Sl No. Activity Description Acceptence Criteria Extent of Insp. ResponsibilityAL-JALHAMI INSPECTION
Ref Doc Verify Doc Jalhami KJO/OIS
1 Documents Approval
1.1 Drawings. SAES-A-202 Review Engineering Manager Project Specification Drawings H R
1.2 Installation Procedure for Walkway and Stairs Review QA/QC Engineer Project Specification Drawings H R
1.3 ASME Sec- IX Review QA/QC Engineer Project Specification Drawings H R
2 Materials
2.1 Visual & Dimensional check for new materials. 100% QCI Project Specification Material test cetrificates R M
3 Pre-fabrication
3.1 100% QCI Project Specification Drawings H W
3.2 100% QCI Project Specification Drawings H W
3.3 100% QCI Project Specification Drawings H W
4
4.1 ASME Sec- IX,12-SAMSS-007 100% QCI Project Specification Drawings H W
ASME Sec- IX,12-SAMSS-007
4.4 ASME Sec- IX,12-SAMSS-007 100% QCI Project Specification Drawings H W
4.3 ASME Sec- IX,12-SAMSS-007 100% QCI Project Specification Drawings H W
4.5 Visual Inspection of all welded joints. ASME Sec- IX,12-SAMSS-007 100% QCI Project Specification Drawings H W
5 Galvanization
INSPECTION AND TEST PLAN
CONTRACT NO : HT 003 SS 11 DOCUMENT NO. : ITP/M-102B/00, Rev-0
WORK ORDER NO. : MSS/15/407 DATE: 16/05/2015
CLIENT : KHAFJI JOINT OPERATIONS (KJO) PROJECT : INSTALLATION OF INTERCONNECTING WALKWAY WITH STAIRS BETWEEN INLET SEPERATORS V-0701 A/B/C AT FDP-1
CONTRACTOR : AL JALHAMI CONTRACTING EST. TITLE: INSTALLATION PROCEDURE
Welding Procedure Specifications, Procedure Qualification Record & Welder Performance Qualification.
SAES-A-202 Approved Drawings & 12-SAMSS-007
Visual & Dimensional check for Columns, angles, channels and boltings.
12-SAMSS-007 & SAES-A-202 Approved Drawings
Visual & Dimensional check for handrail pipes, checkered plates and gratings.
12-SAMSS-007 & SAES-A-202 Approved Drawings
Visual & Dimensional check for Base plates, gusset plates, marking layout and cutting.
12-SAMSS-007 & SAES-A-202 Approved Drawings
Fabrication of Walkway structures, staircase structures and hand railings.
Visual and Dimensional checking of Base plates, Gusset plates, Column, Brasing, and channels after marking and cutting to required dimension.
Visual checking of Gusset plates and Base plates for stagewise fitup & welding with columns and channels.
Visual checking of Handrail pipe for stagewise fitup & welding with brackets and support pads.
Visual and Dimensional checking of Drilled holes of base plates, Gusset plates, channels, angles, brackets and support pads .
![Page 2: ITP for Lpseperator](https://reader036.vdocument.in/reader036/viewer/2022082506/55cf8dfe550346703b8d6649/html5/thumbnails/2.jpg)
AL JALHAMIPage 2 of 2
Sl No. Activity Description Acceptence Criteria Extent of Insp. ResponsibilityAL-JALHAMI INSPECTION
Ref Doc Verify Doc Jalhami KJO/OIS
INSPECTION AND TEST PLAN
CONTRACT NO : HT 003 SS 11 DOCUMENT NO. : ITP/M-102B/00, Rev-0
WORK ORDER NO. : MSS/15/407 DATE: 16/05/2015
CLIENT : KHAFJI JOINT OPERATIONS (KJO) PROJECT : INSTALLATION OF INTERCONNECTING WALKWAY WITH STAIRS BETWEEN INLET SEPERATORS V-0701 A/B/C AT FDP-1
CONTRACTOR : AL JALHAMI CONTRACTING EST. TITLE: INSTALLATION PROCEDURE
5.1 Inspection of galvanized structures. SAES -H-001, ASTM A123 100% QCI Project Specification Drawings H W
6 Civil Foundations
5.1 Inspection marked areas for excavation. 100% QCI Project Specification Drawings H W
5.2 100% QCI Project Specification Drawings H W
5.3 Inspection of Coatings of condrete foundations. 100% QCI Project Specification Drawings H W
7 Erection
7.3 inspection of fitup and onsite welding activities. ASME Sec- IX,12-SAMSS-007 100% QCI Project Specification Drawings H W
8 Final Inspection and wallkthrough
8.1
Final inspection of erected structure and walkthrough. 100% QCI Project Specification Drawings W H
LEGENDS: H- HOLD , W-WITNESS, R-REVIEW, V-VERIFY, M- MONITOR,
Inspection of compaction and stage wise casting of concrete foundations.
SAES-A-202 Approved Drawings & 12-SAMSS-007