financing energy and climate ppp based infrastructures ... · financing energy and climate ppp ....
TRANSCRIPT
Financing Energy and Climate PPP based Infrastructures: Experiences and Emerging Trends
Venice, May 9th ,2014
1
PPPs are no silver bullet solution...
Potential challenges
Loss of public sector control &
flexibility
— Government with limited control over future system design/configuration as needs change
Transaction & monitoring costs/time
— Fixed transaction costs (e.g. mgt time, advisor) relative to project size — Supervision and monitoring costs
Higher cost of capital
— Cost of capital of private sector often higher – except developing countries
— Issue of unmanageable risks, e.g. currency, demand
Misaligned incentives
— Imperfect regulation, regulatory lobbying & capture — Incomplete contracts: renegotiations and disputes due to external
changes — Externalities (Civil consensus, ...)
2
...but PPPs have potential advantages (not just private finance)...
Less white-elephant projects • Chile using PPP filters out about 30% of projects • No bidder interest • Improvement of projects after market sounding
— Double due diligence — No bias of green- vs. brownfield
Improved project
selection
Accelerated infra provision
Potential PPP advantages
Revenue innovation
Whole life-cycle cost optimization
— Overcoming public financing /funding constraints
— Accelerates macro benefits
— Life-cycle dependency (D-B-O-M) — Risk unbundling and re-allocation
(private vs public) — Efficient operations, economies of
scale & technology investment
— Maximizing capacity & utilization — Price segmentation — Innovative & ancillary services
Examples / evidence
Good track-record of on-time project completion • Example Australia: PPPs 3.4% ahead of
schedule; traditional 23.5% behind time
Cost savings of 10-20% • Australia : 7-23% • UK: 17%
High potential for ancillary revenues
3
Cop
yrig
ht ©
201
4 by
The
Bos
ton
Con
sulti
ng G
roup
, Inc
. All
right
s re
serv
ed.
Horizon Electricity integrated Airports Railroads Highways
Oil & Gas T&S Ports
... and Private infra investments with attractive risk-return profile Financial analysis of publicly listed infrastructure operators
Electricity T&D
TSR (10 yrs.)
ROCE
Electricity generation Water
10%
5%
0% 0.9%
9.0% 7.6%
3.5% 4.1%
7.8% 6.9% 6.6% 4.6%
Ret
urn
20%
10%
0%
10.7% 6.9% 7.8% 8.3% 10.1%
15.8% 8.7%
21.5%
10.8%
EBIT margin 45% 21% 25% 23% 16% 18% 14% 14% 13%
Volatility (%)
Beta
Ris
k
20 21 23 26 18 25 15 18 17
0.56 0.57 0.61 0.74 0.43 0.72. 0.49 0.57 0.43
Note: Volatility is calculated as the market-value weighted average of the standard deviation of monthly total shareholder returns (TSR) of individual firms over the last 5 years. Betas are derived from regressing local returns against broad local stock market indices using the last 5 years of monthly returns and aggregating individual firms by equal weighting. Source: BCG analysis; Datastream, Rothballer/Kaserer 2012: The risk profile of infrastructure investments, Journal of Structured Finance (forthcoming)
would be 4.7% excluding
Veolia
4
Cop
yrig
ht ©
201
4 by
The
Bos
ton
Con
sulti
ng G
roup
, Inc
. All
right
s re
serv
ed.
How to be sure to get it right (I) ? BCG-WEF PPP best-practice framework
Source: World Economic Forum, BCG
Project preparation
Balanced risk allocation & regulation
Bankable feasibility
study
Conducive enabling environment
Public-sector readiness
Private-sector readiness
Civil-society readiness
Life-cycle assessment of public vs.
private delivery
(VfM test)
Integrated infra plan &
cost-benefit based project prioritization
Project origination
Rigorous monitoring
of B and O & ex-post
evaluation
Competitive, transparent tendering
& financing support
Project implementation
Long-term contracts need long-term commitment &
resources
Whole life-cycle instead of
opportunistic approach
A PPP programme – not a series of transactions
PPP and privatization design - Economic Regulation - June2012.pptx 5
Cop
yrig
ht ©
201
2 by
The
Bos
ton
Con
sulti
ng G
roup
, Inc
. All
right
s re
serv
ed.
How to be sure to get it right (II) ? Economic regulation design framework
Regulatory framework Regulatory process
Alignment Levers
• Legislation • Design of politically independent institutions • Public sector capacity
Market design
Risk allocation • Information gathering & monitoring
• Stakeholder consultation
• Rate reviews • Appeals,
arbitration and dispute resolution
Regulatory governance & enabling environment
Objectives
3
4
7
5 6
Design principles
1
2
• Operator attractiveness: Profit • State & customer safeguarding: affordability, capacity, quality
Price / revenue regulation
• Requirements & recognition
• Concession duration, ownership, governance
Service regulation • Safe-
guards • Link to
financials
Service regulation
Capex regulation
PPP and privatization design - Economic Regulation - June2012.pptx 6
Cop
yrig
ht ©
201
2 by
The
Bos
ton
Con
sulti
ng G
roup
, Inc
. All
right
s re
serv
ed.
