 971 1207 1071 1330
1080L SS-65 - SS-25 240 487 604 584 725
1003L SS-25 - Janet 74S 240 973 1039 1017 1039
611L Balzac 391S - Dry Creek
186S 138 119 147 131 162
1.80L SS-1 - SS-28 138 160 199 176 219
1.81L SS-1 - SS-20 138 160 177 176 195
1.82L SS-1 - SS-5 138 226 228 249 251
1.83L SS-1 - SS-8 138 218 232 240 255
1.84L SS-1 - SS-5 138 226 228 249 251
1.85L SS-1 - SS-8 138 218 232 240 255
2.80L SS-2 - SS-23 138 285 350 285 350
2.81L SS-2 - SS-9 138 287 287 316 316
2.82L SS-2 - SS-5 138 322 349 354 384
2.83L SS-2 - 138-2.83-70 138 338 354 372 389
2.83L 138-2.83-70 - SS-5 138 287 287 316 316
2.83L 138-2.83-70 - SS-13 138 287 287 316 316
3.82L SS-3 - SS-8 138 156 191 171 210
3.84L SS-3 - SS-13 138 161 191 177 210
6.80L SS-6 - SS-35 138 164 191 180 210
6.82L SS-6 - SS-41 138 161 191 177 210
7.82L SS-7 - Sarcee 42S 138 287 287 287 287
7.84L SS-7 - SS-36 138 287 287 316 316
9.80L SS-9 - SS-31 138 287 287 316 316
9.83L SS-9 - SS-43 138 191 191 210 210
11.81L SS-11 - SS-13 138 287 287 316 316
11.82L SS-11 - SS-14 138 161 191 177 210
11.83L SS-11 - SS-162 138 305 379 335 417
13.60L SS-13 - SS-27 69 66 72 73 79
13.82L SS-13 - SS-22 138 161 204 177 225
14.83L SS-14 - SS-36 138 176 215 194 236
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 16 Public
R3-2015-07-01
Line ID Line Description Voltage Class (kV)
Seasonal Continuous Rating (MVA)
Short-term Emergency Rating (MVA)
Summer Winter Summer Winter
15.60L SS-15 - SS-21 69 72 72 79 79
15.62L SS-15 - SS-16 69 72 72 79 79
16.60L SS-16 - SS-34 69 72 72 79 79
16.61L SS-16 - SS-27 69 72 72 79 79
16.63L SS-16 - SS-36 69 72 72 79 79
20.82L SS-20 - SS-21 138 160 191 176 210
21.61L SS-21 - SS-34 69 72 72 79 79
21.80L SS-21 - Sarcee 42S 138 236 262 285 287
22.81L SS-22 - SS-39 138 285 287 285 316
23.80L SS-23 - Janet 74S 138 285 287 287 287
24.81L SS-24 - SS-31 138 287 287 316 316
24.82L SS-24 - SS-65 138 285 350 285 350
24.83L SS-24 - Janet 74S 138 322 408 341 409
26.81L SS-26 - SS-32 138 260 287 290 316
26.83L SS-26 - SS-65 138 285 350 285 350
28.80L SS-28 - Sarcee 42S 138 273 273 286 287
30.81L SS-30 - Sarcee 42S 138 162 191 178 210
31.84L SS-31 - SS-32 138 161 191 177 210
32.82L SS-32 - SS-54 138 287 287 290 316
32.83L SS-32 - SS-40 138 164 191 180 210
33.83L SS-33 - SS-41 138 191 191 210 210
33.84L SS-33 - SS-43 138 191 191 210 210
36.81L SS-36 - Bearspaw 44S 138 143 172 172 186
37.81L SS-37 - SS-38 138 287 287 316 316
37.82L SS-37 - Janet 745 138 287 287 287 287
38.83L SS-38 - SS-39 138 287 287 316 316
39.82L SS-39 - SS-162 138 287 287 316 316
40.81L SS-40 - SS-41 138 161 191 177 210
162.81L SS-162 - Turbo Balzac
391S 138 287 287 287 287
The TFO also provided the facility ratings of the key existing transformers in the Study Area, as
shown in Table 2.6-2.
Table 2.6-2: Ratings of Key Transformers in the Study Area
Substation Name and Number Transformer ID Transformer Voltages (kV)
Rating (MVA)
Janet 74S 74ST1 240/138 400
74ST2 240/138 400
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 17 Public
R3-2015-07-01
Substation Name and Number Transformer ID Transformer Voltages (kV)
Rating (MVA)
Sarcee 42S 42ST1 240/138 400
42ST2 240/138 400
East Calgary 5S 5ST1 240/138 400
5ST2 240/138 400
SS-162 162.1TR 240/138 400
162.2TR 240/138 400
SS-65 65.1TR 240/138 400
65.2TR 240/138 400
The details of shunt elements in the Study Area, as provided by the TFOs, are shown in Table
2.6-3.
Table 2.6-3: Details of Shunt Elements in the Study Area
Substation Name and Number
Voltage Class (kV)
Capacitors
Number of Switched
Shunt Blocks
Total at Nominal Voltage (MVAr)
Status in Study
2017SP
(MVAr)
2017WP
(MVAr)
SS-2 138 2 160 80 80
SS-14 138 2 48.91 24.46 24.46
SS-21 138 1 48.91 48.91 48.91
SS-31 138 1 48.11 48.11 48.11
SS-38 138 1 48.11 48.11 48.11
SS-41 138 1 53.96 53.96 53.96
Janet 74S 240 2 268.8 134.4 134.4
138 2 146.74 0 0
Sarcee 42S 240 2 201.6 0 100.8
138 1 48.91 0 48.91
Langdon 102S 240 (High Voltage
Terminal) SVC
(Continuous) 216.28 to
-269.2 Within +40 to -80 Operating Range
2.7. Voltage Profile Assumptions
ID #2010-007RS was used to establish system normal (i.e. pre-contingency) voltage profiles for
key area busses prior to commencing any studies. Table 2-1 of the Transmission Planning
Criteria – Basis and Assumptions applies for all the busses not included in the ID #2010-007RS.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 18 Public
R3-2015-07-01
These voltages were used to set the voltage profile for the study base cases prior to power flow
studies.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 19 Public
R3-2015-07-01
3. Study Methodology
All connection studies were completed using PTI PSS/E version 33.
3.1. Connection Studies Carried Out
The studies to be completed for this connection assessment are identified in
Table 3.1-1.
