hiradmat users meeting 29/5/2015 adrian fabich eucard-2 is co-funded by the partners and the...

12
HiRadMat – Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme, Grant Agreement 312453

Upload: doreen-gilbert

Post on 18-Jan-2018

215 views

Category:

Documents


0 download

DESCRIPTION

Feed-throughs Between TNC and TT61 Used already by GlassyC/dBM Inserts - viewing windows arrived at CERN to be installed early June 29/5/2015A. Fabich3 EDMS SPSLHRM_0060

TRANSCRIPT

Page 1: HiRadMat  Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,

HiRadMat –Users Meeting

29/5/2015

Adrian Fabich

EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme, Grant Agreement 312453

Page 2: HiRadMat  Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,

A. Fabich 2

HiRadMat beam …

• GlassyC is installed

Waiting for beam …• Some pulses on 15. May• Now waiting for improvements of SPS extraction

29/5/2015

Page 3: HiRadMat  Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,

A. Fabich 3

Feed-throughsBetween TNC and TT61• Used already by GlassyC/dBM

Inserts - viewing windows• arrived at CERN• to be installed early June

29/5/2015

EDMS SPSLHRM_0060

Page 4: HiRadMat  Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,

A. Fabich 4

TT61 setup

• TT61 will be equipped with– A standard SPS 19” rack (600 mm x 800 mm)– A table

29/5/2015

Page 5: HiRadMat  Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,

A. Fabich 5

Cabling databaseDocument in finalization (EDMS 1415953)• Permanent cabling installed

– Connecting TNC and TJ7 (patch rack)– Connecting TJ7 and control room

Already installed, to be added to DB:– Connecting TNC and TT61– 5 x NE48 (TT61 connector to be exchanged)– 12 x CK50

29/5/2015

Page 6: HiRadMat  Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,

A. Fabich 6

Cabling overviewAn experimental TNC table is equipped with:

From Control Room– 6 x NE48

• 5 x can be used in manual mode• 1 x on automatic plug-in

– 24 x CK50 e.g. for BPM read-out– Several HV cables – manual mode, e g. for BPM supply

From TT61– 5 x NE48 from TT61

• 5 x on automatic plug-in• E.g. for strain gauges

– 12 x CK50• E.g. for high frequency signals (from BPM)

– Dedicated experimental cables (subject to discussion) via empty cable ducts• E.g. fibre optics• Max diameter 35 mm (also for connectors)• Beyond 35 mm requires dedicated study using 3rd feed-through with inner diameter 100 mm

29/5/2015

Page 7: HiRadMat  Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,

A. Fabich 7

Cable proposal forHRMT22 – Ptarg• 5 x NE48 from Control Room

– 2 x in auto-plug-in mode for horizontal stage• Merge to one NE48?

– 2 x in manual mode for vertical stage• Merge to one NE48?

– 1 x in auto-plug-in for LEDs• 2 x NE48 from TT61

– auto-plug-in for vacuum gauges/controls• 4 x CK50 from TT61

– For BPM• No fibres foreseen

This is a preliminary list to be completed by the system responsibles.

29/5/2015

Page 8: HiRadMat  Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,

A. Fabich 8

Cable proposal for HRMT24 – BeGrid

• 4 x NE48 from Control Room– 2 x in manual mode for vertical stage– 1 x in auto-plug-in for LEDs– 2 x in manual mode for For BPKG/BTV

• CK50 from Control Room– For BPKG/BTV

• 5 x NE48 from TT61 – In auto-plug-in for strain gauges

• Fibres required?

Such a list should be- Prepared by each experiment- Re-iterated with HRM coordination

29/5/2015

Page 9: HiRadMat  Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,

A. Fabich 9

Cable proposal for HRMT 27 - RodTarg

NE48 ? :• 1 x Thermocouple cable 24 pairs, Type K• 1 x Thermocouple cable 8 pairs, Type N• 1 x NE8 copper cable

Special cables – to be discussed:- Should be reduced to a minimum

- Space in feed-throughs is limited- Optimizing installation effort

• 2 x Radiation hard camera cables• 3 x Optic fibres respecting the standard G.652• 1 x LumaSense Pyrometer Optic fibre:

http://www.lumasenseinc.com/uploads/Products/Impac/pdf/Datasheets/Pyrometer/Series_740/IGA740_IGA740_LO_Datasheet.pdf

• 2 x PANDA PM Optic Fibers

29/5/2015

Page 10: HiRadMat  Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,

A. Fabich 10

Schedule

29/5/2015

Consider 1-2 additional weeks of back-up for beam slot

Page 11: HiRadMat  Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,

A. Fabich 11

Subsistence for travel/accommodationEuCARD-2 “Transnational Access”

29/5/2015

Do not hesitate sending requests to [email protected] info: https://espace.cern.ch/hiradmat-sps/Wiki%20Pages/[email protected]

Page 12: HiRadMat  Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,

A. Fabich 12

Safety file

• See recommendations by Technical Board

– https://edms.cern.ch/project/CERN-0000094595

• Submit response to [email protected] ADVANCE TO BEAM TIME!