final year project, iga dan

Upload: igadan

Post on 03-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Final Year Project, Iga Dan

    1/67

  • 8/12/2019 Final Year Project, Iga Dan

    2/67

  • 8/12/2019 Final Year Project, Iga Dan

    3/67

    FINAL YEAR PROJECT 2011/2012

    i | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    DECLARATION

    I , IGA DAN, the undersigned do solemnly declare to the best of my knowledge and effort

    that I did the final year project and that the work herein this report is entirely mine and hasnever been submitted by anyone to any institution for the award of academic awards. Any errors,

    mistakes and omissions and others of that kind are of my personal failure and I welcome any

    genuine criticisms

    Signature Date ..

  • 8/12/2019 Final Year Project, Iga Dan

    4/67

    FINAL YEAR PROJECT 2011/2012

    ii | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    DEDICATION

    To my dear mummy, Miss Naluyima Mir iam who has sacrif iced and struggled to bri ng me

    thus far ; without her I wouldnt have made it to this great institution.

  • 8/12/2019 Final Year Project, Iga Dan

    5/67

  • 8/12/2019 Final Year Project, Iga Dan

    6/67

    FINAL YEAR PROJECT 2011/2012

    iv | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    TABLE OF CONTENTS

    DECLARATION ................................................................................................................................... I

    DEDICATION ...................................................................................................................................... II

    ACKNOWLEDGEMENTS............................ ......................... .......................... ......................... ..........III

    TABLE OF FIGURES: ...................................................................................................................... VII

    TABLE OF TABLES: ........................... ......................... .......................... ......................... ................ VIII

    ABSTRACT ........................ .......................... .......................... ......................... ........................... ......... IX

    CHAPTER 1: INTRODUCTION ................................................................................................... 1

    1.1 Background................................................................................................................................................... 1

    1.2 Problem statement ....................................................................................................................................... 2

    1.3 Main objective .............................................................................................................................................. 2

    1.4 Specific objectives ........................................................................................................................................ 2

    1.5 Justification .................................................................................................................................................. 3

    1.6 Scope of the study ........................................................................................................................................ 4

    CHAPTER 2: LITERATURE REVIEW ........................................................................................ 5

    2.1 Benefits and selection of surfacing ............................................................................................................... 5

    2.2 Low cost surfacing on low-volume roads ...................................................................................................... 5

    2.3 Surfacing types available .............................................................................................................................. 6

    2.3.1 Fog seal ................................................................................................................................................ 6

    2.3.2 Priming ................................................................................................................................................ 62.3.3 Primer seal ........................................................................................................................................... 6

    2.3.4 Sand seal .............................................................................................................................................. 7

    2.3.5 Surface dressing ................................................................................................................................... 7

    2.3.6 Slurry seal ............................................................................................................................................ 7

    2.3.7 Otta seal .............................................................................................................................................. 7

    2.3.8 Penetration macadam .......................................................................................................................... 8

    2.3.9 Premixed gravel macadam/Gravel emulsified mix ............ ............. ............ ............. .............. ............ ..... 8

  • 8/12/2019 Final Year Project, Iga Dan

    7/67

    FINAL YEAR PROJECT 2011/2012

    v | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    2.4 Previous studies done about sand seal designs............................................................................................. 8

    CHAPTER 3: METHODOLOGY ........................ .......................... ......................... ...................... 10

    3.1 Traffic Assessment ...................................................................................................................................... 10

    3.1.1 Estimating Traffic Flows ...................................................................................................................... 10

    3.1.2 Traffic forecasting .............................................................................................................................. 10

    3.1.3 Determination of cumulative equivalent standard axles ..................................................................... 10

    3.2 Inventory and general condition ................................................................................................................. 11

    3.3 Structural Evaluation .................................................................................................................................. 11

    3.4 Rainfall Assessment .................................................................................................................................... 13

    3.5 Laboratory tests.......................................................................................................................................... 13

    4.0 RESULTS AND ANALYSIS:................................................................................................. 14

    4.1 Structural Evaluation .................................................................................................................................. 14

    4.1.1 DCP test results .................................................................................................................................. 14

    4.1.2 Subgrade classification: ...................................................................................................................... 15

    4.2 Traffic Assessment: ..................................................................................................................................... 15

    4.2.1 Traffic count results ........................................................................................................................... 15

    4.2.2 Cumulative Equivalent Standard Axle Loads ........................................................................................ 17

    4.2.3 Traffic classification: ............. ............. ............ ............. ............. ............. .............. ............ ............. ....... 18

    4.3 Rainfall Assessment .................................................................................................................................... 184.3.1 Weinert Value .................................................................................................................................... 18

    4.4 Laboratory tests.......................................................................................................................................... 19

    4.4.1 MDD results: ...................................................................................................................................... 19

    Chainage 0+010 ........................................................................................................................................... 19

    Chainage 0+110 ........................................................................................................................................... 20

    Chainage 0+300:.......................................................................................................................................... 20

    4.4.2 Gradation Results:.................................................................................................................................. 21

    Chainage 0+010 ........................................................................................................................................... 21

    Chainage 0+110 ........................................................................................................................................... 22Chainage 0+300 ........................................................................................................................................... 22

    4.4.3 Plasticity Index results: ....................................................................................................................... 23

    Chainage 0+010:.......................................................................................................................................... 23

    Chainage 0+110 ........................................................................................................................................... 24

    Chainage 0+300 ........................................................................................................................................... 25

    4.5 Analysis: Layer thickness Design ................................................................................................................. 25

  • 8/12/2019 Final Year Project, Iga Dan

    8/67

    FINAL YEAR PROJECT 2011/2012

    vi | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    CHAPTER 5.0 CONCLUSIONS AND RECOMMNEDATIONS ......................... ......................... 26

    5.1 Summary .................................................................................................................................................... 26

    5.2 Conclusions: ............................................................................................................................................... 26

    5.2.1 Inventory of the existing road condition ............................................................................................. 26

    5.2.2 Traffic usage of the road:.................................................................................................................... 265.2.3 Subgrade characteristics of the existing road ...................................................................................... 26

    5.2.4 The design of the appropriate sand seal ............................................................................................. 27

    New Pavement Structure............................................................................................................................. 27

    New Pavement Structure............................................................................................................................. 28

    Drainage ..................................................................................................................................................... 28

    REFERENCES .................................................................................................................................... 29

    APPENDICES ......................... ......................... .......................... ......................... ........................... .... 30

    Appendix I: DCP Test Data and Results: ........................................................................................................ 30

    Layer boundary graphs and CBR graphs ............................................................................................................... 36

    Appendix II: Kituza Coffee Research Meteorological Station Data ................................................................ 40

    Appendix III Laboratory tests data: .............................................................................................................. 41

    Appendix IV: Design Charts............................................................................................................................ 49

    Appendix IV: Photographs of the project execution ...................................................................................... 55

  • 8/12/2019 Final Year Project, Iga Dan

    9/67

    FINAL YEAR PROJECT 2011/2012

    vii | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    TABLE OF FIGURES:

    FIGURE 1DYNAMIC CONE PENETROMETER ............................................................................................................ 12

    FIGURE 2SUMMARY OF THE TRAFFIC COUNTS DATA USED TO OBTAIN THE ADT ...................................................... 16

    FIGURE 3PROCTOR CURVE FOR CHAINAGE 0+010 .................................................................................................. 19

    FIGURE 4PROCTOR CURVE FOR CHAINAGE 0+110 .................................................................................................. 20

    FIGURE 5PROCTOR CURVE FOR CHAINAGE 0+300 .................................................................................................. 21

    FIGURE 6SIEVE ANALYSIS FOR CHAINAGE 0+010 ................................................................................................... 21

    FIGURE 7SIEVE ANALYSIS RESULTS FOR CHAINAGE 0+110 ..................................................................................... 22

    FIGURE 8PLASTICITY INDEX RESULTS FOR CHAINAGE 0+010 .................................................................................. 23

    FIGURE 9PLASTICITY INDEX RESULTS FOR CHAINAGE 0+110 .................................................................................. 24

    FIGURE 10PLASTICITY INDEX RESULTS FOR CHAINAGE 0+300 ................................................................................ 25

    FIGURE 11CBRVARIATION WITH THE CHAINAGE ALONG THE ROAD ....................................................................... 26

    FIGURE 12DIAGRAMATIC REPRESENTATION OF THE NEW PAVEMENT STRUCTURE.................................................... 27FIGURE 13LAYER BOUNDARIES AND CBRVARIATION FOR CHAINAGE 0+010 .......................................................... 36

    FIGURE 14LAYER BOUNDARIES AND CBRVARIATION FOR CHAINAGE 0+110 .......................................................... 36

