final year project, iga dan
TRANSCRIPT
-
8/12/2019 Final Year Project, Iga Dan
1/67
-
8/12/2019 Final Year Project, Iga Dan
2/67
-
8/12/2019 Final Year Project, Iga Dan
3/67
FINAL YEAR PROJECT 2011/2012
i | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
DECLARATION
I , IGA DAN, the undersigned do solemnly declare to the best of my knowledge and effort
that I did the final year project and that the work herein this report is entirely mine and hasnever been submitted by anyone to any institution for the award of academic awards. Any errors,
mistakes and omissions and others of that kind are of my personal failure and I welcome any
genuine criticisms
Signature Date ..
-
8/12/2019 Final Year Project, Iga Dan
4/67
FINAL YEAR PROJECT 2011/2012
ii | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
DEDICATION
To my dear mummy, Miss Naluyima Mir iam who has sacrif iced and struggled to bri ng me
thus far ; without her I wouldnt have made it to this great institution.
-
8/12/2019 Final Year Project, Iga Dan
5/67
-
8/12/2019 Final Year Project, Iga Dan
6/67
FINAL YEAR PROJECT 2011/2012
iv | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
TABLE OF CONTENTS
DECLARATION ................................................................................................................................... I
DEDICATION ...................................................................................................................................... II
ACKNOWLEDGEMENTS............................ ......................... .......................... ......................... ..........III
TABLE OF FIGURES: ...................................................................................................................... VII
TABLE OF TABLES: ........................... ......................... .......................... ......................... ................ VIII
ABSTRACT ........................ .......................... .......................... ......................... ........................... ......... IX
CHAPTER 1: INTRODUCTION ................................................................................................... 1
1.1 Background................................................................................................................................................... 1
1.2 Problem statement ....................................................................................................................................... 2
1.3 Main objective .............................................................................................................................................. 2
1.4 Specific objectives ........................................................................................................................................ 2
1.5 Justification .................................................................................................................................................. 3
1.6 Scope of the study ........................................................................................................................................ 4
CHAPTER 2: LITERATURE REVIEW ........................................................................................ 5
2.1 Benefits and selection of surfacing ............................................................................................................... 5
2.2 Low cost surfacing on low-volume roads ...................................................................................................... 5
2.3 Surfacing types available .............................................................................................................................. 6
2.3.1 Fog seal ................................................................................................................................................ 6
2.3.2 Priming ................................................................................................................................................ 62.3.3 Primer seal ........................................................................................................................................... 6
2.3.4 Sand seal .............................................................................................................................................. 7
2.3.5 Surface dressing ................................................................................................................................... 7
2.3.6 Slurry seal ............................................................................................................................................ 7
2.3.7 Otta seal .............................................................................................................................................. 7
2.3.8 Penetration macadam .......................................................................................................................... 8
2.3.9 Premixed gravel macadam/Gravel emulsified mix ............ ............. ............ ............. .............. ............ ..... 8
-
8/12/2019 Final Year Project, Iga Dan
7/67
FINAL YEAR PROJECT 2011/2012
v | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
2.4 Previous studies done about sand seal designs............................................................................................. 8
CHAPTER 3: METHODOLOGY ........................ .......................... ......................... ...................... 10
3.1 Traffic Assessment ...................................................................................................................................... 10
3.1.1 Estimating Traffic Flows ...................................................................................................................... 10
3.1.2 Traffic forecasting .............................................................................................................................. 10
3.1.3 Determination of cumulative equivalent standard axles ..................................................................... 10
3.2 Inventory and general condition ................................................................................................................. 11
3.3 Structural Evaluation .................................................................................................................................. 11
3.4 Rainfall Assessment .................................................................................................................................... 13
3.5 Laboratory tests.......................................................................................................................................... 13
4.0 RESULTS AND ANALYSIS:................................................................................................. 14
4.1 Structural Evaluation .................................................................................................................................. 14
4.1.1 DCP test results .................................................................................................................................. 14
4.1.2 Subgrade classification: ...................................................................................................................... 15
4.2 Traffic Assessment: ..................................................................................................................................... 15
4.2.1 Traffic count results ........................................................................................................................... 15
4.2.2 Cumulative Equivalent Standard Axle Loads ........................................................................................ 17
4.2.3 Traffic classification: ............. ............. ............ ............. ............. ............. .............. ............ ............. ....... 18
4.3 Rainfall Assessment .................................................................................................................................... 184.3.1 Weinert Value .................................................................................................................................... 18
4.4 Laboratory tests.......................................................................................................................................... 19
4.4.1 MDD results: ...................................................................................................................................... 19
Chainage 0+010 ........................................................................................................................................... 19
Chainage 0+110 ........................................................................................................................................... 20
Chainage 0+300:.......................................................................................................................................... 20
4.4.2 Gradation Results:.................................................................................................................................. 21
Chainage 0+010 ........................................................................................................................................... 21
Chainage 0+110 ........................................................................................................................................... 22Chainage 0+300 ........................................................................................................................................... 22
4.4.3 Plasticity Index results: ....................................................................................................................... 23
Chainage 0+010:.......................................................................................................................................... 23
Chainage 0+110 ........................................................................................................................................... 24
Chainage 0+300 ........................................................................................................................................... 25
4.5 Analysis: Layer thickness Design ................................................................................................................. 25
-
8/12/2019 Final Year Project, Iga Dan
8/67
FINAL YEAR PROJECT 2011/2012
vi | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
CHAPTER 5.0 CONCLUSIONS AND RECOMMNEDATIONS ......................... ......................... 26
5.1 Summary .................................................................................................................................................... 26
5.2 Conclusions: ............................................................................................................................................... 26
5.2.1 Inventory of the existing road condition ............................................................................................. 26
5.2.2 Traffic usage of the road:.................................................................................................................... 265.2.3 Subgrade characteristics of the existing road ...................................................................................... 26
5.2.4 The design of the appropriate sand seal ............................................................................................. 27
New Pavement Structure............................................................................................................................. 27
New Pavement Structure............................................................................................................................. 28
Drainage ..................................................................................................................................................... 28
REFERENCES .................................................................................................................................... 29
APPENDICES ......................... ......................... .......................... ......................... ........................... .... 30
