status and future perspective of the hie-isolde project

30
Status and Future Perspective of the HIE- ISOLDE Project IBS-RISP @ CERN, November 19-20, 2012 [email protected]

Upload: cora-flores

Post on 02-Jan-2016

37 views

Category:

Documents


0 download

DESCRIPTION

Status and Future Perspective of the HIE-ISOLDE Project. IBS-RISP @ CERN, November 19-20, 2012 [email protected]. OUTLINE. Scope of HIE-ISOLDE Upgrade of ISOLDE Facility: HIE- ISOLDE R&D A ctivities Outlook for 2012. ISOLDE: the ISOL-type RIB facility at CERN. Pulsed 1.4 GeV - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Status and Future Perspective of the  HIE-ISOLDE Project

Status and Future Perspective of the HIE-ISOLDE Project

IBS-RISP @ CERN, November 19-20, [email protected]

Page 2: Status and Future Perspective of the  HIE-ISOLDE Project

OUTLINE

2

Scope of HIE-ISOLDE

Upgrade of ISOLDE Facility: HIE-ISOLDE

R&D Activities

Outlook for 2012

Page 3: Status and Future Perspective of the  HIE-ISOLDE Project

3

ISOLDE: the ISOL-type RIB facility at CERN

Pulsed 1.4 GeV Proton beam

Courtesy D. Voulot

Page 4: Status and Future Perspective of the  HIE-ISOLDE Project

4 Courtesy F. Wenander

Page 5: Status and Future Perspective of the  HIE-ISOLDE Project

5

Motivation

The High Intensity and Energy (HIE) ISOLDE project builds on the success of the REX-ISOLDE post-accelerator and will focus on the upgrade of the REX facility but also aims to improve the target and front-end part of ISOLDE to fully profit from upgrades of the existing CERN proton injectors (LINAC4 and PSB Upgrade):

Higher energy for the post-accelerated radioactive

beam

More beams (Intensity wise and different species)

Better beams (High purity beams, low emittances,

more flexibility in the beam parameters)

Page 6: Status and Future Perspective of the  HIE-ISOLDE Project

6

HIE-ISOLDE aims at increasing the energy of these RIB up to 10A MeV and their intensity by a factor 10

Energy Upgrade:The HIE-ISOLDE project concentrates on the construction of the SC LINAC and associated infrastructure in order to upgrade the energy of the post-accelerated radioactive ion beams to 5.5 MeV/u in 2015 and 10 MeV/u by 2016

Intensity Upgrade:The design study for the intensity upgrade, also part of HIE-ISOLDE, starts in 2012, and addresses the technical feasibility and cost estimate for operating the facility at 15 kW once LINAC4 and PS Booster are online.

Page 7: Status and Future Perspective of the  HIE-ISOLDE Project

7

NuPECC Long Range Plan 2010 Timeline for RIB Facilities

Page 8: Status and Future Perspective of the  HIE-ISOLDE Project

8

Superconducting LINAC installed in Three Phases

3 stages installation 1.2 MeV/u

3 MeV/u

5.5 MeV/u

10 MeV/u

Now

2014

2016

>2017

Page 9: Status and Future Perspective of the  HIE-ISOLDE Project

9

HIE-ISOLDE SC LINAC

Page 10: Status and Future Perspective of the  HIE-ISOLDE Project

10

R&D activities (2008 – 2011)

Page 11: Status and Future Perspective of the  HIE-ISOLDE Project

Proposed stage 1 HEBT layout

Page 12: Status and Future Perspective of the  HIE-ISOLDE Project

Latest HEBT design – stage 2bAll details on EDMS (HIE-ISOLDE/HEBT LINES OPTICS AND LAYOUT) Drawings, layout tables and (new) madx reference optics files

Page 13: Status and Future Perspective of the  HIE-ISOLDE Project

13

Planning

?

?

Page 14: Status and Future Perspective of the  HIE-ISOLDE Project

14

Civil EngineeringCompressor and Cold Box Building

Civil Engineering finished summer 2012

Autumn 2012 !

