lake charles cracker project (lccp) gas-to-liquids …

41
LAKE CHARLES CRACKER PROJECT (LCCP) & GAS-TO-LIQUIDS PROJECT (GTL) Rezoning Application APRIL 2014 PREPARED FOR: CALCASIEU PARISH POLICE JURY PREPARED BY: C.H. FENSTERMAKER & ASSOCIATES, LLC

Upload: others

Post on 15-Mar-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

 

LAKE CHARLES CRACKER PROJECT (LCCP) &

GAS-TO-LIQUIDS PROJECT (GTL)  

Rezoning Application  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   APRIL 2014 

 

 

 

PREPARED FOR: 

 CALCASIEU PARISH POLICE JURY 

 

 PREPARED BY: 

 C.H. FENSTERMAKER & ASSOCIATES, LLC 

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

2 | P a g e   

  

 

Project Team 

C.H. Fenstermaker & Associate, LLC 135 Regency Square Lafayette, Louisiana 70508 Tel: 337‐237‐2200 www.fenstermaker.com  Kean Miller LLP 400 Convention Street, Suite 700 Baton Rouge, Louisiana 70802 Tel: 225‐382‐3411  Villavaso & Associates, LLC 6304 Beauregard Avenue New Orleans, Louisiana 70124 Tel: 504‐343‐9096                              

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

3 | P a g e   

  

 

TABLE OF CONTENTS 

1.0  INTRODUCTION ................................................................................................................................. 4 

2.0  SASOL GLOBAL .................................................................................................................................. 4 

3.0  THE PROJECTS ................................................................................................................................... 5 

4.0  SITE LAYOUT ...................................................................................................................................... 6 

5.0  ZONING REQUEST ........................................................................................................................... 10 

6.0  ECONOMIC IMPACT ASSESSMENT .................................................................................................. 14 

7.0  SAFETY, HEALTH, AND ENVIRONMENTAL ....................................................................................... 16 

8.0  ENVIRONMENTAL PERMITTING ...................................................................................................... 19 

9.0  TRAFFIC IMPACT ANALYSIS ............................................................................................................. 21 

10.0  DRAINAGE IMPACT ANALYSIS ......................................................................................................... 25 

11.0  CONCLUSION ................................................................................................................................... 28 

REFERENCES ................................................................................................................................................ 29 

EXHIBITS ...................................................................................................................................................... 30 

  

   

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

4 | P a g e   

  

 1.0  INTRODUCTION 

 Sasol North America Inc. (Sasol) plans to make a significant investment in Southwest, Louisiana, with the 

proposed  construction  of  a world‐scale  ethane  cracker  and  derivatives  complex  as well  as  a  gas‐to‐

liquids  facility at  its Westlake  site.   This  innovative  complex will not only benefit our nation’s energy 

security, but will also be a tremendous economic stimulus to this region.   

To begin construction on this project, Sasol  is requesting the rezoning of purchased property within  its 

site  plan.    This  application  has  been  prepared  to  summarize  the  economic,  traffic,  drainage,  and 

environmental  impacts associated with  this project, and  to address  these  impacts  in accordance with 

local, state, and  federal standards.   This  information  is being presented  to  the Calcasieu Parish Police 

Jury  (CPPJ)  – Division  of  Planning  and Development  so  that  it  can make  a  decision  on  this  rezoning 

request. 

Details  pertaining  to  Sasol’s  cooperation  with  other  public  and  private  entities  are  detailed  in  the 

developer’s agreement that accompanies this application. 

2.0  SASOL GLOBAL  Sasol  is  an  international  integrated  energy  and  chemical  company  that  leverages  the  talent  and 

expertise of our more than 35,000 people working in 37 countries.  Sasol develops and commercializes 

technologies  and  builds  and  operates world‐scale  facilities  to  produce  a  range  of  products  including 

SASOL GLOBAL

Based in Johannesburg, South Africa US Headquarters in Houston, Texas 35,000 Employees in 37 Countries Operations produce the building blocks that help make everyday products

including detergents, plastics, and liquid fuels.

CORE VALUES

Safety-People-Integrity-Accountability- Stakeholder Focus-Excellence in all that they do

COMMITMENT

Committed to providing a safe working environment for their employees and being a good neighbor in the communities where they operate.

Committed to advancing sustainable development.

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

5 | P a g e   

  

liquid fuels, high‐value chemicals and low‐carbon electricity.  

These  fuels  and  chemicals  are  then  used  to  produce  the 

building  blocks  that  make  everyday  products  such  as 

detergents, plastics, and fragrances.   

Sasol  is headquartered  in  Johannesburg,  South Africa.    Its 

United States headquarters is in Houston, Texas. 

Sasol’s  Louisiana  industrial  facility,  known  as  the  Lake 

Charles Chemical Complex  (LCCC), purchased  in 2001  from 

RWE  DEA  (and  formerly  known  as  Condea‐Vista),  began 

initial operations  in 1961 with the world's  largest synthetic 

Alcohol  Unit.  Through  the  1960s  and  1970s,  the  facility 

expanded  to  include  a  Normal  Paraffin  Unit,  Ethoxylation 

Unit,  Ethylene  Unit  and  Alumina  Unit.   In  1981,  a  Linear 

Alkylbenzene Unit was added to the facility and in 2004 the 

R&D facility was relocated from Austin, Texas to the LCCC. 

Sasol’s  goal  is  to  minimize  risk,  eliminate  incidents, 

responsibly  manage  environmental  impacts,  and  enable 

excellence  in  operations  and  business  performance  while 

providing a workplace that protects our employees, service 

providers, and neighbors. 

Sasol  makes  important  economic  contributions  to  the 

communities  in which  it operates.   Each year Sasol donates 

more than $300,000 to local nonprofit organizations and is a 

major  contributor  to  the  economy  of  Southwest  Louisiana 

through  annual  taxes  and  the  purchase  of  goods  and 

services totaling more than $160 million.   

 3.0  THE PROJECTS 

Sasol  is  proposing  construction  and  development  of 

approximately  3,034  acres  of  property  just  west  of 

Westlake, Louisiana in central Calcasieu Parish.  The projects 

are composed of two facilities: A chemical facility known as 

the Lake Charles Cracker Project (LCCP) and a Gas‐To‐Liquids 

facility  (GTL).    The  two  projects  have  separate  economic 

drivers, and each can stand alone without the need for the 

other.   

GAS-TO-LIQUIDS PROJECT (GTL)

First in the US

Proven Technology that coverts natural gas into GTL

diesel and other products

Will convert natural gas into more than 96,000 barrels

per day of GTL diesel

Estimated Cost $11-$14 billion

Schedule

2016 Begin Construction 2019 Phase 1 Startup 2020 Phase 2 Startup

LAKE CHARLES CRACKER PROJECT (LCCP)

Ethane “cracking” is the process of breaking down

molecules of ethane contained in natural gas to

create ethylene

Will produce approximately 1.5 million tons of ethylene

per year

Estimated Cost $5-$7 billion

Schedule

2014 Begin Construction 2017 Startup

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

6 | P a g e   

  

 

The chemical facility will be a world‐scale ethane cracker.  Ethane “cracking” is the process of breaking 

down molecules of ethane contained in natural gas to create ethylene, one of the building blocks of the 

petrochemical  industry.   The  facility will produce approximately 1.5 million  tons of ethylene per year.  

The ethylene will be used in seven downstream derivative plants to produce a range of products such as 

detergents,  fragrances,  paints,  film,  synthetic  fibers,  and  food 

packaging.    Estimated  cost  of  the  facility  is  $5  to  $7  billion.  

Pending  final  investment decision, construction  is  set  to begin  in 

2014, with beneficial operations commencing in 2017.  

The  GTL  facility will  be  the  first  in  the United  States.    The  GTL 

facility converts natural gas  into diesel  for transportation, as well 

as  other  products.    GTL  diesel  burns  cleaner  and  has  lower 

greenhouse  gas  emissions  than  conventional  diesel.    It  is  also  virtually  free  of  sulfur  and  aromatic 

compounds.   The  facility will product more  than 96,000 barrels per day of  liquid  fuels and  chemicals 

including: GTL diesel, GTL naphtha,  liquefied petroleum gas, paraffin, GTL base oils and medium hard 

waxes.    Estimated  cost  of  the  facility  is  $11  to  $14  billion.    Pending  final  investment  decision, 

construction would begin  in 2016, with beneficial operations commencing  in 2019.   The project  is  the 

largest single manufacturing investment in the history of Louisiana and one of the largest foreign direct 

investment manufacturing projects in the history of the United States.   

The project will be designed with proven, modern pollution control equipment and waste minimization 

process.    The  project  will  also  have  processes  in  place  that  recycle  wastewater  to  minimize 

environmental impact and conserve water resources. 

 4.0  SITE LAYOUT 

The existing Sasol Lake Charles Chemical Complex is located west of Westlake, Louisiana and is bound by 

Houston River Road to the north and Old Spanish Trail to the South.   The proposed site expansion will 

occur to the west of the existing Sasol facility.    

A general plot plan showing the boundaries of the existing operations, LCCP, GTL, shared facilities, and 

construction support can be seen in Figure 1.   

 

 

 

 

 

LCCP and GTL Projects

Largest single manufacturing investment

in the history of Louisiana.

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

7 | P a g e   

  

 

 Figure 1: Project Plot Plan 

 Similar to Sasol’s existing facility, the LCCP and GTL projects will predominantly be buffered through the 

use of berms, natural vegetation, and facility buildings.  Sasol plans to minimize the visual impact of the 

LCCP and GTL projects.  A driver on Houston River Road  would see something similar to what is shown 

in Figures 2, 3, and 4.  Figure 2 represents the visual along Houston River Road looking towards the GTL 

facility.   Similarly, Figure 3 and Figure 4 represent the views of the LCCP from Houston River Road.   As 

you can see, from both angles, the majority of the facilities will be obstructed by a berm which will be 

manicured with trees and shrubbery.  Along Old Spanish Trail, a driver would see tanks and pipe racks in 

the foreground (Figure 5).  The general location of the renderings in relation to the facility plot plan can 

be seen in Figure 6. 

 

 

 

 

 

 

 

 

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

8 | P a g e   

  

 Figure 2: View #1 – Conceptual Rendering of the GTL facility from Houston River Road looking Southwest 

 

 Figure 3: View #2 – Conceptual Rendering of the LCCP facility from Houston River Road looking Southwest 

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

9 | P a g e   

  

 Figure 4: View #3 – Conceptual Rendering of the LCCP facility from Houston River Road looking Southwest 

 

 Figure 5: View #4 – Conceptual Rendering of the LCCP facility from Old Spanish Trail looking Northwest 

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

10 | P a g e   

  

 Figure 6: General location of the renderings views 

 

5.0  ZONING REQUEST 

Sasol is requesting that Calcasieu Parish: 

 

1. REZONE  SASOL  OWNED  PROPERTY:    Rezone  1,470  acres  of  Sasol‐owned  property  from 

agricultural,  single  family  residential,  mixed  residential,  manufactured  home  park,  general 

commercial, and light industrial to I‐2 Heavy Industrial (Figure 7).  

 

2. COMPLETE A  FEASIBILITY  STUDY  FOR REZONING NON‐SASOL OWNED  PROPERTY: Complete  a 

feasibility  study  to  rezone approximately 177 acres of non‐Sasol owned properties within  the 

overall boundary to I‐2 Heavy Industrial.  Figure 8 shows both the areas that Sasol is requesting 

to  be  rezoned  (purple  color),  as well  as  the  areas  they  are  requesting  a  feasibility  study  be 

completed (green color).   If granted, this would result  in a uniform I‐2 Heavy Industrial zone  in 

this  area.    A map  showing  the  final  proposed  zoning  can  be  found  in  Figure  9  (I‐2  Heavy 

Industrial  is shown  in purple).   Detailed maps and  legal descriptions of  the proposed rezoning 

are included as part of the developer’s agreement that is part of this rezoning application.     

 

 

 

 

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

11 | P a g e   

  

 

3. REVOKEMENT AND  REDEDICATION OF  PUBLIC  ROADS:    Revoke  the  following  public  roads  as 

currently located in their entirety, except for the portions of such roads that may be needed to 

allow  owners  to  access  their  properties:  1st Avenue,  2nd Avenue,  3rd Avenue,  4th Avenue,  5th 

Avenue, 6th Avenue, 7th Avenue, 8th Avenue, Bolsius Road, Center Street, Cynthia Street, Electric 

Drive  (existing  location  and  originally  platted  location),  Evergreen  Road,  Goldrich  Drive, 

Independence Road,  Laurel Avenue,  Lincoln Avenue, Madison  Street, Merlin  Street, Michigan 

Avenue, Orphanage Road, Powell  lane, Rigmaiden Avenue, Trousdale Road, Verret Road, and 

WB Noris Subdivision Road.  In addition revoke all roads within the Sasol property boundary that 

were previously dedicated or recorded but were not constructed.  It is being requested that the 

45 acres of revoked roads also be rezoned as I‐2 Heavy Industrial.  A map showing the requested 

roads to be revoked can be found in Figure 10. 

 

4. COMPLETE A STUDY FOR THE INCLUSION OF REZONED PROPERTY INTO LOCKPORT INDUSTRIAL 

DISTRICT:  Complete a study to include the 1,692 acres of rezoned I‐2 Heavy Industrial property 

into the existing Lockport Industrial District.  A map showing the existing and proposed limits of 

the Lockport Industrial District can be seen in Figure 11. 