Appendix I: DCP Test Data and Results: ........................................................................................................ 30
Layer boundary graphs and CBR graphs ............................................................................................................... 36
Appendix II: Kituza Coffee Research Meteorological Station Data ................................................................ 40
Appendix III Laboratory tests data: .............................................................................................................. 41
Appendix IV: Design Charts............................................................................................................................ 49
Appendix IV: Photographs of the project execution ...................................................................................... 55
-
8/12/2019 Final Year Project, Iga Dan
9/67
FINAL YEAR PROJECT 2011/2012
vii | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
TABLE OF FIGURES:
FIGURE 1DYNAMIC CONE PENETROMETER ............................................................................................................ 12
FIGURE 2SUMMARY OF THE TRAFFIC COUNTS DATA USED TO OBTAIN THE ADT ...................................................... 16
FIGURE 3PROCTOR CURVE FOR CHAINAGE 0+010 .................................................................................................. 19
FIGURE 4PROCTOR CURVE FOR CHAINAGE 0+110 .................................................................................................. 20
FIGURE 5PROCTOR CURVE FOR CHAINAGE 0+300 .................................................................................................. 21
FIGURE 6SIEVE ANALYSIS FOR CHAINAGE 0+010 ................................................................................................... 21
FIGURE 7SIEVE ANALYSIS RESULTS FOR CHAINAGE 0+110 ..................................................................................... 22
FIGURE 8PLASTICITY INDEX RESULTS FOR CHAINAGE 0+010 .................................................................................. 23
FIGURE 9PLASTICITY INDEX RESULTS FOR CHAINAGE 0+110 .................................................................................. 24
FIGURE 10PLASTICITY INDEX RESULTS FOR CHAINAGE 0+300 ................................................................................ 25
FIGURE 11CBRVARIATION WITH THE CHAINAGE ALONG THE ROAD ....................................................................... 26
FIGURE 12DIAGRAMATIC REPRESENTATION OF THE NEW PAVEMENT STRUCTURE.................................................... 27FIGURE 13LAYER BOUNDARIES AND CBRVARIATION FOR CHAINAGE 0+010 .......................................................... 36
FIGURE 14LAYER BOUNDARIES AND CBRVARIATION FOR CHAINAGE 0+110 .......................................................... 36
FIGURE 15BOUNDARIES AND CBRVARIATION FOR CHAINAGE 0+210 ..................................................................... 37
FIGURE 16BOUNDARIES AND CBRVARIATION FOR CHAINAGE 0+300 ..................................................................... 37
FIGURE 17BOUNDARIES AND CBRVARIATION FOR CHAINAGE 0+400 ..................................................................... 38
FIGURE 18BOUNDARIES AND CBRVARIATION FOR CHAINAGE 0+500 ..................................................................... 38
FIGURE 19HISTOGRAM SHOWING THE BASE SBR(%) ............................................................................................ 39
FIGURE 20ASSEMBLING OF THE DCPTEST EQUIPMENT .......................................................................................... 55
FIGURE 21APPLYING BLOWS TO THE SOIL TO GET PENETRATIONS ........................................................................... 55
FIGURE 22RECORDING OF PENTRATIONS ............................................................................................................... 55
FIGURE 23MEASURING OF THE DISTANCES FROM ONE CHAINAGE TO ANOTHER ....................................................... 55
FIGURE 24THE KIRA-KITO ROAD CONDITION......................................................................................................... 55
FIGURE 25RULER USED TO MEASURE THE PENETRATION ........................................................................................ 56
FIGURE 26SAMPLING TO OBTAIN SAMPLES FOR LABORATORY TESTS....................................................................... 56
-
8/12/2019 Final Year Project, Iga Dan
10/67
FINAL YEAR PROJECT 2011/2012
viii | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
TABLE OF TABLES:
TABLE 1RECOMMENDED SPACINGS FOR DCP ........................................................................................................ 11
TABLE 2LABORATORY TESTS CARRIED OUT IN THE PROJECT EXECUTION................................................................. 13
TABLE 3SUMMARY OF THE DCPTEST RESULTS FOR THE DIFFERENT CHAINAGES..................................................... 14
TABLE 4SUBGRADE STRENGTH CLASSIFICATION .................................................................................................... 15
TABLE 5OBTAINING THE CUMULATIVE EQUIVALENT STANDARD AXLES LOADS ON THE ROAD................................. 17
TABLE 6TRAFFIC CLASSIFICATION BASING ON THE RANGE OF ESAS ....................................................................... 18
TABLE 7PROPOSEDNEW PAVEMENT STRUCTURE OF THE ROAD ............................................................................. 27
TABLE 8PROPOSED SURFACING OPTIONS ............................................................................................................... 28
TABLE 9THICKNESS AND REQUIRED CBRVALUES OF THE NEW PAVEMENT STRCUTURE.......................................... 28
TABLE 10UKDCPTEST RESULTS FOR ALL THE CHAINAGES (0+010TO 0+500) ....................................................... 30
TABLE 11MONTHLY EVAPORATION DATA FOR KITUZA COFFEE RESEARCH STATION................................................ 40
TABLE 12MONTHLY MAXIMUM FALL OF RAINFALL FOR KITUZA STATION.............................................................. 40
TABLE 13MONTLY RAINFALL TOTALS OF KITUZA STATION.................................................................................... 40
TABLE 14TEST RESULTS FROM MAXIMUM DRY DENSITY OF THE SOIL FOR CHAINAGE 0+010\ ................................. 41
TABLE 15TEST RESULTS FOR PARTICLE SIZE ANALYSIS TEST (BS1377:PART 2)FOR CHAINAGE 0+010 ................... 43
TABLE 16TEST RESULTS FOR THE MOISTURE-DENSITY RELATIOS FOR CHAINAGE 0+210 ........................................ 44
TABLE 17TEST RESULTS FOR PARTICLE SIZE ANALYSIS TEST (BS1377:PART 2)FOR CHAINAGE 0+210 ................... 46
TABLE 18TEST RESULTS FOR THE MOISTURE-DENSITY RELATIOS OF THE SOIL FOR CHAINAGE 0+300 ............. ......... 47
TABLE 19TEST RESULTS FOR PARTICLE SIZE ANALYSIS TEST (BS1377:PART 2)FOR CHAINAGE 0+300 ................... 48
-
8/12/2019 Final Year Project, Iga Dan
11/67
FINAL YEAR PROJECT 2011/2012
ix | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
ABSTRACT
This report consists of a detailed proposed design of a sand seal for a low volume gravel road
case study being Kira-Kito road which stretches a distance of 1.5km. The main objective was to
design a sand seal. This was done by carrying out an inventory of the existing road condition,
determining the traffic usage of the road and evaluating the sub-grade characteristics of the
existing road.
In-situ field tests such as the DCP test, laboratory tests including; Moisture relations, Particle
size determination, maximum density test and plasticity index tests were some of the methods
that were used to analyse the structural strength and the existing material properties of the soil.
From the traffic counts the cumulative equivalent axles were obtained as 0.502 million ESA thusa traffic class of T2 LV6, the strength was observed to lie mainly from 15 to 29, hence a
subgrade classification of S5. From these results and others such as the maximum evaporation
and maximum rainfall were used to design the sand seal.
-
8/12/2019 Final Year Project, Iga Dan
12/67
FINAL YEAR PROJECT 2011/2012
1 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
CHAPTER 1: INTRODUCTION
1.1 Background
Low-volume rural roads in developing countries are vital to the socio-economic well being of
communities by providing access to schools, clinics, jobs, markets, neighboring communities
and the higher order road network. Therefore, whilst these roads tend to carry relatively low
levels of traffic, they play an important role in contributing to poverty alleviation, social and
economic development and the facilitation of schemes aimed at improving rural livelihoods.
(Done et al TRL, 2001).
Kira-Kito road is a low volume rural road. It is a gravel road, 10 km long located in Kira Town
Council, Wakiso district, Uganda. This road is a low volume national road which is under Kira
Town Council and is very important to Kira town council for access and mobility.
The rural poor in Kira need reliable access for affordable transport or services (both motorized
and non-motorized) such as bicycles, motorcycles, minibuses, buses, cars, whether owned or
hired. Even if a vehicle ride is too expensive for them, they will still depend on the transporters
that bring the medicine and teachers to the village, or carry farm produce to markets. The
challenge is therefore to provide and maintain this rural access for the low traffic currently in
use, on a sustainable basis within the limited resources available.
Many kilometers of this road in become impassable during the wet season cutting many
communities off from access to schools, markets, clinics and job opportunities. In addition, the
cost of operating vehicles on this road during the remainder of the year is disproportionately high
in relation to the service offered. Of equal or greater impact is the unsustainability of replacing
the gravel lost from these roads under environmental and traffic influences.
Using the conventional economic analysis and pavement design techniques, paving of this road
can not be justified. However, when environmental and the social benefits are considered,upgrading of this road carrying traffic as low as 20 vehicles per day to a sand sealed road can be
justified, particularly because large communities are affected.
-
8/12/2019 Final Year Project, Iga Dan
13/67
-
8/12/2019 Final Year Project, Iga Dan
14/67
FINAL YEAR PROJECT 2011/2012
3 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
c) To evaluate the sub-grade characteristics of the existing road
d) To design an appropriate sand seal to accommodate the traffic
1.5 Justification
There are serious constraints to the use of gravel in Kira due to factors relating to material
quality, material availability, climate, terrain, drainage provision and maintenance. There is
overall significant gravel loss and unsuitable deterioration. Thus, it is expected that the use of a
sand sealing would provide appropriate, economical and sustainable alternatives to natural gravel
in this region and the Uganda road sector.
This alternative, involving use of locally available sand may be constructed by small local
enterprises, using low-capital, labour based and light equipment methods. Communities could
also use some of the techniques to improve their own access. Thus the design of a sand seal is
very necessary to pave a way for the application of this sealing alternative.
The sealed surface will have lower maintenance requirements than gravel, not only in terms of
cost but also by reducing the need for imported heavy equipment to transport and compact. In
addition, a number of other strategic issues will be satisfied, which include;
Improved sustainability
Durability in the expected traffic and environmental conditions
Use of locally available materials
Techniques with low capital investment (limited or simple equipment needs) and
manageable by local contractors
Use of local labour and skills
Low volume roads tend to have a greater social and environmental impact as compared to high
volume roads because they connect small towns and rural communities, serve as farm-to-
market/forest-to-market roads, and provide links to parks and recreational areas hence need for
emphasis to be directed to these roads too, which is the reason for considering this project for my
final year.
