james m c intyre
DESCRIPTION
Tagger Microscope Fabrication Readiness Review. James M c Intyre. Microscope Fabrication Readiness Review Feb 07, 2013. Outline. Overview TAGM Milestones Documents & Travelers Personnel Training Special Training & Hazards Construction Plan Scheduling Testing & Acceptance Plans - PowerPoint PPT PresentationTRANSCRIPT
PowerPoint Presentation
1James McIntyreTagger Microscope Fabrication Readiness Review
2OutlineOverviewTAGM MilestonesDocuments & TravelersPersonnel TrainingSpecial Training & Hazards
Construction PlanSchedulingTesting & Acceptance PlansDocumentations & Tracking
QuestionsMicroscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre3OverviewTAGM Milestone
Dark Box ConstructionEnd Date: 06 May 20131st Article Optical Fiber BundleEnd Date: 13 May 2013Complete First 3 Bundles / Select Ref. BundleEnd Date: 17 Jun 2013Submit TAGM Enclosure Design Drawings to JLabEnd Date: 15 Jul 2013Complete Construction of Electronics EnclosureEnd Date: 20 Dec 2013Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
4OverviewTAGM Milestone
Complete 17 Optical Fiber BundlesEnd Date: 03 Jan 2014Complete Construction of Fiber Array EnclosureEnd Date: 17 Jan 2014Complete Assembly of Full Enclosure at UConnEnd Date: 14 Feb 2014TAGM Disassembly / Packing for Shipment to JLabEnd Date: 28 Mar 2014Delivery of TAGM components to JLabEnd Date: 07 Apr 2014Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
5OverviewDocumentation & Travelers
TAGM Milestones
https://docs.google.com/document/d/1WeUDsoiMD2ogm2zvRaglJVA-r9s5hWlLZktTXJdQ6JE/edit?usp=sharing
Construction Plan for the TAGM
https://docs.google.com/document/d/15OreBfdhb5mdpdXz6KMTVQt8ZWMU-4OV9i8Y6vp97Ms/edit?usp=sharing
Specifications of the TAGM Detector
https://docs.google.com/document/d/1rHl580R3X3r2yn3hw1Mh-JC136NzWyE6IE_SoGRjR50/edit?usp=sharing
Quality Assurance & Acceptance Test Plan for the TAGM
https://docs.google.com/document/d/1JL40gx7tPDDFu4aSiad3fTemAp0yiVBPI6D8FB5zb6o/edit?usp=sharingMicroscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
Safety/Conduct TrainingChemical Health and Safety TrainingHazard and chemical characterization/ assessmentChemical Hygiene Plan including standard operating proceduresWaste disposalAir qualityProtective equipmentEmergency response protocol
Collaborative Institutional TrainingCollaborative researchConflict of interestResponsible code of conductMentor and trainee responsibilitiesResearch Misconduct
6Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyreJob TrainingWalk-through the lab areasWhere safety stations, chemical storage, fume hood, MSDS, waste stations, etc. are locatedStandard operating procedureThese will be located at each work stationShift checklist to track adherenceCooperative or supervised first shiftSomeone else always present on the floorSpot checks7Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
8Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
9Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
10Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre11Construction Plan - OverallSchedulingCompletion Date 07 Apr 2014Total Man-power : 3 Grad. Students @ 2140 Grad-hours (total)1 Technician @ 718 Tech-hours2 Student Workers @ 1179 Student-hours (total)1 Machinist @ 840 Machining-hours Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
12Construction PlanInspection & Acceptance Test AreasDark Box Testing AreaTesting Optical FibersElectronicsMicroscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
Allows for testing of:Single fused fibersFiber bundlesCooling unit for the electronics enclosure13Construction PlanInspection & Acceptance Test AreasRough Cut / Fusing AreaCross-sectional DimensionCladding InspectionMicroscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
14Construction PlanInspection & Acceptance Test AreasGluing AreaBundle DimensionsPaint CoverageMicroscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
Gluing Station(Clean room)
15Construction PlanDocumentation & Travelers
Use of Google Documents to Track:Rough CutBendingLight Transmission Testing
Provides up-to-date progress tracking
Envelopes with complete data list accompany components to JLabMicroscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
16Construction Plan Rough CutSchedulingEnd Date 03 Jan 2014Man-power: 1 Student Worker @ 102 hours
Inspection, Testing, & Acceptance PlansCross-sectional dimensionsSciFi Measure every 3 cm (prior to cutting)Light Guides Measure 4cm from each end & 3 other locations (~ 40cm apart)
Documentations & TrackingRough Cut Data Sheet
https://docs.google.com/spreadsheet/ccc?key=0Am3YqcbK4xUxdGdldUt5Nk53UENKUUg5ejgyLWE2bFE&usp=sharing
Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
17Construction Plan Fiber StraighteningSchedulingMan-power: 1 Technician @ 204 hours
Inspection, Testing, & Acceptance PlansCheck for damage to claddingCrazing of fibersMonitoring & recording temperature
Documentations & TrackingStraightening Temperature Data Sheet
https://docs.google.com/spreadsheet/ccc?key=0Am3YqcbK4xUxdGdldUt5Nk53UENKUUg5ejgyLWE2bFE&usp=sharing
Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
SchedulingMan-power: 1 Grad. Student @ 51 hours
Inspection, Testing, & Acceptance PlansCheck for damage to claddingMeasuring Length
Documentations & TrackingEnd-Mill Data Sheet
