l rfd manual

Upload: rommel-hidalgo-diaz

Post on 14-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 l Rfd Manual

    1/757

    LLRRFFDD BBrriiddggeeDDeessiiggnn MMaannuuaall

  • 7/30/2019 l Rfd Manual

    2/757

  • 7/30/2019 l Rfd Manual

    3/757

    ii

    Mn/DOT B RIDGE OFFICE

    LRFD Bridge Design Manual

    Minnesota Department of Transportation3485 Hadley Avenue North Mail Stop 610

    Oakdale, MN 55128-3307Phone: (651) 747-2100 Fax: (651) 747-2108

    JULY 2003 OCTOBER 2003 JANUARY 2004 APRIL 2004 OCTOBER 2004DECEMBER 2004 FEBRUARY 2005 MARCH 2005 NOVEMBER 2005

  • 7/30/2019 l Rfd Manual

    4/757

    OCTOBER 2004 LRFD BRIDGE DESIGN i

    TABLE OF CONTENTS

    1. INTRODUCTION..................................................................................... 1-11.1 Overview Of Manual 5-392 ...............................................................1-1

    1.1.1 Chronology Of Manual 5-392 ...................................................1-11.1.2 Material Contained In Manual 5-392 .........................................1-11.1.3 Updates To Manual 5-392 .......................................................1-21.1.4 Format Of Manual References .................................................. 1-2

    1.2 General Bridge Information ..............................................................1-21.2.1 Bridge Office .........................................................................1-21.2.2 Highway Systems...................................................................1-81.2.3 Bridge Numbers.....................................................................1-81.2.4 Limit States To Consider In Design ......................................... 1-101.2.5 Ductility, Redundancy, Operational Importance ........................ 1-10

    1.3 Procedures................................................................................... 1-101.3.1 Checking Of Mn/DOT Prepared Bridge Plans............................. 1-101.3.2 Checking Of Consultant Prepared Bridge Plans ......................... 1-121.3.3 Schedule For Processing Construction Lettings ......................... 1-151.3.4 Bridge Project Tracking System.............................................. 1-161.3.5 Approval Process For Standards ............................................. 1-18

    2. GENERAL DESIGN AND LOCATION FEATURES........................................ 2-12.1 Geometrics ....................................................................................2-1

    2.1.1 Bridge Geometrics..................................................................2-12.1.2 Bridge Deck Requirements ......................................................2-22.1.3 Bridge Undercrossing Geometrics .............................................2-72.1.4 Geometric Details ................................................................ 2-152.1.5 Bridge Railings .................................................................... 2-27

    2.2 Bridge Aesthetics .......................................................................... 2-272.3 Preliminary Bridge Plans ................................................................ 2-27

    2.3.1 General .............................................................................. 2-272.3.2 Bridge Type Selection ........................................................... 2-37

  • 7/30/2019 l Rfd Manual

    5/757

    OCTOBER 2004 LRFD BRIDGE DESIGN ii

    2.4 Final Bridge Plans and Special Provisions.......................................... 2-422.4.1 Final Design Instructions ....................................................... 2-44

    2.4.1.1 Superstructure ................................................................ 2-442.4.1.1.1 Framing Plan ..................................................... 2-442.4.1.1.2 Concrete Wearing Course .................................... 2-452.4.1.1.3 Diaphragms and Cross-frames ............................. 2-45

    2.4.1.2 Pedestrian Bridges........................................................... 2-462.4.1.3 Temporary Bridges and Widenings ..................................... 2-482.4.1.4 Bridge Approaches........................................................... 2-492.4.1.5 Survey........................................................................... 2-502.4.1.6 Utilities .......................................................................... 2-502.4.1.7 Precedence of Construction Documents............................... 2-512.4.1.8 Design Calculation Requirements ....................................... 2-51

    2.4.2 Final Plans .......................................................................... 2-522.4.2.1 Drafting Standards .......................................................... 2-532.4.2.2 Drafting Guidelines .......................................................... 2-532.4.2.3 General Plan and Elevation ............................................... 2-552.4.2.4 Bridge Layout and Staking Plan ......................................... 2-602.4.2.5 Standard Abbreviations .................................................... 2-632.4.2.6 Inclusion of Standard Bridge Details in Plan Sets.................. 2-632.4.2.7 Use of Bridge Standard Plans ............................................ 2-632.4.2.8 Standard Plan Notes ........................................................ 2-632.4.2.9 Quantity Notes and Pay Items ........................................... 2-64

    2.4.3 Revised Sheets .................................................................... 2-652.5 Reconstruction Guidelines and Details .............................................. 2-66

    2.5.1 Superstructure .................................................................... 2-662.5.1.1 Railings.......................................................................... 2-662.5.1.2 Wearing Course............................................................... 2-682.5.1.3 Expansion/Fixed Joints ..................................................... 2-68

    2.5.2 Substructure ....................................................................... 2-802.5.2.1 Abutments...................................................................... 2-802.5.2.2 Piers.............................................................................. 2-80

    2.5.3 Pavement ........................................................................... 2-80

  • 7/30/2019 l Rfd Manual

    6/757

    OCTOBER 2004 LRFD BRIDGE DESIGN iii

    2.6 Construction Requirements............................................................. 2-86Appendix 2-A: Bridge Type Numbers ....................................................... 2-87

    Appendix 2-B: Bridge Special Provisions................................................... 2-88

    Appendix 2-C: Standard Abbreviations..................................................... 2-92

    Appendix 2-D: Bridge Details Part I (B-Details) ......................................... 2-94

    Appendix 2-E: Bridge Details Part II ........................................................ 2-96

    Appendix 2-F: Bridge Standard Plans: Culverts ......................................... 2-98

    Appendix 2-G: Bridge Standard Plans: Retaining Walls ............................... 2-99

    Appendix 2-H: Standard Plan Notes....................................................... 2-100

    Appendix 2-I: Standard Summary Of Quantities Notes ............................. 2-109

    Appendix 2-J: Bridge Pay Items ............................................................ 2-111

    Appendix 2-K: Conversion From Inches To Decimals Of A Foot .................. 2-115

    3. LOADS AND LOAD FACTORS .................................................................. 3-13.1 Load Factors And Combinations ........................................................3-13.2 Load Modifiers ................................................................................ 3-33.3 Permanent Loads (Dead And Earth)...................................................3-33.4 Live Loads .....................................................................................3-4

    3.4.1 HL-93 Live Load, LL................................................................3-43.4.2 Multiple Presence Factor, MPF .................................................. 3-43.4.3 Dynamic Load Allowance, IM ...................................................3-43.4.4 Pedestrian Live Load, PL .........................................................3-43.4.5 Braking Force, BR ..................................................................3-53.4.6 Centrifugal Force, CE .............................................................. 3-53.4.7 Live Load Application To Buried Structures ................................3-53.4.8 Live Load Surcharge, LS..........................................................3-5

    3.5 Water Loads, WA ............................................................................3-53.6 Wind Loads, WS..............................................................................3-53.7 Wind on Live Load, WL ....................................................................3-63.8 Earthquake Effects, EQ ....................................................................3-63.9 Ice Load, IC ................................................................................... 3-63.10 Earth Pressure, EV, EH, Or ES...........................................................3-63.11 Temperature, Shrinkage, Creep, Settlement, TU, SH, CR And SE ...........3-7

  • 7/30/2019 l Rfd Manual

    7/757

  • 7/30/2019 l Rfd Manual

    8/757

  • 7/30/2019 l Rfd Manual

    9/757

    OCTOBER 2004 LRFD BRIDGE DESIGN vi

    5.7.2 Prestressed I-Beam Design Example....................................... 5-715.7.3 Three-Span Haunched Post-Tensioned Concrete Slab

    Design Example ................................................................. 5-101

    6. STEEL STRUCTURES............................................................................... 6-16.1 Materials .......................................................................................6-16.2 General Dimensions And Details ........................................................6-36.3 General Design Philosophy ...............................................................6-7

    6.3.1 Shear Connectors ..................................................................6-96.3.2 Fatigue................................................................................. 6-96.3.3 Deflections............................................................................6-96.3.4 Camber .............................................................................. 6-10

    6.4 Rolled Beams ............................................................................... 6-136.5 Plate Girders ................................................................................ 6-13

    6.5.1 High Performance Steel Girders.............................................. 6-146.6 Curved Girders ............................................................................. 6-146.7 Box Or Tub Girders ....................................................................... 6-156.8 Bolted Connections And Splices....................................................... 6-156.9 Two-Span Plate Girder Design Example............................................ 6-16

    7. RESERVED

    8. WOOD STRUCTURES.............................................................................. 8-18.1 Materials .......................................................................................8-1

    8.1.1 Wood Products ......................................................................8-18.1.2 Fasteners And Hardware .........................................................8-28.1.3 Wood Preservatives ................................................................8-2

    8.2 Timber Bridge Decks ....................................................................... 8-38.2.1 General ................................................................................ 8-38.2.2 Geometry .............................................................................8-58.2.3 Design/Analysis .....................................................................8-58.2.4 Detailing...............................................................................8-68.2.5 Camber/Deflections................................................................ 8-6

  • 7/30/2019 l Rfd Manual

    10/757

    DECEMBER 2004 LRFD BRIDGE DESIGN vii

    8.3 Timber Pile Caps.............................................................................8-68.3.1 Geometry .............................................................................8-78.3.2 Design/Analysis .....................................................................8-78.3.3 Detailing...............................................................................8-78.3.4 Camber/Deflections................................................................8-7

    8.4 Additional References ......................................................................8-78.5 Design Examples ............................................................................8-8

