fibernet master plan - montgomerycountymd.gov · originally built over fiber plant that the...

83
FiberNet Master Plan Prepared for Montgomery County, Maryland by CTC Technology & Energy Initial Release December 2017 Updated March 2018

Upload: vuongque

Post on 19-Jul-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

     

  

 

  

  

  

   

       

FiberNet Master Plan  

Prepared for Montgomery County, Maryland  by CTC Technology & Energy 

Initial Release December 2017 

Updated March 2018    

FiberNet Master Plan | Updated March 2018 

  

ii  

 

Contents1  Executive Summary ................................................................................................................. 1 

1.1  FiberNet’s Value to the County ........................................................................................ 1 

1.2  FiberNet’s Current Services .............................................................................................. 3 

1.3  FiberNet Sites to Be Added .............................................................................................. 4 

1.4  FiberNet Improvements in Process .................................................................................. 4 

1.5  Recommendations for Future FiberNet Operations ........................................................ 4 

2  Keys to Continued Success: Value of FiberNet ....................................................................... 6 

2.1  FiberNet History ............................................................................................................... 6 

2.2  FiberNet Must Retain Control of Its Infrastructure and Operations................................ 7 

3  Future Needs ........................................................................................................................... 8 

3.1  User Site Additions ........................................................................................................... 8 

3.2  Interagency Support and Collaboration ........................................................................... 9 

3.2.1  Montgomery County Public Schools .................................................................. 11 

3.2.2  Montgomery College ......................................................................................... 14 

3.2.3  Maryland–National Park and Planning Commission ......................................... 16 

3.2.4  Washington Suburban Sanitary Commission .................................................... 19 

3.2.5  Housing Opportunities Commission .................................................................. 21 

3.2.6  Montgomery County Government & Department of Technology .................... 23 

3.3  ultraMontgomery and Broadband Roadmap ................................................................. 25 

3.3.1  ultraMontgomery .............................................................................................. 26 

3.3.2  Broadband Roadmap ......................................................................................... 26 

3.4  Current and Future Initiatives Requiring FiberNet Support ........................................... 26 

4  FiberNet Operations ............................................................................................................. 31 

4.1  Summary of Prior Master Plans ..................................................................................... 31 

4.2  FiberNet Organizational Study ....................................................................................... 32 

4.2.1  Governance ........................................................................................................ 32 

4.2.2  Recommendations ............................................................................................. 34 

4.3  DTS Organizational Realignment .................................................................................... 35 

FiberNet Master Plan | Updated March 2018 

  

iii  

 

4.4  FiberNet—Current Staffing Levels ................................................................................. 36 

4.5  Key Performance Indicators ........................................................................................... 37 

4.5.1  Guidelines for Establishing KPIs ......................................................................... 37 

4.5.2  Classification of Project Status ........................................................................... 39 

4.5.3  Project Management Systems and Methodologies ........................................... 40 

4.5.4  Tools for Evaluating KPIs .................................................................................... 42 

4.6  Status of Physical Infrastructure Remediation, Upgrades, and Additions ..................... 46 

4.6.1  Hub Remediation ............................................................................................... 46 

4.6.2  Feeder Fiber Expansion ...................................................................................... 49 

4.6.3  Maximizing the Value of Existing Infrastructure ............................................... 51 

4.6.4  Documentation Process—Physical Layer ........................................................... 53 

4.7  FiberNet Service Description .......................................................................................... 55 

4.7.1  FiberNet I Services ............................................................................................. 55 

4.7.2  FiberNet II Services ............................................................................................ 56 

4.7.3  FiberNet II.v Services .......................................................................................... 59 

4.8  FiberNet Optical Technology Migration (FiberNet III) ................................................... 63 

Appendix A1: Candidate FiberNet 3.0 Network Electronics Architecture – IP/MPLS Backbone . 67 

Appendix A2: Candidate FiberNet 3.0 Network Electronics Architecture – Optical Backbone.... 68 

Appendix B: Candidate FiberNet 3.0 Network Electronics Architecture – Equipment BOM ....... 69 

Appendix C: Consolidated Site Addition List with Costs ............................................................... 75 

Appendix D: Glossary of Acronyms ............................................................................................... 77 

 

FiguresFigure 1: FiberNet Costs vs. Savings for County ............................................................................. 2 

Figure 2: List of Services by Agency ................................................................................................ 3 

Figure 3: FiberNet Costs vs. Savings for County ............................................................................. 7 

Figure 4: List of Services by Agency ................................................................................................ 9 

Figure 5: Broadband Realignment Organizational Chart .............................................................. 36 

Figure 6: High‐Level Fiber Routing for Cost Estimate ................................................................... 43 

Figure 7 : Output of Cost Estimation Tool .................................................................................... 43 

Figure 8: Value Input ..................................................................................................................... 44 

FiberNet Master Plan | Updated March 2018 

  

iv  

 

Figure 9: Smartsheet Home Page ................................................................................................. 45 

Figure 10: Gantt Chart in Smartsheet ........................................................................................... 45 

Figure 11: FiberNet Map with Hubs .............................................................................................. 46 

Figure 12: Logical Diagram of FiberNet Hubs and Backbone Cable ............................................. 47 

Figure 13: Representative Map of Feeder Fiber Expansion and User Site Additions ................... 49 

Figure 14: Feeder Fiber – Original Build ....................................................................................... 50 

Figure 15: Feeder Fiber – Expanded Build .................................................................................... 50 

Figure 16: Feeder Fiber – Remediated Build ................................................................................ 51 

Figure 17: Microduct Applications ................................................................................................ 52 

Figure 18: Physical Plant Digitization Process ............................................................................... 53 

Figure 19: Physical Plant Documentation Process ........................................................................ 54 

Figure 20: DWDM Service Segmentation Example ....................................................................... 62 

 

TablesTable 1: FiberNet CIP Appropriation by Fiscal Year ........................................................................ 6 

Table 2: FiberNet Operations and Maintenance Budget by Fiscal Year ......................................... 7 

Table 3: Planned Service Enhancements for Participating Agencies ............................................ 10 

Table 4: Pending MCPS Projects Under the FiberNet CIP ............................................................. 13 

Table 5: Pending M–NCPPC Projects Under the FiberNet CIP ...................................................... 17 

Table 6: M –NCPPC Estimated Savings by Migrating to FiberNet ................................................ 18 

Table 7: Cost Recovery Period for Pending M–NCPPC Projects Under FiberNet CIP ................... 19 

Table 8: Pending WSSC Projects Under the FiberNet CIP ............................................................. 20 

Table 9: Pending MCG Projects Under the FiberNet CIP .............................................................. 24 

Table 10: County Initiatives Requiring FiberNet Support ............................................................. 26 

Table 11: UltraMontgomery Initiatives Requiring FiberNet Support ........................................... 29 

Table 12: Anticipated Process for Establishing KPIs ..................................................................... 38 

Table 13: FiberNet Status Indiciator Categories ........................................................................... 40 

Table 14: Hub Remediation Efforts (Completed and Planned) .................................................... 48 

Table 15: Estimated FiberNet III Network Electronics Capital Upgrade Costs ............................. 65 

Table 16: Estimated FiberNet III Network Electronics Annual Maintenance Costs ..................... 65 

 

FiberNet Master Plan | Updated March 2018 

  

1  

 

1 ExecutiveSummaryThis Master Plan is intended as a summary of project status and a planning tool for Montgomery 

County government agencies using FiberNet and the broader FiberNet user community. The 2017 

Master Plan presents: 

FiberNet  strategic needs by each Agency,  and outlines Agency  FiberNet projects and 

initiatives that are planned or in progress;  

Priorities for capital construction, operations and maintenance process improvements;  

A high‐level capital construction schedule and budget for user site buildout plans over 

the next three to four years, including requested sites that have not yet been approved 

for construction or funded.  

Fiber construction to many of the remaining sites on the FiberNet site list will be very expensive. 

The Master Plan recommends that the  ITPCC consider whether FiberNet should be  funded to 

contract for transport services on behalf of the Participating Agencies, to meet the short and mid‐

range bandwidth and connectivity needs of Participating Agencies, when this option is in the best 

interest of the ITPCC.  Beyond these funding issues, the Master Plan explores: 

FiberNet operational  considerations—including  the need  for  sufficient qualified  staff, 

and a management structure that effectively distributes supervision of the network; 

A  FiberNet  governance  structure  based  on  established  roles  and  duties,  not  simply 

informal relationships; and 

The technical options and recommendations to transition to the next generation core 

electronics for FiberNet III.  

This  is the third Master Plan since 1995, and the 2017 Master Plan recommends updating the 

Master Plan on at  least a bi‐annual basis.   The 2017 Master Plan presents  the  technical and 

operations issues that must be addressed as part of the transition to FiberNet III, and the intent 

is  for  the  ITPCC  to work  collaboratively  to  build  consensus  around  operational  choices  and 

technical solutions to implement a transition to FiberNet III.   

1.1 FiberNet’sValuetotheCountyFiberNet was established  in 1995 as a cost‐effective, expandable network to meet the County 

government’s data, voice, and video communications needs. Originally built over fiber plant that 

the Department of Transportation (DOT) had installed for traffic communications, FiberNet was 

one of the first and largest local‐government‐owned fiber networks in the country. It is operated 

by the Department of Technology Services (DTS), with the physical plant maintained by DOT. 

FiberNet’s FY18 operations and maintenance budget  is $4.1 million. By  comparison,  in 2016, 

FiberNet’s  offsets  were  estimated  at  $33  million  per  year  in  monthly  recurring 

FiberNet Master Plan | Updated March 2018 

  

2  

 

telecommunications and network services costs that the County would otherwise have to spend 

for comparable communications services (Figure 1).1  

Figure 1: FiberNet Costs vs. Savings for County 

 

Because of FiberNet, the County is nationally recognized as a leader in public sector provision of 

fiber services to meet internal needs. FiberNet now comprises 665 route miles of fiber connecting 

approximately  474  sites with  24 more  approved  for  construction.  The  fiber  infrastructure  is 

installed mostly as County attachments on utility poles and in County underground conduit. The 

County owns  its fiber and maintains  its pole attachment rights, so FiberNet  is  independent of 

cable and telecommunications companies.2 

In  addition  to  the County’s  substantial  annual  cost  savings  and  the  capacity  FiberNet makes 

available  to County users, which significantly exceeds  the capacity available  from commercial 

services, additional functional benefits include the ability to:  

Determine the priority of repair and construction tasks,  

Choose the most suitable physical cable pathway for new construction,  

Document all aspects of the physical infrastructure,  

Scale and upgrade services according to a known, negotiated price and schedule,  

Construct advanced infrastructure in areas unserved by private sector service providers,  

Determine and manage according to performance metrics, and  

                                                       1 See “Fiscal Benefits of FiberNet,” http://www.montgomerycountymd.gov/dts/fibernet.html  2 FiberNet’s 665 route miles include approximately 100 miles of fiber obtained as part of the Comcast cable franchise agreement. The first sites constructed were primarily public safety sites, but in later years, the Comcast partnership was used to reach sites that were far from the County’s FiberNet fiber and more expensive for the County to construct independent of Comcast. Most of the Comcast fiber is in the last mile or so, and connects to a single site. For the later sites, the County paid Comcast the incremental construction cost for the fiber and has right of use of the cable strands, but the cable belongs to Comcast. If the Comcast franchise is terminated, the County has the right to purchase at depreciated value the sites that Comcast built for the County as part of the franchise, and at no additional cost where the County has already funded fiber construction. 

FiberNet Master Plan | Updated March 2018 

  

3  

 

Determine what uses of the network are acceptable.  

1.2 FiberNet’sCurrentServicesFiberNet is the core network that delivers all County communications services – access to e‐mail, 

the  Internet,  and  311.    FiberNet  serves  as  the  backbone  for  public  safety  communications 

including supporting a redundant 911 calling network, fire station alerting, a significant part of 

public safety radio systems, police station communications, communications to state police, and 

public safety mobile communications are routed through FiberNet.    

In addition to its enterprise responsibilities to Montgomery County Government (MCG), FiberNet 

has  implemented and supported services  for other agencies as one of  its core directives. The 

agencies  include:  Montgomery  County  Public  Schools  (MCPS),  Montgomery  College  (MC), 

Maryland–National Capital Park and Planning Commission  (M–NCPPC), Washington Suburban 

Sanitary  Commission  (WSSC),  and  Housing  Opportunities  Commission  (HOC).  All  primary 

telecommunications services for MCPS, MC, M‐NCPPC, and HOC are delivered over FiberNet.  

Figure 2: List of Services by Agency 

  HOC  MC  MCPS  MCG  M‐NCPPC  WSSC 

Wide Area Network              

Internet Access             

Disaster Recovery Service             

PON             

Local Loop Cost Elimination             

Video Connectivity             

DWDM             

Telephony & Wi‐Fi             

Public Safety Communications             

Governance of  this ongoing  support  is by County Council  resolution and a  formal committee 

called  the  Interagency  Technology  Policy  and  Coordination  Committee  (ITPCC).  Along  with 

coordination, oversight and planning, ITPCC has a CIO Subcommittee to review and recommend 

technical aspects. Depending on each agency’s  individual needs, FiberNet provides services or 

the  infrastructure  for  services  to  the participating agency. Figure 2  illustrates  the  services or 

infrastructure for services utilized or being considered by each agency. 

As part of FiberNet’s responsibilities and obligations to the ITPCC, the Master Plan documents 

each member’s evolving needs and future plans for services, as well as the progress of currently 

approved  projects.  Information  will  continue  to  be  gathered  via  committee  meetings  and 

individual planning sessions with ITPCC members and FiberNet managers. 

FiberNet Master Plan | Updated March 2018 

  

4  

 

1.3 FiberNetSitestoBeAddedThe County government and FiberNet users have requested that FiberNet add 30 priority sites to 

the network over the period of FY17 to FY20. FiberNet has also received requests to fund 39 sites 

through the FiberNet CIP appropriation. In this period, the current number of sites in the FiberNet 

pipeline  totals  54.  Because  other  agencies  and  departments  of  the  County  government  can 

independently fund sites, the total pipeline number could grow. For example, if funding becomes 

available for the M–NCPPC Wi‐Fi in the Parks project, 12 to 15 additional sites could be added to 

the pipeline. 

These sites have been placed into a master construction schedule that spreads the work out over 

the next three to four fiscal years to accommodate FiberNet’s annual budget (see Appendix C).  

1.4 FiberNetImprovementsinProcessIn  addition  to  ongoing  operational  efforts,  FiberNet’s  leadership  has  focused  on  a  series  of 

improvements to the network’s infrastructure. As described in detail below, these include: 

Hub  remediation:  FiberNet  currently  has  12  hub  locations  throughout  the  County.  These 

locations provide aggregation points for the network’s user sites. FiberNet planned to remediate 

the hub sites at a rate of approximately one hub per quarter. (See Section 4.6.1.) 

Feeder fiber expansion: Feeder fiber runs from the hub sites to user sites, with laterals from a 

main feeder branching to individual sites. As with the hub remediation, feeder fiber expansion is 

necessary due to meet current demand and support future site additions. (See Section 4.6.2.) 

Service‐level specification: FiberNet is monitored 24x7 by a DTS Network Operations Center. DTS 

has developed a document that defines the service level agreement (SLA) for FiberNet services— 

creating quantifiable expectations for service. (See Section 4.7.2.) 

1.5 RecommendationsforFutureFiberNetOperationsThe Master  Plan  identifies  a  number  of  recommendations  related  to  FiberNet  operations, 

including:  

Budgeting for expansion: In 2006, ITPCC reached an understanding that the FiberNet CIP would 

fund  extension  of  FiberNet  to  existing  buildings,  and  the  cost  of  a  fiber  connection  and 

termination to a new or significantly renovated building would be incorporated into the capital 

budget for the building, and not become a cost absorbed by the FiberNet budget. Establishing 

cost‐sharing  standards  will  help  prevent  unexpected  overruns  in  budgets  and  promote 

engagement with FiberNet’s end users. (See Section 3.1.) 

FiberNet Master Plan | Updated March 2018 

  

5  

 

Documenting the physical layer: In order to keep up with best practices for network expansion 

and required network reliability, FiberNet will continue its focus on documentation of new fiber 

routes, as well as recording break‐fix changes (see Section 4.6.4).  

Migrating  to new optical  technology: FiberNet’s  current  technological  roadmap  calls  for  the 

implementation of dense wavelength division multiplexing (DWDM) technology on the FiberNet 

high‐speed backbone and passive optical networking (PON) as the means of connecting individual 

users  to  FiberNet  (where  agencies  have  opted  into  PON  deployments 3 ).  Both  approaches 

represent  an  innovative  implementation  of  fiber  networking  technologies. Moreover,  these 

technologies will provide significantly more options in keeping the network secure; will reduce 

the network lifetime cost, the likelihood of failures, and the network’s energy consumption; and 

will make it easier and cheaper to add users and capacity to the network. (See Section 4.8.) 

                                                       3 MCG and MNCPPC are now implementing PON as a wiring standard in new buildings and MC is actively reviewing.  HOC and WSSC have not made a determination.  MCPS has opted out of using PON.  

FiberNet Master Plan | Updated March 2018 

  

6  

 

2 KeystoContinuedSuccess:ValueofFiberNet

2.1 FiberNetHistoryFiberNet was established in 1995 as a cost‐effective, adaptable, expandable network to meet the 

Montgomery County government’s data, voice, and video communications needs. Originally built 

over  fiber plant  that  the Department of Transportation  (DOT) had begun  installing  for  traffic 

communications,  FiberNet  was  one  of  the  first  and  largest  local‐government‐owned  fiber 

networks in the country. It is operated by the Department of Technology Services (DTS), with the 

physical plant maintained by DOT. 

Over  time,  FiberNet was expanded with  fiber provided  through  the County’s  cable  franchise 

agreements  and  further  constructed with  restricted  capital  funding  from  the  cable  franchise 

agreements  and  funds  from  the  federal  government’s  broadband  stimulus  program—the 

American Recovery and Reinvestment Act of 2009 (ARRA) Broadband Technology Opportunities 

Program (BTOP).  

The County is nationally recognized as a leader in public sector provision of fiber services to meet 

internal needs. FiberNet now comprises 665 route miles of fiber connecting approximately 474 

sites with  24 more  approved  for  construction.  The  fiber  infrastructure  is  installed mostly  as 

County attachments on utility poles and in County underground conduit. Unlike Fairfax County 

and the District of Columbia, the County owns its fiber and maintains its pole attachment rights, 

so FiberNet is independent of cable and telecommunications companies.4 

The tables below depict FiberNet’s annual capital expense and operating budgets for fiscal year 

2017 and fiscal year 2018. 

Table 1: FiberNet CIP Appropriation by Fiscal Year 

FY  DOT  FiberNet  Total 

FY17  $752,500 $2,940,000 $3,692,500

FY18  $565,000 $3,325,000 $3,890,000

 

                                                       4 FiberNet’s 665 route miles include approximately 100 miles of fiber obtained as part of the Comcast cable franchise agreement. The first sites constructed were primarily public safety sites, but in later years, the Comcast partnership was used to reach sites that were far from the County’s FiberNet fiber and more expensive for the County to construct independent of Comcast. Most of the Comcast fiber is in the last mile or so, and connects to a single site. For the later sites, the County paid Comcast the incremental construction cost for the fiber and has right of use of the cable strands, but the cable belongs to Comcast. If the Comcast franchise is terminated, the County has the right to purchase at depreciated value the sites that Comcast built for the County as part of the franchise, and at no additional cost where the County has already funded fiber construction. 

 

FiberNet Master Plan | Updated March 2018 

  

7  

 

Table 2: FiberNet Operations and Maintenance Budget by Fiscal Year 

FY  Operations & Maintenance 

FY17  $3,784,000

FY18  $4,096,500

By comparison, in 2016 the network offsets were estimated at $33 million per year in monthly 

recurring telecommunications and network services costs that the County would otherwise have 

to spend for comparable communications services.5  

Figure 3: FiberNet Costs vs. Savings for County 

 

2.2 FiberNetMustRetainControlofItsInfrastructureandOperationsStaffing and organizational issues are important considerations for FiberNet’s ongoing success. 