Table 3.1-1: Engineering Studies Performed
Scenario Number and Name System Conditions Category Power Flow
Voltage Stability
1 2018 WP Pre-project Category A and Category B X
2 2019 SP Pre-Project Category A and Category B X
3 2018 WP Post-Project Category A and Category B X X
4 2019 SP Post-Project Category A and Category B X
3.2. Power Flow Studies
Power flow studies were completed for all study scenarios to identify any thermal or
transmission voltage violations as per the Reliability Criteria, and to identify any POD voltage
deviations from the desired limits in Table 2-1. The purpose of the power flow analysis is to
quantify any violations in the Study Area both for the pre-Project and post-Project study
scenarios. For the Category B power flow studies, transformer taps and switched shunt reactive
compensating devices such as shunt capacitors and reactors were locked and continuous shunt
devices were enabled.
POD low voltage bus deviations were assessed for both the pre-Project and post-Project
networks by first locking all tap changers and area shunt reactive compensating devices to
identify any post-transient voltage deviations above 10%. Second, tap changers were allowed to
move while shunt reactive compensating devices remained locked to determine if any voltage
deviations above 7% would occur in the area. Third, all taps and shunt reactive compensating
devices were allowed to adjust, and voltage deviations above 5%, if any, were reported.
3.2.1. Contingencies Studied
Power flow studies were performed for all Category B contingencies in the Study Area. All
transmission facilities in the Study Area were monitored for Reliability Criteria violations.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 20 Public
R3-2015-07-01
3.3. Voltage Stability Studies
The objective of the voltage stability analysis is to determine the ability of the network to
maintain voltage stability at all the busses under Category A and Category B conditions. The
power-voltage (PV) curve is a representation of voltage change as a result of increased power
transfer between two systems. The incremental transfers are reported to the collapse point.
Voltage stability studies were performed for the post-Project scenario only. For load connection
projects, the load level modelled in post-connection scenarios are the same or higher than in
pre-connection scenarios. Therefore, voltage stability analysis for pre-connection scenarios will
only be performed if post-Project scenarios show voltage stability criteria violations.
Voltage stability (PV) analyses were performed according to the Western Electricity
Coordinating Council (WECC) Voltage Stability Assessment Methodology. WECC voltage
stability criteria state, for load areas, post-transient voltage stability is required for the area
modeled at a minimum of 105% of the reference load level for Category A and Category B
conditions. For this standard, the reference load level is the maximum established planned load.
Typically, voltage stability analysis is carried out assuming the worst case loading scenarios.
For the Project’s worst case scenario, load was increased in the Study Area and the
corresponding generation was increased in Wabamun (Area 40), Edmonton (Area 60) and the
Fort McMurray (Area 25).
3.3.1. Contingencies Studied
Voltage stability studies were performed for all Category B contingencies in the Study Area. All
transmission facilities in the Study Area were monitored for Reliability Criteria violations.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 21 Public
R3-2015-07-01
4. Pre-Project System Assessment
4.1. Power Flow
The pre-project power flow diagrams are provided in the Attachment A.
4.1.1. Scenario 1: 2018 WP Pre-Project
No Reliability Criteria violations were observed under Category A or Category B conditions.
4.1.2. Scenario 2: 2019 SP Pre-Project
Category A condition
No Reliability Criteria violations were observed under the Category A condition.
Category B conditions
No voltage criteria violations were observed under Category B conditions. A thermal criteria
violation was observed under Category B conditions, as shown in Table 4.1-1.
Table 4.1-1: Thermal Criteria Violations for the 2019 SP Pre-Project Scenario Under Category B Conditions
Contingency Limiting Branch
Seasonal Continuous
Line
Rating (MVA)
Short-term Emergency
Rating (MVA)
Pre-Project
Power Flow (MVA)
% Loading
2.83L (SS-2 substation - SS-5 substation - SS-13 substation)
2.82L (SS-2 substation - SS-5 substation)
322 354 366 113
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 22 Public
R3-2015-07-01
5. Connection Alternatives
5.1. Overview
The AESO, in consultation with the DFO and the TFO, examined three transmission alternatives
to meet the DFO’s request for system access service.5
5.2. Connection Alternatives Identified
Below is a description of the developments associated with the transmission alternatives that
were examined for the Project.
Alternative 1- Replace Two Transformers at SS-7 Substation
Alternative 1 involves upgrading the existing SS-7 substation, including replacing both of the
existing 138/25 kV transformers with two 138/25 kV transformers of higher capacity.
Alternative 1 also involves adding one 138 kV circuit breaker, and associated equipment. In
addition, Alternative 1 involves adding a new 25 kV distribution feeder, approximately 5 km in
length.
Alternative 2- Add a Third Transformer at SS-7 Substation
Alternative 2 involves upgrading the existing SS-7 substation, including adding one 138/25 kV
transformer. Alternative 2 also involves adding one 138 kV circuit breaker, four 25 kV feeder
circuit breakers and associated equipment. To complete the required upgrades, the TFO has
advised the AESO that expansion and/or modification of the 138 kV and 25 kV busses would be
required. In addition, Alternative 2 involves adding a total of approximately 14 km of 25 kV
distribution feeders.
Alternative 3- Replace one Transformer at SS-7 Substation and Add a Transformer at SS-28 Substation
Alternative 3 involves upgrading the existing SS-7 substation, including replacing one of the
existing 138/25 kV transformers with one 138/25 kV transformer of higher capacity and adding
one 138 kV circuit breaker and associated equipment. Alternative 3 also involves upgrading the
existing SS-28 substation, including adding one 138/25 kV transformer, one 138 kV circuit
breaker, four 25 kV circuit breakers and associated equipment. In addition, Alternative 3
involves adding a total of approximately 10 km of 25 kV distribution feeders.
5.2.1. Connection Alternatives Selected for Further Studies
Alternative 1 is considered technically feasible and was selected for further study.
5 These alternatives reflect more up to date engineering design than the alternatives identified in EPC’s Statement of Need, No. 7 Substation 138/25 kV Transformer Upgrade, which is filed under a separate cover.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 23 Public
R3-2015-07-01
5.2.2. Connection Alternatives Not Selected for Further Studies
Alternative 2 and Alternative 3 would both involve increased transmission and distribution
development, and hence overall increased cost compared to Alternative 1. Therefore, these
alternatives were not selected for further study.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 24 Public
R3-2015-07-01
6. Technical Analysis of the Connection Alternative
The technical analysis of Alternative 1 was completed with a total load of 40 MW at SS-7
substation, which includes a Project load addition of 5 MW at SS-7 substation.