    FIGURE 15BOUNDARIES AND CBRVARIATION FOR CHAINAGE 0+210 ..................................................................... 37

    FIGURE 16BOUNDARIES AND CBRVARIATION FOR CHAINAGE 0+300 ..................................................................... 37

    FIGURE 17BOUNDARIES AND CBRVARIATION FOR CHAINAGE 0+400 ..................................................................... 38

    FIGURE 18BOUNDARIES AND CBRVARIATION FOR CHAINAGE 0+500 ..................................................................... 38

    FIGURE 19HISTOGRAM SHOWING THE BASE SBR(%) ............................................................................................ 39

    FIGURE 20ASSEMBLING OF THE DCPTEST EQUIPMENT .......................................................................................... 55

    FIGURE 21APPLYING BLOWS TO THE SOIL TO GET PENETRATIONS ........................................................................... 55

    FIGURE 22RECORDING OF PENTRATIONS ............................................................................................................... 55

    FIGURE 23MEASURING OF THE DISTANCES FROM ONE CHAINAGE TO ANOTHER ....................................................... 55

    FIGURE 24THE KIRA-KITO ROAD CONDITION......................................................................................................... 55

    FIGURE 25RULER USED TO MEASURE THE PENETRATION ........................................................................................ 56

    FIGURE 26SAMPLING TO OBTAIN SAMPLES FOR LABORATORY TESTS....................................................................... 56

  • 8/12/2019 Final Year Project, Iga Dan

    10/67

    FINAL YEAR PROJECT 2011/2012

    viii | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    TABLE OF TABLES:

    TABLE 1RECOMMENDED SPACINGS FOR DCP ........................................................................................................ 11

    TABLE 2LABORATORY TESTS CARRIED OUT IN THE PROJECT EXECUTION................................................................. 13

    TABLE 3SUMMARY OF THE DCPTEST RESULTS FOR THE DIFFERENT CHAINAGES..................................................... 14

    TABLE 4SUBGRADE STRENGTH CLASSIFICATION .................................................................................................... 15

    TABLE 5OBTAINING THE CUMULATIVE EQUIVALENT STANDARD AXLES LOADS ON THE ROAD................................. 17

    TABLE 6TRAFFIC CLASSIFICATION BASING ON THE RANGE OF ESAS ....................................................................... 18

    TABLE 7PROPOSEDNEW PAVEMENT STRUCTURE OF THE ROAD ............................................................................. 27

    TABLE 8PROPOSED SURFACING OPTIONS ............................................................................................................... 28

    TABLE 9THICKNESS AND REQUIRED CBRVALUES OF THE NEW PAVEMENT STRCUTURE.......................................... 28

    TABLE 10UKDCPTEST RESULTS FOR ALL THE CHAINAGES (0+010TO 0+500) ....................................................... 30

    TABLE 11MONTHLY EVAPORATION DATA FOR KITUZA COFFEE RESEARCH STATION................................................ 40

    TABLE 12MONTHLY MAXIMUM FALL OF RAINFALL FOR KITUZA STATION.............................................................. 40

    TABLE 13MONTLY RAINFALL TOTALS OF KITUZA STATION.................................................................................... 40

    TABLE 14TEST RESULTS FROM MAXIMUM DRY DENSITY OF THE SOIL FOR CHAINAGE 0+010\ ................................. 41

    TABLE 15TEST RESULTS FOR PARTICLE SIZE ANALYSIS TEST (BS1377:PART 2)FOR CHAINAGE 0+010 ................... 43

    TABLE 16TEST RESULTS FOR THE MOISTURE-DENSITY RELATIOS FOR CHAINAGE 0+210 ........................................ 44

    TABLE 17TEST RESULTS FOR PARTICLE SIZE ANALYSIS TEST (BS1377:PART 2)FOR CHAINAGE 0+210 ................... 46

    TABLE 18TEST RESULTS FOR THE MOISTURE-DENSITY RELATIOS OF THE SOIL FOR CHAINAGE 0+300 ............. ......... 47

    TABLE 19TEST RESULTS FOR PARTICLE SIZE ANALYSIS TEST (BS1377:PART 2)FOR CHAINAGE 0+300 ................... 48

  • 8/12/2019 Final Year Project, Iga Dan

    11/67

    FINAL YEAR PROJECT 2011/2012

    ix | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    ABSTRACT

    This report consists of a detailed proposed design of a sand seal for a low volume gravel road

    case study being Kira-Kito road which stretches a distance of 1.5km. The main objective was to

    design a sand seal. This was done by carrying out an inventory of the existing road condition,

    determining the traffic usage of the road and evaluating the sub-grade characteristics of the

    existing road.

    In-situ field tests such as the DCP test, laboratory tests including; Moisture relations, Particle

    size determination, maximum density test and plasticity index tests were some of the methods

    that were used to analyse the structural strength and the existing material properties of the soil.

    From the traffic counts the cumulative equivalent axles were obtained as 0.502 million ESA thusa traffic class of T2 LV6, the strength was observed to lie mainly from 15 to 29, hence a

    subgrade classification of S5. From these results and others such as the maximum evaporation

    and maximum rainfall were used to design the sand seal.

  • 8/12/2019 Final Year Project, Iga Dan

    12/67

    FINAL YEAR PROJECT 2011/2012

    1 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    CHAPTER 1: INTRODUCTION

    1.1 Background

    Low-volume rural roads in developing countries are vital to the socio-economic well being of

    communities by providing access to schools, clinics, jobs, markets, neighboring communities

    and the higher order road network. Therefore, whilst these roads tend to carry relatively low

    levels of traffic, they play an important role in contributing to poverty alleviation, social and

    economic development and the facilitation of schemes aimed at improving rural livelihoods.

    (Done et al TRL, 2001).

    Kira-Kito road is a low volume rural road. It is a gravel road, 10 km long located in Kira Town

    Council, Wakiso district, Uganda. This road is a low volume national road which is under Kira

    Town Council and is very important to Kira town council for access and mobility.

    The rural poor in Kira need reliable access for affordable transport or services (both motorized

    and non-motorized) such as bicycles, motorcycles, minibuses, buses, cars, whether owned or

    hired. Even if a vehicle ride is too expensive for them, they will still depend on the transporters

    that bring the medicine and teachers to the village, or carry farm produce to markets. The

    challenge is therefore to provide and maintain this rural access for the low traffic currently in

    use, on a sustainable basis within the limited resources available.

    Many kilometers of this road in become impassable during the wet season cutting many

    communities off from access to schools, markets, clinics and job opportunities. In addition, the

    cost of operating vehicles on this road during the remainder of the year is disproportionately high

    in relation to the service offered. Of equal or greater impact is the unsustainability of replacing

    the gravel lost from these roads under environmental and traffic influences.

    Using the conventional economic analysis and pavement design techniques, paving of this road

    can not be justified. However, when environmental and the social benefits are considered,upgrading of this road carrying traffic as low as 20 vehicles per day to a sand sealed road can be

    justified, particularly because large communities are affected.

  • 8/12/2019 Final Year Project, Iga Dan

    13/67

  • 8/12/2019 Final Year Project, Iga Dan

    14/67

    FINAL YEAR PROJECT 2011/2012

    3 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    c) To evaluate the sub-grade characteristics of the existing road

    d) To design an appropriate sand seal to accommodate the traffic

    1.5 Justification

    There are serious constraints to the use of gravel in Kira due to factors relating to material

    quality, material availability, climate, terrain, drainage provision and maintenance. There is

    overall significant gravel loss and unsuitable deterioration. Thus, it is expected that the use of a

    sand sealing would provide appropriate, economical and sustainable alternatives to natural gravel

    in this region and the Uganda road sector.

    This alternative, involving use of locally available sand may be constructed by small local

    enterprises, using low-capital, labour based and light equipment methods. Communities could

    also use some of the techniques to improve their own access. Thus the design of a sand seal is

    very necessary to pave a way for the application of this sealing alternative.

    The sealed surface will have lower maintenance requirements than gravel, not only in terms of

    cost but also by reducing the need for imported heavy equipment to transport and compact. In

    addition, a number of other strategic issues will be satisfied, which include;

    Improved sustainability

    Durability in the expected traffic and environmental conditions

    Use of locally available materials

    Techniques with low capital investment (limited or simple equipment needs) and

    manageable by local contractors

    Use of local labour and skills

    Low volume roads tend to have a greater social and environmental impact as compared to high

    volume roads because they connect small towns and rural communities, serve as farm-to-

    market/forest-to-market roads, and provide links to parks and recreational areas hence need for

    emphasis to be directed to these roads too, which is the reason for considering this project for my

    final year.

