lake charles cracker project (lccp) gas-to-liquids …
TRANSCRIPT
LAKE CHARLES CRACKER PROJECT (LCCP) &
GAS-TO-LIQUIDS PROJECT (GTL)
Rezoning Application
APRIL 2014
PREPARED FOR:
CALCASIEU PARISH POLICE JURY
PREPARED BY:
C.H. FENSTERMAKER & ASSOCIATES, LLC
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
2 | P a g e
Project Team
C.H. Fenstermaker & Associate, LLC 135 Regency Square Lafayette, Louisiana 70508 Tel: 337‐237‐2200 www.fenstermaker.com Kean Miller LLP 400 Convention Street, Suite 700 Baton Rouge, Louisiana 70802 Tel: 225‐382‐3411 Villavaso & Associates, LLC 6304 Beauregard Avenue New Orleans, Louisiana 70124 Tel: 504‐343‐9096
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
3 | P a g e
TABLE OF CONTENTS
1.0 INTRODUCTION ................................................................................................................................. 4
2.0 SASOL GLOBAL .................................................................................................................................. 4
3.0 THE PROJECTS ................................................................................................................................... 5
4.0 SITE LAYOUT ...................................................................................................................................... 6
5.0 ZONING REQUEST ........................................................................................................................... 10
6.0 ECONOMIC IMPACT ASSESSMENT .................................................................................................. 14
7.0 SAFETY, HEALTH, AND ENVIRONMENTAL ....................................................................................... 16
8.0 ENVIRONMENTAL PERMITTING ...................................................................................................... 19
9.0 TRAFFIC IMPACT ANALYSIS ............................................................................................................. 21
10.0 DRAINAGE IMPACT ANALYSIS ......................................................................................................... 25
11.0 CONCLUSION ................................................................................................................................... 28
REFERENCES ................................................................................................................................................ 29
EXHIBITS ...................................................................................................................................................... 30
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
4 | P a g e
1.0 INTRODUCTION
Sasol North America Inc. (Sasol) plans to make a significant investment in Southwest, Louisiana, with the
proposed construction of a world‐scale ethane cracker and derivatives complex as well as a gas‐to‐
liquids facility at its Westlake site. This innovative complex will not only benefit our nation’s energy
security, but will also be a tremendous economic stimulus to this region.
To begin construction on this project, Sasol is requesting the rezoning of purchased property within its
site plan. This application has been prepared to summarize the economic, traffic, drainage, and
environmental impacts associated with this project, and to address these impacts in accordance with
local, state, and federal standards. This information is being presented to the Calcasieu Parish Police
Jury (CPPJ) – Division of Planning and Development so that it can make a decision on this rezoning
request.
Details pertaining to Sasol’s cooperation with other public and private entities are detailed in the
developer’s agreement that accompanies this application.
2.0 SASOL GLOBAL Sasol is an international integrated energy and chemical company that leverages the talent and
expertise of our more than 35,000 people working in 37 countries. Sasol develops and commercializes
technologies and builds and operates world‐scale facilities to produce a range of products including
SASOL GLOBAL
Based in Johannesburg, South Africa US Headquarters in Houston, Texas 35,000 Employees in 37 Countries Operations produce the building blocks that help make everyday products
including detergents, plastics, and liquid fuels.
CORE VALUES
Safety-People-Integrity-Accountability- Stakeholder Focus-Excellence in all that they do
COMMITMENT
Committed to providing a safe working environment for their employees and being a good neighbor in the communities where they operate.
Committed to advancing sustainable development.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
5 | P a g e
liquid fuels, high‐value chemicals and low‐carbon electricity.
These fuels and chemicals are then used to produce the
building blocks that make everyday products such as
detergents, plastics, and fragrances.
Sasol is headquartered in Johannesburg, South Africa. Its
United States headquarters is in Houston, Texas.
Sasol’s Louisiana industrial facility, known as the Lake
Charles Chemical Complex (LCCC), purchased in 2001 from
RWE DEA (and formerly known as Condea‐Vista), began
initial operations in 1961 with the world's largest synthetic
Alcohol Unit. Through the 1960s and 1970s, the facility
expanded to include a Normal Paraffin Unit, Ethoxylation
Unit, Ethylene Unit and Alumina Unit. In 1981, a Linear
Alkylbenzene Unit was added to the facility and in 2004 the
R&D facility was relocated from Austin, Texas to the LCCC.
Sasol’s goal is to minimize risk, eliminate incidents,
responsibly manage environmental impacts, and enable
excellence in operations and business performance while
providing a workplace that protects our employees, service
providers, and neighbors.
Sasol makes important economic contributions to the
communities in which it operates. Each year Sasol donates
more than $300,000 to local nonprofit organizations and is a
major contributor to the economy of Southwest Louisiana
through annual taxes and the purchase of goods and
services totaling more than $160 million.
3.0 THE PROJECTS
Sasol is proposing construction and development of
approximately 3,034 acres of property just west of
Westlake, Louisiana in central Calcasieu Parish. The projects
are composed of two facilities: A chemical facility known as
the Lake Charles Cracker Project (LCCP) and a Gas‐To‐Liquids
facility (GTL). The two projects have separate economic
drivers, and each can stand alone without the need for the
other.
GAS-TO-LIQUIDS PROJECT (GTL)
First in the US
Proven Technology that coverts natural gas into GTL
diesel and other products
Will convert natural gas into more than 96,000 barrels
per day of GTL diesel
Estimated Cost $11-$14 billion
Schedule
2016 Begin Construction 2019 Phase 1 Startup 2020 Phase 2 Startup
LAKE CHARLES CRACKER PROJECT (LCCP)
Ethane “cracking” is the process of breaking down
molecules of ethane contained in natural gas to
create ethylene
Will produce approximately 1.5 million tons of ethylene
per year
Estimated Cost $5-$7 billion
Schedule
2014 Begin Construction 2017 Startup
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
6 | P a g e
The chemical facility will be a world‐scale ethane cracker. Ethane “cracking” is the process of breaking
down molecules of ethane contained in natural gas to create ethylene, one of the building blocks of the
petrochemical industry. The facility will produce approximately 1.5 million tons of ethylene per year.
The ethylene will be used in seven downstream derivative plants to produce a range of products such as
detergents, fragrances, paints, film, synthetic fibers, and food
packaging. Estimated cost of the facility is $5 to $7 billion.
Pending final investment decision, construction is set to begin in
2014, with beneficial operations commencing in 2017.
The GTL facility will be the first in the United States. The GTL
facility converts natural gas into diesel for transportation, as well
as other products. GTL diesel burns cleaner and has lower
greenhouse gas emissions than conventional diesel. It is also virtually free of sulfur and aromatic
compounds. The facility will product more than 96,000 barrels per day of liquid fuels and chemicals
including: GTL diesel, GTL naphtha, liquefied petroleum gas, paraffin, GTL base oils and medium hard
waxes. Estimated cost of the facility is $11 to $14 billion. Pending final investment decision,
construction would begin in 2016, with beneficial operations commencing in 2019. The project is the
largest single manufacturing investment in the history of Louisiana and one of the largest foreign direct
investment manufacturing projects in the history of the United States.
The project will be designed with proven, modern pollution control equipment and waste minimization
process. The project will also have processes in place that recycle wastewater to minimize
environmental impact and conserve water resources.
4.0 SITE LAYOUT
The existing Sasol Lake Charles Chemical Complex is located west of Westlake, Louisiana and is bound by
Houston River Road to the north and Old Spanish Trail to the South. The proposed site expansion will
occur to the west of the existing Sasol facility.
A general plot plan showing the boundaries of the existing operations, LCCP, GTL, shared facilities, and
construction support can be seen in Figure 1.
LCCP and GTL Projects
Largest single manufacturing investment
in the history of Louisiana.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
7 | P a g e
Figure 1: Project Plot Plan
Similar to Sasol’s existing facility, the LCCP and GTL projects will predominantly be buffered through the
use of berms, natural vegetation, and facility buildings. Sasol plans to minimize the visual impact of the
LCCP and GTL projects. A driver on Houston River Road would see something similar to what is shown
in Figures 2, 3, and 4. Figure 2 represents the visual along Houston River Road looking towards the GTL
facility. Similarly, Figure 3 and Figure 4 represent the views of the LCCP from Houston River Road. As
you can see, from both angles, the majority of the facilities will be obstructed by a berm which will be
manicured with trees and shrubbery. Along Old Spanish Trail, a driver would see tanks and pipe racks in
the foreground (Figure 5). The general location of the renderings in relation to the facility plot plan can
be seen in Figure 6.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
8 | P a g e
Figure 2: View #1 – Conceptual Rendering of the GTL facility from Houston River Road looking Southwest
Figure 3: View #2 – Conceptual Rendering of the LCCP facility from Houston River Road looking Southwest
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
9 | P a g e
Figure 4: View #3 – Conceptual Rendering of the LCCP facility from Houston River Road looking Southwest
Figure 5: View #4 – Conceptual Rendering of the LCCP facility from Old Spanish Trail looking Northwest
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
10 | P a g e
Figure 6: General location of the renderings views
5.0 ZONING REQUEST
Sasol is requesting that Calcasieu Parish:
1. REZONE SASOL OWNED PROPERTY: Rezone 1,470 acres of Sasol‐owned property from
agricultural, single family residential, mixed residential, manufactured home park, general
commercial, and light industrial to I‐2 Heavy Industrial (Figure 7).
2. COMPLETE A FEASIBILITY STUDY FOR REZONING NON‐SASOL OWNED PROPERTY: Complete a
feasibility study to rezone approximately 177 acres of non‐Sasol owned properties within the
overall boundary to I‐2 Heavy Industrial. Figure 8 shows both the areas that Sasol is requesting
to be rezoned (purple color), as well as the areas they are requesting a feasibility study be
completed (green color). If granted, this would result in a uniform I‐2 Heavy Industrial zone in
this area. A map showing the final proposed zoning can be found in Figure 9 (I‐2 Heavy
Industrial is shown in purple). Detailed maps and legal descriptions of the proposed rezoning
are included as part of the developer’s agreement that is part of this rezoning application.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
11 | P a g e
3. REVOKEMENT AND REDEDICATION OF PUBLIC ROADS: Revoke the following public roads as
currently located in their entirety, except for the portions of such roads that may be needed to
allow owners to access their properties: 1st Avenue, 2nd Avenue, 3rd Avenue, 4th Avenue, 5th
Avenue, 6th Avenue, 7th Avenue, 8th Avenue, Bolsius Road, Center Street, Cynthia Street, Electric
Drive (existing location and originally platted location), Evergreen Road, Goldrich Drive,
Independence Road, Laurel Avenue, Lincoln Avenue, Madison Street, Merlin Street, Michigan
Avenue, Orphanage Road, Powell lane, Rigmaiden Avenue, Trousdale Road, Verret Road, and
WB Noris Subdivision Road. In addition revoke all roads within the Sasol property boundary that
were previously dedicated or recorded but were not constructed. It is being requested that the
45 acres of revoked roads also be rezoned as I‐2 Heavy Industrial. A map showing the requested
roads to be revoked can be found in Figure 10.
4. COMPLETE A STUDY FOR THE INCLUSION OF REZONED PROPERTY INTO LOCKPORT INDUSTRIAL
DISTRICT: Complete a study to include the 1,692 acres of rezoned I‐2 Heavy Industrial property
into the existing Lockport Industrial District. A map showing the existing and proposed limits of
the Lockport Industrial District can be seen in Figure 11.
See the EXHIBITS section of this report for larger (11”x17”) maps of Figure 1 to Figure 11.
Figure 7: Existing Zoning Map
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
12 | P a g e
Figure 8: Proposed Zoning Map
Figure 9: Final Zoning Map
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
13 | P a g e
Figure 10: Proposal for Streets to be Remain, Rededicate, and Revoke
Figure 11: Proposed Lockport Industrial District Expansion
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
14 | P a g e
6.0 ECONOMIC IMPACT ASSESSMENT On behalf of Sasol, NERA Economic Consulting performed the economic impact assessments for
establishment of the two proposed stand alone industrial facilities. With cooperation from Sasol, NERA
used detailed facility information and customized a state‐of‐the‐art economic model developed by
Regional Economic Models, Inc. (REMI) to study the potential economic impacts of the two proposed
projects for both the state of Louisiana and the United States. Based on the model results and NERA’s
calculations, the LCCP construction is expected to account for 20‐40% of total private investment in the
state of Louisiana while the GTL Project will account for as much as
44%.