Over  the  lifetime of FiberNet,  the County has achieved significant benefits  from operating an 

independent  network.  In  addition  to  the  County’s  substantial  annual  cost  savings  and  the 

capacity  FiberNet makes  available  to  County  users, which  significantly  exceeds  the  capacity 

available from commercial services, additional functional benefits include the ability to:  

Determine the priority of repair and construction tasks,  

Choose the most suitable physical cable pathway for new construction,  

Document all aspects of the physical infrastructure,  

Scale and upgrade services according to a known, negotiated price and schedule,  

Construct advanced infrastructure in areas unserved by private sector service providers,  

Determine and manage according to performance metrics, and  

Determine what uses of the network are acceptable. 

Following the Organizational Study (see Section 4), FiberNet has made efforts to fill key positions 

internally instead of outsourcing those roles.  

                                                       5 See “Fiscal Benefits of FiberNet,” http://www.montgomerycountymd.gov/dts/fibernet.html  

FiberNet Master Plan | Updated March 2018 

  

8  

 

3 FutureNeeds

3.1 UserSiteAdditionsThe County government and FiberNet users have requested that FiberNet add 30 priority sites to 

the network over the period of FY17 to FY20. FiberNet has also received requests to fund 39 sites 

through the FiberNet CIP appropriation. In this period, the current number of sites in the FiberNet 

pipeline  totals  54.  Because  other  agencies  and  departments  of  the  County  government  can 

independently fund sites, the total pipeline number could grow. For example, if funding becomes 

available for the M–NCPPC Wi‐Fi in the parks project, 12 to 15 additional sites could be added to 

the pipeline. 

At some point the cost to construct fiber to a site becomes economically unjustifiable. This does 

not  diminish  the  need  for  reliable  bandwidth;  rather  it  suggests  that  FiberNet may  have  a 

requirement to provide WAN connectivity through other means. 

These sites and the feeder fiber expansion routes have been placed into a master construction 

schedule  that spreads  the work out over  the next  three  to  four  fiscal years  to accommodate 

FiberNet’s annual budget for constructing fiber and connecting user sites (see Appendix C). Cost 

estimates in the aforementioned table were formulated by creating a desk‐level design for each 

route, and applying unit pricing from current County construction contracts. Other constraints 

incorporated into the schedule include the completion of the hub remediation and construction 

of the feeder routes for the sites. 

A  formalized  process will  be  developed  for  adding  to  and  prioritizing  within  the  proposed 

schedule. User site addition  requests come  from multiple agencies with competing priorities. 

Having  impartial methods  and  clear  procedures  in  the  prioritization  of  sites  can  set  proper 

expectations for the various external stakeholders and internal departments. 

In terms of budgeting, there is an inherent economy of scale in connecting multiple sites in one 

fiber  construction  project  and  in  taking  advantage  of  opportunities  provides  by  other 

construction projects  in  the area. This approach can also aid  in creating synergies with other 

related, but not controlling, initiatives.  

The capital projects  listed  in Appendix C represent the existing buildings  for which a FiberNet 

connection would be  funded by  FiberNet,  subject  to  ITPCC  review.    In 2006,  ITPCC member 

agencies reached an understanding that the cost of a fiber connection to a new building should 

be incorporated into the capital budget for the building, and not become a cost absorbed by the 

FiberNet budget. Establishing cost‐sharing standards will help prevent unexpected overruns  in 

budgets and promote engagement with FiberNet’s end users.  

FiberNet Master Plan | Updated March 2018 

  

9  

 

As explored in Section 4.5.4.2, using GIS (Geographical Information Systems) programs to map 

the future sites, and allowing them to be overlaid with proposed fiber expansion initiatives, will 

create efficiencies in fiber construction. This can be one component of a larger strategic plan for 

smart growth of the network. (This topic is explored in Section 4.5.) 

3.2 InteragencySupportandCollaborationIn addition to its enterprise responsibilities to Montgomery County Government (MCG), FiberNet 

has  implemented and supported services  for other agencies as one of  its core directives. The 

agencies  include:  Montgomery  County  Public  Schools  (MCPS),  Montgomery  College  (MC), 

Maryland–National Capital Park and Planning Commission  (M–NCPPC), Washington Suburban 

Sanitary Commission (WSSC), and Housing Opportunities Commission (HOC). Governance of this 

ongoing support is by County Council resolution and a formal committee called the Interagency 

Technology Policy and Coordination Committee (ITPCC). Along with coordination, oversight and 

planning, ITPCC has a CIO Subcommittee to review and recommend technical aspects. Depending 

on each agency’s individual needs, FiberNet provides services or the infrastructure for services 

to the participating agency. Figure 4 illustrates the services or infrastructure for services utilized 

or being considered by each agency. 

Figure 4: List of Services by Agency 

  HOC  MC  MCPS  MCG  M‐NCPPC  WSSC 

Wide Area Network              

Internet Access             

Disaster Recovery Service             

PON             

Local Loop Cost Elimination             

Video Connectivity             

DWDM             

Telephony & Wi‐Fi             

Public Safety Communications             

  

As part of FiberNet’s responsibilities and obligations to the ITPCC, the Master Plan documents 

each member’s evolving needs and future plans for services, as well as the progress of currently 

FiberNet Master Plan | Updated March 2018 

  

10  

 

approved  projects.  Information  will  continue  to  be  gathered  via  committee  meetings  and 

individual planning  sessions with  ITPCC members and  FiberNet managers.   Based on  current 

available information, FiberNet anticipates enhancing the following services: 

Table 3: Planned Service Enhancements for Participating Agencies 

  MCPS  MC  M‐NCPPC  WSSC  HOC  MCG 

Additional Sites Requested   14+  4  20  10    35 

Sites Approved  7  3  6  3‐5    30 

Wi‐Fi             

Dedicated/Direct Links             

Regional Govt/Ed Links             

More ISP Broadband             

Cost Avoidance (Replace Leased Services with FiberNet) 

           

DWDM             

Disaster Recovery             

Enhanced Network Monitoring/NOC 

           

Peering             

Smart County             

Radio             

Kiosks             

PON  X           

 

The  information  in  this  section  was  gathered  through  discussions  held  as  part  of  the 

Organizational Study. Additionally, representatives of each ITPCC member had the opportunity 

to expand and update the description of the entity’s FiberNet needs. This section also estimates 

anticipated agencies’ needs based on available  information about  current  initiatives and  site 

additions.  

This section is comprised of information on the needs of the agencies, as provided or described 

by  those  agencies.  These  needs  have  not  been  prioritized  or  analyzed  by  FiberNet  or MCG. 

Throughout the document references are made to fiscal and calendar years. When a fiscal year 

is designated as in FY17, the reference identifies the FiberNet CIP appropriation year providing 

FiberNet Master Plan | Updated March 2018 

  

11  

 

funds  that  site’s  construction. When a  calendar year  is designated as  in CY17,  the  reference 

identifies the year that site is expected to be connected to FiberNet. The total construction time 

for building a site from the time it is Approved To Build takes from twelve to eighteen months. 

3.2.1 MontgomeryCountyPublicSchools(MCPS)MCPS’s  IT vision statement  in  its Strategic Technology Plan  is: “All  learners will participate  in 

technology‐enriched  learning communities that  inspire  intellectual curiosity and prepare them 

with the knowledge and skills to excel in college and chosen careers in an evolving digital age.”6 

Some of the notable highlights of the strategic plan, as it pertains to FiberNet, are a commitment 

to deploying Wi‐Fi  in every school central services office, developing a sustainable technology 

funding plan, reducing “print instructional text” by 70 percent, “supporting equitable access to 

the MCPS digital community,” and enabling “anytime access to files and appropriate data.” 

3.2.1.1 NeedsAssessmentMCPS representatives provided the following information and insight: 

The greatest factors we anticipate  in terms of the needs for MCPS are  increases  in two major 

areas: 

Dependency on  the  internet  for  cloud  solutions,  such  as Office 365, Google Apps  for 

Education, and Oracle 

Number of end‐user devices that will require network access (WLAN, LAN, and WAN) 

Specifically, these are the anticipated needs for MCPS as it relates to FiberNet and the FiberNet 

solution over the course of the next 10 years, starting in FY19: 

1. Currently, MCPS has an ISP connection to RCN and Atlantech Online (AOI). The connection 

from RCN is made directly into 45 W. Gude, but the AOI connection comes into MCPS by 

way of FiberNet. In anticipation of approaching 20 Gbps of ISP utilization by the end of 

FY19, it would be advantageous for MCPS to have a dedicated link from Gude directly to 

AOI, or to the FiberNet hub where AOI connects. In the event of an RCN outage, our AOI 

connection over FiberNet would be overwhelmed because all school traffic and internet 

traffic would be combined on the one path from FiberNet to the Gude Data Center. 

2. FiberNet should continue  the upgrade of bandwidth  to all schools,  including a 1 Gbps 

capacity  for  the  elementary  schools,  which  we  anticipate  being  adequate  for  the 

foreseeable future. 

                                                       6 “Montgomery County Public Schools Strategic Technology Plan (2014 – 2016),” http://www.montgomeryschoolsmd.org/uploadedFiles/departments/technology/Strategic_Tech_Plan.pdf  

FiberNet Master Plan | Updated March 2018 

  

12  

 

3. While  the  current  1  Gbps  of  bandwidth  capacity  that  FiberNet  is  planning  for  the 

elementary  schools  is  expected  to  be  adequate,  we  anticipate  a  need  for  greater 

bandwidth in middle and high schools. This will require more than the current 20 Gbps 

connection we have into FiberNet from our data center at 45 W. Gude. 

4. Tremendous progress has been made to get our schools connected to FiberNet, but MCPS 

will ultimately need all of our non‐school‐based offices connected as well. We believe this 

is  already  part  of  the  budget  allocation  for  FiberNet,  but  there  has  not  been much 

movement on this given the priority on schools. It may take a few years to get them all 

connected. 

5. Currently, we have secondary Comcast connections in all of our schools. The connection 

goes to the internet over which we use VPN technology to tunnel the traffic between the 

schools/offices back to 45 W. Gude. The path is both inefficient and requires the use of 

additional and specialized equipment to establish the tunnel. It would be a tremendous 

improvement in both privacy and efficiency if FiberNet could leverage a relationship with 

Comcast and bring the connections from each of the modems in those schools and offices 

back to 45 W. Gude by way of FiberNet and not over the internet. 

6. While most of the points on this list speak to needs and additions, one trend we would 

like  to  see  go  away,  for MCPS  at  least,  is  the  use  of  Passive Optical Network  (PON) 

technology to connect our locations. While we recognize the cost savings of a PON‐based 

network, it has substantial obstacles in troubleshooting because it is light based. Point‐

to‐point “visibility” is not as viable as it is on copper‐based technology at the LAN level. 

Additionally, for the locations where PON is used, MCPS staff is limited in terms of what 

we can troubleshoot and resolve  for ourselves. We have to depend on the specialized 

skillset and availability of outside resources, which affects how quickly we can provide 

service to our customers, a service we have traditionally responded within minutes and 

hours to in the past. 

7. MCPS’s Transportation department has added a radio‐based technology to allow wireless 

communications  to and  from buses. As a  result,  three  to  five  radio  towers have been 

added  (or more may  be  coming)  to  connect  the  Transportation  depots  to  the  radio 

network. Given the number of radios that will now connect to the MCPS network through 

these  radio  towers, having  FiberNet  connect  to  these  radio  towers would provide  an 

efficient and reliable connection from the depots to our network using those radios. 

3.2.1.2 CurrentProjectStatusCurrently, there are 9 MCPS sites in the pipeline to be connected under the FiberNet CIP from 

FY17  to  FY19  (Table  4).    Five  sites  have  been  approved  (A)  for  FiberNet  funding:  Richard 

FiberNet Master Plan | Updated March 2018 

  

13  

 

Montgomery Elementary School, Radnor Center, Wilson Wims Elementary School, Emory Grove 

ES  and  West  Farm  Depot  NSBO.    Four  sites  are  still  under  consideration  for  near  term 

construction.  In addition, three sites – Mark Twain Blair Ewing Center, Lynnbrook Center, and 

Randolph Depot – have recently been connected, the Stonestreet Print Shop will be connected 

by a campus  link constructed by MCPS, and two sites – CTI NBSO on Choke Cherry Road and 

Muddy Branch–Festival –  were removed from consideration because they are closing. Prior to 

approval,  there  is  a  need  for  further  analysis  to  determine  the  rationale  for  building  to  the 

unapproved sites. The analysis for site additions considers the agency’s needs and compares the 

overall benefit of the site addition to the cost of construction.  

Table 4: Pending MCPS Projects Under the FiberNet CIP 

STATUS  SITE & BUDGET YEAR IN WHICH FUNDING WILL BE ALLOCATED  COST ESTIMATE 

(A)pproved  FY17 Total  $208,561 

Built  Lynnbrook Center NSBO, 8001 Lynnbrook Drive, Bethesda  $0 

Built  Mark Twain Blair Ewing Center, 14501 Avery Road, Rockville  By Comcast $0

MCPS Campus 

Print Shop Stonestreet NSBO, 660 North Stonestreet Avenue, Adjacent to Other MCPS FiberNet site, MCPS will connect 

$0

Built  Randolph Depot NSBO, 1800 Old Randolph Road, Silver Spring  $49,700 

A  Richard Montgomery ES, 322 W. Edmonston, Rockville  $158,861 

  FY18 Total  $500,701 

Deferred  Hadley Farms NSBO, 7401 Hadley Farms Drive, Gaithersburg  $117,200 

Deferred  Montrose Ctr NSBO, 12301 Academy Way Rockville  $45,200 

A  Radnor Center, 7000 Radnor Lane, Bethesda  $38,700 

A  Wilson Wims ES, 12520 Blue Sky Drive, Clarksburg  $254,400 

A  Emory Grove Holding School (added by deferring Hadley Farms)  $45,200

  FY19 Total  $441,000 

  Kingsley Wilderness Center NSBO, 22870 Whelan Lane, Boyds   $90,000 

  Rica SS, 15000 Broschart Road, Rockville  $142,000 

A  West Farm Depot NSBO, 11920 Bournfield Way, Silver Spring (added by deferring Montrose Center) 

$209,000 

  Grand Total  $1,150,261 

3.2.1.3 FuturePlanningAs there  is a growing convergence to a totally digital  learning environment  incorporating tele‐

classrooms,  self‐service  portals,  paperless  assignments/testing,  virtual  parent/teacher 

communications, and digital administration, the need for a scalable fiber network is paramount. 

According to the latest CIP, student enrollment projections are going to grow especially in areas 

where there are high concentrations of families without internet access at home. Even schools 

that  have  projections  of  lower  student  enrollments  will  still  need more  infrastructure  and 

broadband due to the increasing amount of bandwidth consumption for the ever‐evolving digital 

classroom. 

FiberNet Master Plan | Updated March 2018 

  

14  

 

During FY18, FiberNet proposes to undertake the following tasks to help meet MCPS’s growing 

needs: 

1. Work with Atlantech Online to create a 10 Gbps dense wavelength division multiplexing 

(DWDM)  link between MCPS’s data center,  located at 45 W. Gude, and  two points of 

presence within Atlantech Online’s network 

2. Continue work with MCPS staff  to convert all elementary schools  to 1 Gbps  links  into 

FiberNet 

3. Upgrade the connectivity  into the MCPS data center to multiple, diverse 10 Gbps  links 

using multiplexed DWDM technology 

4. Approach Comcast to request more direct peering with FiberNet to deliver cable modem 

traffic into the data center 

3.2.1.4 BudgetaryConsiderationsIt was  FiberNet’s  understanding  that  all  future  new  school  funding would  include  the  total 

amount of  the network build  in MCPS’s CIP, based on  the 2006 understanding within  ITPCC. 

Currently, Wilson Wims Elementary School and the new Richard Montgomery Elementary School 

are the only remaining schools whose FiberNet connections are scheduled to be funded by the 

FiberNet CIP.  

3.2.2 MontgomeryCollege(MC)Montgomery College’s strategic plan  includes shifting existing  leased services from the private 

sector  to FiberNet. With demand  for bandwidth  rapidly  rising,  the  cost of  connectivity  could 

become a budgetary burden if MC is forced to continue to rely on private service providers.  

3.2.2.1 NeedsAssessmentLike most higher education institutions, MC is looking for broadband solutions that will enhance 

its  ability  to  provide  innovative  research  opportunities  and world‐class  educational  services. 

Meeting these needs requires more than a standard internet connection; specifically, MC seeks: 

A  robust  connection  between  its  campus  locations  to  improve  remote  instruction 

opportunities, facilitate the sharing of resources between MC’s various campus locations, 

and make local campuses more desirable for faculty and students. 

High‐capacity links between MC’s network and outside entities that will allow researchers 

to collaborate with faculty from nearby institutions, like the University of Maryland, on 

large data sets. 

FiberNet Master Plan | Updated March 2018 

  

15  

 

3.2.2.2 CurrentProjectStatusFiberNet is currently in the process of building a new fiber connection to MC’s King Street campus 

and has approved construction for three additional links to the following campus sites: Westfield 

South  Center  Campus,  Gaithersburg  Business  Training  Center,  and  MC’s  Central  Services 

Building’s (CT Building) redundant link. Upon completion of these links FiberNet will be able to 

provide MC with a logical topology that will provide redundancy to its main campus locations on 

par with  the  commercial  service  the  college  currently  receives.  As  FiberNet  builds  out  the 

network and more sites are added, FiberNet will deploy DWDM equipment to create the highly 

meshed topology MC requires. (DWDM networks can place dozens of discrete wavelengths of 

light  on  the  same  fiber  strand.  Each  of  these wavelengths  acts  as  a  separate,  high‐capacity 

network. Not only does DWDM  allow  capacity  to be  added  as needed, but  it  also  increases 

security.) 

3.2.2.3 FuturePlanningWith the continued support of FiberNet, MC is looking to launch additional initiatives over the 

next few years. For example, MC would like to add a diverse path between its network and MAX 

(Mid‐Atlantic  Crossroads,  the  University  of  Maryland’s  government  and  educational  fiber 

network). FiberNet had previously built a DWDM link between MC’s King Street data center and 

the MAX point‐of‐presence  at  the University  of Maryland. A  second  link  to MAX would  add 

redundancy to this critical connection. FiberNet will look for opportunities to build a redundant, 

diversely routed link to MAX for MC. Obtaining access to Maryland State fiber along the Purple 

Line would be an ideal way to achieve the desired connection, and ultraMontgomery continues 

to look for opportunities to achieve this. However, FiberNet will pursue other candidate routes 

to ensure the correct solution is provided to MC. 

In  2012, MC  and MCG  entered  into  a dark  fiber MOU  to  facilitate  allocation of  fiber within 

FiberNet  for  creation  of  a  MC  network  within  FiberNet.    The  implementation  of  DWDM 

technology  (i.e.,  similar  to  a  rainbow,  light  spectrum  is  split  into  separate wave  lengths  and 

frequencies to allow multiple and separate data streams to be transmitted through a single fiber 

strand) may allow a  separate MC network  to be operated using  shared  fiber.    If  the DWDM 

solution meets MC’s needs, the 2012 MC‐MCG dark fiber MOU may need to be updated after 

further consultation with MC  to  reflect provision of an MC Network using optical networking 

segmentation rather than physical fiber segmentation. 

MC would also like to add its site at Standish Place to the network.   

3.2.2.4 BudgetaryConsiderations$750,000  from MC was  transferred  into  the  FiberNet CIP  to  support  construction  related  to 

implementation  of  the  2012  dark  fiber MOU,  and  additional  funding  was  provided  by  the 

FiberNet Master Plan | Updated March 2018 

  

16  

 

FiberNet CIP.  Funding for current MC projects is allocated in the Montgomery College CIP.  No 

other additional funding allocation has been made for any of the new MC projects in the FiberNet 

CIP.  

3.2.3 Maryland–NationalParkandPlanningCommission(M–NCPPC)The  Maryland–National  Capital  Park  and  Planning  Commission  (M–NCPPC)  maintains  and 

administers 52,000 acres of 400+ parks across Montgomery and Prince George’s counties, and 

has  responsibility  for  land  use  planning.  In  addition  to  its  Central  Administrative  Services 

department (which encompasses the Office of the Chief  Information Officer),  Its departments 

include Montgomery County’s Department of Parks and M–NCPPC’s Planning Department and 

Planning Board.  

Montgomery Parks and Montgomery Planning were early embracers of FiberNet, with their three 

major  headquarters  buildings  (Planning–MRO,  Parks–Parkside,  and  Park  Police–Saddlebrook) 

utilizing FiberNet circuits  for many years. Over  the years, M–NCPPC has steadily  increased  its 

FiberNet integration with connectivity to a total of 21 facilities. 