See the EXHIBITS section of this report for larger (11”x17”) maps of Figure 1 to Figure 11. 

 

 Figure 7: Existing Zoning Map 

 

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

12 | P a g e   

  

 Figure 8: Proposed Zoning Map 

 Figure 9: Final Zoning Map 

     

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

13 | P a g e   

  

 Figure 10: Proposal for Streets to be Remain, Rededicate, and Revoke 

 

 Figure 11: Proposed Lockport Industrial District Expansion 

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

14 | P a g e   

  

 6.0  ECONOMIC IMPACT ASSESSMENT  On  behalf  of  Sasol,  NERA  Economic  Consulting  performed  the  economic  impact  assessments  for 

establishment of the two proposed stand alone industrial facilities.  With cooperation from Sasol, NERA 

used  detailed  facility  information  and  customized  a  state‐of‐the‐art  economic model  developed  by 

Regional Economic Models,  Inc.  (REMI)  to study  the potential economic  impacts of  the  two proposed 

projects for both the state of Louisiana and the United States.  Based on the model results and NERA’s 

calculations, the LCCP construction is expected to account for 20‐40% of total private investment in the 

state of  Louisiana while  the GTL Project will account  for as much as 

44%.   

The  NERA  team  also  identified  expected  trends  concerning  gains 

within the Louisiana and United States economies.   On the front end, 

project  construction  expenditures  will  result  in  direct  economic 

growth  through  the  employment  of  construction  crews  in  Louisiana 

and  procurement  of  construction materials  from  the  United  States.  

Indirect  gains  can  result  from  the  projects’  various  needs  for  goods 

and services.  Income from both direct and indirect sources will induce further gains within the state and 

national economies.  For example, higher employment rates and wages will result in increased spending 

on other goods and services.   Therefore,  the construction of  the projects presents a multiplier effect.  

The  proposed  projects  will  directly  employee  more  than  5,000  construction  workers  during  peak 

construction  in  2016,  increasing  overall  employment  in  Louisiana  by  30,000  during  2016  due  to 

multiplier effects.   Although Sasol plans  to hire  locally as much as possible,  the  influx of construction 

workers will  increase  the housing demand  in Calcasieu Parish. These projects will have a  large  impact 

housing availability, rentals, hotels, campgrounds and RV parks,  furthering the multiplier effect. When 

operational the facilities will employee approximately 1,200 workers at an estimated median salary of 

$89,000 a year, compared with  the Calcasieu Parish median  salary of 

$35,772.   

Additionally,  economists  have  determined  that  the  construction  of 

such  sophisticated  operating  facilities  as  those  proposed  by  Sasol 

would  create  an  agglomeration  effect.    This  essentially means  small 

communities or towns will be generated by the additional businesses, 

restaurants, and housing  that will develop near  the proposed project 

sites to accommodate  its workers.   Once construction  is complete and 

the  facilities  are operational,  local,  state and national economies will 

continue to experience direct gains through the employment of facility workers.  Indirect gains will come 

from the consumption of domestic goods and services, ranging from local purchases to using natural gas 

from  the United  States.    Increased  spending  from direct  and  indirect  gains will  continue  to promote 

economic growth on the local, state and national level.  In addition, the agglomeration effect will persist 

throughout the facilities’ operations to accommodate the facility workers.   

The LCCP construction is

expected to account for 20-40% of the

total private investment in the

state of Louisiana.

Calcasieu Parish median salary

$35,772

Sasol Production Employee

median salary $89,000

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

15 | P a g e   

  

The sophistication of these projects brings a need for higher education.  SOWELA Technical Community 

College will provide  training  for  these  and  similar projects. As  a  result,  the College has  received $20 

million  in  state  funding  to  begin  construction  of  new  facilities 

and  training  programs.  Construction  on  the  new  facilities  will 

begin in 2014, furthering the multiplier effect.  

NERA used the REMI model along with detailed expenditure and 

operational  information  from  Sasol,  to  estimate  gains  in  the 

Louisiana  economy  throughout  the  two  proposed  projects’ 

construction  and  operations.    The  table  below  identifies  the 

average  annual economic  gains  for  the  LCCP  and GTL projects.  

Gains  from  the  LCCP  are  calculated  over  the  period  of  2013‐2041,  and  the  GTL  Project  gains  are 

predicted for the period of 2013‐2044.   

Category LCCPIncrease/year

GTLProjectIncrease/year

LouisianaGrossStateProduct(GSP) $900million $3.3billionLouisianaPersonalIncome $300million $1.7billionLouisianaEmployment 3,900jobs 21,000jobsLouisianaGovernmentRevenue $50million $235million

   

According  to  the  economic models,  Sasol will  pay  an  average  of  $150 million  in  property  taxes  to 

Calcasieu  Parish  in  “year  11”  between  the  two  facilities.    Beyond  the  local  and  state  level,  income 

generated  by  the  two  projects  will  contribute  to  the  national  economy  through  the  purchase  of 

domestic goods and  services by Sasol,  its employees, and  the members of  the agglomeration.   NERA 

used  the  REMI  model  to  also  estimate  monetary  gains  for  the  United  States  economy  from  the 

construction and operations of the two proposed projects.   The  table below  identifies average annual 

gains  estimated  for  both  projects.    As  with  Louisiana’s  economic  forecast,  gains  for  the  LCCP  are 

averaged over the period of 2013‐2041, and the GTL Project gains are averaged for the period of 2013‐

2044.   Economic growth for the United States economy  includes the predicted values shown above  in 

Louisiana’s gains.   

Category LCCPIncrease/year

GTLProjectIncrease/year

USGrossDomesticProduct(GDP) $5.1billion $7.8billionUSPersonalIncome $2.1billion $3billionUSEmployment 38,000jobs 55,000jobsUSGovernmentRevenue $260million $439millionUSNetExports ‐‐ $1.7billion

   

Overall, the NERA study results indicate that substantial growth is expected within Calcasieu Parish, the 

state of Louisiana, and U.S. economies as a result of the proposed construction and operations of Sasol’s 

two projects. 

SOWELA Technical Community College

received $20 million in funds from State of

Louisiana specifically for training programs as a result of these projects.

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

16 | P a g e   

  

 7.0  SAFETY, HEALTH, AND ENVIRONMENTAL  Sasol  is  committed,  at  the  highest  level,  to  safe  and 

reliable operations.  Sasol’s Safety, Health, & Environment 

(SHE)  policies  articulate  their  corporate  commitment  to 

safety and reliability. 

Resource  Report  11, which  is  part  of  the  Environmental 

Assessment  completed  by URS  Corporation  on  behalf  of 

Sasol,  describes  the  design,  construction,  operation,  and 

maintenance measures to maximize the projects’ reliability 

and  to  minimize  potential  hazards  to  the  public  from 

potential  failure  of  project  components  and/or  chemical 

releases as a result of accidents or natural catastrophes.   

Sasol follows a wide range of state and federal regulations 

and  guidance  documents  that  apply  to  the  design  and 

operations of new facilities.  Some of these include: 

Process Safety Management (29 CFR 1910.119) 

Risk Management Program (40 CFR Part 68) 

The  National  Oil  and  Hazardous  Substances 

Pollution  Contingency  Plan  and  the  Area 

Contingency Plans for the local Area 

US Coast Guard Marine (USCG) Safety Manual 

Occupational  Safety  and  Health  Administration 

(OSHA) requirements for worker health and safety 

(29 CFR 1910.120) 

USCG  National  Preparedness  for  Response 

Exercise Program 

OSHA  Employee  Emergency  Plans  and  Fire 

Prevention 

Spill Prevention and Control 

Startup, Shutdown, and Malfunction Plans (40 CFR 

Part 63) 

Department of Homeland Security CFATS Program 

Louisiana Department of Natural Resources 

Pipeline Safety Program 

 

SASOL’S COMMITMENT TO SAFETY, HEALTH, AND THE

ENVIRONMENT (SHE)

We, the people of Sasol, striving 

for  excellence  in  all  we  do, 

recognize  the  impact  that  our 

activities  can  have  on  people 

and  the  environment.  Safety, 

health  and  protection  of  the 

environment  will  form  an 

integral part of our planning and 

decision  making.    We  will 

manage our company, wherever 

we  do  business,  in  an  ethical 

way  that  strikes an appropriate 

and  well‐reasoned  balance 

between  economic,  social  and 

environmental needs. We expect 

our  employees  and  service 

providers  globally,  to  take 

personal  responsibility  to 

embrace  this  ambition  in  all  of 

our day‐to‐day activities. 

Our  goal  is  to  eliminate 

incidents,  minimize  risk, 

responsibly  manage 

environmental  impacts  and 

enable  excellence  in  operations 

and business performance while 

providing  a  workplace  that 

takes  into  account  the  safety 

and wellbeing of our people and 

service providers. 

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

17 | P a g e   

  

Sasol is a member of the

Lake Area Industry

Alliance and the Southwest

Louisiana Mutual Aid

   Sasol has planned  the  design,  construction,  and operation of  its proposed  LCCP  and GTL projects  to 

avoid potential and real adverse environmental effects as much as possible.  Strategized planning, well 

designed engineering technologies, and best operating practices will be used to avoid both potential and 

real adverse environmental effects.  

The  likelihood  for potential hazards will be  reduced during  the design phase by using buffer  strips or 

other methods of physical separation around  the project sites and siting and safety design  to prevent 

failures due to natural risks. Other engineered designs, when applicable will use the International Code 

Council for further protection of human life and environment. The proposed projects would be built to 

meet  or  exceed  the  most  stringent  national  and  international  safety  standards,  which  include  full 

containment  storage  tanks,  multiple  gas  detectors,  infrared  fire  detectors,  closed‐circuit  cameras, 

stringent  security  measures  and  advanced  safety  training.  Equipment‐design  specifications  are 

rigorously reviewed to protect operational integrity. 

All  construction  will  be  conducted  pursuant  to  guidelines  of  a  quality  assurance  program  as 

implemented by  the project management  team.  The operation will benefit  from  intensive personnel 

selection  and  training,  strict  procedures,  knowledgeable  supervision,  and  diligent  overview  by 

management. 

Sasol  is a proud and active member of the Lake Area  Industry Alliance (LAIA), 

which  is  comprised  of  23  local  industries.    Sasol’s  participation  in  the  LAIA 

enhances the safety of its facility in several ways.  It enables Sasol to learn best 

practices from other  industries,  it provides  incentive for Sasol to achieve high 

levels  of  safety  as  these  safety  records  will  be  communicated  by  LAIA 

throughout  the  area,  and  it  enables  Sasol  to  develop  communications with 

community officials that are beneficial in the event of an emergency. 

Incident Investigation and Reporting Personal Protective Equipment LCCC Railroad Car Derailment Respiratory Protection Procedure Hazardous Waste Operations And Emergency

Response Hurricane Preparedness Fire Protection LCCC Emergency Notification/Call-Out

Procedure LCCC Security Procedure

LCCC Emergency Response Team Procedure

LCCC Community Awareness andEmergency Response (CAER) Procedure

LCCC Southwest Louisiana Mutual Aid Procedure

LCCC Emergency Head Count Procedure Incident Command System Emergency Telephone Numbers Site Topography  

Sasol has many Sasol-Specific operation standards that will govern the design and operations of the new facilities with rules, regulations and guidelines for:

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

18 | P a g e   

  

SASOL’S SAFETY, HEALTH, AND THE ENVIRONMENT PRINCIPLES

Conducting their business with respect and care for people and the environment Responsible utilization of natural resources Implementing responsible care for all Sasol’s chemical and associated

businesses. Non-chemical business will implement appropriate, recognized codes of practice.

Continually improving our safety, health and environmental performance. Complying, as a minimum, with all applicable legal and other agreed

requirements. Promoting dialogue with stakeholders about safety, health, and environmental

performance.

SASOL ACHIEVES THESE BY:

Implementing internationally recognized safety, health, environmental and quality management systems.

Developing and implementing inherently safer and cleaner technologies. A ‘cradle to grave’ approach to the products we develop, manufacture, use,

distribute, and sell. Informing and appropriately training all employees and contractors on safety,

health, and environmental matters. Responding effectively to safety, health, and environmental emergencies

involving our operations and products. Engaging with relevant authorities and institutions on the formulation of

legislation, standards, and the implementation thereof. Benchmarking internationally on best safety, health, and environmental practices. Sharing safety, health, and environmental reduction best practices throughout

Sasol. Providing appropriate resources required to implement the above.

In  addition  Sasol  is  a  long‐standing member  of  the  Southwest  Louisiana Mutual  Aid  (SLMA).    The 

objective of this organization  is the  joining together of fire‐fighting,  law enforcement, rescue, and first 

aid  manpower  and  facilities  among  Southwest  Louisiana  industries  and  municipalities  for  mutual 

assistance in case of emergency situations ‐ either natural or man‐made.   