The NERA team also identified expected trends concerning gains
within the Louisiana and United States economies. On the front end,
project construction expenditures will result in direct economic
growth through the employment of construction crews in Louisiana
and procurement of construction materials from the United States.
Indirect gains can result from the projects’ various needs for goods
and services. Income from both direct and indirect sources will induce further gains within the state and
national economies. For example, higher employment rates and wages will result in increased spending
on other goods and services. Therefore, the construction of the projects presents a multiplier effect.
The proposed projects will directly employee more than 5,000 construction workers during peak
construction in 2016, increasing overall employment in Louisiana by 30,000 during 2016 due to
multiplier effects. Although Sasol plans to hire locally as much as possible, the influx of construction
workers will increase the housing demand in Calcasieu Parish. These projects will have a large impact
housing availability, rentals, hotels, campgrounds and RV parks, furthering the multiplier effect. When
operational the facilities will employee approximately 1,200 workers at an estimated median salary of
$89,000 a year, compared with the Calcasieu Parish median salary of
$35,772.
Additionally, economists have determined that the construction of
such sophisticated operating facilities as those proposed by Sasol
would create an agglomeration effect. This essentially means small
communities or towns will be generated by the additional businesses,
restaurants, and housing that will develop near the proposed project
sites to accommodate its workers. Once construction is complete and
the facilities are operational, local, state and national economies will
continue to experience direct gains through the employment of facility workers. Indirect gains will come
from the consumption of domestic goods and services, ranging from local purchases to using natural gas
from the United States. Increased spending from direct and indirect gains will continue to promote
economic growth on the local, state and national level. In addition, the agglomeration effect will persist
throughout the facilities’ operations to accommodate the facility workers.
The LCCP construction is
expected to account for 20-40% of the
total private investment in the
state of Louisiana.
Calcasieu Parish median salary
$35,772
Sasol Production Employee
median salary $89,000
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
15 | P a g e
The sophistication of these projects brings a need for higher education. SOWELA Technical Community
College will provide training for these and similar projects. As a result, the College has received $20
million in state funding to begin construction of new facilities
and training programs. Construction on the new facilities will
begin in 2014, furthering the multiplier effect.
NERA used the REMI model along with detailed expenditure and
operational information from Sasol, to estimate gains in the
Louisiana economy throughout the two proposed projects’
construction and operations. The table below identifies the
average annual economic gains for the LCCP and GTL projects.
Gains from the LCCP are calculated over the period of 2013‐2041, and the GTL Project gains are
predicted for the period of 2013‐2044.
Category LCCPIncrease/year
GTLProjectIncrease/year
LouisianaGrossStateProduct(GSP) $900million $3.3billionLouisianaPersonalIncome $300million $1.7billionLouisianaEmployment 3,900jobs 21,000jobsLouisianaGovernmentRevenue $50million $235million
According to the economic models, Sasol will pay an average of $150 million in property taxes to
Calcasieu Parish in “year 11” between the two facilities. Beyond the local and state level, income
generated by the two projects will contribute to the national economy through the purchase of
domestic goods and services by Sasol, its employees, and the members of the agglomeration. NERA
used the REMI model to also estimate monetary gains for the United States economy from the
construction and operations of the two proposed projects. The table below identifies average annual
gains estimated for both projects. As with Louisiana’s economic forecast, gains for the LCCP are
averaged over the period of 2013‐2041, and the GTL Project gains are averaged for the period of 2013‐
2044. Economic growth for the United States economy includes the predicted values shown above in
Louisiana’s gains.
Category LCCPIncrease/year
GTLProjectIncrease/year
USGrossDomesticProduct(GDP) $5.1billion $7.8billionUSPersonalIncome $2.1billion $3billionUSEmployment 38,000jobs 55,000jobsUSGovernmentRevenue $260million $439millionUSNetExports ‐‐ $1.7billion
Overall, the NERA study results indicate that substantial growth is expected within Calcasieu Parish, the
state of Louisiana, and U.S. economies as a result of the proposed construction and operations of Sasol’s
two projects.
SOWELA Technical Community College
received $20 million in funds from State of
Louisiana specifically for training programs as a result of these projects.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
16 | P a g e
7.0 SAFETY, HEALTH, AND ENVIRONMENTAL Sasol is committed, at the highest level, to safe and
reliable operations. Sasol’s Safety, Health, & Environment
(SHE) policies articulate their corporate commitment to
safety and reliability.
Resource Report 11, which is part of the Environmental
Assessment completed by URS Corporation on behalf of
Sasol, describes the design, construction, operation, and
maintenance measures to maximize the projects’ reliability
and to minimize potential hazards to the public from
potential failure of project components and/or chemical
releases as a result of accidents or natural catastrophes.
Sasol follows a wide range of state and federal regulations
and guidance documents that apply to the design and
operations of new facilities. Some of these include:
Process Safety Management (29 CFR 1910.119)
Risk Management Program (40 CFR Part 68)
The National Oil and Hazardous Substances
Pollution Contingency Plan and the Area
Contingency Plans for the local Area
US Coast Guard Marine (USCG) Safety Manual
Occupational Safety and Health Administration
(OSHA) requirements for worker health and safety
(29 CFR 1910.120)
USCG National Preparedness for Response
Exercise Program
OSHA Employee Emergency Plans and Fire
Prevention
Spill Prevention and Control
Startup, Shutdown, and Malfunction Plans (40 CFR
Part 63)
Department of Homeland Security CFATS Program
Louisiana Department of Natural Resources
Pipeline Safety Program
SASOL’S COMMITMENT TO SAFETY, HEALTH, AND THE
ENVIRONMENT (SHE)
We, the people of Sasol, striving
for excellence in all we do,
recognize the impact that our
activities can have on people
and the environment. Safety,
health and protection of the
environment will form an
integral part of our planning and
decision making. We will
manage our company, wherever
we do business, in an ethical
way that strikes an appropriate
and well‐reasoned balance
between economic, social and
environmental needs. We expect
our employees and service
providers globally, to take
personal responsibility to
embrace this ambition in all of
our day‐to‐day activities.
Our goal is to eliminate
incidents, minimize risk,
responsibly manage
environmental impacts and
enable excellence in operations
and business performance while
providing a workplace that
takes into account the safety
and wellbeing of our people and
service providers.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
17 | P a g e
Sasol is a member of the
Lake Area Industry
Alliance and the Southwest
Louisiana Mutual Aid
Sasol has planned the design, construction, and operation of its proposed LCCP and GTL projects to
avoid potential and real adverse environmental effects as much as possible. Strategized planning, well
designed engineering technologies, and best operating practices will be used to avoid both potential and
real adverse environmental effects.
The likelihood for potential hazards will be reduced during the design phase by using buffer strips or
other methods of physical separation around the project sites and siting and safety design to prevent
failures due to natural risks. Other engineered designs, when applicable will use the International Code
Council for further protection of human life and environment. The proposed projects would be built to
meet or exceed the most stringent national and international safety standards, which include full
containment storage tanks, multiple gas detectors, infrared fire detectors, closed‐circuit cameras,
stringent security measures and advanced safety training. Equipment‐design specifications are
rigorously reviewed to protect operational integrity.
All construction will be conducted pursuant to guidelines of a quality assurance program as
implemented by the project management team. The operation will benefit from intensive personnel
selection and training, strict procedures, knowledgeable supervision, and diligent overview by
management.
Sasol is a proud and active member of the Lake Area Industry Alliance (LAIA),
which is comprised of 23 local industries. Sasol’s participation in the LAIA
enhances the safety of its facility in several ways. It enables Sasol to learn best
practices from other industries, it provides incentive for Sasol to achieve high
levels of safety as these safety records will be communicated by LAIA
throughout the area, and it enables Sasol to develop communications with
community officials that are beneficial in the event of an emergency.
Incident Investigation and Reporting Personal Protective Equipment LCCC Railroad Car Derailment Respiratory Protection Procedure Hazardous Waste Operations And Emergency
Response Hurricane Preparedness Fire Protection LCCC Emergency Notification/Call-Out
Procedure LCCC Security Procedure
LCCC Emergency Response Team Procedure
LCCC Community Awareness andEmergency Response (CAER) Procedure
LCCC Southwest Louisiana Mutual Aid Procedure
LCCC Emergency Head Count Procedure Incident Command System Emergency Telephone Numbers Site Topography
Sasol has many Sasol-Specific operation standards that will govern the design and operations of the new facilities with rules, regulations and guidelines for:
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
18 | P a g e
SASOL’S SAFETY, HEALTH, AND THE ENVIRONMENT PRINCIPLES
Conducting their business with respect and care for people and the environment Responsible utilization of natural resources Implementing responsible care for all Sasol’s chemical and associated
businesses. Non-chemical business will implement appropriate, recognized codes of practice.
Continually improving our safety, health and environmental performance. Complying, as a minimum, with all applicable legal and other agreed
requirements. Promoting dialogue with stakeholders about safety, health, and environmental
performance.
SASOL ACHIEVES THESE BY:
Implementing internationally recognized safety, health, environmental and quality management systems.
Developing and implementing inherently safer and cleaner technologies. A ‘cradle to grave’ approach to the products we develop, manufacture, use,
distribute, and sell. Informing and appropriately training all employees and contractors on safety,
health, and environmental matters. Responding effectively to safety, health, and environmental emergencies
involving our operations and products. Engaging with relevant authorities and institutions on the formulation of
legislation, standards, and the implementation thereof. Benchmarking internationally on best safety, health, and environmental practices. Sharing safety, health, and environmental reduction best practices throughout
Sasol. Providing appropriate resources required to implement the above.
In addition Sasol is a long‐standing member of the Southwest Louisiana Mutual Aid (SLMA). The
objective of this organization is the joining together of fire‐fighting, law enforcement, rescue, and first
aid manpower and facilities among Southwest Louisiana industries and municipalities for mutual
assistance in case of emergency situations ‐ either natural or man‐made.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
19 | P a g e
8.0 ENVIRONMENTAL PERMITTING Sasol’s goal is to responsibly manage potential environmental impacts while promoting operational
excellence and business performance. Sasol is committed to complying with all environmental
regulations, specifically to implement the necessary mitigation measures in cooperation with all
regulatory agencies. Sasol is seeking various permits from state and federal agencies to allow the new
construction of the LCCP and GTL projects. Some of these permits include various air quality permits,
wastewater permits, pre‐construction and post‐construction stormwater permits, and US Army Corps of
Engineers (USACE) wetland permits. A complete list including the agency and status are listed within
this report.
LCCP and GTL Permits Agency Status
Clean Air Act (CAA) Prevention of Significant Deterioration (PSD) Permit
Louisiana Department of Environmental Quality (LDEQ)
Permit application submitted to LDEQ: April 30, 2013 Public hearing: March 25, 2014 Anticipated authorization date: May 2014
CAA Title V Permits LDEQ Permit applications submitted to LDEQ: April 30, 2013 Public hearing: March 25, 2014 Anticipated authorization date: May 2014
Clean Water Act (CWA) Section 404 and Rivers and Harbors Act (RHA) Section 10 Permit
U.S. Army Corps of Engineers (USACE)
LCCP/GTL Application submitted: July 24, 2013 Anticipated authorization date: June 2014
Construction Dock Application submitted: May 20, 2013 Anticipated authorization date: June 2014
CWA Section 401 Water Quality Certification
LDEQ Application Submitted: July 24, 2013 Anticipated Authorization date: June 2014
CWA Louisiana Pollutant Discharge Elimination System (LPDES) Permit (Industrial Wastewater Discharge Permit)
LDEQ Permit renewal and modification application submitted to LDEQ: April 30, 2013 Anticipated authorization date: May 2014
LPDES Storm Water General Permit for Construction Activities ‐ Five Acres or More (LAR100000)
LDEQ Notice of Intent submitted: January 7, 2014 Permits received: January 22, 2014
Louisiana Multi‐Sector General Permit (MSGP, LAR05M448) for Storm Water
LDEQ Obtained: the existing facilities holds a Multi‐Sector General Permit that will need to be modified at the appropriate time to cover the LCCP and GTL projects
Louisiana General Permit for Hydrotest Water (LAG679012)
LDEQ Obtained: the existing facilities hold a Hydrotest permit and can be utilized by the LCCP and GTL projects
Solid Waste Permit LDEQ Obtained: the existing facility has a solid waste generator ID and no new solid waste permitted units are anticipated for the LCCP and GTL Projects.