6.1. Power Flow
The post-Project power flow diagrams are provided in Attachment B.
6.1.1. Scenario 3: 2018 WP Post-Project
No Reliability Criteria violations were observed under Category A or Category B conditions.
6.1.2. Scenario 4: 2019 SP Post-Project
Category A condition
No Reliability Criteria violations were observed under the Category A condition.
Category B conditions
No voltage criteria violations were observed under Category B contingency conditions. A
thermal criteria violation, identical to the pre-project 2019 SP scenario, was observed under
Category B conditions, as shown in Table 6.1-1.
Table 6.1-1: Thermal Criteria Violations for the 2019 SP Post-Project Scenario Under Category B Conditions
Contingency Limiting Branch
Seasonal Continuous
Line
Rating (MVA)
Short-term Emergency
Rating (MVA)
Pre- Project Post- Project
% Loading Differ-ence
Power Flow
(MVA) % Loading
Power Flow (MVA)
% Loading
Post-Pre
2.83L (SS-2 substation to SS-5 substation -SS-13 substation)
2.82L (SS-2 substation - SS-5
substation) 322 354 366 113 366 113 0
6.2. Voltage Stability
6.2.1. Scenario 3: 2018 WP Post-Project
Voltage stability analysis was performed for the 2018 WP post-Project scenario. The reference
load level for the Study Area is 1,662 MW. To meet the voltage stability criteria, the minimum
incremental load transfer for the Category B contingencies is 5.0% of the reference load or 83.1
MW (0.05 x 1662 MW = 83.1 MW). Voltage stability results for Category A and the worst five
Category B contingencies are summarized in Table 6.2-1. The voltage stability margin was met
for all studied conditions.
The voltage stability diagrams are provided in Attachment C.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 25 Public
R3-2015-07-01
Table 6.2-1: Voltage Stability Analysis Results for the 2018 WP Post-Project Scenario
Contingency From To Maximum
incremental transfer (MW)
Meets 105% transfer criteria?
N-G-0 Category A 975 Yes
Category B Conditions
Sarcee 42S Transformer T1
n/a
881 Yes
Sarcee 42S Transformer T2
887 Yes
928L (or 906L) Sarcee 42S Benalto 17S 893 Yes
918L SS-162 Johnson 81S 900 Yes
936L (or 937L) East Calgary 5S Langdon 102S 900 Yes
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 26 Public
R3-2015-07-01
7. Mitigation Measures
The thermal criteria violation, observed both pre-Project and post-Project, on the 138 kV
transmission line 2.82L (between SS-2 substation and SS-5 substation), following the loss of the
138 kV transmission line 2.83L (between SS-2 substation and SS-5 substation and SS-13
substation), is currently being managed by real time operational practices, and can continue to
be managed by real time operational practices in the future. This thermal criteria violation will be
permanently mitigated once the Downtown Calgary 138 kV Transmission Reinforcement Project
is in service.6
6The Alberta Utilities Commission (AUC) approved the need for the Downtown Calgary 138 kV Transmission
Reinforcement Project in Decision 21038-D01-2016 and Approval 21038-D02-2016 issued on June 1, 2016. The scheduled ISD is Q1 2021.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 27 Public
R3-2015-07-01
8. Project Interdependencies
The Project does not require the completion of any AESO plans to expand or enhance the
transmission system prior to connection.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Project and System Access Studies (PSAS) Group
Page 28 Public
R3-2015-07-01
9. Conclusion and Recommendations
Based on the study results, Alternative 1 is technically viable. The connection assessment
identified a system performance issue, which was identical in pre-Project and post-Project
scenarios. Real-time operational practices can continue to be used to manage the identified
system performance issue, until the Downtown Calgary 138 kV Transmission Reinforcement
Project is in service.
It is recommended to proceed with the Project using Alternative 1 as the preferred option to
respond to the DFO’s request for system access service. It is also recommended to use real-
time operational practices to manage the identified system performance issue.
Alternative 1 involves upgrading the existing SS-7 substation, including replacing both of the
existing 138/25 kV transformers with two 138/25 kV transformers of higher capacity. Alternative
1 also involves adding one 138 kV circuit breaker, and associated equipment.
It is recommend that each of 138/25 kV transformers at SS-7 substation have a transformation
capability of 44.4 MVA, based on the requested Rate DTS contract capacity increase and the
DFO’s distribution system performance standard for POD substations.
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Transmission Project Delivery
R[x]
29
Public
R2-2012-03-21
Attachment A
Pre-Project Power Flow Diagrams (Scenarios 1 & 2)
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Transmission Project Delivery
R[x]
30
Public
R2-2012-03-21
Attachment B
Post-Project Power Flow Diagrams (Scenarios 3 & 4)
Connection Engineering Study Report for AUC Application: SS-7 Substation Upgrade
Transmission Project Delivery
R[x]
31
Public
R2-2012-03-21
Attachment C
Post-Project Voltage Stability Diagrams (Scenario 3)
AESO
-170.5
-6.8
* 0.0
0.0
* 170.7
15.6
Bus - Voltage (kV/pu)Branch - MW/MvarEquipment - MW/Mvar100.0%Rate A1.120OV0.950UV
CEC #2: 0.0 MW
CEC #1: 0.0 MW
SEC: 454.0 MW
-170.5
-6.8
* 0.0
0.0
P1787
kV: <=4.160 <=13.800 <=25.000 <=69.000 <=138.000 <=240.000 <=500.000 >500.000
BC-AB: -7.6 MW2019SP_PREPROJECT_FINALSYSTEM NORMALFIG A1-1THU, JUN 29 2017 14:13
* 170.7
15.6
906L
916L
936L
937L
1064L
928L
1065L
1003L
985L
37.82L
37.83L
22.81L13.82L
37.81L
932L
901L
901L
752L752AL
688AL
752L 688L
688L 688L
631L
611L162.81L
771L
39.82L
11.83L
11.82L14.83L
11.81L
3.82L
Balzac: 24.0 MW
EATL: -0.1 MW
WATL: 784.6 MW
Sask. Import: -0.1 MW
MATL import: 0.0 MW
3.84L 2.83L
2.83L
2.83L
2.82L1.84L
1.82L
1.83L
1.85L
1.81L
21.80
L
20.82L
1.80L28.80L7.82L
7.84L
1.0140.5
1.0140.1
115.