 

    

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

19 | P a g e   

  

8.0  ENVIRONMENTAL PERMITTING  Sasol’s  goal  is  to  responsibly manage  potential  environmental  impacts while  promoting  operational 

excellence  and  business  performance.    Sasol  is  committed  to  complying  with  all  environmental 

regulations,  specifically  to  implement  the  necessary  mitigation  measures  in  cooperation  with  all 

regulatory agencies.  Sasol is seeking various permits from state and federal agencies to allow the new 

construction of the LCCP and GTL projects.   Some of these permits  include various air quality permits, 

wastewater permits, pre‐construction and post‐construction stormwater permits, and US Army Corps of 

Engineers  (USACE) wetland permits.   A complete  list  including  the agency and status are  listed within 

this report.  

LCCP and GTL Permits Agency Status 

Clean Air Act (CAA) Prevention of Significant Deterioration (PSD) Permit 

Louisiana Department of Environmental Quality (LDEQ) 

Permit application submitted to LDEQ: April 30, 2013 Public hearing:  March 25, 2014 Anticipated authorization date:  May 2014 

CAA Title V Permits  LDEQ  Permit applications submitted to LDEQ: April 30, 2013 Public hearing: March 25, 2014 Anticipated authorization date: May 2014 

Clean Water Act (CWA) Section 404 and Rivers and Harbors Act (RHA) Section 10 Permit 

U.S. Army Corps of Engineers (USACE) 

LCCP/GTL Application submitted: July 24, 2013 Anticipated authorization date: June 2014 

Construction Dock Application submitted: May 20, 2013 Anticipated authorization date:  June 2014 

CWA Section 401 Water Quality Certification  

LDEQ  Application Submitted: July 24, 2013 Anticipated Authorization date:  June 2014  

CWA Louisiana Pollutant Discharge Elimination System (LPDES) Permit (Industrial Wastewater Discharge Permit) 

LDEQ  Permit renewal and modification application submitted to LDEQ: April 30, 2013 Anticipated authorization date:  May 2014 

LPDES Storm Water General Permit for Construction Activities ‐ Five Acres or More (LAR100000) 

LDEQ  Notice of Intent submitted: January 7, 2014 Permits received: January 22, 2014 

Louisiana Multi‐Sector General Permit (MSGP, LAR05M448) for Storm Water 

LDEQ  Obtained:  the existing facilities holds a Multi‐Sector General Permit that will need to be modified at the appropriate time to cover the LCCP and GTL projects 

Louisiana General Permit for Hydrotest Water (LAG679012) 

LDEQ  Obtained:  the existing facilities hold a Hydrotest permit and can be utilized by the LCCP and GTL projects 

Solid Waste Permit  LDEQ  Obtained:  the existing facility has a solid waste generator ID and no new solid waste permitted units are anticipated for the LCCP and GTL Projects.   

Hazardous Waste Permit/RCRA Compliance 

LDEQ 

 

GTL ‐ Application submitted: February 10, 2014. GTL ‐ Anticipated authorization data: January 2015 

 

 

 

 

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

20 | P a g e   

  

ENVIRONMENTAL PERMITS FOR THE LAKE CHARLES CHEMICAL COMPLEX EXISTING FACILITIES 

Existing LCCC Permits  Agency  Description and Status 

Clean Air Act Prevention of Significant Deterioration Permit 

LDEQ  Alumina Unit No. PSD‐LA‐644 (approval of modification to LCCC Alumina Unit, in effect from 9/19/00 to 3/19/02) 

LAB Unit No. PSD‐LA‐291 (M‐3) (approval of modification to LCCC Linear Alkyl Benzene Unit on 11/29/10) 

Clean Air Act Title V Permits  LDEQ  Alumina Unit Title V No. 2565‐V6 (approval of operating permit renewal and modification for the LCCC Alumina Unit, in effect from 10/8/12 until 10/8/17) 

Ethylene‐Activated Sludge‐Steam Unit Title V No. 2743‐V5 (approval of permit modification for the LCCC Ethylene/Activated Sludge /Steam Unit, in effect from 7/12/12 until 8/8/13) 

LAB Unit Title V No. 2894‐V4 (approval of permit modification for the LCCC Linear Alkyl Benzene Unit, in effect from 7/13/12 until 11/29/15) 

NPU Unit Title V No. 2896‐V5 

Alcohol Unit Title V No. 2865‐V4  (approval of permit modification for the LCCC Alcohol Unit, in effect from 9/27/11 until 6/14/16)  

ETO Unit Title V No. 2325‐V4 (approval of permit modification for the LCCC Ethoxylation Unit, in effect from 11/1/12 until 12/9/13) 

CoMonomer Unit Title V No. 3088‐V1 (approval of permit modification for the LCCC CoMonomer‐1 Unit, in effect from 2/22/13 until 4/25/16) 

CWA Section 404 and Rivers and Harbors Act Section 10 Permit 

USACE 

 

MVN‐2011‐02625‐WNN (for work related to construction of the Comonomer 1 unit (a/k/a Tetramerization unit including parking lot, warehouse, receiving area, construction access and haul roads, material storage area) 

MVN‐2012‐1425‐WB (for construction of a railcar storage facility off of E. Burton St.) 

MVN‐2004‐294‐WKK (for construction of a locker room for alcohol unit and a first aid bldg.) 

MVN‐2001‐1302‐WJJ (to install box culverts) 

CWA Louisiana Pollutant Discharge Elimination System (LPDES) Permit (Industrial Wastewater Discharge Permit) 

LDEQ  LPDES Permit No. LA0003336 in effect from 12/1/09 until 11/30/14; renewal application was filed on 4/30/13) 

Louisiana LPDES Storm Water Multi‐Sector General Permit (MSGP, LAR05M448)  

LDEQ  LPDES Storm Water Multi‐Sector General Permit No. LAR05M448 (reissuance notice on 5/27/11 for LPDES storm water general permit for the LCCC) 

Active Construction Storm Water Permit LAR10H509 (for discharges to Bayou Verdine resulting from construction activities associated with construction of the Comonomer 1 unit – construction nearly complete at this time)   

CWA Section 401 Water Quality Certification  

LDEQ  WQC 120613‐01 issued 8/8/12 for Corps Permit MVN‐2012‐1425‐WB to clear land and place fill material for the construction of a railcar storage facility 

WQC 111208 issued 1/6/12 for Corps Permit MVN‐2011‐02625‐WNN to clear land and place fill material for industrial facility expansion 

WQC 110602‐02 issued 6/21/11 for Corps Permit MVN‐2001‐1302‐WJJ to install box culverts for industrial facility expansion 

WQC 090625‐02 issued 7/21/09 for Corps Permit MVN‐2004‐2924‐WKK to clear land and place fill material for construction of an alcohol locker room and first aid office building 

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

21 | P a g e   

  

Existing LCCC Permits  Agency  Description and Status 

LPDES General Permit for Discharges of Hydrostatic Test and Vessel Testing Wastewater 

LDEQ  Reissuance of LPDES General Permit (LAG670000) for Sasol North America, Inc. on February 1, 2013 under Permit No. LAG679012, covering discharge of hydrostatic test and vessel testing wastewater by Sasol North America, Inc. for statewide pipeline operations located in multiple parishes in Louisiana.   

Solid Waste Permit  LDEQ  Standard Type I Permit No. P‐0251R1 (covers Sand Filter Settling Basins (North and South); Holding Pond; and Stormwater Diversion Ponds (North and South)), in effect 1/23/10 until 6/23/20.  

Hazardous Waste Permit/RCRA Compliance 

LDEQ  Hazardous and Solid Waste Amendment (HSWA) Post‐Closure Permit, Part B, LAR000041087‐PC‐RN‐1.  Pursuant to this permit, Sasol North America will perform post‐closure care of the Closed Activated Sludge Unit and the required corrective actions.  Permit is in effect from 8/15/12 to 8/14/22. 

Radioactive Material License 

 

LDEQ  License No. LA‐4902‐L01 (Amendment No. 24) was issued following renewal on July 1, 2013 and expires on July 31, 2018 

   9.0  TRAFFIC IMPACT ANALYSIS  A development the size of Sasol’s LCCP and GTL facilities will inevitably impact traffic within the Parish.  Sasol contracted Alliance Transportation Group to complete a Traffic  Impact Analysis  (TIA) to evaluate the  traffic  impacts  of  the  site  on  the  adjacent  roadway  network  and  to  determine  the  road  traffic improvements necessary to mitigate these impacts.    Analysis was performed under the following scenarios: 

Existing Conditions (2013) 

Construction Ramp‐Up Phase 1 (January 2015) 

Construction Ramp‐Up Phase 2 (May 2015) 

Peak Construction Phase (February 2016) 

Plant Operations and Maintenance Phase (2020)  The study was completed using a timeline of worker activity which anticipates that the project site will generate approximately:  

1,700 worker trips during construction Ramp‐up Phase 1 

3,400 worker trips during construction Ramp‐up Phase 2  

5,100 worker trips during Peak Construction Phase 

1,700 worker trips post construction during the Plant Operations and Maintenance Phase   The Traffic  Impact Analysis (TIA) evaluated the  impact of the traffic associated with the project on the surrounding  roadway  network.  A  total  of  26  intersection  operations were  evaluated:  15 within  the immediate study area and 11 related to off‐site parking facilities.  To mitigate the effect of site generated traffic in the immediate proximity of the construction site, Sasol 

has proposed to implement three off‐site parking facilities and shuttle service for its employees. The off‐

site parking locations analyzed include:  

 

Sasol has completed a Traffic Impact Analysis (TIA) to evaluate the traffic impacts of the

LCCP and GTL projects on the local traffic and to determine the road traffic improvements necessary to mitigate

these impacts.

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

22 | P a g e   

  

Cities Service Highway (LA 108) and Napoleon Street (US 900  

Beglis Parkway (LA 27) and Louis Alleman Parkway 

Beglis Parkway (LA 27) and Mosswood Road. 

 

Additionally,  Sasol  identified  that  there  will  be  multiple  shifts  during  construction  to  minimize 

disruptions to the surrounding roadway network. There will be two day shifts; one beginning at 6:00 AM 

and one beginning at 6:30 AM. Approximately 45 percent of the workforce will be assigned to each of 

these  shifts.  The  remaining 10 percent of  the workforce will be  assigned  to  the night  shift, which  is 

proposed to begin at 6:00 PM. The intersection improvement locations and corresponding phase for all 

mitigation measures are illustrated in Figure 12. 

  

Figure 12: Improvement Locations by Construction Phase 

 

At the time of this application Sasol has received comments from CPPJ and LA DOTD on the TIA.  Sasol 

will address these, as well as any additional comments.   Sasol also agrees  it will continue to work with 

both the Parish and LA DOTD to mitigate traffic impacts.  At a minimum the road traffic improvements 

included in this report will be completed upon completion of the financial investment decision to move 

forward  with  the  projects.    Some  of  these  intersections  will  be  analyzed  for  potential  roundabout 

locations, based on comments from CPPJ and LA DOTD.   

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

23 | P a g e   

  

Ramp‐Up Phase 1 (January 2015) 

During  the  Ramp‐up  Phase  1,  all 

construction  employee  traffic  will 

be  on‐site  with  access  to  the  site 

from  Evergreen  Road,  west  of  the 

KCS  rail  line.  It  is  expected  that 

1,700 workers will be on site for this 

phase of construction. After analysis 

of  the existing  infrastructure  in  the 

area  surrounding  the  project  site, 

construction  of  the  following 

roadway improvements prior to the beginning of Ramp‐up Phase 1 include: 

I‐10 Service Road and I‐10 Eastbound Westlake Ramps: Modify signal timing 

Sampson Street (LA 378) at Sulphur Avenue (LA 379): Modify signal timing 

Sampson Street (LA 378) at John Stine Road: Modify signal timing 

Old Spanish Trail at Trousdale Road: Construct eastbound right‐turn lane 

Old  Spanish  Trail  at  Prater  Road:  Install  traffic  signal;  Construct  westbound  left‐turn  bay  and 

eastbound right‐turn bay 

Old  Spanish  Trail  at  Evergreen  Road:  Install  traffic  signal;  Construct  eastbound  left‐turn  bay; 

Construct  channelized westbound  right‐turn bay with additional northbound acceleration  lane on 

Evergreen Road exiting the intersection; Construct southbound right‐turn bay 

Houston River Road (LA 379) at Beglis Parkway (LA 27): Modify signal timing 

Preliminary construction cost estimates for the improvements associated with this construction phase 

total $1,288,000. 

Ramp‐Up Phase 2 (May 2015) 

In Ramp‐up Phase 2, some  laborer parking will be on‐site with additional parking provided at two off‐

site locations. The off‐site parking will be implemented near the intersections of Napoleon Road (US 90) 

at Coach Williams Drive (LA 108) and Beglis Parkway (LA 27) at Louis Alleman Parkway. On‐site parking 

will continue to access the site from Evergreen Road, west of the KCS rail line. It is expected that 3,400 

workers will be on site for this phase of construction.  

The  following  intersection  improvements  and  traffic  control  modifications  will  be  implemented  to 

accommodate all the site generated traffic.  

Beglis Parkway (LA 27) at Louis Alleman Parkway: Install traffic signal; Construct westbound lane to 

be shared by through and right turning vehicles 

Beglis Parkway (LA 27) at Burton Street: Construct westbound right‐turn bay 

Sasol Mitigation Strategies:

Off-site Parking Facilities and Shuttle Service for Employees

Multiple Employee Shifts Installation of Traffic Signals Modification of Signal Timing Parameters Construction of Turn Lanes Roadway Widening

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

24 | P a g e   

  

Napoleon  Street  (US  90)  at  Coach  Williams  Drive  (LA  108):  Modify  signal  timing  to  allow  for 

permissive/protected eastbound left turn 

Coach Williams Drive (LA 108) at Maplewood Drive: Modify signal timing 

Preliminary construction cost estimates  for  the  improvements associated with  this construction phase 

total $427,000. 