-
8/12/2019 Final Year Project, Iga Dan
15/67
FINAL YEAR PROJECT 2011/2012
4 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
1.6 Scope of the study
The study was carried out on Kira-Kito road and was limited to the first 600m from Kira Primary
School because of economy and to minimize on the challenge of ambiguity which may be caused
by too much work in a short period of time.
The study involved carrying out a traffic assessment of the area for five consecutive days at the
peak hours from 6 am to 9am, 12pm to 3pm and finally from 5pm to 7pm.
Soil samples were obtained from the road at 100m intervals to a depth of up to 500mm and from
the Right hand side, centerline and left hand side respectively.
This project was limited to design of a sand seal only.
-
8/12/2019 Final Year Project, Iga Dan
16/67
FINAL YEAR PROJECT 2011/2012
5 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
CHAPTER 2: LITERATURE REVIEW
2.0 Introduction:
The literature review includes Include some introductory remarks about this chapter, some kind
of summary of what this chapter is about,
2.1 Benefits and selection of surfacing
The construction of an improved road surface can give a range of benefits. These benefits must
be compared with the costs of providing the surface. The primary benefits include:
Waterproof surface that is durable in both wet and dry weather;
Smoother surface (Sampson, 1995) and uniform appearance;
Decreased rate of deterioration resulting in a reduced maintenance requirement (gravel
typically loses 25 mm per year), (Nicholls and Spon, 1998); and
Increased skid resistance (Millard, 1993; TRL, 2000)
The decision to surface a road with any type of bituminous seal can depend on factors such as
the type and condition of the existing surface and strength of the pavement in relation to the
traffic it carries (Botswana, 1999). The quality and availability of materials also needs to be
consider along with the geometry of the road and the local climate (SABITA, 1992; TRL, 2000;
TRH, 1998).
Financial and economic factors are of course important in assessing whether to apply a surface
treatment to a road (Botswana, 1999). The initial construction cost and subsequent maintenance
costs must be assessed against the expected lifespan of the road and benefits to road users. What
may be thought lesser benefits such as riding quality, safety (from improved surface texture) and
environmental improvements (noise, dust) are no less important when justifying upgrading
unpaved roads and tracks.
Ultimately the local construction and maintenance capability must be considered and the
suitability of the construction technique for labour-based methods.
2.2 Low cost surfacing on low-volume roads
The justification (technical, economic, and environmental) for a surfacing on a road which
carries high levels of traffic is clear. However, there are considerable and growing arguments in
favor of extending the use of surfacings to roads with much lower traffic levels of less than 400
-
8/12/2019 Final Year Project, Iga Dan
17/67
FINAL YEAR PROJECT 2011/2012
6 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
vpd (MELTC, 2011). For simple economic reasons, surfacings applied to low-volume roads will
tend to be low cost, although some cost/benefit analysis will always be useful.
Surfaced roads are particularly effective in reducing environmental damage. They can be used to
prevent dust pollution, particularly in towns and villages (Sampson, 1995, Greening et al, 1999).
They reduce the demand for increasingly scarce gravel materials and even in those areas where
materials are available they improve the environment through decreased borrow pit activity
(Rolt, 1995, Kenya, 1993). They also prevent the sedimentation of fine materials that result from
run-off of rainwater from un-surfaced roads (Sampson, 1995).
Finally, and most importantly, it is extremely important that rural roads provide all weather
access for the local community. In some circumstances the only way to ensure this is to provide
effective drainage and seal the road on, at least, some short sections of the road. If this is not
done then as the road continues to deteriorate it may reach a state where access may be totally
lost (Rolt, 1995).
2.3 Surfacing types available
2.3.1 Fog seal
Fog seals use bitumen emulsions and are used to enrich ageing bituminous surfacing and prevent
chipping loss. The fog seal is usually blinded with a layer of fines to prevent pick up by traffic
(ARRB, 1995; TRL, 2000).
2.3.2 Priming
Normally used prior to placing another surfacing for sealing small cracks and providing
adhesion. Priming waterproofs and reduces dust but lasts only a few weeks. Cut-back bitumens
are normally used but emulsions have been trialed, but the results are not yet known (ARRB,
1995) and morever, cut-back bitumens due to environmental concerns are no longer
recommended for use.
2.3.3 Primer seal
This is similar to a sand seal but is made to less rigorous specifications, is less durable having a
life expectancy of 1-3 years (Overby, 1982). It is normally constructed with a cut-back as the
binder but emulsions can be used in conjunction with small aggregate sizes (5 7mm), in fine
and warm conditions, when it provides good adhesion for the aggregate (ARRB, 1995).
-
8/12/2019 Final Year Project, Iga Dan
18/67
FINAL YEAR PROJECT 2011/2012
7 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
2.3.4 Sand seal
This seal consists of first an optional prime coat (1mm); a bitumen layer (1.5mm, cutback
bitumen, emulsion) followed by a graded sand layer (3-5mm) which must then is compacted.
(Beusch et al, 1997). Performance can be improved if a second seal is applied after 3 months
and is best for traffic levels up to 400 vpd. A life of 4-5 years can be expected (van der Walt,
1979).
2.3.5 Surface dressing
Surface dressing comprises a thin film of bitumen sprayed onto the road surface and then
covered with a layer of stone chippings (Beusch et al, 1997). The thin film of binder acts as a
waterproofing layer preventing the entry of surface water into the road structure. The stone
chippings protect this film of binder from damage by vehicle tyres, and form a durable, skid-
resistant and dust-free wearing surface. It can provide an effective and economical running
surface for newly constructed road pavements. Roads carrying up to 1000 vehicles/lane/day are
successfully surfaced with multiple surface dressings (Overby, 1982).
2.3.6 Slurry seal
Slurry seals are laid cold and are a mixture of fine aggregates, Portland cement filler, bitumen
emulsion and additional water (BSI, 1984) (ASTM, 1990). When freshly mixed they have a thick
creamy consistency and can be spread to a thickness of 5 to 10 mm. They are often used over a
single surface dressing to produce a Cape seal. Slurry mixes are best made and spread by
purpose made machines but can be suitable for labour-based construction (Emery et al, 1994)
(SABITA, 1993) (Zimbabwe, 1998).
2.3.7 Otta seal
An Otta seal consists of a layer of binder followed by a layer of aggregate that is extensively
rolled into the binder using a pneumatic tyred roller or loaded trucks(Overby, 1982). It is
different to surface dressing in that a graded gravel or crushed aggregate containing all sizes,
including filler, is used instead of single sized chippings. It depends for its success on the
mechanism of the binder being squeezed up through the aggregate by the action of the rolling.
Due to the fines in the aggregate, 2 to 3 days of pneumatic-tyred compaction (rollers or traffic) is
required to fully coat all the particles. There is no formal design procedure but recommendations
based on case studies have been published (Overby, 1999).
-
8/12/2019 Final Year Project, Iga Dan
19/67
FINAL YEAR PROJECT 2011/2012
8 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
2.3.8 Penetration macadam
Macadam is a paving technique developed by a Scottish Engineer called John Macadam at the
beginning of the 19 thcentury using broken stones of various sizes combined together and placed
in layers. Various developments of this technique are used today. Penetration macadam consists
of layers of broken or crushed stones of size up to 80mm, interspersed with applications of
heated bitumen to grout and seal the surface. It is laid as a waterproof surface on a previously
prepared roadbase. The effect is to achieve a matrix of keyed stones grouted and sealed with
bitumen to a depth of about 60 80mm. The process requires only a basic bitumen heater-
distributor and an 8-10 tonne deadweight roller. Labour methods can be used to place and spread
the materials. Applications of bitumen are high at 7 9 kg/m. Other types of bitumen surface
can achieve a durable waterproof surface with lower bitumen application rates. Alternative
bitumen emulsion surfaces can avoid the requirement for heating with corresponding safety
benefits.
2.3.9 Premixed gravel macadam/Gravel emulsified mix
Gravel aggregate is mixed with an anionic emulsion either by hand or in a small drum mixer
such as a portable cement mixer with the aggregate gravel specification the same as an Otta seal
(Balmaceda&Horak, 1997). After mixing, the material is spread on a primed road base and rolled
in the same way as an Otta seal. The surfacing is comparable to an Otta seal.