The IT Strategic Plan for Parks and Planning includes an initiative to leverage FiberNet wherever 

possible to eliminate reliance upon commercial carriers in favor of FiberNet. The FiberNet NOC 

and  increases  in  FiberNet  staffing are  two efforts  that have ensured  FiberNet’s  viability as a 

primary internet connection supporting M–NCPPC. The new Wheaton headquarters building will 

consolidate  staff—bringing  together  operations  staff  from  the  Parks  department  and 

development  staff  from  the  Planning  department.  FiberNet  services  provided  to  the  new 

headquarters will be a FiberNet III connection and PON technology. 

3.2.3.1 NeedsAssessmentA unique characteristic of M–NCPPC that poses a challenge to fulling the agency’s needs is the 

geographical scope of the parks and facilities it manages. While M–NCPPC’s recreation centers, 

Park Police stations, and maintenance facilities are distributed similarly to MCPS or MC locations 

served by FiberNet, the parks themselves cover much more land, up to the very borders of the 

County.  Providing  such  lengthy  OSP  will  require  a  significant  capital  investment  that  may 

outweigh the potential cost avoidance as compared to buying leased services. 

Cost avoidance  is one of  the major needs of  the agency. As new  facilities are added, or  the 

broadband service contracts at existing facilities expire, M–NCPPC desires to connect those sites 

with FiberNet.  

Given that the agency has its own police force, public safety is another core function. Having the 

availability  to  connect  to  a  robust  broadband  network would  allow  the  police  to  effectively 

deploy fixed and mobile cameras. Moreover, M–NCPPC believes that the cost effectiveness of 

FiberNet Master Plan | Updated March 2018 

  

17  

 

FiberNet must include not only the initial cost of installation and cost avoidance, but the value of 

reliable service as well.  FiberNet, with the recent additional of a more robust NOC, is M–NCPPC’s 

preferred provider for reliable service.   

3.2.3.2 CurrentProjectStatusCurrently, there are 16 M–NCPPC sites in the pipeline to be connected under the FiberNet CIP 

from FY17 to FY20. Four of these sites, including Needwood Mansion, have been approved for 

funding and are scheduled to be built in CY18 and CY19. Network construction to Wheaton Ice 

Arena and Park Maintenance Yard has been completed and is waiting for M‐NCPPC to activate. 

The 12 remaining sites, currently scheduled for FY19 and FY20, have yet to be approved. Prior to 

approval,  there  is  a  need  for  further  analysis  to  determine  the  rationale  for  building  to  the 

identified sites. The analysis for site additions considers the agency’s needs and compares the 

overall benefit of the site addition – including more intangible benefits such as reliability, speed, 

and security – to the financial metrics of construction cost and other cost avoidance.   

Table 5: Pending M–NCPPC Projects Under the FiberNet CIP 

STATUS  SITE & BUDGET YEAR IN WHICH FUNDING WILL BE ALLOCATED  COST ESTIMATE 

(A)pproved  FY17 Total  $90,409 

Built  Wheaton Ice Arena, 11717 Orebaugh Ave, Wheaton  $39,040

Built Wheaton  Regional  Park  Maintenance  Yard,  12012  Kemp  Mill  Rd, Wheaton 

$51,369

  FY18 Total  $201,000 

A  Woodlawn Park Police Substation, 16501 Norwood Rd, Sandy Spring  $201,000 

  FY19 Total  $473,000 

  Meadowside Nature Center, 5100 Meadowside Lane, Rockville  $140,800 

A  Needwood Mansion, 6700 Needwood Rd, Rockville  $195,800 

  Pope Farm Nursery, 7400 Airpark Rd, Gaithersburg  $34,500 

  Waters House, 12535 Milestone Manor Lane, Germantown   $51,900 

  Woodlawn Manor, 16501 Norwood Rd, Sandy Spring  $25,000 

  Woodlawn Visitors Center, 16501 Norwood Rd, Sandy Spring  $25,000 

  FY20 Total  $1,974,900 

  Black Hill Headquarters, 20930 Lake Ridge Dr., Boyds   $500,000 

  Black Hill Northern Region Headquarters & Park Police Office, 14300 Black Hill Rd, Boyds 

$500,000 

  Brookside Nature Center, 1400 Glenallan Ave, Wheaton  $218,600 

  Little Bennett Campgrounds, 23705 Frederick Rd, Clarksburg  $310,200 

  Little Bennett Maintenance Yard, 23701 Frederick Rd, Clarksburg   $42,900 

  Martin Luther King MY, 1120 Jackson Rd, Silver Spring  $182,200 

  Olney Maintenance Yard, 19117 Willow Grove Rd, Olney  $221,000 

  Grand Total  $2,739,309 

FiberNet Master Plan | Updated March 2018 

  

18  

 

3.2.3.3 FuturePlanningThe M–NCPPC website states there are approximately 15 sites currently  in construction, with 

twice that number in the planning or design stages. In addition to avoiding costs by connecting 

existing sites to FiberNet, M–NCPPC would like to connect those new sites as they are completed. 

3.2.3.4 BudgetaryConsiderationsBeside leveraging FiberNet CIP funding, M–NCPPC obtains funding from federal and state grants, 

various bonds, and donations. M–NCPPC also obtained direct funding from the County’s Cable 

Fund to support its Wi‐Fi in the Parks Pilot, and will be seeking additional funding to expand this 

initiative (see Section 3.4).  

M–NCPPC has estimated that by migrating sites to FiberNet, it will save up to $200,000 annually 

in operating expenses (see Table 6).  

Table 6: M –NCPPC Estimated Savings by Migrating to FiberNet 

M–NCPPC Site   Estimated Savings 

Wheaton Regional Park  $20,000 

Black Hill Regional Park  $68,000 

Little Bennett Regional Park  $20,000 

Rock Creek Regional Park  $20,000 

Martin Luther King Jr. Recreational Park  $14,000 

Woodlawn Manor Cultural Park  $15,000 

Rockwood Manor Park  $3,000 

Waters House  $14,000 

Seneca Park  $3,000 

Olney Maintenance Yard  $7,000 

Pope Farm Nursery  $7,000 

Agricultural History Farm Park  $7,000 

Kengla House  $2,000 

 

Comparing Table 5 and Table 6, we find that construction costs to connect all but four sites total 

$1.7 million to $2.4 million—which, based on estimated savings per site, equates to a total cost 

recovery  period  of  8.7  to  12.2  years.    CIP A  represents  one  connection  at  a  location,  CIP  B 

represents all other connections at that location.  Separate buildings within a park site may be 

separated by a significant distance and thus require an additional FiberNet CIP project cost.  (Sites 

listed without cost estimates are new requests from M‐NCPPC provided during the information 

gathering phase of drafting this Master Plan.)  Additional intangible benefits of reliability, speed 

and security are more difficult to calculate and are not displayed below.  

FiberNet Master Plan | Updated March 2018 

  

19  

 

Table 7: Cost Recovery Period for Pending M–NCPPC Projects Under FiberNet CIP 

M–NCPPC Site  CIP A  

(one site) CIP B  

(at same site) Estimated Savings 

A/ Savings (Years) 

A+B/ Savings (Years) 

Wheaton Regional Park  $178,000 $113,500 $20,000 8.9  14.6

Black Hill Regional Park  $500,000 $500,000 $68,000 7.4  14.7

Little Bennett Regional Park  $310,200 $42,900 $20,000 15.5  17.7

Rock Creek Regional Park  $20,000  

Martin Luther King Jr. Recreational Park 

$182,200 $14,000 13.0  13.0

Woodlawn Manor Cultural Park  $201,000 $50,000 $15,000 13.4  16.7

Rockwood Manor Park  $51,900 $3,000 17.3  17.3

Waters House  $51,900 $14,000 3.7  3.7

Seneca Park  $3,000 0.0  0.0

Olney Maintenance Yard  $221,000 $7,000 31.6  31.6

Pope Farm Nursery  $34,500 $7,000 4.9  4.9

Agricultural History Farm Park  $7,000  

Kengla House  $2,000  

   $1,730,700 $706,400 $200,000 8.7  12.2

In the absence of other strategic objectives that could change the business case for an otherwise 

expensive build to a requested site, leasing transport services from a third party may be a cost‐

effective way  to  achieve  the  functionality of  a  FiberNet  fiber  connection, while  avoiding  the 

construction cost to extend FiberNet to the most expensive  locations.  Having FiberNet be the 

leasing agent may ensures that the leased connection works within FiberNet, and also extends 

FiberNet monitoring and services over the added infrastructure, thereby mediating the risks of 

using leased services.  Such solutions may be of benefit to multiple Participating Agencies.   

3.2.4 WashingtonSuburbanSanitaryCommission(WSSC) The WSSC’s  five‐year  IT strategic plan  (2013 to 2018)  includes gradually replacing  its aging  IT 

infrastructure,  scaling  to  meet  an  anticipated  increase  in  demand,  improving  operational 

efficiencies, reducing costs, and improving communications with stakeholders. Highlights of the 

plan include transitioning to distributed architectures, leveraging cloud infrastructure, investing 

in  IT security,  investing  in mobile  infrastructure  to equip staff with  real‐time  information and 

guidance, and developing analytical capabilities to integrate and harness large‐scale data. 

3.2.4.1 NeedsAssessmentAs WSCC updates its infrastructure to include more modern systems, distributed infrastructure, 

and cloud‐based services, the demand for bandwidth between sites and to the internet will likely 

increase. The resiliency and reliability of those network connections will also become increasingly 

important as more processes and services will rely on them. WSSC also plans to install customer 

FiberNet Master Plan | Updated March 2018 

  

20  

 

kiosks in County facilities. These kiosks may require special arrangements to connect back to the 

WSSC network via the existing network at these locations. The fiber network will need to support 

the following: 

Fast, secure, and reliable data transfer between locations. 

Fast and reliable access to internet‐ and cloud‐based services. 

Connections to remote kiosks. 

Monitoring of network performance and bandwidth utilization predict  future use and 

scalability. 

NOC monitoring of outages separate from user reported disruptions. 

3.2.4.2 CurrentProjectStatus Currently,  there  are  10 WSSC  sites  either  requested  or  in  the  construction  pipeline  to  be 

connected using successive FiberNet CIPs from FY17 to FY20. Three of these sites, including the 

Consolidated  Laboratory & West  Farm Depot  site,  have  been  approved  for  funding  and  are 

scheduled to be built in CY18 and CY19. A construction “notice to proceed” has been given on 

the FY17 depot sites. Two sites may be added for less than $20,000. The seven remaining sites, 

currently scheduled for funding  in FY19 and FY20, have yet to be approved. Prior to approval, 

there is a need for further analysis to determine the rationale for building to the identified sites. 

The analysis for site additions considers the agency’s needs and compares the overall benefit of 

the site addition to the cost of construction. 

Table 8: Pending WSSC Projects Under the FiberNet CIP 

STATUS  SITE & BUDGET YEAR IN WHICH FUNDING WILL BE ALLOCATED  COST ESTIMATE 

(A)pproved  FY17 Total  $108,600 

A  Gaithersburg Depot, 111 West Diamond Avenue, Gaithersburg   $53,600 

A  Lyttonsville Depot, 2501 Lyttonsville Road, Silver Spring   $55,000 

  FY18 Total  $329,000 

A Consolidated  Laboratory  &  West  Farm  Depot,  12245  Tech  Road,  Silver Spring 

$309,000 

  North Woodside Standpipe, 1945 Seminary Place, Silver Spring   $10,000 

  Shady Grove Standpipe, 8620 Pleasant Road, Gaithersburg  $10,000 

  FY20 Total  $1,438,000 

  Brighton Dam, 2 Brighton Dam Road, Brookeville   $512,000 

  Colesville Tank, 2201 Industrial Parkway, Silver Spring   $192,000 

  Damascus Elevated Tank, 9950 Damascus Boulevard, Damascus   $372,000 

  Damascus  Wastewater  Treatment  Plant,  23730  Log  House  Road, Gaithersburg 

$234,000 

  Falls Road Standpipe, 8505 Aqueduct Road, Potomac  $128,000 

  Grand Total  $1,875,600 

FiberNet Master Plan | Updated March 2018 

  

21  

 

3.2.4.3 FuturePlanningThe modernization of utility systems will bring with it increased reliance on network connectivity 

for  remote monitoring, control, and automation.  It may also broaden  the  scope of  sites  that 

require wired or wireless connectivity. WSSC may require services that rely on the physical and 

data‐level security, redundancy, and resiliency of diverse fiber paths, DWDM, and MPLS. WSSC 

may also benefit from wireless solutions to support  its  interest  in mobility and providing real‐

time information to staff.  

3.2.4.4 BudgetaryConsiderationsFiberNet’s relationship with WSSC needs to be examined in regard to the funding of new sites 

and projects for WSSC. Montgomery County and WSSC share a mutually beneficial relationship 

in which each provides  services  to  the other at no  cost. WSSC  is not a governmental entity, 

however, and is funded by rate payers. The County will need to determine on a case‐by‐case basis 

whether any additional services it provides should require financial participation from WSSC. 

3.2.5 HousingOpportunitiesCommission(HOC)According to HOC’s 2013 to 2017 strategic plan,7 its mission is to provide affordable housing and 

supportive housing services that enhance the  lives of  low‐ and moderate‐income families and 

individuals throughout the County. “To achieve this mission, HOC operates as a public housing 

agency, a housing finance agency and a housing developer.”8 

While the strategic plan does not specifically focus on information technology, it includes specific 

approaches to using IT to accomplish the agency’s goals and overall mission. 

3.2.5.1 NeedsAssessmentFiberNet can support the availability of online services for HOC’s residents (e.g., maintenance 

requests, online payment)  and enable Wi‐Fi  for  residents  and  staff.  Smart building design  is 

another opportunity to enrich the experience of HOC clients. As new projects are considered or 

properties  are  renovated,  smart  buildings  technologies,  supported  by  FiberNet,  promise 

increased efficiency by connecting systems to reduce operating costs.  

Realizing  that HOC  shares  constituents with MCPS  (i.e.,  students  and  their parents),  aligning 

housing goals with school goals could be mutually beneficial for both agencies. One project that 

could benefit HOC and MPCS is the concept of student lounges. Each HOC property could have a 

dedicated area where students would have free Wi‐Fi access to assist them in their studies and 

homework assignments. While students have access to quality broadband at school, they may 

                                                       7 “Strategic Plan: FY2013‐17,” HOC, http://www.hocmc.org/images/files/ResourceDocs/Strategic‐Plan‐Current.pdf  8 “About HOC: Mission Statement,” http://www.hocmc.org/about‐hoc/about‐us.html  

FiberNet Master Plan | Updated March 2018 

  

22  

 

not have the same level of access to broadband where they live.  In some HOC locations, staff is 

available to provide homework assistance.   

Similar broadband lounges could also benefit residents of HOC properties that have low student 

populations  or  are  completely  dedicated  to  senior  living. Making Wi‐Fi  broadband  lounges 

available to seniors could help them with access services such as Medicaid/Medicare enrollment, 

wellness check‐ins, and  family teleconferencing.  It may also enable more digital  inclusion and 

extra‐curricular STEM programs to be offered at HOC properties. 

Another need currently under consideration by HOC  IT  is disaster  recovery services. FiberNet 

provides  high‐speed  and  redundant  connections  at  the  Atlantech Online  data  center  for  all 

participating  agencies  (PA).  FiberNet  will  very  soon  provide  the  same  capability  to  the 

Montgomery College Tier‐Three Data Center  in Silver Spring. Either may be made available  if 

requested. HOC  could utilize  these  connections  to  reduce or  almost  eliminate  recurring  and 

expensive monthly charges for disaster recovery services. 

HOC could benefit from a formal and separate strategic IT plan. This would allow its internal goals 

and objectives to align with FiberNet. 

3.2.5.2 CurrentProjectStatusThere currently are no HOC sites in the pipeline to be built using FiberNet CIP funding from FY17 

to  FY20.  Three  administrative  headquarter  sites were  previously  connected  to  FiberNet  and 

FiberNet connections for 20 HOC sites were funded by the ARRA‐BTOP grant. Alexander House 

and  several other properties are  scheduled  to be  connected  to  the network via HOC‐funded 

projects.  

3.2.5.3 FuturePlanningFuture planning is a crucial area for FiberNet and HOC to align their priorities and objectives. One 

key factor in the success of such alignment is knowing when new HOC construction or renovation 

are upcoming. Commonly these endeavors take multiple years to plan, approve, and construct. 

In addition, knowing where FiberNet has additional  feeder  fiber expansion can allow HOC  to 

identify additional sites for which it might request FiberNet connections.  Conversely, if FiberNet 

is aware of future HOC site locations, FiberNet may be able to adjust feeder fiber expansion plans 

to support additional HOC FiberNet extensions. 

3.2.5.4 BudgetaryConsiderationsThe sites mentioned above are part of HOC‐funded projects directly contracted with the FiberNet 

outside‐plant contractor. Besides self‐sourcing, or receiving funds from FiberNet’s CIP, state or 

federal grants could be available to expand broadband access for residents of HOC’s initiatives. 

FiberNet Master Plan | Updated March 2018 

  

23  

 

FiberNet will recommend in the FY19 CIP funding to place open‐access Wi‐Fi student lounges in 

all of the HOC properties connected to FiberNet.  

3.2.6 MontgomeryCountyGovernment(MCG)andDepartmentofTechnology(DTS)Montgomery “County’s technology vision is to be a digital county – ready for today and prepared 

for tomorrow.”9 DTS’s strategic plan includes expanding the capacity and reach of its investment 

in broadband as well as a  focus on digital equity. The DTS mission  statement  is “to  leverage 

technology to facilitate the delivery of County government services  in a cost‐effective, timely, 

high‐quality, and secure manner.” Under this mission are goals that include: 

Increased use of web, cloud, and social media platforms (including video) 

Improved security, resiliency, and handling of sensitive (HIPAA and PCI DSS)10 data 

Improved functionality and availability of intranets 

Growing the gigabit economy, Internet of Things, and Smart City applications 

Expanding public Wi‐Fi 

Leveraging and supporting FiberNet 

3.2.6.1 NeedsAssessmentAs the County moves to more web‐based and cloud‐based services, a fast and reliable internet 

connection will become increasingly important to its ability to be productive and to be responsive 

to  its  constituents.  Similarly, WAN  connections  will  become  increasingly  critical  to  County 

operations. WAN services will need to support the technologies required to transmit sensitive 

data with policies in place to define FiberNet’s responsibility, if any, in HIPAA and PCI compliance. 

The fiber network will need to support:  

Fast, secure, and reliable data transfer between locations 

Fast and reliable access to internet‐ and cloud‐based services 

Secure, isolated networks to support PCI, HIPAA, and Smart County applications 

Monitoring of network performance and bandwidth utilization to predict future use and 

scalability 

                                                       9 “Technology Strategic Plan: 2016–2019,” https://www.montgomerycountymd.gov/dts/stratplan.html  10 HIPAA is the Health Insurance Portability and Accountability Act of 1996 and PCI DSS is the Payment Card Industry Data Security Standard.   

FiberNet Master Plan | Updated March 2018 

  

24  

 

NOC monitoring of outages separate from user‐reported disruptions. 

3.2.6.2 CurrentProjectStatusCurrently, there are 17 MCG sites in the pipeline to be funded with successive FiberNet CIPs from 

FY17  to  FY20.  Ross  Boddy  has  been  completed.  The  Good  Hope  site  is  currently  under 

construction and an additional 11 sites have been approved for funding and are scheduled to be 

built in CY18 and CY19. The four remaining sites (Clara Barton, Wheaton/Glenmont Outdoor Pool, 

Scotland, and Western County Outdoor Pool) have yet to be approved. See Table 9, below. 

Prior to approval, there is a need for further analysis to determine the rationale for building to 

the  identified sites. The analysis for site additions considers the agency’s needs and compares 

the overall benefit of the site addition to the cost of construction. 