Peak Construction Phase (February 2016) 

During the Peak Construction Phase, parking will be the same 

as Ramp‐up Phase 2 with an additional off‐site parking facility 

located near  the  intersection of Mosswood Road and Beglis 

Parkway (LA 27). On‐site parking will continue to be accessed 

via Evergreen Road. It  is expected that 5,100 workers will be 

on site for peak construction. 

In order to accommodate the site generated traffic from the 

Peak  Construction  Phase,  the  construction  of  the  following 

roadway  improvements prior  to  the beginning of  this phase 

include:  

Napoleon  Street  (US  90)  at  Prater  Road: Modify  signal 

timing 

Napoleon Street (US 90) at Trousdale Road: Modify signal 

timing 

Beglis Parkway  (LA 27) at Houston River Road  (LA 379): 

Construct  eastbound  right‐turn  bay  and  northbound 

right‐turn bay 

Beglis Parkway (LA 27) at Louis Alleman Parkway: Modify 

striping on  the westbound approach  to allow  for a dual 

left‐turn during the PM peak hour  

Beglis Parkway  (LA 27)  at  I‐10 WB Ramps:  Install  traffic 

signal; Modify pavement markings to create a westbound 

right‐turn bay 

Arizona Street (LA 27) at Patton Street: Construct westbound right‐turn bay 

Arizona Street (LA 27) from south of Patton Street to Mosswood Road: Widen roadway to four lanes 

(two in each direction) 

Preliminary construction cost estimates  for  the  improvements associated with  this construction phase 

total $3,298,000. 

 

Road Traffic Improvements Cost

Ramp-Up Phase 1 January 2015 $1.3 Million

Ramp-Up Phase 2

May 2015 $0.4 Million

Peak Construction Phase

February 2016 $3.3 Million

Plant Operations and Maintenance Phase

2020 $0.2 Million

TOTAL

$5.2 Million

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

25 | P a g e   

  

Plant Operations & Maintenance Phase (2020) 

During  the Operations and Maintenance Phase, all  traffic will be  located on‐site with access primarily from Evergreen Road, west of the KCS rail line. It is expected that 1,700 workers will be on site for the post construction phase of normal plant operations and maintenance.   In  order  to  accommodate  for  all  construction  employee  trips  being  directed  to  on‐site  parking,  the 

analysis determined the following mitigation measure: 

Sampson Street (LA 378) at John Stine Road: Construct eastbound and westbound left‐turn bays 

and modify signal phasing for protected/permissive left turns 

Preliminary construction cost estimates for the improvements associated with this phase total $228,000. 

Total construction cost estimates for the improvements associated with all phases of construction total 

$5,241,000. 

 

10.0  DRAINAGE IMPACT ANALYSIS  As part of the local permitting process with Calcasieu Parish, Sasol submitted a Drainage Impact Analysis 

(DIA)  to  CPPJ  per  the  requirements  of  Parish  Ordinance  5429.    The main  goal  of  the  DIA  was  to 

demonstrate that the LCCP and GTL projects were designed to have no adverse impact on surrounding 

drainage.   

 

No adverse  impact means  that  total  flood  risk, contamination, erosion, and peak  runoff  rates will not 

increase on  surrounding  areas  as  a  result of  the project.    The  report demonstrated  that  the  interim 

phases  of  construction  and  final  site  will  be  built  in  a  manner  to  ensure  no  adverse  impact  on 

surrounding  property.    Sasol’s  DIA  (signed  and  dated  January  20th,  2014)  was  prepared  by  URS 

Corporation and provides an  in‐depth evaluation of the future effects of the LCCP and GTL projects on 

surrounding drainage.  This DIA was approved by the CPPJ on February 20, 2014. 

 

A potential impact during the development of Greenfield property is an increase in stormwater runoff.  

The  DIA  established  baseline  land  use  drainage  conditions  and  runoff  characteristics  and  compared 

them to the proposed runoff conditions from the development.  The DIA proposes methods to mitigate 

these impacts.  Detention ponds are a standard practice to reduce runoff and flood potential from new 

developments.                                 

 

 

 

 

 

 

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

26 | P a g e   

  

Bayou Verdine and Contamination Control 

Bayou Verdine is the controlling variable in the drainage on this site and design measures were taken to 

ensure that the project would not  increase the  flood  levels on this system.   Offsite areas to the north 

flow  through  the  site  via Bayou Verdine  and  these  areas were 

included in the DIA.  The Bayou Verdine system eventually flows 

into  the Calcasieu River.    The design basis  for  this project was 

the 100‐year and 10‐year return period rainfall events. 

Drainage  areas  for  the  proposed  site  include  only  those  areas 

that will  contribute  to  the pond/Bayou Verdine  system.   Areas 

that  contain  potentially  contaminated  runoff will  be  collected 

internally  and  will  not  contribute  to  the  stormwater  system.  

These areas were not included in the drainage areas.  

Rainfall Runoff Determination 

The Soil Conservation Service Curve (SCS) Number Method was used to calculate the existing and post‐

development runoff potential from the site.  This method assigns a number to a parcel of land based on 

the  type of  soil,  conditions of  the  soil,  and  land  cover.   A higher  curve number  (e.g., paved  surface) 

produces more stormwater runoff per acre.   

The SCS Unit Hydrograph method was used to transform runoff potential into actual flow rates passing 

for the site and surrounding areas.  The main variable in the SCS method is time of concentration.  Time 

of concentration measures how fast water accumulates from a given area.   Sloped areas (e.g. rooftops 

and parking  lots)  and hardened  surfaces  speed up  the water  and  shorten  the  time of  concentration 

compared  to  grassed  or  forested  areas.    Detailed  calculations were  performed  to  establish  the  SCS 

variables for each sub‐basin within the project and surrounding 

study area. Sasol proposes nine  (9) detention ponds as part of 

the construction  to mitigate  the  increased  runoff volume  from 

the development.  

The  DIA  used  FEMA‐approved  numerical  models  to  calculate 

current  conditions  and  to  evaluate  the  effectiveness  of  the 

proposed mitigation measures.   HEC‐HMS  calculates  the  peak 

runoff  values  and  HEC‐RAS  computes  the  flood  risk  (flood 

depths) on  surrounding  property.    Taken  together  the models 

have the capability of accurately evaluating the entire drainage system and are the most frequently used 

design combination for pre‐post drainage analysis.  

 

 

 

Sasol proposes 9

detention ponds as part of the construction to mitigate the increased runoff volume from the

development.

Areas that contain

potentially contaminated runoff will be collected internally and will not

contribute to the stormwater system.

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

27 | P a g e   

  

Flood Risk Determination 

The  hydraulic  (HEC‐RAS) model  of  the  site  analyzed  the  existing  flood  depths  of  the  onsite  channel 

network  and was  used  to  ensure  the  post‐development  conditions would  not  adversely  impact  the 

floodplain.   A geometric model of  the channel network stream centerlines and channel cross‐sections 

was created using LiDAR data for the area and site‐specific topographic survey data.  Components of the 

hydraulic model  are  channel  slope,  vegetation  density  and  bank  conditions,  and  bridge  and  culvert 

crossings.  These were investigated closely and are crucial in the models water surface elevation results.   

A major component of the proposed development is re‐routing of Bayou Verdine which currently flows 

through the proposed development area.  The rerouted channel will be lined with concrete through the 

bends and bridge crossings to minimize scour potential in these vulnerable sections.  Figure 13 shows a 

comparison of the existing Bayou Verdine alignment with the proposed channel alignment. 

 Figure 13: Existing versus Proposed Channel Alignment of Bayou Verdine 

 

 

Mitigation Measures and FEMA Flood Zone Implications 

The  results  suggest  that  the  re‐routed  channel  coupled with  a 9 pond detention  system will provide 

adequate mitigation to ensure no adverse impact on surrounding flood levels.  The channel re‐route will 

keep  the  100‐year  floodplain within  its  banks  and will  not  increase  the  limits  of  the  flood  zone  on 

surrounding property.  Bayou Verdine

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

28 | P a g e   

  

Note that the current effective FEMA Flood Insurance Study for this area was completed in 1988 – long 

before  the  creation  of  LiDAR  products  and  expansion  of  surrounding  industrial  areas.      Any  future 

revisions  to  the  FEMA  flood  insurance maps on Bayou Verdine  (if  any) will be  the  result of  external 

factors not attributable to the LCCP and GTL facilities.  Such external factors typically include improved 

modeling  technology,  use  of  high‐resolution  LiDAR  and  topographic  survey  data,  changes  in  survey 

methods, and increased development of surrounding industrial areas.  It was not the purpose or scope 

of this local study to revise the regional FEMA flood insurance maps for Bayou Verdine.   

However, for the channel re‐route a Conditional Letter of Map Revision (CLOMR) permit request will be 

prepared  and  submitted  to  FEMA  as  part  of  the  permit  process.  This  is  required  by  FEMA  when 

proposed  projects  could  alter  the  hydrologic  or  hydraulic 

characteristics of a flooding source and result  in modifications 

to the  floodway, Base Flood Elevations  (BFE), or Special Flood 

Hazard Area (SFHA).  Once construction is complete, a Letter of 

Map  Revision  (LOMR)  study will  be  performed  to  verify  that 

the development  took place as proposed.   Once  the LOMR  is 

approved  by  FEMA,  the  effective  Flood  Insurance  Rate Map 

(FIRM) is updated on location to reflect the completed project.  

The DIA  shows  that  the proposed development will  cause no 

adverse impacts to the local floodplain and flooding depths. 

A  phasing  analysis was  conducted  as  part  of  the DIA  to  ensure  that  during  construction  no  adverse 

floodplain  impacts  would  occur.    This  is  due  to  the  possibility  that  the  GTL  Project  may  not  be 

constructed coincident with  the LCCP.   The DIA proves  that construction phasing of  the development 

will not cause adverse impacts to surrounding areas.  

 11.0  CONCLUSION  This report details Sasol’s commitment to the Parish, through the completion of its economic, drainage, 

and  traffic  impact analysis.   Sasol will  continue  to work  to ensure  that all  safety, environmental, and 

health  aspects  are met  throughout  the  planning,  construction,  and  implementation  of  the  projects 

described herein.   

This  rezoning  application  details  Sasol’s  request  that  Calcasieu  Parish  rezone  1,470.85  acres  of  Sasol 

owned  property  to  I‐2  Heavy  Industrial.    In  addition  Sasol  is  requesting  that  the  Calcasieu  Parish  – 

Division of Planning and Development complete a feasibility study to rezone approximately 176.52 acres 

of  isolated properties within the overall boundary to I‐2 Heavy Industrial.   Sasol  is also requesting that 

the Parish complete a study to  incorporate the newly rezoned,  I‐2 Heavy  Industrial properties  into the 

existing Lockport Industrial District. 

The accompanying Developer’s Agreement, maps, and legal descriptions also detail Sasol’s further 

commitment to the entities within the area.     

The Drainage Impact Analysis (DIA) shows that the proposed LCCP and

GTL facilities will have no adverse impacts to the

local drainage, floodplain and flooding

depths.

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

29 | P a g e   

  

REFERENCES  

Alliance Transportation Group.  Sasol Lake Charles Ethane Cracker/Gas‐to‐Liquids Project (LCCP/GTL) – 

Traffic Impact Analysis. January 2014. 

NERA Economic Consulting.  Economic Impact Assessment of the Sasol Gas‐to‐Liquids (GTL) Facility on 

the Louisiana and US Economies. November 12, 2013 

NERA Economic Consulting.  Economic Impact Assessment of the Sasol Chemical Facility on the Louisiana 

and US Economies.  November 12, 2013. 

URS Corporation.  Revised Drainage Impact Analysis – Sasol North America, Inc. Westlake Sasol GTL and 

Lake Charles Cracker Westlake, Calcasieu Parish Louisiana.  January 2014. 

   

                             Lake Charles Cracker Project & Gas‐to‐Liquids Project                              Rezoning Application  

30 | P a g e   

  

EXHIBITS  

EXHIBIT 1:  Project Plot Plan 

EXHIBIT 2:  View #1 – Conceptual Rendering of the GTL facility from Houston River Road looking 

Southwest 

EXHIBIT 3:  View #2 – Conceptual Rendering of the LCCP facility from Houston River Road looking 

Southwest 

EXHIBIT 4:  View #3 – Conceptual Rendering of the LCCP facility from Houston River Road looking 

Southwest 

EXHIBIT 5:  View #4 – Conceptual Rendering of the LCCP facility from Old Spanish Trail looking 

Northwest 

EXHIBIT 6:  General location of the renderings views 

EXHIBIT 7:   Existing Zoning Map 

EXHIBIT 8:   Proposed Zoning Map 

EXHIBIT 9:   Final Zoning Map 

EXHIBIT 10:  Proposal for Streets to Remain, Rededicate, and Revoke 

EXHIBIT 11:  Proposed Lockport Industrial District Expansion 

  

 

HoustonRiver Rd

Old Spanish Tr

Eve

rgre

en

Rd

Project Plot Plan

LEGEND

LCCP

Construction Support

LCCP-GTL

GTL

Existing Operations

E BurtonSt

Ev

erg

reen

Rd

VC

MP

lan

tR

d

E Burfton St

Ben

jam

inS

t

Old Spanish Tr

Bo

lsiu

sR

dB

ols

ius

Rd

Ly

on

sA

v

Ben

jam

inS

t

E Burton St

3rd Av

Church St

Ele

ctri

cD

r

E Burton St

E Burton St

Ben

jamin

St

7th Av

Mar

yS

t

Pe

rkin

sA

v

Ma d

iso

nS

t

Mar

yS

t

4th Av

VC

MP

lan

tR

d

Jack

M

oss Rd

Fisher St

Houston

River R

d

3rd Av

Ben

jam

inS

t

Co

ach

Wil

liam

sD

r.