1
7.9
564ENMX36S7
1.0139.5
551ENMX28S7
1.0140.5
88.7
21.0
566ENMX20S7
1.0139.6
38.1
23.0
555ENMX14S7
1.0139.6
-15.013.1
576ENMX47S7
561ENMX11S7
1.0140.1
-41.1-4.3
569ENMX3S 7
1.0139.6
-20.2-12.6
1.0139.6
67.1
23.9
67.1
23.9
59.0
9.5
-10.8
600ENMAXGIS
1.0140.6
195.2
113.7
0.97
83
1
185.3
108.4
0.97
8271
568ENMX5S 7
1.0139.7
-241.4
-90.7
-88.6-33.6
-88.6
-33.6
559ENMX13S7
1.0139.7
-20.3
-33.0
20.49.4
5.2
572ENMX39S7
1.0140.6
-100.9
-37.4
573ENMX38S7
1.0140.8
-94.2
6.7
574ENMX37S7
1.0140.6
-126.6
44.7
127BEDDING2
1.0142.9
132.6
67.4
6.4
0.1
-141.3-69.7
1 0.96
6
-140.7-69.5
1 0.96
6
207JANET 7
1.0140.7
177.7
-12.2
197.4
17.1
0.96
722
197.9
17.2
0.96
722
1.0142.9
38.3-11.9
295DRYCREEK
1.0141.2
34.232.2
177AIRDRIE
1.0140.1
4.5
-26.7
503SUMMIT_7
1.0140.2
425NOSE CR7
1.0140.2
318W CROSSF
1.0140.3
312E CROSS7
1.0141.4
77.1
3.1
1.02
72
1
933AIRD TAP
1.0140.4
65.2-3.8-18.9
-8.9
-45.6
12.8
729SUMMITTP
1.0140.2
-6.8-1.3
44.9
-13.2
810AMOCOTAP
1.0140.2
-37.9
14.0
38.1
1
-14.4
1.0139.5
81.9
72.3
1.0142.8
596ENMX7S7
1.0139.7
74.5
19.5
-74.3
-19.0
-45.2-13.4
45.213.2
588ENMX8S 7
552ENMX21S7
550ENMX22S7
6012.83 TAP
1.0140.0
-54.1-18.9
54.218.7
-84.9-41.6
84.941.7
139.2
61.1
-139.1
-60.4
1
-13.4
198BALZAC 7
0.8
1.0139.6
567ENMX1S 7
202SARCEE 7
161SARCEE 4
1.0249.4
162E CALGAR
1.0247.6
-65.685.3
187BEDDING1
1.0245.5
160JANET 4
1.1254.2
166.1
129.5
772ENMX25S7
1.1254.2
-41.1
-6.6
-6.4
159LANGDON4
1.1253.0
177.9-60.9
223.9
72.8
225.073.1
156E CROSS4
1.1252.9
988CROSSF T
1.1252.9
-77.1-3.1
-13.3
9.7
177.9
-60.9
155BENALTO4
1.1253.1
140.6
-19.0141.0
-16.2 -41.6
203SARCEE C
1.114.6
29202SARCEE C
1.114.6
0.97
830.96
251
0.97
830.96
251
3596ENMX7S8
1.026.1
4596ENMX7S9
1.025.4
14.62.91
1.04
38-3
0.00
-14.5-2.02.0
14.5
14.5
2.0
14.6
2.91
1.01
63-3
0.00
-14.5
-2.0
1
AESO
-173.1
-8.6
* 0.0
0.0
* 173.3
17.7
Bus - Voltage (kV/pu)Branch - MW/MvarEquipment - MW/Mvar100.0%Rate A1.120OV0.950UV
CEC #2: 0.0 MW
CEC #1: 0.0 MW
SEC: 454.0 MW
-173.1
-8.6
* 0.0
0.0
P1787
kV: <=4.160 <=13.800 <=25.000 <=69.000 <=138.000 <=240.000 <=500.000 >500.000
BC-AB: -6.8 MW2019SP_PREPROJECT_FINAL138-2.83L ENMAXFIG A1-2THU, JUN 29 2017 14:13
* 173.3
17.7
906L
916L
936L
937L
1064L
928L
1065L
1003L
985L
37.82L
37.83L
22.81L13.82L
37.81L
932L
901L
901L
752L752AL
688AL
752L 688L
688L 688L
631L
611L162.81L
771L
39.82L
11.83L
11.82L14.83L
11.81L
3.82L
Balzac: 24.0 MW
EATL: -0.1 MW
WATL: 784.6 MW
Sask. Import: -0.1 MW
MATL import: 0.0 MW
3.84L 2.83L
2.83L
2.83L
2.82L1.84L
1.82L
1.83L
1.85L
1.81L
21.80
L
20.82L
1.80L28.80L7.82L
7.84L
1.0140.4
1.0139.9
123.
