smacc twelfth report [20 min ] 18/10/2013
DESCRIPTION
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project. SMACC Twelfth report [20 min ] 18/10/2013. Activities since last LSC (27/09/2013) Arc splices installation By Activities By sectors Globally SIT DFBA DN200 Dashboards Activities for the next 2 weeks Conclusions. - PowerPoint PPT PresentationTRANSCRIPT
SMACC Twelfth report[20 min]
18/10/2013
Jean-Philippe Tock (TE-MSC)
On behalf of the SMACC project
Activities since last LSC (27/09/2013) Arc splices installation
• By Activities• By sectors• Globally
SIT
DFBA
DN200
Dashboards
Activities for the next 2 weeks
Conclusions
JPh Tock4/31
Sector 56 : Work on non-conformities including repair of overheated cable Reclosure (not in priority) and final leak test
Sector 67 (Priority sector) Complete installation of insulation boxes and injection Rewelding of M sleeves Leak test of M lines Reclosure of interconnections and final leak tests DFBA consolidation
Sector 78 Installation of shunts – start installation of electrical insulation Quadrupole diodes consolidation DFBAs consolidation Reconnection of Q5L8
Sector 81 Complete ElQC of existing splices Desoldering / Resoldering of splices Installation of shunts
Other sectors: S12: Start ElQC of existing splices S23: Open busbar lines and diodes containers S34 & 45: Reconnection of replacing magnets Advanced opening for outliers and CSCM segments Inspection of connection cryostats
SMACC Main activities for the next 2 weeks
3From last LSC (27.09.2013)
On-going
Completed but NCs, 63 ICs insulated (yesterday)1/3 done; see later
Overheated splice redone, ≈120 ICs reclosed,
3 subsectors validated, 4 under final leak test
Completed (but NCs)
Completed but NCs On-going, 9/14 vac subsectors validated
>100 Ics reclosed, 5/14 sub-sector under final leak test
> ½ sector completedDesoldering almost completed; resoldering is on-going
Completed (≈ 28%)
> ¼ of S12 ElQC tested, compatible with 30% of splices to redo
On-going
½ of M lines open, all diodes containers open
4 in S34 reconnected, 2 in S45 almost reconnected
JPh Tock5/31
SEQUENCE AND STATUS
OK to open
8 sectors
Open ICs
> 7 sectors
Install DN200
100 %
Open M sleeves
> 5 sectors
ELQC(old splices)
> 4 sectors
Undo / Redo splices
≈ 4 sectors
ELQC(new splices)
Machine Cu
> 3.5 sectors
ELQCafter Cu mach.
> 3.5 sectors
Install shunts
≈ 3.5 sectors
ELQCafter shunt
≈ 3.5 sectors
Insulate splices
≈ 2.3 sectors
Weld M
≈ 2 sectors
Leak test M
> 1.5 sector
Close IC
≈ 1 sector
Final LT
≈ 1/5 sector
Consolidate Q diodes
≈ 2.5 sectors
Availability of components
Cancelled
Completed
JPh Tock6/31
SMACC Progress report by activity
Opened interconnections in 8 sectors, > 7 sectors-eq are opened
JPh Tock7/31
SMACC Progress report by activity
M line cutting : ≈ 5.5 sectors equivalent Replacing team trained at the surface, will go in the tunnel next week Takes in charge the insulation removal activities
JPh Tock8/31
SMACC Progress report by activity
Courtesy H Prin
Desoldering : Completed in S56 & 67 & 78 and @ 65 % in S81 Resoldering completed in S56 & 67 & 78 and @ 50% in S81
Rates are compatible with the 30 % of splices to redo and the baseline rate
