learning to see simplicity within a complex project ... · pdf filelearning to see simplicity...

12
Learning to See Simplicity within a Complex Project Through the Lens of Pull Planning Production Planning and Control 751 LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT THROUGH THE LENS OF PULL PLANNING Cynthia C.Y. Tsao 1 and Glenn J. Hammons 2 ABSTRACT Ideally, project teams should get feedback from foremen from key trades to help guide work structuring decisions early in the design process. Doing so enables project teams to reveal the constructability implications intrinsic to different design options. Then, project owners may make product design decisions that would better support the construction process and thus improve the likelihood of meeting their project goals. Unfortunately, if trade foremen missed the opportunity to influence a project’s product design at project inception, the project team may later face daunting challenges to construct project components that appear complex at first glance. This paper describes such a scenario in the building out of an atrium for a $220 million new hospital addition in the U.S. It explores how the project team used pull planning to reveal production lines that needed to be created to build out the hospital’s five- story atrium. It explains how the project team considered various work structuring scenarios and eventually settled on the final work sequence. Thus, this case study will demonstrate how the project team was able to learn how to see simpler process approaches to constructing what initially appeared to be a complex product design. KEYWORDS Work structuring, sequencing, product-process design integration, pull planning, process standardization INTRODUCTION Previous case studies have demonstrated the value of using location-based planning (e.g., Seppänen et al. 2010) and modularity to build out identical and similar building units in the housing (e.g., Lennartsson et al. 2008) and healthcare industries (e.g., Olsen and Ralston 2013). However, modularity combined with pull planning (that is, the collaborative planning process in which meeting attendees determine how work must be sequenced and handed off between different trades to achieve an end milestone) can also be used to assist with building out complex product designs that do not initially appear to contain identical or similar building units. This paper will outline such a case study in which the project team leveraged pull planning, work structuring, and a production system design approach to standardize the process for building out a five-story hospital atrium. 1 Owner, Navilean; Senior Associate, Lean Project Consulting; Adjunct Faculty, Wentworth Inst. of Technology; Brookline, MA, 02445, USA, Phone +1 510/593-4884, [email protected] 2 Project Director, Skanska USA Building Inc., Nemours – AIDHC DE Expansion Project, 1610 Rockland Road, Wilmington, DE, USA, Phone +1 302/298-7663 [email protected]

Upload: doanphuc

Post on 04-Mar-2018

231 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... · PDF fileLearning to See Simplicity within a Complex ... LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... paper describes

Learning to See Simplicity within a Complex Project Through the Lens of Pull Planning

Production Planning and Control 751

LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT THROUGH THE LENS OF

PULL PLANNING Cynthia C.Y. Tsao1 and Glenn J. Hammons2

ABSTRACT Ideally, project teams should get feedback from foremen from key trades to help guide work structuring decisions early in the design process. Doing so enables project teams to reveal the constructability implications intrinsic to different design options. Then, project owners may make product design decisions that would better support the construction process and thus improve the likelihood of meeting their project goals. Unfortunately, if trade foremen missed the opportunity to influence a project’s product design at project inception, the project team may later face daunting challenges to construct project components that appear complex at first glance. This paper describes such a scenario in the building out of an atrium for a $220 million new hospital addition in the U.S. It explores how the project team used pull planning to reveal production lines that needed to be created to build out the hospital’s five-story atrium. It explains how the project team considered various work structuring scenarios and eventually settled on the final work sequence. Thus, this case study will demonstrate how the project team was able to learn how to see simpler process approaches to constructing what initially appeared to be a complex product design.

KEYWORDS Work structuring, sequencing, product-process design integration, pull planning, process standardization

INTRODUCTION Previous case studies have demonstrated the value of using location-based planning (e.g., Seppänen et al. 2010) and modularity to build out identical and similar building units in the housing (e.g., Lennartsson et al. 2008) and healthcare industries (e.g., Olsen and Ralston 2013). However, modularity combined with pull planning (that is, the collaborative planning process in which meeting attendees determine how work must be sequenced and handed off between different trades to achieve an end milestone) can also be used to assist with building out complex product designs that do not initially appear to contain identical or similar building units. This paper will outline such a case study in which the project team leveraged pull planning, work structuring, and a production system design approach to standardize the process for building out a five-story hospital atrium.