Old Spanish Tr

Bra

xton

LnM

ary

St

VC

MP

lan

tR

d

Old Spanish Tr

Houston River Rd

Old Spanish Tr

Wat

ert

ow

erR

d

Charles Av

Harvey Miller Rd

Ed

wa

rds

St

Fe

rnd

al e

Dr

Murrell Rd

Bel

Air

St

E Burton St

Park St

5th Av

Harvey Miller Rd

Rig

maid

enA

v

Or a

St

Ed

na

Har

dy

Ln

Old Spanish Tr

E Burton St

VC

MP

lan

tR

d

Merlin St

4th Av

Perkins Av

Mitc

hell S

t

Old Spanish Tr

E Burton St

Moss Av

7th Av

Lyons Av

6th Av

Reeves Av

Ind

epen

de

nc

eR

d

5th Av

Pry

or

St

3rd Av

2nd Av

1st St1st St

Center St

2nd Av

Old Spanish Tr

Ced

arS

t

Reeves Av

6th Av

Perkins Av

Moss Av

E Burton St

Houston River Rd

Venable Dr

E Burton St

Pra

ter

Rd

4th Av

Rig

ma

iden

Av

Lin

coln

Av

Pa

ttie

Mo

ssR

d

Ind

epen

de

nc

eR

d

Bre

ntw

oo

dD

r

Ind

epen

de

nc

eR

d

E Burton St

Pra

ter

Rd

5th Av

Smith Rd

JC

lop

hu

sR

dJ

Clo

ph

us

Rd

Goldrich Dr

Orphanage Rd

E Burton St

5th Av

Har

de

yR

d

Tro

us

da

le R

d

Wallace Rd

Goldrich Dr

Old Spanish Tr

Ev

erg

ree n

Rd

John Stine Rd

Verret Rd

HoustonRiver Rd

Old Spanish Tr

Junius Rd

Powell Ln

HoustonRiver Rd

Old Spanish Tr

Evergreen Rd

Evergreen Rd

Evergreen Rd

Houston River Rd

Eve

rgreen Rd

20-2

6-A

20-2

5-B

28-509

20-7

4-B

20-56

28-4

69

20-1

29-1

4

19-2

3

29-1

9

19-22

30-12

29-220

-15

7

19-15

29-2

5

29-4

0

29-4

28-4

35

29-3

28-493

20-1

55

29-7

21-93

29-4

1

19-6

28-4

34

21-3

7

19-1

9

21-4

7-C

29-3

1

28-494

19-2

5

19-2

0

19-16

19-1

8

19-8

30-11

19-2

7

28-512

21-95

30-10

21-44

29-53

19-14

30-13

29-5

21-9

7

19-2

4

29-3

0

19-7

20-150

21-49

29-11

29-29

28-4

31

21-41

19-2

1

29-1

6

29-1

21-42

29-63

19-1

7

28-49729

-56

29-1

8

28-6

89

29-57

29-13

29-42

29-39

29-62

29-1

7

28-687

21-94

29-1

0

29-6

21-39

29-64

19-2

8

20-138

19-5

19-26

21-30

20-28

20-111

21-29

20-1

2

20-24

20-3

1

20-149

20-30

20-147

28-9

5

20-172

20-61

28-1

88

20-35

28-3

22

28-3

89

28-6

32

28-2

87

20-1

56

28-4

30

28-1

10

28-551

28-5

22

28-5

9

28-3

62

28-4

12

28-1

24

28-3

23

28-1

36

21-2

28-2

3

28-3

39

20-1

01

28-6

73

28-1

97

20-17

28-6

96

28-435-A

28-6

31

20-2

21-6

3

28-3

0

29-34

28-1

38

28-3

59

28-456

28-7

11

28-5

67

28-549

28-7

10

28-1

95

28-3

94

28-432-A

28-6

30

28-6

97

21-3

2A

20-127

28-6

66

28-2

65

21-92

28-8

2

28-1

8

21-1

4

21-1

1

28-6

53

28-3

98

28-3

72

28-3

92

20-9

8

28-5

58

29-23

28-6

06

28-1

45

28-7

3

28-2

34

28-4

90

21-54

28-33

21-8

5

28-5

40

28-6

92

17-6

9

28-4

10

21-90

28-2

78

21-46

28-2

9

28-253

20-6

28-3

7

20-85

20-9

28-4

21-26

28-5

028

-60

20-129

16-1

20-9

2

28-6

07

28-6

69

28-1

93

20-160

28-2

64

28-2

80

28-5

31

21-3

5

28-4

99

20-2

9

28-2

31

28-5

68

28-458

28-4

33

28-1

67

28-2

94

28-6

29

28-3

37

20-27

28-1

47

28-298

29-9

28-446

28-6

03

28-3

17

28-492

20-7

28-1

64

28-3

32

28-501

28-76

28-2

95

28-1

99

28-3

9

28-8

4

21-5

28-3

19

28-6

70

28-6

33

28-3

6

21-4

5

28-3

95

28-1

62

28-1

82

28-6

11

28-3

31

20-9

7

28-4

17

20-7

6

28-5

-C

28-143

28-1

7

20-153

28-443

20-134

28-59928-451

21-8

0

29-61

21-7

5

28-5

29

20-87

28-3

14

20-180

28-6

56

28-9

28-5

86

28-3

78

28-4

89

28-3

86

28-2

37

28-5

91

28-3

15

28-5

81

20-90

28-2

30

28-5

64

28-6

42

28-442

28-8

7-B

28-5

05

28-7

03

28-1

31

28-6

6

20-148

21-8

1

20-1

3

28-1

28

28-2

41

21-13

20-5

8

29-44

28-1

44

28-211

28-1

18

28-3

38

28-251

28-3

65

28-3

11

28-545

21-25

28-5

-A

20-1

4

28-1

94

28-449

28-8

9

28-301

28-207

20-86

28-3

46

28-8

1

20-118

28-355

21-18

16-2

28-1

16

21-19

28-247

28-2

23

28-6

13

21-7

3

28-4

71

28-4

32

28-6

08

20-115

28-4

14

28-4

80

21-4

3

28-6

20

28-254

28-142

21-7

2

28-3

4

28-4

98

28-5

32

28-601

20-8

2

28-4

82

28-2

84

28-7

12

20-133

28-225

28-2

2

20-63

21-20

28-1

92

21-8

3

28-6

37

28-6

74

28-7

16

28-6

7

28-1

01

21-6

5

20-1

65

29-2

8

28-2

56

28-5

90

21-6

8

20-77

28-5

63

28-6

75

28-2

00

28-4

5

28-5

53

28-9

3

28-4

21

20-9

6

28-1

11

21-1

5

28-1

32

28-252

28-1

68

28-5

92

28-6

41

29-33

28-3

27

28-452

20-122

20-8

3

28-3

88

29-49

28-6

98

28-1

55

2 8-1

23

20-1

54

28-6

76

29-45

20-169

20-64

28-3

96

28-2

71

21-8

28-5

72

28-6

48

28-3

21

28-2

42

28-5

73

28-4

0

28-6

78

28-5

75

28-6

28

28-5

76

28-7

00

28-3

09

28-598

28-4

72

28-1

48

28-9

6

28-5

89

21-12

28-5

33

20-78

28-5

78

28-4

27

20-1

73

28-6

79

28-444

20-88

28-3

18

29-3

5

28-7

06

28-1

56

28-2

24

28-4

81

28-548

28-5

83

28-3

16

28-352

28-1

84

28-4

38

28-3

69

21-51

28-5

62

28-688

28-487

28-6

09

28-2

90

28-1

02

21-6

6

28-6

93

21-3

8

28-6

12

28-4

18

28-6

55

28-4

39

28-1

00

20-175

28-5

41

28-6

22

28-5

66

28-2

67

21-1

29-37

28-3

5

28-1

13

28-5

60

20-1

0

29-36

28-6

59

20-113

28-6

50

28-2

86

21-21

28-9

9

28-3

58

29-6

7

28-3

71

28-6

54

28-3

08

28-6

72

28-544

28-3

30

28-6

14

20-22

28-1

96

29-26

28-1

74

28-3

06

20-80

28-6

35

20-4

6

21-61

20-4

7-A

20-1

05-

B28-461

20-59

20-112

28-9

2

28-297

28-2

77

28-2

91

28-3

44

20-5

5

28-1

08

21-64

20-106

28-8

0

28-2

75

21-52

28-1

4

28-485

21-6

7

28-2

03

21-7

4

28-5

6

28-3

74

20-1

44

21-78

21-7

6

20-6

9

28-2

5

21-57

29-58

28-300

20-48-B

20-1

41

20-60

28-2

59

20-104

20-49

28-407

28-453

28-455

21-23

28-3

40

20-7

0

20-125

20-75

28-3

66

28-1

51

28-3

60

28-7

07

28-6

65

20-109

28-1

53

29-12

28-5

8

21-8

7

20-1

42

28-351

28-6

64

28-3

33

20-9

3

28-8

7-A

20-102

28-6

68

28-476

28-1

17

29-50

28-1

29

21-96

28-6

44

28-4

20

28-2

60

28-5

00

28-478

28-5

4

28-3

73

28-1

06

20-42

28-1

49

28-433-A

28-594

28-7

15

28-208

28-3

24

28-488

28-450

29-60

28-213

28-209

20-171

28-2

8

28-6

17

28-2

55

28-7

9

28-3

93

28-2

70

20-5

28-1

05

21-8

8

28-2

04

28-1

5

28-4

15

28-2

69

28-6

38

28-2

72

28-3

75

28-475

28-2

46

28-6

86

29-22

28-2

43

28-4

25

28-6

9

28-1

81

28-5

23

28-6

4

28-248

28-1

70

28-5

52

29-15

28-6

67

28-6

34

28-5

37

28-6

05

28-2

74

28-1

66

20-1

30

28-299

28-2

02

28-5

61

28-6

49

28-431-A

28-1

21

20-126

20-163

28-1

20

28-404

20-7

1

28-3

63

28-3

8

28-350

28-2

4

28-6

45

28-3

35

28-6

80

28-7

1

29-8

29-52

28-400

28-2

40

28-6

83

28-486

20-1

31

29-27

21-9

28-4

3

28-6

10

28-8

5

28-6

52

28-5

87

28-484

28-3

12

28-8

3

28-1

09

28-5

2

20-117

28-77

28-4

36

28-3

68

28-5

70

20-19

28-6

91

20-124

28-600

28-459

28-4

26

28-503

28-4

7

28-303

21-31

28-4

16

28-1

46

28-5

93

28-3

80

28-1

26

29-59

28-3

90

28-2

0

21-3

3

20-4

4

28-496

28-2

57

28-2

36

28-1

98

28-6

27

20-119

28-6

62

21-7

20-8

28-3

47

28-1

85

20-89

20-152

28-596

21-16

28-4

64

28-5

65

28-3

29

28-1

0

28-1

65

28-1

77

20-182

28-2

58

28-2

66

20-53

28-3

26

28-3

36

28-3

87

28-5

79

28-2

88

28-3

07

28-2

61

28-2

1

29-4

3

28-5

3

29-51

28-447

20-1

40

28-2

79

28-401

28-5

04

28-228

28-6

8

28-2

21

20-164

20-38

28-1

83

28-2

39

28-1

6

28-448

28-6

16

28-3

2

21-24

28-7

09

20-146

29-32

28-4

91

20-120

28-2

35

28-3

61

28-5

28

21-8

2

21-4

0

28-3

42

21-50

28-4

8

20-91

28-7

4

28-3