Hazardous Waste Permit/RCRA Compliance
LDEQ
GTL ‐ Application submitted: February 10, 2014. GTL ‐ Anticipated authorization data: January 2015
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
20 | P a g e
ENVIRONMENTAL PERMITS FOR THE LAKE CHARLES CHEMICAL COMPLEX EXISTING FACILITIES
Existing LCCC Permits Agency Description and Status
Clean Air Act Prevention of Significant Deterioration Permit
LDEQ Alumina Unit No. PSD‐LA‐644 (approval of modification to LCCC Alumina Unit, in effect from 9/19/00 to 3/19/02)
LAB Unit No. PSD‐LA‐291 (M‐3) (approval of modification to LCCC Linear Alkyl Benzene Unit on 11/29/10)
Clean Air Act Title V Permits LDEQ Alumina Unit Title V No. 2565‐V6 (approval of operating permit renewal and modification for the LCCC Alumina Unit, in effect from 10/8/12 until 10/8/17)
Ethylene‐Activated Sludge‐Steam Unit Title V No. 2743‐V5 (approval of permit modification for the LCCC Ethylene/Activated Sludge /Steam Unit, in effect from 7/12/12 until 8/8/13)
LAB Unit Title V No. 2894‐V4 (approval of permit modification for the LCCC Linear Alkyl Benzene Unit, in effect from 7/13/12 until 11/29/15)
NPU Unit Title V No. 2896‐V5
Alcohol Unit Title V No. 2865‐V4 (approval of permit modification for the LCCC Alcohol Unit, in effect from 9/27/11 until 6/14/16)
ETO Unit Title V No. 2325‐V4 (approval of permit modification for the LCCC Ethoxylation Unit, in effect from 11/1/12 until 12/9/13)
CoMonomer Unit Title V No. 3088‐V1 (approval of permit modification for the LCCC CoMonomer‐1 Unit, in effect from 2/22/13 until 4/25/16)
CWA Section 404 and Rivers and Harbors Act Section 10 Permit
USACE
MVN‐2011‐02625‐WNN (for work related to construction of the Comonomer 1 unit (a/k/a Tetramerization unit including parking lot, warehouse, receiving area, construction access and haul roads, material storage area)
MVN‐2012‐1425‐WB (for construction of a railcar storage facility off of E. Burton St.)
MVN‐2004‐294‐WKK (for construction of a locker room for alcohol unit and a first aid bldg.)
MVN‐2001‐1302‐WJJ (to install box culverts)
CWA Louisiana Pollutant Discharge Elimination System (LPDES) Permit (Industrial Wastewater Discharge Permit)
LDEQ LPDES Permit No. LA0003336 in effect from 12/1/09 until 11/30/14; renewal application was filed on 4/30/13)
Louisiana LPDES Storm Water Multi‐Sector General Permit (MSGP, LAR05M448)
LDEQ LPDES Storm Water Multi‐Sector General Permit No. LAR05M448 (reissuance notice on 5/27/11 for LPDES storm water general permit for the LCCC)
Active Construction Storm Water Permit LAR10H509 (for discharges to Bayou Verdine resulting from construction activities associated with construction of the Comonomer 1 unit – construction nearly complete at this time)
CWA Section 401 Water Quality Certification
LDEQ WQC 120613‐01 issued 8/8/12 for Corps Permit MVN‐2012‐1425‐WB to clear land and place fill material for the construction of a railcar storage facility
WQC 111208 issued 1/6/12 for Corps Permit MVN‐2011‐02625‐WNN to clear land and place fill material for industrial facility expansion
WQC 110602‐02 issued 6/21/11 for Corps Permit MVN‐2001‐1302‐WJJ to install box culverts for industrial facility expansion
WQC 090625‐02 issued 7/21/09 for Corps Permit MVN‐2004‐2924‐WKK to clear land and place fill material for construction of an alcohol locker room and first aid office building
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
21 | P a g e
Existing LCCC Permits Agency Description and Status
LPDES General Permit for Discharges of Hydrostatic Test and Vessel Testing Wastewater
LDEQ Reissuance of LPDES General Permit (LAG670000) for Sasol North America, Inc. on February 1, 2013 under Permit No. LAG679012, covering discharge of hydrostatic test and vessel testing wastewater by Sasol North America, Inc. for statewide pipeline operations located in multiple parishes in Louisiana.
Solid Waste Permit LDEQ Standard Type I Permit No. P‐0251R1 (covers Sand Filter Settling Basins (North and South); Holding Pond; and Stormwater Diversion Ponds (North and South)), in effect 1/23/10 until 6/23/20.
Hazardous Waste Permit/RCRA Compliance
LDEQ Hazardous and Solid Waste Amendment (HSWA) Post‐Closure Permit, Part B, LAR000041087‐PC‐RN‐1. Pursuant to this permit, Sasol North America will perform post‐closure care of the Closed Activated Sludge Unit and the required corrective actions. Permit is in effect from 8/15/12 to 8/14/22.
Radioactive Material License
LDEQ License No. LA‐4902‐L01 (Amendment No. 24) was issued following renewal on July 1, 2013 and expires on July 31, 2018
9.0 TRAFFIC IMPACT ANALYSIS A development the size of Sasol’s LCCP and GTL facilities will inevitably impact traffic within the Parish. Sasol contracted Alliance Transportation Group to complete a Traffic Impact Analysis (TIA) to evaluate the traffic impacts of the site on the adjacent roadway network and to determine the road traffic improvements necessary to mitigate these impacts. Analysis was performed under the following scenarios:
Existing Conditions (2013)
Construction Ramp‐Up Phase 1 (January 2015)
Construction Ramp‐Up Phase 2 (May 2015)
Peak Construction Phase (February 2016)
Plant Operations and Maintenance Phase (2020) The study was completed using a timeline of worker activity which anticipates that the project site will generate approximately:
1,700 worker trips during construction Ramp‐up Phase 1
3,400 worker trips during construction Ramp‐up Phase 2
5,100 worker trips during Peak Construction Phase
1,700 worker trips post construction during the Plant Operations and Maintenance Phase The Traffic Impact Analysis (TIA) evaluated the impact of the traffic associated with the project on the surrounding roadway network. A total of 26 intersection operations were evaluated: 15 within the immediate study area and 11 related to off‐site parking facilities. To mitigate the effect of site generated traffic in the immediate proximity of the construction site, Sasol
has proposed to implement three off‐site parking facilities and shuttle service for its employees. The off‐
site parking locations analyzed include:
Sasol has completed a Traffic Impact Analysis (TIA) to evaluate the traffic impacts of the
LCCP and GTL projects on the local traffic and to determine the road traffic improvements necessary to mitigate
these impacts.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
22 | P a g e
Cities Service Highway (LA 108) and Napoleon Street (US 900
Beglis Parkway (LA 27) and Louis Alleman Parkway
Beglis Parkway (LA 27) and Mosswood Road.
Additionally, Sasol identified that there will be multiple shifts during construction to minimize
disruptions to the surrounding roadway network. There will be two day shifts; one beginning at 6:00 AM
and one beginning at 6:30 AM. Approximately 45 percent of the workforce will be assigned to each of
these shifts. The remaining 10 percent of the workforce will be assigned to the night shift, which is
proposed to begin at 6:00 PM. The intersection improvement locations and corresponding phase for all
mitigation measures are illustrated in Figure 12.
Figure 12: Improvement Locations by Construction Phase
At the time of this application Sasol has received comments from CPPJ and LA DOTD on the TIA. Sasol
will address these, as well as any additional comments. Sasol also agrees it will continue to work with
both the Parish and LA DOTD to mitigate traffic impacts. At a minimum the road traffic improvements
included in this report will be completed upon completion of the financial investment decision to move
forward with the projects. Some of these intersections will be analyzed for potential roundabout
locations, based on comments from CPPJ and LA DOTD.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
23 | P a g e
Ramp‐Up Phase 1 (January 2015)
During the Ramp‐up Phase 1, all
construction employee traffic will
be on‐site with access to the site
from Evergreen Road, west of the
KCS rail line. It is expected that
1,700 workers will be on site for this
phase of construction. After analysis
of the existing infrastructure in the
area surrounding the project site,
construction of the following
roadway improvements prior to the beginning of Ramp‐up Phase 1 include:
I‐10 Service Road and I‐10 Eastbound Westlake Ramps: Modify signal timing
Sampson Street (LA 378) at Sulphur Avenue (LA 379): Modify signal timing
Sampson Street (LA 378) at John Stine Road: Modify signal timing
Old Spanish Trail at Trousdale Road: Construct eastbound right‐turn lane
Old Spanish Trail at Prater Road: Install traffic signal; Construct westbound left‐turn bay and
eastbound right‐turn bay
Old Spanish Trail at Evergreen Road: Install traffic signal; Construct eastbound left‐turn bay;
Construct channelized westbound right‐turn bay with additional northbound acceleration lane on
Evergreen Road exiting the intersection; Construct southbound right‐turn bay
Houston River Road (LA 379) at Beglis Parkway (LA 27): Modify signal timing
Preliminary construction cost estimates for the improvements associated with this construction phase
total $1,288,000.
Ramp‐Up Phase 2 (May 2015)
In Ramp‐up Phase 2, some laborer parking will be on‐site with additional parking provided at two off‐
site locations. The off‐site parking will be implemented near the intersections of Napoleon Road (US 90)
at Coach Williams Drive (LA 108) and Beglis Parkway (LA 27) at Louis Alleman Parkway. On‐site parking
will continue to access the site from Evergreen Road, west of the KCS rail line. It is expected that 3,400
workers will be on site for this phase of construction.
The following intersection improvements and traffic control modifications will be implemented to
accommodate all the site generated traffic.
Beglis Parkway (LA 27) at Louis Alleman Parkway: Install traffic signal; Construct westbound lane to
be shared by through and right turning vehicles
Beglis Parkway (LA 27) at Burton Street: Construct westbound right‐turn bay
Sasol Mitigation Strategies:
Off-site Parking Facilities and Shuttle Service for Employees
Multiple Employee Shifts Installation of Traffic Signals Modification of Signal Timing Parameters Construction of Turn Lanes Roadway Widening
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
24 | P a g e
Napoleon Street (US 90) at Coach Williams Drive (LA 108): Modify signal timing to allow for
permissive/protected eastbound left turn
Coach Williams Drive (LA 108) at Maplewood Drive: Modify signal timing
Preliminary construction cost estimates for the improvements associated with this construction phase
total $427,000.
Peak Construction Phase (February 2016)
During the Peak Construction Phase, parking will be the same
as Ramp‐up Phase 2 with an additional off‐site parking facility
located near the intersection of Mosswood Road and Beglis
Parkway (LA 27). On‐site parking will continue to be accessed
via Evergreen Road. It is expected that 5,100 workers will be
on site for peak construction.
In order to accommodate the site generated traffic from the
Peak Construction Phase, the construction of the following
roadway improvements prior to the beginning of this phase
include:
Napoleon Street (US 90) at Prater Road: Modify signal
timing
Napoleon Street (US 90) at Trousdale Road: Modify signal
timing
Beglis Parkway (LA 27) at Houston River Road (LA 379):
Construct eastbound right‐turn bay and northbound
right‐turn bay
Beglis Parkway (LA 27) at Louis Alleman Parkway: Modify
striping on the westbound approach to allow for a dual
left‐turn during the PM peak hour
Beglis Parkway (LA 27) at I‐10 WB Ramps: Install traffic
signal; Modify pavement markings to create a westbound
right‐turn bay
Arizona Street (LA 27) at Patton Street: Construct westbound right‐turn bay
Arizona Street (LA 27) from south of Patton Street to Mosswood Road: Widen roadway to four lanes
(two in each direction)
Preliminary construction cost estimates for the improvements associated with this construction phase
total $3,298,000.
Road Traffic Improvements Cost
Ramp-Up Phase 1 January 2015 $1.3 Million
Ramp-Up Phase 2
May 2015 $0.4 Million
Peak Construction Phase
February 2016 $3.3 Million
Plant Operations and Maintenance Phase
2020 $0.2 Million
TOTAL
$5.2 Million
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
25 | P a g e
Plant Operations & Maintenance Phase (2020)
During the Operations and Maintenance Phase, all traffic will be located on‐site with access primarily from Evergreen Road, west of the KCS rail line. It is expected that 1,700 workers will be on site for the post construction phase of normal plant operations and maintenance. In order to accommodate for all construction employee trips being directed to on‐site parking, the
analysis determined the following mitigation measure:
Sampson Street (LA 378) at John Stine Road: Construct eastbound and westbound left‐turn bays
and modify signal phasing for protected/permissive left turns
Preliminary construction cost estimates for the improvements associated with this phase total $228,000.