2.4 Previous studies done about sand seal designs
MELTC (Uganda) in conjunction with DANIDA under consultancy of TRL and PROME were
the first to carry out studies about Sand seals and work include; Development of training
modules, conducting training and establishment of demonstration sites for low-cost sealing of
roads in Uganda. The project entailed the following activities:
Prepare a training curriculum and training materials covering materials investigation,
appropriate design options for pavements and low-cost structures for labour-based sealed
roads, sealing procedures and techniques, site safety, maintenance of labour-based sealed
roads and any other information as the consultant may deem necessary for achieving the
training objectives;
Train trainers at MELTC,
-
8/12/2019 Final Year Project, Iga Dan
20/67
FINAL YEAR PROJECT 2011/2012
9 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Develop the necessary technical documentation (manuals) for use by local practitioners
including tender documents,
Develop quality control measures for the low-cost sealing of roads.
This study project is different from the work done under MELTC because it is aimed at
designing a sand seal for Kira-Kito road putting into consideration the local, topographical and
environmental conditions in Wakiso and will put into account the local available materials in or
near Mukono.
The Institutional Cooperation between Roads Department, Ministry of Works, Kenya and
Norwegian Road Research Laboratory (NRRL) carried out an appraisal study in Kenya on the
Low-cost Pavement which started in 1982, which was carried out by the Norwegian Road
Research Laboratory (NRRL) and Materials Branch of Ministry of Public Works. The initial
contracts for the project were in 1980 between the Ministry of Works, NRRL and the Norwegian
Agency for Development NORAD. The main objective of the Low-cost Pavement was to
provide specification for construction materials to be utilized on the low volume roads in the
regions without too good quality materials. It was intended that by utilizing local materials the
project would achieve road pavements (Sand seal inclusive) with both acceptable life expectancy
and reasonable maintenance costs. The construction of the trial section started in June 1983 on
the arrival of the first project co-coordinator. Preliminary investigations consisted of gravel and
hard stone surveys together with digging of test trenches. From August 1983 to August 1985 a
total of 16 trail sections were constructed. An additional 6 sections were located adjacent to the
already constructed sections in Kenya.
-
8/12/2019 Final Year Project, Iga Dan
21/67
FINAL YEAR PROJECT 2011/2012
10 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
CHAPTER 3: METHODOLOGY
Include a summary of what this chapter is about
3.1 Traffic Assessment
3.1.1 Estimating Traffic Flows
A 5-day classified traffic count was carried out along the road with the counts distinguishing
between vehicle categories basing on the MoWT road design manual which stipulates a period of
seven days; reason for carrying out only five days was because of consistency of results and
constraints in facilitation. The counts of the traffic were carried out in both directions and the
different vehicle categories included:
Non motorised traffic which included people (Children, adults)
Cars, including passenger cars, vans, minibuses taxis, pick-ups, 4WD vehicles
Buses, including medium and large buses above 24 passenger seats
Light trucks, including small and medium sized trucks with 2 axles.
Medium trucks, including larger trucks with 3 or 4 axles.
Heavy trucks, including trucks with more than 4 axles and articulated trucks
3.1.2 Traffic forecasting
In order to estimate the traffic that will use the road over its design life, a growth rate was
projected basing on Ministry of Works Manual and basing on the value of 4.5% per annum used
by MELTC in designing for low cost sealing options.
3.1.3 Determination of cumulative equivalent standard axles
In order to determine the cumulative equivalent standard axles over the design life of the road,
the following procedure was followed:
i. The daily traffic flow was determined for each class of vehicle weighed using the results
of the traffic survey.
ii. The average daily traffic flow for each class of vehicle was then obtained also.
-
8/12/2019 Final Year Project, Iga Dan
22/67
FINAL YEAR PROJECT 2011/2012
11 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
iii. A forecast of the traffic flow for each class of vehicle was made so as to determine the
total traffic in each class that will travel over the road during the design life
iv. The mean equivalence factors of each class of vehicle were determined from the results
of an axle load survey.
v.
The products of the cumulative traffic flows for each class of vehicle over the design life
of the road and the mean equivalence factor for that class were then calculated and added
together to give the cumulative equivalent standard axle loading for each direction.
3.2 Inventory and general condition
Moving along the existing road, geometric data, shoulder condition data, side drain data,
and carriageway surface condition data was observed to be in a relatively good condition
since the road had just been regraveled and a few defects were observed which basically
constituted;
o Potholes,
o Oversize material,
3.3 Structural Evaluation
The structural assessment was carried out in situ by use of a dynamic cone penetrometer
(DCP) shown in figure 1 below. The spacing for carrying out the DCP test along the roadwas taken as 100m for the entire length of section of 500m because the section my
project is concentrating on is the first 100m thus wasnt necessary to carry out structural
assessment on the entire section.
The procedure of carrying out the DCP test was as per Dynamic Cone Penetrometer tests
and analysis, (Colin Jones, 2007)
The recommended spacings for conducting DCP tests are shown in Error! Reference
source not found.below.
Table 1 Recommended spacings for DCP
Objective Minimum Test Spacing
Routine testing for the rehabilitation of paved roads 500m or less
Areas of distress on paved roads 100m or less
-
8/12/2019 Final Year Project, Iga Dan
23/67
FINAL YEAR PROJECT 2011/2012
12 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Upgrading of gravel roads to sealed roads 500m or less
Design of spot improvements 50m or less
Adopted from TRL Project Report Number: PR/INT/277/04
Figure 1 Dynamic Cone Penetrometer
-
8/12/2019 Final Year Project, Iga Dan
24/67
FINAL YEAR PROJECT 2011/2012
13 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
3.4 Rainfall Assessment
Annual rainfall estimates and the maximum evaporation data was obtained from Meteorological
Department, Ministry of land, water and environment and are shown in chapter 4.
3.5 Laboratory tests
Sampling was carried out concurrently as the DCP test was being carried out and approximately
35 kg were taken per point. This was to make sure that the material was enough to carry out the
necessary tests.
In the laboratory samples of the base material and the subgrade material were be tested for the
tests indicated in the laboratory except the California Bearing ratio because of many reasons
including:
DCP test gave us consistent values for the CBR and thus it was satisfactory to rely on
those results hence not very necessary to carry out the laboratory CBR
Lack of enough resources especially time as many tests were to be carried out and yet
CBR moulds were not easily accessible
The tests which were carried out included the following the procedures indicated in the British
Standards indicated and are summarised in Table 2.
Table 2 Laboratory tests carried out in the project execution
Laboratory Tests Standard
Compaction test BS 1377: Part 4: 1990
Moisture Content BS 1377: Part 2: 1990
Atterbergs Limits BS 1377: Part 2: 1990
Particle Size Distribution BS 1377: Part 2: 1990
-
8/12/2019 Final Year Project, Iga Dan
25/67
FINAL YEAR PROJECT 2011/2012
14 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
4.0 RESULTS AND ANALYSIS:
4.1 Structural Evaluation
4.1.1 DCP test results
The detailed test data obtained while carrying out the DCP test is shown in the Appendix 1 andthe test results can be summarised in the table 3 below obtained from the layer boundary and
CBR graphs in the Appendix 1
Table 3 Summary of the DCP test results for the different chainages
Chainage 0+010
No. CBR (%) Thickness(mm) Depth (mm) Position Strength coeff.
1 31 432 432 Base 0.07
2 8 139 571 Sub-base 0.06
3 22 127 698 Subgrade
Chainage 0+110
No. CBR (%) Thickness(mm) Depth (mm) Position Strength coeff.
1 120 554 554 Base 0.14
2 45 134 688 Sub-base 0.11
3 24 231 919 Subgrade
Chainage 0+210
No. CBR (%) Thickness(mm) Depth (mm) Position Strength coeff.
1 87 329 329 Base 0.13
2 13 117 446 Sub-base 0.08
3 19 353 799 Subgrade
Chainage 0+300
No. CBR (%) Thickness(mm) Depth (mm) Position Strength coeff.
1 68 364 364 Base 0.12
2 10 120 484 Sub-base 0.07
3 20 320 804 Subgrade
Chainage 0+400No. CBR (%) Thickness(mm) Depth (mm) Position Strength coeff.