2
12.0
564ENMX36S7
1.0139.2
551ENMX28S7
1.0140.3
95.5
24.8
566ENMX20S7
1.0139.4
43.5
26.2
555ENMX14S7
1.0139.3
-20.810.9
576ENMX47S7
561ENMX11S7
1.0139.7
-35.2-2.2
569ENMX3S 7
1.0139.2
-47.4-20.4
1.0139.3
80.7
27.9
80.7
27.9
65.9
13.2
-5.3
600ENMAXGIS
1.0140.8
190.2
111.0
0.97
83
1
180.6
105.8
0.97
8271
568ENMX5S 7
1.0139.4
-341.2
-133.8
-96.1-34.3
-96.1
-34.3
559ENMX13S7
1.0139.2
-33.9
-38.4
-6.81.6
16.6
572ENMX39S7
1.0140.4
-112.4
-42.1
573ENMX38S7
1.0140.6
-106.2
1.7
574ENMX37S7
1.0140.5
-138.7
39.4
127BEDDING2
1.0142.7
140.5
71.5
6.4
0.1
-144.5-71.2
1 0.96
6
-143.9-70.9
1 0.96
6
207JANET 7
1.0140.7
189.8
-6.5
197.0
17.3
0.96
722
197.6
17.3
0.96
722
1.0142.7
37.2-13.3
295DRYCREEK
1.0140.9
33.131.8
177AIRDRIE
1.0139.9
5.6
-26.3
503SUMMIT_7
1.0140.1
425NOSE CR7
1.0140.0
318W CROSSF
1.0140.1
312E CROSS7
1.0141.3
78.2
3.6
1.02
72
1
933AIRD TAP
1.0140.3
66.3-3.3-18.9
-8.9
-46.7
12.4
729SUMMITTP
1.0140.1
-6.8-1.3
46.0
-12.8
810AMOCOTAP
1.0140.0
-38.9
13.7
39.2
1
-14.0
1.0139.2
81.4
72.5
1.0142.6
596ENMX7S7
1.0139.5
78.7
21.6
-78.6
-21.0
-49.5-15.3
49.515.2
588ENMX8S 7
552ENMX21S7
550ENMX22S7
6012.83 TAP
1.0139.9
1
-8.7
198BALZAC 7
3.9
1.0139.3
567ENMX1S 7
202SARCEE 7
161SARCEE 4
1.0249.3
162E CALGAR
1.0247.7
-71.681.4
187BEDDING1
1.0245.2
160JANET 4
1.1254.1
171.5
133.0
772ENMX25S7
1.1254.2
-42.2
-7.5
-7.3
159LANGDON4
1.1253.0
179.9-59.7
222.0
71.9
223.172.2
156E CROSS4
1.1252.9
988CROSSF T
1.1252.9
-78.2-3.6
-12.4
10.0
179.9
-59.7
155BENALTO4
1.1253.1
140.2
-18.9140.6
-16.1 -42.7
203SARCEE C
1.114.6
29202SARCEE C
1.114.6
0.97
830.96
251
0.97
830.96
251
3596ENMX7S8
1.026.1
4596ENMX7S9
1.025.4
14.62.91
1.04
38-3
0.00
-14.5-2.02.0
14.5
14.5
2.0
14.6
2.91
1.01
63-3
0.00
-14.5
-2.0
1
AESO
-175.0
21.9
* 0.0
0.0
* 175.3
-12.7
Bus - Voltage (kV/pu)Branch - MW/MvarEquipment - MW/Mvar100.0%Rate A1.120OV0.950UV
CEC #2: 0.0 MW
CEC #1: 0.0 MW
SEC: 444.0 MW
-175.0
21.9
* 0.0
0.0
P1787
kV: <=4.160 <=13.800 <=25.000 <=69.000 <=138.000 <=240.000 <=500.000 >500.000
BC-AB: -25.7 MW2019WP_PREPROJECT_FINALSYSTEM NORMALFIG A1-3THU, JUN 29 2017 14:13
* 175.3
-12.7
906L
916L
936L
937L
1064L
928L
1065L
1003L
985L
37.82L
37.83L
22.81L13.82L
37.81L
932L
901L
901L
752L752AL
688AL
752L 688L
688L 688L
631L
611L162.81L
771L
39.82L
11.83L
11.82L14.83L
11.81L
3.82L
Balzac: 28.0 MW
EATL: -0.1 MW
WATL: 880.5 MW
Sask. Import: -0.1 MW
MATL import: 0.0 MW
3.84L 2.83L
2.83L
2.83L
2.82L1.84L
1.82L
1.83L
1.85L
1.81L
21.80
L
20.82L
1.80L28.80L7.82L
7.84L
1.0140.5
1.0140.4
111.
2
-9.1
564ENMX36S7
1.0139.9
551ENMX28S7
1.0140.5
81.2
6.4
566ENMX20S7
1.0140.1
21.5
14.5
555ENMX14S7
1.0140.1
-15.218.0
576ENMX47S7
561ENMX11S7
1.0140.7
-50.7-5.2
569ENMX3S 7
1.0140.2
-25.2-1.0
1.0140.2
60.4
8.8
60.4
8.8
49.5
-1.3
-26.9
600ENMAXGIS
1.0140.7
188.3
35.5
1.01
22
1
178.9
34.0
1.01
22
1
568ENMX5S 7
1.0140.2
-231.2
-46.6
-86.2-15.9
-86.2
-15.9
559ENMX13S7
1.0140.3
-2.4
-34.8
13.615.1
11.4
572ENMX39S7
1.0141.5
-95.1
-39.3
573ENMX38S7
1.0141.8
-100.2
-3.9
574ENMX37S7
1.0141.7
-133.9
37.0
127BEDDING2
1.0143.4
131.9
65.4
6.3
-0.6
-142.1-60.2
1 0.96
6
-141.5-60.0
1 0.96
6
207JANET 7
1.0141.9
182.9
-10.5
196.0
2.1
0.97
444
196.6
2.1
0.97
444
1.0143.4
45.1-13.6
295DRYCREEK
1.0141.4
46.432.4
177AIRDRIE
1.0140.2
0.2
-27.5
503SUMMIT_7
1.0140.2
425NOSE CR7
1.0140.1
318W CROSSF
1.0140.2
312E CROSS7
1.0141.3
83.7
0.4
1.02
72
1
933AIRD TAP
1.0140.4
69.7-7.4-19.8
-5.3
-49.1
13.1
729SUMMITTP
1.0140.1
-14.0-4.5
48.3
-13.4
810AMOCOTAP
1.0140.2
-34.1
17.4
34.3
1
-17.8
1.0140.4
75.1
56.0
1.0143.3
596ENMX7S7
1.0140.0
83.1
10.2
-83.0
-9.5
-49.2-5.1
49.24.9
588ENMX8S 7
552ENMX21S7
550ENMX22S7
6012.83 TAP
1.0140.4
-58.21.7
58.3-2.0
-74.5-26.8
74.626.8
132.9
25.3
-132.8
-24.8
1
4.2
198BALZAC 7
-0.5
1.0140.1
567ENMX1S 7
202SARCEE 7
161SARCEE 4
1.0250.6
162E CALGAR
1.0250.3
-77.023.7
187BEDDING1
1.0245.6
160JANET 4
1.1253.1
168.9
108.9
772ENMX25S7
1.1253.2
-39.1
-10.5
-10.3
159LANGDON4
1.1253.0
181.5-21.9
222.8
25.8
223.925.9
156E CROSS4
1.1252.4
988CROSSF T
1.1252.4
-83.7-0.4
-10.3
3.7
181.5
-21.9
155BENALTO4
1.1253.1
139.4
-24.1139.9
-21.4 -39.6
203SARCEE C
1.114.8
29202SARCEE C
1.114.8
0.97
830.95
1
0.97
830.95
1
3596ENMX7S8
1.026.1
4596ENMX7S9
1.025.4
16.92.31
1.03
75-3
0.00
-16.8-1.11.1
16.8
16.8
1.1
16.9
2.31
1.01
01-3
0.00
-16.8
-1.1
1
AESO
-171.1
-6.8
* 0.0
0.0
* 171.3
15.7
Bus - Voltage (kV/pu)Branch - MW/MvarEquipment - MW/Mvar100.0%Rate A1.120OV0.950UV
CEC #2: 0.0 MW
CEC #1: 0.0 MW
SEC: 454.0 MW
-171.1
-6.8
* 0.0
0.0
P1787
kV: <=4.160 <=13.800 <=25.000 <=69.000 <=138.000 <=240.000 <=500.000 >500.000
BC-AB: -7.5 MW2019SP_POSTPROJECT_FINALSYSTEM NORMALFIG B1-1THU, JUN 29 2017 14:13
* 171.3
15.7
906L
916L
936L
937L
1064L
928L
1065L
1003L
985L
37.82L
37.83L
22.81L13.82L
37.81L
932L
901L
901L
752L752AL
688AL
752L 688L
688L 688L
631L
611L162.81L
771L
39.82L
11.83L
11.82L14.83L
11.81L
3.82L
Balzac: 24.0 MW
EATL: -0.1 MW
WATL: 784.6 MW
Sask. Import: -0.1 MW
MATL import: 0.0 MW
3.84L 2.83L
2.83L
2.83L
2.82L1.84L
1.82L
1.83L
1.85L
1.81L
21.80
L
20.82L
1.80L28.80L7.82L
7.84L
1.0140.5
1.0140.1
114.