Total construction cost estimates for the improvements associated with all phases of construction total
$5,241,000.
10.0 DRAINAGE IMPACT ANALYSIS As part of the local permitting process with Calcasieu Parish, Sasol submitted a Drainage Impact Analysis
(DIA) to CPPJ per the requirements of Parish Ordinance 5429. The main goal of the DIA was to
demonstrate that the LCCP and GTL projects were designed to have no adverse impact on surrounding
drainage.
No adverse impact means that total flood risk, contamination, erosion, and peak runoff rates will not
increase on surrounding areas as a result of the project. The report demonstrated that the interim
phases of construction and final site will be built in a manner to ensure no adverse impact on
surrounding property. Sasol’s DIA (signed and dated January 20th, 2014) was prepared by URS
Corporation and provides an in‐depth evaluation of the future effects of the LCCP and GTL projects on
surrounding drainage. This DIA was approved by the CPPJ on February 20, 2014.
A potential impact during the development of Greenfield property is an increase in stormwater runoff.
The DIA established baseline land use drainage conditions and runoff characteristics and compared
them to the proposed runoff conditions from the development. The DIA proposes methods to mitigate
these impacts. Detention ponds are a standard practice to reduce runoff and flood potential from new
developments.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
26 | P a g e
Bayou Verdine and Contamination Control
Bayou Verdine is the controlling variable in the drainage on this site and design measures were taken to
ensure that the project would not increase the flood levels on this system. Offsite areas to the north
flow through the site via Bayou Verdine and these areas were
included in the DIA. The Bayou Verdine system eventually flows
into the Calcasieu River. The design basis for this project was
the 100‐year and 10‐year return period rainfall events.
Drainage areas for the proposed site include only those areas
that will contribute to the pond/Bayou Verdine system. Areas
that contain potentially contaminated runoff will be collected
internally and will not contribute to the stormwater system.
These areas were not included in the drainage areas.
Rainfall Runoff Determination
The Soil Conservation Service Curve (SCS) Number Method was used to calculate the existing and post‐
development runoff potential from the site. This method assigns a number to a parcel of land based on
the type of soil, conditions of the soil, and land cover. A higher curve number (e.g., paved surface)
produces more stormwater runoff per acre.
The SCS Unit Hydrograph method was used to transform runoff potential into actual flow rates passing
for the site and surrounding areas. The main variable in the SCS method is time of concentration. Time
of concentration measures how fast water accumulates from a given area. Sloped areas (e.g. rooftops
and parking lots) and hardened surfaces speed up the water and shorten the time of concentration
compared to grassed or forested areas. Detailed calculations were performed to establish the SCS
variables for each sub‐basin within the project and surrounding
study area. Sasol proposes nine (9) detention ponds as part of
the construction to mitigate the increased runoff volume from
the development.
The DIA used FEMA‐approved numerical models to calculate
current conditions and to evaluate the effectiveness of the
proposed mitigation measures. HEC‐HMS calculates the peak
runoff values and HEC‐RAS computes the flood risk (flood
depths) on surrounding property. Taken together the models
have the capability of accurately evaluating the entire drainage system and are the most frequently used
design combination for pre‐post drainage analysis.
Sasol proposes 9
detention ponds as part of the construction to mitigate the increased runoff volume from the
development.
Areas that contain
potentially contaminated runoff will be collected internally and will not
contribute to the stormwater system.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
27 | P a g e
Flood Risk Determination
The hydraulic (HEC‐RAS) model of the site analyzed the existing flood depths of the onsite channel
network and was used to ensure the post‐development conditions would not adversely impact the
floodplain. A geometric model of the channel network stream centerlines and channel cross‐sections
was created using LiDAR data for the area and site‐specific topographic survey data. Components of the
hydraulic model are channel slope, vegetation density and bank conditions, and bridge and culvert
crossings. These were investigated closely and are crucial in the models water surface elevation results.
A major component of the proposed development is re‐routing of Bayou Verdine which currently flows
through the proposed development area. The rerouted channel will be lined with concrete through the
bends and bridge crossings to minimize scour potential in these vulnerable sections. Figure 13 shows a
comparison of the existing Bayou Verdine alignment with the proposed channel alignment.
Figure 13: Existing versus Proposed Channel Alignment of Bayou Verdine
Mitigation Measures and FEMA Flood Zone Implications
The results suggest that the re‐routed channel coupled with a 9 pond detention system will provide
adequate mitigation to ensure no adverse impact on surrounding flood levels. The channel re‐route will
keep the 100‐year floodplain within its banks and will not increase the limits of the flood zone on
surrounding property. Bayou Verdine
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
28 | P a g e
Note that the current effective FEMA Flood Insurance Study for this area was completed in 1988 – long
before the creation of LiDAR products and expansion of surrounding industrial areas. Any future
revisions to the FEMA flood insurance maps on Bayou Verdine (if any) will be the result of external
factors not attributable to the LCCP and GTL facilities. Such external factors typically include improved
modeling technology, use of high‐resolution LiDAR and topographic survey data, changes in survey
methods, and increased development of surrounding industrial areas. It was not the purpose or scope
of this local study to revise the regional FEMA flood insurance maps for Bayou Verdine.
However, for the channel re‐route a Conditional Letter of Map Revision (CLOMR) permit request will be
prepared and submitted to FEMA as part of the permit process. This is required by FEMA when
proposed projects could alter the hydrologic or hydraulic
characteristics of a flooding source and result in modifications
to the floodway, Base Flood Elevations (BFE), or Special Flood
Hazard Area (SFHA). Once construction is complete, a Letter of
Map Revision (LOMR) study will be performed to verify that
the development took place as proposed. Once the LOMR is
approved by FEMA, the effective Flood Insurance Rate Map
(FIRM) is updated on location to reflect the completed project.
The DIA shows that the proposed development will cause no
adverse impacts to the local floodplain and flooding depths.
A phasing analysis was conducted as part of the DIA to ensure that during construction no adverse
floodplain impacts would occur. This is due to the possibility that the GTL Project may not be
constructed coincident with the LCCP. The DIA proves that construction phasing of the development
will not cause adverse impacts to surrounding areas.
11.0 CONCLUSION This report details Sasol’s commitment to the Parish, through the completion of its economic, drainage,
and traffic impact analysis. Sasol will continue to work to ensure that all safety, environmental, and
health aspects are met throughout the planning, construction, and implementation of the projects
described herein.
This rezoning application details Sasol’s request that Calcasieu Parish rezone 1,470.85 acres of Sasol
owned property to I‐2 Heavy Industrial. In addition Sasol is requesting that the Calcasieu Parish –
Division of Planning and Development complete a feasibility study to rezone approximately 176.52 acres
of isolated properties within the overall boundary to I‐2 Heavy Industrial. Sasol is also requesting that
the Parish complete a study to incorporate the newly rezoned, I‐2 Heavy Industrial properties into the
existing Lockport Industrial District.
The accompanying Developer’s Agreement, maps, and legal descriptions also detail Sasol’s further
commitment to the entities within the area.
The Drainage Impact Analysis (DIA) shows that the proposed LCCP and
GTL facilities will have no adverse impacts to the
local drainage, floodplain and flooding
depths.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
29 | P a g e
REFERENCES
Alliance Transportation Group. Sasol Lake Charles Ethane Cracker/Gas‐to‐Liquids Project (LCCP/GTL) –
Traffic Impact Analysis. January 2014.
NERA Economic Consulting. Economic Impact Assessment of the Sasol Gas‐to‐Liquids (GTL) Facility on
the Louisiana and US Economies. November 12, 2013
NERA Economic Consulting. Economic Impact Assessment of the Sasol Chemical Facility on the Louisiana
and US Economies. November 12, 2013.
URS Corporation. Revised Drainage Impact Analysis – Sasol North America, Inc. Westlake Sasol GTL and
Lake Charles Cracker Westlake, Calcasieu Parish Louisiana. January 2014.
Lake Charles Cracker Project & Gas‐to‐Liquids Project Rezoning Application
30 | P a g e
EXHIBITS
EXHIBIT 1: Project Plot Plan
EXHIBIT 2: View #1 – Conceptual Rendering of the GTL facility from Houston River Road looking
Southwest
EXHIBIT 3: View #2 – Conceptual Rendering of the LCCP facility from Houston River Road looking
Southwest
EXHIBIT 4: View #3 – Conceptual Rendering of the LCCP facility from Houston River Road looking
Southwest
EXHIBIT 5: View #4 – Conceptual Rendering of the LCCP facility from Old Spanish Trail looking
Northwest
EXHIBIT 6: General location of the renderings views
EXHIBIT 7: Existing Zoning Map
EXHIBIT 8: Proposed Zoning Map
EXHIBIT 9: Final Zoning Map
EXHIBIT 10: Proposal for Streets to Remain, Rededicate, and Revoke
EXHIBIT 11: Proposed Lockport Industrial District Expansion
HoustonRiver Rd
Old Spanish Tr
Eve
rgre
en
Rd
Project Plot Plan
LEGEND
LCCP
Construction Support
LCCP-GTL
GTL
Existing Operations
E BurtonSt
Ev
erg
reen
Rd
VC
MP
lan
tR
d
E Burfton St
Ben
jam
inS
t
Old Spanish Tr
Bo
lsiu
sR
dB
ols
ius
Rd
Ly
on
sA
v
Ben
jam
inS
t
E Burton St
3rd Av
Church St
Ele
ctri
cD
r
E Burton St
E Burton St
Ben
jamin
St
7th Av
Mar
yS
t
Pe
rkin
sA
v
Ma d
iso
nS
t
Mar
yS
t
4th Av
VC
MP
lan
tR
d
Jack
M
oss Rd
Fisher St
Houston
River R
d
3rd Av
Ben
jam
inS
t
Co
ach
Wil
liam
sD
r.