https://docs.google.com/spreadsheet/ccc?key=0Am3YqcbK4xUxdDdBcHlPbERlejlYbmhlSnRqVElxZGc&usp=sharing
18Construction Plan End-Mill Fiber CutMicroscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
SchedulingMan-power: 1 Technician @ 68 hours
Inspection, Testing, & Acceptance PlansCheck for damage to claddingCheck for surface imperfections
Documentations & TrackingPolishing Data Sheet
https://docs.google.com/spreadsheet/ccc?key=0Am3YqcbK4xUxdERoaXd6UnRldXhaVzVzd1d2dVB4R2c&usp=sharing
19Construction Plan Fiber-End PolishingMicroscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
Polishing: End-Mill to copier paperStraight edge when polished in collar (shown above)20Construction Plan Fiber FusingSchedulingMan-power:1 Grad. Student @ 136 hours1 Technician @ 136 hours
Inspection, Testing, & Acceptance PlansCross-sectional dimensions at the fusing jointCladding damage
Documentations & TrackingFiber Fusing Data Sheet
https://docs.google.com/spreadsheet/ccc?key=0Am3YqcbK4xUxdDB2VFRtcVplLUxJdzJpU0RiQUYxUnc&usp=sharing
Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
21Construction Plan Individual Fiber InspectionSchedulingMan-power:1 Grad. Student @ 272 hours1 Student Worker @ 272 hours
Inspection, Testing, & Acceptance PlansLight transmission
Documentations & TrackingIndividual Fiber Inspection Data Sheet
https://docs.google.com/spreadsheet/ccc?key=0Am3YqcbK4xUxdFpLdGd6R3l4SUFNTzRKNWk3b3QyVXc&usp=sharing
Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
22Construction Plan Fiber PaintingSchedulingMan-power: 1 Grad. Student @ 68 hours
Inspection, Testing, & Acceptance PlansCross-sectional dimensionsEven coating
Documentations & TrackingFiber Painting Data Sheet
https://docs.google.com/spreadsheet/ccc?key=0Am3YqcbK4xUxdGZyN2ptMVZUcnFySDRnZThmcDF2SGc&usp=sharing
Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
23Construction Plan Bundle BendingSchedulingMan-power:1 Grad. Student @ 272 hours1 Student Worker @ 272 hours
Inspection, Testing, & Acceptance PlansFiber cross-sectional shapeCrazingCladding cracking Documentations & TrackingBundle Bending Data Sheet
https://docs.google.com/spreadsheet/ccc?key=0Am3YqcbK4xUxdGZNREdVSXc4UEo1LW9FbWNYY1FYR3c&usp=sharing
Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
StartFinish
24Construction Plan Bundle DryingSchedulingMan-power:1 Grad. Student @ 136 hours
Inspection, Testing, & Acceptance PlansInspect for fiber damageEnsure completely dry prior to gluing
Documentations & TrackingNone needed
Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
25Construction Plan GluingSchedulingMan-power:1 Grad. Student @ 408 hours1 Student Worker @ 408 hours
Inspection, Testing, & Acceptance PlansCross-sectional dimensionsDamage to fiber endsExcess glue
Documentations & TrackingBundle Gluing Data Sheet
https://docs.google.com/spreadsheet/ccc?key=0Am3YqcbK4xUxdEs0WUtxb1oySHNqVFhydU9NTFpmTlE&usp=sharing
Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
26Construction Plan Fiber Bundle InspectionSchedulingMan-power:1 Grad. Student @ 204 hours1 Technician @ 204 hours
Inspection, Testing, & Acceptance PlansLight transmission
Documentations & TrackingIndividual Fiber Inspection Data Sheet
https://docs.google.com/spreadsheet/ccc?key=0Am3YqcbK4xUxdFpLdGd6R3l4SUFNTzRKNWk3b3QyVXc&usp=sharing
Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
27Construction Plan TAGM Drawing SubmissionSchedulingEnd Date 15 Jul 2013Man-power:1 Grad. Student @ 144 hours1 Technician @ 36 hours
Inspection, Testing, & Acceptance PlansSpot check of dimensions by technician
Documentations & TrackingTAGM Drawings located on UConn PAN Wiki
http://zeus.phys.uconn.edu/wiki/index.php/Full_Scale_Tagger_Microscope_Drawings
Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
28Construction Plan Construction of Electronics EnclosureSchedulingEnd Date 20 Dec 2013Man-power:3 Grad. Student @ 144 hours1 Technician @ 20 hours1 Student Worker @ 40 hours
Inspection, Testing, & Acceptance PlansLight seal test
Documentations & TrackingPictures & construction notes maintained on the UConn PAN WikiMicroscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
29Construction Plan Construction of Fiber Array EnclosureSchedulingEnd Date 17 Jan 2014Man-power:3 Grad. Student @ 165 hours1 Technician @ 20 hours1 Student Worker @ 40 hours
Inspection, Testing, & Acceptance PlansLight seal test
Documentations & TrackingPictures & construction notes maintained on the UConn PAN WikiMicroscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
e-30Construction Plan Construction of Full TAGMSchedulingEnd Date 14 Feb 2014Man-power:2 Grad. Student @ 68 hours1 Student Worker @ 16 hours
Inspection, Testing, & Acceptance PlansLight seal test30 Day Cosmic-Ray Testing of the TAGM
Documentations & TrackingCosmic-Ray Testing Data Sheet
https://docs.google.com/spreadsheet/ccc?key=0Am3YqcbK4xUxdEFGUENRT0hETVNIVzlOUkNGVGNaWUE&usp=sharing
Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
31Construction Plan Delivery to JLabSchedulingEnd Date 07 Apr 2014Man-power:2 Grad. Students @ 72 hours1 Technician @ 30 hours1 Student Worker @ 29 hoursInspection, Testing, & Acceptance PlansEnsure proper documentation is shipped with the componentsSpot checks Documentations & TrackingTravelers Sent in shipping boxesAvailable also onlineMicroscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre
32Questions???Microscope Fabrication Readiness ReviewFeb 07, 2013James McIntyre