final interim design presentation

Upload: cehblake1

Post on 03-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Final Interim Design Presentation

    1/49

    Concept Design of an Ultra-Deepwater

    Rare Earth Mineral Mining System

    Ranald Cartwright Christopher Blake David Fraser

    Euan Greer Russell Torrance Luke Chapman

    Interim Design Presentation

    17thof March, 2014

  • 8/12/2019 Final Interim Design Presentation

    2/49

    Presentation Overview

    Current Stage of Project

    Change of Project Focus

    Overview of Design Configuration

    Main Design Elements

    Riser System

    Mineral Collection Tool

    Flow Assurance

    Processing and Separation Systems

    Powering and Control Installation and Maintenance

    Project Time Plan

    Next Steps

  • 8/12/2019 Final Interim Design Presentation

    3/49

    CHOSEN DESIGN CONFIGURATION

  • 8/12/2019 Final Interim Design Presentation

    4/49

    Depth:

    4970m

    5000m

    CHOSEN DESIGN CONFIGURATION

    Installation

    Processing &Separation

    Riser System

    Flow

    Assurance Mineral

    Collection Tool

    Powering

  • 8/12/2019 Final Interim Design Presentation

    5/49

    Depth:

    4970m

    5000m

    Hydrocyclones

    Boost Pump

    Hopper

    FLOATING HUB

  • 8/12/2019 Final Interim Design Presentation

    6/49

    RISER SYSTEM

  • 8/12/2019 Final Interim Design Presentation

    7/49

    RISER STRUCTURE

    Initial Configuration

    Component Selection

    Riser Joint Burst and Loading Criteria specified by ABS

  • 8/12/2019 Final Interim Design Presentation

    8/49

    Depth:

    4970m

    5000m

    Integrated Lines

    Gas/Power/Comms

    Buoyancy Module

    (Balmoral)

    5.2IDRiser

    Riser Configuration

  • 8/12/2019 Final Interim Design Presentation

    9/49

    Depth:

    4970m

    5000m

    RISER CONFIGURATION

  • 8/12/2019 Final Interim Design Presentation

    10/49

    MINING AREA ENVIRONMENTAL CONDITIONS

    5000m Water Depth

    Hs = 4m and Tp = 9s

    Unidirectional and Bi-axial CurrentProfiles

    WD (m) Current Speed (m/s)

    1 0.4500 0.3

    1000 0.35000 0.2

  • 8/12/2019 Final Interim Design Presentation

    11/49

    OrcaFlex9.7a

    Vertical CurrentProfile

    Speed(m/s)

    0.80.60.40.20

    Z(m)

    0

    -1000

    -2000

    -3000

    -4000

    -5000

    OrcaFlex9.7a

    Vertical CurrentProfile

    Speed(m/s)

    0.40.20-0.2-0.4

    Z(m)

    0

    -1000

    -2000

    -3000

    -4000

    -5000

    OrcaFlex9.7a

    Spectral Densityfor WaveTrain 'Hs=4m'

    Frequency(Hz)

    0.40.30.20.10

    SpectralDensity(m^2/Hz)

    40

    30

    20

    10

    0

    Unidirectional

    MINING AREA ENVIRONMENTAL CONDITIONS

    Bi-Axial Wave Spectra

  • 8/12/2019 Final Interim Design Presentation

    12/49

    KEY CHALLENGES

    Determining the slip-joint and tensioner orientation

    Buoyancy Placement to be Sympathetic to Installation

    Vessel Loading during Operation

    Modelling Challenges

  • 8/12/2019 Final Interim Design Presentation

    13/49

    MINERAL COLLECTION TOOL

  • 8/12/2019 Final Interim Design Presentation

    14/49

    Depth:

    4970m

    5000m

    COLLECTION TOOL CONTROL

  • 8/12/2019 Final Interim Design Presentation

    15/49

  • 8/12/2019 Final Interim Design Presentation

    16/49

    Subsea Electromagnetic Hydrocyclone

    Assess forces required to effectively move and control the system

    Create a dynamic model of collection tool and assess motion underapplied forces: Control rams

    Hub Motions Seabed Friction

    Impact of Motions Collection Efficiency and Operability

    Environmental Considerations

    Investigate the method of operation

    COLLECTION TOOL ANALYSIS

  • 8/12/2019 Final Interim Design Presentation

    17/49

    Depth:

    4970m

    5000m

    OPERATION

  • 8/12/2019 Final Interim Design Presentation

    18/49

    FLOW ASSURANCE

  • 8/12/2019 Final Interim Design Presentation

    19/49

    Depth:

    4970m

    5000m

    Bundled Gas Lines x2

    Flow

    Assurance

    Centrifugal Boost Pump[Provides Seabed to Hub Lift]

    Massive Topsides Compressor[Tengiz Field Khazakstan 10,000 psi]

    LIFT MECHANISM CONFIGURATION

    Gas Injection at Hub

  • 8/12/2019 Final Interim Design Presentation

    20/49

    Depth:

    4970m

    5000m

    TOPSIDES GAS COMPRESSION

  • 8/12/2019 Final Interim Design Presentation

    21/49

    Depth:

    4970m

    5000m

    SUBSEA GAS INJECTION

  • 8/12/2019 Final Interim Design Presentation

    22/49

    REQUIRED FLOWRATE

    Hjulstrm Diagram

  • 8/12/2019 Final Interim Design Presentation

    23/49

    Subsea Electromagnetic HydrocycloneFLOW PARAMETERS

    Gas Lift with Boost Pump

    Required Mass : 100 t/hr (dry weight)

    Flow at Inlet: 221 t/hr (slurry)

    Flow to topsides : 108 t/hr (partially dewatered)

    Flow Rate to meet target : 3 m/s

  • 8/12/2019 Final Interim Design Presentation

    24/49

    Subsea Electromagnetic HydrocycloneCHALLENGES

    Key Issues:

    Required Mass of lifting gas

    Supercritical Liquids

    Change in Lifting Properties

    Gas Expansion towards surface

  • 8/12/2019 Final Interim Design Presentation

    25/49

    Subsea Electromagnetic HydrocycloneCHALLENGES

    Key Issues:

    Required Mass of lifting gas

    Supercritical Liquids

    Change in Lifting Properties

    Gas Expansion towards surface

    Air Phase Diagram

  • 8/12/2019 Final Interim Design Presentation

    26/49

    PROCESSING & SEPARATION SYSTEM

  • 8/12/2019 Final Interim Design Presentation

    27/49

    Separation and Processing

    Subsea electromagnetic

    hydrocyclone

    Topside gravity concentrator

    Tailings disposal

    SYSTEM CONFIGURATION

  • 8/12/2019 Final Interim Design Presentation

    28/49

    Subsea Electromagnetic Hydrocyclone

    Watson Magnetic Cyclone Design:

    Magnetic force coupled with

    centrifugal force

    Magnetic/Dense particles forced

    outward

    REEs collected from underflow

    Water/Clay to overflow and

    discharged

    SYSTEM CONFIGURATION

  • 8/12/2019 Final Interim Design Presentation

    29/49

    Subsea Electromagnetic Hydrocyclone

    Hydrocyclone size

    Inlet velocity

    Required magnetic field

    strength Hydrocyclone Equilibrium Conditions

    SEPARATION ANALYSIS OUTCOMES

  • 8/12/2019 Final Interim Design Presentation

    30/49

    Subsea Electromagnetic Hydrocyclone

    Assumptions for clay properties

    Magnetic susceptibility of particles

    Compatibility with desired flow conditions

    CHALLENGES

  • 8/12/2019 Final Interim Design Presentation

    31/49

    Knelson Concentrator:

    High capacity

    Established method

    Able to process desired particle

    size

    TOPSIDE GRAVITY CONCENTRATOR

  • 8/12/2019 Final Interim Design Presentation

    32/49

    Analysis:

    Based on subsea separation

    results

    Catalogue selection to meet

    requirements

    TOPSIDE GRAVITY CONCENTRATOR

  • 8/12/2019 Final Interim Design Presentation

    33/49

    System:

    Topside and Subsea Disposal Systems

    In accordance with ISA guidelines

    TAILINGS DISPOSAL

  • 8/12/2019 Final Interim Design Presentation

    34/49

    POWERING & CONTROL SYSTEMS

  • 8/12/2019 Final Interim Design Presentation

    35/49

    The umbilical will be a dynamic design, due to the depth of operation.

    Will be attached to the riser during installation (similar to current drilling

    operations).

    Will contain powering and control to the hub components.