99

20-1

66

28-7

14

28-6

25

28-5

38

28-547

28-2

28-353

28-7

28-6

04

21-59

28-302

28-4

09

28-6

84

20-23

28-3

43

28-1

57

28-5

59

20-159

28-7

02

28-1

2

28-6

61

20-1

5

28-210

21-4

28-4

68

28-5

36

28-3

20

28-6

51

28-1

71

28-2

45

28-141

28-8

22-9

28-6

21-58

20-151

28-5

30

28-6

18

28-4

29

28-445

28-6

5

29-5

4

28-1

1

28-3

13

20-6

8

28-1

72

28-5

80

28-3

83

29-47

28-3

25

28-402

28-5

34

28-3

97

20-1

28

28-5

39

28-3

34

28-2

68

28-3

82

28-2

7

20-1

00

28-1

80

28-1

73

28-7

08

28-2

63

28-6

82

28-2

44

20-176

28-6

81

20-4

20-39

28-5

69

28-4

37

28-595

29-24

28-1

78

21-5

3

28-406

28-460

20-81

20-1

70

28-4

2

28-5

25

28-4

9

28-348

28-1

87

21-8

6

28-7

13

28-6

39

28-6

99-

A

28-6

1

28-2

73

28-1

50

28-3

91

21-77

28-5

88

28-7

17

20-4

5

28-249

28-1

75

28-1

22

28-1

19

20-3

4

28-3

79

28-7

01

21-3

6

28-7

04

28-2

33

20-1

39

21-8

4

21-1

0

28-436-A

28-5

1

28-3

81

28-6

19

28-3

57

20-1

79

28-6

47

28-2

93

28-1

03

28-6

85

20-40

28-502

28-2

83

21-17

28-1

61

28-349

28-1

59

28-5

24

28-483

28-5

56

28-5

27

28-8

6

28-1

3

28-2

32

28-4

11

28-5

85

28-507

28-546

28-3

41

21-6

2

28-3

56

21-6

28-2

29

21-47

28-1

58

28-1

27

28-4

6

28-405

20-137

28-5

28-477

28-2

89

28-4

62

29-20

28-440

28-5

5

28-2

22

20-50

28-5

43

28-2

01

28-5

-B

28-4

19

28-474

20-116

28-78

29-38

28-5

57

28-1

60

28-1

25

20-103

28-597

20-108

28-1

79

28-7

2

28-4

4

20-7

2

21-7

1

20-1

81

28-354

28-3

1

28-1

35

28-441

28-1

12

20-9

4

28-1

39

28-1

04

28-1

14

28-3

67

21-6

9

20-1

45-

B

28-4

63

28-6

58

28-1

34

28-140

21-7

9

28-6

60

28-1

15

28-1

89

28-6

24

20-6

7

28-1

76

20-2

1

28-1

54

20-178

20-9

5

20-3

3

28-6

2

28-5

26

28-3

28

20-168

21-89

28-206

20-62

28-434-A

29-6

8

21-4

A

20-1

36

20-66

28-3

05

20-1

61

28-5

-D

21-28

20-65

21-48

28-511

20-9

9

20-177

28-6

63

29-65

28-4

67

28-6

15

28-1

33

20-37

28-2

6

28-1

52

28-403

28-1

9

28-6

21

20-43

28-5

74

28-2

85

28-212

29-21

29-6

6

20-114

28-1

90

28-304

28-6

77

28-2

92

20-84

21-56

28-6

23

28-3

21-70

28-7

0

20-36

28-250

28-5

55

20-7

3

28-3

85

28-2

81

28-1

69

28-454

20-123

20-121

28-1

-A

28-3

64

28-6

3

28-4

1

28-6

71

20-52

28-1

37

28-6

26

28-6

95

20-54

28-6

02

20-1

1

20-5

7

28-457

21-3

20-162

28-5

35

28-227

28-6

46

28-1

30

28-1

91

20-41

28-506

28-3

84

28-2

38

28-1

07

28-2

62

28-4

22

28-5

42

28-479

20-20

20-174

20-1

6

28-4

08

21-4

7-B

-1

28-226

28-6

90

20-132

28-9

4

28-5

84

28-1

86

20-110

28-2

82

28-2

05

28-4

66

28-6

57

28-470

28-5

71

21-32

28-5

7

28-3

70

20-1

58

28-4

24

20-3

-B

28-2

20

20-107

28-2

76

28-2

96

28-3

10

28-3

45

20-3

2

28-6

43

28-5

77

28-4

13

28-8

8

28-9

0

28-5

82

28-7

05

28-4

23

28-9

1

28-6

36

28-6

40

28-9

8

20-1

43

20-7

9

28-550

21-91

21-27

20-51

21-60

29-48

28-9

728

-16

3

21-55

28-5

54

28-4

65

28-6

94

28-75

28-4

73

29-55

20-18

20-167

20-135

21-4

7-B

21-22

20-4

7

20-4

6-A

20-7

4-A

20-1

05-

A

21-47-B

21-4

7- C

20-2

6-B

20-2

5-A

28-4

69-

A

20-3

-A

20-48-A

28-1

28-6

99-

B

21-4

7-A

19-1

7

20-145-A

20-145-C

21-34

This map shows existing Calcasieu Parish zoning

CURRENT AS OF FEBRUARY 10, 2014

Legend

Overall Rezoning Boundary

Parcel Lines

(a1) Agricultural

(c1) Light Commercial

(c2) General Commercial

(c3) Central Business Commercial

(city) Zoned by Local Municipality

(i1) Light Industrial

(i2) Heavy Industrial

(i2r) Heavy Industrial Restricted

(r1) Single Family Residential

(r2) Mixed Residential

(rm) Multi-Family Residential

(rmhp) Manufactured Home ParkExisting Zoning

Old Spanish Tr

Ben

jam

inS

t

VC

MP

l an

tR

d

Merlin St

Bo

lsiu

sR

d

Ly on

sA

v

Ma

di s

on

St

3rd Av

Church St

Rig

ma

ide

nA

v

Ele

ctr

icD

r

7th Av

Ma

ryS

t

4th Av

Fisher St

HoustonRiver Rd

Fe

rnd

al e

Dr

Bra

xton

Ln

Charles Av

Wat

ert

ow

erR

d

Harvey Miller Rd

Murrell Rd

Be

lAir

St

E Burton St

5th Av

Ora

St

Moss Av

6th AvIn

dep

en

de

nc

eR

d

Pry

or

St

2nd Av

1st St

Center St

Venable Dr

Pra

ter

Rd

Bre

ntw

oo

dD

r

Lin

col n

Av

Sm

ith

Rd

Goldrich Dr

Pa

ttie

Mo

ssR

d

Har

de

yR

d

Ver

ret

Rd

John Stine Rd

Ev

erg

reen

Rd

Perkins Av

Jack MossR

d

Ed

wa

rds

St

Ed

na

Ha

rdy

Ln

Mit

ch

ellS

tCed

ar S

t

Co

ach

Will

iam

sD

r.J

Clo

ph

us

Rd

Orp

han

age

Rd

Tro

us

da

leR

d

Ju

niusRd

Powell Ln

Park St

Reeves Av

Wallace Rd

21-34

20-2

6-A

20-2

5-B

28-509

20-7

4-B

20-56

28-4

69

20-1

29-1

4

19-2

3

29-1

9

19-22

30-12

29-2

20-1

57

19-15

29-2

5

29-4

0

29-4

28-4

35

29-3

28-493

20-1

55

29-7

21-93

29-4

1

19-6

28-4

34

21-3

7

19-1

9

21-4

7-C

29-3

1

28-494

19-2

5

19-2

0

19-16

19-1

8

19-8

30-11

19-2

7

28-512

21-95

30-10

21-44

29-53

19-14

30-1

3

29-5

21-9

7

19-2

4

29-3

0

19-7

20-150

21-49

29-11

29-29

28-4

31

21-41

19-2

1

29-1

629-1

21-42

29-63

19-1

7

28-497

29-5

6

29-1

8

28-6

89

29-57

29-13

29-42

29-39

29-62

29-1

7

28-687

21-94

29-1

0

29-6

21-39

29-64

19-2

8

20-138

19-5

19-26

21-30

20-28

20-111

21-29

20-1

2

20-24

20-3

1

20-149

20-30

20-147

28-9

5

20-172

20-61

28-1

88

20-35

28-3

22

28-3

89

28-6

32

28-2

87

20-1

56

28-4

30

28-1

10

28-551

28-5

22

28-5

9

28-3

62

28-4

12

28-1

24

28-3

23

28-1

36

21-2

28-2

3

28-3

39

20-1

01

28-6

73

28-1

97

20-17

28-6

96

28-435-A

28-6

31

20-2

21-6

3

28-3

0

29-34

28-1

38

28-3

59

28-456

28-7

11

28-5

67

28-549

28-7

10

28-1

95

28-3

94

28-432-A

28-6

30

28-6

97

21-3

2A

20-127

28-6

66

28-2

65

21-92

28-8

2

28-1

8

21-1

4

21-1

1

28-6

53

28-3

98

28-3

72

28-3

92

20-9

8

28-5

58

29-23

28-6

06

28- 1

45

28-7

3

28-2

34

28-4

90

21-54

28-33

21-8

5

28-5

40

28-6

92

17-6

9

28-4

10

21-90

28-2

78

21-46

28-2

9

28-253

20-6

28-3

7

20-85

20-9

28-4

21-26

28-5

028

-60

20-129

16-1

20-9

2

28-6

07

28-6

69

28-1

93

20-160

28-2

64

28-2

80

28-5

31

21-3

5

28-4

99

20-2

9

28-2

31

28-5

68

28-458

28-4

33

28-1

67

28-2

94

28-6

29

28-3

37

20-27

28-1

47

28-298

29-9

28-446

28-6

03

28-3

17

28-492

20-7

28-1

64

28-3

32

28-501

28-76

28-2

95

28-1

99

28-3

9

28-8

4

21-5

28-3

19

28-6

70

28-6

33

28-3

6

21-4

5

28-3

95

28-1

62

28-1

82

28-6

11

28-3

31

20-9

7

28-4

17

20-7

6

28-5

-C

28-143

28-1

7

20-153

28-443

20-134

28-59928-451

21-8

0

29-61

21-7

5

2 8-5

29

20-87

28-3

14

20-180

28-6

56

28-9

28-5

86

28-3

78

28-4

89

28-3

86

28-2

37

28-5

91

28-3

15

28-5

81

20-90

28-2

30

28-5

64

28-6

42

28-442

28-8

7-B

28-5

05

28-7

03

28-1

31

28-6

6

20-148

21-8

1

20-1

3

28-1

28

28-2

41

21-13

20-5

8

29-44

28-1

44

28-211

28-1

18

28-3

38

28-251

28-3

65

28-3

11

28-545

21-25

28-5

-A

20-1

4

28-1

94

28-449

28-8

9

28-301

28-207

20-86

28-3

46

28-8

1

20-118

28-355

21-18

16-2

28-1

16

21-19

28-247

28-2

23

28-6

13

21-7

3

28-4

71

28-4

32

28-6

08

20-115

28-4

14

28-4

80

21-4

3

28-6

20

28-254

28-142

21-7

2

28-3

4

28-4

98

28-5

32

28-601

20-8

2

28-4

82

28-2

84

28-7

12

20-133

28-225

28-2

2

20-63

21-20

28-1

92

21-8

3

28-6

37

28-6

74

28-7

16

28-6

7

28-1

01

21-6