Old Spanish Tr
Bra
xton
LnM
ary
St
VC
MP
lan
tR
d
Old Spanish Tr
Houston River Rd
Old Spanish Tr
Wat
ert
ow
erR
d
Charles Av
Harvey Miller Rd
Ed
wa
rds
St
Fe
rnd
al e
Dr
Murrell Rd
Bel
Air
St
E Burton St
Park St
5th Av
Harvey Miller Rd
Rig
maid
enA
v
Or a
St
Ed
na
Har
dy
Ln
Old Spanish Tr
E Burton St
VC
MP
lan
tR
d
Merlin St
4th Av
Perkins Av
Mitc
hell S
t
Old Spanish Tr
E Burton St
Moss Av
7th Av
Lyons Av
6th Av
Reeves Av
Ind
epen
de
nc
eR
d
5th Av
Pry
or
St
3rd Av
2nd Av
1st St1st St
Center St
2nd Av
Old Spanish Tr
Ced
arS
t
Reeves Av
6th Av
Perkins Av
Moss Av
E Burton St
Houston River Rd
Venable Dr
E Burton St
Pra
ter
Rd
4th Av
Rig
ma
iden
Av
Lin
coln
Av
Pa
ttie
Mo
ssR
d
Ind
epen
de
nc
eR
d
Bre
ntw
oo
dD
r
Ind
epen
de
nc
eR
d
E Burton St
Pra
ter
Rd
5th Av
Smith Rd
JC
lop
hu
sR
dJ
Clo
ph
us
Rd
Goldrich Dr
Orphanage Rd
E Burton St
5th Av
Har
de
yR
d
Tro
us
da
le R
d
Wallace Rd
Goldrich Dr
Old Spanish Tr
Ev
erg
ree n
Rd
John Stine Rd
Verret Rd
HoustonRiver Rd
Old Spanish Tr
Junius Rd
Powell Ln
HoustonRiver Rd
Old Spanish Tr
Evergreen Rd
Evergreen Rd
Evergreen Rd
Houston River Rd
Eve
rgreen Rd
20-2
6-A
20-2
5-B
28-509
20-7
4-B
20-56
28-4
69
20-1
29-1
4
19-2
3
29-1
9
19-22
30-12
29-220
-15
7
19-15
29-2
5
29-4
0
29-4
28-4
35
29-3
28-493
20-1
55
29-7
21-93
29-4
1
19-6
28-4
34
21-3
7
19-1
9
21-4
7-C
29-3
1
28-494
19-2
5
19-2
0
19-16
19-1
8
19-8
30-11
19-2
7
28-512
21-95
30-10
21-44
29-53
19-14
30-13
29-5
21-9
7
19-2
4
29-3
0
19-7
20-150
21-49
29-11
29-29
28-4
31
21-41
19-2
1
29-1
6
29-1
21-42
29-63
19-1
7
28-49729
-56
29-1
8
28-6
89
29-57
29-13
29-42
29-39
29-62
29-1
7
28-687
21-94
29-1
0
29-6
21-39
29-64
19-2
8
20-138
19-5
19-26
21-30
20-28
20-111
21-29
20-1
2
20-24
20-3
1
20-149
20-30
20-147
28-9
5
20-172
20-61
28-1
88
20-35
28-3
22
28-3
89
28-6
32
28-2
87
20-1
56
28-4
30
28-1
10
28-551
28-5
22
28-5
9
28-3
62
28-4
12
28-1
24
28-3
23
28-1
36
21-2
28-2
3
28-3
39
20-1
01
28-6
73
28-1
97
20-17
28-6
96
28-435-A
28-6
31
20-2
21-6
3
28-3
0
29-34
28-1
38
28-3
59
28-456
28-7
11
28-5
67
28-549
28-7
10
28-1
95
28-3
94
28-432-A
28-6
30
28-6
97
21-3
2A
20-127
28-6
66
28-2
65
21-92
28-8
2
28-1
8
21-1
4
21-1
1
28-6
53
28-3
98
28-3
72
28-3
92
20-9
8
28-5
58
29-23
28-6
06
28-1
45
28-7
3
28-2
34
28-4
90
21-54
28-33
21-8
5
28-5
40
28-6
92
17-6
9
28-4
10
21-90
28-2
78
21-46
28-2
9
28-253
20-6
28-3
7
20-85
20-9
28-4
21-26
28-5
028
-60
20-129
16-1
20-9
2
28-6
07
28-6
69
28-1
93
20-160
28-2
64
28-2
80
28-5
31
21-3
5
28-4
99
20-2
9
28-2
31
28-5
68
28-458
28-4
33
28-1
67
28-2
94
28-6
29
28-3
37
20-27
28-1
47
28-298
29-9
28-446
28-6
03
28-3
17
28-492
20-7
28-1
64
28-3
32
28-501
28-76
28-2
95
28-1
99
28-3
9
28-8
4
21-5
28-3
19
28-6
70
28-6
33
28-3
6
21-4
5
28-3
95
28-1
62
28-1
82
28-6
11
28-3
31
20-9
7
28-4
17
20-7
6
28-5
-C
28-143
28-1
7
20-153
28-443
20-134
28-59928-451
21-8
0
29-61
21-7
5
28-5
29
20-87
28-3
14
20-180
28-6
56
28-9
28-5
86
28-3
78
28-4
89
28-3
86
28-2
37
28-5
91
28-3
15
28-5
81
20-90
28-2
30
28-5
64
28-6
42
28-442
28-8
7-B
28-5
05
28-7
03
28-1
31
28-6
6
20-148
21-8
1
20-1
3
28-1
28
28-2
41
21-13
20-5
8
29-44
28-1
44
28-211
28-1
18
28-3
38
28-251
28-3
65
28-3
11
28-545
21-25
28-5
-A
20-1
4
28-1
94
28-449
28-8
9
28-301
28-207
20-86
28-3
46
28-8
1
20-118
28-355
21-18
16-2
28-1
16
21-19
28-247
28-2
23
28-6
13
21-7
3
28-4
71
28-4
32
28-6
08
20-115
28-4
14
28-4
80
21-4
3
28-6
20
28-254
28-142
21-7
2
28-3
4
28-4
98
28-5
32
28-601
20-8
2
28-4
82
28-2
84
28-7
12
20-133
28-225
28-2
2
20-63
21-20
28-1
92
21-8
3
28-6
37
28-6
74
28-7
16
28-6
7
28-1
01
21-6
5
20-1
65
29-2
8
28-2
56
28-5
90
21-6
8
20-77
28-5
63
28-6
75
28-2
00
28-4
5
28-5
53
28-9
3
28-4
21
20-9
6
28-1
11
21-1
5
28-1
32
28-252
28-1
68
28-5
92
28-6
41
29-33
28-3
27
28-452
20-122
20-8
3
28-3
88
29-49
28-6
98
28-1
55
2 8-1
23
20-1
54
28-6
76
29-45
20-169
20-64
28-3
96
28-2
71
21-8
28-5
72
28-6
48
28-3
21
28-2
42
28-5
73
28-4
0
28-6
78
28-5
75
28-6
28
28-5
76
28-7
00
28-3
09
28-598
28-4
72
28-1
48
28-9
6
28-5
89
21-12
28-5
33
20-78
28-5
78
28-4
27
20-1
73
28-6
79
28-444
20-88
28-3
18
29-3
5
28-7
06
28-1
56
28-2
24
28-4
81
28-548
28-5
83
28-3
16
28-352
28-1
84
28-4
38
28-3
69
21-51
28-5
62
28-688
28-487
28-6
09
28-2
90
28-1
02
21-6
6
28-6
93
21-3
8
28-6
12
28-4
18
28-6
55
28-4
39
28-1
00
20-175
28-5
41
28-6
22
28-5
66
28-2
67
21-1
29-37
28-3
5
28-1
13
28-5
60
20-1
0
29-36
28-6
59
20-113
28-6
50
28-2
86
21-21
28-9
9
28-3
58
29-6
7
28-3
71
28-6
54
28-3
08
28-6
72
28-544
28-3
30
28-6
14
20-22
28-1
96
29-26
28-1
74
28-3
06
20-80
28-6
35
20-4
6
21-61
20-4
7-A
20-1
05-
B28-461
20-59
20-112
28-9
2
28-297
28-2
77
28-2
91
28-3
44
20-5
5
28-1
08
21-64
20-106
28-8
0
28-2
75
21-52
28-1
4
28-485
21-6
7
28-2
03
21-7
4
28-5
6
28-3
74
20-1
44
21-78
21-7
6
20-6
9
28-2
5
21-57
29-58
28-300
20-48-B
20-1
41
20-60
28-2
59
20-104
20-49
28-407
28-453
28-455
21-23
28-3
40
20-7
0
20-125
20-75
28-3
66
28-1
51
28-3
60
28-7
07
28-6
65
20-109
28-1
53
29-12
28-5
8
21-8
7
20-1
42
28-351
28-6
64
28-3
33
20-9
3
28-8
7-A
20-102
28-6
68
28-476
28-1
17
29-50
28-1
29
21-96
28-6
44
28-4
20
28-2
60
28-5
00
28-478
28-5
4
28-3
73
28-1
06
20-42
28-1
49
28-433-A
28-594
28-7
15
28-208
28-3
24
28-488
28-450
29-60
28-213
28-209
20-171
28-2
8
28-6
17
28-2
55
28-7
9
28-3
93
28-2
70
20-5
28-1
05
21-8
8
28-2
04
28-1
5
28-4
15
28-2
69
28-6
38
28-2
72
28-3
75
28-475
28-2
46
28-6
86
29-22
28-2
43
28-4
25
28-6
9
28-1
81
28-5
23
28-6
4
28-248
28-1
70
28-5
52
29-15
28-6
67
28-6
34
28-5
37
28-6
05
28-2
74
28-1
66
20-1
30
28-299
28-2
02
28-5
61
28-6
49
28-431-A
28-1
21
20-126
20-163
28-1
20
28-404
20-7
1
28-3
63
28-3
8
28-350
28-2
4
28-6
45
28-3
35
28-6
80
28-7
1
29-8
29-52
28-400
28-2
40
28-6
83
28-486
20-1
31
29-27
21-9
28-4
3
28-6
10
28-8
5
28-6
52
28-5
87
28-484
28-3
12
28-8
3
28-1
09
28-5
2
20-117
28-77
28-4
36
28-3
68
28-5
70
20-19
28-6
91
20-124
28-600
28-459
28-4
26
28-503
28-4
7
28-303
21-31
28-4
16
28-1
46
28-5
93
28-3
80
28-1
26
29-59
28-3
90
28-2
0
21-3
3
20-4
4
28-496
28-2
57
28-2
36
28-1
98
28-6
27
20-119
28-6
62
21-7
20-8
28-3
47
28-1
85
20-89
20-152
28-596
21-16
28-4
64
28-5
65
28-3
29
28-1
0
28-1
65
28-1
77
20-182
28-2
58
28-2
66
20-53
28-3
26
28-3
36
28-3
87
28-5
79
28-2
88
28-3
07
28-2
61
28-2
1
29-4
3
28-5
3
29-51
28-447
20-1
40
28-2
79
28-401
28-5
04
28-228
28-6
8
28-2
21
20-164
20-38
28-1
83
28-2
39
28-1
6
28-448
28-6
16
28-3
2
21-24
28-7
09
20-146
29-32
28-4
91
20-120
28-2
35
28-3
61
28-5
28
21-8
2
21-4
0
28-3
42
21-50
28-4
8
20-91
28-7
4
28-3
99
20-1
66
28-7
14
28-6
25
28-5
38
28-547
28-2
28-353
28-7
28-6
04
21-59
28-302
28-4
09
28-6
84
20-23
28-3
43
28-1
57
28-5
59
20-159
28-7
02
28-1
2
28-6
61
20-1
5
28-210
21-4
28-4
68
28-5
36
28-3
20
28-6
51
28-1
71
28-2
45
28-141
28-8
22-9
28-6
21-58
20-151
28-5
30
28-6
18
28-4
29
28-445
28-6
5
29-5
4
28-1
1
28-3
13
20-6
8
28-1
72
28-5
80
28-3
83
29-47
28-3
25
28-402
28-5
34
28-3
97
20-1
28
28-5
39
28-3
34
28-2
68
28-3
82
28-2
7
20-1
00
28-1
80
28-1
73
28-7
08
28-2
63
28-6
82
28-2
44
20-176
28-6
81
20-4
20-39
28-5
69
28-4
37
28-595
29-24
28-1
78
21-5
3
28-406
28-460
20-81
20-1
70
28-4
2
28-5
25
28-4
9
28-348
28-1
87
21-8
6
28-7
13
28-6
39
28-6
99-
A
28-6
1
28-2
73
28-1
50
28-3
91
21-77
28-5
88
28-7
17
20-4
5
28-249
28-1
75
28-1
22
28-1
19
20-3
4
28-3
79
28-7
01
21-3
6
28-7
04
28-2
33
20-1
39
21-8
4
21-1
0
28-436-A
28-5
1
28-3
81
28-6
19
28-3
57
20-1
79
28-6
47
28-2
93
28-1
03
28-6
85
20-40
28-502
28-2
83
21-17
28-1
61
28-349
28-1
59
28-5
24
28-483
28-5
56
28-5
27
28-8