From last LSC (27.09.2013)
From last LSC (27.09.2013)
100
80
JPh Tock9/31
SMACC Progress report by activity
Shunts are installed in ≈ 3.5 sectors-eq (1/2)
Rate in 81 is sticking to the baseline «Last 10% effect» in 3 sectors Delay reduced: < 1/2 week (nominal rate)
Shunt weekly installation rate (4 weeks sliding average)
JPh Tock10/31
SMACC Progress report by activity
Shunts are installed in ≈ 3.5 sectors-eq (2/2)
JPh Tock11/31
SMACC Progress report by activity
Installation of insulation box: 56 & 67 are completed and 1/3 in 78,
Courtesy H Prin / M Duret
63 Ics are completed in 78 Rate is still too low but improving
(41 is the maximum achieved so far, average of the last 4 weeks: 33) Progress curves will be integrated with the new baseline
JPh Tock12/31
SMACC Progress report by activity
Quadrupole diodes
> 6 sectors are opened / ≈ 2.5 sectors are consolidated
Components to cover 78 and 1/3 of 81 (3.3 sectors)
Not on the immediate critical path
Second order launched for critical components (expensive)
Delivery expected in a month time
A third solution (reasonable price) is under investigation as a fall back solution
Visit of the 1st company today (Delay issues and also NC components)
Courtesy L Grand-Clement / F Savary
JPh Tock13/31
SMACC Progress report by activity
M Welding : 410 ICs welded, ≈ 2 sec-eq:
No welding this week to build a buffer of ICs ready to be welded (Announced @ last LSC) Holes in 56 and 67 will be done next week Work at a rate of 35-40 IC/week to start next week in 78 (About 70 ICs will be
available on Monday), to sustain up to end 2013 Will be integrated in the overall rebaselining
JPh Tock14/31
SMACC Progress report by activity
M sleeves leak testing : (320 ICs) are leak tested (≈ 1.5 sec-eq)
All possible subsectors of S56 (11/14) are leak tested
9/14 subsectors are leak tested in 67
Present situation will be included in the general rebaselining
Courtesy P Cruikshank / L Mourier
JPh Tock15/31
SMACC Progress report by activity
Reclosure of interconnections : On-going in 67 (priority) and 56 (> 1 sec eq),
120 ICs are reclosed in 56 and 100 in 67 Priority is on S67 Global rate to increase and reach baseline
value with the reinforcement of part of the DN200 team
JPh Tock16/31
SMACC Progress report by activity
Final leak test: Starting
3 subsectors validated 9 more under test
(4 in 56 and 5 in 67) Almost 1 sec eq Results in 2 weeks time
JPh Tock17/31
SMACC Progress report by sector
Main activities are on non-conformities Overheated cable resoldered, now to be shunted and
reinsulated Uninstall shunts to remove the DFBAK shuffling module Similar repair (Sandwich) to be applied in other ICs
Courtesy M Duret, N Dalexandro, P Voisin, R Principe
QQBI.27R8
QBQI.18R8
JPh Tock18/31
SMACC Progress report by sector
All non-problematic ICs are shunted, insulated and rewelded Main activities are the leak test of M lines, the reclosure and the final leak tests
This sector should be the first to be ready for pressure test Planned to be completely reclosed for end of November
JPh Tock19/31
SMACC Progress report by sector
All non-problematic ICs are shunted Main activities are the installation of the electrical insulation and the rewelding of M
