jean-philippe tock (te-msc) on behalf of the smacc project
TRANSCRIPT
SMACC Seventeenth report[20 min]
24/01/2014
Jean-Philippe Tock (TE-MSC)
On behalf of the SMACC project
Activities since last LSC (10/01/2014) Arc splices installation
• By Activities• By sectors
SIT DFBA (See next presentation)
Dashboards
Specials Quadrupole diodes Dipole diodes
Activities for the next 2 weeks
Conclusions
JPh Tock4/34
Sector 56 : Final leak test and surface work on DFBAK SHM Investigation on dipole diodes
Sector 67 : Pressure test planned for 15.01.2014 Leak tests, ElQA
Sector 78 Progress on M leak tests and closure of interconnections Disconnect DFBAO SHM (Priority to be defined)
Sector 81 Complete the M lines rewelding M leak tests
Sector 12 Complete electrical insulation Progress on quad diodes consolidation
Sector 23 Cu machining Installation of shunts Start electrical insulation
Sector 34 Cu machining Installation of shunts
Sector 45 M lines opening & ElQC in the zone of He spill test, temporary reclosure of ICs
SMACC Main activities for the last 2 weeks
OK, 8 remain due to NCs
> Half done but on hold
OK, 3 remains due to NCs
OK, 6 remain due to NCs
>25% done
On-going, Splices condemned by spill test were measured, reclosure completed this week
Pressure tested successfully, See later
SHM disconnecred and at the surface
> 90% leak tested, > 80% reclosed
> 75 % tested
On-going, almost half done
From last LSC (10.01.2014)
All is reclosed but the IC with DFBAK, Good progress, see next presentationInsulation vacuum leak tested on >80% of S56
OK, 14 remain due to NCs
>50% done
JPh Tock5/34
SEQUENCE AND STATUS
OK to open
8 sectors
Open ICs
8 sectors
Install DN200
100 %
Open M sleeves
> 7.4 sectors
ElQC(old splices)
> 7 sectors
Undo / Redo splices
≈ 6.5 sectors
ElQC(new splices)
Machine Cu
> 6.5 sectors
ElQCafter Cu mach.
≈ 6.5 sectors
Install shunts
> 6.3 sectors
ElQCafter shunt
> 6 sectors
Insulate splices
≈ 5.2 sectors
Weld M
> 4.2 sectors
Leak test M
> 3.2 sectors
Close IC
≈ 3 sectors
Final LT
≈ 1.9 sector
Consolidate Q diodes
≈ 4.6 sectors
Stopped,Will slightly impact in 2 weeks
Cancelled
Completed
Completed
Completed
JPh Tock6/34
SMACC Progress report by activity
Courtesy H Prin
Desoldering / Resoldering: Completed in about 6.5 sectors equivalent
Desoldering in 23 is completed and well advanced in 34
54 ICs had not almost no splices to be redone (1 of) For geometrical reason
Still enough ICs available for Cu machining
9777
JPh Tock7/34
SMACC Progress report by activity
Shunts are installed in ≈ 6.4 sectors-eq (1354 ICs ≈ 80%)
• Almost completed in 23• Work in sectors 23-34 (No
infrastructure at P3)• Slightly > 1 week ahead of schedule• Mind the last X% effect
Shunt weekly installation rate (4 weeks sliding average)
JPh Tock8/34
SMACC Progress report by activity
Insulation box: Installed in 5.2 sectors equivalent
Courtesy H Prin / G Maury
• > 80 injected in W3 and in W4 • > 50 ICs are ready for injection• Under recovery
(< 1 week behind baseline)• Only 7 IC left in 5 first sectors
(<1 %)• Buffer of >3 weeks wrt welding
92
JPh Tock9/34
SMACC Progress report by activity