• Demand • Commodity cost • Maintenance • Labour • Technology
1 - Align the evaluation of the risks of the investment and allocate them properly
Prototypical risk allocation between public and private sector
Design Build Financing Operations
• Site acquisition • Permits • Ground
conditions • Protests
• Delay • Cost overrun • Sub-contractor • Material
• Interest rate • Financing
availability
Political
Macro
• Law change • Tax change • Change of regulation
• Inflation, x-rate
• Force Majeure • Economic growth
Risk typically allocated to public sector
Risk typically shared or allocated to public/private sector
Risk typically allocated to private sector
Changing perception of the risk in energy
PPP and privatization design - Economic Regulation - June2012.pptx 7
Cop
yrig
ht ©
201
2 by
The
Bos
ton
Con
sulti
ng G
roup
, Inc
. All
right
s re
serv
ed.
2 – Clear definition and stability of the overall market design and segment bundling decision (I)
Assess competitiveness of value chain segments
Decide on segment bundling/unbundling1
Decide on market design
A B C
Each value chain segment of the infrastructure service to be analyzed along the factors
• Economies of scale & scope • Other entry barriers
… yielding an assessment of the potential competitiveness
Value chain segments are then either bundled or unbundled
• Unbundled: preferred option due to benefits of competition
• Bundled: if high coordination costs or political constraints
… yielding the market segmentation
For each market segment, the type of competition or regulation needs to be decided
• In-market competition • For-market competition • Price regulation
… yielding the final market design
Example
1. Unbundling is the separation of competitive and non-competitive value chain segments in an industry Source: BCG analysis
Infra- structure
Terminal operation
Ground services
Facility mgt.
Non- Aviation
"Competitive" "Monopolistic"
Infra- structure
Terminal operation
Ground services
Facility mgt.
Non- Aviation
Unbundling Bundling
Infra- structure
Terminal operation
Ground services
Facility mgt.
Non- Aviation
Competition Regulated monopoly
Toward a New Balance of Power - Long version - English - 9Mar13.pptx 8
Cop
yrig
ht ©
201
3 by
The
Bos
ton
Con
sulti
ng G
roup
, Inc
. All
right
s re
serv
ed.
Transport
2 – Clear definition and stability of the overall market design and segment bundling decision (II)
Sales and DSOs
Centralized generation and storage
TSO
Consumption
1980–1990: Vertical integration
Sales
Trading
Centralized generation and storage
DSO
Consumption
Distributed generation
2000–2010: Unbundling
Energy trading
Distribution and transport (excluding metering)
Steered consumption
Trading
DSO
Centralized generation and storage
Metering and communication
Sales and decentral markets
Distributed generation and storage
~ 2020+: Deconstruction
TSO
TSO
Toward a New Balance of Power - Long version - English - 9Mar13.pptx 9
Cop
yrig
ht ©
201
3 by
The
Bos
ton
Con
sulti
ng G
roup
, Inc
. All
right
s re
serv
ed.
3 – Clear definition of the pillars of the price regulation and their alignment with the industry specific requirements
Regulatory scope
• Full regulation
• Partial regulation
– with subsidy
• Partial regulation
– w/o subsidy
Pricing methodology • Usage based
– Rate of return
– Price /
revenue cap
(I-X+-E)
– Liberalization
• Availability
contracts
Review frequency
• Annual
• 2-3 years
• 4-5 years
• > 5 years
Price regulation
Key determinants for
fair price
• WACC
• Regulated asset
base
Source: BCG analysis
Capex management
• Inclusion options
• Requirements
• Enforcement
Hot issues
PPP and privatization design - Economic Regulation - June2012.pptx 10
Cop
yrig
ht ©
201
2 by
The
Bos
ton
Con
sulti
ng G
roup
, Inc
. All
right
s re
serv
ed.
Sector Type of regulation
Rate-of-Return regulation still dominant vs. I-X regulation However, over last two decades increasing use of I-X
Electricity
Gas/Water
Transport
Telecom
Percentage of countries
Mobile services 22 41% 36% 23%
Fixed-line services 23 35% 43% 22%
Fixed-line network 24 50% 29% 21%
Airports 19 42% 37% 21%
Ports 16 25% 6% 69%
Road 16 38% 38% 25%
Rail 19 63% 21% 16%
Water supply 16 63% 19% 19%
Gas distribution 24 71% 25% 4%
Gas transmission 23 70% 26% 4%
Distribution 22 55% 41% 5%
Transmission 24 67% 29% 4%
Generation 20 15% 5% 80%
RoR/Cost-based regulation I-X incentive regulations Liberalization 1. Rate-of-return and other cost based approached 2. Price Cap as well as other incentive regimes Note: Data from OECD countries. Cost-based regulation includes Rate-of-Return regulation and other cost-based approaches. Incentive regulation includes Price Cap as well as other incentive regimes, e.g. revenue caps Source: Égert, B. (2009) Infrastructure investment in network industries: The role of incentive regulation and regulatory independence, CESifo Working Paper
Usage-based models—Overview
PPP and privatization design - Economic Regulation - June2012.pptx 11
Cop
yrig
ht ©
201
2 by
The
Bos
ton
Con
sulti
ng G
roup
, Inc
. All
right
s re
serv
ed.
4 - Adaptive regulation to cope with unpredictability & cyclicality if clear regulatory governance
Regulator roles and responsibilities
Political independence
Decision-making autonomy
Enablement and capability-building
a b c d
Thank you
bcg.com | bcgperspectives.com