7
7.5
564ENMX36S7
1.0139.4
551ENMX28S7
1.0140.5
87.2
20.4
566ENMX20S7
1.0139.7
36.2
22.4
555ENMX14S7
1.0139.6
-12.313.8
576ENMX47S7
561ENMX11S7
1.0140.1
-43.4-4.9
569ENMX3S 7
1.0139.6
-20.0-12.6
1.0139.7
66.6
23.7
66.6
23.7
57.7
8.9
-12.3
600ENMAXGIS
1.0140.7
195.0
113.3
0.97
83
1
185.2
108.0
0.97
8271
568ENMX5S 7
1.0139.7
-241.7
-90.4
-89.3-33.7
-89.3
-33.7
559ENMX13S7
1.0139.7
-19.1
-32.6
20.49.3
6.2
572ENMX39S7
1.0140.7
-101.3
-37.3
573ENMX38S7
1.0140.8
-94.4
6.8
574ENMX37S7
1.0140.6
-126.6
44.9
127BEDDING2
1.0142.9
133.4
67.5
6.3
0.1
-141.2-69.6
1 0.96
6
-140.7-69.3
1 0.96
6
207JANET 7
1.0140.7
177.3
-12.6
197.2
16.8
0.96
722
197.8
16.8
0.96
722
1.0142.9
37.7-12.0
295DRYCREEK
1.0141.2
33.832.1
177AIRDRIE
1.0140.1
4.7
-26.6
503SUMMIT_7
1.0140.2
425NOSE CR7
1.0140.2
318W CROSSF
1.0140.3
312E CROSS7
1.0141.4
76.8
2.9
1.02
72
1
933AIRD TAP
1.0140.4
65.0-3.9-18.8
-8.9
-45.5
12.9
729SUMMITTP
1.0140.2
-6.8-1.3
44.9
-13.3
810AMOCOTAP
1.0140.2
-37.9
14.1
38.1
1
-14.5
1.0139.6
81.7
72.1
1.0142.9
596ENMX7S7
1.0139.6
80.0
21.5
-79.8
-20.8
-39.7-12.0
39.711.8
588ENMX8S 7
552ENMX21S7
550ENMX22S7
6012.83 TAP
1.0140.1
-54.2-18.9
54.218.6
-85.0-41.5
85.141.6
139.5
61.0
-139.3
-60.3
1
-13.1
198BALZAC 7
0.4
1.0139.6
567ENMX1S 7
202SARCEE 7
161SARCEE 4
1.0249.4
162E CALGAR
1.0247.6
-66.685.0
187BEDDING1
1.0245.5
160JANET 4
1.1254.2
166.1
129.2
772ENMX25S7
1.1254.2
-41.3
-6.6
-6.4
159LANGDON4
1.1253.0
177.7-61.5
224.2
72.6
225.472.9
156E CROSS4
1.1253.0
988CROSSF T
1.1253.0
-76.8-2.9
-13.4
9.6
177.7
-61.5
155BENALTO4
1.1253.1
140.7
-19.0141.1
-16.2 -41.8
203SARCEE C
1.114.6
29202SARCEE C
1.114.6
0.97
830.96
251
0.97
830.96
251
3596ENMX7S8
1.026.1
4596ENMX7S9
1.026.1
20.14.51
1.05
-30.
00
-20.0-2.82.8
20.0
20.0
2.8
20.1
4.51
1.05
-30.
00
-20.0
-2.8
1
AESO
-173.7
-8.6
* 0.0
0.0
* 173.9
17.8
Bus - Voltage (kV/pu)Branch - MW/MvarEquipment - MW/Mvar100.0%Rate A1.120OV0.950UV
CEC #2: 0.0 MW
CEC #1: 0.0 MW
SEC: 454.0 MW
-173.7
-8.6
* 0.0
0.0
P1787
kV: <=4.160 <=13.800 <=25.000 <=69.000 <=138.000 <=240.000 <=500.000 >500.000
BC-AB: -6.7 MW2019SP_POSTPROJECT_FINAL138-2.83L ENMAXFIG B1-2THU, JUN 29 2017 14:13
* 173.9
17.8
906L
916L
936L
937L
1064L
928L
1065L
1003L
985L
37.82L
37.83L
22.81L13.82L
37.81L
932L
901L
901L
752L752AL
688AL
752L 688L
688L 688L
631L
611L162.81L
771L
39.82L
11.83L
11.82L14.83L
11.81L
3.82L
Balzac: 24.0 MW
EATL: -0.1 MW
WATL: 784.6 MW
Sask. Import: -0.1 MW
MATL import: 0.0 MW
3.84L 2.83L
2.83L
2.83L
2.82L1.84L
1.82L
1.83L
1.85L
1.81L
21.80
L
20.82L
1.80L28.80L7.82L
7.84L
1.0140.4
1.0139.9
122.
