Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 0
World Bioenergy 2012, Jonkoping, Sweden, 29th May 2012
Dae-Woong Lim, Managing Director, Eco-Frontier
Experiences of biomass power and pellets in Asia
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 1
Eco-Frontier from Asia
Experiences in Asia
Malaysia
China
Korea
West meets East
Contents
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 2
Eco-Frontier from Asia
Carbon credits business • Volumes: Over 20Mt of carbon credits • Project types: Energy efficiency, coal mine methane, biomass power, hydro power, landfill gas, HFC
Sustainable finance business • Advisory for sustainable funds at US$1.5 billion • Clients: Korea Development Bank AM, Samsung AM, Shinhan BNP Paribas, Hana UBS, Woori Bank, Industrial Bank of Korea, etc.
Biomass power business • Malaysia: 23MW + 150t/hr steam • China: 30MW, 60MW(fuel switching) • Korea: 40MW(fuel switching) • Others: Europe and USA
Global Brain & Business Group Korea, Malaysia, Indonesia, China, USA, UK
Sustainability consulting business • Industry: Construction, petrochemical, pulp & paper, electronics, finance, etc. • Utility: Electricity, district heating, transportation, housing, landfill, etc. • Governments: Korea, Indonesia, World Bank, ASEM, etc.
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 3
200 MW
1. Malaysia: Biomass Policy
Feed-in-Tariff (FiT)
Renewable energy will increase from <1% in 2009 to 5.5% of Malaysia’s total electricity generated by 2015
65 MW
290 MW
100 MW
330 MW Biomass
41.5
23 X
2009 2015
<1% 5.5%
Biogas
Mini-hydro
Solar PV
Solid waste
Moving towards renewable energy replaces the need for
fossil-fuel power plants
Planned increase in renewable energy capacity
% of total
electricity
generated
• Introduction of Fee-in-Tariff (FiT)
of 1% to be incorporated into the
electricity tariffs of consumers
• Establishment of a Renewable
Energy Fund from the FiT to be
administered by a special agency
under KeTTHA
• This provides an annual CO2
avoidance of 3.2 million tonnes
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 4
1. Malaysia: Biomass Policy (FiT Rates)
Renewable Energy Base Rate Period Annual Degression
Biogas 0.28~0.32 RM/kWh 16 years 0.5%
Biomass 0.27~0.31 RM/kWh 16 years 0.5%
Mini-hydro 0.23~0.24 RM/kWh 21 years 0.0%
Solar PV 0.85~1.23 RM/kWh 21 years 8.0%
Biomass incentives
FiT rates
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 5
1. Malaysia: Potential Renewables
Biomass Solar Biogas Mini-Hydro Solid Waste
Potentials
Examples
>6,500 MW
(40% buildings)
1MW
- MBIPV Project
(SURIA 1,000 Demo)
- Yearly average
irradiance 1,400-1,900
kWh/m2
1,340 MW
by 2030
Total 39MW and more
under construction
- Biogen project
- Palm oil waste
410 MW
By 2028
Total 4.45MW and
more under
construction
- Palm Oil Mill effluent
(POME)
- Cassava waste
- Livestock etc.
490 MW
By 2020
Total 30.3MW and
more under
construction
- Run of the river with
minimum impounding
360 MW
By 2022
Total 5.5MW and more
under construction
- Waste collected in
Malaysia appr. 21,000
tonnes/day
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 6
1. Malaysia: Biomass Feedstock
Business focus of Eco-Frontier
Wood Pellet from Short Rotation Coppice Plantation
Wood Pellet from Logging industry chain
EFB/OPF Pellet and PKS from Oil Palm Plantation
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 7
1. Malaysia: Biomass CHP of Eco-Frontier (1/2)
Acquisition
ECF’s Share (Sole Developer):
25% (paid-in capital: 5.5M USD)
ECF’s CER: 50% of entire CERs
Project Overview
Type: Biomass Combined Heat Power Plant
Site: POIC, Sabah, Malaysia
Investment: 100M USD
Size: Power 23MW + Steam 150t/hr (Max.)
CER: 120,000tons/year x 21-year period
Exclusive rights to supply steam and power
in the cluster
Electricity
Steam
CER
EFB
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 8
1. Malaysia: Biomass CHP of Eco-Frontier (2/2)
Total Investment: $100M
The largest biomass
renewable energy
project
• SPC establishment
• Land purchase contract
• Permits & approvals
• Supply & purchasing
contracts
• Feasibility analysis
& basic structuring
Construction Start
in 2010
Operation
Management
9M USD joint investment 4.5M USD dividends/yr for 20 years
Engineering
Procurement
Construction
60M USD size plant construction
Equity / Debt
Financing
63M USD loan injection MLA and loan institution KIAMCO participating preferred stocks * MLA: Mandated lead arranger
Shared
Service
Various services from legal to tech Total advisory service fee: 2M USD
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 9
2. China: Biomass Policy
“Sales guarantee
of renewable power ”
“Fixed price: RMB0.75/kwh”
from biomass power
“Sales guarantee of electricity
during commissioning period”
Advantages of biomass power
Renewable energy development act, 2010,
Electricity control methods in utility renewable energy,2007
Development and reform commission, 2010
Development and reform commission, 2009
Over production Under production Commissioning
100% sales guarantee with fixed price
Renewable energy development act (2010)
• Sales guarantee of produced electricity by state owned company
• Renewable energy price-stability benefits in utility green power programs
State owned company
with high creditworthiness ;
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 10
2. China: Biomass Markets
Construction 13GWe
Biomass power by 2015
• Current: 4GWe (2012)
• 9GWe = 30MWe Power station x 300
units
• Fully support by government and states
122mllion tonnes of fuel needs
• Biomass use for power: 70.6%
• Unused land area: 25.8%
• 200m ha of SRC forestation by 2020
Encouraging by government
by2015
Biomass power expansion
(12th five-year plan)
High electricity sales price
Cent/kWh
US$
Low fuel cost
0,00 50,00 100,00 150,00
동남아
중국
미국
영국
Supply price ($/ton)
- 0,50 1,00 1,50
동남아
중국
미국
영국
Calorific value (Cent/MJ)
US$/t
0,10 0,10
0,12
0,08
0,10
0,00
0,02
0,04
0,06
0,08
0,10
0,12
0,14
※ Included FIT / Subsidy
※ Quarter in SE Asia
The UK
USA
China
SE Asia
The UK
USA
China
SE Asia Malaysia Philippines China USA The UK
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 11
2. China: Biomass Power of Eco-Frontier (1/2)
Project Outline
Type: Biomass Power Generation
(Fuel: Cotton trunk, fast growing tree, mulberry trunk)
Site: Shandong, China
Total Investment: 50M USD
Size: Power 30MW
CER: 150,000 tons/yr x 10 years
ECF’s Share (Co-Developer): 13.5% (paid-in capital: 2.5M USD)
Supported by
Minister of Environment in Korea
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 12
2. China: Biomass Power of Eco-Frontier (2/2)
Development and Construction Partners
Operation Partners
Pre-Feasibility Study
Shandong Energy and Building Design Institute
Shandong Pingyuan Han Yuan Green Energy Co., Ltd.