1 96 313 313 Base 0.14
2 26 217 530 Sub-base 0.1
3 20 268 798 Subgrade
Chainage 0+500
-
8/12/2019 Final Year Project, Iga Dan
26/67
FINAL YEAR PROJECT 2011/2012
15 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
No. CBR (%) Thickness(mm) Depth (mm) Position Strength coeff.
1 59 226 226 Base 0.11
2 37 344 570 Sub-base 0.1
3 29 241 811 Subgrade
4.1.2 Subgrade classification:
From the results of the DCP tests as analysed using the UKDCP software above, it was
established that the Subgrade strength class of the road was mainly lying from 15 to 29 thus the
subgrade class of the road from the specification given in the TRL road note 31 shown in the
table 4 below is S5.
Table 4 Subgrade strength classification
(MoWT Road Design Manual, 2010)
4.2 Traffic Assessment:
4.2.1 Traffic count results
The traffic counts were carried out for five consecutive days as shown in the traffic count sheets
appended to the document in appendix VI. The data was analysed as shown in the figure 2
below to obtain the Average Daily Traffic (ADT) indicated in the last column as the Mean per
day.
-
8/12/2019 Final Year Project, Iga Dan
27/67
FINAL YEAR PROJECT 2011/2012
16 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Figure 2 Summary of the traffic counts data used to obtain the ADT
6-9am 12-3pm 5-8pm
Mean
per
3hrs
mean
per
12hrs
6-9am 12-3pm 5-8pmMean
per 3hrs
mean
per
12hrs
6-9a m 1 2-3p m 5 -8p m
Mean
per
3hrs
mean
per 12hrs6-9am 2-3pm5-8pm
Mean
per
3hrs
mean
per
12hrs
6-9am 12-3pm 5-8pm
Mean
per
3hrs
mean
per
12hrs
Total mean per
12 hrs for 5 days
Pedestrians 218 91 175 161 645 255 101 173 176 705 223 105 200 176 704 193 132 202 176 703 122 124 134 127 507 3264
Bicycles 17 10 20 16 63 11 12 13 12 48 6 9 6 7 28 11 3 11 8 33 6 4 4 5 19 191
Motorcycles 133 107 156 132 528 130 98 172 133 533 152 112 140 135 539 174 127 211 171 683 132 143 121 132 528 2811
Saloon cars and taxis 42 33 43 39 157 37 42 39 39 157 39 37 41 39 156 51 31 56 46 184 23 42 21 29 115 769
Light Goods Vans:
(Pickups, 4WD)61 41 49 50 201 71 43 50 55 219 63 62 51 59 235 54 46 63 54 217 41 39 26 35 141 1013
Small Bus: Minibuses and
Matatus16 8 10 11 45 14 11 6 10 41 7 12 5 8 32 4 13 6 8 31 2 2 0 1 5 155
Medium Bus: Coasters 3 0 1 1 5 2 0 2 1 5 2 0 4 2 8 2 0 4 2 8 0 0 0 0 0 27
Buses
Light Single Unit Trucks:
Dynas and tractors5 18 4 9 36 3 14 7 8 32 7 21 3 10 41 5 11 10 9 35 11 13 16 13 53 197
Medium-Large Single Unit
Trucks: Lorries, fusos0 6 2 3 11 0 3 0 1 4 0 2 0 1 3 0 5 0 2 7 0 0 0 0 0 24
3 Hour Total 495 314 460 423 1692 523 324 462 436.3 1745 499 360 450 436.3 1745 494 368 563 475 1900 337 367 322 342 1368 8451
Vehicle Class
Traffic Tallying Form
Area/Town: Kira Town Council
Location: Kira Primary School 0+010
COUN
Project: Design of a sand seal for a low volume gravel road
Road: Kira-Kito Road
Name: IGA DAN 08/U/481
Tuesday Wednesday Thursday Friday Saturday
-
8/12/2019 Final Year Project, Iga Dan
28/67
FINAL YEAR PROJECT 2011/2012
17 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
4.2.2 Cumulative Equivalent Standard Axle Loads
Table 5 obtaining the Cumulative Equivalent Standard axles loads on the road
Vehicle Class Axles Load/ kg
EALF(Axles/8160)
Numberper day
ESAL
Pedestrians 653Bicycles 38
Motorcycles 562
Saloon cars and taxis 1000 0.1225 154 19
Light Goods Vans:
(Pickups, 4WD)
2000 0.2451 203 50
Small Bus: Minibuses and
Matatus
3000 0.3676 31 11
Medium Bus: Coasters 4500 0.5515 5 3
Light Single Unit Trucks:Dynas and tractors 4000 0.4902 39 19
Medium-Large Single Unit
Trucks: Lorries, fusos
7500 0.9191 5 4
Buses 10000 1.2255 0
TOTAL 107
CESAL = ESAL 365 100R
1 + R100
x+y 1 + R100
yWhere
A= Total ESA / day
R= Traffic growth rate which is taken as 4.5% per annum
x= design life in years taken as 5 years
y= number of years before start of design life
= 107 365 1004.5
1 + 4.5100
10+1 1 + 4.5100
1= 501,512
CESAL= 0.502 MESAs
-
8/12/2019 Final Year Project, Iga Dan
29/67
FINAL YEAR PROJECT 2011/2012
18 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Thence the Cumulative Equivalent Standard Axle Loads applied on the road is 0.502 Million
ESAs
4.2.3 Traffic classification:
From the TRL road note 31, the traffic class is obtained depending on the number of Equivalent
Standard Axles as can be shown in the table 6 below
Table 6 Traffic classification basing on the range of ESAs
(MoWT Road Design Manual, 2010)
The traffic classification of the road is LV6 T2 as the CESALs is 501,512 ESA
4.3 Rainfall Assessment
Annual rainfall estimates and maximum evaporation data obtained from the Meteorological
Department is indicated in appendix II and the maximum evaporation in the hottest month was
found as 180mm and the average annual rainfall over the last five years was found as 1387.4mm.
4.3.1 Weinert Value
This value is computed from the equation below;
= 12 (MELTC, 2011)Where Ey is the evaporation in the hottest month of the year; in mm which
according to the Kituuza Meteorological centre data is found to be 180mm
and
Pais the annual precipitation; in mm which is 1387.4 mm
-
8/12/2019 Final Year Project, Iga Dan
30/67
FINAL YEAR PROJECT 2011/2012
19 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
= 12 1801387.4
= 1.56
Thus the Weinert number is less than 4.
4.4 Laboratory testsThe laboratory results obtained from the testing of samples obtained from the road to ascertain if
the current material is suitable for re-use or modification or has to be removed entirely from the
road and new material imported is shown in the appendix III.