6
28-1
3
28-2
32
28-4
11
28-5
85
28-507
28-546
28-3
41
21-6
2
28-3
56
21-6
28-2
29
21-47
28-1
58
28-1
27
28-4
6
28-405
20-137
28-5
28-477
28-2
89
28-4
62
29-20
28-440
28-5
5
28-2
22
20-50
28-5
43
28-2
01
28-5
-B
28-4
19
28-474
20-116
28-78
29-38
28-5
57
28-1
60
28-1
25
20-103
28-597
20-108
28-1
79
28-7
2
28-4
4
20-7
2
21-7
1
20-1
81
28-354
28-3
1
28-1
35
28-441
28-1
12
20-9
4
28-1
39
28-1
04
28-1
14
28-3
67
21-6
9
20-1
45-
B
28-4
63
28-6
58
28-1
34
28-140
21-7
9
28-6
60
28-1
15
28-1
89
28-6
24
20-6
7
28-1
76
20-2
1
28-1
54
20-178
20-9
5
20-3
3
28-6
2
28-5
26
28-3
28
20-168
21-89
28-206
20-62
28-434-A
29-6
8
21-4
A
20-1
36
20-66
28-3
05
20-1
61
28-5
-D
21-28
20-65
21-48
28-511
20-9
9
20-177
28-6
63
29-65
28-4
67
28-6
15
28-1
33
20-37
28-2
6
28-1
52
28-403
28-1
9
28-6
21
20-43
28-5
74
28-2
85
28-212
29-21
29-6
6
20-114
28-1
90
28-304
28-6
77
28-2
92
20-84
21-56
28-6
23
28-3
21-70
28-7
0
20-36
28-250
28-5
55
20-7
3
28-3
85
28-2
81
28-1
69
28-454
20-123
20-121
28-1
-A
28-3
64
28-6
3
28-4
1
28-6
71
20-52
28-1
37
28-6
26
28-6
95
20-54
28-6
02
20-1
1
20-5
7
28-457
21-3
20-162
28-5
35
28-227
28-6
46
28-1
30
28-1
91
20-41
28-506
28-3
84
28-2
38
28-1
07
28-2
62
28-4
22
28-5
42
28-479
20-20
20-174
20-1
6
28-4
08
21-4
7-B
-1
28-226
28-6
90
20-132
28-9
4
28-5
84
28-1
86
20-110
28-2
82
28-2
05
28-4
66
28-6
57
28-470
28-5
71
21-32
28-5
7
28-3
70
20-1
58
28-4
24
20-3
-B
28-2
20
20-107
28-2
76
28-2
96
28-3
10
28-3
45
20-3
2
28-6
43
28-5
77
28-4
13
28-8
8
28-9
0
28-5
82
28-7
05
28-4
23
28-9
1
28-6
36
28-6
40
28-9
8
20-1
43
20-7
9
28-550
21-91
21-27
20-51
21-60
29-48
28-9
728
-16
3
21-55
28-5
54
28-4
65
28-6
94
28-75
28-4
73
29-55
20-18
20-167
20-135
21-4
7-B
21-22
20-4
7
20-4
6-A
20-7
4-A
20-1
05-
A
21-47-B
21-4
7- C
20-2
6-B
20-2
5-A
28-4
69-
A
20-3
-A
20-48-A
28-1
28-6
99-
B
21-4
7-A
19-1
7
20-145-A
20-145-C
21-34
This map shows existing Calcasieu Parish zoning
CURRENT AS OF FEBRUARY 10, 2014
Legend
Overall Rezoning Boundary
Parcel Lines
(a1) Agricultural
(c1) Light Commercial
(c2) General Commercial
(c3) Central Business Commercial
(city) Zoned by Local Municipality
(i1) Light Industrial
(i2) Heavy Industrial
(i2r) Heavy Industrial Restricted
(r1) Single Family Residential
(r2) Mixed Residential
(rm) Multi-Family Residential
(rmhp) Manufactured Home ParkExisting Zoning
Old Spanish Tr
Ben
jam
inS
t
VC
MP
l an
tR
d
Merlin St
Bo
lsiu
sR
d
Ly on
sA
v
Ma
di s
on
St
3rd Av
Church St
Rig
ma
ide
nA
v
Ele
ctr
icD
r
7th Av
Ma
ryS
t
4th Av
Fisher St
HoustonRiver Rd
Fe
rnd
al e
Dr
Bra
xton
Ln
Charles Av
Wat
ert
ow
erR
d
Harvey Miller Rd
Murrell Rd
Be
lAir
St
E Burton St
5th Av
Ora
St
Moss Av
6th AvIn
dep
en
de
nc
eR
d
Pry
or
St
2nd Av
1st St
Center St
Venable Dr
Pra
ter
Rd
Bre
ntw
oo
dD
r
Lin
col n
Av
Sm
ith
Rd
Goldrich Dr
Pa
ttie
Mo
ssR
d
Har
de
yR
d
Ver
ret
Rd
John Stine Rd
Ev
erg
reen
Rd
Perkins Av
Jack MossR
d
Ed
wa
rds
St
Ed
na
Ha
rdy
Ln
Mit
ch
ellS
tCed
ar S
t
Co
ach
Will
iam
sD
r.J
Clo
ph
us
Rd
Orp
han
age
Rd
Tro
us
da
leR
d
Ju
niusRd
Powell Ln
Park St
Reeves Av
Wallace Rd
21-34
20-2
6-A
20-2
5-B
28-509
20-7
4-B
20-56
28-4
69
20-1
29-1
4
19-2
3
29-1
9
19-22
30-12
29-2
20-1
57
19-15
29-2
5
29-4
0
29-4
28-4
35
29-3
28-493
20-1
55
29-7
21-93
29-4
1
19-6
28-4
34
21-3
7
19-1
9
21-4
7-C
29-3
1
28-494
19-2
5
19-2
0
19-16
19-1
8
19-8
30-11
19-2
7
28-512
21-95
30-10
21-44
29-53
19-14
30-1
3
29-5
21-9
7
19-2
4
29-3
0
19-7
20-150
21-49
29-11
29-29
28-4
31
21-41
19-2
1
29-1
629-1
21-42
29-63
19-1
7
28-497
29-5
6
29-1
8
28-6
89
29-57
29-13
29-42
29-39
29-62
29-1
7
28-687
21-94
29-1
0
29-6
21-39
29-64
19-2
8
20-138
19-5
19-26
21-30
20-28
20-111
21-29
20-1
2
20-24
20-3
1
20-149
20-30
20-147
28-9
5
20-172
20-61
28-1
88
20-35
28-3
22
28-3
89
28-6
32
28-2
87
20-1
56
28-4
30
28-1
10
28-551
28-5
22
28-5
9
28-3
62
28-4
12
28-1
24
28-3
23
28-1
36
21-2
28-2
3
28-3
39
20-1
01
28-6
73
28-1
97
20-17
28-6
96
28-435-A
28-6
31
20-2
21-6
3
28-3
0
29-34
28-1
38
28-3
59
28-456
28-7
11
28-5
67
28-549
28-7
10
28-1
95
28-3
94
28-432-A
28-6
30
28-6
97
21-3
2A
20-127
28-6
66
28-2
65
21-92
28-8
2
28-1
8
21-1
4
21-1
1
28-6
53
28-3
98
28-3
72
28-3
92
20-9
8
28-5
58
29-23
28-6
06
28- 1
45
28-7
3
28-2
34
28-4
90
21-54
28-33
21-8
5
28-5
40
28-6
92
17-6
9
28-4
10
21-90
28-2
78
21-46
28-2
9
28-253
20-6
28-3
7
20-85
20-9
28-4
21-26
28-5
028
-60
20-129
16-1
20-9
2
28-6
07
28-6
69
28-1
93
20-160
28-2
64
28-2
80
28-5
31
21-3
5
28-4
99
20-2
9
28-2
31
28-5
68
28-458
28-4
33
28-1
67
28-2
94
28-6
29
28-3
37
20-27
28-1
47
28-298
29-9
28-446
28-6
03
28-3
17
28-492
20-7
28-1
64
28-3
32
28-501
28-76
28-2
95
28-1
99
28-3
9
28-8
4
21-5
28-3
19
28-6
70
28-6
33
28-3
6
21-4
5
28-3
95
28-1
62
28-1
82
28-6
11
28-3
31
20-9
7
28-4
17
20-7
6
28-5
-C
28-143
28-1
7
20-153
28-443
20-134
28-59928-451
21-8
0
29-61
21-7
5
2 8-5
29
20-87
28-3
14
20-180
28-6
56
28-9
28-5
86
28-3
78
28-4
89
28-3
86
28-2
37
28-5
91
28-3
15
28-5
81
20-90
28-2
30
28-5
64
28-6
42
28-442
28-8
7-B
28-5
05
28-7
03
28-1
31
28-6
6
20-148
21-8
1
20-1
3
28-1
28
28-2
41
21-13
20-5
8
29-44
28-1
44
28-211
28-1
18
28-3
38
28-251
28-3
65
28-3
11
28-545
21-25
28-5
-A
20-1
4
28-1
94
28-449
28-8
9
28-301
28-207
20-86
28-3
46
28-8
1
20-118
28-355
21-18
16-2
28-1
16
21-19
28-247
28-2
23
28-6
13
21-7
3
28-4
71
28-4
32
28-6
08
20-115
28-4
14
28-4
80
21-4
3
28-6
20
28-254
28-142
21-7
2
28-3
4
28-4
98
28-5
32
28-601
20-8
2
28-4
82
28-2
84
28-7
12
20-133
28-225
28-2
2
20-63
21-20
28-1
92
21-8
3
28-6
37
28-6
74
28-7
16
28-6
7
28-1
01
21-6
5
20-1
65
29-2
8
28-2
56
2 8-5
90
21-6
8
20-77
28-5
63
28-6
75
28-2
00
28-4
5
28-5
53
28-9
3
28-4
21
20-9
6
28-1
11
21-1
5
28-1
32
28-252
28-1
68
28-5
92
28-6
41
29-33
28-3
27
28-452
20-122
20-8
3
28-3
88
29-49
28-6
98
28-1
55
28-1
23
20-1
54
2 8-6
76
29-45
20-169
20-64
28-3
96
28-2
71
21-8
28-5
72
28-6
48
28-3
21
28-2
42
28-5
73
28-4
0
28-6
78
28-5
75
28-6
28
2 8-5
76
28-7
00
28-3
09
28-598
28-4
72
28-1
48
28-9
6
28-5
89
21-12
28-5
33
20-78
28-5
78
28-4
27
20-1
73
28-6
79
28-444
20-88
28-3
18
29-3
5
28-7
06
2 8-1
56
28-2
24
28-4
81
28-548
28-5
83
28-3
16
28-352
28-1
84
28-4
38
28-3
69
21-51
28-5
62
28-688
28-487
28-6
09
28-2
90
28-1
02
21-6
6
28-6
93
21-3
8
28-6
12
28-4
18
28-6
55
28-4
39
28-1
00
20-175
28-5
41
28-6
22
28-5
66
28-2
67
21-1
29-37
28-3
5
28-1
13
28-5
60
20-1
0
29-36
28-6
59
20-113
28-6
50
2 8-2
86
21-21
28-9
9
28-3
58
29-6
7
28-3
71
28-6
54
28-3
08
28-6
72
28-544
28-3
30
28-6
14
20-22
28-1
96
29-26
28-1
74
28-3
06
20-80
28-6
35
20-4
6
21-61
20-4
7-A
20-1
05
-B
28-461
20-59
20-112
28-9
2
28-297
28-2
77
28-2
91
28-3
44
20-5
5
28-1
08
21-64
20-106
28-8
0
28-2
75
21-52
28-1
4
28-485
21-6
7
28-2
03
21-7
4
28-5
6
28-3
74
20-1
44
21-78
21-7
6
20-6
9
28-2
5
21-57
29-58
28-300
20-48-B
20-1
41
20-60
28-2
59
20-104
20-49
28-407
28-453
28-455
21-23
28-3
40
20-7
0
20-125
20-75
28-3
66
28-1
51
28-3
60
28-7
07
28-6
65
20-109
28-1
53
29-12
28-5
8
21-8
7
20-1
42
28-351
28-6
64
28-3
33
20-9
3
28-8
7-A
20-102
28-6
68
28-476
28-1
17
29-50
28-1
29
21-96
28-6
44
28-4
20
28-2
60
28-5
00
28-478
28-5
4
28-3
73
28-1
06
20-42
28-1
49
28-433-A
28-594
28-7
15
28-208
28-3
24
28-488
28-450
29-60
28-213
28-209
20-171
28-2
8
28-6
17
28-2
55
28-7
9
28-3
93
28-2
70
20-5
28-1
05
21-8
8
28-2
04
28-1
5
28-4
15
28-2
69
28-6
38
28-2
72
28-3
75
28-475
28-2
46
28-6
86
29-22
28-2
43
28-4
25
28-6
9
28-1
81
28-5
23
28-6
4
28-248
28-1
70
28-5
52
29-15
28-6
67
28-6
34
28-5
37
28-6
05
28-2
74
28-1
66
20-1
30
28-299
28-2
02
28-5
61
28-6
49