  • 8/12/2019 Final Year Project, Iga Dan

    15/67

    FINAL YEAR PROJECT 2011/2012

    4 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    1.6 Scope of the study

    The study was carried out on Kira-Kito road and was limited to the first 600m from Kira Primary

    School because of economy and to minimize on the challenge of ambiguity which may be caused

    by too much work in a short period of time.

    The study involved carrying out a traffic assessment of the area for five consecutive days at the

    peak hours from 6 am to 9am, 12pm to 3pm and finally from 5pm to 7pm.

    Soil samples were obtained from the road at 100m intervals to a depth of up to 500mm and from

    the Right hand side, centerline and left hand side respectively.

    This project was limited to design of a sand seal only.

  • 8/12/2019 Final Year Project, Iga Dan

    16/67

    FINAL YEAR PROJECT 2011/2012

    5 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    CHAPTER 2: LITERATURE REVIEW

    2.0 Introduction:

    The literature review includes Include some introductory remarks about this chapter, some kind

    of summary of what this chapter is about,

    2.1 Benefits and selection of surfacing

    The construction of an improved road surface can give a range of benefits. These benefits must

    be compared with the costs of providing the surface. The primary benefits include:

    Waterproof surface that is durable in both wet and dry weather;

    Smoother surface (Sampson, 1995) and uniform appearance;

    Decreased rate of deterioration resulting in a reduced maintenance requirement (gravel

    typically loses 25 mm per year), (Nicholls and Spon, 1998); and

    Increased skid resistance (Millard, 1993; TRL, 2000)

    The decision to surface a road with any type of bituminous seal can depend on factors such as

    the type and condition of the existing surface and strength of the pavement in relation to the

    traffic it carries (Botswana, 1999). The quality and availability of materials also needs to be

    consider along with the geometry of the road and the local climate (SABITA, 1992; TRL, 2000;

    TRH, 1998).

    Financial and economic factors are of course important in assessing whether to apply a surface

    treatment to a road (Botswana, 1999). The initial construction cost and subsequent maintenance

    costs must be assessed against the expected lifespan of the road and benefits to road users. What

    may be thought lesser benefits such as riding quality, safety (from improved surface texture) and

    environmental improvements (noise, dust) are no less important when justifying upgrading

    unpaved roads and tracks.

    Ultimately the local construction and maintenance capability must be considered and the

    suitability of the construction technique for labour-based methods.

    2.2 Low cost surfacing on low-volume roads

    The justification (technical, economic, and environmental) for a surfacing on a road which

    carries high levels of traffic is clear. However, there are considerable and growing arguments in

    favor of extending the use of surfacings to roads with much lower traffic levels of less than 400

  • 8/12/2019 Final Year Project, Iga Dan

    17/67

    FINAL YEAR PROJECT 2011/2012

    6 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    vpd (MELTC, 2011). For simple economic reasons, surfacings applied to low-volume roads will

    tend to be low cost, although some cost/benefit analysis will always be useful.

    Surfaced roads are particularly effective in reducing environmental damage. They can be used to

    prevent dust pollution, particularly in towns and villages (Sampson, 1995, Greening et al, 1999).

    They reduce the demand for increasingly scarce gravel materials and even in those areas where

    materials are available they improve the environment through decreased borrow pit activity

    (Rolt, 1995, Kenya, 1993). They also prevent the sedimentation of fine materials that result from

    run-off of rainwater from un-surfaced roads (Sampson, 1995).

    Finally, and most importantly, it is extremely important that rural roads provide all weather

    access for the local community. In some circumstances the only way to ensure this is to provide

    effective drainage and seal the road on, at least, some short sections of the road. If this is not

    done then as the road continues to deteriorate it may reach a state where access may be totally

    lost (Rolt, 1995).

    2.3 Surfacing types available

    2.3.1 Fog seal

    Fog seals use bitumen emulsions and are used to enrich ageing bituminous surfacing and prevent

    chipping loss. The fog seal is usually blinded with a layer of fines to prevent pick up by traffic

    (ARRB, 1995; TRL, 2000).

    2.3.2 Priming

    Normally used prior to placing another surfacing for sealing small cracks and providing

    adhesion. Priming waterproofs and reduces dust but lasts only a few weeks. Cut-back bitumens

    are normally used but emulsions have been trialed, but the results are not yet known (ARRB,

    1995) and morever, cut-back bitumens due to environmental concerns are no longer

    recommended for use.

    2.3.3 Primer seal

    This is similar to a sand seal but is made to less rigorous specifications, is less durable having a

    life expectancy of 1-3 years (Overby, 1982). It is normally constructed with a cut-back as the

    binder but emulsions can be used in conjunction with small aggregate sizes (5 7mm), in fine

    and warm conditions, when it provides good adhesion for the aggregate (ARRB, 1995).

  • 8/12/2019 Final Year Project, Iga Dan

    18/67

    FINAL YEAR PROJECT 2011/2012

    7 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    2.3.4 Sand seal

    This seal consists of first an optional prime coat (1mm); a bitumen layer (1.5mm, cutback

    bitumen, emulsion) followed by a graded sand layer (3-5mm) which must then is compacted.

    (Beusch et al, 1997). Performance can be improved if a second seal is applied after 3 months

    and is best for traffic levels up to 400 vpd. A life of 4-5 years can be expected (van der Walt,

    1979).

    2.3.5 Surface dressing

    Surface dressing comprises a thin film of bitumen sprayed onto the road surface and then

    covered with a layer of stone chippings (Beusch et al, 1997). The thin film of binder acts as a

    waterproofing layer preventing the entry of surface water into the road structure. The stone

    chippings protect this film of binder from damage by vehicle tyres, and form a durable, skid-

    resistant and dust-free wearing surface. It can provide an effective and economical running

    surface for newly constructed road pavements. Roads carrying up to 1000 vehicles/lane/day are

    successfully surfaced with multiple surface dressings (Overby, 1982).

    2.3.6 Slurry seal

    Slurry seals are laid cold and are a mixture of fine aggregates, Portland cement filler, bitumen

    emulsion and additional water (BSI, 1984) (ASTM, 1990). When freshly mixed they have a thick

    creamy consistency and can be spread to a thickness of 5 to 10 mm. They are often used over a

    single surface dressing to produce a Cape seal. Slurry mixes are best made and spread by

    purpose made machines but can be suitable for labour-based construction (Emery et al, 1994)

    (SABITA, 1993) (Zimbabwe, 1998).

    2.3.7 Otta seal

    An Otta seal consists of a layer of binder followed by a layer of aggregate that is extensively

    rolled into the binder using a pneumatic tyred roller or loaded trucks(Overby, 1982). It is

    different to surface dressing in that a graded gravel or crushed aggregate containing all sizes,

    including filler, is used instead of single sized chippings. It depends for its success on the

    mechanism of the binder being squeezed up through the aggregate by the action of the rolling.

    Due to the fines in the aggregate, 2 to 3 days of pneumatic-tyred compaction (rollers or traffic) is

    required to fully coat all the particles. There is no formal design procedure but recommendations

    based on case studies have been published (Overby, 1999).

  • 8/12/2019 Final Year Project, Iga Dan

    19/67

    FINAL YEAR PROJECT 2011/2012

    8 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    2.3.8 Penetration macadam

    Macadam is a paving technique developed by a Scottish Engineer called John Macadam at the

    beginning of the 19 thcentury using broken stones of various sizes combined together and placed

    in layers. Various developments of this technique are used today. Penetration macadam consists

    of layers of broken or crushed stones of size up to 80mm, interspersed with applications of

    heated bitumen to grout and seal the surface. It is laid as a waterproof surface on a previously

    prepared roadbase. The effect is to achieve a matrix of keyed stones grouted and sealed with

    bitumen to a depth of about 60 80mm. The process requires only a basic bitumen heater-

    distributor and an 8-10 tonne deadweight roller. Labour methods can be used to place and spread

    the materials. Applications of bitumen are high at 7 9 kg/m. Other types of bitumen surface

    can achieve a durable waterproof surface with lower bitumen application rates. Alternative

    bitumen emulsion surfaces can avoid the requirement for heating with corresponding safety

    benefits.

    2.3.9 Premixed gravel macadam/Gravel emulsified mix

    Gravel aggregate is mixed with an anionic emulsion either by hand or in a small drum mixer

    such as a portable cement mixer with the aggregate gravel specification the same as an Otta seal

    (Balmaceda&Horak, 1997). After mixing, the material is spread on a primed road base and rolled

    in the same way as an Otta seal. The surfacing is comparable to an Otta seal.