Three samples were obtained and thoroughly tested for the tests indicated in the methodology
and they are all indicated in the appendix III
4.4.1 MDD results:
Chainage 0+010
Figure 3 Proctor curve for chainage 0+010
Max. Dry Density (MDD) = 1,775 Kg/m3
Optimum Moisture Content (OMC) = 13.6 %
1700
1710
1720
1730
1740
1750
1760
1770
1780
9 10 11 12 13 14 15
DryDensity(Kg/
m3)
Moisture Content %
Proctor Curve
Series1
-
8/12/2019 Final Year Project, Iga Dan
31/67
FINAL YEAR PROJECT 2011/2012
20 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Chainage 0+110
Figure 4 Proctor curve for chainage 0+110
Max. Dry Density (MDD) = 1,704 Kg/m3
Optimum Moisture Content (OMC) = 12.1%
Chainage 0+300:
Max. Dry Density (MDD) = 1,660 Kg/m3
Optimum Moisture Content OMC = 12.3%
1,500
1,520
1,540
1,560
1,580
1,600
1,620
1,640
1,660
1,6801,700
1,720
9.0 10.0 11.0 12.0 13.0 14.0 15.0
DryDensity(Kg/m3)
Moisture Content %
Proctor Curve
Series1
-
8/12/2019 Final Year Project, Iga Dan
32/67
FINAL YEAR PROJECT 2011/2012
21 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Figure 5 Proctor curve for Chainage 0+300
4.4.2 Gradation Results:
Chainage 0+010
Figure 6 Sieve analysis for chainage 0+010
1,560
1,570
1,580
1,590
1,600
1,610
1,620
1,630
1,640
1,650
1,660
1,670
9.0 10.0 11.0 12.0 13.0 14.0 15.0
AxisTitle
Axis Title
Proctor Curve
Series1
0.0
20.0
40.0
60.0
80.0
100.0
120.0
0.010 0.100 1.000 10.000
Percentagepassing
Diameter of particles (mm)
Sieve analysis graph for chainage 0+010
-
8/12/2019 Final Year Project, Iga Dan
33/67
FINAL YEAR PROJECT 2011/2012
22 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Chainage 0+110
Figure 7 Sieve analysis results for chainage 0+110
Chainage 0+300
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
100.0
0.010 0.100 1.000 10.000
PercentagePassing%
Diameter of particles (mm)
Sieve Analysis graph for sample from chainage 0+110
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
100.0
0.010 0.100 1.000 10.000
Passing%
Diameter (mm)
Sieve analysis graph for chainage 0+300
-
8/12/2019 Final Year Project, Iga Dan
34/67
FINAL YEAR PROJECT 2011/2012
23 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
4.4.3 Plasticity Index results:
Chainage 0+010:
Figure 8 Plasticity Index results for chainage 0+010
RESULTS
Liquid Limit ( LL ) = 48.5%
Plastic Limit ( PL ) = 34.6%
Plasticity Index ( PI=LL-PL ) = 13.9%
44.0
45.0
46.0
47.0
48.0
49.0
50.0
51.0
52.0
53.0
0 10 20 30 40 50
Moisturecontent
Number of blows
-
8/12/2019 Final Year Project, Iga Dan
35/67
FINAL YEAR PROJECT 2011/2012
24 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Chainage 0+110
Figure 9 Plasticity index results for chainage 0+110
RESULTS
Liquid Limit ( LL ) = 44.3%
Plastic Limit ( PL ) = 30.6%
Plasticity Index ( PI=LL-PL ) = 13.7%
42.5
43.0
43.5
44.0
44.5
45.0
45.5
46.0
0 10 20 30 40 50
Moisturecontent
Number of blows
-
8/12/2019 Final Year Project, Iga Dan
36/67
FINAL YEAR PROJECT 2011/2012
25 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Chainage 0+300
Figure 10 Plasticity index results for chainage 0+300
RESULTS
Liquid Limit ( LL ) = 33.4%
Plastic Limit ( PL ) = 21.0%
Plasticity Index ( PI=LL-PL ) = 12.4%
4.5 Analysis: Layer thickness Design
Basing on the following results obtained in from the tests carried out above the base following
design parameters were obtained;
The range of the Weinert value is less than 4,
The design cumulative equivalent standard axle loads (CESALs) was obtained as 0.502
MESAsthus traffic class of LV6 T2
The subgrade CBR was obtained in the range of 15-29.
30.0
31.0
32.0
33.0
34.0
35.0
36.0
37.0
38.0
0 10 20 30 40 50
Moisturecontent
Number of blows
-
8/12/2019 Final Year Project, Iga Dan
37/67
FINAL YEAR PROJECT 2011/2012
26 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
CHAPTER 5.0 CONCLUSIONS AND RECOMMNEDATIONS
5.1 Summary
This chapter has put into consideration the tests carried out and the results obtained the with the
aid of design manuals and specifications, it has given the design suitable for this road of a sand
seal as can be shown below;
5.2 Conclusions:
5.2.1 Inventory of the existing road condition
The general condition of the road was in a very good condition thus in case of carrying out the
sand seal, there will be need of slight reshaping.
5.2.2 Traffic usage of the road:
From the traffic flow analysis the traffic class of the road obtained in the results section is T2 isLow Volume LV6 hence LV6 T2 as the CESALs is 501,512 ESA
5.2.3 Subgrade characteristics of the existing road
The in-situ CBR values of the subgrade are generally good. If in-situ CBR values obtained from
the DCP tests exceed 10% then the road foundation should be strong enough to carry traffic load
on low volume roads. Hence the fact that the CBR values are in the range of 15-29 then subgrade
is adequate and design Subgrade strength class S5. Below is figure 11 which shows the variation
of CBR for the subgrade and base;
.
Figure 11 CBR variation with the chainage along the road
0
20
40
60
80
100
120
140
0 100 200 300 400 500 600
CBR(%)
Chainage (m)
CBR values for DCP test
Subgrade
Base
Linear (Subgrade)
Linear (Base)
-
8/12/2019 Final Year Project, Iga Dan
38/67
FINAL YEAR PROJECT 2011/2012
27 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
The CBR values for the base layer are of concern because, on low volume roads, the minimum
allowable soaked CBR is 40%. The results show that the in-situ CBR values obtained average
approximately 78% which is significantly higher than the minimum required soaked CBR; where
the values are very low such as at chainage 0+010 being 40 there is need for strengthening and
some modification may be necessary to improve the material characteristics.
5.2.4 The design of the appropriate sand seal
New Pavement Structure
Given the above traffic, Weinert number, subgrade and sub-base CBRs and using the design
chart in appendix III for N
-
8/12/2019 Final Year Project, Iga Dan
39/67
FINAL YEAR PROJECT 2011/2012
28 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
From the laboratory tests, the material used for the construction of the Base and sub-base gives
desired properties of MDD, plasticity Index and gradation thus there is no need to import
material and in cases of shortage the borrow pits where the material was initially obtained can be
used to obtain more gravel material.
The proposed surfacing is as shown in the table 8 below:
Table 8 Proposed surfacing options
Material Surfacing Binder to be used
Quarry fines from
Kira Town Council
Sand Seal with Quarry fines Bitumen EmulsionK1-60 (80-100 Pen Base Bitumen)
River Sand Sand Seal Bitumen EmulsionK1-60 (80-100 Pen Base Bitumen)
New Pavement Structure
Given the above traffic, Weinert number, subgrade and sub-base CBRs and using the design
chart in appendix III for N
-
8/12/2019 Final Year Project, Iga Dan
40/67
FINAL YEAR PROJECT 2011/2012
29 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
REFERENCES
Archondo-Callao, R.S. (1999). Paving of Unpaved Roads. Economically - Justified Paving Cost.
Infrastructure
BEUSCH A, HARTMANN P, PETTS R C, WINKELMANN P, (1997). Low cost road
construction in Indonesia - Labor-Based Road Projects in Manggaria District.
GIUMMARRA G (2001). Road Classifications, Geometric Designs and Maintenance Standards
for Low Volume Roads. Research Report AR354, ARRB Transport Research Ltd,
Vermont South, Victoria.