    8.5.1 Longitudinally Laminated Timber Deck Design Example ............... 8-88.5.2 Design Example: Timber Pile Cap ........................................... 8-26

    9. DECKS AND DECK SYSTEMS................................................................... 9-19.1 General .........................................................................................9-1

    9.1.1 Deck Drainage.......................................................................9-29.2 Concrete Deck on Beams ................................................................. 9-2

    9.2.1 Deck Design and Detailing.......................................................9-49.3 Reinforced Concrete Deck Design Example ....................................... 9-17

    10. FOUNDATIONS .................................................................................... 10-110.1 Determination of Foundation Type and Capacity ................................ 10-1

    10.1.1 Foundation Report................................................................ 10-110.1.2 Foundation Recommendations ............................................... 10-1

    10.2 Piles............................................................................................ 10-310.3 Drilled Shafts ............................................................................... 10-510.4 Footings ...................................................................................... 10-8

    10.4.1 General .............................................................................. 10-810.4.2 Footing Supported on Piling or Drilled Shafts............................ 10-910.4.3 Spread Footings................................................................. 10-10

    10.5 Pile Bent Piers and Abutments ...................................................... 10-1110.6 Evaluation of Existing Pile Foundations when Exposed by Scour ......... 10-1110.7 Structure Excavation and Backfill .................................................. 10-13

  • 7/30/2019 l Rfd Manual

    11/757

    OCTOBER 2004 LRFD BRIDGE DESIGN viii

    Appendix 10-A: Sample Bridge Construction Unit Recommendations

    (Future Content) .......................................................... 10-14

    11. ABUTMENTS, PIERS, AND WALLS ....................................................... 11-111.1 Abutments ................................................................................... 11-1

    11.1.1 Integral or Contraction Abutments.......................................... 11-311.1.2 Parapet Abutments............................................................... 11-6

    11.1.2.1 Low Abutments ............................................................... 11-911.1.2.2 High Abutments .............................................................. 11-9

    11.1.3 Wingwalls ......................................................................... 11-1211.1.4 Approach Panels ................................................................ 11-20

    11.2 Piers ......................................................................................... 11-2111.2.1 Geometrics ....................................................................... 11-2111.2.2 Columns ........................................................................... 11-2111.2.3 Cap.................................................................................. 11-2111.2.4 Crash Walls....................................................................... 11-2211.2.5 Design and Reinforcement................................................... 11-2311.2.6 Miscellaneous .................................................................... 11-24

    11.2.6.1 Pile Bent ...................................................................... 11-2511.3 Retaining Walls........................................................................... 11-25

    11.3.1 Cantilever Retaining Walls ................................................... 11-2511.3.2 Counterfort Retaining Walls ................................................. 11-2511.3.3 Anchored Walls.................................................................. 11-2611.3.4 Mechanically Stabilized Earth Walls....................................... 11-2611.3.5 Prefabricated Modular Walls................................................. 11-2811.3.6 Timber Noise Walls on Retaining Walls .................................. 11-2811.3.7 Cantilevered Sheet Pile Walls ............................................... 11-2811.3.8 Design Charts of Cantilevered Sheet Pile Soil Retention

    Walls for Temporary Applications.......................................... 11-29

    11.4 Design Examples ........................................................................ 11-3911.4.1 High Parapet Abutment Design Example................................ 11-3911.4.2 Retaining Wall Design Example ............................................ 11-7111.4.3 Three-Column Pier Design Example ...................................... 11-93

  • 7/30/2019 l Rfd Manual

    12/757

    OCTOBER 2004 LRFD BRIDGE DESIGN ix

    12. BURIED STRUCTURES.......................................................................... 12-112.1 Geotechnical Properties ................................................................. 12-112.2 Box Culverts ................................................................................ 12-2

    12.2.1 Precast ............................................................................... 12-212.2.2 Cast-In-Place ...................................................................... 12-4

    12.3 Design Guidance........................................................................... 12-412.4 Arch Or 3-Sided Structure Design Data ............................................ 12-612.5 Design Criteria for Long-Span Corrugated Steel Structures ............... 12-1412.6 10' x 10' Precast Concrete Box Culvert Design Example.................... 12-18

    13. RAILINGS ........................................................................................... 13-113.1 Materials ..................................................................................... 13-113.2 Design Requirements..................................................................... 13-1

    13.2.1 Traffic Railing ..................................................................... 13-813.2.2 Pedestrian/Bicycle Railing...................................................... 13-913.2.3 Combination Railing ........................................................... 13-1013.2.4 Protective Screening........................................................... 13-1013.2.5 Architectural/Ornamental Railings ........................................ 13-11

    13.3 Design Examples ........................................................................ 13-1213.3.1 F Rail Design Example ..................................................... 13-1213.3.2 Adhesive Anchor Design Example ......................................... 13-27

    14. JOINTS AND BEARINGS ...................................................................... 14-114.1 Bridge Movements and Fixity .......................................................... 14-114.2 Expansion Joints .......................................................................... 14-2

    14.2.1 Thermal Movements ............................................................. 14-214.2.2 Expansion Joint Opening ....................................................... 14-214.2.3 Expansion Joint Detailing ...................................................... 14-314.2.4 Modular Expansion Joints ...................................................... 14-3

    14.3 Bearings ...................................................................................... 14-414.3.1 Loads and Movements .......................................................... 14-414.3.2 Bearing Details .................................................................... 14-414.3.3 Elastomeric Bearings ............................................................ 14-5

  • 7/30/2019 l Rfd Manual

    13/757

  • 7/30/2019 l Rfd Manual

    14/757

    JULY 2003 LRFD BRIDGE DESIGN 1-1

    This section contains general information about the manual along with a

    general description of the Bridge Office and its procedures. It also

    includes guidance on use of the ductility, redundancy, and operational

    importance factors given in LRFD 1.3.3 through 1.3.5.

    Mn/DOT utilizes a decimal numbering system to classify documents. The

    5 before the hyphen represents a publication related to engineering

    functions. The 300 series of documents is assigned to the Bridge

    Office; the 90 series indicates that this is a Manual. The last digit 2

    specifies that the subject matter of the document is Design.

    The original bridge design manual, numbered 5-392, provided guidance

    for the design of highway structures in Minnesota in accordance with

    allowable stress design methods. Subsequently, it has received periodic

    updates as design methods have changed. This version of the Bridge

    Design Manual contains significant changes. It presents Mn/DOTs design

    practices in conformance with a new design methodology, Load and

    Resistance Factor Design (LRFD), and also contains fifteen

    comprehensive design examples.

    Use of this manual does not relieve the design engineer of responsibility

    for the design of a bridge or structural component. Although Bridge

    Office policy is presented here for numerous situations, content of the

    manual is not intended to be exhaustive. Therefore, use of this manual

    must be tempered with sound engineering judgement.

    After the introductory material provided in this section, the manual

    contains material arranged around the following section headings. To

    simplify locating material, section numbers correspond to those used in

    the LRFD specifications:

    1. Introduction

    2. General Design and Location Features

    3. Loads and Load Factors

    4. Structural Analysis and Evaluation5. Concrete Structures

    6. Steel Structures

    7. Reserved

    8. Wood Structures

    9. Decks and Deck Systems

    10. Foundations

    11. Abutments, Piers, and Walls

    12. Buried Structures

    1 .

    I N T RODUCT I O N

    1 . 1 O v e r v ie w o f

    M a n u a l 5 - 3 9 2

    1 . 1 .1 Ch r o n o l o g y

    o f M a n u a l 5 - 3 9 2

    1 . 1 . 2 M a t e r i a l

    Co n t a i n e d i n

    M a n u a l 5 - 3 9 2

  • 7/30/2019 l Rfd Manual

    15/757

    JULY 2003 LRFD BRIDGE DESIGN 1-2

    13. Railings

    14. Joints and Bearings

    Memos

    This manual will be updated multiple times each year as procedures are

    updated and new information becomes available. Current files for each

    section of the manual are available on the Bridge Office Web site

    [http://www.dot.state.mn.us/bridge/].

    Each section of the manual contains general information at the start of

    the section. Design examples (if appropriate) are located at the end of

    each section. The general content is divided into subsections that are

    identified with numerical section labels in the left margin. Labels for

    design example subsections are identified with alphanumeric labels in the

    left hand margin. The left hand margin also contains references to LRFD

    Design Specification Articles, Equations, and Tables. These references

    are enclosed in square brackets.

    Within the body of the text, references to other sections of this manual

    are directly cited (e.g. Section 10.1). References to the LRFD

    Specifications within the main body of the text contain a prefix of: LRFD.

    A bridge is defined under Minnesota Rule 8810.8000 as a structure

    having an opening measured horizontally along the center of the roadway

    of ten feet or more between undercopings of abutments, between spring

    line of arches, or between extreme ends of openings for multiple boxes.

    Bridge also includes multiple pipes where the clear distance between

    openings is less than half of the smaller contiguous opening.

    In accordance with Minnesota Statute 15.06 Subd. 6, the Commissioner

    of Transportation has delegated approval authority for State Preliminary

    Bridge Plans, and State, County and City Final Bridge Plans to the State

    Bridge Engineer. Plans for all bridge construction or reconstructionprojects located on the Trunk Highway System, and plans on County or

    City highways funded fully or in part by state funds shall be approved by

    the State Bridge Engineer.