    UMBILICAL DESIGN

  • 8/12/2019 Final Interim Design Presentation

    36/49

    Selection of the power and communication cables currently being chosen

    with reference to,

    IEC 60502-1 (Power cables: 1 kV up to 3 kV)

    IEC 60502-2 (Power cables: 6 kV up to 30 kV)

    DNV-RP-F401 (Electrical Power Cables in Subsea Applications)

    Internal structural design of the umbilical to be produced, outlining

    materials and components.

    UMBILICAL DESIGN

  • 8/12/2019 Final Interim Design Presentation

    37/49

    CONTROL SYSTEMS

    Buoyancy Modules

    Automated control of buoyancy modules no longer required.

    Pipe Control

    The control of the pipe will be via a hydraulic ram system located in the

    hub.

    3D model of the hydraulic system and its operation.

    A mathematical model of the control of the hydraulic systems operations

    (varying control inputs, to find the best operating conditions of the ram).

  • 8/12/2019 Final Interim Design Presentation

    38/49

    Pump and compressor selection yet to be confirmed as operation

    conditions are required.

    Once selected, specification of each will be compiled (supplying powering

    requirements).

    A total power amount for various operational conditions will then be

    specified with a suitable generation method chosen.

    A distribution diagram will be construction outlining power draws and

    potential losses.

    POWER REQUIREMENTS

  • 8/12/2019 Final Interim Design Presentation

    39/49

    INSTALLATION & MAINTENANCE

  • 8/12/2019 Final Interim Design Presentation

    40/49

    INSTALLATION AND MAINTENANCE OF MINERAL RECOVERY SYSTEM

    Huisman Dual Multi Purpose Tower (DMPT)

    Possible hook load of 1,090 tonnes

    No V-Door limitation due to box shape and not lattice

    Compatible with specified riser tensioners

    Moonpool skid cart capable of moving 800 tonne

    structure such as mineral recovery tool

    Using Aker CLIP risers it is possible to deploy rapidly

  • 8/12/2019 Final Interim Design Presentation

    41/49

  • 8/12/2019 Final Interim Design Presentation

    42/49

    RESPONSE OF RISER DURING INSTALLATION

    Using Orcaflex model to calculate riser response

    Continuation of Static Analysis from Riser Section

    Completed every 20m until riser depth is 200m to accurately measure bending and

    deflections through splash and wave zone

    Every 200m thereafter until target depth reached

    Analysed to find limiting environmental conditions for installation and retrieval of

    system

    Excess loads assessed during loading and retrieval phase

  • 8/12/2019 Final Interim Design Presentation

    43/49

    SYSTEM MAINTENANCE

    Investigate components used within project to detail

    maintenance intervals and procedures

    Establish the operating window of the system

    Will allow the maintainability of the system to be

    assessed and cost estimates provided

    FMECA undertaken to establish how a failure effects

    the system as a whole

    Initial operability found and measures to increase

    operability window implemented

  • 8/12/2019 Final Interim Design Presentation

    44/49

    GOING FORWARD

    Properties of buoyancy to be received from BalmoralOffshore

    Run initial Orcaflex model for first iteration of buoyancyplacement

    Ascertain if parameters such as stress in riser are withinacceptable limits in varying environments

    Compare deck layouts and derive an effective and safepositioning of installation and maintenance equipment

    Consider procedure if a storm is to hit mining area

    Construct FMECA of equipment and investigate effects ofpreventative measures

  • 8/12/2019 Final Interim Design Presentation

    45/49

    CONCLUSION & NEXT STEPS

  • 8/12/2019 Final Interim Design Presentation

    46/49

    Time Plan

    Mining System Concept (Gantt Project)

  • 8/12/2019 Final Interim Design Presentation

    47/49

    Next Steps

    Further analysis on each section as has been summarised Several minor challenges to overcome

    Still to receive information for certain sections

    Continue to complete analysis and link sections together

    Upon completion of the main elements described theoperability and economic viability of the system can beassessed

    Next major deadline is final report hand-in on May 7th

  • 8/12/2019 Final Interim Design Presentation

    48/49

    Conclusion

    All main elements of project progressing well

    Project has satisfied all aims and objectives thus far

    Currently slightly behind schedule

    Will change after exams

    We have a 2 week contingency built into schedule

    Confident in delivering a high-quality final project in May

  • 8/12/2019 Final Interim Design Presentation

    49/49

    Thank you for listening

    Any Questions?