5

20-1

65

29-2

8

28-2

56

2 8-5

90

21-6

8

20-77

28-5

63

28-6

75

28-2

00

28-4

5

28-5

53

28-9

3

28-4

21

20-9

6

28-1

11

21-1

5

28-1

32

28-252

28-1

68

28-5

92

28-6

41

29-33

28-3

27

28-452

20-122

20-8

3

28-3

88

29-49

28-6

98

28-1

55

28-1

23

20-1

54

2 8-6

76

29-45

20-169

20-64

28-3

96

28-2

71

21-8

28-5

72

28-6

48

28-3

21

28-2

42

28-5

73

28-4

0

28-6

78

28-5

75

28-6

28

2 8-5

76

28-7

00

28-3

09

28-598

28-4

72

28-1

48

28-9

6

28-5

89

21-12

28-5

33

20-78

28-5

78

28-4

27

20-1

73

28-6

79

28-444

20-88

28-3

18

29-3

5

28-7

06

2 8-1

56

28-2

24

28-4

81

28-548

28-5

83

28-3

16

28-352

28-1

84

28-4

38

28-3

69

21-51

28-5

62

28-688

28-487

28-6

09

28-2

90

28-1

02

21-6

6

28-6

93

21-3

8

28-6

12

28-4

18

28-6

55

28-4

39

28-1

00

20-175

28-5

41

28-6

22

28-5

66

28-2

67

21-1

29-37

28-3

5

28-1

13

28-5

60

20-1

0

29-36

28-6

59

20-113

28-6

50

2 8-2

86

21-21

28-9

9

28-3

58

29-6

7

28-3

71

28-6

54

28-3

08

28-6

72

28-544

28-3

30

28-6

14

20-22

28-1

96

29-26

28-1

74

28-3

06

20-80

28-6

35

20-4

6

21-61

20-4

7-A

20-1

05

-B

28-461

20-59

20-112

28-9

2

28-297

28-2

77

28-2

91

28-3

44

20-5

5

28-1

08

21-64

20-106

28-8

0

28-2

75

21-52

28-1

4

28-485

21-6

7

28-2

03

21-7

4

28-5

6

28-3

74

20-1

44

21-78

21-7

6

20-6

9

28-2

5

21-57

29-58

28-300

20-48-B

20-1

41

20-60

28-2

59

20-104

20-49

28-407

28-453

28-455

21-23

28-3

40

20-7

0

20-125

20-75

28-3

66

28-1

51

28-3

60

28-7

07

28-6

65

20-109

28-1

53

29-12

28-5

8

21-8

7

20-1

42

28-351

28-6

64

28-3

33

20-9

3

28-8

7-A

20-102

28-6

68

28-476

28-1

17

29-50

28-1

29

21-96

28-6

44

28-4

20

28-2

60

28-5

00

28-478

28-5

4

28-3

73

28-1

06

20-42

28-1

49

28-433-A

28-594

28-7

15

28-208

28-3

24

28-488

28-450

29-60

28-213

28-209

20-171

28-2

8

28-6

17

28-2

55

28-7

9

28-3

93

28-2

70

20-5

28-1

05

21-8

8

28-2

04

28-1

5

28-4

15

28-2

69

28-6

38

28-2

72

28-3

75

28-475

28-2

46

28-6

86

29-22

28-2

43

28-4

25

28-6

9

28-1

81

28-5

23

28-6

4

28-248

28-1

70

28-5

52

29-15

28-6

67

28-6

34

28-5

37

28-6

05

28-2

74

28-1

66

20-1

30

28-299

28-2

02

28-5

61

28-6

49

28-431-A

28-1

21

20-126

20-163

28-1

20

28-404

20-7

1

28-3

63

28-3

8

28-350

28-2

4

28-6

45

28-3

35

28-6

80

28-7

1

29-8

29-52

28-400

28-2

40

28-6

83

28-486

20-1

31

29-27

21-9

28-4

3

28-6

10

28-8

5

28-6

52

28-5

87

28-484

28-3

12

28-8

3

28-1

09

28-5

2

20-117

28-77

28-4

36

28-3

68

28-5

70

20-19

28-6

91

20-124

28-600

28-459

28-4

26

28-503

28-4

7

28-303

21-31

28-4

16

28-1

46

28-5

93

28-3

80

28-1

26

29-59

28-3

90

28-2

0

21-3

3

20-4

4

28-496

28-2

57

28-2

36

28-1

98

28-6

27

20-119

28-6

62

21-7

20-8

28-3

47

28-1

85

20-89

20-152

28-596

21-16

28-4

64

28-5

65

28-3

29

28-1

0

2 8-1

65

28-1

77

20-182

28-2

58

28-2

66

20-53

28-3

26

28-3

36

28-3

87

28-5

79

28-2

88

28-3

07

28-2

61

28-2

1

29-4

3

28-5

3

29-51

28-447

20-1

40

28-2

79

28-401

28-5

04

28-228

28-6

8

28-2

21

20-164

20-38

28-1

83

2 8-2

39

28-1

6

28-448

28-6

16

28-3

2

21-24

28-7

09

20-146

29-32

28-4

91

20-120

28-2

35

28-3

61

28-5

28

21-8

2

21-4

0

28-3

42

21-50

28-4

8

20-91

28-7

4

28-3

99

20-1

66

28-7

14

28-6

25

2 8-5

38

28-547

28-2

28-353

28-7

28-6

04

21-59

28-302

28-4

09

28-6

84

20-23

28-3

43

28-1

57

28-5

59

20-159

28-7

02

28-1

2

28-6

61

20-1

5

28-210

21-4

28-4

68

28-5

36

28-3

20

28-6

51

28-1

71

28-2

45

28-141

28-8

22-9

28-6

21-58

20-151

28-5

30

28-6

18

28-4

29

28-445

28-6

5

29-5

4

28-1

1

28-3

13

20-6

8

28-1

72

2 8-5

80

28-3

83

29-4

7

28-3

25

28-402

28-5

34

28-3

97

20-1

28

28-5

39

28-3

34

28-2

68

28-3

82

28-2

7

20-1

00

28-1

80

28-1

73

28-7

08

28-2

63

28-6

82

28-2

44

20-176

28-6

81

20-4

20-39

28-5

69

28-4

37

28-595

29-24

28-1

78

21-5

3

28-406

28-460

20-81

20-1

70

28-4

2

28-5

25

28-4

9

28-348

28-1

87

21-8

6

28-7

13

28-6

39

28-6

99

-A

28-6

1

28-2

73

28-1

50

28-3

91

21-77

28-5

88

28-7

17

20-4

5

28-249

28-1

75

28-1

22

28-1

19

20-3

4

28-3

79

28-7

01

21-3

6

28-7

04

28-2

33

20-1

39

21-8

4

21-1

0

28-436-A

28-5

1

28-3

81

28-6

19

28-3

57

20-1

79

28-6

47

28-2

93

28-1

03

28-6

85

20-40

28-502

28-2

83

21-17

28-1

61

28-349

28-1

59

28-5

24

28-483

28-5

56

28-5

27

28-8

6

28-1

3

28-2

32

28-4

11

28-5

85

28-507

28-546

28-3

41

21-6

2

28-3

56

21-6

28-2

29

21-47

28-1

58

28-1

27

28-4

6

28-405

20-137

28-5

28-477

28-2

89

28-4

62

29-20

28-440

28-5

5

28-2

22

20-50

28-5

43

28-2

01

28-5

-B

28-4

19

28-474

20-116

28-78

29-38

28-5

57

28-1

60

28-1

25

20-103

28-597

20-108

28-1

79

28-7

2

28-4

4

20-7

2

21-7

1

20-1

81

28-354

28-3

1

28-1

35

28-441

28-1

12

20-9

4

28-1

39

28-1

04

28-1

14

28-3

67

21-6

9

20-1

45

-B

28-4

63

28-6

58

28-1

34

28-140

21-7

9

28-6

60

28-1

15

28-1

89

28-6

24

20-6

7

28-1

76

20-2

1

28-1

54

20-178

20-9

5

20-3

3

28-6

2

28-5

26

28-3

28

20-168

21-89

28-206

20-62

28-434-A

29-6

8

21-4

A

20-1

36

20-66

28-3

05

20-1

61

28-5

-D

21-28

20-65

21-48

28-511

20-9

9

20-177

28-6

63

29-65

28-4

67

28-6

15

28-1

33

20-37

28-2

6

28-1

52

28-403

28-1

9

28-6

21

20-43

28-5

74

28-2

85

28-212

29-21

29-6

6

20-114

28-1

90

28-304

28-6

77

28-2

92

20-84

21-56

28-6

23

28-3

21-70

28-7

0

20-36

28-250

28-5

55

20-7

3

28-3

85

28-2

81

28-1

69

28-454

20-123

20-121

28-1

-A

28-3

64

28-6

3

28-4

1

28-6

71

20-52

28-1

37

28-6

26

28-6

95

20-54

28-6

02

20-1

1

20-5

7

28-457

21-3

20-162

28-5

35

28-227

28-6

46

28-1

30

28-1

91

20-41

28-506

28-3

84

28-2

38

28-1

07

28-2

62

28-4

22

28-5

42

28-479

20-20

20-174

20-1

6

28-4

08

21-4

7-B

-1

28-226

28-6

90

20-132

28-9

4

28-5

84

28-1

86

20-110

28-2

82

28-2

05

28-4

66

28-6

57

28-470

28-5

71

21-32

28-5

7

28-3

70

20-1

58

28-4

24

20-3

-B

28-2

20

20-107

28-2

76

28-2

96

28-3

10

28-3

45

20-3

2

28-6

43

28-5

77

28-4

13

2 8-8

8

28-9

0

28-5

82

28-7

05

28-4

23

28-9

1

28-6

36

2 8-6

40

28-9

8

20-1

43

20-7

9

28-550

21-91

21-27

20-51

21-60

29-4

8

28-9

728

-16

3

21-55

28-5

54

28-4

65

28-6

94

28-75

28-4

73

29-55

20-18

20-167

20-135

21-4

7-B

21-22

20-4

7

20-4

6-A

20-7

4-A

20-1

05

-A

21-47-B

21-4

7-C

20-2

6-B

20-2

5-A

28-4

69

-A

20-3

-A

20-48-A

28-1

28-6

99

-B

21-4

7-A

19-1

7

20-145-A

20-145-C

Legend

Overall Rezoning Boundary

To Be Rezoned As Part Of This Application - (i2) Heavy Industrial

To Be Rezoned By Parish Through Feasibility Study - (i2) Heavy Industrial Proposed Zoning

This map shows proposed areas to be rezoned i2_Heavy Industrial

8thAv

E Burfton St

Bo

lsiu

sR

d

Church St

Mic

hig

an

Av

Ma

dis

on

St

Fe

rnd

ale

Dr

Fisher St

Be

nja

min

St B

rax

ton

LnM

ary

St

Wa

tert

ow

er

Rd

Charles Av

JackMoss Rd

Ed

wa

rds

St

Murrell Rd

Be

lAir

St

Park St

Harvey Miller Rd

Ora

St

Ed

na

Ha

rdy

Ln

VC

MP

lan

tR

d

Merlin St

Mitch

ell St

7th Av

Lyons Av

Pry

or

St

3rd Av

1st St

Center St

2nd Av

Ce

da

rS

t

Reeves Av

6th Av

Perkins Av

Co

ac

hW

illi

am

sD

r.