M Welding : ≈ 872 ICs welded, > 4 sec-eq:
Routinely 12 ICs/day Work concentrated in 1 sector 4 leaks were found end of 2013 (2 in
S78 and 2 in S81)Investigations are still on-going (2), To be followed
As presented LSC 4.10.2013
11 weeks @ 34
18 weeks @ 51
37 ICS behind forecast(Eq to 3 days ;Recovered in a month)
JPh Tock10/34
SMACC Progress report by activity
M sleeves leak testing : (780 ICs) are leak tested (> 3.5 sec-eq)
Following the M lines About 1 month behind schedule Should recover as for the M welding
Courtesy P Cruikshank / L Mourier
JPh Tock11/34
SMACC Progress report by activity
Reclosure of interconnections : Almost 3 sec equivalent are reclosed
Started closing 81 about a week ahead of baseline Reclosing temporarily IC in 45 for He Spill test Only 15 IC (About 1 day) behind schedule globally
JPh Tock12/34
SMACC Progress report by activity
Final leak test: ≈ 1.7 sec equivalent completely validated
3 weeks to have results after repumping 4 subsectors under test in 78, 5th one next week (> 1/3) First sector to be released soon in 81 (Today or beginning of next week) About 5 weeks behind schedule; limited by release rate
SMACC Sector 67
Leak test at 10 bar (half design pressure) QRL, LSS cryostats, Arc beam vacuum : OK Magnet cryostat and DFBAs:
New leak on C’K circuit (A19R6) at 10 bar, recloses at 1 barLongitudinal localisation and repair with the other NCs
Demonstrates the interest of the “0.5 * design pressure leak test” Dixit P Cruikshank
Purge is on-goingTo come:
ElQA Flushing ElQA
Campaign to fix NCs (leaks, thermometer, possible short circuits in diodes, ?) beginning of March 14
Courtesy P Cruikshank
JPh Tock14/34
SMACC Progress report by sector
Main activities are : Work on NCs (Not priority: DFBAO)
1 NC blocks the W leak test of usually 16 ICs Leak test of M lines Closure of interconnections Leak test on insulation vacuum
Courtesy M Pojer
JPh Tock15/34
SMACC Progress report by sector
Main activities are : Leak test of M lines Reclosure of IC
Main activity is : The welding of M lines
JPh Tock16/34
SMACC Progress report by sector
Main activities are : Installation of electrical insulation Work on overheated splices
(More info later) Preparation for Q diodes
consolidation
Main activities are : Almost all old present splices have
been measured Splices redoing Cu machining Shunt installation
JPh Tock17/34
SMACC Sector 45 He Spill test
W4 (end) : Temporary relosure of W-bellows on 26 Ics (On-going)Preparation of test (TE-CRG)
W5 : Half of sector (L5) not accessible for AUG testsW6 : He spill test during the nights (Access restrictions)
JPh Tock18/34
SMACC Dashboards
Opening is completed Shunting is slightly ahead on schedule The installation of insulation boxes is recovering Welding rate is more than required to recover baseline schedule Reclosure: to increase, next week will be a good benchmark in 81 Insulation vacuum leak test : Limited by release rate
SMACC summary status Updated 24-Jan-14
19-Apr-13 212 13-May-13 17-Jun-13 211 19-Jul-13 05-Jul-13 211 08-Aug-13 19-Jul-13 211 15-Aug-13 30-Aug-13 211 27-Sep-13 17-Sep-13 179 25-Oct-13-11 212 -6 -54 212 -41474 -58 212 -41494 4 212 -41501 -10 212 8 212