lines (to start next week)
JPh Tock20/31
SMACC Dashboards
Opening is ahead of schedule Shunting is almost back on schedule Critical activity is the insulation (Progress curve
soon to be included) Welding and M leak test are limited by release
rate, confident that nominal rate can be achieved, margin has been eaten up
Reclosure: Not yet nominal rate, to be increased Final leak test on-going for almost 1 sec eq
JPh Tock21/31
SMACC Progress report by sector
JPh Tock22/31
SMACC summary status Updated 17-Oct-13
19-Apr-13 212 13-May-13 17-Jun-13 210 19-Jul-13 05-Jul-13 206 08-Aug-13 19-Jul-13 168 15-Aug-13 30-Aug-13 119 27-Sep-13 17-Sep-13 43 25-Oct-13-11 212 -6 -54 212 -41474 -58 212 -41494 4 212 -41501 -10 212 8 212
08-Apr-13 100% 07-May-13 24-Apr-13 99% 08-May-13 97% 23-Jul-13 79% 20-Aug-13 56% 25-Sep-13 20%
16-May-13 211 06-Jun-13 22-Jul-13 209 23-Aug-13 13-Aug-13 203 17-Sep-13 27-Aug-13 152 24-Sep-13 30-Sep-13 100 27-Oct-13 15-Oct-13 0 22-Nov-13-20 211 10 -31 211 -41509 8 211 -41534 5 211 -41541 -27 211 -41574 -41562 211 -41600
26-Apr-13 100% 16-Jun-13 21-Jun-13 99% 21-Aug-13 96% 01-Sep-13 72% 03-Sep-13 47% 0%
07-Jun-13 212 27-Jun-13 26-Aug-13 209 30-Sep-13 18-Sep-13 0 22-Oct-13 02-Oct-13 0 29-Oct-13 28-Oct-13 0 22-Nov-13 12-Nov-13 0 20-Dec-13-24 212 12 -3 212 -41547 -41535 212 -41569 -41549 212 -41576 -41575 212 -41600 -41590 212 -41628
14-May-13 100% 09-Jul-13 23-Aug-13 99% 0% 0% 0% 0%
28-Jun-13 212 18-Jul-13 01-Oct-13 107 04-Nov-13 23-Oct-13 0 26-Nov-13 06-Nov-13 0 03-Dec-13 27-Jan-14 0 21-Feb-14 11-Feb-14 0 21-Mar-14-38 212 8 -11 212 -41582 -41570 212 -41604 -41584 212 -41611 -41666 212 -41691 -41681 212 -41719
21-May-13 100% 26-Jul-13 20-Sep-13 50% 0% 0% 0% 0%
19-Jul-13 212 08-Aug-13 05-Nov-13 0 09-Dec-13 27-Nov-13 0 14-Jan-14 11-Dec-13 0 21-Jan-14 24-Feb-14 0 21-Mar-14 11-Mar-14 0 22-Apr-14-53 212 21 -41583 212 -41617 -41605 212 -41653 -41619 212 -41660 -41694 212 -41719 -41709 212 -41751
27-May-13 100% 29-Aug-13 0% 0% 0% 0% 0%
09-Aug-13 212 29-Aug-13 10-Dec-13 0 27-Jan-14 20-Jan-14 0 21-Feb-14 31-Jan-14 0 27-Feb-14 24-Mar-14 0 22-Apr-14 08-Apr-14 0 21-May-14-67 212 19 -41618 212 -41666 -41659 212 -41691 -41670 212 -41697 -41722 212 -41751 -41737 212 -41780
03-Jun-13 100% 17-Sep-13 0% 0% 0% 0% 0%16-Jul-0025-Nov-13 198 13-Dec-13 29-Jan-14 0 04-Mar-14 24-Feb-14 0 28-Mar-14 07-Mar-14 0 03-Apr-14 24-Apr-14 0 22-May-14 07-May-14 0 20-Jun-14
-188 212 -41621 -41668 212 -41702 -41694 212 -41726 -41705 212 -41732 -41753 212 -41781 -41766 212 -4181021-May-13 93% 0% 0% 0% 0% 0%
06-Jan-14 37 24-Jan-14 05-Mar-14 0 08-Apr-14 31-Mar-14 0 07-May-14 11-Apr-14 0 13-May-14 22-May-14 0 20-Jun-14 06-Jun-14 0 18-Jul-14-255 212 -41663 -41703 212 -41737 -41729 212 -41766 -41740 212 -41772 -41781 212 -41810 -41796 212 -41838
26-Apr-13 17% 0% 0% 0% 0% 0%
19-Apr-13 1506 24-Jan-14 17-Jun-13 735 08-Apr-14 05-Jul-13 409 07-May-14 19-Jul-13 320 13-May-14 30-Aug-13 219 20-Jun-14 17-Sep-13 43 18-Jul-14-11 1695 -41663 -54 1695 -41737 -58 1695 -41766 4 1695 -41772 -10 1695 -41810 8 1695 -41838
08-Apr-13 89% 24-Apr-13 43% 08-May-13 24% 23-Jul-13 19% 20-Aug-13 13% 25-Sep-13 3%
Sleeves Welding M lines Leak Test ICs closure Ins Vac LtestShunts InstallationICs Opening