Table 9: Pending MCG Projects Under the FiberNet CIP 

STATUS  SITE & BUDGET YEAR IN WHICH FUNDING WILL BE ALLOCATED  COST ESTIMATE 

(A)pproved  FY17 Total  $522,877

A  Aquatic Center, 5900 Executive Blvd. Rockville  $52,900 

Built  Betty Ann Krahnke Center, 14810 Broschart Rd, Gaithersburg  $49,677 

A  East County Rec, 3310 Gateshead Manor Way, Silver Spring, MD  $68,100 

A  East County Gov’t Center, 3300 Briggs Chaney Rd, Silver Spring, MD  $68,100

A  Gwendolyn Coffield Comm. Center, 2450 Lyttonsville Rd, Silver Spring  $70,000 

A  MLK Swim Center, 1201 Jackson Rd, Silver Spring  $142,900 

Built  Ross Boddy, 18529 Brooke Rd, Sandy Spring  ‐ 

A  Schweinhart Sr. Center, 1000 Forest Glen Rd, Silver Spring  $71,200 

  FY18 Total  $308,900 

Built  Good Hope, 14715 Good Hope Rd (using separate MCG CIP funds)  ‐ 

A  Jane Lawton Comm. Center (Leland), 4301 Willow Lane, Chevy Chase  $67,800 

A  Long Brch. Comm. Center, 8700 Piney Branch Rd, Silver Spring  $100,000 

  Olney Swim Center, 16601 Georgia Ave, Olney  $76,700 

A  Silver Spring Health Center, 8630 Fenton Street, 10th floor, Silver Spring  $64,400 

  FY19 Total  $330,700

  Clara Barton, 7425 MacArthur Blvd., Cabin John  $127,200 

A  Longwood Comm. Center, 19300 Georgia Ave, Brookeville  $122,600 

  Wheaton/Glenmont Outdoor Pool, 12601 Dalewood Dr, Wheaton  $80,900 

  FY20 Total  $611,500 

  Scotland, 7700 Scotland Dr., Potomac  $111,500 

  Western County Outdoor Pool, 20151 Fisher Ave, Poolesville  $500,000 

  Grand Total  $1,773,977 

FiberNet Master Plan | Updated March 2018 

  

25  

 

3.2.6.3 FuturePlanningAs the County moves forward with various new applications, FiberNet will need the flexibility to 

scale to meet demand for on‐site and cloud‐based services and for specialized networks to meet 

the functional and security needs of new applications. 

3.2.6.4 BudgetaryConsiderationsThe County’s “Technology Strategic Plan”11 notes the following approximate annual budgets:  

Government Operating Budget: $5 billion 

Government Capital Budget: $15 billion 

DTS Operating Budget: $45 million 

DTS Capital Budget: $120 million 

As  stated  previously,  FiberNet’s  annual  operating  budget  in  FY16  was  $3.5 million;  capital 

expenses were budgeted at $4.2 million. By comparison, the network offsets an estimated $33 

million per year  in monthly recurring telecommunications and network services costs that the 

County would otherwise have to spend  for comparable communications services. The County 

expects to continue to benefit from sharing 

assets  among  partner  agencies,  including 

the expanded use of FiberNet. The County 

also plans to seek alternate funding outside 

of  the  County  budget, which may  involve 

collaborative efforts.  

3.3 ultraMontgomery andBroadbandRoadmap

Beyond its directive to deliver and operate 

enterprise services and support interagency 

objectives,  FiberNet  is  poised  to  expand 

broadband  for  other  innovative  purposes. 

DTS,  the  County  Council,  and  the  County 

Executive  have  all  launched  initiatives  for 

broadband.  Coordination  of  strategies, 

alignment  of  priorities,  and  cross‐

stakeholder  collaboration  can  create 

synergies with a broadband deployment and network operation. 

                                                       11 “Technology Strategic Plan: 2016–2019.” 

FiberNet Master Plan | Updated March 2018 

  

26  

 

3.3.1 ultraMontgomeryAs part of the County Executive’s “Six Point Economic Plan,”12 ultraMontgomery was established 

to promote gigabit + (plus) speed networks across the County. Exploring and implementing public 

and private partnerships, it will drive carrier‐class ultra‐high speed broadband. Ultra‐high speed 

broadband can be the economic catalyst for many community innovations, including knowledge‐

based  job creation;  innovation centers  for biotech,  research, and cybersecurity;  test beds  for 

technological  advancement;  and  public‐private  partnerships  to  grow  open‐access  Wi‐Fi  for 

constituents. 

3.3.2 BroadbandRoadmapThe DTS Office of Broadband Programs,  in partnership with  ITPCC and with support  from the 

County Council, has developed a Broadband Roadmap. The major focus areas are to have a robust 

County network to enable ITPCC members to meet their missions, to attract and retain business 

and a skill workforce to create a future‐ready economy, and empower residents, businesses and 

non‐profits to participate in the digital economy.  

Additionally,  the  role of broadband  in economic development and  societal advancement has 

been  discussed  in  white  papers,  including  “Moving  Montgomery  Forward  with  Gigabit 

Networks.”13 

3.4 CurrentandFutureInitiativesRequiringFiberNetSupportYear  over  year,  the  demand  for  bandwidth  and Quality  of  Service  (QoS)  is  growing  beyond 

FiberNet  II’s ability to deliver at these performance  levels. Upgrading FiberNet at the physical 

layer (Section 4.6) and optical  layer (Section 4.8) are necessary enhancements given the many 

critical County  initiatives  that  FiberNet directly  supports.  Table 10  lists  the  approved County 

initiatives requiring FiberNet support, both current efforts and those planned over the next four 

fiscal years. 

Table 10: County Initiatives Requiring FiberNet Support 

Initiative   Agency  Description 

Montgomery College Private Network 

MC  FiberNet has recently commissioned a DWDM project to fully and redundantly mesh the four main MC sites: Germantown, Rockville, King Street, and CT Building. Other sites will be added as fiber is delivered to each location. (Westfield, Gaithersburg, Calhoun & Standish Place) 

                                                       12 http://www.montgomerycountymd.gov/ep/overview.html  13 http://councilmemberriemer.com/2016/05/progress‐report‐on‐broadband‐high‐speed‐digital‐networks.html  

FiberNet Master Plan | Updated March 2018 

  

27  

 

Initiative   Agency  Description 

Land Mobile Radio Deployment 

MCPD, MCG  MCPD will be implementing a Land Mobile Radio project with six of a possible 15 sites to go operational by 2019. All sites will be connected by a microwave network with strategic, redundant connections to FiberNet. Project details (e.g., the support required from FiberNet) have been developed, equipment has been procured, and changes to the FiberNet optical plant are in the CY17 construction pipeline.  

MCPS Connection to Recovery Point Services 

MCPS, RPS  FiberNet has recently commissioned a project to create a DWDM link between the W. Gude Data Center and Recovery Point Systems, in Germantown. The link will support MCPS’s disaster recovery procedures.  

 

School Switch Upgrades and FiberNet II Connection 

MCPS  Over the past two years FiberNet has funded the procurement of new switches for MCPS schools. These switches are all deployed. All high schools and middle schools are running at 1 Gig. The work continues to turn up the WAN speeds for all elementary schools. This will significantly increase the traffic on the FiberNet Core.  

Additionally, FiberNet recommends the new DWDM infrastructure be chosen as the early solution to aggregate K‐12 traffic over very high bandwidth links into the MCPS data center. 

DWDM   WSSC, MC, and MCG 

Multiple DWDM optical bypass projects. See the FiberNet service catalog for more information on DWDM (Section 4).  

Wheaton Redevelopment Project 

MCGOV, M–NCPPC 

FiberNet is working with the architectural design team to develop the IT specification for this 15‐story shared building that will be operated by M–NCPPC. This will be a major PON deployment on a scale similar to the Multi Agency Service Park. (see below) 

FiberNet Master Plan | Updated March 2018 

  

28  

 

Initiative   Agency  Description 

Wheaton Wi‐Fi Project 

MCGOV, Parking Authority 

This project will consist of providing free Wi‐Fi in the Wheaton triangle and near the Wheaton Metro stop to residents and visitors. FiberNet will need to increase fiber capacity in the area, design a wireless solution to provide adequate coverage, collaborate with WMATA, and explore further expansion along the Wheaton corridor. $50,000 in funding has been provided for this Wi‐Fi project in the Wheaton Redevelopment Project CIP. 

Multi‐Agency Service Park (MASP) 

MCPS, MCGOV & M–NCPPC 

FiberNet staff recently completed all aspects of the MASP project creating facilities for all three agencies in a modern service park. Services include WAN and LAN connectivity over PON. (See the FiberNet service catalog for more information on PON). 

FiberNet has recently commissioned work to multi‐home the MASP to a diversely routed second FiberNet hub. This action will significantly improve the availability of services to this very important service park. 

Park Wi‐Fi  M–NCPPC  Design and deploy open‐access Wi‐Fi networks at 13 selected parks as an amenity for park visitors and to promote public safety. The network will be designed to support wireless camera connectivity.  

M–NCPPC Data Center Migration 

M–NCPPC and MCGOV 

This fall (CY17), MC and M–NCPPC have agreed that M–NCPPC will relocate its enterprise data center into MC’s King Street Data Center (KSDC). FiberNet will build a 10 Gig DWDM pipe between the MRO and KSDC to support this migration. This is a very important tactical move for M–NCPPC because it will provide network redundancy during the Wheaton Headquarters relocation.  

Public Wi‐Fi in Government Buildings 

MCGOV  This project would involve FiberNet supporting public Wi‐Fi at approximately 50 targeted user sites (175 indoor WAPs, 13 outdoor WAPs). The sites include recreation, innovation and health centers, and County government sites. The estimated budget for this deployment is $1,250,000. 

FiberNet Master Plan | Updated March 2018 

  

29  

 

Initiative   Agency  Description 

IP/TV over FiberNet 

MCGOV & RCN  An element in the recently signed RCN Cable Franchise obligates the company to provide IP delivered CATV into FiberNet for delivery to the Participating Agencies. The estimated cost to delivery this service is $500,000. 

 

Table 11: UltraMontgomery Initiatives Requiring FiberNet Support 

Initiative   Agency  Description 

East County Fiber Highway 

ultraMontgomery This project is to build a new fiber route along US 29 from Hub J in White Oak to ICBN fiber in Howard County at Scaggsville Road. This connection will give FiberNet a diverse connection to the ICBN network (connecting central Maryland counties and cities) and provide the County access to the Johns Hopkins Applied Physics Lab (APL), the TierPoint Data Center in Baltimore, and fiber at the Pennsylvania border. The fiber build will also support public–private partnerships, fiber/conduit networks for business, and economic growth along the US 29 corridor at targeted areas such as Viva White Oak and Burtonsville Crossing. This route also can be leveraged to connect to WSSC, support Wi‐Fi and operations on Bus Rapid Transit along US 29, support IoT testbeds, and connect FTS's planned Ashburn route cable along MD 200 to the ByteGrid data center. The estimated fiber route distance for this project is 49,579 feet. It will utilize existing FiberNet infrastructure and joint build opportunities to reduce the overall build cost. 

White Oak Science Gateway Conduit 

ultraMontgomery This project involves coordinating with County DOT to identify areas in the Viva White Oak corridor where road widenings will occur so additional conduit can be placed for future FiberNet needs. The conduit placed under this project could be leveraged for future builds to user sites as well as P3 opportunities. The revised preliminary estimate for this project ranges from $682,000 to $1.35 million.  Discussions are underway to determine whether to expand the conduit network to other planned White Oak developments. 

FiberNet Master Plan | Updated March 2018 

  

30  

 

Initiative   Agency  Description 

Interconnection with Fiber Routes to the Equinix Data Center  

ultraMontgomery This project proposes to connect data centers in the County to the Equinix data center in Ashburn, VA. This project plans to connect Atlantech Online’s data center in Rockville and to USA Fiber’s Ashburn VA data center connections by leveraging County fiber.  

Great Seneca Science Corridor 

ultraMontgomery The Great Seneca Science Corridor project proposes a FiberNet connection from NIST to Darnestown Road, where FTS Fiber has a connection to the Equinix data center in Ashburn, Virginia. 

Purple Line Fiber 

 

ultraMontgomery This project potentially provides a fiber swap with the Maryland DOT and/or the Dept. of Information Technology’s networkMaryland. The County would obtain access to strands of the State’s fiber along the Purple Line route in exchange for a connection to the University of Maryland. In return, the County would provide strands on Democracy Blvd. between I‐270 and Old Georgetown Road. 

Bus Rapid Transit   ultraMontgomery This project plans to support DOT’s free Wi‐Fi access on transit to support video streaming to public transportation users along the Bus Rapid Transit corridors. The initial pilot will be along US 29 and will leverage the East County Fiber Highway and existing FiberNet cable to provide Wi‐Fi service from Burtonsville to Silver Spring. Additional routes under consideration are Rockville Pike from Clarksburg to Bethesda, and Veirs Mill from Wheaton to Rockville. Project timeline will depend on DOT’s completion of the infrastructure upgrades for the Bus Rapid Transit lanes and the performance of DOT’s Wi‐Fi pilots. 

Fiber connection to DC‐Net 

ultraMontgomery This project proposes to connect FiberNet with Washington, D.C. government’s network (DC‐Net) via a peering point at MC's Takoma Campus Data Center. DC‐Net would like to provide lit services over FiberNet to many federal buildings located in Montgomery County, starting with two buildings in Silver Spring.  

 

FiberNet Master Plan | Updated March 2018 

  

31  

 

4 FiberNetOperations

4.1 SummaryofPriorMasterPlansThe first FiberNet Master Plan was published in March 1995, as part of the creation of FiberNet. 

The Master Plan included the justification of creating a countywide fiber network, the purpose 

FiberNet would serve for each participating agency, the creation of a committee for governance, 

and interoperability with other state and regional systems.  

The  1995  Master  Plan  presented  many  cost  justifications  for  the  County’s  operation  and 

consolidation of its telecommunications networks. For example, FiberNet replaced G‐Net, a 30‐

mile, open‐access, coaxial cable PEG network that was formerly part of the cable system; that 

network had become technologically obsolete.  

The  1995  FiberNet  network  design  incorporated  synchronous  optical  network  (SONET)  and 

asynchronous transfer mode (ATM) technologies. The original backbone from hub to hub was 48‐

count  fiber,  solely  for  the  purpose  of  hub  connectivity  (not  to  feed  sites).  The  feeder  fiber 

connecting the end‐user sites to the closest hub was designed as 24‐count fiber. The 1995 Master 

Plan  also  recommended  that  the  participating  agencies  share  the  cost  of  additional  capital 

improvement budgets.  

The 1995 Master Plan estimated that the network would encompass a total of 550 miles, but it 

now includes 665 route miles of plant. Despite that increased size, however, FiberNet’s annual 

operations and maintenance budget (currently $1.4 million) aligns with the 1995 Master Plan’s 

estimate of $1.3 million. 

The second Master Plan was published in April 2002. Objectives and topics covered in that report 

included: identifying current agencies’ uses of FiberNet, itemizing the costs per site per agency 

for  a  comprehensive  network  buildout,  assessing  agencies’  needs  and  strategic  visions, 

highlighting  priorities,  communicating  risks  (such  as  delays),  and  reviewing  the  then‐current 

broadband  industry. Each agency was evaluated and categorized based on bandwidth use and 

anticipated needs.  

The  Interagency  Technology  Policy  and  Coordination  Committee  (ITPCC) was  created  by  the 

County Council in 1984 and its policy coordination role expanded by Council in 1994.  The 2002 

Master Plan recommended the creation of an ITPCC technical subcommittee that would schedule 

and  communicate operational  functions of  the network  for each participating  ITPCC  agency. 

Currently,  the  technical  subcommittee  acts  as  the  active  change  control  board  for  service‐

impacting maintenance events. 

FiberNet Master Plan | Updated March 2018 

  

32  

 

Another notable recommendation of the 2002 Master Plan was to have interagency memoranda 

of  understanding  (MOU)—such  as  the MOU  that  FiberNet  subsequently  entered  into  with 

Montgomery College—and service‐level agreements (SLA) to ensure effective sharing of funding 

to  support  FiberNet  deployments.  The  2002 Master  Plan  also  recommended  that  FiberNet 

implement  chargebacks  to  support  future  expansions  related  to  specific  agencies.  The 

chargeback concept was implemented for a few years, but subsequently replaced.  Instead of the 

County  providing  additional  funding  to  each  Agency  and  each  Agency  contributing  back  to 

FiberNet, the County calculates a per site annual chargeback to fund future upgrades.  The FY18 

County Council‐approved  operating  budget  for Montgomery County Government  at  Item  39 

states that the FiberNet chargeback requirement of the County Government is estimated to be 

$5,180,600. 

The 2002 FiberNet Master Plan also recommended that the policy group explore the privatization 

of the FiberNet network and/or cable plant. This concept was analyzed in an Organizational Study 

(see below), and the recommendation to continue to operate FiberNet as a fully County‐operated 

network with a high level of service was accepted by ITPCC. 

The 2002 report also stated  that 39 of 124 elementary schools would be connected by FY05. 

Currently all but two elementary schools are connected with FiberNet service. 

4.2 FiberNetOrganizationalStudyTo  assess  the  current  organization  and  how well  it  addresses  FiberNet’s  core  directives,  an 

organizational study was prepared in November 2016. The 2017 FiberNet Organizational Study 

was distributed to the ITPCC CIOs in February 2017. 

This Master Plan incorporates key findings and analysis from the Organizational Study that are 

relevant to strategic planning of FiberNet. The Organizational Study covered a variety of topics, 

including  key  considerations  for  ensuring  FiberNet’s  continual  high  performance,  FiberNet’s 

recent reorganization in the Office of Broadband Programs (within the Department of Technology 

Services or “DTS”), case  studies of  similar networks,  recommendations  regarding maintaining 

FiberNet within DTS  and/or  the County,  and  the planned evolution  to  an upgraded network 

architecture (FiberNet III).  

4.2.1 GovernanceThe Organizational Study made several recommendations regarding governance of FiberNet. In 

terms of  the organizational  form  itself,  the study  recommended  that FiberNet should  remain 

within DTS under an Office of Broadband Programs, but with a number of stipulations to ensure 

better  alignment  to  ITPCC  objectives,  better  transparency  of  financial  data,  and  better 

management of joint resources from DTS and DOT.  

FiberNet Master Plan | Updated March 2018 

  

33  

 

The study made the following recommendations to enable FiberNet’s management and ITPCC to 

make strategically informed choices regarding the organization of staffing, in‐ vs out‐sourcing of 

required services, and efficiencies: 

Adopt enterprise accounting 

Provide better transparency and tracking of resources against allocated funds 

Develop  templates  for  financial  reporting  to  ITPCC  as  well  as  sample  financial  Key 

Performance Indicators (KPIs) 

The study recommended that enterprise accounting would be best accomplished with a non‐

discretionary account (NDA).  In addition to the stated goal  in the study of  insulating FiberNet 

from DTS  budget  and  hiring  restrictions,  an NDA would  also  facilitate  resource  tracking  and 

financial reporting efforts, and make it easier to generate the data for the KPIs (see Section 4.5). 

Additional sample metrics should incorporate allocation of the time spent on FiberNet by shared 

resources  within  DOT  and  DTS,  broken  down  by  project  and/or  funding  area  (e.g.,  capital 

improvements, maintenance and operations).  

The following initiatives will support these efforts: 

Work with the County Office of Management and Budget (OMB) to develop roadmap for 

migrating FiberNet to an NDA; if an NDA is not feasible, an enterprise accounting system 

can be developed with an as‐if‐NDA approach 

Develop financial categories—some of which track against funding source—for reporting  

o The categories should be able to disaggregate contracts, spending, and resource 

times against capital improvement/expansion vs maintenance and operations 

o The  categories  should  be  broad  enough  to  allow  outsourced  contracts  to  be 

comparable to in‐sourced staff time to facilitate sourcing decisions, and to allow 

FiberNet to identify where augmentation contract vehicles may be desired 

Analyze  and  disaggregate  current  contracts  and  purchase  orders  (POs)  against  these 

categories;  if  a master  contract  vehicle  includes both  activation/construction  services 

associated  with  capital  improvement  and  routine  and/or  emergency  maintenance 

services, these should be reorganized so invoices and costs are clearly apportioned to the 

specific bucket of costs in each category 

Analyze timesheets to enable similar disaggregation and tracking of resource time 

FiberNet Master Plan | Updated March 2018 

  

34  

 

Develop and add project‐specific sub‐categorization to contracted and in‐house detailed 

reporting so costs can be tracked by project; FiberNet projects specifically identified by 

ITPCC as supporting particular strategic objectives should, to the extent possible, adopt 

naming that reflects such objectives 

Develop coordination between DOT and FiberNet at the management level to incorporate 

supervision  and  FiberNet‐related  job  evaluation metrics  into DOT’s  formal  evaluation 

process for shared resources 

Develop  proposed  financial  reporting  templates/dashboard—also  known  as  key 

performance  indicators,  or  KPI—that  could  serve  as  a  starting  point  for  ITPCC, 

Department of General Services (DGS), DTS, and DOT feedback 

At the level of executive oversight and governance, the study also recommended that the ITPCC 

Charter  and  the  Change  Control  Board  Charter  be  updated  to  clarify  oversight  and  board 

responsibilities, and to update it to reflect current technology and services.  