08-Apr-13 100% 07-May-13 24-Apr-13 100% 08-May-13 100% 23-Jul-13 100% 20-Aug-13 100% 25-Sep-13 84%
16-May-13 211 06-Jun-13 22-Jul-13 211 23-Aug-13 13-Aug-13 211 17-Sep-13 27-Aug-13 211 24-Sep-13 30-Sep-13 211 27-Oct-13 15-Oct-13 211 22-Nov-13-20 211 10 -31 211 60 8 211 48 5 211 51 -27 211 22 7 211 11
26-Apr-13 100% 16-Jun-13 21-Jun-13 100% 22-Oct-13 21-Aug-13 100% 04-Nov-13 01-Sep-13 100% 14-Nov-13 03-Sep-13 100% 18-Nov-13 22-Oct-13 100% 03-Dec-13
07-Jun-13 212 27-Jun-13 26-Aug-13 211 30-Sep-13 18-Sep-13 211 22-Oct-13 02-Oct-13 194 29-Oct-13 28-Oct-13 181 22-Nov-13 12-Nov-13 0 20-Dec-13-24 212 12 -3 212 -41547 33 212 -41569 44 212 -41576 29 212 -41600 -41590 212 -41628
14-May-13 100% 09-Jul-13 23-Aug-13 100% 21-Oct-13 100% 15-Nov-13 92% 26-Nov-13 85% 0%
28-Jun-13 212 18-Jul-13 01-Oct-13 211 04-Nov-13 23-Oct-13 206 26-Nov-13 06-Nov-13 163 03-Dec-13 27-Jan-14 21 21-Feb-14 11-Feb-14 0 21-Mar-14-38 212 8 -11 212 -41582 34 212 -41604 29 212 -41611 -7 212 -41691 -41681 212 -41719
21-May-13 100% 26-Jul-13 20-Sep-13 100% 26-Nov-13 97% 05-Dec-13 77% 20-Jan-14 10% 0%
19-Jul-13 212 08-Aug-13 05-Nov-13 211 09-Dec-13 27-Nov-13 48 14-Jan-14 11-Dec-13 0 21-Jan-14 24-Feb-14 0 21-Mar-14 11-Mar-14 0 22-Apr-14-53 212 21 -11 212 -41617 55 212 -41653 -41619 212 -41660 -41694 212 -41719 -41709 212 -41751
27-May-13 100% 29-Aug-13 25-Oct-13 100% 21-Jan-14 23% 0% 0% 0%
09-Aug-13 212 29-Aug-13 10-Dec-13 198 27-Jan-14 20-Jan-14 0 21-Feb-14 31-Jan-14 0 27-Feb-14 24-Mar-14 0 22-Apr-14 08-Apr-14 0 21-May-14-67 212 19 -25 212 -41666 -41659 212 -41691 -41670 212 -41697 -41722 212 -41751 -41737 212 -41780
03-Jun-13 100% 17-Sep-13 15-Nov-13 93% 0% 0% 0% 0%30-Jul-0025-Nov-13 212 13-Dec-13 29-Jan-14 101 04-Mar-14 24-Feb-14 0 28-Mar-14 07-Mar-14 0 03-Apr-14 24-Apr-14 0 22-May-14 07-May-14 0 20-Jun-14
-188 212 -49 -48 212 -41702 -41694 212 -41726 -41705 212 -41732 -41753 212 -41781 -41766 212 -4181021-May-13 100% 25-Oct-13 12-Dec-13 48% 0% 0% 0% 0%
06-Jan-14 212 24-Jan-14 05-Mar-14 0 08-Apr-14 31-Mar-14 0 07-May-14 11-Apr-14 0 13-May-14 22-May-14 0 20-Jun-14 06-Jun-14 0 18-Jul-14-255 212 -53 -41703 212 -41737 -41729 212 -41766 -41740 212 -41772 -41781 212 -41810 -41796 212 -41838
26-Apr-13 100% 02-Dec-13 0% 0% 0% 0% 0%
19-Apr-13 1695 24-Jan-14 17-Jun-13 1354 08-Apr-14 05-Jul-13 887 07-May-14 19-Jul-13 779 13-May-14 30-Aug-13 624 20-Jun-14 17-Sep-13 390 18-Jul-14-11 1695 -53 -54 1695 -41737 -58 1695 -41766 4 1695 -41772 -10 1695 -41810 8 1695 -41838
08-Apr-13 100% 02-Dec-13 24-Apr-13 80% 08-May-13 52% 23-Jul-13 46% 20-Aug-13 37% 25-Sep-13 23%
S34
S45
LHC
S67
S78
S81
S12
S23
ICs Opening
S56
Sleeves Welding M lines Leak Test ICs closure Ins Vac Leak testShunts Installation
Completed
Completed
New
New
JPh Tock20/34
SMACC Progress report SIT
SIT All cryomagnets are reconnected Team members are partially reinforcing the train and the DFBA activities Activities linked to NC and overheated splices Intervention on triplet braids to start end of January (See next slide). Discussions with RP (should be OK).