Page 15: Status and Future Perspective of the  HIE-ISOLDE Project

B. 170

B. 198B. 199

Racks sub systems

Electrical systems: Oct 2012 – June 2013

Page 16: Status and Future Perspective of the  HIE-ISOLDE Project

16

Cooling & Ventilation

Cooling & Ventilation: Oct 2012 – June 2013

B. 199 cold box buildingB. 198 compressor building

Experimental hall 170

Page 17: Status and Future Perspective of the  HIE-ISOLDE Project

17

Modular Linac & Cryo LineCourtesy: Stephane Maridor

Cryo Cold Line- stage 1: January 2014 – June 2014

20155.5MeV/u

Linac CM 1&2 - stage 1: August 2014 – October 2014

Sep 2014 – Feb 2015

Page 18: Status and Future Perspective of the  HIE-ISOLDE Project

18

Cryo Cold Line- stage 2

Modular Cryo Line

Linac CM High-β 1,2,3&4 - stage 2a

Courtesy: Stephane Maridor

2016 ?10MeV/u

Page 19: Status and Future Perspective of the  HIE-ISOLDE Project

19

Cryo Cold Line- stage 2

Modular Cryo LineCourtesy: Stephane Maridor

2017 ?

Linac CM High-β 1,2,3 & 4, Low-β 1&2 - stage 2b

Chopper Line

and Chopper Line

Page 20: Status and Future Perspective of the  HIE-ISOLDE Project

Call for Letters of Intent (deadline May 21 2010)

• 34 Letters submitted• 284 Participants from 76 Laboratories in 22 Countries• 30 LOIs make use of the Energy and Intensity

increases; 4 of the intensity upgrade only • Major mechanisms are Coulex (13) and transfer(16); elastic scattering(3); fission(2)• (3) letters concern masses and moments; (4)

astrophysics and (5) major new instrumentation• Major subjects: Nuclear shapes ; Shell evolution; Halo

properties; Nuclear astrophysics

Page 21: Status and Future Perspective of the  HIE-ISOLDE Project

Miniball + T-REX• Segmented Ge array • Inner Si-strip detection for charged

particles (T-REX)• No show stopping beam requirements

but would benefit from slow extraction and buncher/chopper

setup Geometrical properties

Energy properties(FWHM values)

Timing Power

MINIBALL

(+general purpose reaction chamber)

<3mrad + 2-3mm FWHM diameter (at 5-10 MeV/u energy)*

En. Spread: <1e-3

En. Accuracy: <1%

En. Stability: ?

Would profit from microstructure required by HELIOS

About 26 kW

Page 22: Status and Future Perspective of the  HIE-ISOLDE Project

Helios

• Solenoid for transfer reactions

• Needs buncher/chopper for TOF measurement with 2 ns resolution

setup Geometrical properties

Energy properties(FWHM values)

Timing Power

HELIOS 3mrad + 5mm FWHM diameter at 5-10 MeV/u

En. Spread: <1e-3

En. Accuracy: <1%

En. Stability:

Important (for 10MeV/u):

resolution <2ns on target

repetition rate: 1/100 ns

no background (<1% acceptable)

below 25 kW

Page 23: Status and Future Perspective of the  HIE-ISOLDE Project

ACTAR

• Active target for resonant scattering and transfer reactions

• Allows to measure with very low intensities

setup Geometrical properties

Energy properties(FWHM values)

Timing Power

ACTAR

(input: R. Raabe)

<2 mrad + 3mm FWHM diameter at 5-10 MeV/u*

En. Spread: <1e-2

En. Accuracy:

En. Stability:

About 25 kW

Page 24: Status and Future Perspective of the  HIE-ISOLDE Project

24

BUDGET

Page 25: Status and Future Perspective of the  HIE-ISOLDE Project

25

OUTLOOK Civil Engineering Works completed

Installation of Main Services (EL, CV, others)

Decision on the procurement of Cryogenic Plant (FC Dec. 2012)

Ready to launch procurement of first batch of high-beta cavities => via CATE + others

Ready to launch procurement of CM1 and CM2 => via CATE

Ready to launch procurement of HEBT phase-1

Cost and Schedule Review (22-23 Nov. 2012)

