huckabee construction update april 2012
DESCRIPTION
Presented at April 16, 2012 Board of trustees Meeting.TRANSCRIPT
Huckabee
GEORGETOWN ISD2010 BOND PROGRAM UPDATE
A P R I L 2 01 2
2010 BOND PROGRAM UPDATE
Georgetown Independent School District 2
Huckabee
TABLE OF CONTENTS
East View High School Phase 2 Additions, Package 2 3
Georgetown High School Additions and Renovations 7
Completed Projects 12
2010 BOND PROGRAM UPDATE
Georgetown Independent School District 3
Huckabee
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2Original: $25,574,000
CATE Addition – $2,121,338Baseball & Softball Turf - $880,000
Total - $28,575,338
Existing East View High School
A. New Athletic AdditionB. New Fine Arts AdditionC. New Academic AdditionD. New CTE BuildingE. New ROTC Addition (Alt.)F. New Tennis CourtsG. New Tennis Building H. New Baseball/Softball Fieldhouse,
Bleachers, Lighting & Pressbox I. New Practice FieldsJ. New Parking (1,070 spaces)
A
B
C
D
F
J
GH
B
J
J
J
J
Bid Package 1
E
Highway 29
CR 104
HH
I
I
Academic Wing
CTE Building
Softball Field House
First Floor
Second Floor
New Academic Addition
New Academic Addition
New Fine Arts Addition
New Athletic Addition
New CTE/ROTC Addition
General Contractor
2010 BOND PROGRAM UPDATE
Georgetown Independent School District 4
Huckabee
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2
ACADEmIC ADDITION• Interior partition installation is nearing completion.• Exterior masonry veneer is currently being installed around the academic wing.• Roof structure, decking and insulation are in place. Finished metal roof panels will start
being installed next.
ATHLETIC ADDITION• Exterior masonry veneer is complete at the locker room addition• Ceiling installation and wall painting has begun at the locker rooms.• Exterior masonry veneer is currently being installed around the gym and is nearing
completion. Veneer installation at the gym enrty will begin next.• Roof installation is complete at the gym roof. Roof installation at the gym entry will begin
next.• Painting and lighting inside the gym will begin next.
CATE/ROTC• Steel super-structure is in place for both east and west sides of the CATE.• masonry walls at the exterior are being constructed.• masonry walls for the storage mezzanine are being constructed. Once these are complete
the slab for the storage mezzanine will be poured.
Academic Corridor
2010 BOND PROGRAM UPDATE
Georgetown Independent School District 5
Huckabee
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2
Academic Wing Gym & Locker Rooms
2010 BOND PROGRAM UPDATE
Georgetown Independent School District 6
HuckabeeGym Entry CATE
2010 BOND PROGRAM UPDATE
Georgetown Independent School District 7
Huckabee
GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS
Construction Manager
BAIRD WILLIAMS CONSTRUCTION
Project Manager
CTE Wing
Science Labs
Academic
Special Education
Library
Cafeteria
Computer Labs
Athletics
Fine Arts
Academic
AuditoriumAthletics
Athletics
Athletics
Huckabee
BAIRD WILLIAMS CONSTRUCTION
GEORGETOWN HIGH SCHOOL3D Rendering
Front EntryBoards.indd 4 7/26/11 8:55 AM
2010 BOND PROGRAM UPDATE
Georgetown Independent School District 8
Huckabee
PHASE ICAFETERIA/CLASSROOm ADDITION• Steel super-structure is in place. Steel roof decking is being installed.• Perimeter and interior masonry walls are being constructed.
ATHLETICS ADDITION• masonry wall construction has begun.• The remaining slab for the locker rooms is set to pour next.
KITCHEN RENOVATION• Utility rough-in at existing slab is complete.• Utility rough-in for new slab will begin next. Once rough-in is complete, the new kitchen
slab can be poured.• New steel structure supporting the existing roof is in place.
EXISTING GYm & LOCKER ROOm RENOVATION• Demolition of existing wood floor at lower gym is complete.• Demolition of locker rooms at lower gym and upper gym is ongoing. Once demolition in
these areas is complete, utility rough-in for new locker rooms and restrooms can begin.
GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS
Cafeteria Interior
2010 BOND PROGRAM UPDATE
Georgetown Independent School District 9
Huckabee
GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS
Cafeteria Exterior Locker Room Addition
2010 BOND PROGRAM UPDATE
Georgetown Independent School District 10
HuckabeeKitchen Renovation Locker Room Demolition
2010 BOND PROGRAM UPDATE
Georgetown Independent School District 11
Huckabee
GEORGETOWN HIGH SCHOOL AND RENOVATIONS
Athletic Addition
KitchenExpansion
CafeteriaExpansion
Aerial
GreenhouseClassroomAddition
2010 BOND PROGRAM UPDATE
Georgetown Independent School District 12
Huckabee
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1
Contract Amount: $5,321,000Substantial Completion Date: August 19, 2011
General Contractor: Charter Builders
COMPLETED PROJECTS
Field House Locker Room
NEW WAREHOUSE FACILITY
Contract Amount: $641,000
Substantial Completion Date: November 9, 2011General Contractor: CSS, Inc.
Interior View of Warehouse
ANNIE PURL ELEMENTARY SCHOOL ROOF AND HVAC MODIFICATION
Contract Amount: $229,000Substantial Completion Date: August 12, 2011
General Contractor: Saratoga
New HVAC Unit and Roofing
Field House Weight Room Storage Shed New Ceiling and Light Fixtures