hie-isolde hebt: characteristics
DESCRIPTION
HIE-ISOLDE HEBT: characteristics. Beamline diameter: 40 mm (REX: 100 mm) Beamline height: 1.75 m Beamline vacuum: low 1e-7- high 1e-8 mbar Connection of setups: Beamline ends with fast vacuum valve, DN40 - PowerPoint PPT PresentationTRANSCRIPT
HIE-ISOLDE HEBT: characteristicsBeamline diameter: 40 mm (REX: 100 mm)Beamline height: 1.75 mBeamline vacuum: low 1e-7- high 1e-8 mbar
Connection of setups:Beamline ends with fast vacuum valve, DN40On the setup’s side: permanent KF40 double cross with a Penning and Pirani connected to ISOLDE vacuum interlock
Space for experiments – between cable trench and Jura wall
Moving equipment: from new SAS, along the wall
Trench 88cm
Beamine cable trays
Space for experiments – on this side of the trench
• Setup• Electronics + dewars• Cable path• Patch panel
Surveyors’ reference pole (position to be discussed)
Miniball cables length is 15m
5.1 m
2.6 m
1:100
MINIBALL
Miniball - Requirements:
Electricity needs:• Power – setup, pumps:• Power – electronics:• 3 phase plugs:
63A 32A electronics, 10A PC, 16A setup one 3 phase plug
Signals from/to ISOLDE (e.g. proton or laser pulse)
SC, Proton on target, EBIS, laser pulse
Cable trays yes
Gases -
Cryogenics yes
Mechanical support structures -
trench
Ca. 1.3 m
Trench below experiments will be reinforced to keep stability and withstand the weight
1.75 m Ca. 1.2 m
235
cm
87 cm
270
cm
90 cm
trench
Beamine cable trays
Space for experiments – on this side of the trench
Please mark:• Setup• Electronics• Cable path
Surveyors’ reference pole (position to be discussed)
Ion beam focus: in the middle of the trench
trench
Beamine cable trays
Space for experiments – on this side of the trench
Please mark:• Setup• Electronics• Cable path
Surveyors’ reference pole (position to be discussed)
Ion beam focus: in the middle of the trench
ACTAR
Requirements for ACTAR TPC:
Electricity needs:• Power – setup, pumps: • Power – electronics:• 3 phase plugs:
Standard vacuum system, vol ≈100 lt≈2 kW detector power supplies---
Signals from/to ISOLDE (e.g. proton or laser pulse)
Proton, gate, Laser, EBIS
Cable trays Detector to electronic racks: not necessary
Gases C4H10, D2, He, Ar, CO2…
Cryogenics No
Mechanical support structures To be decided
Beam focal pointMiddle of the trench
Active target chamberGas
control/bottles
Gas control
Electronics
Electronics
Electronics
Beam pipe,auxiliary detectors,safety valves
Mk: Can it move to the right?
trench
CF40 valve
If possible: leave space for a CF40 cross with vacuum gauges
Beam focus
Ca. 1.3 m
Trench below experiments will be reinforced to keep stability and withstand the weight
1.75 m Ca. 1.2 m
Active target chamber
Beam pipe,auxiliary detectors,safety valves
Requirements:
Electricity needs:• Power – setup, pumps:• Power – electronics:• 3 phase plugs:
Signals from/to ISOLDE (e.g. proton or laser pulse) Cable trays
Gases
Cryogenics
Mechanical support structures
Please mark your setup and electronics
Beam focal pointMiddle of the trench
Please mark your setup and connections
Movable
trench
CF40 valve
If possible: leave space for a CF40 cross with vacuum gauges
Beam focus
Ca. 1.3 m
Trench below experiments will be reinforced to keep stability and withstand the weight
1.75 m Ca. 1.2 m
Demineralised 27-deg waterCompressed air, gas lines
power
Movable power box
Requirements - CORSET:
Electricity needs: 2 racks for NIM crates
Signals from/to ISOLDE (e.g. proton or laser pulse)
Pulse arrival
Cable trays -
Gases -
Cryogenics -
Mechanical support structures
▪ Reaction chamber with diameter of 0.75 - 1 m
▪ 2 racks for NIM crates; can be installed remote
▪ No special devices for the mounting of CORSET are needed
The CORSET Spectrometer
rotatable
Si stop detectorTOF(MCP detectors)
0.5 – 1 m Si detector
TOF detector
The CORSET Spectrometer
CORSET reaction chamber at GSI
1 m
Needs for the Installation of CORSET
▪ Reaction chamber with diameter of 0.75 - 1 m
▪ 2 racks for NIM crates; can be installed remote
▪ No special devices for the mounting of CORSET are needed
Please mark your setup and electronics
Beam focal pointMiddle of the trench
rota
tabl
e
Si st
op d
etec
tor
TOF
(MCP
det
ecto
rs)
0.5 – 1 m
electronics
Requirements – tilted foils:Tilted Foils b-NMR setup
Electricity needs:• Power – setup, pumps:• Power – electronics:• 3 phase plugs:
1 x 64 Amp (magnet supply + pumps)2 x 16 Amp not required
Signals from/to ISOLDE (e.g. proton or laser pulse)
signals from EBIS
Cable trays No special trays required
Gases No
Cryogenics Not considered for the moment
Mechanical support structures Adjustable height
General overview
General overview
Magnet support –adjustable height