1 Owner, Navilean; Senior Associate, Lean Project Consulting; Adjunct Faculty, Wentworth Inst. of

Technology; Brookline, MA, 02445, USA, Phone +1 510/593-4884, [email protected] 2 Project Director, Skanska USA Building Inc., Nemours – AIDHC DE Expansion Project, 1610

Rockland Road, Wilmington, DE, USA, Phone +1 302/298-7663 [email protected]

Page 2: LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... · PDF fileLearning to See Simplicity within a Complex ... LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... paper describes

Cynt

752

PROIn Jcon(AIprov(FKcon(144201andDep

Fi

Fromprodthe perspatithe inclMecthe the

thia C.Y. Tsao

Proceedi

OJECT OVJuly 2011,

nstruct an eDHC) in Wvided mast

KP 2014). nstruction of4 beds total1) (Figures

d trauma capartment, fiv

igure 1: AIDrendering (

m its incepduction mantwo bed to

sonal bathroient care mocontractor

luding bathrchanical-Elbed towersrepetitive n

Fi

and Glenn J. H

ings IGLC-22,

VERVIEWthe Nemo

expansion Wilmingtoner planningThe $220 f two new fl) and 188 ps 1 and 2). are capabilve-story “M

DHC Expan(FKP Archiption, the Anagement (H

owers contaioom. Althoodels, therebuilt the o

room pods,ectrical-Plu

s’ corridorsnature of the

igure 3: AID

Hammons

June 2014 |

W ours Foundof the Nemn, Delawarg, architectu

million, 3football-shaparking spaThe projectities, and t

Main Street”

nsion exteriitects 2011)AIDHC exHowell andin patient ro

ough the 14e was a highoriginal sch headwalls,

umbing supp. The blue-e building sp

DHC Level

Oslo, Norway

dation selecmours/Alfrere (Skanskaure, and int38,460 m2

aped towersaces on the t expands ththe first fl

” atrium, ret

ior

Fic

xpansion prd Ballard 19oom units c

44 patient ch degree of hedule arou, and footwport servicecolored patpace within

3 Floor Pla

y

cted Skansked I. duPoa 2011). Fterior desig

(414,000 s that proviground levehe hospitaloor will in

tail stores, a

igure 2: AIDconstructionroject was 998). Six of containing scare rooms f room-to-round prefabr

walls. The coes into prefatient care ron the footbal

an (FKP Arc

ka USA Buont HospitaFKP Architgn services

ft2) projecde space foel (FKP 201’s acute carnclude a neand dining fa

DHC Expann (Photo bymade for oits eight buspace for a encompass

oom similariicating typiontractor alabricated ovooms in Figll-shaped be

chitects 201

uilding Incal for Chiltects of Tfor the pro

ct includes or 72 beds e11 and Skanre, critical cew Emerge

facilities (ib

nsion under y C. Tsao) one-piece f

uilt-out floosingle bed

sed a varietrity. As a reical assemblso migratedverhead rackgure 3 illusted towers.

12)

c. to dren exas oject

the each nska care, ency id).

flow rs in and

ty of esult, blies d all ks in trate

Page 3: LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... · PDF fileLearning to See Simplicity within a Complex ... LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... paper describes

On revidevups stud

numlistshanoveconlast

conDesshowconnot

howcharplanof thsim

ATRAIDThethe conTheskym (

F

the AIDHCiewing the

veloping a lifor each o

dies to deterUsing data

mber of pros. Then, th

nded off beerall lead timnverted an o responsibleOnce the c

nducted anotspite a shakw as the jo

ntractor begso repetitivThe contrac

w pull planracteristics nning, the che atypical

mplicity that

RIUM OVDHC’s five-e face that is

atrium feantain custome atrium flolights surro125 feet) lif

Figure 4: AIrendering (

Learning to Se

C expansionproject as aist of the typ

of the variourmine accura from the oduction linhe contractoetween tradmes for prodoffsite waree moment (Bcontractor sther pull plaky start on ob site’s rhyan to wond