    The Bridge Office is responsible for conducting all bridge and structural

    design activities and for providing direction, advice, and services for all

    1 . 1 . 3 U p d a t e s t o

    M a n u a l 5 - 3 9 2

    1 . 2 G en e r a l B r i d g e

    I n f o r m a t i on

    1 . 2 . 1 B r i d g e O f f i ce

    1 . 1 . 4 Fo rm a t o f

    M a n u a l R e fe r e n c e s

  • 7/30/2019 l Rfd Manual

    16/757

    JULY 2003 LRFD BRIDGE DESIGN 1-3

    bridge construction and maintenance activities. The responsibilities

    include:

    Providing overall administrative and technical direction for the

    office.

    Reviewing and approving all preliminary and final bridge plans

    prepared by the office and consultants.

    Representing the Department in bridge design, construction and

    maintenance matters with other agencies.

    The office is under the direction of the State Bridge Engineer. It is

    composed of sections and units as shown on the organizational chart

    (Figure 1.2.1.1). Each of these subdivisions with their principal functions

    is listed as follows:

    A. Bridge Design Section

    Responsible for the design, plans, and special provisions activities for

    bridges, and miscellaneous transportation structures.

    1. Design Unit

    a. Designs and drafts bridge plans.

    b. Reviews bridge plans prepared by consulting engineers.

    c. Prepares special provisions for bridge plans.

    d. Designs and drafts plans for miscellaneous highway structures.

    e. Provides technical assistance, designs, and plans for special

    bridge and structural problems.

    2. Bridge Standards and Research Unit

    a. Provides design aids and standards for the office and for

    consultants, counties, and cities.

    b. Coordinates the development and users of computer programs

    with data processing systems.

    c. Supports computer users throughout the office and manages

    the local area network.

    d. Provides oversight for research projects, which involve the

    Office of Bridges and Structures.

    3. Design/Build Unit

    a. Provides oversight of design/build projects.4. LRFD Implementation

    a. Maintains LRFD Bridge Design Manual.

    b. Provides support to office and consulting engineers concerning

    LRFD issues.

    B. Bridge Planning Section

    Responsible for program, cost estimates, preliminary bridge plan

    activities for Trunk Highways and review of state aid bridges.

  • 7/30/2019 l Rfd Manual

    17/757

    JULY 2003 LRFD BRIDGE DESIGN 1-4

    1. Bridge Agreements and Estimates Unit

    a. Selects and negotiates with consulting engineers and

    administers engineering agreements for the preparation of

    bridge plans.

    b. Provides liaison between the office and the consulting engineer

    retained to prepare bridge plans.

    c. Coordinates public and private utility requirements for bridges.

    d. Prepares preliminary, comparative and final cost estimates.

    e. Maintains and provides current program and plan status

    records.

    2. Preliminary Plans

    a. Conducts preliminary studies from layouts and develops

    preliminary bridge plans.

    b. Provides liaison with district and central office road design

    through the design stage.

    c. Obtains required permits from other agencies for bridges.

    3. State Aid Bridge Unit

    a. Reviews bridge plans and special provisions for county and

    municipal state aid projects.

    b. Provides technical assistance to counties and municipalities,

    when requested, for nonparticipating projects.

    C. Bridge Construction and Maintenance Section

    Responsible for bridge construction and maintenance specifications,

    and bridge construction and maintenance advisory service activities to

    the office and to the job site.

    1. Construction and Maintenance Unit; North, Metro and South

    Regions

    a. Provides construction and maintenance advisory service to

    bridge construction and maintenance engineers in the field.

    b. Writes bridge construction and maintenance specifications,

    manuals and bulletins.

    c. Writes and maintains the file of current special provisions for

    bridge construction and maintenance.

    d. Performs preliminary, periodic and final review of bridge

    construction and maintenance projects and makesrecommendations.

    e. Reviews bridge plans and special provisions prior to lettings

    and makes recommendations.

    f. Aids municipal and county engineers with bridge construction

    and maintenance problems, upon request.

    g. Provides foundation design including selection of pile type,

    length, design load, and foundation preparation.

  • 7/30/2019 l Rfd Manual

    18/757

    JULY 2003 LRFD BRIDGE DESIGN 1-5

    h. Reviews bridge improvement projects and prepares

    recommendations for scope of work.

    2. Bridge Ratings Unit

    a. Makes bridge ratings and load postings analysis for existing

    bridges and maintains the records.

    b. Reviews and approves special load permit requests.

    3. Structural Metals Inspection Unit

    a. Provides inspection services for structural metals, fabrication

    and assembly to ensure conformity with plans and

    specifications.

    4. Fabrication Methods Unit

    a. Reviews and approves structural metals shop drawings

    submitted by fabricators.

    b. Provides fabrication advisory service to designers, fabricators

    and field construction and maintenance personnel.

    c. Provides overhead sign design services to the Office of Traffic

    Engineering, including the design of bridge-mounted sign

    trusses.

    5. Bridge Management Unit

    a. Maintains inventory and inspection data for the 19,600 bridges

    in Minnesota. Works with all agencies to make certain

    appropriate data is collected.

    b. Responsible for implementing bridge management systems to

    provide information on bridges for maintenance, repair,

    rehabilitation and replacement.

    6. Bridge Inspection Unit

    a. Provides expert assistance to the Districts in organizing and

    conducting inspections of complex bridges, special features,

    and fracture critical bridges.

    b. Conducts quality assurance inspections of all agencies

    responsible for bridge inspections in Minnesota.

    c. Reviews, recommends and provides bridge inspection training

    for District, county, and municipal bridge inspectors.

    D. Hydraulic Engineering Section

    Responsible for providing statewide hydraulic engineering servicesthat include design, construction and maintenance activities. In

    addition, the section provides leadership in the development and

    implementation of hydraulic automation technology, establishes policy

    pertaining to hydrology and hydraulics, prepares design aids, provides

    client training, participates in research projects, and represents the

    department on state and national committees.

    1. Bridge Design Hydraulics Unit

  • 7/30/2019 l Rfd Manual

    19/757

    JULY 2003 LRFD BRIDGE DESIGN 1-6

    a. Provides bridge and culvert waterway designs for trunk

    highway, county, city and township projects.

    b. Analyzes and evaluates inplace bridges for scour.

    c. Provides technical assistance to counties and municipalities

    upon request.

    d. Provides training in hydrology and hydraulics.

    2. Road Design Hydraulics Unit

    a. Evaluates and codes all bridges over water for scour.

    b. Provides technical assistance to Districts on all aspects of

    drainage design.

    c. Reviews and cost prorates storm drains on the municipal and

    county state aid system.

    d. Coordinates the review of new products and development of

    specifications and policies pertaining to their use.

    3. Hydraulics Automation Unit

    a. Provides leadership and technical direction for managing the

    statewide hydraulic automation effort.

    b. Develops and implements the means to integrate the hydraulic

    design process with the road design process.

    c. Develops, implements, and supports a hydraulic information

    system to facilitate the sharing of hydraulic data among all

    users and stakeholders.

    e. Provides statewide training and support in the implementation

    and use of hydraulic automation techniques.

  • 7/30/2019 l Rfd Manual

    20/757

    JULY 2003 LRFD BRIDGE DESIGN 1-7

  • 7/30/2019 l Rfd Manual

    21/757

  • 7/30/2019 l Rfd Manual

    22/757

    JULY 2003 LRFD BRIDGE DESIGN 1-9

    2. Since about 1950, a five-digit number has been assigned to each

    bridge as it was constructed. The first two digits coincide with the

    county number (01-87) in which the bridge is located (99 refers to

    temporary bridges). The last three digits are assigned consecutively

    using the following guidelines:

    a. 001-499 are used for regular trunk highway bridges.

    b. 500-699 are used for county bridges.

    c. 700-999 are used for interstate bridges (any bridge on or

    over the interstate system).

    3. In 1991, additional numbers were required for bridges on the state

    aid system in Hennepin County and for interstate bridges in Hennepin

    County. To allocate more numbers for bridges on the local system an

    alpha character is used as the third character of the bridge number.

    For example, the next bridge number after Bridge No. 27699 will be

    Bridge No. 27A00. Note that this happens only after 500 and 600

    series have been exhausted.

    To allocate more numbers on the Interstate road system, the 400

    series of numbers will be used along with the 700, 800, 900's

    presently used. For a bridge number XXYZZ, the following now

    applies:

    XX = county number (99 = Temporary Bridge)

    Y = 0, 1, 2, 3, or R, T, U (for Trunk Highway Bridges)

    Y = 4, 7, 8, 9, or V, or W (for Interstate Bridges)

    Y = X and Y (Trunk Highway or Interstate Culverts)

    Y = 5 or 6 or A through H (for non-trunk highway Bridges)

    Y = J through N, and P, Q (for non-trunk highway Culverts)

    ZZ = Sequence number (00 through 99)

    4. In cases of twin bridges, a westbound or southbound lane bridge is

    generally assigned a lower number than an eastbound or northbound

    lane bridge.

    All bridge numbers are assigned by the Bridge Office (phone 651-747-2122). A complete listing of all numbered bridges is available in

    computer printout form entitled Minnesota Trunk Highway Bridge Log-

    Statewide Listing.

  • 7/30/2019 l Rfd Manual

    23/757

    JULY 2003 LRFD BRIDGE DESIGN 1-10

    Bridge designs shall typically consider Strength, Service, Extreme Event,

    and Fatigue limit states. The limit state checks will vary with the

    component under consideration. Not all elements will require

    consideration of all limit states. For example, the fatigue limit state need

    not be considered for fully prestressed pretensioned elements.

    For most structures and structural elements the load modifiers for

    ductility, redundancy, and operational importance shall be 1.00.

    Exceptions are noted below:

    1. The ductility factor shall be 1.05 for prestressed concrete through-

    girder pedestrian bridges when they are over-reinforced.

