NORTHRIDGE RENOVATION PROPOSED CONCEPT PLAN
June 2016
![Page 2: HRCA's Proposed Concept Plan for Northridge Renovation](https://reader036.vdocument.in/reader036/viewer/2022062503/58889bc41a28ab264b8b4e4d/html5/thumbnails/2.jpg)
RECREATION CENTER AT NORTHRIDGEBuilding History
1982 - Original building completed by Developer – Mission Viejo
1986 - Addition - Gym
2001 - Addition of Cardio & Weight Area $6.2M
2013 - Men’s and Women’s Showers Renovated $80K - McKinstry Energy Saving Project $1.0M
2015 - Gym and Racquetball Flooring replaced $156K - Racquetball Court Renovation – Ongoing $23K/court
![Page 3: HRCA's Proposed Concept Plan for Northridge Renovation](https://reader036.vdocument.in/reader036/viewer/2022062503/58889bc41a28ab264b8b4e4d/html5/thumbnails/3.jpg)
PLANNING PROCESS Goal: Collect suggestions for improving facilities Identify future capital needs
Facilities Focus Group – Delegates & Members invited – June 2014
• Improve Northridge Entrance and Lobby Areas• Replace Northridge Gym Floor• Refurbish Northridge Racquetball Courts
Frequent Users Survey – All Facilities – June 2014
• 72% - Northridge should be 1st Rec. Center to be updated & remodeled - 267 Surveys
• 94% - Facebook Survey also agreed - 71 Surveys
![Page 4: HRCA's Proposed Concept Plan for Northridge Renovation](https://reader036.vdocument.in/reader036/viewer/2022062503/58889bc41a28ab264b8b4e4d/html5/thumbnails/4.jpg)
SPACE PLANNING PROJECTAugust 2015 – March 2016
• Barker Rinker Seacat - Nat’l. Architectural Consultant
• Examined usage data (Open to Close) – (All facilities)
• Take a fresh look at space utilization• Resource document (64 pages) • Staff tied findings into proposed improvements for Northridge• Improvements tested for feasibility
NORTHRIDGE RENOVATION CONCEPT PLAN• Populous - Int’l. Award Winning Sports Facility Design Firm
• Staff & Board Input - Developed Concept Plan.
![Page 5: HRCA's Proposed Concept Plan for Northridge Renovation](https://reader036.vdocument.in/reader036/viewer/2022062503/58889bc41a28ab264b8b4e4d/html5/thumbnails/5.jpg)
![Page 6: HRCA's Proposed Concept Plan for Northridge Renovation](https://reader036.vdocument.in/reader036/viewer/2022062503/58889bc41a28ab264b8b4e4d/html5/thumbnails/6.jpg)
![Page 7: HRCA's Proposed Concept Plan for Northridge Renovation](https://reader036.vdocument.in/reader036/viewer/2022062503/58889bc41a28ab264b8b4e4d/html5/thumbnails/7.jpg)
![Page 8: HRCA's Proposed Concept Plan for Northridge Renovation](https://reader036.vdocument.in/reader036/viewer/2022062503/58889bc41a28ab264b8b4e4d/html5/thumbnails/8.jpg)
![Page 9: HRCA's Proposed Concept Plan for Northridge Renovation](https://reader036.vdocument.in/reader036/viewer/2022062503/58889bc41a28ab264b8b4e4d/html5/thumbnails/9.jpg)
![Page 10: HRCA's Proposed Concept Plan for Northridge Renovation](https://reader036.vdocument.in/reader036/viewer/2022062503/58889bc41a28ab264b8b4e4d/html5/thumbnails/10.jpg)
NEXT STEPSFOR 2017 COMPLETION
• Proposed Concept Plan on the website for Delegate/Member review. • Public comment sent to Annie [email protected]• Staff to review suggestions / comments• July 2016 - Delegate Update - Request approval to move forward
• July 2016 - RFP’s to Architects and Contractors• August – Begin Design Process• November – Budget Approval
• April 2017 - Begin Construction• Oct. – Nov. - Complete Construction