While the need  for  further development and updates of the SLA  is covered  in other sections, 

template MOUs  and  SLAs may  need  further  development  if  FiberNet  participates  in  leasing 

arrangement with the private sector. Such efforts will require corresponding financial reporting 

and categorization, and formalization of agreements with DOT and refinements in underpinning 

contracts with outsourced vendors to meet the SLA terms. 

FiberNet has created a workplan for addressing the KPI issue (see Table 12). 

4.2.2 RecommendationsIn addition to recommending an appropriate governance model, the report highlighted specific 

strategic  recommendations  broadly  defined  by  the  following  areas  of  interest: Architecture, 

Budget & Financial Stability, Operations, Organization and Governance, Reporting, and Service 

Quality and Financial Transparency. The ITPCC intends that future editions of the Master Plan will 

explore  these  recommendations  and  that  the  recommendations  be  addressed  in  a  phased 

approach that would be conducive to steady and incremental changes in the network. 

Recommendations explored in the 2017 Master Plan include the following: 

• Operations (Section 4) 

o Develop a formal service catalog  

• Key Performance Indicators (KPIs) and Reporting (Section 4.5) 

o Review available department tools for efficiencies relating to outside plant (OSP) 

project management and reporting 

FiberNet Master Plan | Updated March 2018 

  

35  

 

o Evaluate the effectiveness of tools used for OSP projects and explore alternative 

management tools 

o Explore project management templates for O&M and CIP projects  

• Architecture 

o FiberNet  III – explore  the  step  for an  incremental approach  for modernization 

(Section 4.8) 

Additional issues identified in the Organizational Study will be explored in future updates to the 

Master Plan. These include the following topics and recommendations: 

Specify and acquire resource management tools 

Evaluate new approaches to fiber installation 

Evaluate PM methodology and contracts management 

Develop  agreement  and  coordination  process  with  DOT  for  effective  resource 

management and evaluation 

Develop cost estimation and reporting tools and standardized business processes for fiber 

builds 

Identify areas of training/professional development for FiberNet staff (DTS and DOT)  

Disentanglement of assets in hub sites 

Develop  templates  (MOU and  cost  structure) and business processes  for partnerships 

with third parties, including DC‐Net 

Develop RFP/requirements documents to separate and manage maintenance, repair, and 

OSP engineering tasks 

Conduct business case analysis and cost alternatives for fiber locating services (internal 

and outsourcing models) 

4.3 DTSOrganizationalRealignmentThe Department of Technology Services (DTS) was reorganized to create an Office of Broadband 

Programs  and  a  Broadband  Program  Executive  position.  The  reorganization  was  based  on 

broadband responsibilities pertaining to current activities and future anticipated needs.  

An  interim  reorganization  took place on  July  1,  2016  (see  Figure  5).  The  reorganization was 

approved with the adoption of the FY18 budget. Along with revising and consolidating functional 

responsibilities,  new  positions  were  created  to  focus  responsibilities  and  directions.  The 

Broadband  Program  Executive  and  FiberNet  Architect  positions  were  designed  to  enable 

FiberNet Master Plan | Updated March 2018 

  

36  

 

FiberNet  to  consistently  perform  at  the  highest  levels  of  service;  the  Broadband  Program 

Executive position  is designed  to create a single point of accountability over all FiberNet and 

broadband activities.  

Following that  interim realignment, DTS conducted an Organizational Study (see Section 4) to 

determine how FiberNet’s  functions should be organized  to best serve  the County and  ITPCC 

members, including whether it should remain in DTS or the County, operated as a consortium, or 

outsourced  to  be  operated  by  a  commercial  entity.  The  FiberNet Organizational  Study was 

published in February 2017. 

Figure 5: Broadband Realignment Organizational Chart 

 

4.4 FiberNet—CurrentStaffingLevelsFiberNet needs sufficient staff, both to respond to immediate user requests and to adequately 

plan and address medium‐ and long‐term needs. In recent years, FiberNet has operated with a 

core  of  qualified  staff  that  is  able  to  respond  to  emergency  requests  and  provide  basic 

connectivity, but may have difficulty, due  to workload and  time constraints,  in  responding  to 

requests to add sites, upgrade speeds, and serve new needs. FiberNet has recently added staff 

FiberNet Master Plan | Updated March 2018 

  

37  

 

for the network operations center (NOC) to partially address staffing challenges; it is also in the 

process of hiring a NOC supervisor. Other staffing additions are in process. 

It is also critical that the network be able to stay current with technology and expertise in order 

to keep pace with the increasing needs of FiberNet users, and to protect those users from risks, 

including network failures and security breaches. Therefore, having more staff than the minimum 

needed to handle baseline and emergency requirements is not simply convenient, but a proven 

concept.  

4.5 KeyPerformanceIndicatorsKey performance indicators (KPI) capture the essentials of a key process. When done right, a good 

KPI  tells  you  something  essential  about  the  value  your  enterprise  is  delivering,  establishes 

whether the enterprise is providing the service that the users need, and identifies areas that may 

need improvement. FiberNet’s KPI workplan is shown in Table 12 below. 

4.5.1 GuidelinesforEstablishingKPIsUnlike  other  performance  indicators  and metrics,  KPIs  are  oriented  toward managers  and 

executives to allow them to act, to ask questions, to improve. Some KPIs are straightforward, and 

common to most enterprises, like budget variance and on‐time completion of projects. Others 

are unique to the enterprise. All, however, flow from strategic objectives and goals.  

As an example, a modernization project  to upgrade hub sites with new equipment  to enable 

FiberNet to provision Layer 214 services to all customers by the end of a fiscal cycle has a well‐

defined goal for which a clear completion and acceptance test can be defined. Thus, performance 

indicators to track progress are easy to define (e.g., percent of sites completed, percent of site 

upgrade milestones completed on time). These become key performance indicators only if they 

are strategically important—if they enable efficiencies that are important to stakeholders, or new 

services, or revenue, or if they present a large expenditure (and therefore risk). They must also 

have well‐defined business processes: it is not possible to track progress or intervene to mitigate 

risks to ensure success unless it is very clear what the process is supposed to look like and when 

it is at risk and why. 

KPIs can be developed at management level but must reflect strategic concerns by stakeholders. 

They  are  essential  for  allowing  learning  and  improvements  in  FiberNet,  for  defining  what 

“success”  looks  like, and for prioritizing efforts where  impact  is most  important.  If done right, 

they create their own drives for improving processes and refining the ability to isolate risks and 

                                                       14 FiberNet is beginning to offer Layer 2 services by using DWDM.  Layer 2 will allow point‐to‐point connectivity between data centers.    

FiberNet Master Plan | Updated March 2018 

  

38  

 

mitigate them, and they promote a shared view among all stakeholders rather than conflicting 

definitions of what matters due to differing roles, affiliations, skill sets, and experience. 

On the capital improvement side, KPIs generally vary more based on project and initiative and 

the specific objectives intended. But FiberNet also operates as a service provider, so in the end, 

FiberNet is judged by how well it delivers its telecommunications services. Thus, some KPIs such 

as  uptime  are  relatively  straightforward.  Others  may  require  maturity  and  better  defined 

business processes.  

For example, to deliver faster intervention and systematically prioritize critical links and public 

safety, differing SLAs need to be defined; tracking based on those sites/links and SLAs will be 

essential. Otherwise, being able to report 99.999 percent uptime for all sites without differing 

SLAs might mask a failure to meet the service requirements for a significant site, while achieving 

100% compliance with many less significant ones.   

The table below illustrates the anticipated process for establishing KPIs. 

Table 12: Anticipated Process for Establishing KPIs 

No.  Milestone  Involvement/ Resources 

Target Completion 

Status 

1  Identify candidate KPIs  CTC/DTS 10/6/2017  Completed

2 Kickoff with ITPCC CIOs 

ITPCC CIOs, Principals, DTS

10/2/2017  Completed 

3  Identify candidate KPIs with FiberNet Architect

FiberNet Architect  10/17/2017  Completed 

4  Prepare White Paper / KPI analysis for CCB 

FiberNet Architect  3/14/2018  Close to Completion 

5  Implement Pilot Database  FiberNet Architect 12/15/2017  Completed

6  Facilitate KPI Working group brainstorming session 

CCB  3/28/2018  Not Started 

Identify resources/sources of data for KPIs 

CTC/DTS for FiberNet related data, individual agencies for any agency‐specific data

4/15/2018  In Progress 

8  Score KPIs on maturity  CTC 5/15/2018  In Progress

9  Select high priority KPIs for inclusion in dashboard 

CTC, CCB  5/25/2018  Not Started 

10 Identify County KPI platforms 

CTC, DTS (CountyStat, Tivoli, Netcool, PowerBI, Excel)

5/20/2018  In Progress 

11  Evaluate suitability of solutions for KPI dashboard 

CTC, DTS, Vendor support

6/1/2018  Not Started 

FiberNet Master Plan | Updated March 2018 

  

39  

 

No.  Milestone  Involvement/ Resources 

Target Completion 

Status 

12  Map KPIs against Business Processes 

CTC, DTS  6/15/2018  In Progress 

13  Implement select KPIs for pilot  DTS 6/1/2018 In Progress

14  Feedback/Validate with CCB  CCB 6/10/2018  Not Started

15  Implement remaining selected KPIs 

CTC, DTS  6/20/2018  Not Started 

16  Feedback from CCB and rest of ITPCC 

CCB, ITPCC CIOs, Principals

7/1/2018  Not Started 

17  Implement feedback changes to dashboard 

CTC, DTS  7/10/2018  Not Started 

18  Document generic business processes 

CTC  7/10/2018  Not Started 

19  Develop ConOps for KPI management and dashboard solution 

CTC, DTS  6/10/2018  Not Started 

20 Migrate Platform to County 

CTC, Architect, NOC Manager

7/15/2018  Not Started 

21  Generate KPI catalog  CTC 7/1/2018 Not Started

22  Generate Solution Presentation and Training Presentation 

CTC  7/31/2018  Not Started 

 

4.5.2 ClassificationofProjectStatusDetermining project status is a fundamental principle in any project environment. Knowing the 

status of any individual tasks allows the owner of the task to determine priorities and resource 

planning to complete the task. Additionally, other interested and responsible stakeholders can 

have knowledge of the tasks that need to be completed that influence or affect their responsible 

tasks.  Without  clear  and  structured  status  categories,  effective  reporting  cannot  be 

accomplished. Furthermore,  it  is essential to have accurate and consistent status  indicators to 

apply to reports, and also dashboards, for project sponsor awareness. 

Currently FiberNet status and project coordination is conducted via a biweekly meeting by the 

individuals  responsible  for  completing  that  tasks. While  the  in‐person meeting  is  extremely 

valuable  and  promotes  collaboration,  it  is  not  an  entirely  effective  tool  for  reporting  and 

recording historical  timelines.  (Such  information  is very useful  for  future  forecasting and goal 

setting.) Along with the biweekly meeting, various  individual contributors supply spreadsheets 

as site‐specific status trackers to other stakeholders. Each of the spreadsheets that record status, 

notes, updates, and roadblocks have individual formats and structures that are not universally 

aligned with other spreadsheets.  In addition, after a project is completed, it is simply removed 

from the spreadsheet, and thus performance data is not retained. 

FiberNet Master Plan | Updated March 2018 

  

40  

 

FiberNet will apply a seven‐category status  indicator  to each user site,  initiative, or overbuild 

segment. This will be the first step toward aligning all individual contributors and stakeholders in 

tracking and managing their tasks. Table 13 below shows the seven distinct categories that will 

be used in all FiberNet documents that describe status.  

Table 13: FiberNet Status Indiciator Categories 

Status Indicator   Description 

0 – Candidate  The facility is a potential FiberNet site 

1 – Requested A participating Agency has requested that the location be placed on FiberNet 

2 – Approved to build  The location is budgeted in the CIP and approved to build 

3 – Permitting & make ready  Design, permitting and make ready has begun 

4 – Notice to Proceed  Construction may begin by OSP Contractor 

5 – Under construction  The site is under construction 

6 – Awaiting agencies  The site is waiting for the Agency to perform a task 

7 – On net  The site is on FiberNet and in production 

 

An Intrinsic value gained by universal categories or indicators for status of tasks is to ascertain 

how long the task takes to accomplish. Each task status will have a start and stop date. The start 

and stop dates will determine the duration of the task. It will be possible to use historical data of 

task duration to communicate and provide effective forecasting for participating agencies’ (PA) 

organizational uses. This information can be extremely useful to PAs in making network decisions 

regarding  issues such as new  technology deployments, add/move/change efforts, operational 

costs for telecommunications, and general network operations. 

4.5.3 ProjectManagementSystemsandMethodologiesA  formal  project  management  system  can  help  with  many  aspects  of  a  project,  including 

planning,  resource allocation, budgeting,  time management, and  reporting. There are a wide 

range of project management systems tailored to fit a variety of working styles, project types, 

and  organizational  structures.  They  range  in  complexity  from  simple  “to‐do  list”  systems  to 

detailed and formalized practices described over multiple volumes of literature. Such a complex 

and detailed system may not be necessary for an organization the size of FiberNet, but adopting 

an appropriate project management structure can provide great benefits.  

A traditional, and perhaps the simplest, project management methodology is to break a project 

into component tasks, create plans for each task, and place those tasks in sequence. This project 

breakdown  allows  for  a  detailed  view  of  a  complete  project.  Each  task  can  be  examined 

separately  to determine  the prerequisites  from previous  tasks,  the dependencies  required  to 

move on to the next task, the resources required for the task, and a time estimate for completion. 

FiberNet Master Plan | Updated March 2018 

  

41  

 

This allows  for more accurate estimates of  the  time, budget, and  resources  required  for  the 

project as a whole and can help identify potential road blocks, unrealized requirements, and the 

effects  that  one  task may  have  on  tasks  down  the  line.  This  is  called  the Waterfall method 

because  of  the  way  one  task  flows  into  the  next.  Waterfall  project  management  is 

straightforward, but may not be well suited for projects with tasks that should not be arranged 

sequentially or that have complex interdependencies.  

The  types  of  projects  undertaken within  FiberNet  are  unlikely  to  require  advanced  project 

management methodologies such as Agile that are adapted to quick development cycles with 

iterative prototypes that seek  input from varied user community. Instead, premium should be 

placed on interagency and inter‐department coordination at the design and planning stage, basic 

PM  literacy,  ability  to  use  the  basic  functions  of  Microsoft  Project,  and  the  practice  of 

understanding the processes required for completion, who is required for each task, etc. Are we 

on time? Do we have enough resources? Can we speed anything up or will that blow up other 

dependencies?  Such  questions  drive  the  metrics  that  give  FiberNet  the  KPIs  it  needs. 

Management needs to be able to ask questions regarding larger risks, competition for resources 

between projects and priorities, and other  larger  issues, but emphasis for most FiberNet staff 

should be more on  the basic methodology of  following  a project based  approach,  and work 

together to address obstacles to getting a project completed on time and budget. 

Regardless of the project management system in use, some project planning is required. A project 

plan will likely include the following steps:  

• Identify the project goal, which should include requirements for the project deliverable, 

scope, and restrictions 

• Break the project down into tasks 

• Identify task dependencies 

• Identify resources, such as staff and materials, that each task will require 

• Estimate time required for each task 

• Estimate costs for each task 

• Schedule  the  project  tasks,  which  will  require  balancing  time  estimates  and  time 

restrictions such as a deadline for the deliverables 

• Create a budget, which will require balancing estimated costs and cost restrictions such 

as an imposed maximum budget amount 

FiberNet Master Plan | Updated March 2018 

  

42  

 

During the execution of the project, a project manager should be prepared to track and enforce 

the project schedule and budget. This may require tracking time and expenses as the project 

progresses and collecting status updates or progress reports from the project team. This will help 

the  project  manager  to  identify  roadblocks,  delays,  or  unexpected  costs  in  time  to  make 

adjustments. These data can also be used to make more accurate estimate or adjust processes 

for future projects. 

4.5.4 ToolsforEvaluatingKPIsTool identification—looking within DTS at existing dashboard resources, considering CountyStat 

possibilities, and evaluating staff and software resources—will be an integral part of establishing 

KPIs for FiberNet. The degree to which a tool will be useful will depend on a range of factors, 

including: 

• Learning curve for FiberNet staff  

• Dependence on vendors or internal staff for using it 

• Ability to keep some KPIs internal and to limit access within the organization (not all KPIs 

should be public) 

• Costs, if any  

4.5.4.1 IBMTivoliNetcoolNetworkManagementThe County has access to the IBM Tivoli Netcool Network Management tool, which can help in 

tracking FiberNet’s conformance to KPIs such as “uptime” and “mean‐time‐to‐repair” to ensure 

that  the  network meets  its  goals.  The  tool  is  a  network monitoring  platform  that  identifies 

bottlenecks and other network  issues to enable faster resolution and help avoid outages. The 

issue management  functionality assigns  the  right  level of priority  for event  resolution.  It also 

helps reduce manual intervention by allowing for automated scripts against recurring problems. 

The tool has near real‐time and historical reporting capabilities to proactively measure data on 

network  availability  and  performance,  and  to  isolate  the  causes  of  network  downtime.  The 

platform also automates and streamlines network device configuration management.  

Another  indicator of performance,  the “number of  site activations done on  time,”  should be 

adopted in parallel using relevant project management tools. Once a site is activated, the IBM 

Tivoli Netcool solution can verify the network’s status and update network maps automatically 

without manual intervention. 

4.5.4.2 GISCostEstimationMultiple approaches can be taken to estimate fiber construction costs. Given the geographic and 

spatial context of  fiber construction,  the most effective method would harness GIS. The ESRI 

FiberNet Master Plan | Updated March 2018 

  

43  

 

Attribute Assistant  is available as a  free download as part of ArcGIS Solutions. The Attribute 

Assistant allows for rules to be applied on the fly in a dynamic environment. This means that after 

drawing  in  a  fiber  route,  the  predefined  rules  are  immediately  applied  to  the  route  in  the 

database—which in this case would produce a cost estimate. (See Figure 6.) 

Figure 6: High‐Level Fiber Routing for Cost Estimate 

 

The rules would consist of known construction costs that would apply in the different scenarios. 

The output produced would be a cost given the parameters; the output could be exported to 

Microsoft Excel. (See Figure 7.) 

Figure 7 : Output of Cost Estimation Tool 

 

Another part of the appeal of this product is its scalability. Rules are input via a dynamic value 

table. (See Figure 8.) In this case the dynamic value table calculates based on a fully burdened 

rate of $59 per foot, as can be seen in the “Value Info” field. The rules for when to apply particular 

costs can be adapted to find a balance of accuracy and initial data input required.  

FiberNet Master Plan | Updated March 2018 

  

44  

 

For instances, on the most basic level, a fully burdened rate could be applied to each distance 

drawn into GIS. This pricing would be a per foot cost that is averaged out to include everything 

from materials to labor. On the other end of the spectrum one could enter rules for all aspects 

of  construction  from  labor  to materials  such  as  traffic  control,  splicing,  and material  costs. 

Applying more  rules  requires more upfront  investment  in  time  spent  inputting  rules  into  the 

system—but, in turn, the estimator tool will be more closely aligned with the actual costs.  

Figure 8: Value Input 

 

There  are  some  limitations  to  this  approach.  Primarily,  the  individual  conducting  the  cost 

estimate will need to be familiar with GIS to design the routing. Setting up this tool requires a 

fairly high knowledge of GIS. Using  the  tool can be accomplished by  training a person who  is 

comfortable with computers, but not necessarily experienced with GIS. Another limiting factor is 

that this tool requires an ESRI ArcGIS for Desktop license—meaning that everyone using the tool 

would need a  license, or that a desktop would need to be set up to allow anyone wanting to 

estimate fiber construction costs to remote into a shared computer. 