    2. The importance factor shall be 1.05 for a bridge which satisfies any

    one of the following three criteria: 1) it is a major river crossing, 2)

    its ADT is greater than or equal to 40,000, or 3) it is a new mainline

    interstate bridge.

    3. The importance factor shall be 0.95 for bridges with an ADT less than

    500.

    This section covers the Bridge Office procedures for checking of bridge

    plans, scheduling of projects, and revising or creating standards.

    The general practice of most engineering offices is to require that designs

    they produce be checked before they are reviewed and certified by the

    Engineer in Responsible Charge. Although this practice has always

    been required for structures designed for Mn/DOT, it is recognized that

    the quality of the checking process often varies according to time

    restraints, confidence in the designer, and the instructions given to the

    checker. Therefore, in order to maintain a consistent design checking

    process the following guidance is given for routine bridge designs.

    For more complex or unusual designs, the checker is advised to discuss

    additional requirements with the design unit leader. Also, the checking

    process described is not meant to apply to the check or review functionsrequired for Mn/DOT review of consultant plans (see Section 1.3.2.) or

    for construction false work reviews. (See the Bridge Construction

    Manual.)

    Three types of design checking will apply:

    a. An independent analysis of the completed design.

    b. A check of original design computations for mathematical accuracy,

    application of code, and accepted engineering practice, and

    1 . 2 .5 D u c t i l i t y ,

    R e d u n d a n c y ,

    O p e r a t i o n a l

    I m p o r t a n c e

    [ 1 . 3 . 3 ]

    [ 1 . 3 . 4 ]

    [ 1 . 3 . 5 ]

    1 . 3 P r o c e d u r e s

    1 . 3 .1 Ch e c k i n g o f

    M n / DO T Pr e p a r e d

    B r i d g e P l a n s

    1 . 2 . 4 L im i t S t a t e s

    t o Co n s i d e r i n

    De s i g n

  • 7/30/2019 l Rfd Manual

    24/757

    JULY 2003 LRFD BRIDGE DESIGN 1-11

    c. A review of drafted details for constructibility, and accepted

    engineering practice.

    Generally, an independent analysis to confirm the adequacy of the

    complete design is preferred. Significant differences should be discussed

    and resolved before the plan is certified. The separate set of calculations

    should be included with the design file as a record of the completed

    design check.

    When circumstances prevent a complete independent analysis, as a

    minimum, an independent analysis shall be completed for the following:

    a. Live and dead loads

    b. Critical beam lines

    c. A pier cap

    d. A pier footing

    e. Main reinforcement for high abutments

    f. An abutment footing

    However, for the elements not independently analyzed, the original

    computations should be checked for mathematical accuracy of original

    design computations, applications of code, and accepted engineering

    practice. Checked computations should be initialed by the checker, and

    the independent analysis should be included in the design file.

    When doing a separate analysis, the checker may make simplifying

    assumptions to streamline the checking process. However, when major

    differences are found, results must be discussed and resolved with the

    designer. For instance, for normal piers, piling might be analyzed for

    dead and live loads only if lateral loads appear to have been reasonably

    applied in the original computations or the AISC Beam Diagram and

    Formula Tables may be used to approximate pier cap moment and

    shear.

    Whether the check is a completely independent analysis or a minimal

    analysis combined with a computations check, some details, such as the

    reinforcing details in a wall corner, also require review by the checker.Often referencing old bridge plans with similar details allows the checker

    to compare the current design to details that have performed well in the

    past.

  • 7/30/2019 l Rfd Manual

    25/757

    JULY 2003 LRFD BRIDGE DESIGN 1-12

    Consultant prepared bridge plans are created by private engineering

    firms through contracts with the Department. The finished plans are

    complete to the extent that they can be used for construction.

    Since these plans receive final approval of the State Bridge Engineer,

    there must be assurance that the plans are geometrically accurate and

    buildable; structural design is adequate and design codes have been

    correctly applied; proper direction is given to the construction contractor;

    and all construction costs are accounted for. Plan errors may cause

    costly construction delays or safety may be compromised by an

    inadequate design.

    To keep consultant plan reviews consistent and timely, a procedure was

    developed as a guide that assigns priority to specific items in the plans.

    The overall review includes a Thorough Check and Cursory Review of

    various items. The distinction between Thorough Check and Cursory

    Review is as follows:

    Thorough Check refers to performing complete mathematical

    computations in order to identify discrepancies in the plans, or

    conducting careful comparisons of known data and standards of the

    Project with values given in the plan.

    Cursory Review refers to a comparative analysis for agreement with

    standard practice and consistency with similar structures, all with

    application of engineering judgment. Mathematical analysis is not

    required, but may be deemed necessary to identify the extent of a

    discrepancy.

    The review procedure is listed on the CONSULTANT BRIDGE PLAN

    REVIEW form following this section. Headings on this list are defined as

    follows:

    PARTIAL PLAN: In order to assure that the consultant is proceeding in

    the right direction, an early submittal of the plan is required. This

    submittal usually consists of the General Plan and Elevation sheetshowing the overall geometry of the structure and the proposed beam

    type and spacing; the Bridge Layout Sheet; the Framing Plan sheet; and

    the Bridge Survey sheets. Errors and inconsistencies found in this phase

    can be corrected before the entire plan is completed. For example, a

    framing plan, including the proposed beams, must be assured as

    workable on the partial plan before the consultant gets deep into the

    design of the remainder of the bridge.

    1 . 3 . 2 Ch e c k i n g o f

    C o n s u l t a n t

    P r e p a r e d B r i d g e

    P l a n s

  • 7/30/2019 l Rfd Manual

    26/757

    JULY 2003 LRFD BRIDGE DESIGN 1-13

    FINAL PLAN: A final plan should be complete in all areas to the extent

    that it can be certified by the designer, although a certification signature

    is not required for this phase.

    THOROUGH CHECK: Items indicated for checking on the consultants

    partial plan must be correct. Given geometry must fit the roadway

    layout. Most of this information can be checked using data from the

    approved preliminary plan. Approval of the partial plan will indicate that

    Mn/DOT is satisfied with the geometry and proposed structure, and the

    consultant may proceed with further development of the plan. For the

    final plan, obvious drafting and numerical errors should be marked to

    point out the errors to the consultant, however, the reviewer should not

    provide corrections to errors in the consultants numerical computations.

    Checking on the final plan should be thorough to eliminate possible errors

    that may occur, such as the pay items in the Schedule of Quantities.

    Plan notes and pay items can be difficult for a consultant to anticipate

    because of frequent changes by Mn/DOT. Pay items must be correct

    because these are carried throughout the entire accounting system for

    the Project. Plan (P) quantities must also be correctly indicated.

    CURSORY REVIEW: Normally, a cursory review would not require

    numerical calculations. This type of review can be conducted by reading

    and observing the contents of the plan in order to assure the

    completeness of the work. The reviewer should be observant to

    recognize what looks right and what doesnt look right. Obvious errors or

    inconsistencies on any parts of the plan should be marked for correction.

    Although structural design is usually the major focus of any plan, most

    consultants are well versed in design procedures and should need only

    minimal assistance from our office. A comparison of the consultants

    calculations with the plan details should be performed to assure that the

    plans reflect their design and that the applicable codes are followed. An

    independent design by our office is time consuming and is not

    recommended unless there is a reasonable doubt as to the adequacy of

    the consultants design.

    NO REVIEW: A thorough review of these items would be time-consuming

    and may not produce corrections that are vital to construction; therefore,

    it is recommended that little or no time be spent on the listed items.

    Numerous errors can occur in the Bills of Reinforcement and quantity

    values. However, checking this information is also time-consuming,

    hence the burden of providing correct data should be placed on the

    consultant.

  • 7/30/2019 l Rfd Manual

    27/757

    JULY 2003 LRFD BRIDGE DESIGN 1-14

    CONSULTANT BRIDGE PLAN REVIEW

    Br. No. ________ RTE ____ DATE: PARTIAL PLAN REC'D. _____ DATE FINAL PLAN REC'D. ______

    DESIGN GROUP _______________________ CONSULTANT ______________________________

    No. OF SHEETS IN PLAN ______ DESCRIBE COMPLEXITY_________________________________EST. REVIEW TIME BY DESIGN GROUP ________(hrs.) ACTUAL REVIEW TIME __________(hrs)

    PARTIAL PLAN FINAL PLAN

    THOROUGH CHECK THOROUGH CHECK

    Horizontal and vertical clearances Pay items and plan quantities

    Stations and elevations on survey line Project numbers

    Deck and seat elevations at working points Design data block & Rating on GP&E sheet

    Deck cross-section dimensions Job number

    Working line location and data Certification block

    Coordinates at working points and key stations Standard plan notes

    Substructure locations by station Concrete mix numbers

    Framing Plan Construction joint locations

    Conformance to preliminary plan Prestressed beam design if inadequate design is suspected

    Design loads Bridge seat elevations at working points

    Utilities on bridge

    Existing major utilities near bridge

    CURSORY REVIEWSteel beam splice locations and diaphragm spacing; flangeplate thickness increments (enough to save 800+ # ofsteel)Abutment and Pier design to be checked againstconsultants calculations

    Conformance to foundation recommendations.Pile loads and earth pressures. Check against consultantscalculations.

    CURSORY REVIEW Rebar series increments (min. 3)

    Proposed precast beams [per 5-393.509(2)] Interior beam seat elevations

    Precast conformance to industry standards Bottom-of-footing elevations (for adequate cover)

    Proposed steel beam sections Railing lengths and metal post spacing (check for fit)

    Use of B-details and standard plan sheets

    Conformance to aesthetic requirements

    Notes General, construction, reference, etc.