Moss Av

Venable Dr

Bre

ntw

oo

dD

r

4th Av

Rig

ma

ide

nA

v

Li n

co

lnA

v

Ind

ep

en

de

nc

eR

d

Smith Rd

Junius Rd

JC

lop

hu

sR

d

Orphanage Rd

Pa

ttie

Mo

ss

Rd

E Burton St

5th Av

Ha

rde

yR

d

Pra

ter

Rd

Wallace Rd

Goldrich Dr

Tro

us

da

leR

d

Verret Rd

Powell Ln

John Stine Rd

Old Spanish Tr

Houston River Rd

Eve

rgreen Rd

21-34

20-2

6-A

20-2

5-B

28-509

20-7

4-B

20-56

28-4

69

20-1

29-1

4

19-2

3

29-1

9

19-22

30-12

29-2

20-1

57

19-15

29-2

5

29-4

0

29-4

28-4

35

29-3

28-493

20-1

55

29-7

21-93

29-4

1

19-6

28-4

34

21-3

7

19-1

9

21-4

7-C

29-3

1

28-494

19-2

5

19-2

0

19-16

19-1

8

19-8

30-11

19-2

7

28-512

21-95

30-10

21-44

29-53

19-14

30-13

29-5

21-9

7

19-2

4

29-3

0

19-7

20-150

21-49

29-11

29-29

28-4

31

21-41

19-2

1

29-1

629-1

21-42

29-63

19-1

7

28-497

29-5

6

29-1

8

28-6

89

29-57

29-13

29-42

29-39

29-62

29-1

7

28-687

21-94

29-1

0

29-6

21-39

29-64

19-2

8

20-138

19-5

19-26

21-30

20-28

20-111

21-29

20-1

2

20-24

20-3

1

20-149

20-30

20-147

28-9

5

20-172

20-61

28-1

88

20-35

28-3

22

28-3

89

28-6

32

28-2

87

20-1

56

28-4

30

28-1

10

28-551

28-5

22

28-5

9

28-3

62

28-4

12

28-1

24

28-3

23

28-1

36

21-2

28-2

3

28-3

39

20-1

01

28-6

73

28-1

97

20-17

28-6

96

28-435-A

28-6

31

20-2

21-6

3

28-3

0

29-34

28-1

38

28-3

59

28-456

28-7

11

28-5

67

28-549

28-7

10

28-1

95

28-3

94

28-432-A

28-6

30

28-6

97

21-3

2A

20-127

28-6

66

28-2

65

21-92

28-8

2

28-1

8

21-1

4

21-1

1

28-6

53

28-3

98

28-3

72

28-3

92

20-9

8

28-5

58

29-23

28-6

06

28-1

45

28-7

3

28-2

34

28-4

90

21-54

28-33

21-8

5

28-5

40

28-6

92

17-6

9

28-4

10

21-90

28-2

78

21-46

28-2

9

28-253

20-6

28-3

7

20-85

20-9

28-4

21-26

28-5

028

-60

20-129

16-1

20-9

2

28-6

0728

-669

28-1

93

20-160

28-2

64

28-2

80

28-5

31

21-3

5

28-4

99

20-2

9

28-2

31

28-5

68

28-458

28-4

33

28-1

67

28-2

94

28-6

29

28-3

37

20-27

28-1

47

28-298

29-9

28-446

28-6

03

28-3

17

28-492

20-7

28-1

64

28-3

32

28-501

28-76

28-2

95

28-1

99

28-3

9

28-8

4

21-5

28-3

19

28-6

70

28-6

33

28-3

6

21-4

5

28-3

95

28-1

62

28-1

82

28-6

11

28-3

31

20-9

7

28-4

17

20-7

6

28-5

-C

28-143

28-1

7

20-153

28-443

20-134

28-59928-451

21-8

0

29-61

21-7

5

28-5

29

20-87

28-3

14

20-180

28-6

56

28-9

28-5

86

28-3

78

28-4

89

28-3

86

28-2

37

28-5

91

28-3

15

28-5

81

20-90

28-2

3028

-564

28-6

42

28-442

28-8

7-B

28-5

05

28-7

03

28-1

31

28-6

6

20-148

21-8

1

20-1

3

28-1

28

28-2

41

21-13

20-5

8

29-44

28-1

44

28-211

28-1

18

28-3

38

28-251

28-3

65

28-3

11

28-545

21-25

28-5

-A

20-1

4

28-1

94

28-449

28-8

9

28-301

28-207

20-86

28-3

46

28-8

1

20-118

28-355

21-18

16-2

28-1

16

21-19

28-247

28-2

23

28-6

13

21-7

3

28-4

71

28-4

32

28-6

08

20-115

28-4

14

28-4

80

21-4

3

28-6

20

28-254

28-142

21-7

2

28-3

4

28-4

98

28-5

32

28-601

20-8

2

28-4

82

28-2

84

28-7

12

20-133

28-225

28-2

2

20-63

21-20

28-1

92

21-8

3

28-6

3728

-674

28-7

16

28-6

7

28-1

01

21-6

5

20-1

65

29-2

8

28-2

56

28-5

90

21-6

8

20-77

28-5

63

28-6

75

28-2

00

28-4

5

28-5

53

28-9

3

28-4

21

20-9

6

28-1

11

21-1

5

28-1

32

28-252

28-1

68

28-5

92

28-6

41

29-33

28-3

27

28-452

20-122

20-8

3

28-3

88

29-49

28-6

98

28-1

55

28-1

23

20-1

54

28-6

76

29-45

20-169

20-64

28-3

96

28-2

71

21-8

28-5

72

28-6

48

28-3

21

28-2

42

28-5

73

28-4

0

28-6

78

28-5

75

28-6

28

28-5

76

28-7

00

28-3

09

28-598

28-4

72

28-1

48

28-9

6

28-5

89

21-12

28-5

33

20-78

28-5

78

28-4

27

20-1

73

28-6

79

28-444

20-88

28-3

18

29-3

5

28-7

06

28-1

56

28-2

24

28-4

81

28-548

28-5

83

28-3

16

28-352

28-1

84

28-4

38

28-3

69

21-51

28-5

62

28-688

28-487

28-6

09

28-2

90

28-1

02

21-6

6

28-6

93

21-3

8

28-6

12

28-4

1828

-655

28-4

39

28-1

00

20-175

28-5

41

28-6

22

28-5

66

28-2

67

21-1

29-37

28-3

5

28-1

13

28-5

60

20-1

0

29-36

28-6

59

20-113

28-6

50

28-2

86

21-21

28-9

9

28-3

58

29-6

7

28-3

71

28-6

54

28-3

08

28-6

72

28-544

28-3

30

28-6

14

20-22

28-1

96

29-26

28-1

74

28-3

06

20-80

28-6

35

20-4

6

21-61

20-4

7-A

20-1

05-B

28-461

20-59

20-112

28-9

2

28-297

28-2

77

28-2

91

28-3

44

20-5

5

28-1

08

21-64

20-106

28-8

0

28-2

75

21-52

28-1

4

28-485

21-6

7

28-2

03

21-7

4

28-5

6

28-3

74

20-1

44

21-78

21-7

6

20-6

9

28-2

5

21-57

29-58

28-300

20-48-B

20-1

41

20-60

28-2

59

20-104

20-49

28-407

28-453

28-455

21-23

28-3

40

20-7

0

20-125

20-75

28-3

66

28-1

51

28-3

60

28-7

07

28-6

65

20-109

28-1

53

29-12

28-5

8

21-8

7

20-1

42

28-351

28-6

64

28-3

33

20-9

3

28-8

7-A

20-102

28-6

68

28-476

28-1

17

29-50

28-1

29

21-96

28-6

44

28-4

20

28-2

60

28-5

00

28-478

28-5

4

28-3

73

28-1

06

20-42

28-1

49

28-433-A

28-594

28-7

15

28-208

28-3

24

28-488

28-450

29-60

28-213

28-209

20-171

28-2

8

28-6

17

28-2

55

28-7

9

28-3

93

28-2

70

20-5

28-1

05

21-8

8

28-2

0428

-15

28-4

15

28-2

69

28-6

38

28-2

7228

-375

28-475

28-2

4628

-686

29-22

28-2

43

28-4

25

28-6

9

28-1

81

28-5

23

28-6

4

28-248

28-1

70

28-5

52

29-15

28-6

67

28-6

34

28-5

37

28-6

05

28-2

74

28-1

66

20-1

30

28-299

28-2

02

28-5

61

28-6

49

28-431-A

28-1

21

20-126

20-163

28-1

20

28-404

20-7

1

28-3

63

28-3

8

28-350

28-2

4

28-6

4528

-335

28-6

80

28-7

1

29-8

29-52

28-400

28-2

4028

-683

28-486

20-1

3129-27

21-9

28-4

3

28-6

10

28-8

5

28-6

52

28-5

87

28-484

28-3

12

28-8

3

28-1

09

28-5

2

20-117

28-77

28-4

36

28-3

68

28-5

70

20-19

28-6

91

20-124

28-600

28-459

28-4

26

28-503

28-4

7

28-303

21-31

28-4

16

28-1

46

28-5

93

28-3

80

28-1

26

29-59

28-3

90

28-2

0

21-3

3

20-4

4

28-496

28-2

57

28-2

36

28-1

98

28-6

27

20-119

28-6

62

21-7

20-8

28-3

47

28-1

85

20-89

20-152

28-596

21-16

28-4

64

28-5

65

28-3

29

28-1

0

28-1

65

28-1

77

20-182

28-2

58

28-2

66

20-53

28-3

26

28-3

36

28-3

87

28-5

79

28-2

88

28-3

07

28-2

61

28-2

1

29-4

3

28-5

3

29-51

28-447

20-1

40

28-2

79

28-401

28-5

04

28-228

28-6

8

28-2

21

20-164

20-38

28-1

83

28-2

39

28-1

6

28-448

28-6

16

28-3

2

21-24

28-7

09

20-146

29-32

28-4

91

20-120

28-2

35

28-3

61

28-5

28

21-8

2

21-4

0

28-3

42

21-50

28-4

8

20-91

28-7

4

28-3

99

20-1

66

28-7

14

28-6

25

28-5

38

28-547

28-2

28-353

28-7

28-6

04

21-59

28-302

28-4

09

28-6

84

20-23

28-3

43

28-1

57

28-5

59

20-159

28-7

02

28-1

2

28-6

61

20-1

5

28-210

21-4

28-4

68

28-5

36

28-3

20

28-6

51

28-1

71

28-2

45

28-141

28-8

22-9

28-6

21-58

20-151

28-5

30

28-6

1828-4

29

28-445

28-6

5

29-5

4

28-1

1

28-3

13

20-6

8

28-1

72

28-5

80

28-3

83

29-4

7

28-3

25

28-402

28-5

34

28-3

97

20-1

28

28-5

39

28-3

34

28-2

68

28-3

82

28-2

7

20-1

00

28-1

80

28-1

73

28-7

08

28-2

63

28-6

8228

-244

20-176

28-6

81

20-4

20-39

28-5

69

28-4

37

28-595

29-24

28-1

78

21-5

3

28-406

28-460

20-81

20-1

70

28-4

2

28-5

25

28-4

9

28-348

28-1

87

21-8

6

28-7

13

28-6

39

28-6

99-A

28-6

1

28-2

73

28-1

50

28-3

91

21-77

28-5

88

28-7

17

20-4

5

28-249

28-1

75

28-1

22

28-1

19

20-3

4

28-3

79

28-7

01

21-3

6

28-7

04

28-2

33

20-1

39

21-8

4

21-1

0

28-436-A

28-5

1

28-3

81

28-6

19

28-3

57

20-1

79

28-6

47

28-2

93

28-1

03

28-6

85

20-40

28-502

28-2

83

21-17

28-1

61

28-349

28-1

59

28-5

24

28-483

28-5

56

28-5

27

28-8

6

28-1

3

28-2

32

28-4

11

28-5

85

28-507

28-546

28-3

41

21-6

2

28-3

56

21-6

28-2

29

21-47

28-1

58

28-1

27

28-4

6

28-405

20-137

28-5

28-477

28-2

89

28-4

62

29-20

28-440

28-5

5

28-2

22

20-50

28-5

43

28-2

01

28-5

-B

28-4

19

28-474

20-116

28-78

29-38

28-5

57

28-1

60

28-1

25

20-103

28-597

20-108

28-1

79

28-7

2

28-4

4

20-7

2

21-7

1

20-1

81

28-354

28-3

1

28-1

35

28-441

28-1

12

20-9

4

28-1

39

28-1

04

28-1

14

28-3

67

21-6

9

20-1

45-B

28-4

63

28-6

58

28-1

34

28-140

21-7

9

28-6

60

28-1

15

28-1

89

28-6

24

20-6

7

28-1

76

20-2

1

28-1

54

20-178

20-9

5

20-3

3

28-6

2

28-5

26

28-3

28

20-168

21-89

28-206

20-62

28-434-A

29-6

8

21-4

A

20-1

36

20-66

28-3

05

20-1

61

28-5

-D

21-28

20-65

21-48

28-511

20-9

9

20-177

28-6

63

29-65

28-4

67

28-6

15

28-1

33

20-37

28-2

6

28-1

52

28-403

28-1

9

28-6

21

20-43

28-5

74

28-2

85

28-212

29-21

29-6

6

20-114

28-1

90

28-304

28-6

77

28-2

92

20-84

21-56

28-6

23

28-3

21-70

28-7

0

20-36

28-250

28-5

55

20-7

3

28-3

85

28-2

81

28-1

69

28-454

20-123

20-121

28-1

-A

28-3

64

28-6

3

28-4

1

28-6

71

20-52

28-1

37

28-6

26

28-6

95

20-54

28-6

02

20-1

1

20-5

7

28-457

21-3

20-162

28-5

35

28-227

28-6

46

28-1

30

28-1

91

20-41

28-506

28-3

84

28-2

38

28-1

07

28-2

62

28-4

22

28-5

42

28-479

20-20

20-174

20-1

6

28-4

08

21-4

7-B

-1

28-226

28-6

90

20-132

28-9

4

28-5

84

28-1

86

20-110

28-2

82

28-2

05

28-4

66

28-6

57

28-470

28-5

71

21-32

28-5

7

28-3

70

20-1

58

28-4

24

20-3

-B

28-2

20

20-107

28-2

76

28-2

96

28-3

10

28-3

45

20-3

2

28-6

43

28-5

77

28-4

13

28-8

8

28-9

0

28-5

82

28-7

05

28-4

23

28-9

1

28-6

36

28-6

40

28-9

8

20-1

43

20-7

9

28-550

21-91

21-27

20-51

21-60

29-4

8

28-9

728

-163

21-55

28-5

54

28-4

65

28-6

94

28-75

28-4

73

29-55

20-18

20-167

20-135

21-4

7-B

21-22

20-4

7

20-4

6-A

20-7

4-A

20-1

05-A

21-47-B

21-4

7-C

20-2

6-B

20-2

5-A

28-4

69-A

20-3

-A

20-48-A

28-1

28-6

99-B

21-4

7-A

19-1

7

20-145-A

20-145-C

This map shows the area after it has been rezoned

Legend

Overall Rezoning Boundary

Parcel Lines

(a1) Agricultural

(c1) Light Commercial

(c2) General Commercial

(c3) Central Business Commercial

(city) Zoned by Local Municipality

(i1) Light Industrial

(i2) Heavy Industrial

(i2r) Heavy Industrial Restricted

(r1) Single Family Residential

(r2) Mixed Residential

(rm) Multi-Family Residential

(rmhp) Manufactured Home ParkFinal Zoning

Public Road(COB 1064_Pg

468)

1st

6th

Cynthia

Bol

siu

s

Pub

licR

oa

d(C

OB

106

4_

Pg

46

2)

5th

Murrell

Ora

Ma

dis

on

Ele

ctri

c(R

eco

rde

d)

Ele

ctri

c(C

urre

nt)

Ele

ctri

c

Merlin

7th

Lin

coln

Lau

rel

8th

Har

de

y

Ind

epe

nd

en

ce

2nd

Center

W.B

.N

ori

sS

ub

.R

d

Public Road (1131779,1132404)

Public Road (COB 323_Pg 252)

Ve

rre

t

3rd

Goldrich

VC

M

4th

Public Road (COB 241_Pg 321)

Mic

hig

an

Orp

hana

ge

Powell

Tro

usd

ale

Evergreen

Harvey Miller

Rig

ma

ide

n

0 0.35Miles

Proposal For Streets To Remain,Rededicate, & Revoke

005This map shows the streets to be revoked, rededicated, and streets

to remain.

Streets To Be Revoked1st - 261'

2nd - 1325'

3rd - 1768'

4th - 3143'

5th - 2900'

6th - 1555'

7th - 1500'

8th - 981'

Bolsius - 395'

Center - 1336'

Cynthia - 329'

Electric (Recorded) - 582'

Electric - 587'

Evergreen - 4409'

Goldrich - 2327'

Independence - 1303'

Laurel - 883'

Lincoln - 1433'

Madison - 558'

Merlin - 767'

Michigan - 2234'

Orphanage - 1153'

Powell - 2133'

Public Road (1131779,1132404) - 1547'

Public Road (COB 1064_Pg 462) - 402'

Public Road (COB 1064_Pg 468) - 556'

Public Road (COB 241_Pg 321) - 6646'

Public Road (COB 323_Pg 252) - 1567'

Rigmaiden - 1442'

Trousdale - 2311'

Verret - 1747'

W.B. Noris Sub. Rd - 1416'

Streets To Remain Murrell - 518'

1st - 1066'

3rd - 656'

4th - 213'

5th - 430'

6th - 307'

7th - 155'

Electric (Current) - 582'

Evergreen - 9080'

Hardey - 1215'

Harvey Miller - 1017'

Michigan - 289'

Ora - 612'

VCM - 2603'

Streets To Be Rededicated3rd - 656'

HoustonRiver

Old Spanish

Ev

erg

ree

n

Legend

Existing Nelson District

Proposed Lockport Expansion

Existing Lockport District

Proposed Lockport District Expansion

This map shows the existingLockport & Nelson Districts & proposed Lockport District

Expansion