4.5.4.3 ProjectManagement/CommunicationToolThere are several simple, cost‐effective project management and collaboration  tools  that can 

assist with  the  timely deployment and activation of new sites. For  instance, Smartsheet15 is a 

web‐based Software as a Service (SaaS) tool that can serve as a portal for the real‐time progress 

tracking of site activations. It can also be used to streamline communication and documentation. 

The tool offers a single interface with useful features such as Gantt charts, resource allocations, 

consolidation of comments and emails, document sharing, automated email reminders, and cost 

tracking. The tool also offers customized interfaces for construction or technology management. 

Figure 9 and Figure 10 below depict the user interface for this tool. 

                                                       15 https://www.smartsheet.com/landing‐b, accessed August 2017 

FiberNet Master Plan | Updated March 2018 

  

45  

 

Figure 9: Smartsheet Home Page 

 

 

Figure 10: Gantt Chart in Smartsheet 

 

 

FiberNet Master Plan | Updated March 2018 

  

46  

 

4.6 StatusofPhysicalInfrastructureRemediation,Upgrades,andAdditions

4.6.1 HubRemediationFiberNet  currently  has  12  hub  locations  throughout  the  County.  These  locations  provide 

aggregation points for the network’s user sites. Hubs are connected to each other via backbone 

cable and each hub connects with nearby user sites via feeder fiber (Section 4.6.2). Figure 11 

illustrates the general location of the FiberNet hubs and routes; Figure 12 is a logical diagram of 

the same. Note that Hub A will functionally eliminate Hub C by the first quarter of 2018, so Hub 

C not shown in Figure 11. 

Figure 11: FiberNet Map with Hubs 

 

FiberNet Master Plan | Updated March 2018 

  

47  

 

Figure 12: Logical Diagram of FiberNet Hubs and Backbone Cable 

Hub A

Hub C

Hub B

Hub D

Hub E Hub F

Hub G

Hub H

Hub I

Hub J

Hub K

Hub L

 

The  need  for  hub  remediation  became  evident  during  the  Inter‐County Broadband Network 

(ICBN) project. Funded through the American Recovery and Reinvestment Act of 2009, the ICBN 

added more than 100 user sites to the FiberNet network  in  less than two years—a substantial 

increase over the rate at which FiberNet had previously added sites to the network.  

ICBN increased the total number of sites on the network beyond the hub locations’ capacity to 

serve them. Because of ICBN’s inability to spend grant funds to expand the hub sites at that time 

(due to scope limits in the grant), FiberNet served the orphaned sites from the newly built Hub 

A, located at the EOB. This was always considered a temporary solution; the County planned to 

migrate the sites served at Hub A back to the originally planned hub locations after the capacity 

of those hubs was increased via the remediation work. These hub remediations would also give 

the County capacity at the hubs to add future user sites. 

Due to the amount of effort and coordination required, FiberNet planned to remediate the hub 

sites at a rate of approximately one hub per quarter. Priority for remediation was originally set 

to target hubs that were the furthest away from Hub A, and to work back toward Hub A over 

FiberNet Master Plan | Updated March 2018 

  

48  

 

time, to minimize disruption to the ICBN sites served out of Hub A. However, the schedule has 

been altered to account for circumstances beyond FiberNet’s control.  

Table 14 lists the completed and planned hub remediation efforts. 

Table 14: Hub Remediation Efforts (Completed and Planned) 

Network Hub Facility  Planned 

Completion Notes 

Hub J – White Oak  Complete  Completed Q3‐2014 

Hub I – Wheaton  Complete  Completed Q4‐2014 

Hub F – Silver Spring  Complete  Completed Q1‐2015 

Hub E – Bethesda  Complete   Completed Q2‐2015 

Hub B – Seven Locks  Complete   Completed Q3‐2015 

Hub G – Gaithersburg  Complete   Completed Q3‐2016 

Hub H – Crabbs Branch  Complete  Completed Q2‐2017 

Hub L – Quince Orchard  Complete  Completed Q4‐2017 

Hub A – Rockville (EOB)  Q1‐2018 May move up in the schedule if roadblocks delay other hubs 

Hub K – Norbeck   Q3‐2018  Park and Ride may be redeveloped 

Hub D – Executive Blvd.  Q1‐2019 Hub may be relocated depending on 

White Flint development  

 

Upon completion of the project, the County may compare the enhanced capacity of each hub to 

an  analysis  of  future  requirements  to  verify  that  the  project’s  goals were met  and  that  no 

additional capacity is needed. 

Additional  analysis  of  the  remediated  hub  sites,  to  assess whether  heating,  ventilation,  air 

conditioning (HVAC) and backup power upgrades are needed, could lead to the benefit of higher 

fortification. Hub H has already been remediated and could serve as a test bed for performance 

evaluation. For budgeting purposes, we note that upgrading HVAC and backup power can cost 

approximately $50,000 to $100,000 per hub location.  

FiberNet Master Plan | Updated March 2018 

  

49  

 

4.6.2 FeederFiberExpansionFeeder  fiber  in Montgomery County  is  cable  that  runs  from  the hub  sites  to user  sites, with 

laterals from a main feeder branching to  individual sites. As with the hub remediation, feeder 

fiber  expansion  is  necessary  due  to  the  ICBN  site  additions  and  other  potential  future  site 

additions. Figure 13 illustrates the FiberNet infrastructure and planned feeder fiber and user site 

expansions in a small portion of the County.  

Figure 13: Representative Map of Feeder Fiber Expansion and User Site Additions 

 

ICBN  only  funded  one‐third  of  the  needed  feeder  fiber  routes;  the  remainder  were  not 

constructed due to project budget constraints. FiberNet  is now  looking to build the remaining 

routes (Hubs G, I, J, and L) as part of its feeder fiber expansion. These feeder routes need to be 

built before the County can add user sites to those hub locations. 

FiberNet Master Plan | Updated March 2018 

  

50  

 

Figure 14 illustrates FiberNet’s original approach to constructing feeder fiber. 

Figure 14: Feeder Fiber – Original Build 

 

Figure 15 illustrates the current state (in which new service drops have been extended from the 

existing feeder fiber to connect new sites).  

Figure 15: Feeder Fiber – Expanded Build 

 

 

FiberNet Master Plan | Updated March 2018 

  

51  

 

Figure 16 illustrates the proposed future state of the feeder fiber, after the remediation efforts 

described here. 

Figure 16: Feeder Fiber – Remediated Build 

 

4.6.3 MaximizingtheValueofExistingInfrastructureIn addition  to hub and  feeder  fiber  remediation, practices  to maximize  the use of FiberNet’s 

existing infrastructure can reduce the cost of new construction. FiberNet already takes advantage 

of overlashing cable to existing aerial attachments and it is considering new technologies such as 

MaxCell innerduct or placing microduct in existing ducts to maximize the capacity of underground 

routes (see Figure 17).  

FiberNet Master Plan | Updated March 2018 

  

52  

 

Figure 17: Microduct Applications 

 

The benefits of  installing  these  technologies  include  creating multiple pathways  in  the  same 

footprint as a single‐pathway design (at a comparatively lower price than constructing additional 

conduit or fiber) and creating joint‐build opportunities.  

The microduct technology also has the benefit of enabling pulling and pushing fiber over a greater 

distance as compared to conventional conduit or roll duct.  (A recent trial  installation of a 48‐

count  fiber  in a microduct pathway  in Baltimore County exceeded 1,700  feet  for a single pull 

distance.)  

To provide additional capacity for future needs, the County is considering installing more strands 

(larger‐count cables) than it requires when it builds new fiber. The incremental cost of increasing 

cable size during  initial construction  is small  in comparison to the cost of overbuilding existing 

routes to add capacity. As depicted in Figure 17 above, four 288‐count microfiber cables could 

be installed in a typical four‐way microduct. FiberNet is exploring sections of the network that 

can be used as a test bed for this new infrastructure technique. 

2” HDPE SDR11 roll duct 

(with 216‐count fiber, 

armored) 

Two‐way HDPE 

microduct (with 

288‐count fiber, 

non‐armored) 

Four‐way HDPE 

microduct (no fiber) 

FiberNet Master Plan | Updated March 2018 

  

53  

 

4.6.4 DocumentationProcess—PhysicalLayerIn recent years, FiberNet has made significant progress  in documentation of  its physical cable 

infrastructure. It has electronically documented all network routes and most network attributes, 

and will complete the documentation in the coming months, once the FiberNet hub remediation 

is complete. 

The documentation will reap benefits in FiberNet’s ability to cost‐effectively plan and maintain 

the network. It will also improve FiberNet’s ability to collaborate with other network providers 

and  institutions,  both  in  the  planning  phase  and  in  operations.  A  reliable,  centralized,  and 

standardized mapping system provides transparent information to potential users and partners 

and also makes it easier to establish service level agreements, in which FiberNet commits to a 

particular level or reliability and performance. 

The digitization effort (Figure 18) required FiberNet to transfer paper documentation of both its 

physical routing and its fiber allocation data into fiber asset management software (OSPInSight) 

integrated  with  the  County’s  Geographical  Information  System  (GIS).  OSPInSight  captures 

important attributes of  the  fiber  such as  route, cable count,  fiber capacity,  fiber assignment, 

splicing,  and method  of  construction.  The  digital  conversion  was  done  at  a  desk  by  a  GIS 

technician, complemented by discussions with the FiberNet OSP staff. In general, the conversion 

was not field‐verified at the time of entry—relying instead on the accuracy of the paper mapping 

and the recollection of FiberNet staff.  

Figure 18: Physical Plant Digitization Process 

 

To date, 100 percent of the physical routing has been entered into OSPInSight. However, the fiber 

allocation information has only been entered for cables that terminate at hub locations where 

hub remediation has occurred (Section 4.6.1). Since fiber allocations in the hubs are changed as 

part of  the hub remediation work, FiberNet determined  that  the entering of  this data should 

occur after the remediation is complete to avoid having to input the data twice. 

FiberNet Master Plan | Updated March 2018 

  

54  

 

In the future, the County should consider documenting new routes after construction (Figure 19). 

Figure 19: Physical Plant Documentation Process 

 

The  conversion of physical  layer  records  to  an electronic  format has benefits beyond  simply 

creating a repository for data essential to operate the network. This data can be manipulated to 

create maps or data sets that can be  leveraged by County  leadership and staff outside of the 

FiberNet team. Some examples of what this data can be used for include working with private 

partners on dark fiber leasing and strategic planning to coordinate joint construction efforts for 

multiple County agencies. 

The County has already taken steps to make documentation more widely available. The updated 

OSPInSight data  is regularly  imported to a website containing an ultraMontgomery smart map 

where the data can be viewed by County employees and partners.  

FiberNet Master Plan | Updated March 2018 

  

55  

 

In order to keep up with best practices for network expansion and required network reliability, 

FiberNet will continue its focus on documentation of new fiber routes, as well as recording break‐

fix changes. Additionally, the following steps can enhance the current process: 

• Mobile Access – Adding the capability for authorized field personnel and FiberNet staff 

and  leadership to view  information  in the field and elsewhere using mobile devices so 

that accurate, real‐time  information  is available as needed and FiberNet can reduce  its 

reliance on paper map sets in vehicles. This capability is part of the development path of 

OSPInSight. 

• Audits  –  Performing  ongoing  quality  assurance  assessment  on  the  existing  data  by 

performing a full field verification over the course of the next few years 

• Planning Tool – Acquiring or developing an estimation tool that can quickly design and 

price potential network expansions in multiple scenarios (see Section 4.5.4.2) 

The  aforementioned  steps  are  being  considered  as  possible  enhancements.  Currently,  no 

budgets are allocated to develop the processes.  

4.7 FiberNetServiceDescriptionFiberNet is Montgomery County’s facilities‐based, edge‐to‐edge voice, video, and data Wide Area 

Network.  FiberNet  provides  the  communications  infrastructure  and  services  needed  to 

interconnect Montgomery County government agency telecommunications and data networking 

equipment.  FiberNet  includes  all  hardware,  software,  optical,  electro‐optical  and  support 

services purchased, contracted, and installed in support of its service infrastructure.  

Currently there are two full generations of FiberNet (I and II) running concurrently and a nascent 

successor network, FiberNet II.v (“two‐point‐five”). FiberNet I will be decommissioned by the end 

of 2019. Each iteration of FiberNet offers its own suite of service offerings and associated levels 

of support.  

4.7.1 FiberNetIServicesFiberNet I is a legacy network restricted to the delivery of TDM circuits for the Public Safety Radio 

System (PSRS). Edge sites deploy either an ATM Integrated Access Device (IAD) or a major ATM 

node chassis. At the request of the DTS Radio Shop, almost every circuit in FiberNet I is configured 

as a permanent virtual circuit (PVC). Therefore, FiberNet I protocol has no switching control with 

regard to the delivery of voice services for the PSRS. The PSRS TDM network is currently a hybrid 

cloud of carrier T1 services, microwave links and FiberNet I circuits. All circuit selection decisions 

are made within the PSRS cloud. FiberNet I will be decommissioned when the new PSRS backhaul 

network is commissioned in FY19. 

FiberNet Master Plan | Updated March 2018 

  

56  

 

4.7.1.1 TechnicalSpecifications

4.7.1.1.1 CoreNetworkFiberNet I’s core network is composed of GDC ATM switching equipment. The core network is an 

Asynchronous Transfer Mode (ATM) switching fabric operating at OC‐3 speeds in the core and at 

the  customer  edge.  The  core  backbone  is  implemented  over  a  partially meshed  backbone 

interconnecting twelve free‐standing hubs. Each individual hub connects over disparately routed 

links to at least three other hubs but for one hub connecting to only two hubs.  

4.7.1.1.2 EdgeNetworkATM‐delivered FiberNet edge sites may be connected by any of the following Ethernet standard 

encapsulations 10BaseT or Fast Ethernet. Though FiberNet I has the capability to attach sites with 

these encapsulations, in a peak load demand situation, FiberNet I is unable to deliver sustained 

cell rates of more than 3 megabits with its current infrastructure. This infrastructure will not be 

enhanced. Currently this service is restricted to the FiberNet I management plane. 

4.7.1.2 ServiceLevelSpecificationsThe DTS Radio Shop is currently the only remaining customer on FiberNet I. The radio shop works 

directly with  the  FiberNet NOC, which  provides  24x7  on‐call  support,  to  resolve  any  service 

issues. 

4.7.2 FiberNetIIServicesFiberNet  II provides WAN,  internet,  video,  and  telecommunications  services  for Participating 

Agency (PA) customers. FiberNet II has been engineered to support mission‐critical public safety 

applications,  eGovernment  with  internet  access  requirements  (i.e.,  using  IT  to  facilitate 

government functions), and routine daily services such as telephony, e‐mail, video, mainframe, 

client‐server, and file transfer applications.  

FiberNet II is a common‐carrier‐like IP network providing:  

• Transport and routing of data, voice and video content  

• Quality of Service marked packets for real time applications like VoIP 

• Internet connectivity  

• Connectivity to regional networks including; networkMaryland, NCRnet, and ICBN 

• PON solutions for campus and office building deployment 

• Network operations and control of all FiberNet backbone assets 

• PA assistance for all FiberNet services  

FiberNet Master Plan | Updated March 2018 

  

57  

 

4.7.2.1 TechnicalSpecifications

4.7.2.1.1 CoreNetworkFiberNet  II’s  core  network  is  based  on  Cisco  CAT65xx  technology.  This  generation  of  Cisco 

equipment has reached its “end‐of‐life” and is no longer available from Cisco. New purchases are 

sourced from the aftermarket and are certified by the seller for Cisco maintenance. Cisco will 

stop maintenance and  technical assistance center  (TAC) support  for  this  line of equipment  in 

October  2022.  The  core  network  implements  an MPLS/VPN  network  (Multi‐Protocol  Label 

Switching to create Virtual Private Networks) operating at 10 Gbps speeds in the core and with a 

variety of  site  specific  link  speeds  ranging  from 100 Mbps  to 10 Gbps. The  core backbone  is 

implemented over a partially meshed backbone of twelve hub nodes each of which implements 

three or more disparately routed links connecting neighboring hubs.  

4.7.2.1.2 EdgeNetworkFiberNet  II edge  sites may be  connected with either  a  Transition Media Converter or native 

optical GBIC.  In every  instance,  the device  connecting a  site  to  FiberNet  is either a  FiberNet 

Provider Edge  (PE)  switch or  a  FiberNet Customer Edge  (CE)  switch. Most  FiberNet  sites  are 

directly  connected  into  the  PA’s  CE  switch  over  an  Ethernet/IP  link.  Circuit  provisioning  is 

performed  on  a  site‐by‐site  basis  by  DTS’s  Network  Services  Team  using  VPN  Routing  and 

Forwarding  (VRF)  technology  to  provide  logical  separation  between  all  of  the  participating 

agencies.  

FiberNet II edge sites may be connected by any of the following Ethernet standard encapsulations 

10Base‐T, 100Base‐FX, 1000Base or 10GBase. Customer Edge layer 0 media are either copper or 

single mode fiber depending on the requirement. 

Including all sites regardless of transport technology, FiberNet II currently serves over 545 edge 

sites. Regardless of funding source, FiberNet expects to add 19 sites by end‐of CY18 and 20 more 

sites in CY19. 

4.7.2.1.3 PassiveOpticalNetworkFiberNet  II  is now capable of  implementing PON technology to extend fiber to the desktop or 

wireless  network  in  new  and  renovated  PA  buildings. Montgomery  County’s Department  of 

General  Services  and  Department  of  Technology  Services  have  adopted  PON  to  increase 

reliability and capacity and to reduce operational and maintenance costs.  

PON eliminates the end‐user switches connecting voice, video, data, and CATV devices to the 

core network. These switches are replaced with a single logical gateway (Optical Line Terminal; 

or OLT) connecting the user‐base to network resources located in the network’s core. The OLT 

talks downstream to an Optical Network Terminal (ONT) connecting the end‐point device using 

FiberNet Master Plan | Updated March 2018 

  

58  

 

a CAT 6 cable. On the upstream side, the OLT talks to a network core switch/router for access to 

applications and the  internet. It  is possible for the OLT to support devices up to 15 kilometers 

away.  

Essentially, PON enables any agency to “flatten” the network, remove intermediate equipment, 

support disparate  technologies, and  simplify network  support  for client devices over a  single 

structured cable plant operated from a “head‐end.”  

FiberNet has developed  the expertise  to  install PON on a  large scale as demonstrated by  the 

projects shown below. 

FiberNet II has successfully completed four PON deployment projects: 

1. Multi‐Agency Service Park  

In collaboration with the Department of General Services, FiberNet designed and installed 

a PON throughout the Multi‐Agency Service Park (MASP). MASP, a 132‐acre LEED Silver 

sustainable service park, is comprised of more than 30 free‐standing buildings, including 

six large facilities housing hundreds of County employees. The deployment consisted of a 

single PON infrastructure that supports staff from MCPS Food Service, the Public Safety 

Training Academy (Police and Fire), and MCPS and M–NCPPC maintenance depots. All IT 

services  originate  in  a  single  20x20  free‐standing  headend  centrally  located  on  the 

property. 

2. 1401 Rockville Pike 

With funding from the Real Estate Office in the Department of General Services, FiberNet 

built  the  Information  and Communications  infrastructure  supporting  three  floors of  a 

Class A Office building in Rockville that houses County agencies. 

3. Council Office Building (COB) Remodeling 

FiberNet staff, using funds from the Department of General Services, provided the design 

and  construction  management  for  the  buildout  of  the  first  of  three  floors  being 

remodeled in the Council Office Building. The remaining floors are to be built out in the 

fall of 2017 and the spring of 2018. 

4. Executive Office Building (EOB) 

FiberNet, with funding from the DTS budget, will completely replace the network access 

layer in the Executive Office Building with a dedicated PON that will initially deliver voice, 

video, and data.  

FiberNet Master Plan | Updated March 2018 

  

59  

 

The Office of Broadband Programs is currently working with the Department of General Services 

to design and place Information and communication technology infrastructure in the following 

four major construction projects. PON has been selected for the structured cable system in each 

project. 

1. Wheaton Revitalization Project office building 

2. Wheaton Library and Community Recreation Center 

3. Grey Courthouse 

4. South County Recreation & Aquatic Center 

FiberNet II’s Enterprise PON service is provided by placing a PON optical line terminal (OLT) device 

in a central network location at the PA building or campus. The OLT connects to up to 64 fibers 

and each fiber may be connected to a splitter in a zone box, a small enclosure that can be placed 

in a ceiling tile. The splitter connects each of the OLT fibers to up to 32 fibers that connect to an 

optical network terminal (ONT). The ONT converts the fiber signal to copper Ethernet (10Base‐T, 

100Base‐T, or 1000Base‐T) for the last few feet of the connection to the user’s edge device. Edge 

devices can include Wi‐Fi access points, desktop/laptop computers, cameras, and sensors.  

