FINAL DESIGN APPROVAL REQUEST ZA-DC-F-04 Issue 12 DOCUMENTS REQUIRED PLOT NUMBER PRELIMINARY DESIGN REQUEST NO. (IF ANY) New Renewal APPLICATION DETAILS (TICK APPROPRIATE BOX) Sub-Structure Final 1. Structural Design Drawing (as per Circular No. 400 ) 2. RC Structural Design Review Checklist (Form No. ZA- DC-F-83) 3. Structural calculations and structural model (soft copy) 4. Peer review report (as per Structural Guidelines) (If applicable) For Final (New Submission Only): SUBMISSION DETAILS (TICK APPROPRIATE BOX) Initial Submission Re-submission I hereby certify that the information, data and documents provided with this application are true, genuine and correct to the best of my knowledge. In case of default/failure to comply with any of the aforesaid conditions or the documents submitted by us is found false/forged, our application will be rejected forfeiting any applicable fees paid SUBMITTAL TYPE (TICK APPROPRIATE BOX) CONSULTANT 1. Architectural, Structural and Mechanical Design Drawings (as per Circular No.400) 2. Consultant appointment letter from owner 3. Project Details Sheet stamped and signed by consultant 4. Dubai Universal Design Code Checklist 5. Green Building Declaration stamped and signed by consultant 6. Green Building Code Checklist stamped and signed by consultant 7. NOC from Department of Civil Aviation (if applicable) 8. NOC and stamped drawings from Ministry of Awqaf & Religious Affairs (for Masjid) 9. DM Environmental Department approval for swimming pools, industrial use (industrial/manufacturing ), gray water treatment plant (if applicable) 10. Approved vehicle access and traffic impact study from RTA 11. Gate Level confirmation from RTA 12. RC Structural Design Review Checklist (Form No. ZA-DC-F-83) 13. Structural calculations and structural model (soft copy) PO Box 478844, Dubai, UAE T +971 800-4-DDA (332) F +971 4 427 2449 dda.gov.ae - Request will be accepted only if Site Plan is valid. - Soil Investigation Report (Form No. ZA-DC-F-07B) must be approved by DDA before applying for this service. - No documents are required for design renewal application. Terms and Conditions Notes: 14. Peer review report (as per Structural Guidelines) (If applicable) 15. District cooling service provider NOC (if applicable) 16. Valid NOC from DEWA (Electricity&Water) 17. Civil Defence final design approval 18. NOC from Telecom Operator (Du/Etisalat) 19. Sewerage Connection Confirmation from Master Developer/ infrastructure consultant/ DM- Drainage Department 20. Mechanical Design Review Checklist (ZA-DC-F-117) For Sub-Structure (New Submission Only): NAME MOBILE EMAIL DATE & SIGNAURE STAMP REQUESTER DETAILS

Upload: others

Post on 11-Feb-2022

13 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FINAL DESIGN APPROVAL REQUEST - dda.gov.ae

FINAL DESIGN APPROVAL REQUEST

ZA-DC-F-04 Issue 12

DOCUMENTS REQUIRED

PLOT NUMBERPRELIMINARY DESIGN REQUEST NO. (IF ANY)

NewRenewal

APPLICATION DETAILS(TICK APPROPRIATE BOX)

Sub-StructureFinal

1.Structural Design Drawing (as per Circular No. 400 )2.RC Structural Design Review Checklist (Form No. ZA-

DC-F-83)3.Structural calculations and structural model (soft copy)4.Peer review report (as per Structural Guidelines) (If

applicable)

For Final (New Submission Only):

SUBMISSION DETAILS(TICK APPROPRIATE BOX)

Initial Submission Re-submission

• I hereby certify that the information, data and documents provided with this application are true, genuine and correct to the bestof my knowledge. In case of default/failure to comply with any of the aforesaid conditions or the documents submitted by us isfound false/forged, our application will be rejected forfeiting any applicable fees paid

SUBMITTAL TYPE(TICK APPROPRIATE BOX)

CONSULTANT

1. Architectural, Structural and Mechanical Design Drawings (asper Circular No.400)

2. Consultant appointment letter from owner3. Project Details Sheet stamped and signed by consultant4. Dubai Universal Design Code Checklist5. Green Building Declaration stamped and signed by consultant6. Green Building Code Checklist stamped and signed by

consultant7. NOC from Department of Civil Aviation (if applicable)8. NOC and stamped drawings from Ministry of Awqaf &

Religious Affairs (for Masjid)9. DM Environmental Department approval for swimming pools,

industrial use (industrial/manufacturing ), gray water treatment plant (if applicable)

10. Approved vehicle access and traffic impact study from RTA11. Gate Level confirmation from RTA12. RC Structural Design Review Checklist (Form No. ZA-DC-F-83)13. Structural calculations and structural model (soft copy)

PO Box 478844, Dubai, UAET +971 800-4-DDA (332) F +971 4 427 2449

dda.gov.ae

- Request will be accepted only if Site Plan is valid.- Soil Investigation Report (Form No. ZA-DC-F-07B) must be approved by DDA before applying for this service.- No documents are required for design renewal application.Terms and Conditions

Notes:

14. Peer review report (as per Structural Guidelines) (If applicable)15. District cooling service provider NOC (if applicable)16. Valid NOC from DEWA (Electricity&Water)17. Civil Defence final design approval18. NOC from Telecom Operator (Du/Etisalat)19. Sewerage Connection Confirmation from Master Developer/ infrastructure consultant/ DM- Drainage Department20. Mechanical Design Review Checklist (ZA-DC-F-117)

For Sub-Structure (New Submission Only):

NAME

MOBILE

EMAIL

DATE &SIGNAURE

STAMP

REQUESTER DETAILS