ve? Are therctor quickly

nning couldthat typic

contractor eatrium spacexists withi

VERVIEW -story “Mais adjacent t

ature drywam-made ferroor is mad

ounded by dfts inside th

IDHC Expa(FKP Archi

ee Simplicity w

n project, thea whole to pes and quaus prefabricrate duration

time and es along wi

or conductedes to buildduction. Fin

ehouse spacBallard andstarted delivan to streamimplementi

ythm of instder, “Could re opportuniy homed in

help. Althcally enablexperimentece. As a resin a comple

in Street” ato the atrium

all pop-out rous metal

de of terrazdrywall soffihe atrium to

ansion atriumitects 2011)

within a Comp

Prod

e contractordetermine

antities of pcated units, ns for buildmotion stuith the labo

ed a pull pd out the pnally, to mice into the pd Zabelle 20vering pref

mline the proing the job tallation bepull planni

ities to try tn on the prohough the ae better pr

ed with pull sult, the conex product d

trium is roum elevators

sections wpowder-co

zzo and thfits and acou

complete th

m

Fiund

plex Project Th

duction Plannin

r’s prefabricpotential ar

prefabricatedand (4) co

ding out eachudies, the cor, tooling rplan to finaprefabricateinimize oveproject’s pr000) and begfabricated uocess for insite pull p

gan to takeing be applthis out on toject’s atriuatrium seemroduction mplanning to

ntractor startdesign.

ughly an eigfeatures a c

with meltdowoated rail poe atrium c

ustical ceilinhe atrium ce

gure 5: AIDder construc

hrough the Le

ng and Contro

cation procereas for pred units, (3)

onducting timh prefabricacontractor requirementalize how wd units andrhead costs

refabricationgan productunits to thestalling prelan, results

e hold. It walied to somehis project?

um and set med to lackmanagemeno plan out tted learning

ght-sided spcurtain wallwn glass, aosts with laeiling featung tile. Tradeiling work

DHC Expanction (Photo

ens of Pull Plan

ol

ess includedefabricationbuilding m

ime and moated unit. establishedts, and matwork wouldd calculate

s, the contran facility attion of the ue job site, efabricated us soon begaas then thatething that ?” about study

k the repetnt through the construcg how to see

pace (Figurel. Some faceand other faminated gures three des used tw

k (Figure 5).

nsion atriumo by C. Tsao

nning

753

d: (1) , (2) ock-

otion

the erial d be e the actor t the units. they units. an to t the was

ying itive pull

ction e the

e 4). es of faces lass. oval o 38

m o)

Page 4: LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... · PDF fileLearning to See Simplicity within a Complex ... LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... paper describes

Cynt

754

Thewoowalchilplacthe sub

WOIn Oassiwor“Whdoinatriu– (4wercon

corkwerclocworteam

Ficlco

WitkneglasHowatriusubwermisIn acou

atriu

thia C.Y. Tsao

Proceedi

e ceilings ood wall covlkways to hldren. The ceholders foposts couldcontractor w

ORK STRUOctober 201istant superrk structurinhat path shng what wum work vs4) “How wire interdepencert as oppoAt the moskscrew fashre any advackwise pathrk paths emm wanted to

igure 6: Goilockwise, inorkscrew, adownwards

th regards toew which trss, acousticwever, it waum work scontractor wre negotiatinscellaneous addition, th

uld then deteAt the samum work v

and Glenn J. H

ings IGLC-22,

of the walkwverings, andhouse artwo

walkways’or the ferrod be installewould add a

UCTURING13, the contrintendent, ng issues (Bhould the tr

work and ws. non-atriumll atrium wendent in mosed to just t basic leve

hion or oneantages to

h. Taking thmerged for to determine

ing n a and s

Figcounin a

do “Who shorades were cal ceiling, as still uncesuch as mewas contracng with themetals sub

he atrium teermine how

me time, thvs. non-atri

Hammons

June 2014 |

ways alongd light fixtuork from loc concrete f

ous metal raed. Also, ona topping sla

G ISSUES tractor’s atrsenior proj

Ballard 1999rades take then?” (Tsam work?” work interact

many ways,independen

el, work fore face at a thaving atri

hese two facthe atrium how to esta

gure 7: Goinnter-clockwcorkscrew, downwardsould be doin

involved incurtain w

ertain whichltdown glactually resp

e curtain wacontractor’s

eam neededw to sequenc

e atrium teium work (

Oslo, Norway

g the atriumures. Glass cal artists thfloors contail posts, annce most atrab on top o