    Quantity items on tabulations

    Precast beam design (Check against consultantscalculations)

    NO CHECK OR REVIEW REQUIRED

    Diagonals on Layout sheet

    Figures in Bills of Reinforcement

    Bar shapes and dimensions

    Rebar placement dimensions

    Bar marks on details against listed bars

    Quantity values (including total of tabulations)

  • 7/30/2019 l Rfd Manual

    28/757

    JULY 2003 LRFD BRIDGE DESIGN 1-15

    To meet the Department s schedule requirements for construction

    lettings, the following schedule for processing bridge plans, special

    provisions and estimates must be followed. This schedule applies to all

    projects: Federal Aid, State Funds and Maintenance. In general,

    processing of bridge plans, special provisions and estimates for lettings

    shall be given priority over all other work, and every effort must be made

    to complete the processing in advance of the times shown, which are

    deadlines.

    SCHEDULE AND REMARKSDEADLINE TIME BEFORE

    LETTING DATE

    Federal Project State Project

    Bridge plans complete to the extent thatprocessing can be completed on schedule.

    14 Weeks(Friday)

    12 Weeks(Friday)

    Preliminary bridge pay items andquantities for estimate (to Estimating Unit

    Design Services)

    13 Weeks(Friday)

    11 Weeks(Friday)

    Bridge plan and special provisions review

    Complete (by Bridge Construction Unit)13 Weeks

    (Friday)11 Weeks

    (Friday)

    Bridge special provisions complete, otherInformation or material for inclusion in

    Roadway Special Provisions complete (toSpecial Provisions & Final Processing Unit

    Design Services)

    12 Weeks

    (Friday)10 Weeks

    (Friday)

    Bridge plans complete, approved and

    dated (to Office Management Unit)12 Weeks

    (Friday)10 Weeks

    (Friday)

    Final bridge pay items and quantities forestimate (to estimating Unit - Design

    Services)

    12 Weeks(Friday)

    10 Weeks(Friday)

    Final computer runs for bridge estimate during 9th week during 8th week

    Office copy and final bridge plans (Bridgeplans to Special & Final Processing Unit -

    Design Services for submittal to FHWA)

    8 1/2 weeks

    (Tuesday)7 weeks

    (Friday)

    Federal Project to FHWA 7 1/2 weeks(Tuesday)

    7 weeks

    (Friday)

    Preliminary advertisement 6 1/2 weeks

    (Tuesday)

    6 weeks

    (Friday)Final advertisement 5 1/2 weeks

    (Tuesday)5 weeks(Friday)

    Sale of plans and proposals 5 weeks (Friday) 5 weeks(Friday)

    Last date for mailing letter addendums bySpecial Provisions & Final Processing Unit

    Design Services

    10 days(Wednesday)

    10 days(Wednesday)

    1 . 3 . 3 S ch e d u l e f o r

    P r o c e s s i n g

    C o n s t r u c t i o n

    L e t t i n g s

  • 7/30/2019 l Rfd Manual

    29/757

    JULY 2003 LRFD BRIDGE DESIGN 1-16

    Completing a bridge design project for contract letting is a multiple step

    process that involves input from a variety of work units and personnel.

    To follow the process of these projects, the following major milestones

    shown in Tables 1.3.4.1 and 1.3.4.2 are tracked in the Bridge Program

    and Project Management System (PPMS). The project typically begins in

    the Preliminary Plan Unit, continues through a Bridge Final Design Unit,

    and is completed with the Engineer s Estimate. The progress and

    activities completed on active bridge projects are updated monthly.

    Table 1.3.4.1 PPMS Activities for Mn/DOT Prepared Bridge Plans

    PPMS

    ACTIVITY NO.

    COMPLETED

    ACTIVITY

    % PROJECT

    COMPLETED

    0012

    0020

    00220023

    0025

    0030

    0031

    0035

    0040

    0045

    0050

    0076

    0080

    0085

    0090

    Program Estimate

    Bridge Survey

    Bridge HydraulicsBridge Grades (Packet)

    Bridge Foundations

    Bridge Construction Foundation Review

    Bridge Aesthetics Recommendation

    Bridge Preliminary Plan

    District Letter & Prelim. Bridge Estimate

    Bridge FHWA Approval

    Final Bridge Plan

    Designed:

    Drawn:

    Checked:

    Bridge Plan Specifications

    Bridge Plan Review by Bridge Construction

    Bridge Plan Signed

    Bridge Engineer s Estimate

    0 %

    5 %

    6 %8 %

    13 %

    14 %

    14 %

    15 %

    20 %

    20 %

    20 - 40 %

    40 - 65 %

    65 - 85 %

    90 %

    90 %

    95 %

    100 %

    1 . 3 . 4 B r i d g e

    P r o j e c t T r a c k i n g

    S y s t em

  • 7/30/2019 l Rfd Manual

    30/757

    JULY 2003 LRFD BRIDGE DESIGN 1-17

    Table 1.3.4.2 PPMS Activities for Consultant Prepared Bridge Plans

    PPMSACTIVITY NO.

    COMPLETEDACTIVITY

    % PROJECTCOMPLETED

    0012

    0019

    002000220023

    0025

    00300031

    00350040

    00450060

    0062

    00640066

    00680070

    00750076

    0080

    00850090

    Program Estimate

    Bridge Consultant Pre Design Start

    Bridge SurveyBridge HydraulicsBridge Grades (Packet)

    Bridge Foundations

    Bridge Construction Foundation ReviewBridge Aesthetics Recommendation

    Preliminary PlanDistrict Letter & Bridge Prelim. Estimate

    Bridge FHWA ApprovalBridge Consultant Start

    Consultant Partial Plan Delivery

    Mn/DOT Review Partial PlanConsultant Final Plan Delivery

    Mn/DOT Review Final PlanConsultant Final Plan In

    Tracing BackcheckBridge Plan Specifications

    Bridge Plan Review by Bridge Construction

    Bridge Plan Signed

    Engineer s Estimate

    0 %

    3 %

    5 %6 %8 %

    13 %

    14 %14 %

    15 %20 %

    20 %20 %

    25 %

    30 %30 - 80 %

    85 %88 %

    88 %90 %

    90 %

    100 %100 %

  • 7/30/2019 l Rfd Manual

    31/757

    JULY 2003 LRFD BRIDGE DESIGN 1-18

    1 . 3 . 5 A p p r o v a l

    P r o c e s s f o r

    S t a n d a r d s

    NEED FOR NEW ORREVISED STANDARD

    INPUT FROM S.S.R.C.INPUT FROM BRIDGEDESIGN ENGINEER

    INPUT FROM

    CONSULTANTS,INDUSTRY, ANDOTHER Mn/DOT

    OFFICES

    INPUT FROM BRIDGESTANDARDSENGINEER

    INPUT FROM BRIDGEDESIGN UNITS

    R. & D. COMMITTEEFOR POLICY AND APPROVAL

    TO MAKE CHANGES TOSTANDARD OR DEVELOP

    A NEW STANDARD

    IDEA IS SCRAPPED NO

    NE WSTANDARD

    DEVELOPED BYSTANDARDS

    UNIT, DESIGNUNIT OR

    CONSULTANT

    S.S.R.C., WITHSTANDARDSUNIT, MAKESCHANGES TOSTANDARD

    STANDARDGOES TOR. & D.

    COMMITTEE FORAPPROVAL

    THE WORDM OD IFI ED A ND AREVISION DATE IS

    ADDED TOSTANDARD.

    STANDARD IS MADEAVAILABLE.

    COMMENTS RESOLVED ANDCHANGES MADE .

    STANDARD IS SENT TOSTATE BRIDGE ENGINEER

    FOR APPROVAL. A COPY ISSENT TO THE STANDARDS

    UNIT.

    YELLOWROUTING

    SHEET ISDEVELOPED BYBRIDGE

    STANDARDSENGINEER

    REVISED

    STANDARDAFFECTS ONLYBRIDGEOFFICE

    NO

    YE S

    MODIFY

    ACCEPT

    APPROVALDATE AND

    SIGNATUREADDED TO

    STANDARD.

    TRANSMITTAL LETTERDEVELOPED BY

    BRIDGE STANDARDSENGINEER AND

    SIGNED BY STATEBRIDGE ENGINEER.

    TRANSMITTAL LETTERAND STANDARD SENTTO PRINTER. COPIES

    ENTERED INTOSTANDARDS UNIT

    FILE.

    ARCHIVE OLDSTANDARD

    WITHBACKGROUNDOF CHANGES

    MANUAL INSERTSRECEIVED BY USERS

    FOR PLACEMENTINTO MANUALS.

    STANDARD IS SENT OUT ONYELLOW TO OTHER OFFICES

    WITHIN Mn/DOT AND TO BRIDGEOFFICE PERSONNEL. THE WORD

    M OD IF IED A ND RE VI SIO N DA TEIS REMOVED BEFORE

    DISTRIBUTION.

    CHANGESREQUESTED BYBRIDGE OFFICE

    AND OTHEROFFICES ARE

    MADE .

    MINOREDITORIALCHANGESMADE TO

    STANDARD

    NO

    REVISIONDATE IS MORE

    THAN ONEYEAR OLD

    YE S

    MODIFY

    YE S

  • 7/30/2019 l Rfd Manual

    32/757

    APRIL 2004 LRFD BRIDGE DESIGN 2-1

    2 . GENERAL

    DESI GN AND

    LOCAT I ON

    FEATURES

    2 . 1 Ge om e t r i c s

    2 . 1 . 1 B r i d g e

    G eom e t r i c s

    The design of a bridge typically takes place in two major phases of work:

    preliminary design and final design. During preliminary design, the

    structure type, the foundation type, the aesthetics, and the primary

    geometry for the bridge are determined. During final design, specific

    details for all of the elements of the bridge are developed and presented

    in the plan set. These details include material descriptions, quantities,

    and geometric information. Final plan sets are typically assembled in an

    order that roughly follows the order of construction: from the ground up.

