finalization of master plan stege elementary school presentation may 14, 2013 powell & partners,...

23
FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

Upload: pamela-bennett

Post on 17-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

FINALIZATION OF MASTER

PLAN

STEGE ELEMENTARY SCHOOL PRESENTATIONMAY 14, 2013

POWELL & PARTNERS, ARCHITECTS

Page 2: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

SITE PLAN

PROJECT EXPERIENCE AT POWELL & PARTNERS

EXISTING CONDITION

Page 3: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

EXISTING SITE CONDITIONS ANALYSIS

PROJECT EXPERIENCE AT POWELL & PARTNERS

SITE PLAN

Page 4: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

SITE DEVELOPMENT GOALS

SITE & AREA PLAN

Page 5: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

SITE PLAN

NEW CONDITION

Page 6: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

FLOOR PLAN

PROJECT EXPERIENCE AT POWELL & PARTNERS

NEW CONDITION

Page 7: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

SITE PLAN

PROJECT EXPERIENCE AT POWELL & PARTNERS

NEW LANDSCAPE SCHEME

Page 8: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

SITE PLAN

PROJECT EXPERIENCE AT POWELL & PARTNERS

NEW LANDSCAPE IMAGERY

Page 9: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

ELEVATIONS

NEW CONDITION

Page 10: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

POWELL & PARTNERS, ARCHITECTS

SCHEDULE NO. 1

Page 11: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

POWELL & PARTNERS, ARCHITECTS

SCHEDULE NO. 2

Page 12: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

SCHEDULE NO. 3

POWELL & PARTNERS, ARCHITECTS

Page 13: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

PRELIMINARY BUDGET

Powell & Partners

Page 14: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

PHASING PLAN – OPTION 1

PROJECT EXPERIENCE AT POWELL & PARTNERS

New Condition

Page 15: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

PHASING PLAN – OPTION 2

NEW CONDITION

Page 16: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

TYPICAL KINDERGARTEN CLASSROOM

PROJECT EXPERIENCE AT POWELL & PARTNERS

NEW CONDITION

Page 17: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

TYPICAL GRADE 1-3 CLASSROOM

PROJECT EXPERIENCE AT POWELL & PARTNERS

NEW CONDITION

Page 18: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

TYPICAL GRADE 4-6 CLASSROOM

PROJECT EXPERIENCE AT POWELL & PARTNERS

NEW CONDITION

Page 19: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

LIBRARY

PROJECT EXPERIENCE AT POWELL & PARTNERS

NEW CONDITION

Page 20: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

PLAY STRUCTURES

PLAYGROUND TYPES

Page 21: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

PLAY STRUCTURES

PROJECT EXPERIENCE AT POWELL & PARTNERS

PLAYGROUND THEMES

Page 22: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

PLAY STRUCTURES

NATURAL PLAYGROUNDS

Page 23: FINALIZATION OF MASTER PLAN STEGE ELEMENTARY SCHOOL PRESENTATION MAY 14, 2013 POWELL & PARTNERS, ARCHITECTS

PLAY STRUCTURES

TREE HOUSE

SQUIRREL

RACOON

TALK TUBE

LOG STEPPER MAZE TREE CLIMB

LADDER