FOR ATRrium team cect enginee9, Tsao et ato completeao and Tomwhich then at with other, the atriumntly and seqr the eight-stime. Furthium work pctors into ac(Figures 6,ablish the b

ng wise,

and

Figclock

atd

ng what won atrium w

wall, drywalh trade woulss installatiponsible forall subcontrs subcontra

d to settle oce the tradeseam also ex(Figure 10)

y

m face contfronted nic

hat would btain plywoond they neerium work wf the walkw

RIUM WORconsisting oer, and leanl. 2004) fore atrium wommelein 20allowed the

r productionm team conquentially. sided atriumermore, it wproceed in ccount, four

7, 8, and 9est starting

gure 8: Goinkwise, one ft a time, anddownwardsork and whework – miscll, paint, mld be responion. While r installing ractor to takactor (i.e., ton the atrius through thxamined w). Once the

ain acousticches are locbe of particod pockets eded to be rwas comple

way floors.

RK of a senior n coach star atrium worork?” (2) “004) (3) “We project tean lines?” Sinnsidered som

m could procwas uncleara clockwis

r permutatio9). In additpoint for at

ng face d

Figcounone

anden?” the concellaneous m

mechanical, nsible for sothe miscelthe meltdo

ke care of tho be a sub-

um work pahe atrium sphat should e atrium te

cal ceiling cated alongcular intere

that servedremoved beete, the conc

superintendarted evaluark includingWho should

What countam to determnce these is

ome of them

ceed either r whether tse vs. counons for posstion, the atrtrium work.

gure 9: Goinnter-clockwface at a tim

d downwardntractor alremetals, inteand electr

ome portionllaneous meown glass, hat work as-subcontracath so that pace.

be counteeam establis

tile, g the st to d as efore crete

dent, ating g: (1) d be ts as mine sues

m in

in a there nter-sible rium

ng wise, me, ds eady erior rical. ns of etals they s the ctor). they

d as shed

Page 5: LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... · PDF fileLearning to See Simplicity within a Complex ... LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... paper describes

whieleminteprio

PLAIn ltradworWadiag(Figbectradthe

sizepathforeworsche

camalsoatriuB8,arralinepapfrom

ich elementments in oeract with oority over at

Figure 1

ANNING Tlate Novemde project mrked with trlkway Topgram that bgure 11). Tause it was

des. Each watrium as arIn addition

es, and durahs. By the eemen postedrk zones B3eduled a folSince they

me to the seo set up theum layout. so they w

anged the pe from the dper for the am the first s

Learning to Se

ts counted other produother produtrium work

10: Basic el

THE ATRImber 2013, tmanagers anrades to puping Slabs.roke the eig

The handoumore collo

work zone corea “B” and

n, the handoations for eaend of this id sticky not3, B4, and Bllow-up pulhad experi

econd sessioe plotter paOn the job

would see wlotter paperdoor that viatrium ceilisession, so th

ee Simplicity w

as atrium wuction linesuction linesand vice ve

lements of t

IUM WORthe contractnd foremen ull plan atriu.” At the pght-sided atut used the oquial and wode started d the bed towout instructach work zoinitial pull ptes that idenB5. As the ll planning sence from ton in early aper on thesite, visitor

work zones r containingisitors used ng and worhe trades w

within a Comp

Prod

work, they s before de (e.g., whe

ersa).