S56
S34
S45
LHC
S67
S78
S81
S12
S23
SMACC Dashboards
JPh Tock23/31
SMACC Dashboards
JPh Tock24/31
SMACC Progress report SIT
SIT All cryomagnets are reconnected, except the 2 dipoles in S45 and the Q5L8 (SAM) Standard reconnection will be done by the train when it will arrive Just started: Interventions on SAM He level gauges: Accessible for MME intervention (Not critical) On hold: Intervention on the triplets braid
Disconnection of the DFBAK SHM that will start next Monday (See TE-CRG presentation)
Courtesy N Bourcey, S Le Naour
JPh Tock25/31
SMACC Progress report DFBA DFBA: See TE-CRG presentation Impact of interventions to fix the M bellows is under integration in the new baseline DFBAK shuffling module to be disconnected DFBAO on-hold
Courtesy TE-CRG, TE-MSC and EN-MME
?
JPh Tock26/31
SMACC Progress report DN200 DN200 : Work completed
Courtesy Jose Manu Gomes de Faria, A Musso and collaboration with DUBNA
DN200 to install on removed cryomagnets and for the installation of the cryogenics BLM
Part of the team is staying and is trained to assist the opening/closure of interconnections and also the upgrade of the IC thermal shields
JPh Tock27/31
SMACC Dashboards
Baseline: 38.1 % (30.9 %)Completed: 33.7 % (27.0 %)Delay 12 (11) days
Baseline: 54.6 % (49.6 %)Completed: 45.8 % (38.7 %)Delay 30 (28) days
Baseline: 56.6 % (47.4 %)Completed: 37.4 % (32.0 %)Delay 39 (38) days
Baseline: 100 % (100 %)Completed: 100 % (88.2 %)
Completed
Delay stable
Delay stable
Not representativeTo be rebaselined
JPh Tock28/31
SMACC Dashboards
Progress:Baseline: 42.8% (36.3 %)Completed: 36.8% (30.1 %)
Delay 18 (18) days
Stable ; Δbaseline ≈ Δcompleted
JPh Tock29/31
SMACC Summary on progress
Main 13 kA Splices: Delay stabilised to 2 weeks
Special Interventions: Delay stable, new activities (DFBAK SHM)
DFBA:To be rebaselined
DN200:Completed
SMACC: About 3 weeks (stable)
Delays are stableNominal rate achieved these last 5 weeks !
JPh Tock30/31
Sector 56 : Work on non-conformities including installation of all shunts, completion of M welding Disconnection of DFBAK SHM Reclosure (not in priority) and final leak test
Sector 67 (Priority sector) Leak test of M lines Reclosure of interconnections and final leak tests
Sector 78 Installation of electrical insulation M lines rewelding (35-40 ICs /wk) Quadrupole diodes consolidation DFBAs consolidation Reconnection of Q5L8
Sector 81 Desoldering / Resoldering of splices Installation of shunts
Other sectors: S12: ElQC of existing splices S23: Open busbar lines S34: Opening of interconnections S45: Reconnection of replacing magnets and opening of diodes containers Inspection of connection cryostats
SMACC Main activities for the next 2 weeks
JPh Tock31/31
Conclusions DN 200 installation is completed Repair the overheated cable in 56 completed as planned Delays are stabilised
Margin has been eaten up for some activities (M welding, M leak test) Solution is under implementation for the components of the quadrupole
diodes
Issues:Consolidate the splices production rates and increase the rate
of installation of the insulation systems keeping qualityImpact of repair of DFBA bellows (SIT & Vac subsectors)
So far, not so bad …