Courtesy N Bourcey, S Le Naour
JPh Tock21/34
SMACC Progress report SIT : Interventions on triplets braid
Consolidation of triplet braids
To be confirmed by CRG
By order of priority:1. Q1R1/Q1L5: Install braids2. Q1L1/Q1R5: Remove braids3. Q1L2/Q1L8: Remove braids
Q1R2/Q1R8: Install braids4. D1L2/D1L8: Remove braids on DFBX side
D1R2/D1R8: Remove braids on arc side
Present status : 1 was done in 2009 2 and 3 are planned within SMACC during LS1
Similar to previous interventions but without thermometers 4 will only be done if resources available and no impact on schedule
(consider not done during LS1)
JPh Tock22/34
SMACC Dashboards
Baseline: 66.5 % (62.4 %)Completed: 64.4 % (58.8 %)Delay 7 (9) days
Baseline: 67.8 % (66.8 %)Completed: 63.9 % (60.3 %)Delay 24 (27) days
Decreasing delay
Delay stable
Arc splices: Rates are stableAll activities are still on-goingTrend should remain in the next 1-2 monthsMain delay is in S12
DFBA: See next presentation
Preliminary
JPh Tock23/34
SMACC Dashboards
Progress:Baseline: 67.8% (64.4 %)Completed: 63.7% (58.4 %)
Delay 15 (16) days
Stable ; Δbaseline >≈ Δcompleted
JPh Tock24/34
SMACC Quadrupole diodes (1/5)
Quadrupole diodes : ON HOLD
4.66 sectors are consolidated (56,67,78, 81 and 2/3 of 12- Up to Q28L2) Components: 4 types :
1. Stainless steel plates (#4000) : All received with spares2. Inconel nuts (#8000) : OK for the whole LHC3. Inconel threaded plates (#4000): For 32 diodes at CERN (2/3 sec-eq). 4. Inconel studs (#8000) : 2 at CERN so < 1 diode-eq
Delivery expected from supplier 3 W6 No reliable news from supplier 1
Do not count on its deliveries (Conservative or realistic?)
Courtesy L Grand-Clement, R Moron –Ballester, F Savary
JPh Tock25/34
SMACC Quadrupole diodes (2/5)
Quadrupole diodes : ON HOLD
Action plan: (1 to 5 on-going in parallel)1. Splitting the work in 2 to prepare consolidation as much as possible :
5 weeks originally foreseen per sector All containers are open Measurements before consolidation and removal of helicoil is on-going in S23
2 weeks per sector when components are available (with the present resources)
2. Launching orders to cover the complete LHC(+margin) without counting supplier 13. Visit supplier 3 next Tuesday (28.01.2014)4. Investigate means to reduce delays (overtime)5. Procure tooling to allow doubling the team6. Identify resources with the right profile and who will become free (W5)7. Train these resources as soon as components are available (W7 onwards)
(Goal is to double the rate so 1 week per sector)8. Assessing the impact on the schedule and interference with other activities
(see next slide) and optimising the sequence (Priority by sectors, subsectors with other large NCs,…)
Courtesy L Grand-Clement, R Moron –Ballester, F Savary
JPh Tock26/34
SMACC Quadrupole diodes (3/5)
Quadrupole diodes : ON HOLD
Impact on other activities:1. Welding:
Can weld 3 ICs/4 and 6 welds/7 2. Welding visual inspection:
Have to come back to inspect welds of the diodes containers3. M lines leak test :
Can limit impact on schedule with extra tooling (plugs)Increase the workload, likely in a critical period
4. Closure of interconnections : If Pt3 is OK, 3 ICs/4 can be closed Increase the workload, but likely acceptable
5. Leak test of insulation vacuumCannot be doneAccording to baseline, should start W14 where we are blocked presently
Courtesy L Grand-Clement, R Moron –Ballester, F Savary
JPh Tock27/34
SMACC Quadrupole diodes (4/5)
Courtesy L Grand-Clement, F Savary
Quadrupole diodes : Bare busbars
Contact resistanceQBQI.14L1
