Institute of Transportation Engineers Technical Session – March 10, 2011. U of M: Central Campus Transit Center. ITE Technical Session: 3/10/11 U of M: CCTC. The Project Team Design, Planning & Construction: Hubbell, Roth & Clark, Inc. (HRC) Grissim, Metz, Andriese Associates (GMA) - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Institute of Transportation Engineers Technical Session – March 10, 2011

Institute of Transportation EngineersTechnical Session – March 10, 2011U of M: Central Campus Transit Center

Page 2: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

The Project Team› Design, Planning & Construction:

Hubbell, Roth & Clark, Inc. (HRC) Grissim, Metz, Andriese Associates (GMA) O’Neal Construction Incorporated (OCI)

› Stakeholders: University of Michigan – Architecture, Engineering &

Construction (AEC) University Departments City of Ann Arbor Ann Arbor Transportation Authority (AATA)

Page 3: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Overview & Introduction› Scope of Work & Project Goals

Location & Function Improve safety, capacity and ADA Accessibility Infrastructure improvements Create a multi-modal “Place” for all transit Provide a striking yet complementary architectural design

› Funding ARRA through AATA STPU through U of M 5307 Funds through AATA Local (U of M)

Page 4: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Location & Function

DIAG

N. UNIVERSITY

STAT

E ST

.

S. UNIVERSITY

CHEMISTRY

CC LITTLE

RUTHVEN MUSEUM

DENTISTRY

N. UNIVERSITY

UM Bus Stops

Page 5: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Improve Safety

Page 6: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Multi-modal improvements

Page 7: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Planning and Schematic Design› Project Data

Posted speed: 25 mph North University ADT: 7200 Pedestrian crossing peak hour volume: 1000 Pedestrian peak hour volume along N. University: 700 Bus volume along N. University: Approx 75 per hour

› Scope of Work Project budget: $4,000,000 Maximize project goals Accelerated schedule

Page 8: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Planning and Schematic Design› Options explored & studied

Bus storage area needed Pedestrian travel patterns Pedestrian capacity analysis and bus loading evaluation Shelter capacity analysis and expansion considerations Traffic and turning movement study Roadway improvement options & recommendations Sustainable design studies & recommendations Bicycle lane configuration and location

Page 9: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Planning and Schematic Design› Options explored & studied (Continued)

Lighting options & recommendations Options to enhance median area Wayfinding opportunities Options for dynamic signs and kiosks Construction staging and temporary bus stop options Options to reduce scope to meet budget Evaluation of bidding project (lump sum versus unit

price) Project justification report for University Regents

Page 10: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Detailed Design› Schedule:

March 2009 – Notice to proceed August 2009 – Schematic design complete January 2010 – Final plans complete

› Infrastructure Improvements Watermain replacement Storm sewer improvements Road reconstruction

Page 11: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Detailed Design› Multimodal improvements

Consolidate pedestrian crossings Provide bicycle lanes Improve University plaza areas Consolidate bus stops (AATA and University) Provide ADA Accessible site Install bicycle racks to meet demand Construct bus stop shelters on both sides Wayfinding (static & dynamic signs, kiosks)

Page 12: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Detailed Design› Custom Bus Stop Shelters

Drilled piers & steel structure Glass enclosures Translucent panel roof

› Maintenance of Traffic & Construction Staging Full road closure Coordination with City and University Work not to start until after school (May) Road to be open during Ann Arbor Art Fair (July) Work to be complete prior to school start (September)

Page 13: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Detailed Design – Layout Plan

Page 14: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Detailed Design – Layout Plan

Page 15: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Detailed Design – Layout Plan

Page 16: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Construction› Aggressive schedule

Pre-purchased steel Infrastructure improvements & site work Structural elements Roof panels Amenities (bike racks, wayfinding, pavers, etc.)

› Site constraints & requirements Small project area Road open by Art Fair Maintain ingress/egress to University buildings

Page 17: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Construction› Challenges

Unanticipated utilities Material changes Delays

› Solutions Fast-track decisions & design changes Contract negotiations Overtime and additional manpower

Page 18: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Construction Progress

Page 19: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Construction Progress

Page 20: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Construction Progress

Page 21: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Before and After

Page 22: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Before and After

Page 23: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Before & After

Page 24: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Before & After

Page 25: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Before & After

Page 26: Institute of Transportation Engineers Technical Session – March 10, 2011

ITE Technical Session: 3/10/11U of M: CCTC

Questions?