Page 1: FEED-IN MANAGEMENT & ZERO EXPORT - Fronius · PDF fileSYSTEM REQUIREMENTS FOR ZERO EXPORT / Hardware Requirements / Fronius SnapINverter with integrated Fronius Datamanager 2.0 or

FEED-IN MANAGEMENT &

ZERO EXPORT

Fronius International GmbH

Froniusplatz 1

4600 Wels

Page 2: FEED-IN MANAGEMENT & ZERO EXPORT - Fronius · PDF fileSYSTEM REQUIREMENTS FOR ZERO EXPORT / Hardware Requirements / Fronius SnapINverter with integrated Fronius Datamanager 2.0 or

OVERVIEW

/ Feed-in management

/ Electricity grid operators in many countries increasingly demand feed-in limitations as a condition

for grid connection. With the dynamic feed-in control, Fronius offers a solution for optimal feed-in

management for photovoltaic systems. If there are feed-in limitations, the inverter supplies the

connected loads in the household or the building. Additionally the inverter reduces its output

according to the maximum power value accepted by the grid operator.

/ What‘s new?

/ As of now Fronius inverters support zero export, meaning a feed-in limitation of 0%. Thus, no PV

electricity is being fed into the grid. The requirements from the grid operator can easily be met via a

setting on the web interface of the inverter.

/ All Fronius SnapINverters inclusive the Fronius Symo Hybrid support this feature.

2Fronius International GmbH / Feed-in Management & Zero export / 01.2017 - v03

Page 3: FEED-IN MANAGEMENT & ZERO EXPORT - Fronius · PDF fileSYSTEM REQUIREMENTS FOR ZERO EXPORT / Hardware Requirements / Fronius SnapINverter with integrated Fronius Datamanager 2.0 or

SYSTEM REQUIREMENTS FOR ZERO EXPORT

/ Hardware Requirements

/ Fronius SnapINverter with integrated Fronius

Datamanager 2.0 or Fronius Datamanager Box 2.0

/ Fronius Symo Hybrid

/ Fronius Smart Meter 1)

/ Fronius Smart Meter 63A-1

/ Fronius Smart Meter 63A-3

/ Fronius Smart Meter 50kA-31) This feature cannot be guaranteed with a S0 pulse meter.

/ Software Requirements

/ Datamanager Firmware 3.5.1-2 and higher

/ Fronius Symo Hybrid Firmware 1.4.1-11 and higher

/ Inverters with older firmware may require a firmware

update3

Fronius International GmbH / Feed-in Management & Zero export / 01.2017 - v03

Page 4: FEED-IN MANAGEMENT & ZERO EXPORT - Fronius · PDF fileSYSTEM REQUIREMENTS FOR ZERO EXPORT / Hardware Requirements / Fronius SnapINverter with integrated Fronius Datamanager 2.0 or

CONFIGURATION

4Fronius International GmbH / Feed-in Management & Zero export / 01.2017 - v03

/ The configuration can be done via the web interface of the Datamanager (see

“settings DNO Editor”)

Adjustable range:

-10% to 100% of the total DC power

Default value in percent or Watt

Page 5: FEED-IN MANAGEMENT & ZERO EXPORT - Fronius · PDF fileSYSTEM REQUIREMENTS FOR ZERO EXPORT / Hardware Requirements / Fronius SnapINverter with integrated Fronius Datamanager 2.0 or

APPLICATION EXAMPLE 1: 10% LIMITATION

5Fronius International GmbH / Feed-in Management & Zero export / 01.2017 - v03

/ Requirement: 10% limitation from the grid supplier

/ Instead of 10% also 60% (Germany) can be requested

Page 6: FEED-IN MANAGEMENT & ZERO EXPORT - Fronius · PDF fileSYSTEM REQUIREMENTS FOR ZERO EXPORT / Hardware Requirements / Fronius SnapINverter with integrated Fronius Datamanager 2.0 or