Page 26: Status and Future Perspective of the  HIE-ISOLDE Project

26

Thank you

HIE-ISOLDE web site -> http://hie-isolde.web.cern.ch/hie-isolde/

CATHI-ITN web site -> https://espace.cern.ch/Marie-Curie-CATHI/default.aspx

Page 27: Status and Future Perspective of the  HIE-ISOLDE Project

27

Acknowledgements

The ISOLDE CollaborationThe HIE-ISOLDE Project Team and groups within CERN Accelerator and Technology SectorThe Swedish Knut and Alice Wallenberg Foundation (KAW 2005-0121) The Belgian Big Science program of the FWO (Research Foundation Flanders) and the Research Council K.U. Leuven The CATHI Marie Curie Initial Training Network: EU-FP7-PEOPLE-2010-ITN Project number 264330.The Spanish Programme “Industry for Science” from CDTI

Page 28: Status and Future Perspective of the  HIE-ISOLDE Project

HIE-ISO

LDE Project

1. Project Management

2. Linac Systems

4. Installation&

Commissioning

3. Infrastructure&

Integration

8.3 Access System GS/ASE

8.2 Radioprotection DG/SCR

HIE-LIN

ACD

esign Study

5. Target Study

6. Target Area and Class-A Lab Integration

7. Injection & Beam distribution

8.4 Access System GS/ASE

8. Safety

2.1 Cavity RF BE/RF

2.2 Cavity Design manufacturing EN/MME TE/VSC

2.3 Beam dynamics BE/RF-ABP

2.4 Cryomodules TE/MSC EN/MME

2.5 Beam Instrumentations BE/BI

2.6 SC Solenoid TE/MSC

2.7 Beam transfer line (magnets) TE/MSC

2.8 Linac Integration EN/MEF2.9 Vacuum TE/VCS2.10 Survey BE/ABP

3.4 Electrical systems EN/EL

3.5 Cryogenic system TE/CRG

3.6 Power converters TE/EPC

3.7 Industrial Control system EN/ICE

4.1 Single cavity test BE/RF

4.2 Cryomodule test BE/RF

4.3 Transport & Handling EN/HE

3.8 Beam Control system BE/CO

5.1 Target design EN/STI-HE

5.2 Front Ends EN/STI TE/EPC-ABT

5.3 Beam Diagnostics BE/BI

6.1 Layout upgrade EN/MEF

6.2 Cooling and ventilation EN/CV

6.3 Electrical systems EN/EL

6.4 Vacuum TE/VCS

6.5 Survey BE/ABP

6.6 Civil engineering GS/SEM

6.7 LL Control system EN/STI

7.1 Off line separator EN/STI

7.2 Separator areas EN/STI

7.3 Experiment Hall EN/MEF

7.4 Beam lines BE/ABP

Steering Committee International Advisory Panel

8.1 Safety Coordinator GS/DI

3.1 Civil Engineering GS/SEM3.2 Integration EN/MEF3.3 Cooling ventilation EN/CV

3.9 Interlocks TE/MPE

4.4 Planning & Installation EN/MEF

4.5 Linac commissioning BE/RF-OP

1.1 Project Leader – Y. Kadi (EN/HDO)

1.2 Project Safety Coordinator – A.P. Bernardes

1.3 Technical Coordinator – M. Pasini BE/RF

1.4 Design Study Coordinator–R.Catherall EN/STI

1.5 Budget and Planning – E.Delachenal EN/GMS

1.6 Administration – E. Cochet EN/GMS

Work Breakdown Structure

Page 29: Status and Future Perspective of the  HIE-ISOLDE Project

29

Acknowledgements

International Collaboration

I. Goulas

International Advisory Panel

A. Bracco

Steering Committee

M. Huyse

Physics CoordinationMaria Garcia-Borge

Linac System

W. Venturinia

Design Study

R. Catherall

SafetyA.P. Bernardes

SafetyWorking Group

Design Study

Working Group

Linac Commissio

ningWorkingGroup

Cryo-modulesWorkingGroup

RFAccelerati

ngWorkingGroup

BeamDynamicsWorkingGroup

Technical Coordination

Y. Kadi

Project ManagementY. Kadi

Infrastructure &

IntegrationWorking

Group

Infrastructure&

IntegrationE. Siesling

High-EnergyBeam

Transfer WG

PhysicsWorking Group

Page 30: Status and Future Perspective of the  HIE-ISOLDE Project

Research Training Themes Addressed by the CATHI Proposal

(56 FTE over 4 years)

Y. Kadi HIE-ISOLDE Proposal, IEFC, August 21, 2009HIE-ISOLDE General Meeting, 19 March 2010 30