 The OLTs used by FiberNet II are capable of serving up to 2,048 ONTs and 8,192 edge devices. 

Each device can receive selectable levels of capacity up to 2.4 Gbps. 

4.7.2.2 ServiceLevelSpecificationsFiberNet  II  is monitored by a DTS Network Operations Center operating on a 24x7  schedule. 

FiberNet models the NOC on the FCAPS16 management framework created by the ISO to model 

operations  of  a  Telecommunications  Management  Network  (TMN).  DTS  has  developed  a 

document that defines the service level agreement (SLA) for FiberNet II services. This document 

can be  referenced  for  specific details  regarding  the SLA. The SLA document does not  include 

reference  to  the newly offered PON  technology;  it needs  to be updated  to  include  this new 

service offering.  

4.7.3 FiberNetII.vServicesFiberNet II.v is a precursor to FiberNet III, which will be based on optical network technologies. 

FiberNet  II.v  uses  Dense  Wave  Division  Multiplexing  (DWDM)  equipment  built  by  MRV 

Communications to deliver multiple high speed (10 Gbps) links over a single fiber‐pair. Currently 

FiberNet II.v is using DWDM for the following applications: 

High‐capacity point‐to‐point (P2P) links for agency specific connections 

Optical separation of traffic to provide private networks 

                                                       16 Fault‐management, configuration, accounting, performance, and security. 

FiberNet Master Plan | Updated March 2018 

  

60  

 

FiberNet has successfully deployed DWDM for the following projects: 

1. Montgomery College to MAX at the University of Maryland 

FiberNet built a dedicated DWDM link between Montgomery College’s King Street data 

center and the MAX point‐of‐presence at the University of Maryland. The portion of this 

link that  is outside of Montgomery County’s geographical boundaries uses optical fiber 

built and maintained by Prince George’s County during the ARRA fiber project; The link 

provides  a  10 Gbps  link  for Montgomery  College  and  a  second  10 Gbps  link  for  the 

Maryland Research and Education Network (MDREN). 

2. WSSC Great Seneca Water Treatment to WSSC headquarters in Prince Georges County 

FiberNet  created  four  dedicated  10  Gbps  links  between  WSSC’s  Prince  George’s 

Headquarters and the Great Seneca Water Treatment Plant. Roughly 80 percent of the 

optical fiber path is diversely routed to guard against optical fiber breaks. 

3. E911 redundant network for public safety 

FiberNet built a highly redundant, fully meshed Layer 2 network among the three most 

critical public safety sites in the County. These three sites carry all of the emergency public 

safety telephony. 

4. Computer‐aided dispatch network 

FiberNet  built  a  dedicated,  isolated  10  Gbps  link  between  the  Public  Safety 

Communications Center  (PSCC)  and  the Alternate Emergency Communications Center 

(AECC) to carry computer‐aided dispatch communications for the Montgomery County 

Police and Fire & Rescue Service. 

Three additional projects are currently underway: 

1. MCPS to RPS for disaster recovery 

FiberNet is scheduled to build a major node at Recovery Point Services, which will provide 

disaster recovery services for Montgomery County agencies. The node will carry IP traffic 

in 10 Gbps increments and EtherChannel as well. The node will also be equipped with an 

ASR 6906 switch capable of accepting high‐speed interface traffic. 

2. M–NCPPC HQ to Montgomery College Data Center 

In support of M–NCPPC and Montgomery College, FiberNet will provide dedicated Layer 

2 connectivity  from the Parks and Planning department’s Montgomery Regional Office 

FiberNet Master Plan | Updated March 2018 

  

61  

 

Building data center to MC’s King Street data center. This service will enable Parks and 

Planning to relocate its data center to a Tier 3 data center, improving its availability. This 

will  be  especially  beneficial  as  Parks  and  Planning  transitions  into  its  new Wheaton 

headquarters in 2020.  

3. Montgomery College Layer 1 private network 

FiberNet will build a DWDM network for Montgomery College. The network will connect 

its three main campus locations and the new CT Building on Corporate Boulevard. 

Additional requests for this technology are pending and will be considered within the operational 

framework of the ITPCC.  

Of special note, Atlantech Online has agreed to  interoperate with FiberNet to provide DWDM 

connectivity  to  client  Participating  Agencies.  MCPS  has  recently  requested  this  capability. 

Montgomery College will be able to more directly interoperate with Atlantech Online for UCaaS 

and internet connectivity. It is the responsibility of each PA to negotiate directly with Atlantech 

Online regarding these services—but FiberNet will be the platform for the services, which will 

reduce the overall cost to the PA. 

4.7.3.1 TechnicalSpecificationsDWDM  is  now  the  standard  technology  for  the  highest  speed  network  routes  and  network 

backbones. Using  a highway metaphor,  these would be  the  “interstate”  routes between  the 

network hubs—the network equivalent of  I‐270,  I‐495, and MD‐200. These routes need to be 

fast, reliable, and able to accommodate sudden and unexpected  increases  in demand. DWDM 

technology accommodates these needs by:  

1. Operating at high capacities—typically 100 Gbps or greater, which is more than 100 times 

faster than typical business and institutional fiber connections, and  

2. Having dozens of “lanes” of these connections in a single fiber strand, by sending dozens 

of different light colors through the fiber strand.  

State‐of‐the‐art DWDM technology has capacity for 88 different colors (or wavelengths), so using 

100 Gbps technology, this is 8.8 Tbps. Higher‐cost DWDM can operate at 400 Gbps, providing a 

significant upgrade capability without needing to build any additional fiber. 

Furthermore, DWDM equipment has lower speed interfaces to accommodate a range of optical 

and  electrical  connections  within  the  100  Gbps  link.  The  DWDM  technology  assigns  each 

interface to a separate “timeslot” within the 100 Gbps link, so a device connected to “slot 1” on 

one end of the link connects to “slot 1” on the other end of the link (Figure 20). 

FiberNet Master Plan | Updated March 2018 

  

62  

 

Figure 20: DWDM Service Segmentation Example 

  

FiberNet is poised to implement 100 Gbps DWDM on parts of its network backbone. Figure 20 

illustrates how that link is used to segment different types of traffic. In the middle is a fiber ring; 

the  reliability of DWDM  is due  in part  to  the  fact  that  if one  side of  the  ring  is broken,  the 

communications continues uninterrupted using the other side.  

DWDM  also  increases  security.  The  separate  interfaces  on  each  side  (Public  Safety,  County, 

Federal Research, Montgomery College, ultraMontgomery) are on separate channels from the 

other interfaces and the traffic does not use the same routers, switches, or addresses. This is the 

most  secure  type  of  separation,  short  of  using  entirely  separate  fiber  strands,  and makes  it 

possible for a single fiber strand to carry internet traffic and secure public safety communications, 

sensitive health care information, and leased circuits from private sector service providers.  

DWDM also reduces costs because it allows for a single fiber strand to operate faster and add 

more users, reducing  the demand  for scarce  fibers.  It also  increases efficiency  in staffing and 

management, making  it possible to add users and connections through remote control by the 

network  operator,  rather  than  physically  connecting many  separate  devices  and managing 

network routers and switches for each connection. Finally,  it enables a wide range of network 

governance models, making  it possible either for FiberNet to operate with an entirely “hands‐

off” approach to the communications of various users,17 or for FiberNet to operate full turn‐key 

services, including managing user desktops and internet access for a wide range of entities.

                                                       17 For example, simply picking up and handing off Montgomery College communications at the campuses, rather than needing to be concerned about network routes or addresses or College devices at FiberNet hub sites. 

FiberNet Master Plan | Updated March 2018 

  

63  

 

4.7.3.2 ServiceLevelSpecificationsThe current FiberNet SLA document developed by DTS does not cover FiberNet II.v services and 

should be amended to do so. 

4.8 FiberNetOpticalTechnologyMigration(FiberNetIII)One of  the benefits of  fiber optic  technology  is  its  ability  to  scale  capacity  and  increase  the 

features of the network simply by replacing or upgrading the electronics. The original FiberNet 

fiber from the 1990s supports the third generation of FiberNet electronics operating at 100 Gbps, 

almost 10,000 times faster than the 1.5 Mbps T1 circuits on the original FiberNet. Furthermore, 

innovations  in technology make the current electronics more easily monitored, more  flexible, 

and more secure than earlier electronics. 

FiberNet’s  current  technological  roadmap  calls  for  the  implementation  of  dense wavelength 

division multiplexing  (DWDM)  technology on  the FiberNet high‐speed backbone, and passive 

optical  networking  (PON)  as  the  means  of  connecting  individual  users  to  FiberNet.  Both 

approaches represent an  innovative  implementation of fiber networking technologies and are 

explained in detail above. Moreover, these technologies will provide significantly more options 

in keeping the network secure; will reduce the network lifetime cost, the likelihood of failures, 

and the network’s energy consumption; and will make  it easier and cheaper to add users and 

capacity to the network. 

The next  generation of  FiberNet electronics upgrades will deliver  an exponential  increase  in 

capacity  and  enhanced  service  level  guarantees, which  are  necessary  to meet  the  growing 

demands of a continuously evolving and expanding user base. FiberNet is a multi‐tenant network 

that has provided carrier‐class Internet Protocol (IP) data transport services over Multi‐Protocol 

Label Switching (MPLS) for many years, leveraging best‐in‐class hardware and best practices for 

network design at each layer of the network. As this hardware reaches the end of its useful life, 

it is necessary to plan for the graceful refresh of the underlying equipment so the network can 

remain transparent to the end user while meeting the demands of emerging requirements.  

FiberNet III will offer modernized security tools and enhanced capabilities to deliver guaranteed 

service levels. Most importantly, the proposed upgrades will allow FiberNet to keep pace with 

exponential growth  in  capacity demands, offering more  than  tenfold  increases  in  capacity at 

every layer of the network.  

The existing network provides connectivity to nearly 465 anchor sites, mostly over 1 Gbps optics 

that are mostly rate limited to sub‐1 Gbps speeds. A total of 12 hub sites aggregate connections 

from these sites and form a backbone “mesh” network architecture comprised of 10 Gbps links. 

MPLS  is used to provide  logical segmentation of network traffic  in the form of Layer 3 Virtual 

Private Networks (L3VPNs) for each “customer” agency, and enables advanced mechanisms for 

FiberNet Master Plan | Updated March 2018 

  

64  

 

traffic engineering and quality of service (QoS) to be employed to ensure virtually any  level of 

reliability and performance necessary.  

FiberNet III will not represent a paradigm shift in technology or architecture; rather, building on 

the lessons learned in the past and the successes of the current network, the proposed upgrades 

represent  much  more  of  the  same  reliability  and  proactive  approach  to  meeting  capacity 

demands, enabled by  faster electronics and  the  latest  technology advancements. Specifically, 

there are two main components to the proposed upgrades: 

1. DWDM Backbone –  the  recent deployment of  the County’s DWDM optical backbone 

positions FiberNet to expand  its capacity  levels to meet future needs. This deployment 

targeted an  increased efficiency  in the utilization of the underlying physical  fiber optic 

infrastructure, but future scalability is another primary objective. Expanding the current 

deployment to support many more optical wavelengths over the same fiber optic strands 

is intrinsic to its intended purpose, and allows the County to deliver virtually any level of 

capacity  for  internal  or  external  customer  entities  without  depleting  physical  fiber 

infrastructure resources. 

2. IP/MPLS  Switches  and  Routers  –  the  current  network,  supporting  up  to  1  Gbps 

connections to customer sites that are aggregated over 10 Gbps backbone connections, 

will be upgraded by a factor of more than 10 simply as a result of the current state of the 

industry  for  comparable products. Each  customer  site will  receive a multi‐gigabit‐per‐

second connection over one or more 10 Gigabit Ethernet (10GE) interfaces, aggregated 

at each FiberNet hub onto redundant 100 Gigabit Ethernet (100GE) backbone links. Each 

switch  and  router  in  the  FiberNet  backbone  will  require  physical  upgrades  to  take 

advantage of this next generation of technological capability. 

Network upgrades can be phased over several years to address needs in order of priority and 

to  accommodate  budgetary  constraints.  Backbone  (DWDM  and  core/distribution  router) 

upgrades must occur first, but customer site upgrades can occur more gradually on a case‐by‐

case  basis.  Existing  and  new  backbone  components  may  need  to  be  interconnected  and 

maintained in parallel during a portion of this transition.  

In total, based on 500 sites, a capital expenditure of approximately $30.3 million is required for 

the  entire  network  upgrade  (Table  15).  This  total  includes  contractor  support  for  design, 

configuration,  and  integration  of  backbone  network  equipment  upgrades. We  estimate  the 

associated  annual  maintenance  costs,  comprised  of  manufacturer  support  contracts  for 

replacement  of  failed  hardware,  software  upgrades,  and  remote  technical  support,  at 

approximately  $1.4  million  (Table  16),  offset  entirely  or  in  large  part  by  a  corresponding 

elimination of existing network equipment maintenance costs once retired. 

FiberNet Master Plan | Updated March 2018 

  

65  

 

Table 15: Estimated FiberNet III Network Electronics Capital Upgrade Costs 

Component  Per Site Cost  Quantity Extended 

Cost 

DWDM Backbone Upgrades  $236,000 10  $2,360,000

Core Router  $3,060,000 2  $6,120,000

Service Edge (Distribution) Router  $960,000 12  $11,520,000

Customer Edge Switch   $17,000 500  $8,500,000

Design and Integration Support (Backbone Network Only) 

N/A 1  $1,800,000

Capital Total:  $30,300,000

 

Table 16: Estimated FiberNet III Network Electronics Annual Maintenance Costs 

Component  Per Site Cost  Quantity Extended 

Cost 

DWDM Node  $30,000 10  $300,000

Core Router  $165,000 2  $330,000

Service Edge (Distribution) Router  $47,000 12  $564,000

Customer Edge Switch   $950 500  $475,000

Annual Maintenance Total:  $1,369,000

 

Estimated  costs are based on a  candidate Cisco and MRV‐based architecture  consistent with 

existing  deployments,  but we  note  that  there  are  numerous  competitive  offerings  in  these 

markets  for  the  County  to  explore  within  these  budgetary  estimates.  The  specific  solution 

examined anticipates the activation of multiple 100 Gbps wavelengths between existing FiberNet 

DWDM backbone nodes  to support connections between core and distribution  layer  routers. 

Furthermore, the proposed upgrades include the deployment of redundant core routers (Cisco 

ASR 9910) capable of high density 100 GE  link aggregation and high capacity distribution  layer 

routers in the “service provider” edge (Cisco ASR 9904) capable of high density 10 GE aggregation 

and 100 GE uplinks.  

Phased upgrades to customer edge switches (Cisco ME 3600‐X) would be required as needed to 

address  site‐specific demands  for  capacity needs  above 1 Gbps  (leveraging 10GE  interfaces). 

Appendix  A  and  Appendix  B  provide  a  schematic  and  detailed  equipment  bills  of materials 

(BOMs), respectively, for the proposed network upgrades.  

The  initial phased approach will  identify  four  to  six DWDM  links between hubs with  suitable 

environmental conditions. The amount of traffic, measured in bandwidth, for each hub will also 

be considered when choosing the hubs for the FiberNet III phase 1 approach.  

FiberNet Master Plan | Updated March 2018 

  

66  

 

Existing  backbone  fibers  can  support  the  new  DWDM  links.  Once  the  core  links  are 

commissioned, traffic will be aggregated at the hubs. At this core phase, no changes are to be 

implement on edge peripherals. Agencies and FiberNet users can cut over as bandwidth needs 

are realized on a location by location basis.  

Further  cost  analysis  is  needed  to  separate  current  DWDM  projects  with  FiberNet  III  core 

upgrades. Where current bandwidth needs allow, there can be some cost savings achieved by 

sharing DWDM links for specific initiative with the initial FiberNet III core upgrade. 

FiberNet Master Plan | Updated March 2018 

  

67  

 

AppendixA1:CandidateFiberNet3.0NetworkElectronicsArchitecture–IP/MPLSBackbone 

 

   

FiberNet Master Plan | Updated March 2018 

  

68  

 

AppendixA2:CandidateFiberNet3.0NetworkElectronicsArchitecture–OpticalBackbone 

 

FiberNet Master Plan | Updated March 2018 

  

69  

 

AppendixB:CandidateFiberNet3.0NetworkElectronicsArchitecture–EquipmentBOM

Candidate Cisco ASR 9k / ME 3600‐X Electronics BOM

Core Router (Cisco ASR 9910)  Description  Model Number   Qty.  List Price  Discount  Extended Price 

ASR 9910 8 Line Card Slot Chassis  ASR‐9910  1   $65,000   45%  $35,750 

ASR 9910 Air Reflector  ASR‐9910‐AIRREF  1  $400   45%  $220 

ASR 9K Slide guide rail for 19" 4 post  A9K‐SLIDE‐RAIL  1  $550   45%  $303 

ASR‐9910 4 Post Mounting Kit  ASR‐9910‐4P‐KIT  1  $‐  45%  $0 

ASR 9910 Switch Fabric Card  A99‐SFC‐S  5   $50,000   45%  $137,500 

ASR 9910 Fan Tray  ASR‐9910‐FAN  2   $5,000   45%  $5,500 

ASR9K AC Power Enclosure Module Version 3 

A9K‐AC‐PEM‐V3  2   $1,700   45%  $1,870 

6KW AC Power Module Version 3  PWR‐6KW‐AC‐V3  2   $5,600   45%  $6,160 

Power Cord for AC V2 Power Module (USA)  PWR‐CAB‐AC‐USA  4   $ ‐  45%  $0 

ASR9000; Lean Core, Internet Back Bone; For Tracking Only 

A9K‐IP‐CORE  1   $ ‐  45%  $0 

ASR 9910 Route Processor for Service Edge  A99‐RSP‐TR  2   $70,000   45%  $77,000 

Cisco IOS XR IP/MPLS Core Software 3DES  XR‐A9K‐PXK9‐06.00  1   $15,000   45%  $8,250 

ASR 9900 8‐port 100GE LC ‐SE OTN  A99‐8X100GE‐SE  1   $1,300,000   45%  $715,000 

Infrastructure VRF LC License. Support up to 8 VRFs 

A9K‐IVRF‐LIC  2   $10,000   45%  $11,000 

CPAK‐100G‐LR4 Transceiver module, 10km SMF 

CPAK‐100G‐LR4  3   $40,000   45%  $66,000 

CPAK‐100G‐SR10 Transceiver module, 100m OM3 MMF 

CPAK‐100G‐SR10  5   $6,995   45%  $19,236 

ASR 9900 8‐port 100GE LC ‐SE OTN  A99‐8X100GE‐SE  1   $1,300,000   45%  $715,000 

Infrastructure VRF LC License. Support up to 8 VRFs 

A9K‐IVRF‐LIC  1   $10,000   45%  $5,500 

FiberNet Master Plan | Updated March 2018 

  

70  

 

Core Router (Cisco ASR 9910)  Description  Model Number   Qty.  List Price  Discount  Extended Price 

CPAK‐100G‐LR4 Transceiver module, 10km SMF 

CPAK‐100G‐LR4  2   $40,000   45%  $44,000 

CPAK‐100G‐SR10 Transceiver module, 100m OM3 MMF 

CPAK‐100G‐SR10  6   $6,995   45%  $23,084 

24‐port 10GE, Service Edge Optimized LC  A9K‐24X10GE‐SE  1   $400,000   45%  $220,000 

10GBASE‐SR SFP Module  SFP‐10G‐SR  24   $995   45%  $13,134 

Infrastructure VRF LC License. Support up to 8 VRFs 

A9K‐IVRF‐LIC  1   $10,000   45%  $5,500 

24‐port 10GE, Service Edge Optimized LC  A9K‐24X10GE‐SE  1   $400,000   45%  $220,000 

10GBASE‐SR SFP Module  SFP‐10G‐SR  24   $995   45%  $13,134 

Infrastructure VRF LC License. Support up to 8 VRFs 

A9K‐IVRF‐LIC  1   $10,000   45%  $5,500 

Core Router Subtotal:  $2,348,640 

Core Router Annual Maintenance  Description  Model Number   Qty.  List Price  Discount Extended Price