Beforedisconnection (µΩ)
Afterconsolidation (µΩ)
Busbar/heatsink(µΩ)
BB_d_A (less Ni) 2.0 0.2 0.1
BB_d_B (bare) 1.6 0.4 0.1
BB_d_C (less Ni) 1.3 0.4 0
BB_d_D (bare) 0.5 0.4 0.6
BB_m_A (Ag) 1.5 0.3
BB_m_B (Ag) 1.1 0.3
BB_m_C (Ag) 1.4 0.6
BB_m_D (Ag) 2.3 0.4
JPh Tock28/34
SMACC Quadrupole diodes (4/5)
Courtesy L Grand-Clement, F Savary
Quadrupole diodes : Bare busbars
Contact resistanceQBQI.16R8
BeforeDisconnection(µΩ)
AfterConsolidation(µΩ)
BB_d_A 0.5 0.1
BB_d_B (bare) 1.3 0.4
BB_d_C (less Ni) 2 0.5
BB_d_D (bare) 1.0 0.2
BB_m_A (Ag) 0.8 0.5
BB_m_B (less Ag) 0.5 0.1
BB_m_C (Ag) 0.9 0.3
BB_m_D (less Ag) 2.1 0.2
JPh Tock29/34
SMACC Quadrupole diodes (4/5)
Courtesy L Grand-Clement, F Savary
Quadrupole diodes : Bare busbars
Bare busbar QBQI.32R7• Magnet busbar/connection plate
Contact resistanceQBQI.32R7
Beforedisconnection (µΩ)
Afterconsolidation (µΩ)
BB_d_A (Ni) 2.1 0.5
BB_d_B (Ni) 2.3 0.6
BB_d_C (Ni) 1.9 1.1
BB_d_D (Ni) 2.5 0.3
BB_m_A (Bare) 1.3 0.2
BB_m_B (Bare) 1.5 0.5
BB_m_C (Bare) 0.6 0.5
BB_m_D (Bare) 1.3 0.2
JPh Tock30/34
SMACC Quadrupole diodes (4/5)
Courtesy L Grand-Clement, F Savary
Quadrupole diodes : Bare busbars
3 cases so far in sectors 78 & 81 (SSS from start of production) Contacts resistance of bare busbars are lower than Ni/Ag coated ones [“almost”
acceptable] and are less degraded so far than Ni/Ag coated ones Actions have to be defined (Diodes WG):
Ranging from use as is to … …. Magnet busbars exchange requires to change the SSS !
Busbars / heatsink contacts are electrically measured but not visually inspected systematically
Inventory of diodes stacks ready for installation is limited
JPh Tock31/34
SMACC Dipole diodes No outlier in 67 and 81 In 56, 3 dipole diodes (MDB) have been extracted and
will be replaced in the coming days In 78: 4 outlier leads (3 diodes)
Too early too conclude; it has to be analysed within the diodes WG (MPE-MSC)
Courtesy M Bednarek & ElQA team
Location
MTF_ID Diode lead Contact resistance [Ohm]
A15L8 HCLBARB000-IN003058 Anode 208 µA15L8 HCLBARB000-IN003058 Cathode 89.8 µA18L8 HCLBBRD000-IN003012 Anode 18.9 μA21R7 HCLBBRA000-IN003014 Cathode 16.6 µ
JPh Tock32/34
SMACC Summary on progress
Main 13 kA Splices: Delay reduces Unavailabilty of components for QDiodes consolidation
Special Interventions: Delay stable
DFBA: See next presentation
SMACC: Slightly more than 2 weeks of delay
Delays are sligthly reducingVery slightly more than nominal rate achieved
these last 17 weeks !
JPh Tock33/34
Sector 56 : Final leak test and surface work on DFBAK SHM Investigation on dipole diodes
Sector 67 : Pressure test successfull Purge, ElQA, Flushing (CRG/MPE): Not formally SMACC project
Sector 78 (Not priority) Work on NC Work on DFBAO at the surface
Sector 81 (Priority) Complete the M leak tests of non problematic Ics Progress on IC closure
Sector 12 Progress on M lines rewelding Start M leak test
Sector 23 Progress on the installation of electrical insulation Work on overheated splices Complete preparation for Q diodes consolidation
Sector 34 Complete splices unsoldering Installation of shunts
Sector 45 Start desoldering and resoldering of splices
SMACC Main activities for the next 2 weeks
JPh Tock34/34
ConclusionsDelays are starting to reduceMind the last X % (S78 is at 91%) effect…
DFBA consolidation (see next presentation)
?: Source of leaks in 78/81 ? : Actions to undertake for bare busbar in Q diodes (Diodes WG)
Issues:Components for consolidation of quadrupole diodesOther diodes issues (Diodes WG-MPE/MSC)Repair of NCs in parallel with production work (March in 67)