    2.4 Previous studies done about sand seal designs

    MELTC (Uganda) in conjunction with DANIDA under consultancy of TRL and PROME were

    the first to carry out studies about Sand seals and work include; Development of training

    modules, conducting training and establishment of demonstration sites for low-cost sealing of

    roads in Uganda. The project entailed the following activities:

    Prepare a training curriculum and training materials covering materials investigation,

    appropriate design options for pavements and low-cost structures for labour-based sealed

    roads, sealing procedures and techniques, site safety, maintenance of labour-based sealed

    roads and any other information as the consultant may deem necessary for achieving the

    training objectives;

    Train trainers at MELTC,

  • 8/12/2019 Final Year Project, Iga Dan

    20/67

    FINAL YEAR PROJECT 2011/2012

    9 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Develop the necessary technical documentation (manuals) for use by local practitioners

    including tender documents,

    Develop quality control measures for the low-cost sealing of roads.

    This study project is different from the work done under MELTC because it is aimed at

    designing a sand seal for Kira-Kito road putting into consideration the local, topographical and

    environmental conditions in Wakiso and will put into account the local available materials in or

    near Mukono.

    The Institutional Cooperation between Roads Department, Ministry of Works, Kenya and

    Norwegian Road Research Laboratory (NRRL) carried out an appraisal study in Kenya on the

    Low-cost Pavement which started in 1982, which was carried out by the Norwegian Road

    Research Laboratory (NRRL) and Materials Branch of Ministry of Public Works. The initial

    contracts for the project were in 1980 between the Ministry of Works, NRRL and the Norwegian

    Agency for Development NORAD. The main objective of the Low-cost Pavement was to

    provide specification for construction materials to be utilized on the low volume roads in the

    regions without too good quality materials. It was intended that by utilizing local materials the

    project would achieve road pavements (Sand seal inclusive) with both acceptable life expectancy

    and reasonable maintenance costs. The construction of the trial section started in June 1983 on

    the arrival of the first project co-coordinator. Preliminary investigations consisted of gravel and

    hard stone surveys together with digging of test trenches. From August 1983 to August 1985 a

    total of 16 trail sections were constructed. An additional 6 sections were located adjacent to the

    already constructed sections in Kenya.

  • 8/12/2019 Final Year Project, Iga Dan

    21/67

    FINAL YEAR PROJECT 2011/2012

    10 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    CHAPTER 3: METHODOLOGY

    Include a summary of what this chapter is about

    3.1 Traffic Assessment

    3.1.1 Estimating Traffic Flows

    A 5-day classified traffic count was carried out along the road with the counts distinguishing

    between vehicle categories basing on the MoWT road design manual which stipulates a period of

    seven days; reason for carrying out only five days was because of consistency of results and

    constraints in facilitation. The counts of the traffic were carried out in both directions and the

    different vehicle categories included:

    Non motorised traffic which included people (Children, adults)

    Cars, including passenger cars, vans, minibuses taxis, pick-ups, 4WD vehicles

    Buses, including medium and large buses above 24 passenger seats

    Light trucks, including small and medium sized trucks with 2 axles.

    Medium trucks, including larger trucks with 3 or 4 axles.

    Heavy trucks, including trucks with more than 4 axles and articulated trucks

    3.1.2 Traffic forecasting

    In order to estimate the traffic that will use the road over its design life, a growth rate was

    projected basing on Ministry of Works Manual and basing on the value of 4.5% per annum used

    by MELTC in designing for low cost sealing options.

    3.1.3 Determination of cumulative equivalent standard axles

    In order to determine the cumulative equivalent standard axles over the design life of the road,

    the following procedure was followed:

    i. The daily traffic flow was determined for each class of vehicle weighed using the results

    of the traffic survey.

    ii. The average daily traffic flow for each class of vehicle was then obtained also.

  • 8/12/2019 Final Year Project, Iga Dan

    22/67

    FINAL YEAR PROJECT 2011/2012

    11 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    iii. A forecast of the traffic flow for each class of vehicle was made so as to determine the

    total traffic in each class that will travel over the road during the design life

    iv. The mean equivalence factors of each class of vehicle were determined from the results

    of an axle load survey.

    v.

    The products of the cumulative traffic flows for each class of vehicle over the design life

    of the road and the mean equivalence factor for that class were then calculated and added

    together to give the cumulative equivalent standard axle loading for each direction.

    3.2 Inventory and general condition

    Moving along the existing road, geometric data, shoulder condition data, side drain data,

    and carriageway surface condition data was observed to be in a relatively good condition

    since the road had just been regraveled and a few defects were observed which basically

    constituted;

    o Potholes,

    o Oversize material,

    3.3 Structural Evaluation

    The structural assessment was carried out in situ by use of a dynamic cone penetrometer

    (DCP) shown in figure 1 below. The spacing for carrying out the DCP test along the roadwas taken as 100m for the entire length of section of 500m because the section my

    project is concentrating on is the first 100m thus wasnt necessary to carry out structural

    assessment on the entire section.

    The procedure of carrying out the DCP test was as per Dynamic Cone Penetrometer tests

    and analysis, (Colin Jones, 2007)

    The recommended spacings for conducting DCP tests are shown in Error! Reference

    source not found.below.

    Table 1 Recommended spacings for DCP

    Objective Minimum Test Spacing

    Routine testing for the rehabilitation of paved roads 500m or less

    Areas of distress on paved roads 100m or less

  • 8/12/2019 Final Year Project, Iga Dan

    23/67

    FINAL YEAR PROJECT 2011/2012

    12 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Upgrading of gravel roads to sealed roads 500m or less

    Design of spot improvements 50m or less

    Adopted from TRL Project Report Number: PR/INT/277/04

    Figure 1 Dynamic Cone Penetrometer

  • 8/12/2019 Final Year Project, Iga Dan

    24/67

    FINAL YEAR PROJECT 2011/2012

    13 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    3.4 Rainfall Assessment

    Annual rainfall estimates and the maximum evaporation data was obtained from Meteorological

    Department, Ministry of land, water and environment and are shown in chapter 4.

    3.5 Laboratory tests

    Sampling was carried out concurrently as the DCP test was being carried out and approximately

    35 kg were taken per point. This was to make sure that the material was enough to carry out the

    necessary tests.

    In the laboratory samples of the base material and the subgrade material were be tested for the

    tests indicated in the laboratory except the California Bearing ratio because of many reasons

    including:

    DCP test gave us consistent values for the CBR and thus it was satisfactory to rely on

    those results hence not very necessary to carry out the laboratory CBR

    Lack of enough resources especially time as many tests were to be carried out and yet

    CBR moulds were not easily accessible

    The tests which were carried out included the following the procedures indicated in the British

    Standards indicated and are summarised in Table 2.

    Table 2 Laboratory tests carried out in the project execution

    Laboratory Tests Standard

    Compaction test BS 1377: Part 4: 1990

    Moisture Content BS 1377: Part 2: 1990

    Atterbergs Limits BS 1377: Part 2: 1990

    Particle Size Distribution BS 1377: Part 2: 1990

  • 8/12/2019 Final Year Project, Iga Dan

    25/67

    FINAL YEAR PROJECT 2011/2012

    14 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    4.0 RESULTS AND ANALYSIS:

    4.1 Structural Evaluation

    4.1.1 DCP test results

    The detailed test data obtained while carrying out the DCP test is shown in the Appendix 1 andthe test results can be summarised in the table 3 below obtained from the layer boundary and

    CBR graphs in the Appendix 1

    Table 3 Summary of the DCP test results for the different chainages

    Chainage 0+010

    No. CBR (%) Thickness(mm) Depth (mm) Position Strength coeff.

    1 31 432 432 Base 0.07

    2 8 139 571 Sub-base 0.06

    3 22 127 698 Subgrade

    Chainage 0+110

    No. CBR (%) Thickness(mm) Depth (mm) Position Strength coeff.

    1 120 554 554 Base 0.14

    2 45 134 688 Sub-base 0.11

    3 24 231 919 Subgrade

    Chainage 0+210

    No. CBR (%) Thickness(mm) Depth (mm) Position Strength coeff.

    1 87 329 329 Base 0.13

    2 13 117 446 Sub-base 0.08

    3 19 353 799 Subgrade

    Chainage 0+300

    No. CBR (%) Thickness(mm) Depth (mm) Position Strength coeff.

    1 68 364 364 Base 0.12

    2 10 120 484 Sub-base 0.07

    3 20 320 804 Subgrade

    Chainage 0+400No. CBR (%) Thickness(mm) Depth (mm) Position Strength coeff.

    1 96 313 313 Base 0.14

    2 26 217 530 Sub-base 0.1

    3 20 268 798 Subgrade

    Chainage 0+500

  • 8/12/2019 Final Year Project, Iga Dan

    26/67

    FINAL YEAR PROJECT 2011/2012

    15 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    No. CBR (%) Thickness(mm) Depth (mm) Position Strength coeff.