28-431-A
28-1
21
20-126
20-163
28-1
20
28-404
20-7
1
28-3
63
28-3
8
28-350
28-2
4
28-6
45
28-3
35
28-6
80
28-7
1
29-8
29-52
28-400
28-2
40
28-6
83
28-486
20-1
31
29-27
21-9
28-4
3
28-6
10
28-8
5
28-6
52
28-5
87
28-484
28-3
12
28-8
3
28-1
09
28-5
2
20-117
28-77
28-4
36
28-3
68
28-5
70
20-19
28-6
91
20-124
28-600
28-459
28-4
26
28-503
28-4
7
28-303
21-31
28-4
16
28-1
46
28-5
93
28-3
80
28-1
26
29-59
28-3
90
28-2
0
21-3
3
20-4
4
28-496
28-2
57
28-2
36
28-1
98
28-6
27
20-119
28-6
62
21-7
20-8
28-3
47
28-1
85
20-89
20-152
28-596
21-16
28-4
64
28-5
65
28-3
29
28-1
0
2 8-1
65
28-1
77
20-182
28-2
58
28-2
66
20-53
28-3
26
28-3
36
28-3
87
28-5
79
28-2
88
28-3
07
28-2
61
28-2
1
29-4
3
28-5
3
29-51
28-447
20-1
40
28-2
79
28-401
28-5
04
28-228
28-6
8
28-2
21
20-164
20-38
28-1
83
2 8-2
39
28-1
6
28-448
28-6
16
28-3
2
21-24
28-7
09
20-146
29-32
28-4
91
20-120
28-2
35
28-3
61
28-5
28
21-8
2
21-4
0
28-3
42
21-50
28-4
8
20-91
28-7
4
28-3
99
20-1
66
28-7
14
28-6
25
2 8-5
38
28-547
28-2
28-353
28-7
28-6
04
21-59
28-302
28-4
09
28-6
84
20-23
28-3
43
28-1
57
28-5
59
20-159
28-7
02
28-1
2
28-6
61
20-1
5
28-210
21-4
28-4
68
28-5
36
28-3
20
28-6
51
28-1
71
28-2
45
28-141
28-8
22-9
28-6
21-58
20-151
28-5
30
28-6
18
28-4
29
28-445
28-6
5
29-5
4
28-1
1
28-3
13
20-6
8
28-1
72
2 8-5
80
28-3
83
29-4
7
28-3
25
28-402
28-5
34
28-3
97
20-1
28
28-5
39
28-3
34
28-2
68
28-3
82
28-2
7
20-1
00
28-1
80
28-1
73
28-7
08
28-2
63
28-6
82
28-2
44
20-176
28-6
81
20-4
20-39
28-5
69
28-4
37
28-595
29-24
28-1
78
21-5
3
28-406
28-460
20-81
20-1
70
28-4
2
28-5
25
28-4
9
28-348
28-1
87
21-8
6
28-7
13
28-6
39
28-6
99
-A
28-6
1
28-2
73
28-1
50
28-3
91
21-77
28-5
88
28-7
17
20-4
5
28-249
28-1
75
28-1
22
28-1
19
20-3
4
28-3
79
28-7
01
21-3
6
28-7
04
28-2
33
20-1
39
21-8
4
21-1
0
28-436-A
28-5
1
28-3
81
28-6
19
28-3
57
20-1
79
28-6
47
28-2
93
28-1
03
28-6
85
20-40
28-502
28-2
83
21-17
28-1
61
28-349
28-1
59
28-5
24
28-483
28-5
56
28-5
27
28-8
6
28-1
3
28-2
32
28-4
11
28-5
85
28-507
28-546
28-3
41
21-6
2
28-3
56
21-6
28-2
29
21-47
28-1
58
28-1
27
28-4
6
28-405
20-137
28-5
28-477
28-2
89
28-4
62
29-20
28-440
28-5
5
28-2
22
20-50
28-5
43
28-2
01
28-5
-B
28-4
19
28-474
20-116
28-78
29-38
28-5
57
28-1
60
28-1
25
20-103
28-597
20-108
28-1
79
28-7
2
28-4
4
20-7
2
21-7
1
20-1
81
28-354
28-3
1
28-1
35
28-441
28-1
12
20-9
4
28-1
39
28-1
04
28-1
14
28-3
67
21-6
9
20-1
45
-B
28-4
63
28-6
58
28-1
34
28-140
21-7
9
28-6
60
28-1
15
28-1
89
28-6
24
20-6
7
28-1
76
20-2
1
28-1
54
20-178
20-9
5
20-3
3
28-6
2
28-5
26
28-3
28
20-168
21-89
28-206
20-62
28-434-A
29-6
8
21-4
A
20-1
36
20-66
28-3
05
20-1
61
28-5
-D
21-28
20-65
21-48
28-511
20-9
9
20-177
28-6
63
29-65
28-4
67
28-6
15
28-1
33
20-37
28-2
6
28-1
52
28-403
28-1
9
28-6
21
20-43
28-5
74
28-2
85
28-212
29-21
29-6
6
20-114
28-1
90
28-304
28-6
77
28-2
92
20-84
21-56
28-6
23
28-3
21-70
28-7
0
20-36
28-250
28-5
55
20-7
3
28-3
85
28-2
81
28-1
69
28-454
20-123
20-121
28-1
-A
28-3
64
28-6
3
28-4
1
28-6
71
20-52
28-1
37
28-6
26
28-6
95
20-54
28-6
02
20-1
1
20-5
7
28-457
21-3
20-162
28-5
35
28-227
28-6
46
28-1
30
28-1
91
20-41
28-506
28-3
84
28-2
38
28-1
07
28-2
62
28-4
22
28-5
42
28-479
20-20
20-174
20-1
6
28-4
08
21-4
7-B
-1
28-226
28-6
90
20-132
28-9
4
28-5
84
28-1
86
20-110
28-2
82
28-2
05
28-4
66
28-6
57
28-470
28-5
71
21-32
28-5
7
28-3
70
20-1
58
28-4
24
20-3
-B
28-2
20
20-107
28-2
76
28-2
96
28-3
10
28-3
45
20-3
2
28-6
43
28-5
77
28-4
13
2 8-8
8
28-9
0
28-5
82
28-7
05
28-4
23
28-9
1
28-6
36
2 8-6
40
28-9
8
20-1
43
20-7
9
28-550
21-91
21-27
20-51
21-60
29-4
8
28-9
728
-16
3
21-55
28-5
54
28-4
65
28-6
94
28-75
28-4
73
29-55
20-18
20-167
20-135
21-4
7-B
21-22
20-4
7
20-4
6-A
20-7
4-A
20-1
05
-A
21-47-B
21-4
7-C
20-2
6-B
20-2
5-A
28-4
69
-A
20-3
-A
20-48-A
28-1
28-6
99
-B
21-4
7-A
19-1
7
20-145-A
20-145-C
Legend
Overall Rezoning Boundary
To Be Rezoned As Part Of This Application - (i2) Heavy Industrial
To Be Rezoned By Parish Through Feasibility Study - (i2) Heavy Industrial Proposed Zoning
This map shows proposed areas to be rezoned i2_Heavy Industrial
8thAv
E Burfton St
Bo
lsiu
sR
d
Church St
Mic
hig
an
Av
Ma
dis
on
St
Fe
rnd
ale
Dr
Fisher St
Be
nja
min
St B
rax
ton
LnM
ary
St
Wa
tert
ow
er
Rd
Charles Av
JackMoss Rd
Ed
wa
rds
St
Murrell Rd
Be
lAir
St
Park St
Harvey Miller Rd
Ora
St
Ed
na
Ha
rdy
Ln
VC
MP
lan
tR
d
Merlin St
Mitch
ell St
7th Av
Lyons Av
Pry
or
St
3rd Av
1st St
Center St
2nd Av
Ce
da
rS
t
Reeves Av
6th Av
Perkins Av
Co
ac
hW
illi
am
sD
r.
Moss Av
Venable Dr
Bre
ntw
oo
dD
r
4th Av
Rig
ma
ide
nA
v
Li n
co
lnA
v
Ind
ep
en
de
nc
eR
d
Smith Rd
Junius Rd
JC
lop
hu
sR
d
Orphanage Rd
Pa
ttie
Mo
ss
Rd
E Burton St
5th Av
Ha
rde
yR
d
Pra
ter
Rd
Wallace Rd
Goldrich Dr
Tro
us
da
leR
d
Verret Rd
Powell Ln
John Stine Rd
Old Spanish Tr
Houston River Rd
Eve
rgreen Rd
21-34
20-2
6-A
20-2
5-B
28-509
20-7
4-B
20-56
28-4
69
20-1
29-1
4
19-2
3
29-1
9
19-22
30-12
29-2
20-1
57
19-15
29-2
5
29-4
0
29-4
28-4
35
29-3
28-493
20-1
55
29-7
21-93
29-4
1
19-6
28-4
34
21-3
7
19-1
9
21-4
7-C
29-3
1
28-494
19-2
5
19-2
0
19-16
19-1
8
19-8
30-11
19-2
7
28-512
21-95
30-10
21-44
29-53
19-14
30-13
29-5
21-9
7
19-2
4
29-3
0
19-7
20-150
21-49
29-11
29-29
28-4
31
21-41
19-2
1
29-1
629-1
21-42
29-63
19-1
7
28-497
29-5
6
29-1
8
28-6
89
29-57
29-13
29-42
29-39
29-62
29-1
7
28-687
21-94
29-1
0
29-6
21-39
29-64
19-2
8
20-138
19-5
19-26
21-30
20-28
20-111
21-29
20-1
2
20-24
20-3
1
20-149
20-30
20-147
28-9
5
20-172
20-61
28-1
88
20-35
28-3
22
28-3
89
28-6
32
28-2
87
20-1
56
28-4
30
28-1
10
28-551
28-5
22
28-5
9
28-3
62
28-4
12
28-1
24
28-3
23
28-1
36
21-2
28-2
3
28-3
39
20-1
01
28-6
73
28-1
97
20-17
28-6
96
28-435-A
28-6
31
20-2
21-6
3
28-3
0
29-34
28-1
38
28-3
59
28-456
28-7
11
28-5
67
28-549
28-7
10
28-1
95
28-3
94
28-432-A
28-6
30
28-6
97
21-3
2A
20-127
28-6
66
28-2
65
21-92
28-8
2
28-1
8
21-1
4
21-1
1
28-6
53
28-3
98
28-3
72
28-3
92
20-9
8
28-5
58
29-23
28-6
06
28-1
45
28-7
3
28-2
34
28-4
90
21-54
28-33
21-8
5
28-5
40
28-6
92
17-6
9
28-4
10
21-90
28-2
78
21-46
28-2
9
28-253
20-6
28-3
7
20-85
20-9
28-4
21-26
28-5
028
-60
20-129
16-1
20-9
2
28-6
0728
-669
28-1
93
20-160
28-2
64
28-2
80
28-5
31
21-3
5
28-4
99
20-2
9
28-2
31
28-5
68
28-458
28-4
33
28-1
67
28-2
94
28-6
29
28-3
37
20-27
28-1
47
28-298
29-9
28-446
28-6
03
28-3
17
28-492
20-7
28-1
64
28-3
32
28-501
28-76
28-2
95
28-1
99
28-3
9
28-8
4
21-5
28-3
19
28-6
70
28-6
33
28-3
6
21-4
5
28-3
95
28-1
62
28-1
82
28-6
11
28-3
31
20-9
7
28-4
17
20-7
6
28-5
-C
28-143
28-1
7
20-153
28-443
20-134
28-59928-451
21-8
0
29-61
21-7
5
28-5
29
20-87
28-3
14
20-180
28-6
56
28-9
28-5
86
28-3
78
28-4
89
28-3
86
28-2
37
28-5
91
28-3
15
28-5
81
20-90
28-2
3028
-564
28-6
42
28-442
28-8
7-B
28-5
05
28-7
03
28-1
31
28-6
6
20-148
21-8
1
20-1
3
28-1
28
28-2
41
21-13
20-5
8
29-44
28-1
44
28-211
28-1
18
28-3
38
28-251
28-3
65
28-3
11
28-545
21-25
28-5
-A
20-1
4
28-1
94
28-449
28-8
9
28-301
28-207
20-86
28-3
46
28-8
1
20-118
28-355
21-18
16-2
28-1
16
21-19
28-247
28-2
23
28-6
13
21-7
3
28-4
71
28-4
32
28-6
08
20-115
28-4
14
28-4
80
21-4
3
28-6
20
28-254
28-142
21-7
2
28-3
4
28-4
98
28-5
32
28-601
20-8
2
28-4
82
28-2
84
28-7
12
20-133
28-225
28-2
2
20-63
21-20
28-1
92
21-8
3
28-6
3728
-674
28-7
16
28-6
7
28-1
01
21-6
5
20-1
65
29-2
8
28-2
56
28-5
90
21-6
8
20-77
28-5
63
28-6
75
28-2
00
28-4
5
28-5
53
28-9
3
28-4
21
20-9
6
28-1
11
21-1
5
28-1
32
28-252
28-1
68
28-5
92
28-6
41
29-33
28-3
27
28-452
20-122
20-8
3
28-3
88
29-49
28-6
98
28-1
55
28-1
23
20-1