8
11.6
564ENMX36S7
1.0139.2
551ENMX28S7
1.0140.3
94.1
24.1
566ENMX20S7
1.0139.4
41.7
25.6
555ENMX14S7
1.0139.3
-18.111.6
576ENMX47S7
561ENMX11S7
1.0139.7
-37.6-2.9
569ENMX3S 7
1.0139.2
-47.2-20.3
1.0139.4
80.2
27.7
80.2
27.7
64.6
12.7
-6.9
600ENMAXGIS
1.0140.8
190.0
110.6
0.97
83
1
180.4
105.4
0.97
8271
568ENMX5S 7
1.0139.4
-341.7
-133.4
-96.8-34.4
-96.8
-34.4
559ENMX13S7
1.0139.2
-32.8
-38.0
-6.91.6
17.6
572ENMX39S7
1.0140.4
-112.7
-42.0
573ENMX38S7
1.0140.6
-106.4
1.8
574ENMX37S7
1.0140.5
-138.6
39.6
127BEDDING2
1.0142.7
141.3
71.5
6.3
0.1
-144.4-71.1
1 0.96
6
-143.8-70.8
1 0.96
6
207JANET 7
1.0140.7
189.4
-6.9
196.9
16.9
0.96
722
197.5
16.9
0.96
722
1.0142.7
36.6-13.3
295DRYCREEK
1.0141.0
32.731.7
177AIRDRIE
1.0140.0
5.8
-26.3
503SUMMIT_7
1.0140.1
425NOSE CR7
1.0140.1
318W CROSSF
1.0140.2
312E CROSS7
1.0141.3
78.0
3.4
1.02
72
1
933AIRD TAP
1.0140.3
66.1-3.5-18.8
-8.9
-46.6
12.5
729SUMMITTP
1.0140.1
-6.8-1.3
45.9
-12.9
810AMOCOTAP
1.0140.1
-38.9
13.8
39.2
1
-14.1
1.0139.2
81.2
72.3
1.0142.6
596ENMX7S7
1.0139.4
84.3
23.6
-84.1
-22.8
-44.0-13.9
44.013.8
588ENMX8S 7
552ENMX21S7
550ENMX22S7
6012.83 TAP
1.0139.9
1
-8.5
198BALZAC 7
3.5
1.0139.3
567ENMX1S 7
202SARCEE 7
161SARCEE 4
1.0249.3
162E CALGAR
1.0247.7
-72.781.2
187BEDDING1
1.0245.3
160JANET 4
1.1254.2
171.5
132.8
772ENMX25S7
1.1254.2
-42.3
-7.5
-7.3
159LANGDON4
1.1253.0
179.7-60.3
222.4
71.6
223.571.9
156E CROSS4
1.1252.9
988CROSSF T
1.1252.9
-78.0-3.4
-12.4
9.9
179.7
-60.3
155BENALTO4
1.1253.1
140.3
-18.9140.6
-16.1 -42.8
203SARCEE C
1.114.6
29202SARCEE C
1.114.6
0.97
830.96
251
0.97
830.96
251
3596ENMX7S8
1.026.1
4596ENMX7S9
1.026.1
20.14.51
1.05
-30.
00
-20.0-2.82.8
20.0
20.0
2.8
20.1
4.51
1.05
-30.
00
-20.0
-2.8
1
AESO
-175.4
21.8
* -0.
00.
0
* 175.6
-12.5
Bus - Voltage (kV/pu)Branch - MW/MvarEquipment - MW/Mvar100.0%Rate A1.120OV0.950UV
CEC #2: 0.0 MW
CEC #1: 0.0 MW
SEC: 444.0 MW
-175.4
21.8
* -0.
00.
0
P1787
kV: <=4.160 <=13.800 <=25.000 <=69.000 <=138.000 <=240.000 <=500.000 >500.000
BC-AB: -26.5 MW2019WP_POSTPROJECT_FINALSYSTEM NORMALFIG B1-3THU, JUN 29 2017 14:13
* 175.6
-12.5
906L
916L
936L
937L
1064L
928L
1065L
1003L
985L
37.82L
37.83L
22.81L13.82L
37.81L
932L
901L
901L
752L752AL
688AL
752L 688L
688L 688L
631L
611L162.81L
771L
39.82L
11.83L
11.82L14.83L
11.81L
3.82L
Balzac: 28.0 MW
EATL: -0.1 MW
WATL: 880.5 MW
Sask. Import: -0.1 MW
MATL import: 0.0 MW
3.84L 2.83L
2.83L
2.83L
2.82L1.84L
1.82L
1.83L
1.85L
1.81L
21.80
L
20.82L
1.80L28.80L7.82L
7.84L
1.0140.5
1.0140.4
110.