    1 59 226 226 Base 0.11

    2 37 344 570 Sub-base 0.1

    3 29 241 811 Subgrade

    4.1.2 Subgrade classification:

    From the results of the DCP tests as analysed using the UKDCP software above, it was

    established that the Subgrade strength class of the road was mainly lying from 15 to 29 thus the

    subgrade class of the road from the specification given in the TRL road note 31 shown in the

    table 4 below is S5.

    Table 4 Subgrade strength classification

    (MoWT Road Design Manual, 2010)

    4.2 Traffic Assessment:

    4.2.1 Traffic count results

    The traffic counts were carried out for five consecutive days as shown in the traffic count sheets

    appended to the document in appendix VI. The data was analysed as shown in the figure 2

    below to obtain the Average Daily Traffic (ADT) indicated in the last column as the Mean per

    day.

  • 8/12/2019 Final Year Project, Iga Dan

    27/67

    FINAL YEAR PROJECT 2011/2012

    16 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Figure 2 Summary of the traffic counts data used to obtain the ADT

    6-9am 12-3pm 5-8pm

    Mean

    per

    3hrs

    mean

    per

    12hrs

    6-9am 12-3pm 5-8pmMean

    per 3hrs

    mean

    per

    12hrs

    6-9a m 1 2-3p m 5 -8p m

    Mean

    per

    3hrs

    mean

    per 12hrs6-9am 2-3pm5-8pm

    Mean

    per

    3hrs

    mean

    per

    12hrs

    6-9am 12-3pm 5-8pm

    Mean

    per

    3hrs

    mean

    per

    12hrs

    Total mean per

    12 hrs for 5 days

    Pedestrians 218 91 175 161 645 255 101 173 176 705 223 105 200 176 704 193 132 202 176 703 122 124 134 127 507 3264

    Bicycles 17 10 20 16 63 11 12 13 12 48 6 9 6 7 28 11 3 11 8 33 6 4 4 5 19 191

    Motorcycles 133 107 156 132 528 130 98 172 133 533 152 112 140 135 539 174 127 211 171 683 132 143 121 132 528 2811

    Saloon cars and taxis 42 33 43 39 157 37 42 39 39 157 39 37 41 39 156 51 31 56 46 184 23 42 21 29 115 769

    Light Goods Vans:

    (Pickups, 4WD)61 41 49 50 201 71 43 50 55 219 63 62 51 59 235 54 46 63 54 217 41 39 26 35 141 1013

    Small Bus: Minibuses and

    Matatus16 8 10 11 45 14 11 6 10 41 7 12 5 8 32 4 13 6 8 31 2 2 0 1 5 155

    Medium Bus: Coasters 3 0 1 1 5 2 0 2 1 5 2 0 4 2 8 2 0 4 2 8 0 0 0 0 0 27

    Buses

    Light Single Unit Trucks:

    Dynas and tractors5 18 4 9 36 3 14 7 8 32 7 21 3 10 41 5 11 10 9 35 11 13 16 13 53 197

    Medium-Large Single Unit

    Trucks: Lorries, fusos0 6 2 3 11 0 3 0 1 4 0 2 0 1 3 0 5 0 2 7 0 0 0 0 0 24

    3 Hour Total 495 314 460 423 1692 523 324 462 436.3 1745 499 360 450 436.3 1745 494 368 563 475 1900 337 367 322 342 1368 8451

    Vehicle Class

    Traffic Tallying Form

    Area/Town: Kira Town Council

    Location: Kira Primary School 0+010

    COUN

    Project: Design of a sand seal for a low volume gravel road

    Road: Kira-Kito Road

    Name: IGA DAN 08/U/481

    Tuesday Wednesday Thursday Friday Saturday

  • 8/12/2019 Final Year Project, Iga Dan

    28/67

    FINAL YEAR PROJECT 2011/2012

    17 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    4.2.2 Cumulative Equivalent Standard Axle Loads

    Table 5 obtaining the Cumulative Equivalent Standard axles loads on the road

    Vehicle Class Axles Load/ kg

    EALF(Axles/8160)

    Numberper day

    ESAL

    Pedestrians 653Bicycles 38

    Motorcycles 562

    Saloon cars and taxis 1000 0.1225 154 19

    Light Goods Vans:

    (Pickups, 4WD)

    2000 0.2451 203 50

    Small Bus: Minibuses and

    Matatus

    3000 0.3676 31 11

    Medium Bus: Coasters 4500 0.5515 5 3

    Light Single Unit Trucks:Dynas and tractors 4000 0.4902 39 19

    Medium-Large Single Unit

    Trucks: Lorries, fusos

    7500 0.9191 5 4

    Buses 10000 1.2255 0

    TOTAL 107

    CESAL = ESAL 365 100R

    1 + R100

    x+y 1 + R100

    yWhere

    A= Total ESA / day

    R= Traffic growth rate which is taken as 4.5% per annum

    x= design life in years taken as 5 years

    y= number of years before start of design life

    = 107 365 1004.5

    1 + 4.5100

    10+1 1 + 4.5100

    1= 501,512

    CESAL= 0.502 MESAs

  • 8/12/2019 Final Year Project, Iga Dan

    29/67

    FINAL YEAR PROJECT 2011/2012

    18 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Thence the Cumulative Equivalent Standard Axle Loads applied on the road is 0.502 Million

    ESAs

    4.2.3 Traffic classification:

    From the TRL road note 31, the traffic class is obtained depending on the number of Equivalent

    Standard Axles as can be shown in the table 6 below

    Table 6 Traffic classification basing on the range of ESAs

    (MoWT Road Design Manual, 2010)

    The traffic classification of the road is LV6 T2 as the CESALs is 501,512 ESA

    4.3 Rainfall Assessment

    Annual rainfall estimates and maximum evaporation data obtained from the Meteorological

    Department is indicated in appendix II and the maximum evaporation in the hottest month was

    found as 180mm and the average annual rainfall over the last five years was found as 1387.4mm.

    4.3.1 Weinert Value

    This value is computed from the equation below;

    = 12 (MELTC, 2011)Where Ey is the evaporation in the hottest month of the year; in mm which

    according to the Kituuza Meteorological centre data is found to be 180mm

    and

    Pais the annual precipitation; in mm which is 1387.4 mm

  • 8/12/2019 Final Year Project, Iga Dan

    30/67

    FINAL YEAR PROJECT 2011/2012

    19 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    = 12 1801387.4

    = 1.56

    Thus the Weinert number is less than 4.

    4.4 Laboratory testsThe laboratory results obtained from the testing of samples obtained from the road to ascertain if

    the current material is suitable for re-use or modification or has to be removed entirely from the

    road and new material imported is shown in the appendix III.

    Three samples were obtained and thoroughly tested for the tests indicated in the methodology

    and they are all indicated in the appendix III

    4.4.1 MDD results:

    Chainage 0+010

    Figure 3 Proctor curve for chainage 0+010

    Max. Dry Density (MDD) = 1,775 Kg/m3

    Optimum Moisture Content (OMC) = 13.6 %

    1700

    1710

    1720

    1730

    1740

    1750

    1760

    1770

    1780

    9 10 11 12 13 14 15

    DryDensity(Kg/

    m3)

    Moisture Content %

    Proctor Curve

    Series1

  • 8/12/2019 Final Year Project, Iga Dan

    31/67

    FINAL YEAR PROJECT 2011/2012

    20 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Chainage 0+110

    Figure 4 Proctor curve for chainage 0+110

    Max. Dry Density (MDD) = 1,704 Kg/m3

    Optimum Moisture Content (OMC) = 12.1%

    Chainage 0+300:

    Max. Dry Density (MDD) = 1,660 Kg/m3

    Optimum Moisture Content OMC = 12.3%

    1,500

    1,520

    1,540

    1,560

    1,580

    1,600

    1,620

    1,640

    1,660

    1,6801,700

    1,720

    9.0 10.0 11.0 12.0 13.0 14.0 15.0

    DryDensity(Kg/m3)

    Moisture Content %

    Proctor Curve

    Series1

  • 8/12/2019 Final Year Project, Iga Dan

    32/67

    FINAL YEAR PROJECT 2011/2012

    21 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Figure 5 Proctor curve for Chainage 0+300

    4.4.2 Gradation Results:

    Chainage 0+010

    Figure 6 Sieve analysis for chainage 0+010

    1,560

    1,570

    1,580

    1,590

    1,600

    1,610

    1,620

    1,630

    1,640

    1,650

    1,660

    1,670

    9.0 10.0 11.0 12.0 13.0 14.0 15.0

    AxisTitle

    Axis Title

    Proctor Curve

    Series1

    0.0

    20.0

    40.0

    60.0

    80.0

    100.0

    120.0

    0.010 0.100 1.000 10.000

    Percentagepassing

    Diameter of particles (mm)

