HS2 – Britain’s new high speed railwaySusan Bridges, Engagement ManagerAlan Payne, Project ManagerAndy de Bell, BBV Community Engagement ManagerAlex Esslemont, Engagement Manager
8 February 2018
-
Agenda items
• Key Contacts
• Programme update
• MWCC Introduction
• Traffic management
-
Area North Engagement Team & Partners
3
Jonathan LordSenior Engagement Manager – Area North
Susan BridgesEngagement Manager –
Joan GoodenEngagement Executive
Tahir Ahmed Engagement Manager –
Rachel JohnsonEngagement Manager -
Rachna ShahEngagement Executive
EWC
Alex
Esslemont
Laing
O’Rourke and
Murphy &
Sons (JV)
MWCC
Andy de Bell
Balfour
Beatty Vinci
MWCC
Geoff
Durand
Balfour
Beatty Vinci
EWC - Enabling Works Contractor• Surveys, environmental & habitat creation, highway works, compound set up
MWCC - Main Works Contractor • Design and construction of main assets – embankments, cuttings, viaducts, bridges, tunnels
-
Programme
2018 2019 2020 2021 2022 2023 2024 2025 2026
1 Surveys and bat house
2 A46 compound
3 Outline Design
4 Detailed design
5 Main Works
6 Env. works
7 Retaining Wall
8 Highway works – Ashow Rd
9 Highway works – Stoneleigh Rd
10 A46 bridge
9 Rail Systems
High Level Programme
-
Construction Work in the vicinity of Stoneleigh PC
Bat house
Woodland Planting
Ashow Road BridgeB4115
Signalisation of A46 junction if WCC new roundabout does not process
Stoneleigh Road bridge & new entrance to Stoneleigh Park including new roundaboutB4113
Environmental works to create new habitat
New A46 bridge Temporary diversion of A46 to enable constructionTemporary new southbound access from compound
HS2 site compound and stockpile areas
-
A46 Improvements – Warwickshire County Council
We are working closely with Warwickshire County Council & Stoneleigh Park.
Opportunities to use new roundabout to reduce construction traffic impact
-
www.gov.uk/hs2
MWCC Key Dates/ Programme Update
-
8
MWCC - Overall programme
ADVANCE WORKS
Video on GI now or with HS2 piece?
-
Stage One Gateway Process
9
Now
-
10
MWCC - Indicative Design & Construction Start Dates
Key Asset
Detail
Design
Start
Indicative Construction
Start date & duration
B4113 alignment, overbridge, roundabout and Park access
Q4 2019 2022
Stoneleigh Park retaining wall Q2 2019 Q1 2020 to Q4 2022
Stoneleigh Park overbridgesQ2 2019 &
Q2 2020
Q3 2020 until Q2 2021 & Q3 2021 to Q4
2022
River Avon Viaduct Q2 2019 Q3 2021 to Q3 2022
B4115 underbridge Q2 2020 Q4 2021 to Q3 2022
A46 OverbridgeQ4 2020 Finalising programme
-
www.gov.uk/hs2
Traffic Management Strategy
-
Route-wide Traffic Management Plan
HS2’s overall objectives for managing transport, traffic and highways for the delivery of the Project are set out within the RTMP.
Code of Construction Practice
Environmental Statement
HS2 Phase 1 Act provisions
Undertakings and Assurances
Route-wide TMP
Rights
Obligations
Practice
-
Predicted HS2 Traffic Flows from the Environmental Statement
-
HS2 Traffic Liaison Groups and Interfacing Meetings
Formal consultation with WCC Highways over highway works and transport routes
-
Lorry Routes Management• We have a route wide Undertaking to ensure highest standards for vehicles – engagement with haulage/industry
suppliers• All lorries to be Euro6 standard by 2020 – highest environmental standards with lowest emissions and highest fuel
efficiency• Lorry routes are set out in the Environmental Statement & agreed with the Highway Authority – with routes signed• A vehicle monitoring system will record vehicles entering sites in order to measure and assure that the sites do not
breach flow limits.• HS2 Lorries will have indicators for ease of recognition• All lorries will have 360 degree or 4 way cameras recordable for four weeks• All drivers will be required to undertake urban rural driver safety training – new standards created • HS2 will monitor contractor performance
-
Thank you