    This section of the manual contains a large amount of information useful

    for the preparation and assembly of plans for a project. To facilitate the

    production of plans and standardize the content of bridge plan sets,

    special provisions, B-Details, standard plans, standard plan notes, and

    standard pay items have been prepared by the Bridge Office. Appendices

    to Section 2 identify the material available.

    As the name of the section implies, content for this section is general in

    nature. Guidance for the design of specific structural elements (e.g.

    decks, retaining walls, etc.) is provided elsewhere in the manual.

    Definitions

    For discussion of bridge geometrics in this section, roadways are

    classified as Mainline Highways, Ramps, Local Roads, and Local Streets.

    Each of these four groups is further classified under either Urban or Rural

    Design.

    The following definitions apply:

    Mainline Highways Roadways that carry through traffic lanes for

    freeways, expressways, and primary and secondary highways.

    Local Roads Rural roads off the trunk highway system.

    Local Streets Urban roads off the state trunk highway system.

    Ramps Segments of roadway connecting two or more legs at an

    interchange.

    Urban Design Roadways with curbs on the right and/or left sides.

    Rural Design Roadways without curbs. Median Width The distance between the edges of opposing through

    traffic lanes.

    Auxiliary Lane A lane adjoining a through traffic lane for a purpose

    supplementary to through traffic movement such as truck climbing,

    weaving, speed change or turning.

  • 7/30/2019 l Rfd Manual

    33/757

  • 7/30/2019 l Rfd Manual

    34/757

    APRIL 2004 LRFD BRIDGE DESIGN 2-3

    Functions of the shoulder include:

    Recovery area to regain control of a vehicle.

    Emergency parking area for stalled vehicles and escape route for

    stranded motorists.

    Passageway for bicycles and occasional pedestrians.

    Passageway for emergency vehicles.

    Parking area for bridge maintenance and inspection vehicle (snooper).

    Temporary traffic lane during deck repairs or overlay construction.

    Area for deck drainage and snow storage.

    Accommodates passing of wide oversize loads, especially farm

    machinery.

    On two-lane highways, the shoulders provide an escape area to avoid

    a head-on collision with an oncoming passing vehicle.

    The following shoulder widths for both rural and urban design apply to

    trunk highway bridges. In addition, these standards apply to bridges on

    local roads at a trunk highway freeway interchange. For local roads and

    streets, the bridge roadway widths are given in the State Aid Manual,

    Section 5-892.210 and the State Aid Operations Rules, Chapter 8820.

    Exceptionally long bridges or bridges with a high cost per square foot

    should be evaluated on an individual basis and modifications to these

    standards are allowed based on judgment. In addition to these values,

    the bridge roadway width shall meet the additional requirements for sight

    distance and sharp curvature as specified in Part 3 below.

    1) Rural Designa) Two-Lane Rural Design

    Shoulder widths are given in the table on Figure 2.1.4.1 and are

    dependent on the functional classification of the roadway and

    traffic volumes.

    b) Four-Lane Rural Design

    i) Right Shoulder 12'-0"

    ii) Left Shoulder 6'-0"

    c) Six- or Eight-Lane Rural Divided Highway

    i) Right Shoulder 12'-0"

    ii) Left Shoulder 12'-0"The full inside shoulder allows disabled vehicles in the left lane

    to stop on the inside shoulder rather than try to cross two or

    three lanes of traffic to get to the outside shoulder.

    d) Mainline Rural Bridge with Auxiliary Lane

    i) Right Shoulder 8'-0"

    e) Mainline Rural Bridge with Entrance or Exit Ramps

    i) Right Shoulder 8'-0"

  • 7/30/2019 l Rfd Manual

    35/757

    MARCH 2005 LRFD BRIDGE DESIGN 2-4

    f) Rural Bridges with Turn Lanes

    i) Right Turn Lane

    (1)Right shoulder 6'-0"

    ii) Left Turn Lanes

    (1)Adjacent to a barrier railing: 4'-0" minimum shoulder, 6'-0"

    desirable.

    g) Rural Ramp Bridges (one 16'-0" lane, one-way)

    i) Right Shoulder 6'-0"

    ii) Left Shoulder 4'-0"

    On ramp bridges the dimension from edge of lane to gutter is

    reduced to prevent the appearance of a two-lane bridge on a

    one-lane ramp. The roadway width is 26'-0", which allows

    traffic to pass a stalled vehicle. With a 16'-0" lane the outside

    2'-0" could, in effect, be considered as part of the shoulder for

    a 12'-0" lane.

    2) Urban Design (Approach Curbs)

    For urban designs the bridge gutter lines shall be aligned with the

    curb line on the approaching roadway with the following exceptions:

    a) On four-lane divided highways where there are no median curbs,

    the left shoulder shall be 6'-0".

    b) On six- and eight-lane divided highways where there are no

    median curbs, the left shoulder shall be 10'-0" minimum.

    c) On one-lane urban ramps (16'-0" approach roadway), both right

    and left shoulders shall be 4'-0" (provides a 24'-0" roadway).

    d) Where an auxiliary lane, ramp, or taper extends onto a mainlinebridge, the right shoulder shall be 6'-0".

    e) The minimum distance to a barrier railing is 6'-0" desired, 4'-0"

    minimum.

    Urban shoulder widths will vary according to functional class, traffic

    volumes, scope of work, and quality of pavement surface. Typical

    values are shown in the Road Design Manual, Tables 4-4.01A,

    4-4.01B, and 4-4.01C. Provide a 2'-0" reaction distance to a raised

    island type median or sidewalk curb where vehicle speeds are 40 mph

    and under. For design speeds 45 mph and higher, provide a 4'-0"reaction distance.

    3) Bus Shoulders

    Where the right shoulder has been designated as a bus shoulder a

    12'-0" width shall be provided across bridges. See Road Design

    Manual 4-4.03 and Table 4-4.03A.

  • 7/30/2019 l Rfd Manual

    36/757

    MARCH 2005 LRFD BRIDGE DESIGN 2-5

    4) Additional Width Criteria

    a) Where a ramp (loop) bridge is on a radius of 190'-0" or less, or

    when the volume of trucks is 10% or greater, the effective traffic

    lane is increased from 16'-0" to 18'-0" in width to accommodate

    truck turning movements. Increase the width of the ramp bridge

    accordingly.

    b) For curved bridges longer than 100 feet, check the horizontal

    stopping sight distance and increase the inside shoulder width up

    to a maximum of 10'-0". See Road Design Manual, Chapter 3 for

    calculation of this distance. The 2001 edition of the AASHTO

    book, A Policy on Geometric Design of Highways and Streets,

    changed the height of object from 6" (muffler) to 2'-0" (tail light).

    Table 2.1.2.1 gives widths required for a continuously curving

    bridge for various design speeds and curvature, and applies only

    where the line of sight is blocked by the railing.

    Table 3.1.2.1

    Shoulder Width Requirements for Curved Bridges

    SHOULDER WIDTH FOR DEGREE OF

    CURVATURE LISTEDDESIGN

    SPEED6 FT. 8 FT. 10 FT.

    70 mph to 0o 45 > 0o 45 to 1o > 1o

    60 mph to 1o 15 > 1o 15 to 2o > 2o

    50 mph to 2o 30 > 2o 30 to 3o 15 > 3o 15

    40 mph to 5o 30 > 5o 30 to 7o > 7o

    c) For bridges on tapers, the taper should begin or end at a pier or

    an abutment, or continue across the entire length of the bridge.

    Extra width to eliminate or simplify a taper or curvature is

    permissible where justified by simplified design and construction.

    Cross Slopes on Bridges

    1) The cross slope on bridge traffic lanes is the same as the approaching

    roadway lanes, normally 0.02 ft./ft. The shoulder cross slope on the

    bridge may continue at 0.02 ft./ft. or, if better drainage is desired,

    may be 0.005 ft./ft. greater than the adjacent lane, with a maximum

    cross slope of 0.04 ft./ft. When the bridge deck is superelevated, the

    shoulders shall have the same slopes as the adjacent bridge traffic

    lanes.

    Keep superelevation transitions off bridges. In instances where they

    are unavoidable, it is preferable for ease of deck pouring to maintain

  • 7/30/2019 l Rfd Manual

    37/757

    MARCH 2005 LRFD BRIDGE DESIGN 2-6

    a straight line across the deck at all locations (allows a straight screed

    between paving rails placed at both sides of the deck.)

    2) Ramp cross slopes shall be uniform between the bridge curbs with a

    slope of 0.02 ft./ft. to the right unless superelevated.

    Bridge Median

    On divided highways with a separate bridge for each roadway, the

    openings between bridges must be a minimum of 8'-0" wide if access for

    bridge inspection vehicles (snoopers) is required.

    Longitudinal joints along the median of bridges should be used only for

    bridge roadways wider than about 100 feet or for other special cases. By

    eliminating this joint on bridges with medians, simpler detailing and

    simpler construction can be used.

    Bridge Sidewalks and Bikeways

    Bridge sidewalks of 6'-0" minimum widths are to be provided where

    justified by pedestrian traffic. When bicycle traffic is expected, the width

    should be 8'-0" minimum and 10'-0" desirable. Where an off road

    bikeway is to be carried across a bridge, the full width of the approach

    bikeway may be continued across the bridge up to a maximum width of

    12'-0". Widths beyond 12'-0" are considered excessive. When the

    shoulders of the bikeway cannot be carried over bridges, provide lead-in

    guardrail.