    Sieve analysis graph for chainage 0+010

  • 8/12/2019 Final Year Project, Iga Dan

    33/67

    FINAL YEAR PROJECT 2011/2012

    22 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Chainage 0+110

    Figure 7 Sieve analysis results for chainage 0+110

    Chainage 0+300

    0.0

    10.0

    20.0

    30.0

    40.0

    50.0

    60.0

    70.0

    80.0

    90.0

    100.0

    0.010 0.100 1.000 10.000

    PercentagePassing%

    Diameter of particles (mm)

    Sieve Analysis graph for sample from chainage 0+110

    0.0

    10.0

    20.0

    30.0

    40.0

    50.0

    60.0

    70.0

    80.0

    90.0

    100.0

    0.010 0.100 1.000 10.000

    Passing%

    Diameter (mm)

    Sieve analysis graph for chainage 0+300

  • 8/12/2019 Final Year Project, Iga Dan

    34/67

    FINAL YEAR PROJECT 2011/2012

    23 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    4.4.3 Plasticity Index results:

    Chainage 0+010:

    Figure 8 Plasticity Index results for chainage 0+010

    RESULTS

    Liquid Limit ( LL ) = 48.5%

    Plastic Limit ( PL ) = 34.6%

    Plasticity Index ( PI=LL-PL ) = 13.9%

    44.0

    45.0

    46.0

    47.0

    48.0

    49.0

    50.0

    51.0

    52.0

    53.0

    0 10 20 30 40 50

    Moisturecontent

    Number of blows

  • 8/12/2019 Final Year Project, Iga Dan

    35/67

    FINAL YEAR PROJECT 2011/2012

    24 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Chainage 0+110

    Figure 9 Plasticity index results for chainage 0+110

    RESULTS

    Liquid Limit ( LL ) = 44.3%

    Plastic Limit ( PL ) = 30.6%

    Plasticity Index ( PI=LL-PL ) = 13.7%

    42.5

    43.0

    43.5

    44.0

    44.5

    45.0

    45.5

    46.0

    0 10 20 30 40 50

    Moisturecontent

    Number of blows

  • 8/12/2019 Final Year Project, Iga Dan

    36/67

    FINAL YEAR PROJECT 2011/2012

    25 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Chainage 0+300

    Figure 10 Plasticity index results for chainage 0+300

    RESULTS

    Liquid Limit ( LL ) = 33.4%

    Plastic Limit ( PL ) = 21.0%

    Plasticity Index ( PI=LL-PL ) = 12.4%

    4.5 Analysis: Layer thickness Design

    Basing on the following results obtained in from the tests carried out above the base following

    design parameters were obtained;

    The range of the Weinert value is less than 4,

    The design cumulative equivalent standard axle loads (CESALs) was obtained as 0.502

    MESAsthus traffic class of LV6 T2

    The subgrade CBR was obtained in the range of 15-29.

    30.0

    31.0

    32.0

    33.0

    34.0

    35.0

    36.0

    37.0

    38.0

    0 10 20 30 40 50

    Moisturecontent

    Number of blows

  • 8/12/2019 Final Year Project, Iga Dan

    37/67

    FINAL YEAR PROJECT 2011/2012

    26 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    CHAPTER 5.0 CONCLUSIONS AND RECOMMNEDATIONS

    5.1 Summary

    This chapter has put into consideration the tests carried out and the results obtained the with the

    aid of design manuals and specifications, it has given the design suitable for this road of a sand

    seal as can be shown below;

    5.2 Conclusions:

    5.2.1 Inventory of the existing road condition

    The general condition of the road was in a very good condition thus in case of carrying out the

    sand seal, there will be need of slight reshaping.

    5.2.2 Traffic usage of the road:

    From the traffic flow analysis the traffic class of the road obtained in the results section is T2 isLow Volume LV6 hence LV6 T2 as the CESALs is 501,512 ESA

    5.2.3 Subgrade characteristics of the existing road

    The in-situ CBR values of the subgrade are generally good. If in-situ CBR values obtained from

    the DCP tests exceed 10% then the road foundation should be strong enough to carry traffic load

    on low volume roads. Hence the fact that the CBR values are in the range of 15-29 then subgrade

    is adequate and design Subgrade strength class S5. Below is figure 11 which shows the variation

    of CBR for the subgrade and base;

    .

    Figure 11 CBR variation with the chainage along the road

    0

    20

    40

    60

    80

    100

    120

    140

    0 100 200 300 400 500 600

    CBR(%)

    Chainage (m)

    CBR values for DCP test

    Subgrade

    Base

    Linear (Subgrade)

    Linear (Base)

  • 8/12/2019 Final Year Project, Iga Dan

    38/67

    FINAL YEAR PROJECT 2011/2012

    27 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    The CBR values for the base layer are of concern because, on low volume roads, the minimum

    allowable soaked CBR is 40%. The results show that the in-situ CBR values obtained average

    approximately 78% which is significantly higher than the minimum required soaked CBR; where

    the values are very low such as at chainage 0+010 being 40 there is need for strengthening and

    some modification may be necessary to improve the material characteristics.

    5.2.4 The design of the appropriate sand seal

    New Pavement Structure

    Given the above traffic, Weinert number, subgrade and sub-base CBRs and using the design

    chart in appendix III for N

  • 8/12/2019 Final Year Project, Iga Dan

    39/67

    FINAL YEAR PROJECT 2011/2012

    28 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    From the laboratory tests, the material used for the construction of the Base and sub-base gives

    desired properties of MDD, plasticity Index and gradation thus there is no need to import

    material and in cases of shortage the borrow pits where the material was initially obtained can be

    used to obtain more gravel material.

    The proposed surfacing is as shown in the table 8 below:

    Table 8 Proposed surfacing options

    Material Surfacing Binder to be used

    Quarry fines from

    Kira Town Council

    Sand Seal with Quarry fines Bitumen EmulsionK1-60 (80-100 Pen Base Bitumen)

    River Sand Sand Seal Bitumen EmulsionK1-60 (80-100 Pen Base Bitumen)

    New Pavement Structure

    Given the above traffic, Weinert number, subgrade and sub-base CBRs and using the design

    chart in appendix III for N

  • 8/12/2019 Final Year Project, Iga Dan

    40/67

    FINAL YEAR PROJECT 2011/2012

    29 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    REFERENCES

    Archondo-Callao, R.S. (1999). Paving of Unpaved Roads. Economically - Justified Paving Cost.

    Infrastructure

    BEUSCH A, HARTMANN P, PETTS R C, WINKELMANN P, (1997). Low cost road

    construction in Indonesia - Labor-Based Road Projects in Manggaria District.

    GIUMMARRA G (2001). Road Classifications, Geometric Designs and Maintenance Standards

    for Low Volume Roads. Research Report AR354, ARRB Transport Research Ltd,

    Vermont South, Victoria.

    Guidelines for the Geometric Design of Very Low Volume Local Roads (ADT

  • 8/12/2019 Final Year Project, Iga Dan

    41/67

    FINAL YEAR PROJECT 2011/2012

    30 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    APPENDICES

    Appendix I: DCP Test Data and Results:

    DCP test Data:

    Table 10 UK DCP test results for all the chainages (0+010 to 0+500)

    UK DCP Test Data SheetProject name Design of a Sand Seal for a Low Volume gravel Road; Case study: Kira-Kito Road

    Test number 1 2 3

    Chainage (km) 10 110 200

    Location Carriageway Shoulder Carriageway

    Lane number 0 0

    Offset (m) 0 0 0

    Direction

    Zero error (mm) 11 11 11

    Test date 17/04/2012 17/04/2012 17/04/2012

    Remarks Left hand side Right hand side Centreline

    Layers removed 0 0 0

    Surface type Unpaved Unpaved UnpavedSurface moisture Dry Dry Dry

    Surface thickness (mm)

    Surface condition

    Surface strength

    coefficient

    Base thickness (mm)

    Base condition

    Blows Depth (mm) Blows Depth

    (mm)

    Blows Depth

    (mm)