the five-stor

RK tor providedinvolved inum work frpull plannintrium into e

term “worwould thus b

with a “B”wers as areated foremenone and on planning ef

ntified somepull plan w

session for athe first puDecember

e walls of trs typicallyB4 and B5

g work zonto enter in

rk zones B3were able to

plex Project Th

duction Plannin

needed to etermining ether the ot

ry atrium an

d basic Lean atrium worom the endng start, theeight modulrk zones” be more acc” because pras “A” and n to identify

each floor ffort, the atre work in thwas far fromatrium work

ull planning 2013 better

the double-y observed t5 straight ahes B4 and B

nto the traile3, B4, and revise them

hrough the Le

ng and Contro

account forhow atrium

ther produc

nd its adjace

an Construcork. Then, td milestonee contractores to help gas opposedcessible as aroject drawi“C” (Figurey work desto demonst

rium projeche atrium cem completek two weeksession, th

r prepared. -wide trailehe atrium fhead. Thus,B5 based oer (Figure 1B5 contain

m throughout

ens of Pull Plan

ol

r the remainm work wction lines t

ent areas

ction traininthe atrium te of “Readyr handed oguide the trd to “modua concept toings designe 10). scriptions, ctrate their w

ct managerseiling as wee, the contraks later. he atrium tr

The contraer to mimicfrom work z, the contra

on a direct s12). The ploned sticky nut the meetin

nning

755

ning ould took

ng to team y for out a ades

ules” o the nated

crew work and

ell as actor

ades actor c the zone actor sight otter

notes ng.

Page 6: LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... · PDF fileLearning to See Simplicity within a Complex ... LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... paper describes

Cynt

756

At t7, 8corkm (deliHowand

teamcomtradsuppwor

the walatriuadjalinesess

atriumeecomfini

undflooaccelargmedterr

thia C.Y. Tsao

Proceedi

Figure 11:the start of 8, and 9) wkscrew fash75 feet) liftiberation, thwever, it w

d if there weWith the gm then askmplete to alldes concludport the liftrk from the The atriumatrium pul

lkway ceilinum floors acent to atries. These desion, so the Although tum pull plaeting attend

mpleted befoshing out thMeanwhile

derstand howor so they cess to over

ge lifts cleardium lift corazzo layout

and Glenn J. H

ings IGLC-22,

: Pull plannithe session

with the tradhion would ts sooner, buhe trades aas still uncl

ere any advagroup’s deciked, “Does low for the

ded that onlyt switch. Thend milesto

m team also l planning ngs and flowould be tium walkwecisions comatrium trad

the atrium ans, they didees recogniore atrium fhe atrium cee, the atriumw they wishould begin half of the rly could n

ould fit, let at to a differe

Hammons

June 2014 |

ing handoutn, the atriumdes. The seallow the put he was o

all concurrelear how toantages to wision to wothe face wlifts to be

y the fifth fen, the atriu

one of “Readecided to sessions asors locatedtreated as ays would b

mbined helpdes became mceiling andd influenceized that it face work beeiling soffitsm team starhed to proceinstallationfloor (Figu

not fit withinalone two ment time fram

Oslo, Norway

t Fm team discuenior superproject to swopen to consed with theo identify thworking clocork in a cowork on theswitched?”floor’s faceum team anady to Switc

define atris all work id along the separate prbe managed

ped establishmore focus

d floors wee the second

would be began. As a rs before focrted meetineed. They ren outside of ure 13). Thin half of th

medium liftme so it wo

y

Figure 12: Pussed possi

rintendent nwitch from sidering othe senior suphe best startckwise vs. c

orkscrew fase fourth an After runn

e work woud trades foc

ch Lifts” forium work thinvolving thatrium. Th

roduction lid as part ofh the bounded in their p

ere not dired pull plannbetter if theresult, the dcusing on bung with the equested to the atrium.

is was challhe floor, it ws. As a resu

ould not imp

Pull planningble work pa

noted that p38 m (125

her work patperintendenting point fcounter-clocshion in pland fifth flooning some culd need to cused on pur each atriumhat would bhe atrium fen, the atriines, and thf the bed todaries for thplanning. ctly incorp

ning sessione atrium ceidrywall foreuilding out t

terrazzo sulayout in th However, lenging becwas unclearult, the atriupact the atriu

g room layoaths (Figureproceeding feet) lifts to

aths. After snt’s suggestfor atrium wckwise. ace, the atrors need to

calculationsbe complet

ulling the atrm work zonbe addresseface, as weium ceiling he tower w

ower produche pull plann

porated inton. Pull planiling work weman prioritthe atrium fubcontracto

he middle oflayout requ

cause while ar if a large um team shium pull pla

out es 6, in a o 23 ome tion.

work

rium o be , the te to rium ne. ed in ll as and

walls ction ning

o the ning were tized face. or to f the uired

two and

ifted an.