Guidelines for the Geometric Design of Very Low Volume Local Roads (ADT
-
8/12/2019 Final Year Project, Iga Dan
41/67
FINAL YEAR PROJECT 2011/2012
30 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
APPENDICES
Appendix I: DCP Test Data and Results:
DCP test Data:
Table 10 UK DCP test results for all the chainages (0+010 to 0+500)
UK DCP Test Data SheetProject name Design of a Sand Seal for a Low Volume gravel Road; Case study: Kira-Kito Road
Test number 1 2 3
Chainage (km) 10 110 200
Location Carriageway Shoulder Carriageway
Lane number 0 0
Offset (m) 0 0 0
Direction
Zero error (mm) 11 11 11
Test date 17/04/2012 17/04/2012 17/04/2012
Remarks Left hand side Right hand side Centreline
Layers removed 0 0 0
Surface type Unpaved Unpaved UnpavedSurface moisture Dry Dry Dry
Surface thickness (mm)
Surface condition
Surface strength
coefficient
Base thickness (mm)
Base condition
Blows Depth (mm) Blows Depth
(mm)
Blows Depth
(mm)
-
8/12/2019 Final Year Project, Iga Dan
42/67
FINAL YEAR PROJECT 2011/2012
31 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
0 32 0 25 0 17
1 42 2 37 1 28
2 47 2 42 1 34
2 56 2 46 2 41
2 63 3 52 2 46
3 75 3 55 3 50
3 86 5 65 5 58
3 97 5 76 5 63
3 110 5 90 5 69
3 120 5 105 5 80
3 134 5 110 5 93
3 147 5 135 5 110
3 158 5 150 5 124
3 172 5 163 3 135
3 185 5 175 3 145
3 198 5 186 3 153
3 212 5 199 3 160
3 226 5 215 3 169
3 241 5 243 3 175
3 260 2 264 3 181
3 282 2 278 3 189
2 303 2 290 3 195
2 328 2 300 3 205
2 345 2 310 3 213
2 359 2 320 3 222
2 371 3 334 3 234
2 384 3 343 3 248
2 399 3 350 3 267
2 412 3 356 2 280
2 426 3 360 2 294
-
8/12/2019 Final Year Project, Iga Dan
43/67
FINAL YEAR PROJECT 2011/2012
32 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
2 443 3 364 2 308
2 465 5 370 2 324
1 490 5 373 2 340
1 526 5 377 2 360
1 566 7 380 1 386
1 582 7 382 1 419
1 590 10 389 1 442
2 604 10 397 1 457
2 615 10 406 1 470
2 626 10 424 1 485
2 634 10 443 1 495
2 645 10 465 1 507
2 654 10 487 1 520
2 663 10 520 1 530
2 672 5 540 1 542
2 680 5 565 1 555
2 690 3 583 1 569
2 699 2 595 1 584
2 709 2 607 1 600
2 619 1 615
3 635 1 630
3 655 1 645
2 666 1 660
2 679 1 674
2 689 1 690
2 699 1 704
2 710 1 718
2 721 1 729
2 730 1 742
2 740 1 755
-
8/12/2019 Final Year Project, Iga Dan
44/67
FINAL YEAR PROJECT 2011/2012
33 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
2 750 1 768
2 760 1 783
2 769 1 795
2 779 1 810
UK DCP Test Data Sheet
Project name Design of a Sand Seal for a Low Volume gravel Road; Case study: Kira-Kito Road
Test number 4 5 6
Chainage (km) 300 400 500
Location Carriageway Shoulder Carriageway
Lane number 0 0
Offset (m) 0 0 0
Direction
Zero error (mm) 11 11 11
Test date (dd/mm/yyyy) 17/04/2012 17/04/2012 17/04/2012
Remarks Left hand side Right hand side Centreline
Layers removed 0 0 0
Surface type Unpaved Unpaved Unpaved
Surface moisture Very Dry Dry Moderate
Surface thickness (mm)
Surface condition
Surface strengthcoefficient
Base type
Base thickness (mm)
Base condition
Blows Depth (mm) Blows Depth (mm) Blows Depth (mm)
0 15 0 11 0 22
2 26 2 20 2 36
2 34 2 26 2 45
2 42 2 34 2 55
-
8/12/2019 Final Year Project, Iga Dan
45/67
FINAL YEAR PROJECT 2011/2012
34 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
2 51 2 40 2 61
2 58 3 45 2 69
2 67 5 51 2 75
2 72 5 55 2 84
3 80 10 68 2 92
3 89 10 81 2 102
3 96 10 101 2 111
3 105 10 127 2 120
3 113 7 150 2 130
3 121 7 166 2 140
3 130 7 186 2 147
3 140 7 217 2 156
3 150 5 242 2 165
3 158 3 259 2 175
3 167 3 280 2 185
3 176 2 295 2 194
3 186 2 308 2 205
3 197 2 324 2 214
3 211 2 343 2 225
3 223 1 352 2 237
3 245 1 373 2 253
3 260 1 384 2 265
3 272 1 395 2 279
3 286 1 406 2 295
3 302 1 419 2 309
3 319 1 430 2 324
3 337 1 440 2 340
3 358 1 440 2 355
2 375 1 450 2 373
1 402 1 460 2 390
-
8/12/2019 Final Year Project, Iga Dan
46/67
FINAL YEAR PROJECT 2011/2012
35 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
1 445 1 470 2 405
1 465 1 480 2 423
1 480 1 490 2 438
1 495 1 500 2 454
1 509 1 510 2 470
1 523 1 520 1 475
1 538 1 530 1 482
1 550 1 541 1 488
1 564 1 554 1 495
1 576 1 569 1 502
1 590 1 580 1 510
1 603 1 594 1 515
1 615 1 608 1 523
1 627 1 620 1 523
1 639 1 633 1 530
1 652 1 647 1 537
1 665 1 662 2 552
1 675 1 675 2 568
1 689 1 690 2 581
1 702 1 703 2 600
1 715 1 715 2 618
1 725 1 725 2 635
1 725 1 739 2 654
1 740 1 750 2 670
1 755 1 762 2 689
1 769 1 774 2 707
1 785 1 785 2 729
1 800 1 796 2 729
1 815 1 809 2 751
2 774
-
8/12/2019 Final Year Project, Iga Dan
47/67
FINAL YEAR PROJECT 2011/2012
36 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Layer boundary graphs and CBR graphs
Chainage 0+010:
Figure 13 Layer boundaries and CBR variation for chainage 0+010
Chainage 0+110:
Figure 14 Layer boundaries and CBR variation for chainage 0+110
-
8/12/2019 Final Year Project, Iga Dan
48/67
FINAL YEAR PROJECT 2011/2012
37 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Chainage 0+210:
Figure 15 boundaries and CBR variation for chainage 0+210
Chainage 0+300:
Figure 16 boundaries and CBR variation for chainage 0+300
-
8/12/2019 Final Year Project, Iga Dan
49/67
FINAL YEAR PROJECT 2011/2012
38 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Chainage 0+400:
Figure 17 boundaries and CBR variation for chainage 0+400
Chain age 0+500:
Figure 18boundaries and CBR variation for chainage 0+500
-
8/12/2019 Final Year Project, Iga Dan
50/67
FINAL YEAR PROJECT 2011/2012
39 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Histogram to indicate the Base CBR
Figure 19 Histogram showing the base SBR (%)
-
8/12/2019 Final Year Project, Iga Dan
51/67
FINAL YEAR PROJECT 2011/2012
40 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Appendix II: Kituza Coffee Research Meteorological Station Data
Long Term M ean (LTM ) Monthly Evaporation (mm) (PAN TYPE ....A........)
