FIMS Data Validation Improvements
AndLessons Learned
Phil Dalby, PE, LEED AP, CFMOffice of Acquisition and Project Management
Property Management Virtual Workshop May 22, 2013
Agenda
• FIMS Validations• Status of FY 2013 Validations• Validation Trends• QA Reviews• FY 2013 Validation Plan• Best Practices• Lessons learned• Questions
3
FIMS
• Reliance on FIMS is increasing – Good News– Current user community consists of almost 500 people– The user base has increased by 40% over the last 5 years– We have seen an increased level of interest in FIMS training by
management and facilities personnel in the field• OMB's and GSA’s focus has shifted from data
completeness to data quality/accuracy– This makes our data validation process all the more important– We have seen significant improvement– Still plenty of room for improvement
• OMB considers our validation Process a best practice• GAO encouraged continued use of the FIMS validation
process
Call the hotline!!
Importance of FIMS Validations
• FIMS is the Department’s repository of real property information
– Legal/regulatory requirement• Annual Submission to the FRPP
– Required by 41 CFR § 102-84.55– 41 CFR § 102-84.30 requires agencies to verify the accuracy of each FRPP
submission• 20,000 records with upwards of 175 data elements per record
– Used in decision-making throughout the Department– Populates the Federal Real Property Profile– Supplemental data for financial reporting– Avoids unnecessary data calls and site-level queries
FY 2013 FIMS Validation Status
• 50 Sites to be validated• 22 Validated to date– 16 Green– 1 Yellow– 5 Red
• LPSO is lead on multi-program sites– One scorecard per site
Go’in for Green!
Quality Assurance Reviews
• ~ Eight per year• Try to get to each site every 4 to5 years• Share and capture best practices• Ensure validations are consistent Department-
wide• OPAM/HQ Program Office do not run validation– Observe process– Provide assistance – Answer questions
We’re from Washington and we're here to help!
FIMS
FY2013 FIMS Validation Plan
• FY2013 Three validations will be performed– One validation will include a random sample of DOE
owned buildings, trailers, and Other Structures and Facilities (OSF)
– The second validation will include all DOE leased buildings, trailers and Other Structures and Facilities (OSF)
– The third validation will include DOE owned, DOE ingrant – DOE leased and withdrawn from public domain land
– Contractor leased assets will not be validated– Bridge Safety Inspections will be verified
FIMS Validation Process
Planning the
ValidationLesson 3
InbriefLesson 4
Determine Sample Size
Lesson 5
Generate Random SampleLesson 6
Review Outliers
and Generate
Outlier ReportLesson 6
Generate DOE Leased
ReportLesson 6
Generate Land
Report Lesson 6
Generate Bridge Safety
Inspection ReportLesson 6
Populate Data
Validation FormsLesson 7 Identify
Assets for Physical
Walkthroughs
Lesson 7
Data Element ReviewLesson 8
Source Documents
Lesson 9
Desktop Validation Lesson 10
Conduct Walkthroug
hs Lesson 11
Prepare Scorecards
Lesson 12
Prepare Outbrief & Follow-up
Actions Lesson 13
Best Practices
• Complete source documentation worksheet– Streamlines process– Provides contact information of source data owner (SDO)
• Develop source documentation notebook– Tab for each data element– Signed Memo, dated, clarifying process for obtaining source data
by SDO– Be prepared to go into detail on how you arrived at the values for
the source data• Develop local data base for source data• Review entire process prior to validation
FIMS
Lessons Learned/Reminders
• DM inspection no longer than at 5 years apart– Check inspection dates before validation
• Source data required to be updated annually
• Source documentation development– Develop a table for Source Data Owner (SDO)
• SDO provides data or• SDO reviews, makes corrections and certifies existing data
– Signs and dates table certifying data is accurate – One SDO per table– Certified by one SDO– SDO must personally review and certify data as correct
This procedure can not be used for the following data elements
RPV Net Square Feet Annual Actual Maintenance
DM Utilization Annual Operating Costs
Size (Gross Sqft, Primary Qty, Secondary Qty)
Lessons Learned/Reminders
• FIMS generated RPVs– Use FIMS User Guide Appendix F to crosswalk Usage Code and RPV
model• Update process memos if process changes• Estimated disposition year for excessed assets
– If Site does not have a planned date for disposition• Use 9999• Update annually
• Conduct walkthrough for 25 to 30% of sample• Drive by as many of the remaining assets in the sample set as
practical
Lessons Learned/Reminders
The Facilities Walkthrough
• During Walkthrough:– Verify • Usage code• Status• Utilization
– Do a “sanity check” on deferred maintenance– Verify that multiple buildings and/or trailers assets
are not being reported as one single record in FIMS
Rating of Status ChartFIMS
ScorecardStatus Score
PerformanceMeasures *
Remainder of Validated Elements
Notes
GreenAll performance measures green and…
All other elements at-least yellow
Preferred level of data quality
Yellow
Any one performance measure yellow or…
No more than one of the remaining elements red
Minimal acceptable level of data quality
RedAny one performance measure red or…
More than one of the remaining elements red
Unacceptable data quality
*FRPC Performance Measures: Replacement Plant Value, Deferred Maintenance, Utilization, Annual Operating Costs and Annual Actual Maintenance
Corrective Action Plan (CAP)
• Sample available on FIMS website at http://fimsinfo.doe.gov/data_validation.htm
• Usually just the scorecard with a few additional columns to identify:– Corrective action plan completed within 30 days of validation– Point of contact– Estimated date of completion
Questions?
Phil Dalby PE, LEED APDepartment of EnergyOffice of Acquisition and Project Management (APM) - MA-652Phone: (202) 586-4548Cell: (202) 615-3405Fax: (202) [email protected]