54
28-6
76
29-45
20-169
20-64
28-3
96
28-2
71
21-8
28-5
72
28-6
48
28-3
21
28-2
42
28-5
73
28-4
0
28-6
78
28-5
75
28-6
28
28-5
76
28-7
00
28-3
09
28-598
28-4
72
28-1
48
28-9
6
28-5
89
21-12
28-5
33
20-78
28-5
78
28-4
27
20-1
73
28-6
79
28-444
20-88
28-3
18
29-3
5
28-7
06
28-1
56
28-2
24
28-4
81
28-548
28-5
83
28-3
16
28-352
28-1
84
28-4
38
28-3
69
21-51
28-5
62
28-688
28-487
28-6
09
28-2
90
28-1
02
21-6
6
28-6
93
21-3
8
28-6
12
28-4
1828
-655
28-4
39
28-1
00
20-175
28-5
41
28-6
22
28-5
66
28-2
67
21-1
29-37
28-3
5
28-1
13
28-5
60
20-1
0
29-36
28-6
59
20-113
28-6
50
28-2
86
21-21
28-9
9
28-3
58
29-6
7
28-3
71
28-6
54
28-3
08
28-6
72
28-544
28-3
30
28-6
14
20-22
28-1
96
29-26
28-1
74
28-3
06
20-80
28-6
35
20-4
6
21-61
20-4
7-A
20-1
05-B
28-461
20-59
20-112
28-9
2
28-297
28-2
77
28-2
91
28-3
44
20-5
5
28-1
08
21-64
20-106
28-8
0
28-2
75
21-52
28-1
4
28-485
21-6
7
28-2
03
21-7
4
28-5
6
28-3
74
20-1
44
21-78
21-7
6
20-6
9
28-2
5
21-57
29-58
28-300
20-48-B
20-1
41
20-60
28-2
59
20-104
20-49
28-407
28-453
28-455
21-23
28-3
40
20-7
0
20-125
20-75
28-3
66
28-1
51
28-3
60
28-7
07
28-6
65
20-109
28-1
53
29-12
28-5
8
21-8
7
20-1
42
28-351
28-6
64
28-3
33
20-9
3
28-8
7-A
20-102
28-6
68
28-476
28-1
17
29-50
28-1
29
21-96
28-6
44
28-4
20
28-2
60
28-5
00
28-478
28-5
4
28-3
73
28-1
06
20-42
28-1
49
28-433-A
28-594
28-7
15
28-208
28-3
24
28-488
28-450
29-60
28-213
28-209
20-171
28-2
8
28-6
17
28-2
55
28-7
9
28-3
93
28-2
70
20-5
28-1
05
21-8
8
28-2
0428
-15
28-4
15
28-2
69
28-6
38
28-2
7228
-375
28-475
28-2
4628
-686
29-22
28-2
43
28-4
25
28-6
9
28-1
81
28-5
23
28-6
4
28-248
28-1
70
28-5
52
29-15
28-6
67
28-6
34
28-5
37
28-6
05
28-2
74
28-1
66
20-1
30
28-299
28-2
02
28-5
61
28-6
49
28-431-A
28-1
21
20-126
20-163
28-1
20
28-404
20-7
1
28-3
63
28-3
8
28-350
28-2
4
28-6
4528
-335
28-6
80
28-7
1
29-8
29-52
28-400
28-2
4028
-683
28-486
20-1
3129-27
21-9
28-4
3
28-6
10
28-8
5
28-6
52
28-5
87
28-484
28-3
12
28-8
3
28-1
09
28-5
2
20-117
28-77
28-4
36
28-3
68
28-5
70
20-19
28-6
91
20-124
28-600
28-459
28-4
26
28-503
28-4
7
28-303
21-31
28-4
16
28-1
46
28-5
93
28-3
80
28-1
26
29-59
28-3
90
28-2
0
21-3
3
20-4
4
28-496
28-2
57
28-2
36
28-1
98
28-6
27
20-119
28-6
62
21-7
20-8
28-3
47
28-1
85
20-89
20-152
28-596
21-16
28-4
64
28-5
65
28-3
29
28-1
0
28-1
65
28-1
77
20-182
28-2
58
28-2
66
20-53
28-3
26
28-3
36
28-3
87
28-5
79
28-2
88
28-3
07
28-2
61
28-2
1
29-4
3
28-5
3
29-51
28-447
20-1
40
28-2
79
28-401
28-5
04
28-228
28-6
8
28-2
21
20-164
20-38
28-1
83
28-2
39
28-1
6
28-448
28-6
16
28-3
2
21-24
28-7
09
20-146
29-32
28-4
91
20-120
28-2
35
28-3
61
28-5
28
21-8
2
21-4
0
28-3
42
21-50
28-4
8
20-91
28-7
4
28-3
99
20-1
66
28-7
14
28-6
25
28-5
38
28-547
28-2
28-353
28-7
28-6
04
21-59
28-302
28-4
09
28-6
84
20-23
28-3
43
28-1
57
28-5
59
20-159
28-7
02
28-1
2
28-6
61
20-1
5
28-210
21-4
28-4
68
28-5
36
28-3
20
28-6
51
28-1
71
28-2
45
28-141
28-8
22-9
28-6
21-58
20-151
28-5
30
28-6
1828-4
29
28-445
28-6
5
29-5
4
28-1
1
28-3
13
20-6
8
28-1
72
28-5
80
28-3
83
29-4
7
28-3
25
28-402
28-5
34
28-3
97
20-1
28
28-5
39
28-3
34
28-2
68
28-3
82
28-2
7
20-1
00
28-1
80
28-1
73
28-7
08
28-2
63
28-6
8228
-244
20-176
28-6
81
20-4
20-39
28-5
69
28-4
37
28-595
29-24
28-1
78
21-5
3
28-406
28-460
20-81
20-1
70
28-4
2
28-5
25
28-4
9
28-348
28-1
87
21-8
6
28-7
13
28-6
39
28-6
99-A
28-6
1
28-2
73
28-1
50
28-3
91
21-77
28-5
88
28-7
17
20-4
5
28-249
28-1
75
28-1
22
28-1
19
20-3
4
28-3
79
28-7
01
21-3
6
28-7
04
28-2
33
20-1
39
21-8
4
21-1
0
28-436-A
28-5
1
28-3
81
28-6
19
28-3
57
20-1
79
28-6
47
28-2
93
28-1
03
28-6
85
20-40
28-502
28-2
83
21-17
28-1
61
28-349
28-1
59
28-5
24
28-483
28-5
56
28-5
27
28-8
6
28-1
3
28-2
32
28-4
11
28-5
85
28-507
28-546
28-3
41
21-6
2
28-3
56
21-6
28-2
29
21-47
28-1
58
28-1
27
28-4
6
28-405
20-137
28-5
28-477
28-2
89
28-4
62
29-20
28-440
28-5
5
28-2
22
20-50
28-5
43
28-2
01
28-5
-B
28-4
19
28-474
20-116
28-78
29-38
28-5
57
28-1
60
28-1
25
20-103
28-597
20-108
28-1
79
28-7
2
28-4
4
20-7
2
21-7
1
20-1
81
28-354
28-3
1
28-1
35
28-441
28-1
12
20-9
4
28-1
39
28-1
04
28-1
14
28-3
67
21-6
9
20-1
45-B
28-4
63
28-6
58
28-1
34
28-140
21-7
9
28-6
60
28-1
15
28-1
89
28-6
24
20-6
7
28-1
76
20-2
1
28-1
54
20-178
20-9
5
20-3
3
28-6
2
28-5
26
28-3
28
20-168
21-89
28-206
20-62
28-434-A
29-6
8
21-4
A
20-1
36
20-66
28-3
05
20-1
61
28-5
-D
21-28
20-65
21-48
28-511
20-9
9
20-177
28-6
63
29-65
28-4
67
28-6
15
28-1
33
20-37
28-2
6
28-1
52
28-403
28-1
9
28-6
21
20-43
28-5
74
28-2
85
28-212
29-21
29-6
6
20-114
28-1
90
28-304
28-6
77
28-2
92
20-84
21-56
28-6
23
28-3
21-70
28-7
0
20-36
28-250
28-5
55
20-7
3
28-3
85
28-2
81
28-1
69
28-454
20-123
20-121
28-1
-A
28-3
64
28-6
3
28-4
1
28-6
71
20-52
28-1
37
28-6
26
28-6
95
20-54
28-6
02
20-1
1
20-5
7
28-457
21-3
20-162
28-5
35
28-227
28-6
46
28-1
30
28-1
91
20-41
28-506
28-3
84
28-2
38
28-1
07
28-2
62
28-4
22
28-5
42
28-479
20-20
20-174
20-1
6
28-4
08
21-4
7-B
-1
28-226
28-6
90
20-132
28-9
4
28-5
84
28-1
86
20-110
28-2
82
28-2
05
28-4
66
28-6
57
28-470
28-5
71
21-32
28-5
7
28-3
70
20-1
58
28-4
24
20-3
-B
28-2
20
20-107
28-2
76
28-2
96
28-3
10
28-3
45
20-3
2
28-6
43
28-5
77
28-4
13
28-8
8
28-9
0
28-5
82
28-7
05
28-4
23
28-9
1
28-6
36
28-6
40
28-9
8
20-1
43
20-7
9
28-550
21-91
21-27
20-51
21-60
29-4
8
28-9
728
-163
21-55
28-5
54
28-4
65
28-6
94
28-75
28-4
73
29-55
20-18
20-167
20-135
21-4
7-B
21-22
20-4
7
20-4
6-A
20-7
4-A
20-1
05-A
21-47-B
21-4
7-C
20-2
6-B
20-2
5-A
28-4
69-A
20-3
-A
20-48-A
28-1
28-6
99-B
21-4
7-A
19-1
7
20-145-A
20-145-C
This map shows the area after it has been rezoned
Legend
Overall Rezoning Boundary
Parcel Lines
(a1) Agricultural
(c1) Light Commercial
(c2) General Commercial
(c3) Central Business Commercial
(city) Zoned by Local Municipality
(i1) Light Industrial
(i2) Heavy Industrial
(i2r) Heavy Industrial Restricted
(r1) Single Family Residential
(r2) Mixed Residential
(rm) Multi-Family Residential
(rmhp) Manufactured Home ParkFinal Zoning
Public Road(COB 1064_Pg
468)
1st
6th
Cynthia
Bol
siu
s
Pub
licR
oa
d(C
OB
106
4_
Pg
46
2)
5th
Murrell
Ora
Ma
dis
on
Ele
ctri
c(R
eco
rde
d)
Ele
ctri
c(C
urre
nt)
Ele
ctri
c
Merlin
7th
Lin
coln
Lau
rel
8th
Har
de
y
Ind
epe
nd
en
ce
2nd
Center
W.B
.N
ori
sS
ub
.R
d
Public Road (1131779,1132404)
Public Road (COB 323_Pg 252)
Ve
rre
t
3rd
Goldrich
VC
M
4th
Public Road (COB 241_Pg 321)
Mic
hig
an
Orp
hana
ge
Powell
Tro
usd
ale
Evergreen
Harvey Miller
Rig
ma
ide
n
0 0.35Miles
Proposal For Streets To Remain,Rededicate, & Revoke
005This map shows the streets to be revoked, rededicated, and streets
to remain.
Streets To Be Revoked1st - 261'
2nd - 1325'
3rd - 1768'
4th - 3143'
5th - 2900'
6th - 1555'
7th - 1500'
8th - 981'
Bolsius - 395'
Center - 1336'
Cynthia - 329'
Electric (Recorded) - 582'
Electric - 587'
Evergreen - 4409'
Goldrich - 2327'
Independence - 1303'
Laurel - 883'
Lincoln - 1433'
Madison - 558'
Merlin - 767'
Michigan - 2234'
Orphanage - 1153'
Powell - 2133'
Public Road (1131779,1132404) - 1547'
Public Road (COB 1064_Pg 462) - 402'
Public Road (COB 1064_Pg 468) - 556'
Public Road (COB 241_Pg 321) - 6646'
Public Road (COB 323_Pg 252) - 1567'
Rigmaiden - 1442'
Trousdale - 2311'
Verret - 1747'
W.B. Noris Sub. Rd - 1416'
Streets To Remain Murrell - 518'
1st - 1066'
3rd - 656'
4th - 213'
5th - 430'
6th - 307'
7th - 155'
Electric (Current) - 582'
Evergreen - 9080'
Hardey - 1215'
Harvey Miller - 1017'
Michigan - 289'
Ora - 612'
VCM - 2603'
Streets To Be Rededicated3rd - 656'