hie-isolde project status report yacine kadi cern hie-isolde project

27
HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Upload: evangeline-moore

Post on 19-Jan-2016

225 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

HIE-ISOLDE ProjectStatus Report

Yacine KADICERN

HIE-ISOLDE Project

Page 2: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

2

OUTLINE

Status of the Technical InfrastructureResults from the Machine CommissioningFuture PlansConclusions

HIE-PCG meeting, Y. Kadi, 21 Sep. 2015

Page 3: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

3

Water station B197

Technical Infrastructure (E. Siesling)

HIE SC Linac

Equipment platform

High Energy Beam Transfer lines

HEBT

Compressor building 198

Cold Box building 199

ISOLDE target zone

ISOLDE Low Energy

Page 4: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Cryo System: fully commissioned. Liquid He made.

Cryogenic Plant

4

Page 5: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Cryo Cold Line & all 6 Jumper Boxes: installed and instrumentedPressure tests done on Cold Line.

5

Cryo Distribution Line

Page 6: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

HEBT Lines

6

MiniBall

Scattering Chamber

Page 7: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Cryo-Module 1 installed on Saturday 2nd May.Cool-down: mid-June to mid-July

7

SC Linac

Page 8: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

CM1 HW commissioning: main results (W. Venturini)

8

Cryogenics: ~100% availability over 2 months, then problems (4 CB stops + incident)

Vacuum: in range of 10-11 mbar Cold alignment: ~1.2 mm vertical offset corrected Cavity conditioning OK, only CAV2 has FE Cavity tuning OK: all cavities at 101.28 MHz, mid range Cavity performance: 6 MV/m/CAV with less than 50 W Serious issue with power coupler identified Solenoid performance: OK, “feature” under control Combined powering cavities and solenoid OK Static heat load measured within specs ( ~ 10 W) LLRF loops working well beyond specs at 2 MV/m

Page 9: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Issues for phase 1: RF coupler

9

Observation: RF drifts when driving cavities at high power to initially assumed operational bandwidths thermal effects in the power coupler

Potential showstopper

Actions taken:

• Dedicated test in SM18 permanent damage at 200 W• Post mortem analysis• Second test in SM18 OK after 9 hours at 60 W• Test bench at room temperature: no damage with 500 W

for 1 hour, or 250 W for 24 hours• Third test in SM18 week 36, testing possible fix• Adapting low level RF loops to reduce bandwidth as much

as possible (now 3 Hz 50 W seemed possible)• On Saturday 29th August, CAV4 powered at 14 W

(minimum requirement for operation) for 24 h clear signatures of degradation!

80 W !

Page 10: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Testing possible fix at SM18 (A. Miyazaki)

10

Addition of a Thermal Anchor

Page 11: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Coupler with the additional thermal anchor (50W 9h)

11

Page 12: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Coupler Powering (A. Miyazaki)

12

black: without anchorred: with anchor

Time constant p1 is shorter by factor two with same reflected power

Page 13: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Coupler Cooling (A. Miyazaki)

13

black: without anchorred: with anchor

Time constant p1 is shorter by factor seven with same reflected power

Page 14: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Coupler Temperature (A. Miyazaki)

14

185

160

135

110

85

60 Cu b

lock

tem

pera

ture

[K]

65

60

55

50

45

40

35

Cu b

lock

tem

pera

ture

[K]

Without Thermal Anchor

With Thermal Anchor

Page 15: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Effect on Eacc (A. Miyazaki)

15

black: without anchorred: with anchor

Page 16: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Adapting the LLRF (D. Valuch et al.)

16

• On 13/09/2015 all five cavities were successfully powered and locked using an automatic sequence

• Relatively stable operation at 2.5MV/m with 3Hz bandwidth• Field quality in per-cent/degree mode. Worse than the specification, with sufficient

power we can do much better. • rms power limited to ~20W, saturation set to 40W• Coupler gets damaged at 80W for 24 hours.

Page 17: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Adapting the LLRF (D. Valuch et al.)

17

Microphonics is the limiting factor for low power operation

Low frequency vibrations (1-5Hz), higher frequency vibration (50Hz) in the cryostat not yet understood

Perturbations are seriously affecting the cavity field – operation at high field (>3MV/m) without tightly locked loops is not possible

Cavity 4 coupler collapsed, but cavity operational at >3Hz bandwidth => Field limitation

Cavity 5 coupler motor is not fully operational – bandwidth can not be set to more than 2Hz

Page 18: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Adapting the LLRF: next steps (D. Valuch et al.)