Page 7: LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... · PDF fileLearning to See Simplicity within a Complex ... LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... paper describes

LEAFKP(FigintetypirepeFurtthe snapinteconatriu

focuceilatriuthe so tplanalththe cam

Figure 1Terrazzo la

ARNING TP Architectgure 4). Asentional to ically createetition withthermore, thdrywall su

pping a lineersection of nsistency in um team regOnce the seus on plannling pull plaum face, inthree remaithey quicklns. This ledhough it was

senior projme up with t

Tab

Floor

2nd

3rd

4th

5th

Learning to Se

3: Terrazzoayout area o

TO SEE SIts’ atrium ds a result, create a moes building

hin the desighe contracto

ubcontractore on the flo

f two curvesdesign fromgarded the aecond pull p

ning atrium an, they wecluding B4 ining pull ply developed the atriums still challeect enginee

the followin

ble 1: Areas

E-shaped Dr

B1,

B1, B2,

B2, B3

ee Simplicity w

o pattern witoutlined in r

IMPLICITYdesign uses

each sectioore interestchallenges

gn to gain tor regarded r had to ideor, (2) in so

s, (3) all atrim one atriumatrium face planning meface work. A

ere able to fwhich repr

plans were sed them bym team to enging to seer started tryng areas of r

of repetitio

ywall Pop-ou

B6

B6, B7

B3, B6, B7

3, B6, B7

within a Comp

Prod

th atrium oured, and terr

Y IN A COdrywall po

on “pops-outing aesthetbecause it i

the benefitsd the atrium entify poinome atriumium faces wm face to thdesign as c

eeting begaAs a result,fully plan oresented thesimilar to thy copying o

realize thaee. After theying to idenrepetition w

on in AIDHC

uts Ferrou

B1

B

plex Project Th

duction Plannin

utlined in purazzo layout

OMPLEX Dp-outs to but” differentic. Howeveis difficult fs of learning

face as comnts in spacem face locatiwere on a rahe next. Thucomplex andan, the atrium, while the tout five of te curtain wahe pull planover informat repetitione second puntify the so

within the atr

C’s comple

us Metal Rail

1, B2, B3, B5,

B2, B3, B5, B8

B5, B8

B1, B5, B8

hrough the Le

ng and Contro

urple (Romat starts from

DESIGN reak up thently, and ther, “interestfor buildersg curves anmplex to bu

for layoutions, corneradius, and (4us, on first d a challengm team asktrades did nthe eight puall. Then, thns they had jmation fromn did exist ull planningource of thatrium (Table

x atrium de

Posts Cu

B7

8

ens of Pull Plan

ol

an 2013). m the + sign

e space visuhis variatioting aesthet

s to find enond fewer setuild becauset as opposers formed at4) there waimpression

ge to build. ked the tradenot completeull plans forhey realized

just complem the other

in the atrig session enat repetition e 1):

esign

urtain Wall

B4

B4

B4

B4

nning

757

.

ually on is tics” ough tups. e: (1) ed to t the

as no , the

es to e the r the that

eted, pull

ium, nded,

and

Page 8: LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... · PDF fileLearning to See Simplicity within a Complex ... LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... paper describes