SNTC‐8X5XNBD ASR 9910 8 Line Card Slot Chassis CON‐SNT‐ASR9910A 

1  $3,445   15%  $2,928 

SNTC‐8X5XNBD ASR 9910 Switch Fabr CON‐SNT‐A99SCFCS 

1  $2,650   15%  $2,253 

SNTC‐8X5XNBD ASR 9900 8‐port 100GE LC ‐SE OTN 

CON‐SNT‐A9900GES 

1  $68,900   15%  $58,565 

SNTC‐8X5XNBD CPAK‐100G‐LR4 Transceiver module, 10km S 

CON‐SNT‐CPAK10G4 

1  $2,800   15%  $2,380 

SNTC‐8X5XNBD CPAK‐100G‐SR10 Transceiver module100m 

CON‐SNT‐CPAK30UG 

1  $490   15%  $417 

SNTC‐8X5XNBD ASR 9900 8‐port 100GE LC ‐SE OTN 

CON‐SNT‐A9900GES 

1  $68,900   15%  $58,565 

SNTC‐8X5XNBD CPAK‐100G‐LR4 Transceiver module, 10km S 

CON‐SNT‐CPAK10G4 

1  $2,800   15%  $2,380 

SNTC‐8X5XNBD CPAK‐100G‐SR10 Transceiver module100m 

CON‐SNT‐CPAK30UG 

1  $490   15%  $417 

FiberNet Master Plan | Updated March 2018 

  

71  

 

Core Router Annual Maintenance  Description  Model Number   Qty.  List Price  Discount Extended Price

SNTC‐8X5XNBD 24‐port 10GE, Service Edge Optimized LC 

CON‐SNT‐A9K24X1S 

1  $21,200   15%  $18,020 

SNTC‐8X5XNBD Infrastructure VRF LC License CON‐SNT‐A9KIVRFL 

1  $530   15%  $451 

SNTC‐8X5XNBD 24‐port 10GE, Service Edge Optimized LC 

CON‐SNT‐A9K24X1S 

1  $21,200   15%  $18,020 

SNTC‐8X5XNBD Infrastructure VRF LC License CON‐SNT‐A9KIVRFL 

1  $530   15%  $451 

Core Router Annual Maintenance Subtotal: $164,845

 

Service Provider Edge (Distribution) Router (Cisco ASR 9904)

Description  Model Number   Qty.  List Price  Discount Extended Price

ASR‐9904 2 Line Card Slot Chassis  ASR‐9904  1  $13,100   45%  $7,205 

ASR9K Route Switch Processor with 440G/slot Fabric and 12GB 

A9K‐RSP440‐SE  2  $65,000   45%  $71,500 

ASR‐9904 System Filter  ASR‐9904‐FILTER  1  $300   45%  $165 

ASR‐9904 System Fan Tray  A9K‐9904‐FAN  1  $3,700   45%  $2,035 

ASR9K AC Power Entry Module Version 2  ASR9K‐AC‐PEM‐V2  1  $1,200   45%  $660 

3KW AC Power Module Version 2  PWR‐3KW‐AC‐V2  2  $2,800   45%  $3,080 

Power Cord for AC V2 Power Module (USA)  PWR‐CAB‐AC‐USA  2  $0   45%  $0 

Cisco ASR9000; No Physical Part; For Tracking Only 

A9K‐CORE  1  $0   45%  $0 

Cisco IOS XR IP/MPLS Core Software 3DES XR‐A9K‐PXK9‐06.00 

1  $15,000   45%  $8,250 

400G Modular Linecard, Service Edge Optimized  A9K‐MOD400‐SE  1  $300,000   45%  $165,000 

ASR 9000 4‐port 100GE Infrastructure VRF License 

A9K‐400G‐IVRF  1  $20,000   45%  $11,000 

ASR 9000 20‐port 10GE Modular Port Adapter A9K‐MPA‐20X10GE 

1  $162,500   45%  $89,375 

SFP+ Bidirectional for 10km, downstream  SFP‐10G‐BXD‐I  10  $5,200   45%  $28,600 

FiberNet Master Plan | Updated March 2018 

  

72  

 

Service Provider Edge (Distribution) Router (Cisco ASR 9904)

Description  Model Number   Qty.  List Price  Discount Extended Price

ASR 9000 2‐port 100GE Modular Port Adapter A9K‐MPA‐2X100GE 

1  $162,500   45%  $89,375 

CPAK‐100G‐SR10 Transceiver module, 100m OM3 MMF 

CPAK‐100G‐SR10  2  $6,995   45%  $7,695 

400G Modular Linecard, Service Edge Optimized  A9K‐MOD400‐SE  1  $300,000   45%  $165,000 

ASR 9000 4‐port 100GE Infrastructure VRF License 

A9K‐400G‐IVRF  1  $20,000   45%  $11,000 

ASR 9000 20‐port 10GE Modular Port Adapter A9K‐MPA‐20X10GE 

2  $162,500   45%  $178,750 

SFP+ Bidirectional for 10km, downstream  SFP‐10G‐BXD‐I  32  $5,200   45%  $91,520 

Distribution Router Subtotal: $930,210

 

Service Provider Edge (Distribution) Router Maintenance

Description  Model Number   Qty.  List Price  Discount Extended Price

SNTC‐8X5XNBD ASR‐9904 2 Line Card Slot Chassis CON‐SNT‐ASR99042 

1  $694   15%  $590 

SNTC‐8X5XNBD ASR9K Route Switch Processor 440G/slot 

CON‐SNT‐A9KRSP4S 

1  $3,392   15%  $2,883 

SNTC‐8X5XNBD Cisco IOS XR IP/MPLS CON‐SNT‐XRA9K600 

1  $795   15%  $676 

SNTC‐8X5XNBD 400G Modular Linecard, Service Edge Opti 

CON‐SNT‐A9KMOD4E 

1  $15,900   15%  $13,515 

SNTC‐8X5XNBD ASR 9000 20‐port 10GE Modular Port Adapt 

CON‐SNT‐A9KMPA2E 

1  $8,613   15%  $7,321 

SNTC‐8X5XNBD ASR 9000 2‐port 100GE Modular Port Adapt 

CON‐SNT‐A9KMPAGX 

1  $8,613   15%  $7,321 

SNTC‐8X5XNBD CFP2 to CPAK adapter for 10x10G interface 

CON‐SNT‐CVRCFPAR 

1  $105   15%  $89 

SNTC‐8X5XNBD CPAK‐100G‐SR10 Transceiver module100m 

CON‐SNT‐CPAK30UG 

1  $490   15%  $417 

SNTC‐8X5XNBD 400G Modular Linecard, Service Edge Opti 

CON‐SNT‐A9KMOD4E 

1  $15,900   15%  $13,515 

FiberNet Master Plan | Updated March 2018 

  

73  

 

SNTC‐8X5XNBD ASR 9000 20‐port 10GE Modular Port Adapt 

CON‐SNT‐A9KMPA2E 

1  $863   15%  $734 

Distribution Router Annual Maintenance Subtotal: $47,060

Customer Edge Switch (Cisco ME 3600‐X)  Description  Model Number   Qty.  List Price  Discount  Extended Price 

ME3600X Ethernet Access Switch 24 GE SFP + 2 10GE SFP+  ME‐3600X‐24FS‐M 

1  $12,988   45%  $7,143 

ME3600X 10GE Upgrade License  ME3600X‐10G 1  $2,995   45%  $1,647 

Cisco ME 360X SERIES IOS UNIVERSAL TAR S360XVK9T‐15403S 

1  $0   45%  $0 

ME3600X /ME3800X AC Power Supply  PWR‐ME3KX‐AC 1  $995   45%  $547 

ME3600X /ME3800X AC Power Supply  PWR‐ME3KX‐AC 1  $995   45%  $547 

ME3600X Metro IP Access license  ME3600X‐I 1  $0   45%  $0 

AC power cord (North America)  CAB‐AC‐ME 2  $0   45%  $0 

ETSI Rack Mount for ME 3600X and ME3800X Series Switches 

RCKMNT‐ME3KX‐ETSI 

1  $75   45%  $41 

Cisco ME 3600X and ME3800X SD Memory Card 2GB 

MEM‐ME3K‐2GB1  $395   45%  $217 

SFP+ Bidirectional for 10km, upstream  SFP‐10G‐BXU‐I 1  $5,200   45%  $2,860 

10GBASE‐SR SFP Module  SFP‐10G‐SR 1  $995   45%  $547 

Customer Edge Switch Subtotal: $13,551

 

Customer Edge Switch Maintenance  Description  Model Number   Qty.  List Price  Discount  Extended Price 

SNTC‐8X5XNBD ME3600X Ethernet Access Switch 24 GE SFP 

CON‐SNT‐M36X24FS 

1  $880   15%  $748 

SNTC‐8X5XNBD ME3600X 10GE Upgrade Licensew/Electronic Delivery 

CON‐SNT‐LME360XG 

1  $240   15%  $204 

SNTC‐8X5XNBD ME3600X Metro IP Access license CON‐SNT‐ME3600XI 

1  $0   15%  $0 

Customer Edge Switch Annual Maintenance Subtotal: $952

FiberNet Master Plan | Updated March 2018 

  

74  

 

 

Candidate MRV Electronics BOM

MRV DWDM Optidriver – 100G Add/Drop Node

Description  Model Number   Qty.  List Price  Discount  Extended Price 

OTN/FEC 100G Dual CFP, single slot  OD‐TXP100GF‐2C  4   $ 16,669   30%   $ 46,673 

CFP 100G SM DWDM Coherent single wavelength tunable 50GH 

CFP‐100G‐DWCHT  4   $ 59,995   30%   $ 167,986 

CFP2 100G MM SR10 100m multi‐rate 100G Ethernet and OTU4  

CFP2‐100G‐SR10  4   $ 7,500   30%   $ 21,000 

Core Router Subtotal:  $235,659   DWDM Node Annual Maintenance 

Description  Model Number   Qty.  List Price  Discount  Extended Price Unlimited Service/Support Web site access with SW & Documentation Updates. 24x7 Service /Support TAC for Telephone support. Overnight hardware replacement ‐ NBD. Cost: 10% of HW List. 

SVC‐PRIORITY+  1   $33,665.60   10%   $30,299 

Core Router Annual Maintenance Subtotal:  $ 30,299 

FiberNet Master Plan | Updated March 2018 

  

75  

 

AppendixC:ConsolidatedSiteAdditionListwithCostsSTATUS  SITE & BUDGET YEAR IN WHICH FUNDING WILL BE ALLOCATED  COST ESTIMATE

(A)pproved  FY17 Total  $940,447 

  M–NCPPC  $90,409

Built  Wheaton Ice Arena, 11717 Orebaugh Ave, Wheaton  $39,040 

Built  Wheaton Regional Park Maintenance Yard, 12012 Kemp Mill Rd, Wheaton  $51,369 

  MCG  $532,877 

A  Aquatic Center, 5900 Executive Blvd. Rockville  $52,900 

Built  Betty Ann Krahnke Center, 14810 Broschart Road, Gaithersburg  $49,677 

A  East County Rec, 3310 Gateshead Manor Way  $68,100 

A  East County Gov’t Center, Briggs Chaney Road, Silver Spring  $68,100

A  Gwendolyn Coffield CC, 2450 Lyttonsville Rd., Silver Spring  $70,000 

A  MLK Swim Center, 1201 Jackson Rd., Silver Spring  $142,900 

A  Ross Boddy, 18529 Brooke Rd., Sandy Spring  $10,000 

A  Schweinhart Sr. Center, 1000 Forest Glen Rd., Silver Spring  $71,200 

  MCPS  $208,561

Built  Lynnbrook Ctr NSBO, 8001 Lynnbrook Dr., Bethesda  $0 

Built  Mark Twain Blair Ewing Center, 14501 Avery Road, Rockville   (Comcast) $0 

MCPS Campus 

Print Shop Stonestreet NSBO, 660 North Stonestreet Avenue  $0 

Built  Randolph Depot NSBO, 1800 Old Randolph Road, Silver Spring  $49,700 

A  Richard Montgomery ES, 322 W. Edmonston, Rockville  $158,861 

  WSSC  $108,600 

A  Gaithersburg Depot, 111 West Diamond Avenue, Gaithersburg   $53,600 

A  Lyttonsville Depot, 2501 Lyttonsville Road, Silver Spring   $55,000 

  FY18 TOTAL  $1,010,600 

  M–NCPPC  $201,000 

A  Woodlawn Park Police Substation, 16501 Norwood Rd, Sandy Spring  $201,000 

  MCG  $308,900 

Built  Good Hope, 14715 Good Hope Rd, DGS CIP Funded  $0 

A  Jane Lawton Community Center (Leland), 4301 Willow Lane, Chevy Chase  $67,800 

A  Long Brch. Comm. Center, 8700 Piney Branch Rd., Silver Spring  $100,000 

  Olney Swim Center, 16601 Georgia Ave., Olney  $76,700 

A  Silver Spring Health Center, 8630 Fenton Street, 10th floor, Silver Spring  $64,400 

  MCPS  $500,700 

Deferred  Hadley Farms NSBO, 7401 Hadley Farms Dr., Gaithersburg  $117,200 

Deferred  Montrose Center NSBO, 12301 Academy Way, Rockville  $45,200 

A  Emory Grove Holding School, 18100 Washington Grove Lane  $45,200

A  Radnor Center, 7000 Radnor Lane, Bethesda  $38,700 

A  Wilson Wims ES, 12520 Blue Sky Drive, Clarksburg  $254,400 

FiberNet Master Plan | Updated March 2018 

  

76  

 

STATUS  SITE & BUDGET YEAR IN WHICH FUNDING WILL BE ALLOCATED  COST ESTIMATE

    FY19  $1,573,700

  M–NCPPC  $473,000 

  Meadowside Nature Center, 5100 Meadowside Lane, Rockville  $140,800 

A  Needwood Mansion, 6700 Needwood Rd, Rockville  $195,800 

  Pope Farm Nursery, 7400 Airpark Rd, Gaithersburg  $34,500 

  Waters House, 12535 Milestone Manor Lane, Germantown   $51,900 

  Woodlawn Manor, 16501 Norwood Rd, Sandy Spring  $25,000 

  Woodlawn Visitors Center, 16501 Norwood Rd, Sandy Spring  $25,000 

  MCG  $330,700 

  Clara Barton, 7425 MacArthur Blvd., Cabin John  $127,200 

A  Longwood Comm. Center, 19300 Georgia Ave., Brookeville  $122,600 

  Wheaton/Glenmont Outdoor Pool, 12601 Dalewood Dr., Wheaton  $80,900 

  MCPS  $441,000

  Kingsley Wilderness Center NSBO, 22870 Whelan Lane, Boyds   $90,000 

  Rica SS, 15000 Broschart Road, Rockville  $142,000 

A  West Farm Depot NSBO, 11920 Bournfield Way, Silver Spring  $209,000 

  WSSC  $329,000 

A  Consolidated Laboratory & West Farm Depot, 12245 Tech Road, Silver Spring  $309,000 

  North Woodside Standpipe, 1945 Seminary Place, Silver Spring   $10,000 

  Shady Grove Standpipe, 8620 Pleasant Road, Gaithersburg  $10,000 

  FY20  $4,024,400 

  M–NCPPC  $1,974,900 

  Black Hill Headquarters, 20930 Lake Ridge Dr., Boyds   $500,000 

 Black Hill Northern Region Headquarters & Park Police Office, 14300 Black Hill Rd, Boyds 

$500,000 

  Brookside Nature Center, 1400 Glenallan Ave, Wheaton  $218,600 

  Little Bennett Campgrounds, 23705 Frederick Rd, Clarksburg  $310,200 

  Little Bennett Maintenance Yard, 23701 Frederick Rd, Clarksburg  $42,900 

  Martin Luther King MY, 1120 Jackson Rd, Silver Spring  $182,200 

  Olney Maintenance Yard, 19117 Willow Grove Rd, Olney  $221,000 

  MCG  $611,500 

  Scotland, 7700 Scotland Dr., Potomac  $111,500 

  Western County Outdoor Pool, 20151 Fisher Ave, Poolesville  $500,000 

  WSSC  $1,438,000 

  Brighton Dam, 2 Brighton Dam Road, Brookeville   $512,000 

  Colesville Tank, 2201 Industrial Parkway, Silver Spring   $192,000 

  Damascus Elevated Tank, 9950 Damascus Boulevard, Damascus   $372,000 

 Damascus Wastewater Treatment Plant, 23730 Log House Road, Gaithersburg  

$234,000 

  Falls Road Standpipe, 8505 Aqueduct Road, Potomac  $128,000 

  Grand Total  $7,549,147 

 

FiberNet Master Plan | Updated March 2018 

  

77  

 

AppendixD:GlossaryofAcronymsAgenciesandDepartmentsDGS – Montgomery County Department of General Services 

DOT – Montgomery County Department of Transportation  

DTS – Montgomery County Department of Technology Services  

GIS – Montgomery County DTS division of Geographical Information Systems 

HOC – Housing Opportunities Commission    

ITPCC – Interagency Technology Policy and Coordination Committee   

MC – Montgomery College   

MCG – Montgomery County Government   

MCPS – Montgomery County Public Schools  

M–NCPPC – Maryland–National Capital Park and Planning Commission  

OMB – Montgomery County Office of Management and Budget 

NSBO – MCPS Non‐School‐Based Office 

PA – Participating Agencies  

WSCC – Washington Suburban Sanitary Commission 

 

PlacesandNetworksAECC – Alternate Emergency Communications Center  

COB – Montgomery County Council Office Building  

CT Building – Montgomery College’s Central Services Building  

DC‐Net – Washington, D.C. government’s network  

EOB – Montgomery County Executive Office Building  

ICBN – Inter‐County Broadband Network  

KSDC – Montgomery College’s King Street Data Center (located the Takoma Park/Silver Spring campus) 

MASP – Multi‐Agency Service Park (located in Montgomery Village) 

MAX – Mid‐Atlantic Crossroads, the University of Maryland’s government and educational fiber network 

MDREN – Maryland Research and Education Network  

MRO – M‐NCPPC’s Montgomery Regional Office Building  

PSCC – Public Safety Communications Center  

PSRS – Public Safety Radio System 

 

FiberNet Master Plan | Updated March 2018 

  

78  

 

GeneralARRA – American Recovery and Reinvestment Act of 2009   

BTOP – Broadband Technology Opportunities Program 

HIPAA – Health Insurance Portability and Accountability Act of 1996  

MOU – Memoranda of Understanding  

NDA – Non‐Discretionary Account  

PCI DSS – Payment Card Industry Data Security Standard 

POs – Purchase Orders 

SLA – Service Level Agreement  

 

TechnicalATM – Asynchronous Transfer Mode  

CCB – Configuration Control Board 

CE – Customer Edge  

DWDM – Dense Wavelength Division Multiplexing  

FiberNet II – Second generation of FiberNet network operating architecture 

FiberNet II.v – Interim bridge between FiberNet II and FiberNet III operating architectures   

FiberNet III – Third generation of FiberNet operating architecture that supports Layer 2 connectivity 

GIS – Geographical Information System 

HVAC – Heating, Ventilation, and Air Conditioning  

IAD – ATM Integrated Access Device  

IP – Internet Protocol (data transport services)  

ISP – Inside Plant 

ISP – Internet Service Provider 

KPI – Key Performance Indicator 

L3VPNs – Layer 3 Virtual Private Networks  

Layer 2 – second level of Open System Interconnection (OSI) model 

MPLS – Multi‐Protocol Label Switching  

MPLS/VPN network  – Multi‐Protocol Label Switching to create Virtual Private Networks 

NOC – Network Operations Center  

OLT – Optical Line Terminal 

ONT – Optical Network Terminal  

OSP – Outside Plant  

P2P – Point‐to‐Point  

FiberNet Master Plan | Updated March 2018 

  

79  

 

PE – Provider Edge  

PON – Passive Optical Networking   

PVC – Permanent Virtual Circuit  

QoS – Quality of Service  

SaaS – Software as a Service 

SONET – Synchronous Optical Network  

TAC – Technical Assistance Center  

TDM – Time‐Division Multiplexing (method of transmitting data)  

TMN – Telecommunications Management Network 

UCaaS – Unified Communications as a Service 

VPN – Virtual Private Network 

VRF – Virtual Private Network Routing and Forwarding  

WAN – Wide Area Network