    The curb height for sidewalks adjacent to the roadway is 8". When the

    design speed on the street is over 40 mph, a concrete barrier is required

    between the roadway and the sidewalk (or bikeway). In addition, a

    pedestrian (or bikeway) railing is required on the outside.

    When a barrier is provided between the traffic lanes and the sidewalk,

    use the bridge slab for the walkway (i.e., do not require an additional

    pour for sidewalk). Advise the road plans designer to provide for any

    necessary sidewalk ramping off the bridge.

    Sidewalks and bikeways shall have a minimum cross slope of 0.01 ft./ft.

    Protective Rails at Bridge Approaches

    The ends of bridge railings must be protected from being impacted

    (except on low speed roads such as city streets). For design speeds over

    40 mph, a crash tested guardrail transition (normally plate beam

    guardrail) is required.

  • 7/30/2019 l Rfd Manual

    38/757

    MARCH 2005 LRFD BRIDGE DESIGN 2-7

    2 . 1 . 3 B r i d g e

    U n d e r c r o s s i n g

    G eom e t r i c s

    Refer to State-Aid Operation Rules, Chapter 8820 for guardrail

    requirements on local bridges.

    General Criteria for Lateral Clearance

    Bridge undercrossing geometrics must rationalize safety requirements

    with costs and physical controls such as span length and permissible

    depth of structure. The following guidelines apply in establishing these

    geometrics:

    1) Safety

    Piers, abutments, side slopes and back slopes steeper than 1:3, and

    guardrails can all be hazards to an out of control vehicle. It is

    desirable at all bridge undercrossings to provide a clear zone recovery

    area beside the roadway that is free from these hazards. This clear

    zone is given in the Road Design Manual, Section 4-6.0 and is a

    function of the roadway curvature, design speed, ADT, and ground

    slope. For the area under bridges a practical maximum clear zone of

    30 feet may be used as permitted in the 2002 AASHTO Roadside

    Design Guide, Table 3.1 based on consistent use and satisfactory

    performance. Eliminate side piers from the roadside area wherever

    possible. The desirable bridge undercrossing will satisfy the above

    safety criteria.

    For those locations where it is totally impractical to provide a full clear

    zone recovery area at an undercrossing (as at some railroadunderpasses and in certain urban situations), lesser side clearances

    are permitted. Where the full recovery areas must be infringed upon,

    the greatest side clearances that circumstances will permit shall be

    used. A side clearance of 20 feet is not as desirable as 30 feet but is

    still better than the absolute minimum clearance. Minimum lateral

    clearances are specified under the section for Lateral Clearance for

    Mainline Highways.

    Where drainage must be carried along the roadway passing under a

    bridge, either a culvert must be provided at the approach fill or theditch section must be carried through at the toe of the bridge

    approach fill. The use of a culvert will often permit more desirable

    bridge geometrics, but the culvert openings can also introduce a

    roadside hazard. A determination regarding drainage (need for

    culverts, size of a culvert, and assessment of possible hazard) will be

    a controlling factor in deciding geometrics of the bridge for the site.

  • 7/30/2019 l Rfd Manual

    39/757

    MARCH 2005 LRFD BRIDGE DESIGN 2-8

    2) Economics

    Prestressed concrete beam spans (in length up to about 145 feet) are

    normally the most economical type of construction for grade

    separations. In addition, there will usually be greater economy in

    constructing grade separations using two long spans rather than

    constructing four shorter spans, provided that a concrete

    superstructure can be used.

    3) Aesthetics

    The use of longer spans will necessitate a deeper superstructure and

    higher approach fills. Consideration must be given to the effect of the

    depth of structure on the overall appearance and design of the

    undercrossing.

    For rough calculations during preliminary planning, the depth of

    highway bridge superstructures can be assumed to be about 1/20 of

    the length of the longest span. (Depth of superstructure refers to the

    dimension from top of slab to bottom of beam.) Contact the

    Preliminary Bridge Plans Engineer for the exact dimensions to be used

    in final planning. Contact the Preliminary Bridge Plans Engineer for

    depth of structure on railroad bridges.

    Lateral Clearance for Mainline Highways

    1) The desirable lateral clearance right and left from the edge of through

    traffic lanes to any hazard (as described above) is the full clear zone.

    30'-0" may be used as a practical maximum. Side piers shall beeliminated entirely wherever feasible.

    2) The details for rural design provide for selection of geometrics that

    carry the ditch section through the bridge (Alternate B), and also

    geometrics that have a filled ditch (Alternate A). (See Figures 2.1.4.1

    and 2.1.4.3.) Alternate A permits a shorter bridge superstructure and

    thereby improves the economics and the chance of eliminating side

    piers and is used almost exclusively. However, Alternate A can only

    be used where ditch culverts will be deleted or used without

    introducing a significant safety hazard.

    3) Where the roadway ditch section (rural design) is modified at the

    bridge (Alternate A), a longitudinal transition from the ditch section to

    the 0.04 ft./ft. side slope under the bridge must be provided. Use a

    maximum longitudinal slope of 1:20.

    4) For an auxiliary lane, the clear zone must be maintained from both

    the through traffic lane and the auxiliary lane.

  • 7/30/2019 l Rfd Manual

    40/757

    MARCH 2005 LRFD BRIDGE DESIGN 2-9

    5) For ramps and tapers adjacent to the mainline highway, the clear

    zone must be maintained from both the through lane and the taper.

    A reduced design speed, usually 50 mph, is assumed for the taper.

    6) Minimum Lateral Clearances

    The following paragraphs list those instances where less than

    desirable geometrics can be considered and describes the minimum

    values that will apply. Where geometrics less than desirable are to be

    used, approval of the State Bridge Engineer and State Design

    Engineer must be obtained. For plate beam guardrail with standard

    6'-3" post spacing, a minimum of 3'-0" is required between the face

    of the guardrail and the face of the pier or abutment to allow room for

    the guardrail to deflect. (See Road Design Manual10-7.02.01.)

    a) Through Traffic Lanes Right Side

    For urban design, the lateral clearance on the right measured

    from the edge of the through lane shall be not less than 10'-0"

    width for an approaching shoulder plus the minimum width of

    approaching berm. This will result in minimum dimension of

    16'-0" from the edge of a lane to face of substructure unit.

    For auxiliary lanes, tapers, and ramps along urban mainline

    highways, the minimum lateral clearance from the edge of a lane

    to face of pier or abutment on the right is 10'-0". This provides

    room to construct the standard 6'-0" ramp shoulder plus providing

    an additional 4'-0" of space for guardrail. However, in no eventshall the distance from the edge of a through lane to the face of a

    pier be less than 16'-0".

    For rural design, the lateral clearance on the right may be reduced

    from the full clear zone distance at railroad overpasses. At these

    locations the minimum clearance on the right shall be as described

    above for urban designs.

    b) Through Traffic Lanes Left Side of Divided Highways

    i) Urban Highways with Continuous Median BarriersThe minimum clearances at continuous median barriers are

    based on the use of a concrete barrier between the roadways.

    (See Std. Plate 8322.)

    For urban design, four-lane divided roadways, the minimum

    clearance on the left will be based on providing an 8'-0" wide

    shoulder from the edge of a through lane to median gutter line

    away from the bridge. The 8'-0" wide shoulder may be

  • 7/30/2019 l Rfd Manual

    41/757

    MARCH 2005 LRFD BRIDGE DESIGN 2-10

    infringed upon as necessary to carry the median barrier

    around a bridge pier. At normal grade separations, using 3'-0"

    thick piers, the 8'-0" shoulder may be reduced to 6'-2" at the

    pier. (See Figure 2.1.4.11.)

    For urban design, six- and eight-lane divided roadways, the

    minimum clearance on the left is based on providing a

    10'-0" minimum wide shoulder from the edge of a through

    lane to median gutter line outside of the bridge. As described

    above for four-lane divided roadways, this dimension may be

    infringed upon as necessary to carry the median barrier

    around a bridge pier. This may result in reducing the shoulder

    width from 10'-0" to 8'-2" at normal grade separations

    (assuming 3'-0" thick pier). (See Figure 2.1.4.11.)

    ii) Urban Highways without Continuous Median Barriers

    The warrant requiring a median barrier is based on the median

    width and the ADT. (See Road Design Manual.) At those

    locations where the clear distance to a center pier is less than

    the clear zone distance from the edge of a lane, but where a

    continuous barrier will not be provided, a plate beam barrier

    will normally be required at the pier.

    The pier with plate beam guardrail protection can be used only

    in medians that are 18'-6" or wider for four-lane divided

    highways, and 22'-6" or wider for six- and eight-lane dividedhighways. (Dimensions are from the edge of lane to edge of

    lane.) Piers on high speed roadways should not be placed in

    medians narrower than 18'-6" (four- lane) or 22'-6" (six- or

    eight-lane).

    The face of the plate beam will be located 2'-0" from the face

    of the pier. At normal grade separations (with 3'-0" pier

    thickness) this will result in a dimension of 5'-6" from the edge

    of lane to face of the guardrail on four-lane divided roads, and

    a dimension of 7'-6" from the edge of lane to face of theguardrail on six- and eight-lane divided roads.

    iii) Rail Overpasses Using Rural Design

    For rural design, the median width (edge of lane to edge of

    lane) for roadways passing under railroads may be considered

    for a reduction. Where a reduced width is used, the distance

    from the edge of lane to face of pier should be not less than

    20'-0".

