floor plans, infrastructure logistics hie-isolde spectrometer workshop physics department, lund...

46
Floor plans, Infrastructure & Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

Upload: leona-mcdowell

Post on 18-Jan-2018

227 views

Category:

Documents


0 download

DESCRIPTION

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 3 Isolde Today

TRANSCRIPT

Page 1: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

Floor plans, Infrastructure & Logistics

Hie-Isolde Spectrometer Workshop

Physics Department, Lund University

10 March, 2011

Hie-Isolde

Erwin Siesling

Page 2: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 2

Abstract

• Isolde today• Hie-Isolde – The Energy upgrade

– Planning– Civil Engineering,

Cryogenics and Ventilation – Superconducting Linac

and Beam Transfer Line• User requirements?• Impact on Isolde & REX operation• User facilities (under discussion)• Future projects

Page 3: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 3

Isolde Today

Page 4: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 4

Isolde Today

Target ZoneTarget Zone

Page 5: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 5

Isolde Today

Separator zonesGPS and HRS Separator

Page 6: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 6

Isolde Today

Experimental hall: Beam deliveryExperimental hall: Beam delivery

Page 7: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 7

Isolde Today

REX post-accelerating Linac

Miniball experiment

REX post-accelerating Linac

Page 8: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 8

From Isolde to Hie-Isolde Step by Step

Page 9: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 9

Hie-Isolde Planning

A simplified presentation of the different stages:

-What is the impact on operations?

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

2011 2012 2013 2014 2015 2016

CivilMain services

CryoCM 1&2 CM 3&4

5.5MeV/u10MeV/u

Beam Transfer Line

CM 5&6

Page 10: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 10

Civil Engineering

Construction starting date: June 2011

Page 11: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 11

Civil EngineeringRemoval of the transport hangar

Page 12: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 12

Civil EngineeringTerrain flattening

Page 13: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 13

Civil EngineeringNew SAS

September 2011

Page 14: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 14

Civil EngineeringMove of the controlled access

September 2011

Page 15: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 15

Civil EngineeringCompressor Building

Start end September 2011

Page 16: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 16

Civil EngineeringCold Box Building

Civil Engineering finished by July 2012

Page 17: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 17

Main ServicesElectrical systems, Cooling & Ventilation

Page 18: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 18

Electrical systems: July 2012 – March 2013 Cooling & Ventilation: Aug 2012 – March 2013

Main Services

Page 19: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling

Ventil units

19

Cooling & Ventilation

Page 20: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 20

Cooling & Ventilation

Page 21: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling

Ventilation unit Cooling unit

21

Cooling & Ventilation

Page 22: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling

Cooling units

22

Cooling & Ventilation

Page 23: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling

Cryo equipment

23

Cryogenics

Compressors: April 2013 – October 2013 Cold Box & Cryo-line: Jan 2014 – June 2014

Page 24: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 24

Hie-IsoldeNew controlled access point

Page 25: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 25

Hie-Isolde

Page 26: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 26

Hie-Isolde

Page 27: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 27

Hie-Isolde

Page 28: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 28

SC Linac

Cutting walls & install tunnel: long 2013 shutdown

Cold Line: January 2014 – June 2014 Allowing a normal 2012 REX / Miniball run

Page 29: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 29

Modular installation

Cryo Modules 1 & 2: July 2014 – Oct 2014

REX physics at 5.5MeV/u for 2015 First beam at 5.5MeV/u autumn 2014

High β

Low β

1 2 3 4

5 6

Page 30: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 30

Cryo Modules 3 & 4: January - April 2016

Modular installation

High β

Low β

1 2 3 4

5 6

Final Energy 10MeV/uCryo Modules 5 & 6: January - April 2017

Page 31: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 31

Hie-Isolde SC Linac

5.5MeV/u by the autumn of 2014 First 10MeV/u by April 2016

Hie-Isolde SC Linac:

Page 32: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 32

Beam Transfer Line

Page 33: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 33

Beam Transfer Line

Straight line with 2 branches – July 2013 - April 2014 Miniball move: Oct 2013 – April 2014

Miniball

Actar / HeliosMiniball

Beam diagnostics

Stage 1:

Page 34: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 34

Beam Transfer Line

The bend Spectrometer installation and 2nd Miniball move

MiniballSpectrometer Actar / HeliosMiniball

Stage 2:

TSR

TSR and beyond.. Stage 3:

Page 35: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 35

User Requirements

Requirements for the experimentsInfo needed on:

• Power consumption• Cooling & ventilation• Cryogenics• Alignment & spacing (nr of racks)• Sensitivity to radiation, temp & vibrations• Transport requirements

Page 36: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 36

Isolde & REX Operations

long shutdown 2013 Lin4 major sdsd sd sdCM1&2

Isolde & REX Operations:

/////

///// shutdown Isolde & REX perturbations REX stop

Main serv.

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

2011 2012 2013 2014 2015 2016

CivilMain services

CryoCM 1&2 CM 3&4

5.5MeV/u10MeV/u

Beam Transfer Line

CM 5&6

Jan 2013 Aug 2014

Page 37: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 37

User Facilities

1. Increasing the surface of the Solid State Lab in building B.115:For RP safety reasons all solid state activities will be moved from B.275 to B.115This will suppress the existing workshop in B.115 and courtyard between B.115 and B.601

 2. Replace the existing building 507 by a new full concrete building :

Ground floor (only accessible from within the surveyed area): - Labs and workshop

First floor (accessible from outside the surveyed area):- Data Acquisition rooms- Visitor Centre - Kitchen

Long shutdown 2013?

under discussion

Page 38: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 38

Present situation (ground floor Jura side):

Control room

User Facilities

Page 39: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 39

Solid State Lab 115

1. Increasing the surface of the Solid State Lab in B.115:

Control room

Page 40: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 40

Replace building 507

Control room

2. Replacing the existing building 507 by a new building - Ground floor (only accessible from within the surveyed area):

Page 41: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 41

Control room

2. Replacing the existing building 507 by a new building - First floor (accessible from outside the surveyed area):

Replace building 507

Page 42: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 42

TSR @ Hie-Isolde

TSR Max Planck Institute Heidelberg

TSR@HIE-ISOLDELOI submitted Jan 2011 (K. Blaum, Y. Litvinov)

Future

Page 43: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 43

TSR @ Hie-Isolde

Would the TSR fit? No.

CH F

But could be an option for additional beamlines

Page 44: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 44

TSR @ Hie-Isolde

Page 45: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 45

TSR @ Hie-Isolde

Possible TSR installation above the CERN cable-tunnel. Tilted beamline coming up from the machine.

Page 46: Floor plans, Infrastructure  Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling

HIE Infrastructure, Lund 10 March 2011 Erwin Siesling 46

Acknowledgement

• EN/HDO: YACINE KADI,• BE/RF : MATTEO PASINI• GS/SE : DANIEL PARCHET, ELISEO PEREZ-DUENAS• EN/CV : PAUL PEPINSTER, BENOIT BELLIN-CROYAT• EN/EL : RENE NECCA• TE/CRG : NICOLAS DELRUELLE, JOS METSELAAR• EN/STI : ANA-PAULA BERNARDES, RICHARD CATHERALL• EN/MEF : STEPHANE MARIDOR• GS/DI : CYRILLE BEDEL• TE/MSC : YANN LECLERCQ