FCC-14051311-JGU, V0.2, May 20. Future Circular Collider (FCC) H2020 Study Submission Proposal. http://cern.ch/fcc. Michael Benedikt ESGARD 22. May 2014. Refocused Contents. FCC is option for next generation European Accelerator/Collider infrastructure - PowerPoint PPT PresentationTRANSCRIPT
1H2020 FCC DS proposalMichael BenediktESGARD Meeting 22 May 2014
FCC-14051311-JGU, V0.2, May 20
Future Circular Collider (FCC)H2020 Study Submission
Proposal
Michael BenediktESGARD 22. May 2014
http://cern.ch/fcc
2H2020 FCC DS proposalMichael BenediktESGARD Meeting 22 May 2014
Refocused Contents
• FCC is option for next generation European Accelerator/Collider infrastructure
• Hadron Collider is long-term goal and determining cost and infrastructure factor
• Key technical challenges, cost estimate and optimization of hadron collider form core part of proposal
• One work package on key design question of lepton collider to understand performance
3H2020 FCC DS proposalMichael BenediktESGARD Meeting 22 May 2014
FCC H2020 Scope and StrategyIn line with European Strategy update: • Prepare a concept for a future energy-frontier hadron collider,
including its required infrastructure, to assess its feasibility in terms of technological reach and project implementation at a global level and to present a cost estimate.
• Address key machine design aspect for a future lepton collider based on the same infrastructure.
• Physics, experiment and detector aspects not included in H2020.
4H2020 FCC DS proposalMichael BenediktESGARD Meeting 22 May 2014
Six Work Packages
HH Interaction region design
HH Arc design
HH Cryo-magnet-vacuum-beam pipe
HH high-field magnet design
EE Interaction region design
Collider functionalmachine design
Key technologicalaspects
Collider functional machine design
Management, Coordination and Implementation
Coordination, CDR,Strategy, Cost
5H2020 FCC DS proposalMichael BenediktESGARD Meeting 22 May 2014
H2020 contents vs overall FCC
• FCC hh• The 4 proposed WPs contain the most important and critical
design aspects for performance, cost and feasibility of HH.• Injector complex and Infrastructure studies are not included.
They are site specific and will be guaranteed by CERN.• Cost estimate will be included in management WP. All technical
systems and infrastructure not included in H2020 will be based on scaling or extrapolation from LHC experience and from ongoing EU programs (EuCARD2, HiLumi, etc.)
• FCC ee• Proposed WP focuses on most important and critical design
aspects for machine performance.
6H2020 FCC DS proposalMichael BenediktESGARD Meeting 22 May 2014
Preliminary Overall Resources
WP WP Name Resources Requested
1 HH – IR 372 110
2 HH – Arc 204 48
3 HH – Beam pipe 180 84
4 HH – High-field magnet 200 65
5 EE – IR 240 60
6 Management & Implementation 120 0
Total PM 1316 367
Estimated volume ~12 MEUR ~3.6 MEUR
• Material budget (~1 ME) and travel budget still missing.• Need to focus further the WPs and reduce EU request to
fit into 3 ME call limit.
7H2020 FCC DS proposalMichael BenediktESGARD Meeting 22 May 2014
Participants with EC funding
Organisation Country
1 ALBA-CELLS Spain
2 CEA France
3 CIEMAT Spain
4 CNRS France
5 Cockcroft Institute United Kingdom
6 Daresbury/ASTEC United Kingdom
7 DESY Germany
8 INFN Italy
9 Univ. Oxford (JAI) United Kingdom
10 Karlsruhe Institute of Technology Germany
11 TU Darmstadt Germany
8H2020 FCC DS proposalMichael BenediktESGARD Meeting 22 May 2014
Participants without EC funding
Organisation Country
1 Budker Institute Russia
2 CERN Intergovernmental
3 EPFL Lausanne Switzerland
4 Univ. Geneva Switzerland
• US DOE labs and Asian contribution not yet included, will probably be included at FCC and not H2020 level.