  • 7/30/2019 l Rfd Manual

    42/757

    MARCH 2005 LRFD BRIDGE DESIGN 2-11

    Lateral Clearances for Ramps

    When rural or urban ramps pass under a bridge independently, piers

    should be eliminated and the approaching typical section should be

    carried through the bridge. On extremely skewed bridges where piers

    are necessary, place the face of pier 2'-0" further from roadway than toe

    of back slope. (See Figure 2.1.4.8.)

    Lateral Clearances for Local Roads

    Lateral clearances for local roads are dependent on ADT. The applicable

    values are shown on Figure 2.1.4.9.

    Lateral Clearance for Local Streets

    Locate the face of piers or abutments on or beyond the property line.

    This will provide for the ultimate development of the section by local

    authorities. A minimum distance of 6'-0" from the face of a curb to the

    face of pier or abutment must be provided.

    Lateral Clearance for Railroads

    Lateral clearances at railroads are to be determined as follows:

    1) The statutory clearances diagram shown on Figure 2.1.4.10

    represents the absolute minimums that must be adhered to. For

    design, a minimum horizontal clearance of 9'-0" to a pier or abutment

    is to be used (8'-6" legal).

    2) Side piers are placed 4'-0" in from the back slope control point (18'-0"

    clear to the centerline of track for a cut section without amaintenance road). This puts the face of pier 2'-0" outside the

    bottom of a 3'-0" deep ditch with a 1:2 slope and allows the railroad

    to periodically clean the ditch with track-mounted equipment.

    3) Mn/DOT and FHWA have agreed to the horizontal clearances shown in

    Figure 2.1.4.10 (25'-0" minimum clearance to pier, 30'-6" to back

    slope control point) for mainline BNRR tracks at sites meeting the

    following conditions:

    a) When the standard will not increase the cost of the structure by

    more than $50,000.b) When sufficient vertical clearance exists between the tracks and

    inplace or proposed roadway profile to accommodate the structure

    depth necessary for the longer spans typically required by the

    standard.

    If these conditions cannot be met, submit a letter to the Railroad

    Administration Section along with the signed Preliminary Bridge Plan

  • 7/30/2019 l Rfd Manual

    43/757

    MARCH 2005 LRFD BRIDGE DESIGN 2-12

    stating the reasons the standard cannot be met including an estimate

    of the increased cost if applicable.

    4) Back slopes shall be 1:2 and pass through the back slope control

    point shown on Figure 2.1.4.10 for the applicable case. The

    dimension to the back slope control point indicates the maximum

    extent of federal participation in the construction and must not be

    exceeded.

    5) The Preliminary Bridge Plans Engineer will contact the Railroad

    Administration Section of the Office of Railroads and Waterways to

    determine the need for provisions for a maintenance road for track

    maintenance equipment. If the Railroad Administration Section

    determines that the need is justified, the dimension to the back slope

    control point can be increased up to 8'-0".

    Waterway Sections Under Bridge Crossing Streams

    The Waterway Analysis (hydraulics report) gives information on the

    required stream cross section under the bridge including waterway area

    and low member elevation. Potential flood damage, both upstream and

    downstream, and permitting agencies requirements must be considered.

    Vertical Clearance for Underpasses

    Table 2.1.3.1 lists the minimum vertical clearance requirements for trunk

    highway underpasses.

    Table 2.1.3.1

    Vertical Clearance for Underpasses

    TYPE OF STRUCTUREDESIGN VERTICAL

    CLEARANCES

    Trunk Highway Under Roadway Bridge 16'-4"

    Trunk Highway Under Railroad Bridge 16'-4"

    Railroad Under Trunk Highway Bridge 23'-0" *

    Trunk Highway Under Pedestrian Bridge 17'-4"

    Trunk Highway Under Sign Bridge 17'-4"

    Portal Clearances on Truss or Arch 20'-0"

    * Critical vertical clearance point offset 8'-6" from centerline of track, statutoryminimum vertical clearance is 22'-0".

    For trunk highway bridges over local streets and roads, the minimum

    vertical clearance is 16'-4" for rural-suburban designs and 14'-6" for

  • 7/30/2019 l Rfd Manual

    44/757

  • 7/30/2019 l Rfd Manual

    45/757

    MARCH 2005 LRFD BRIDGE DESIGN 2-14

    Vertical Clearance over Waterways

    1) Non-Navigable Waterways

    A 3'-0" minimum clearance between the 50-year flood stage and low

    point on the bridge superstructure is recommended. This amount of

    clearance is desired to provide for larger floods and also for the

    passage of ice and/or debris. If this amount of clearance is not

    attainable due to constraints relating to structure depth, roadway

    grades or other factors, reduced clearance may be allowed. The

    Preliminary Bridge Plans Engineer, after consultation with the

    Hydraulics Section and the Mn/DOT District Office, will determine the

    required clearance.

    2) Navigable Waterways

    a) Waterways that require a construction permit from Coast Guard

    (generally considered to be waterways for commercial shipping):

    The Mississippi River downstream from I-694 in Fridley

    The Minnesota River downstream from Chaska

    The St. Croix River downstream from Taylors Falls

    The St. Louis River downstream from Oliver, Wisconsin.

    Guide vertical clearances published by the Coast Guard are:

    Mississippi River:

    52'-0" above 2% flowline or 60'-0" above normal pool,

    whichever is greater, for the portion downstream of the

    Burlington Northern Railroad Bridge near the University of

    Minnesota (mile point 853.0). 4'-0" above river stage of 40,000 c.f.s. for the river portion

    upstream (mile point 853.0 to 857.6).

    Minnesota River:

    55'-0" above normal pool from mouth to I-35W bridge

    (mile point 10.8).

    30.8 feet above 1881 high water from I-35W bridge to

    Chaska.

    St. Croix River:

    52'-0" above 2% flowline or 60'-0" above normal pool from

    mouth to Stillwater. St. Louis River:

    The Bong Bridge over the St. Louis River Bay in Duluth has

    a vertical clearance of 120'-0".

    The Preliminary Bridge Plans Engineer shall be consulted when

    establishing navigation clearances.

  • 7/30/2019 l Rfd Manual

    46/757

  • 7/30/2019 l Rfd Manual

    47/757

    APRIL 2004 LRFD BRIDGE DESIGN 2-16

    F ig u r e 2 . 1 . 4 .1

    G eom e t r i c s

    2 - L a n e H ig h w a y ( R u r a l )

  • 7/30/2019 l Rfd Manual

    48/757

  • 7/30/2019 l Rfd Manual

    49/757

  • 7/30/2019 l Rfd Manual

    50/757

  • 7/30/2019 l Rfd Manual

    51/757

    APRIL 2004 LRFD BRIDGE DESIGN 2-20

    F ig u r e 2 . 1 . 4 .5

    D e s ir a b l e G eom e t r i c s

    6 - L a n e D iv i d e d H i g h w a y ( R u r a l)

  • 7/30/2019 l Rfd Manual

    52/757

    MARCH 2005 LRFD BRIDGE DESIGN 2-21

    F ig u r e 2 . 1 . 4 .6

    D e s ir a b l e G eom e t r i c s

    6 - L a n e D iv i d e d H ig h w a y ( U r b a n )

    (Details for 8-Lane Divided Highway Are Similar)

  • 7/30/2019 l Rfd Manual

    53/757

    MARCH 2005 LRFD BRIDGE DESIGN 2-22

    F ig u r e 2 . 1 . 4 .7

    D e s ir a b l e G eom e t r i c s

    6 " R a is e d I s l a n d , Tu r n L a n e s , a n d S id e w a l k s ( U r b a n )

  • 7/30/2019 l Rfd Manual

    54/757

    APRIL 2004 LRFD BRIDGE DESIGN 2-23

    F ig u r e 2 . 1 . 4 .8

    D e s ir a b l e G eom e t r i c s

    R am p s ( R u r a l a n d U r b a n )

  • 7/30/2019 l Rfd Manual

    55/757

    APRIL 2004 LRFD BRIDGE DESIGN 2-24

    F ig u r e 2 . 1 . 4 .9

    L o c a l R o a d s

    ( R u r a l )

  • 7/30/2019 l Rfd Manual

    56/757

    APRIL 2004 LRFD BRIDGE DESIGN 2-25

    F ig u r e 2 . 1 . 4 . 1 0

    Ra i lr o a d Cl e a r a n c e s

  • 7/30/2019 l Rfd Manual

    57/757

  • 7/30/2019 l Rfd Manual

    58/757

    APRIL 2004 LRFD BRIDGE DESIGN 2-27

    2 . 1 . 5 B r i d g e

    Ra i l i n g s

    2 . 2 B r i d g e

    A e s t h e t i c s

    2 . 3 P r e l i m i n a r y

    B r i d g e P l a n s

    2 . 3 . 1 Ge n e r a l

    See Section 13 of this manual for the policy on design of bridge railings

    for Mn/DOT projects.

    The aesthetic design process is initiated early in a bridge projects life.

    The Preliminary Bridge Plans Engineer will determine which of three

    levels of aesthetic attention is appropriate for the bridge.

    Level A is intended for bridges with major cultural or aesthetic

    significance.

    Level B is used for mid-level structures, including highway corridors.

    Level C is used for routine bridges.

    Maximum levels of Mn/DOT participation in aesthetic costs are given in

    the Mn/DOT Policy Manual, Chapter 6, 6-41. For Level A the maximum is

    15% but not to exceed $3 million per bridge; for Level B the maximum is

    7% but not to exceed $300,000 per bridge; for Level C the maximum is

    5% but not to exceed $200,000 per bridge.

    The Preliminary Bridge Plans Engineer along with the District Project

    Manager coordinates the implementation of the aesthetic design process

    as it relates to bridges. Other people, offices