lcgp project mini case study hotcat small (crossgates)
TRANSCRIPT
LCGP ProjectMini Case Study
Hotcat Small (Crossgates)
Hotcat Small (Crossgates)
STATISTICS
Equipment supplier : Bruest Catalytics Heaters
Method of Preheating : Hotcat
Installed preheater capacity : 380kW
Peak Site Demand : 144kW
Main Works Contractor : Stanningley Engineering Services Ltd
Commissioned : February 2015
Hotcat Small (Crossgates)
Hotcat Small (Crossgates)
LESSONS LEARNT
1. Carrying out a separate G17 design approval /
appraisal for the preheater itself is
meaningless
2. NGN Comments. Rectified by NGN on behalf of
Bruest prior to commissioning:
i. The heat exchanger is designed as a pressure vessel (not as a pipe). The appropriate maintenance of a pressure vessel will need to be carried out by NGN
ii. Metal on metal pipe clips will not be used in future
iii. Cable terminations to be checked by Bruest before units are dispatched
iv. Where multi-core cables are used, all cores will serve a purpose. Cables with excess numbers of cores will not be specified
v. If electrical equipment is not intended to be sited in a hazardous area, it shall not be specified as if it was to be sited in a hazardous area
3. Consider programme risks of potential
obstructions underground when constructing
new bases