  • 8/12/2019 Final Year Project, Iga Dan

    42/67

    FINAL YEAR PROJECT 2011/2012

    31 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    0 32 0 25 0 17

    1 42 2 37 1 28

    2 47 2 42 1 34

    2 56 2 46 2 41

    2 63 3 52 2 46

    3 75 3 55 3 50

    3 86 5 65 5 58

    3 97 5 76 5 63

    3 110 5 90 5 69

    3 120 5 105 5 80

    3 134 5 110 5 93

    3 147 5 135 5 110

    3 158 5 150 5 124

    3 172 5 163 3 135

    3 185 5 175 3 145

    3 198 5 186 3 153

    3 212 5 199 3 160

    3 226 5 215 3 169

    3 241 5 243 3 175

    3 260 2 264 3 181

    3 282 2 278 3 189

    2 303 2 290 3 195

    2 328 2 300 3 205

    2 345 2 310 3 213

    2 359 2 320 3 222

    2 371 3 334 3 234

    2 384 3 343 3 248

    2 399 3 350 3 267

    2 412 3 356 2 280

    2 426 3 360 2 294

  • 8/12/2019 Final Year Project, Iga Dan

    43/67

    FINAL YEAR PROJECT 2011/2012

    32 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    2 443 3 364 2 308

    2 465 5 370 2 324

    1 490 5 373 2 340

    1 526 5 377 2 360

    1 566 7 380 1 386

    1 582 7 382 1 419

    1 590 10 389 1 442

    2 604 10 397 1 457

    2 615 10 406 1 470

    2 626 10 424 1 485

    2 634 10 443 1 495

    2 645 10 465 1 507

    2 654 10 487 1 520

    2 663 10 520 1 530

    2 672 5 540 1 542

    2 680 5 565 1 555

    2 690 3 583 1 569

    2 699 2 595 1 584

    2 709 2 607 1 600

    2 619 1 615

    3 635 1 630

    3 655 1 645

    2 666 1 660

    2 679 1 674

    2 689 1 690

    2 699 1 704

    2 710 1 718

    2 721 1 729

    2 730 1 742

    2 740 1 755

  • 8/12/2019 Final Year Project, Iga Dan

    44/67

    FINAL YEAR PROJECT 2011/2012

    33 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    2 750 1 768

    2 760 1 783

    2 769 1 795

    2 779 1 810

    UK DCP Test Data Sheet

    Project name Design of a Sand Seal for a Low Volume gravel Road; Case study: Kira-Kito Road

    Test number 4 5 6

    Chainage (km) 300 400 500

    Location Carriageway Shoulder Carriageway

    Lane number 0 0

    Offset (m) 0 0 0

    Direction

    Zero error (mm) 11 11 11

    Test date (dd/mm/yyyy) 17/04/2012 17/04/2012 17/04/2012

    Remarks Left hand side Right hand side Centreline

    Layers removed 0 0 0

    Surface type Unpaved Unpaved Unpaved

    Surface moisture Very Dry Dry Moderate

    Surface thickness (mm)

    Surface condition

    Surface strengthcoefficient

    Base type

    Base thickness (mm)

    Base condition

    Blows Depth (mm) Blows Depth (mm) Blows Depth (mm)

    0 15 0 11 0 22

    2 26 2 20 2 36

    2 34 2 26 2 45

    2 42 2 34 2 55

  • 8/12/2019 Final Year Project, Iga Dan

    45/67

    FINAL YEAR PROJECT 2011/2012

    34 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    2 51 2 40 2 61

    2 58 3 45 2 69

    2 67 5 51 2 75

    2 72 5 55 2 84

    3 80 10 68 2 92

    3 89 10 81 2 102

    3 96 10 101 2 111

    3 105 10 127 2 120

    3 113 7 150 2 130

    3 121 7 166 2 140

    3 130 7 186 2 147

    3 140 7 217 2 156

    3 150 5 242 2 165

    3 158 3 259 2 175

    3 167 3 280 2 185

    3 176 2 295 2 194

    3 186 2 308 2 205

    3 197 2 324 2 214

    3 211 2 343 2 225

    3 223 1 352 2 237

    3 245 1 373 2 253

    3 260 1 384 2 265

    3 272 1 395 2 279

    3 286 1 406 2 295

    3 302 1 419 2 309

    3 319 1 430 2 324

    3 337 1 440 2 340

    3 358 1 440 2 355

    2 375 1 450 2 373

    1 402 1 460 2 390

  • 8/12/2019 Final Year Project, Iga Dan

    46/67

    FINAL YEAR PROJECT 2011/2012

    35 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    1 445 1 470 2 405

    1 465 1 480 2 423

    1 480 1 490 2 438

    1 495 1 500 2 454

    1 509 1 510 2 470

    1 523 1 520 1 475

    1 538 1 530 1 482

    1 550 1 541 1 488

    1 564 1 554 1 495

    1 576 1 569 1 502

    1 590 1 580 1 510

    1 603 1 594 1 515

    1 615 1 608 1 523

    1 627 1 620 1 523

    1 639 1 633 1 530

    1 652 1 647 1 537

    1 665 1 662 2 552

    1 675 1 675 2 568

    1 689 1 690 2 581

    1 702 1 703 2 600

    1 715 1 715 2 618

    1 725 1 725 2 635

    1 725 1 739 2 654

    1 740 1 750 2 670

    1 755 1 762 2 689

    1 769 1 774 2 707

    1 785 1 785 2 729

    1 800 1 796 2 729

    1 815 1 809 2 751

    2 774

  • 8/12/2019 Final Year Project, Iga Dan

    47/67

    FINAL YEAR PROJECT 2011/2012

    36 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Layer boundary graphs and CBR graphs

    Chainage 0+010:

    Figure 13 Layer boundaries and CBR variation for chainage 0+010

    Chainage 0+110:

    Figure 14 Layer boundaries and CBR variation for chainage 0+110

  • 8/12/2019 Final Year Project, Iga Dan

    48/67

    FINAL YEAR PROJECT 2011/2012

    37 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Chainage 0+210:

    Figure 15 boundaries and CBR variation for chainage 0+210

    Chainage 0+300:

    Figure 16 boundaries and CBR variation for chainage 0+300

  • 8/12/2019 Final Year Project, Iga Dan

    49/67

    FINAL YEAR PROJECT 2011/2012

    38 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Chainage 0+400:

    Figure 17 boundaries and CBR variation for chainage 0+400

    Chain age 0+500:

    Figure 18boundaries and CBR variation for chainage 0+500

  • 8/12/2019 Final Year Project, Iga Dan

    50/67

    FINAL YEAR PROJECT 2011/2012

    39 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Histogram to indicate the Base CBR

    Figure 19 Histogram showing the base SBR (%)

  • 8/12/2019 Final Year Project, Iga Dan

    51/67

    FINAL YEAR PROJECT 2011/2012

    40 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Appendix II: Kituza Coffee Research Meteorological Station Data

    Long Term M ean (LTM ) Monthly Evaporation (mm) (PAN TYPE ....A........)

    Table 11 Monthly evaporation data for Kituza coffee research station

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    Mean 138 122 147 122 120 110 100 105 124 134 122 128

    Highest 163 144 169 138 140 129 115 134 154 180 139 175

    Lowest 87 101 124 113 107 94 76 78 95 104 111 97

    Monthly Maximum Fall of Rainfall (mm)

    Table 12 Monthly Maximum fall of rainfall for Kituza Station

    Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    2007 24.0 17.0 29.5 31.0 30.3 45.0 16.5 26.2 55.5 54.0 37.0 30.5

    2008 91.0 14.0 38.0 93.0 30.2 20.0 13.8 14.3 21.2 35.0 22.0 6.5

    2009 19.0 25.0 16.0 34.0 37.0 12.0 19.0 38.0 32.5 58.0 53.2 31.5

    2010 22.5 95.0 60.0 63.0 20.0 22.0 28.5 20.5 62.5 31.0 45.0 40.5

    2011 15.0 16.0 35.0 30.4 25.5 7.8 18.0 54.0 29.5 30.6 58.0 68.0

    Monthly Rainfall Totals (mm)

    Table 13 Montly Rainfall totals of Kituza station

    Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    2007 133.3 64.2 69.5 140.8 106.3 119.0 82.3 81.1 234.0 157.8 151.5 48.0

    2008 154.4 47.2 191.9 348.2 103.3 33.3 39.1 43.7 83.4 184.8 82.4 17.3

    2009 34.1 73.8 26.0 204.8 157.0 35.0 34.1 124.8 96.8 232.1 232.4 126.2

    2010 51.5 273.3 258.5 191.1 104.5 70.8 47.8 48.4 118.1 110.2 111.2 110.2

    2011 22.2 24.2 161.9 137.7 90.1 14.8 21.7 135.7 142.8 102.8 289.3 204.3

  • 8/12/2019 Final Year Project, Iga Dan

    52/67

    FINAL YEAR PROJECT 2011/2012

    41 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Appendix III Laboratory tests data:

    Table 14 Test results from Maximum Dry Density of the soil for chainage 0+010\

    DESIGN OF A SAND SEAL FOR A LOW VOLUME GRAVEL ROAD

    Project Road: Kira-Kito Road

    DATA SHEET FOR MOISTURE - DENSITY RELATIONS OF SOILS

    USING 4.54 KG. RAMMER ( OMC & MDD TEST ) As per BS 1377:Part 4

    Sample No: 1 Sampling Date: 17 -04-12

    Source/Location of Sample: Kira Kito Testing Date: 25 -04-12

    Km 0+100 LHS

    Sample Description : Red Gravel Material Technician: Iga Dan

    Proposed Use: Wearing C

    Mass of mould (g): 5,120 Volume (cm3): 2,299

    Specimen Number/Mould No. 1 2 3 4 5

    Mass of mould+base+compacted specimen ( m2 ) 9,480 9,640 9,758 9,730 9,680

    Mass of mould + base (m1) 5,120 5,120 5,120 5,120 5,120

    Mass of compacted specimen(m2-m1) 4,360 4,520 4,638 4,610 4,560

    Bulk Density = (m2-m1) x mould factor 1.896 1.966 2.017 2.005 1.983

    Moisture content container No

    Weight of wet soil + container m1 153.40 154.10 206.00 166.33 132.15 147.11 190.80 128.96 190.42 129.98

  • 8/12/2019 Final Year Project, Iga Dan

    53/67

    FINAL YEAR PROJECT 2011/2012

    42 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Weight of dry soil + container m2 143.81 142.24 187.23 150.97 119.96 133.11 169.90 117.00 169.90 117.00

    Mass of container m3 30.39 30.99 31.42 30.71 30.74 30.71 30.56 29.00 30.56 29.00

    Weight of water (m1-m2) 9.6 11.9 18.8 15.4 12.2 14.0 20.9 12.0 20.5 13.0

    Weight of dry sample (m2-m3) 113.4 111.3 155.8 120.3 89.2 102.4 139.3 88.0 139.3 88.0

    8.5 10.7 12.0 12.8 13.7 13.7 15.0 13.6 14.7 14.8

    Moisture content w (m1-m2)/(m2-m3) x 100 9.6 12.4 13.7 14.3 14.7

    Dry density = (100x bulk density)/(100+w) kg/m3 1,731 1,749 1,775 1,754 1,729

  • 8/12/2019 Final Year Project, Iga Dan

    54/67

    FINAL YEAR PROJECT 2011/2012

    43 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Table 15 Test results for Particle size analysis test (BS 1377: Part 2) for chainage 0+010

    DESIGN OF A SAND SEAL FOR A LOW VOLUME GRAVEL ROAD

    PROJECT: Kira-Kito Road

    PARTICLE SIZE ANALYSIS (BS 1377:Part 2)

    Sample reference :1 Sampling Date: 17

    -04-

    12

    Location Kira Kito Testing Date: 25

    -04-

    12

    Km 0+100 LHS

    Sample Description Red Gravel Material

    Initial wt before washing : Moisture Content :

    Dry wt after washing : Initial Dry Weight 1300

    Grading Modulus = 2.02

    Diameter Partial Cumulative Cumulative % Passing Grading Limits

    Retained Retained Retained

    (mm) Mass(g) Mass (g) (%) (%) (%)

    50.000 0.00 0.0 0.0 100.0

    37.500 0.00 0.0 0.0 100.0

    20.000 96.98 97.0 7.5 92.5

    10.000 24.85 121.8 9.4 90.6

    5.000 59.10 180.9 13.9 86.1

    2.360 247.12 428.1 32.9 67.1

    1.180 227.07 655.1 50.4 49.6

    0.500 286.22 941.3 72.4 27.6

    0.425 49.91 991.3 76.3 23.8

    0.300 92.04 1083.3 83.3 16.7

    0.150 104.59 1187.9 91.4 8.6

    0.075 14.82 1202.7 92.5 7.5

    Pan 2.49

  • 8/12/2019 Final Year Project, Iga Dan

    55/67

  • 8/12/2019 Final Year Project, Iga Dan

    56/67

    FINAL YEAR PROJECT 2011/2012

    45 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Weight of wet soil + container m1 103.27 115.98 149.51 144.15 134.14 151.57 168.74 128.96 208.60 129.98

    Weight of dry soil + container m2 97.02 108.45 138.21 133.46 123.08 138.42 153.22 117.00 186.14 117.00

    Mass of container m3 30.39 30.99 31.42 30.71 30.45 30.56 30.56 29.00 30.56 29.00

    Weight of water (m1-m2) 6.3 7.5 11.3 10.7 11.1 13.2 15.5 12.0 22.5 13.0

    Weight of dry sample (m2-m3) 66.6 77.5 106.8 102.8 92.6 107.9 122.7 88.0 155.6 88.0

    9.4 9.7 10.6 10.4 11.9 12.2 12.7 13.6 14.4 14.8

    Moisture content w (m1-m2)/(m2-m3) x 100 9.6 10.5 12.1 13.1 14.6

    Dry density =(100x bulk density)/(100+w) Kg/m3 1,521 1,620 1,700 1,647 1,606

  • 8/12/2019 Final Year Project, Iga Dan

    57/67

  • 8/12/2019 Final Year Project, Iga Dan

    58/67

    FINAL YEAR PROJECT 2011/2012

    47 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Table 18 Test results for the Moisture-Density Relatios of the soil (BS 1377: Part 4) for chainage 0+300

    DESIGN OF A SAND SEAL FOR A LOW VOLUME GRAVEL ROAD

    Project Road: Kira-Kito Road

    DATA SHEET FOR MOISTURE - DENSITY RELATIONS OF SOILS

    USING 4.54KG. RAMMER ( OMC & MDDTEST )

    As per BS 1377: Part4

    Sample No: Sampling Date: 17 -04-12

    Source/Location of Sample: Kira Kito Testing Date: 25 -04-12

    Km 0+300 LHS

    Sample Description : Red Gravel Material Technician:IgaDan

    Proposed Use: Wearing Course

    Mass of mould(g): 5,120

    Volume(cm3): 2,299

    Specimen Number/MouldNo. 1 2 3 4 5

    Mass of mould+base+compacted specimen ( m2 ) 9,030 9,190 9,380 9,400 9,370

    Mass of mould + base (m1) 5,120 5,120 5,120 5,120 5,120

    Mass of compacted specimen(m2-m1) 3,910 4,070 4,260 4,280 4,250

    Bulk Density = (m2-m1) x mould factor 1.701 1.770 1.853 1.862 1.849

    Weight of wet soil +container m1 140.32

    115.98

    208.60

    129.98 161.75 153.30

    138.74

    128.96 149.51

    144.15

    Weight of dry soil + containerm2 132.02

    109.75

    192.01

    120.45 147.61 140.49

    126.52

    117.00 134.91

    129.46

    Mass of container m3 30.39 30.99 31.42 30.71 30.90 30.52 30.56 27.00 33.56 29.00

    Weight of water (m1-m2) 8.3 6.2 16.6 9.5 14.1 12.8 12.2 12.0 14.6 14.7

    Weight of dry sample (m2-m3) 101.6 78.8 160.6 89.7 116.7 110.0 96.0 90.0 101.4 100.5

    8.2 7.9 10.3 10.6 12.1 11.6 12.7 13.3 14.4 14.6

    Moisture content w (m1-m2)/(m2-m3) x 100 8.0 10.5 11.9 13.0 14.5

    Dry density = (100x bulk density)/(100+w) kg/m3 1,574 1,602 1,656 1,647 1,614

  • 8/12/2019 Final Year Project, Iga Dan

    59/67

  • 8/12/2019 Final Year Project, Iga Dan

    60/67

    FINAL YEAR PROJECT 2011/2012

    49 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Appendix IV: Design Charts

  • 8/12/2019 Final Year Project, Iga Dan

    61/67

    FINAL YEAR PROJECT 2011/2012

    50 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

  • 8/12/2019 Final Year Project, Iga Dan

    62/67

    FINAL YEAR PROJECT 2011/2012

    51 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

  • 8/12/2019 Final Year Project, Iga Dan

    63/67

    FINAL YEAR PROJECT 2011/2012

    52 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

  • 8/12/2019 Final Year Project, Iga Dan

    64/67

    FINAL YEAR PROJECT 2011/2012

    53 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

  • 8/12/2019 Final Year Project, Iga Dan

    65/67

    FINAL YEAR PROJECT 2011/2012

    54 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

  • 8/12/2019 Final Year Project, Iga Dan

    66/67

    FINAL YEAR PROJECT 2011/2012

    55 | P a g e Iga Dan 08/U/481 Bsc. Civil Engineering

    Appendix IV: Photographs of the project execution

    Figure 20Assembling of the DCP test equipment

    Figure 21 Applying blows to the soil to get penetrations

    Figure 22 Recording of pentrations

    Figure 23 Measuring of the distances from one chainageto another

    Figure 24 The Kira-Kito road condition

  • 8/12/2019 Final Year Project, Iga Dan

    67/67

    FINAL YEAR PROJECT 2011/2012

    Figure 25 Ruler used to measure the penetration Figure 26 Sampling to obtain samples for laboratorytests