APPLICATION EXAMPLE 2: ZERO FEED-IN

6Fronius International GmbH / Feed-in Management & Zero export / 01.2017 - v03

/ Requirement: No PV energy is fed into the public grid

Page 7: FEED-IN MANAGEMENT & ZERO EXPORT - Fronius · PDF fileSYSTEM REQUIREMENTS FOR ZERO EXPORT / Hardware Requirements / Fronius SnapINverter with integrated Fronius Datamanager 2.0 or

APPLICATION EXAMPLE 3: -2% LIMITATION

7Fronius International GmbH / Feed-in Management & Zero export / 01.2017 - v03

/ Requirement: Permanent, mininal consumption from public grid

/ Reason: Grid suppliers are afraid that PV energy is fed into the public grid

despite the zero feed-in regulation. Therefore the -2% can be seen as a safety

factor. It is selected to guarantee a continuous minimum consumption (like a

buffer).

Page 8: FEED-IN MANAGEMENT & ZERO EXPORT - Fronius · PDF fileSYSTEM REQUIREMENTS FOR ZERO EXPORT / Hardware Requirements / Fronius SnapINverter with integrated Fronius Datamanager 2.0 or

CONFIGURATION DIAGRAM

8Fronius International GmbH / Feed-in Management & Zero export / 01.2017 - v03

The Fronus Smart Meter

can also be installed in

the consumption path.

Page 9: FEED-IN MANAGEMENT & ZERO EXPORT - Fronius · PDF fileSYSTEM REQUIREMENTS FOR ZERO EXPORT / Hardware Requirements / Fronius SnapINverter with integrated Fronius Datamanager 2.0 or

SPECIFICATION ZERO EXPORT

/ Adjustable Range: -10% to 100%

/ Settling time: < 5 Seconds

/ Applies only to the following system configuration:

/ 1 - 5 Fronius SnapINverter 1)

/ 1 Fronius Datamanager

/ 1 Fronius Smart Meter

/ Phase-balanced

/ In three-phase systems, the sum of the load on all phases is being measured and the inverters are

feeding in symmetrically. No regulation per-phase.

/ Failure safety:

/ If the connection between the Fronius Datamanager and the Fronius Smart Meter fails, the inverters

reduce their output to the predefined minimal value (fall back scenario).

1) For system size > 5 Fronius SnapINverters the settling time of under 5 seconds cannot be guaranteed. Furthermore the configuration

with several inverters is not possible with Fronius Hybrid inverters. Only one Fronius Hybrid inverter can be combined with one Fronius

Smart Meter.

9Fronius International GmbH / Feed-in Management & Zero export / 01.2017 - v03

Page 10: FEED-IN MANAGEMENT & ZERO EXPORT - Fronius · PDF fileSYSTEM REQUIREMENTS FOR ZERO EXPORT / Hardware Requirements / Fronius SnapINverter with integrated Fronius Datamanager 2.0 or

SPECIFICATION ZERO EXPORT

/ Chronological sequence by load shedding

Example:

Fronius Primo 8.2-1-M

Zero export

Load drop from 6700W to 1700W

Further details see manufacturer’s declation!

10Fronius International GmbH / Feed-in Management & Zero export / 01.2017 - v03

Page 11: FEED-IN MANAGEMENT & ZERO EXPORT - Fronius · PDF fileSYSTEM REQUIREMENTS FOR ZERO EXPORT / Hardware Requirements / Fronius SnapINverter with integrated Fronius Datamanager 2.0 or

AVAILABLE DOCUMENTS

/ Planning guide for dynamic power reduction

/ Manufacturer`s declaration

/ Flyer

11Fronius International GmbH / Feed-in Management & Zero export / 01.2017 - v03

Page 12: FEED-IN MANAGEMENT & ZERO EXPORT - Fronius · PDF fileSYSTEM REQUIREMENTS FOR ZERO EXPORT / Hardware Requirements / Fronius SnapINverter with integrated Fronius Datamanager 2.0 or

All information is without guarantee in spite of careful editing - liability excluded.