(Project SPC)
Shareholders (33.4%)
GS EPS (31.5%)
Eco-Frontier (13.5%)
Pre-Feasibility Study Review
Jipyong&Jisung, Pöyry
Pre-Construction Consulting
Mott MacDonald
Construction PM
Mott MacDonald
EPC contractor
SEPCO 1
Shenzhen Han Yuan (55%)
Project Finance (66.6%)
Plant Operation
Project SPC
Fuel Supply
Fuel Supply SPC (JV of Project SPC &
Local Agri. Federation)
Power Purchase
Shandong Power Corp.
CER Purchase
Eco-Frontier Carbon Partners in UK
Advisor, Arranger, Agent, and Lender
Korea Development Bank
Feasibility Study
Korea Ratings, Lee&Ko, AON
ECA
Korea Trade Insurance Corp.
CDM Coordinator
Eco-Frontier
CDM Consultant
COWI
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 13
2. China: Biomass Fuel Switching of Eco-Frontier
Coal boiler
(60MW X 3set)
Coal
(210,000t/yr)
Coal
(210,000t/yr)
Coal plant
Coal
Biomass power (converted)
Electricity
(55MW)
Electricity
(120MW)
Aluminum
Plant
State
Grid
50MW
(0.75RMB/kWh)
110MW
(0.51RMB/kWh)
5MW (In-house)
10MW (In-house)
Renewable
energy sales
Project Overview
Type: Coal plant acquisition & replacing coal with biomass Site: Qianjiang, China
Total Investment: USD 160 million (expected) Capacity: 60MW
Amount of biomass fuel needed: app. 1 million ton/yr (supported by city)
Biomass
Feedstock
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 14
RPS (Renewable Portfolio Standard) implements from 2012
A standard obligates major electric power company(capacity : more than 500MW)
to supply some rate of the energy they provide as renewable energy.
Obligatory electronic supply of renewable energy
= Total electricity supply of electronic business X Obligatory rate
2% 2.5%
3% 3.5%
4%
5%
6%
7%
8%
9%
10%
'12 '13 '14 '15 '16 '17 '18 '19 '20 '21 '22
Obligatory rate
NRE generation (BAU)
3. Korea: Biomass Policy
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 15
3. Korea: Pellet Demand of Korea in 2022
400 million MWh
10%
40 million MWh
50%
20 million MWh
Annual
electricity
production
RPS
Electricity
production by
renewable energy Electricity
production by
biomass
Pellet needs in 2022
12.5M ton/yr 12.5M ton/yr
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 16
3. Korea: Pellet Business Target of Eco-Frontier
Biomass pellet projects under development
Indonesia
Vietnam
Thailand
Targets: Securing 2 million tonnes of pellet by 2015
Country Business partners Production target
1 Indonesia OOOO
(state owned company) 50,000 ton/yr
2 Malaysia SOOOO OOOOOOOO
(state owned company) 80,000 ton/yr
3 Indonesia OOOO OOOOO
(private company) 500,000 ton/yr
4 Indonesia OOOO
(state owned company) 400,000 ton/yr
5 Vietnam AOOOOO & OOOOOOO
(private company) 50,000 ton/yr
6 Malaysia OOOOOO
(private company) 200,000 ton/yr
7 Indonesia OOOOOO
(private company) 300,000 ton/yr
8 Thailand OOOOOO
(private company) 150,000 ton/yr
Malaysia
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 17
West meets East.
East Experiences of biomass projects
EPC capability of biomass projects
Utility companies who want to go abroad
Investment and financing capability
Available biomass resources, etc.
West Policy for biomass projects
Markets for biomass projects
Experiences of biomass projects
Technologies of biomass projects
Copyright ⓒ 2012 Eco-Frontier Co. All rights reserved. 18
The end of document
Dedicated to making a difference today for a better tomorrow,
we contribute to the world’s sustainable development,
help healthy growth of businesses, and improve people’s quality of life.
Copyright ⓒ 2012 Eco-Frontier. All Rights Reserved.
Contact: Dae-Woong Lim, Managing Director, Eco-Frontier
6F DMC Hi-Tech Industry Center, 1580 Sangam-dong, Mapo-Gu, Seoul, Korea, http://www.ecofrontier.com
E: [email protected], T: +82-(0)2-3153-7722(office), +82-(0)10-3211-0430(mobile)