Table 11 Monthly evaporation data for Kituza coffee research station
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Mean 138 122 147 122 120 110 100 105 124 134 122 128
Highest 163 144 169 138 140 129 115 134 154 180 139 175
Lowest 87 101 124 113 107 94 76 78 95 104 111 97
Monthly Maximum Fall of Rainfall (mm)
Table 12 Monthly Maximum fall of rainfall for Kituza Station
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2007 24.0 17.0 29.5 31.0 30.3 45.0 16.5 26.2 55.5 54.0 37.0 30.5
2008 91.0 14.0 38.0 93.0 30.2 20.0 13.8 14.3 21.2 35.0 22.0 6.5
2009 19.0 25.0 16.0 34.0 37.0 12.0 19.0 38.0 32.5 58.0 53.2 31.5
2010 22.5 95.0 60.0 63.0 20.0 22.0 28.5 20.5 62.5 31.0 45.0 40.5
2011 15.0 16.0 35.0 30.4 25.5 7.8 18.0 54.0 29.5 30.6 58.0 68.0
Monthly Rainfall Totals (mm)
Table 13 Montly Rainfall totals of Kituza station
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2007 133.3 64.2 69.5 140.8 106.3 119.0 82.3 81.1 234.0 157.8 151.5 48.0
2008 154.4 47.2 191.9 348.2 103.3 33.3 39.1 43.7 83.4 184.8 82.4 17.3
2009 34.1 73.8 26.0 204.8 157.0 35.0 34.1 124.8 96.8 232.1 232.4 126.2
2010 51.5 273.3 258.5 191.1 104.5 70.8 47.8 48.4 118.1 110.2 111.2 110.2
2011 22.2 24.2 161.9 137.7 90.1 14.8 21.7 135.7 142.8 102.8 289.3 204.3
-
8/12/2019 Final Year Project, Iga Dan
52/67
FINAL YEAR PROJECT 2011/2012
41 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Appendix III Laboratory tests data:
Table 14 Test results from Maximum Dry Density of the soil for chainage 0+010\
DESIGN OF A SAND SEAL FOR A LOW VOLUME GRAVEL ROAD
Project Road: Kira-Kito Road
DATA SHEET FOR MOISTURE - DENSITY RELATIONS OF SOILS
USING 4.54 KG. RAMMER ( OMC & MDD TEST ) As per BS 1377:Part 4
Sample No: 1 Sampling Date: 17 -04-12
Source/Location of Sample: Kira Kito Testing Date: 25 -04-12
Km 0+100 LHS
Sample Description : Red Gravel Material Technician: Iga Dan
Proposed Use: Wearing C
Mass of mould (g): 5,120 Volume (cm3): 2,299
Specimen Number/Mould No. 1 2 3 4 5
Mass of mould+base+compacted specimen ( m2 ) 9,480 9,640 9,758 9,730 9,680
Mass of mould + base (m1) 5,120 5,120 5,120 5,120 5,120
Mass of compacted specimen(m2-m1) 4,360 4,520 4,638 4,610 4,560
Bulk Density = (m2-m1) x mould factor 1.896 1.966 2.017 2.005 1.983
Moisture content container No
Weight of wet soil + container m1 153.40 154.10 206.00 166.33 132.15 147.11 190.80 128.96 190.42 129.98
-
8/12/2019 Final Year Project, Iga Dan
53/67
FINAL YEAR PROJECT 2011/2012
42 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Weight of dry soil + container m2 143.81 142.24 187.23 150.97 119.96 133.11 169.90 117.00 169.90 117.00
Mass of container m3 30.39 30.99 31.42 30.71 30.74 30.71 30.56 29.00 30.56 29.00
Weight of water (m1-m2) 9.6 11.9 18.8 15.4 12.2 14.0 20.9 12.0 20.5 13.0
Weight of dry sample (m2-m3) 113.4 111.3 155.8 120.3 89.2 102.4 139.3 88.0 139.3 88.0
8.5 10.7 12.0 12.8 13.7 13.7 15.0 13.6 14.7 14.8
Moisture content w (m1-m2)/(m2-m3) x 100 9.6 12.4 13.7 14.3 14.7
Dry density = (100x bulk density)/(100+w) kg/m3 1,731 1,749 1,775 1,754 1,729
-
8/12/2019 Final Year Project, Iga Dan
54/67
FINAL YEAR PROJECT 2011/2012
43 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Table 15 Test results for Particle size analysis test (BS 1377: Part 2) for chainage 0+010
DESIGN OF A SAND SEAL FOR A LOW VOLUME GRAVEL ROAD
PROJECT: Kira-Kito Road
PARTICLE SIZE ANALYSIS (BS 1377:Part 2)
Sample reference :1 Sampling Date: 17
-04-
12
Location Kira Kito Testing Date: 25
-04-
12
Km 0+100 LHS
Sample Description Red Gravel Material
Initial wt before washing : Moisture Content :
Dry wt after washing : Initial Dry Weight 1300
Grading Modulus = 2.02
Diameter Partial Cumulative Cumulative % Passing Grading Limits
Retained Retained Retained
(mm) Mass(g) Mass (g) (%) (%) (%)
50.000 0.00 0.0 0.0 100.0
37.500 0.00 0.0 0.0 100.0
20.000 96.98 97.0 7.5 92.5
10.000 24.85 121.8 9.4 90.6
5.000 59.10 180.9 13.9 86.1
2.360 247.12 428.1 32.9 67.1
1.180 227.07 655.1 50.4 49.6
0.500 286.22 941.3 72.4 27.6
0.425 49.91 991.3 76.3 23.8
0.300 92.04 1083.3 83.3 16.7
0.150 104.59 1187.9 91.4 8.6
0.075 14.82 1202.7 92.5 7.5
Pan 2.49
-
8/12/2019 Final Year Project, Iga Dan
55/67
-
8/12/2019 Final Year Project, Iga Dan
56/67
FINAL YEAR PROJECT 2011/2012
45 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Weight of wet soil + container m1 103.27 115.98 149.51 144.15 134.14 151.57 168.74 128.96 208.60 129.98
Weight of dry soil + container m2 97.02 108.45 138.21 133.46 123.08 138.42 153.22 117.00 186.14 117.00
Mass of container m3 30.39 30.99 31.42 30.71 30.45 30.56 30.56 29.00 30.56 29.00
Weight of water (m1-m2) 6.3 7.5 11.3 10.7 11.1 13.2 15.5 12.0 22.5 13.0
Weight of dry sample (m2-m3) 66.6 77.5 106.8 102.8 92.6 107.9 122.7 88.0 155.6 88.0
9.4 9.7 10.6 10.4 11.9 12.2 12.7 13.6 14.4 14.8
Moisture content w (m1-m2)/(m2-m3) x 100 9.6 10.5 12.1 13.1 14.6
Dry density =(100x bulk density)/(100+w) Kg/m3 1,521 1,620 1,700 1,647 1,606
-
8/12/2019 Final Year Project, Iga Dan
57/67
-
8/12/2019 Final Year Project, Iga Dan
58/67
FINAL YEAR PROJECT 2011/2012
47 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Table 18 Test results for the Moisture-Density Relatios of the soil (BS 1377: Part 4) for chainage 0+300
DESIGN OF A SAND SEAL FOR A LOW VOLUME GRAVEL ROAD
Project Road: Kira-Kito Road
DATA SHEET FOR MOISTURE - DENSITY RELATIONS OF SOILS
USING 4.54KG. RAMMER ( OMC & MDDTEST )
As per BS 1377: Part4
Sample No: Sampling Date: 17 -04-12
Source/Location of Sample: Kira Kito Testing Date: 25 -04-12
Km 0+300 LHS
Sample Description : Red Gravel Material Technician:IgaDan
Proposed Use: Wearing Course
Mass of mould(g): 5,120
Volume(cm3): 2,299
Specimen Number/MouldNo. 1 2 3 4 5
Mass of mould+base+compacted specimen ( m2 ) 9,030 9,190 9,380 9,400 9,370
Mass of mould + base (m1) 5,120 5,120 5,120 5,120 5,120
Mass of compacted specimen(m2-m1) 3,910 4,070 4,260 4,280 4,250
Bulk Density = (m2-m1) x mould factor 1.701 1.770 1.853 1.862 1.849
Weight of wet soil +container m1 140.32
115.98
208.60
129.98 161.75 153.30
138.74
128.96 149.51
144.15
Weight of dry soil + containerm2 132.02
109.75
192.01
120.45 147.61 140.49
126.52
117.00 134.91
129.46
Mass of container m3 30.39 30.99 31.42 30.71 30.90 30.52 30.56 27.00 33.56 29.00
Weight of water (m1-m2) 8.3 6.2 16.6 9.5 14.1 12.8 12.2 12.0 14.6 14.7
Weight of dry sample (m2-m3) 101.6 78.8 160.6 89.7 116.7 110.0 96.0 90.0 101.4 100.5
8.2 7.9 10.3 10.6 12.1 11.6 12.7 13.3 14.4 14.6
Moisture content w (m1-m2)/(m2-m3) x 100 8.0 10.5 11.9 13.0 14.5
Dry density = (100x bulk density)/(100+w) kg/m3 1,574 1,602 1,656 1,647 1,614
-
8/12/2019 Final Year Project, Iga Dan
59/67
-
8/12/2019 Final Year Project, Iga Dan
60/67
FINAL YEAR PROJECT 2011/2012
49 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Appendix IV: Design Charts
-
8/12/2019 Final Year Project, Iga Dan
61/67
FINAL YEAR PROJECT 2011/2012
50 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
-
8/12/2019 Final Year Project, Iga Dan
62/67
FINAL YEAR PROJECT 2011/2012
51 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
-
8/12/2019 Final Year Project, Iga Dan
63/67
FINAL YEAR PROJECT 2011/2012
52 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
-
8/12/2019 Final Year Project, Iga Dan
64/67
FINAL YEAR PROJECT 2011/2012
53 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
-
8/12/2019 Final Year Project, Iga Dan
65/67
FINAL YEAR PROJECT 2011/2012
54 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
-
8/12/2019 Final Year Project, Iga Dan
66/67
FINAL YEAR PROJECT 2011/2012
55 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering
Appendix IV: Photographs of the project execution
Figure 20Assembling of the DCP test equipment
Figure 21 Applying blows to the soil to get penetrations
Figure 22 Recording of pentrations
Figure 23 Measuring of the distances from one chainageto another
Figure 24 The Kira-Kito road condition
-
8/12/2019 Final Year Project, Iga Dan
67/67
FINAL YEAR PROJECT 2011/2012
Figure 25 Ruler used to measure the penetration Figure 26 Sampling to obtain samples for laboratorytests