18

Localize the source of vibrations Measure the microphonics in Generator Mode Switch off pumps and other equipment, 10-15 minute cycle time

Deploy new firmware and FESA class to address minor bugs Implement automatic cavity sequence (new FESA class) Start preparing the OP interaction (MachineSetpoint property)

Attempt to lock all cavities at higher than 2.5MV/m (yield 6MV/m): Need to increase the power limit, otherwise not possible. Closely monitor the Forward power for deposited heat

Page 19: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Cryolab Test Set-up (T. Koettig)

19

First cool-down is planned for this MondayThe goal is to measure the temperature distribution along the coax cable and coupler antenna first w/o RF powerThen start powering with stepwise increase in RF power until we see a thermal runawayTest set-up will be used also to qualify new RF coupler assembly

Page 20: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

HIE ISOLDE roadmap 2015

20

w1 w2 w3 w4 w6 w7 w8 w9 w10 w11 w12 w13 w14 w15 w16 w17 w19 w20 w21 w22 w23 w24 w25 w26 w27 w28 w29 w30 w32 w33 w34 w35 w36 w37 w38 w39 w40 w41 w42 w43 w44 w45 w46 w47 w48 w49 w50 w51

CM1 Assembly

CM1 Installation & Test Transport test Installation, warm testsCM commissioning: 11 weeks

XT00 Installation&Tests Powering Survey&Al.

XT001 Installation&Tests PoweringSurvey&Al. Smoothing alignment

XT002 Installation&Tests Survey&Al.Powering Smoothing alignment

Cryogenics Facilities

Machine Checkout Dry runs 2/3 weeks

REX-ISOLDE REX refurbishment and hardware commissioning Powering REX beam commissioning

Beam Commissioning 5/6 weeks

Physics at 4.3 MeV/u 4 weeks Run extension ?

July August September October November DecemberJan-15 February March April May June

Tests related to RF coupler limitations

Possible interleaving

All HEBT hardware commissioned on scheduleCM1 cooled down and hardware tests completeIssue with power coupler looking for an operational pointCryogenics Incident on 12th August

Cryo incident Aug 12th

Page 21: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Overall Summary• Enormous progress since April 2015

• Infrastructure in place• HEBT hardware commissioning completed• CM1 installed, cooled and powered. Full test campaign carried out• REX beam commissioning well advanced • Beam commissioning of SC Linac is possible in September

• The results of hardware tests (problem on RF couplers) highlighted that CM1 is not fully qualified for sustained operation as planned

• Agree with Collaboration on a common scope for 2015 Physics run

Page 22: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Thank you for your attention

Page 23: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

DBoxes commissioning in

XT00-XT01S. Sadovich (BE/BI)

Page 24: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

DB status in XT00 – XT01• FC – Faraday Cup

• SS – Scanning slit

• Coll – Collimator slit

• Stripping foils are not installed

LBD1FC; SS; Coll; SD

SBD1FC; SS;

Coll

SBD2FC; SS;

Coll

SBD3FC; SS;

Coll

SBD4FC; SS;

Coll

SBD5FC; SS; Coll; SD

LBD2FC; SS;

Coll

LBD3FC; SS;

Coll

LBD4FC; SS;

Coll

CM1

Wal

l

Problems:• Short cut (cup - repeller) in FC in SBD1• Leak/Broken SS in SBD5

All instruments inLBD1 SBD1 SBD2 SBD3 SBD4 SBD5are installed and checked with beam (FC)

All instruments inLBD2 LBD3 LBD4are installed and ready to be checked with beam

XT01

XT00

Page 25: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Next steps

• As soon as beam available:• Testing profile measurement in all DBs• Testing emittance measurement option• TOF measurements

• As soon as scheduled:• Change SS in SDB5

• Winter SD:• Repair FC in SDB1

Page 26: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

Proposed beam line layout

Page 27: HIE-ISOLDE Project Status Report Yacine KADI CERN HIE-ISOLDE Project

HIE-ISOLDE Roadmap

I

II

III

Legend:

Existing REX-structures:RFQ, IHS: 20-gap IH-structure, 7GX: 7-gap split-ring cavities, 9GP: 9-gap IH-structure

Beam phaseswk 14/2015 SD 2015/16

SD 2016/17 SD 2016/17

REX