9
-9.3
564ENMX36S7
1.0139.8
551ENMX28S7
1.0140.5
80.3
6.1
566ENMX20S7
1.0140.1
20.4
14.3
555ENMX14S7
1.0140.1
-13.518.3
576ENMX47S7
561ENMX11S7
1.0140.7
-52.1-5.4
569ENMX3S 7
1.0140.1
-25.0-1.0
1.0140.2
60.1
8.7
60.1
8.7
48.8
-1.6
-27.8
600ENMAXGIS
1.0140.7
188.2
35.5
1.01
22
1
178.7
33.9
1.01
22
1
568ENMX5S 7
1.0140.2
-231.2
-46.4
-86.5-15.9
-86.5
-15.9
559ENMX13S7
1.0140.3
-1.8
-34.6
13.615.0
11.9
572ENMX39S7
1.0141.5
-95.3
-39.2
573ENMX38S7
1.0141.8
-100.2
-3.7
574ENMX37S7
1.0141.7
-133.7
37.1
127BEDDING2
1.0143.4
132.4
65.4
6.2
-0.6
-142.0-60.1
1 0.96
6
-141.4-59.9
1 0.96
6
207JANET 7
1.0141.8
182.5
-10.8
195.8
1.9
0.97
444
196.4
1.9
0.97
444
1.0143.4
44.6-13.7
295DRYCREEK
1.0141.4
46.132.4
177AIRDRIE
1.0140.2
0.4
-27.5
503SUMMIT_7
1.0140.2
425NOSE CR7
1.0140.1
318W CROSSF
1.0140.3
312E CROSS7
1.0141.3
83.5
0.3
1.02
72
1
933AIRD TAP
1.0140.4
69.6-7.5-19.7
-5.3
-49.0
13.1
729SUMMITTP
1.0140.2
-13.9-4.5
48.2
-13.5
810AMOCOTAP
1.0140.2
-34.1
17.5
34.3
1
-17.9
1.0140.4
75.0
55.9
1.0143.3
596ENMX7S7
1.0140.0
86.3
11.1
-86.1
-10.3
-46.0-4.5
46.04.3
588ENMX8S 7
552ENMX21S7
550ENMX22S7
6012.83 TAP
1.0140.4
-58.21.8
58.2-2.0
-74.6-26.8
74.626.7
133.0
25.3
-132.9
-24.7
1
4.3
198BALZAC 7
-0.6
1.0140.1
567ENMX1S 7
202SARCEE 7
161SARCEE 4
1.0250.6
162E CALGAR
1.0250.3
-77.323.4
187BEDDING1
1.0245.6
160JANET 4
1.1253.1
168.7
108.6
772ENMX25S7
1.1253.2
-39.0
-8.9
-8.7
159LANGDON4
1.1253.0
181.0-20.7
222.8
26.0
223.826.0
156E CROSS4
1.1252.4
988CROSSF T
1.1252.4
-83.5-0.3
-10.6
3.6
181.0
-20.7
155BENALTO4
1.1253.1
139.6
-24.1140.1
-21.3 -39.4
203SARCEE C
1.114.8
29202SARCEE C
1.114.8
0.97
830.95
1
0.97
830.95
1
3596ENMX7S8
1.026.0
4596ENMX7S9
1.026.0
20.13.01
1.03
75-3
0.00
-20.0-1.31.3
20.0
20.0
1.3
20.1
3.01
1.03
75-3
0.00
-20.0
-1.3
1
0.860
0.880
0.900
0.920
0.940
0.960
0.980
1.000
1.020
1.040
1.060
0 200 400 600 800 1000 1200
Bu
s V
olt
age
(p
u)
Incremental Power Transfer (MW)
System Normal
SS-162 Bus 127 (BEDDING2)138 kV
Sarcee 42S Bus 161 (SARCEE 4)240 kV
SS-162 Bus 187 (BEDDING1)240 kV
Sarcee 42S Bus 202 (SARCEE 7)138 kV
SS-14 Bus 555 (ENMX14S7)138 kV
SS-11 Bus 561 (ENMX11S7)138 kV
SS-36 Bus 564 (ENMX36S7)138 kV
SS-7 Bus 596 (ENMX7S7)138 kV
SS-36 Bus 599 (ENMX36S8)69 kV
0.000
0.200
0.400
0.600
0.800
1.000
1.200
0 200 400 600 800 1000
Bu
s V
olt
age
(p
u)
Incremental Power Transfer (MW)
42ST1 Contigency
SS-162 Bus 127 (BEDDING2)138 kV
Sarcee 42S Bus 161 (SARCEE 4)240 kV
SS-162 Bus 187 (BEDDING1)240 kV
Sarcee 42S Bus 202 (SARCEE 7)138 kV
SS-14 Bus 555 (ENMX14S7)138 kV
SS-11 Bus 561 (ENMX11S7)138 kV
SS-36 Bus 564 (ENMX36S7)138 kV
SS-7 Bus 596 (ENMX7S7)138 kV
SS-36 Bus 599 (ENMX36S8)69 kV
0.000
0.200
0.400
0.600
0.800
1.000
1.200
0 200 400 600 800 1000
Bu
s V
olt
age
(p
u)
Incremental Power Transfer (MW)
42ST2 Contigency
SS-162 Bus 127 (BEDDING2)138 kV
Sarcee 42S Bus 161 (SARCEE 4)240 kV
SS-162 Bus 187 (BEDDING1)240 kV
Sarcee 42S Bus 202 (SARCEE 7)138 kV
SS-14 Bus 555 (ENMX14S7)138 kV
SS-11 Bus 561 (ENMX11S7)138 kV
SS-36 Bus 564 (ENMX36S7)138 kV
SS-7 Bus 596 (ENMX7S7)138 kV
SS-36 Bus 599 (ENMX36S8)69 kV
0.860
0.880
0.900
0.920
0.940
0.960
0.980
1.000
1.020
1.040
1.060
0 200 400 600 800 1000
Bu
s vo
ltag
e (
pu
)
Incremental Power Transfer (MW)
928L Contigency
SS-162 Bus 127 (BEDDING2)138 kV
Sarcee 42S Bus 161 (SARCEE 4)240 kV
SS-162 Bus 187 (BEDDING1)240 kV
Sarcee 42S Bus 202 (SARCEE 7)138 kV
SS-14 Bus 555 (ENMX14S7)138 kV
SS-11 Bus 561 (ENMX11S7)138 kV
SS-36 Bus 564 (ENMX36S7)138 kV
SS-7 Bus 596 (ENMX7S7)138 kV
SS-36 Bus 599 (ENMX36S8)69 kV
0.860
0.880
0.900
0.920
0.940
0.960
0.980
1.000
1.020
1.040
1.060
0 200 400 600 800 1000
Bu
s V
olt
age
(p
u)
Incremental Power Transfer (MW)
918L Contigency
SS-162 Bus 127 (BEDDING2)138 kV
Sarcee 42S Bus 161 (SARCEE 4)240 kV
SS-162 Bus 187 (BEDDING1)240 kV
Sarcee 42S Bus 202 (SARCEE 7)138 kV
SS-14 Bus 555 (ENMX14S7)138 kV
SS-11 Bus 561 (ENMX11S7)138 kV
SS-36 Bus 564 (ENMX36S7)138 kV
SS-7 Bus 596 (ENMX7S7)138 kV
SS-36 Bus 599 (ENMX36S8)69 kV
0.860
0.880
0.900
0.920
0.940
0.960
0.980
1.000
1.020
1.040
1.060
0 200 400 600 800 1000
Bu
s V
olt
age
(p
u)
Incremental Power Transfer (MW)
936L Contigency
SS-162 Bus 127 (BEDDING2)138 kV
Sarcee 42S Bus 161 (SARCEE 4)240 kV
SS-162 Bus 187 (BEDDING1)240 kV
Sarcee 42S Bus 202 (SARCEE 7)138 kV
SS-14 Bus 555 (ENMX14S7)138 kV
SS-11 Bus 561 (ENMX11S7)138 kV
SS-36 Bus 564 (ENMX36S7)138 kV
SS-7 Bus 596 (ENMX7S7)138 kV
SS-36 Bus 599 (ENMX36S8)69 kV