lcgp project mini case study hotcat small (crossgates)

4
LCGP Project Mini Case Study Hotcat Small (Crossgates)

Upload: mervin-cox

Post on 24-Dec-2015

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: LCGP Project Mini Case Study Hotcat Small (Crossgates)

LCGP ProjectMini Case Study

Hotcat Small (Crossgates)

Page 2: LCGP Project Mini Case Study Hotcat Small (Crossgates)

Hotcat Small (Crossgates)

STATISTICS

Equipment supplier : Bruest Catalytics Heaters

Method of Preheating : Hotcat

Installed preheater capacity : 380kW

Peak Site Demand : 144kW

Main Works Contractor : Stanningley Engineering Services Ltd

Commissioned : February 2015

 

Page 3: LCGP Project Mini Case Study Hotcat Small (Crossgates)

Hotcat Small (Crossgates)

Page 4: LCGP Project Mini Case Study Hotcat Small (Crossgates)

Hotcat Small (Crossgates)

LESSONS LEARNT

1. Carrying out a separate G17 design approval /

appraisal for the preheater itself is

meaningless

2. NGN Comments. Rectified by NGN on behalf of

Bruest prior to commissioning:

i. The heat exchanger is designed as a pressure vessel (not as a pipe). The appropriate maintenance of a pressure vessel will need to be carried out by NGN

ii. Metal on metal pipe clips will not be used in future

iii. Cable terminations to be checked by Bruest before units are dispatched

iv. Where multi-core cables are used, all cores will serve a purpose. Cables with excess numbers of cores will not be specified

v. If electrical equipment is not intended to be sited in a hazardous area, it shall not be specified as if it was to be sited in a hazardous area

3. Consider programme risks of potential

obstructions underground when constructing

new bases