huckabee construction update april 2012

12
Huckabee GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012

Upload: georgetown-independent-school-district

Post on 21-May-2015

480 views

Category:

Education


5 download

DESCRIPTION

Presented at April 16, 2012 Board of trustees Meeting.

TRANSCRIPT

Page 1: Huckabee Construction Update April 2012

Huckabee

GEORGETOWN ISD2010 BOND PROGRAM UPDATE

A P R I L 2 01 2

Page 2: Huckabee Construction Update April 2012

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 2

Huckabee

TABLE OF CONTENTS

East View High School Phase 2 Additions, Package 2 3

Georgetown High School Additions and Renovations 7

Completed Projects 12

Page 3: Huckabee Construction Update April 2012

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 3

Huckabee

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2Original: $25,574,000

CATE Addition – $2,121,338Baseball & Softball Turf - $880,000

Total - $28,575,338

Existing East View High School

A. New Athletic AdditionB. New Fine Arts AdditionC. New Academic AdditionD. New CTE BuildingE. New ROTC Addition (Alt.)F. New Tennis CourtsG. New Tennis Building H. New Baseball/Softball Fieldhouse,

Bleachers, Lighting & Pressbox I. New Practice FieldsJ. New Parking (1,070 spaces)

A

B

C

D

F

J

GH

B

J

J

J

J

Bid Package 1

E

Highway 29

CR 104

HH

I

I

Academic Wing

CTE Building

Softball Field House

First Floor

Second Floor

New Academic Addition

New Academic Addition

New Fine Arts Addition

New Athletic Addition

New CTE/ROTC Addition

General Contractor

Page 4: Huckabee Construction Update April 2012

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 4

Huckabee

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2

ACADEmIC ADDITION• Interior partition installation is nearing completion.• Exterior masonry veneer is currently being installed around the academic wing.• Roof structure, decking and insulation are in place. Finished metal roof panels will start

being installed next.

ATHLETIC ADDITION• Exterior masonry veneer is complete at the locker room addition• Ceiling installation and wall painting has begun at the locker rooms.• Exterior masonry veneer is currently being installed around the gym and is nearing

completion. Veneer installation at the gym enrty will begin next.• Roof installation is complete at the gym roof. Roof installation at the gym entry will begin

next.• Painting and lighting inside the gym will begin next.

CATE/ROTC• Steel super-structure is in place for both east and west sides of the CATE.• masonry walls at the exterior are being constructed.• masonry walls for the storage mezzanine are being constructed. Once these are complete

the slab for the storage mezzanine will be poured.

Academic Corridor

Page 5: Huckabee Construction Update April 2012

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 5

Huckabee

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2

Academic Wing Gym & Locker Rooms

Page 6: Huckabee Construction Update April 2012

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 6

HuckabeeGym Entry CATE

Page 7: Huckabee Construction Update April 2012

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 7

Huckabee

GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS

Construction Manager

BAIRD WILLIAMS CONSTRUCTION

Project Manager

CTE Wing

Science Labs

Academic

Special Education

Library

Cafeteria

Computer Labs

Athletics

Fine Arts

Academic

AuditoriumAthletics

Athletics

Athletics

Huckabee

BAIRD WILLIAMS CONSTRUCTION

GEORGETOWN HIGH SCHOOL3D Rendering

Front EntryBoards.indd 4 7/26/11 8:55 AM

Page 8: Huckabee Construction Update April 2012

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 8

Huckabee

PHASE ICAFETERIA/CLASSROOm ADDITION• Steel super-structure is in place. Steel roof decking is being installed.• Perimeter and interior masonry walls are being constructed.

ATHLETICS ADDITION• masonry wall construction has begun.• The remaining slab for the locker rooms is set to pour next.

KITCHEN RENOVATION• Utility rough-in at existing slab is complete.• Utility rough-in for new slab will begin next. Once rough-in is complete, the new kitchen

slab can be poured.• New steel structure supporting the existing roof is in place.

EXISTING GYm & LOCKER ROOm RENOVATION• Demolition of existing wood floor at lower gym is complete.• Demolition of locker rooms at lower gym and upper gym is ongoing. Once demolition in

these areas is complete, utility rough-in for new locker rooms and restrooms can begin.

GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS

Cafeteria Interior

Page 9: Huckabee Construction Update April 2012

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 9

Huckabee

GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS

Cafeteria Exterior Locker Room Addition

Page 10: Huckabee Construction Update April 2012

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 10

HuckabeeKitchen Renovation Locker Room Demolition

Page 11: Huckabee Construction Update April 2012

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 11

Huckabee

GEORGETOWN HIGH SCHOOL AND RENOVATIONS

Athletic Addition

KitchenExpansion

CafeteriaExpansion

Aerial

GreenhouseClassroomAddition

Page 12: Huckabee Construction Update April 2012

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 12

Huckabee

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1

Contract Amount: $5,321,000Substantial Completion Date: August 19, 2011

General Contractor: Charter Builders

COMPLETED PROJECTS

Field House Locker Room

NEW WAREHOUSE FACILITY

Contract Amount: $641,000

Substantial Completion Date: November 9, 2011General Contractor: CSS, Inc.

Interior View of Warehouse

ANNIE PURL ELEMENTARY SCHOOL ROOF AND HVAC MODIFICATION

Contract Amount: $229,000Substantial Completion Date: August 12, 2011

General Contractor: Saratoga

New HVAC Unit and Roofing

Field House Weight Room Storage Shed New Ceiling and Light Fixtures