Cynt

758

Comwaltherandsectand

STAWitatrium (

Fi

thia C.Y. Tsao

Proceedi

mbining thills (Figure 1re were two

d (2) ferroustions “E-wo

d they called

Figu(B6

ANDARDIth the new cum team de10’) of stan

igure 15: Aa

and Glenn J. H

ings IGLC-22,

s insight wi14), the atrio basic types metal rail ork” becausd the ferrous

ure 14: Pull6, B7, and B

IZING THEclarity that eveloped twndard “E-wo

Atrium face pand 3 m (10

Hammons

June 2014 |

ith studyingium team rees of atrium

posts sectiose some drys metal rail

l plans for aB8 pull plan

E BUILDINthe atrium f

wo new pullork” and 3 m

pull plans th0’) of standa

Oslo, Norway

g the color pealized that

m face workons. The atywall pop-oposts sectio

atrium workns not shown

NG PROCEface consistl plans in mm (10’) of s

hat represenard “Rail-wo

y

patterns in tt in addition

k flows – (1trium team out sectionsons “Rail-w

k zones B1, n due to spa

ESS FOR Ated of “E-w

mid-Decembtandard “Ra

nted 3 m (10ork” (Photo

the pull plann to the cur) drywall pcalled the ds resembled

work.”

B2, B3, andace limitatio

ATRIUM Fwork” and “Rber 2013 thaail-work” (F

0’) of standao by C. Tsao

ns on the trrtain wall wpop-out sectdrywall popd the letter

d B5 ons)

FACE WORail-work,”at representFigure 15).

dard “E-woro)

ailer work, tions p-out “E,”

ORK ” the ed 3

k”

Page 9: LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... · PDF fileLearning to See Simplicity within a Complex ... LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... paper describes

Learning to See Simplicity within a Complex Project Through the Lens of Pull Planning

Production Planning and Control 759

The atrium team was careful to copy over the productivity rates developed by trade project managers and foremen from the earlier pull plans into the new 3 m (10’) length standard pull plans. In a few instances, the new pull plans were more conservative in terms of the time estimate for completing work. Figure 15 shows the new pull plans captured on a single sheet of plotter paper with the 3 m (10’) of standard “Rail-work” on top and the 3 m (10’) of standard “E-work” on the bottom.

After developing the new pull plans, the atrium team met with the trade foremen to get their feedback and develop buy-in into the new pull plans (Miles 1998). At first, some foremen were concerned that these “new plans” deviated from the earlier plans that they developed in early December 2013 with their project managers. To allay their concerns, the atrium team moved the old pull plans into the conference room and walked the foremen slowly through the new pull plans so they could see that the new plans were either equal or more conservative in time estimate. It was only after the step-by-step walk-through between the old and new pull plans that the foremen became comfortable with the new pull plans and were willing to follow them.

DETERMINING WHERE TO START ATRIUM FACE WORK With standard work processes established for atrium face work, the atrium team now had to resolve: (1) how to determine where to start the work, (2) whether to have work move in a clockwise or counter-clockwise fashion, and (3) how atrium face work would interact with the other production lines. After the mid-December 2013 meeting with the trade foremen, the atrium team decided to hold off on terrazzo work until after the trades completed the bulk of atrium face work. This then de-coupled the atrium floor production line from the atrium face production line (Figure 10).

Next, the atrium team re-examined the atrium ceiling production line. At that time, the drywall foreman was planning on completing the northern half of the drywall soffits before moving on to the southern half. Once the soffits were installed, the other trades still needed to use the high 38 m (125 feet) lifts to complete two more elements of atrium ceiling work – painting and acoustical ceiling tile. The atrium team concluded that in order to switch from 38 m (125 feet) lifts to 23 m (75 feet) lifts sooner, painting and acoustical ceiling tile work should be broken up and managed in two phases – first, to complete the northern half of the atrium ceiling and then, to complete the southern half. This enabled the trades to overlap at least some of the atrium ceiling work. The atrium team would have preferred to break up the atrium ceiling work into three or more phases, but it was impossible to do so because there were only two lifts available in the atrium.

Now that the sequence for the last activities of atrium ceiling work has been established, the atrium team could then determine its impact on atrium face work. The northern half of the atrium face consists of work zones B2, B3, B4, and B5 (Figure 11). The southern half of the atrium face consists of work zones B1, B8, B7, and B6. The atrium team studied how atrium make-ready work had been progressing to that point (e.g., removing the plywood pockets from the concrete floors) and determined that it felt more natural and made more sense for atrium face work to proceed in a clockwise fashion as most workers were right-handed. As a result, the atrium team could finally establish where to start atrium face work – in work zone B2, and work would proceed in a clockwise fashion.

Page 10: LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... · PDF fileLearning to See Simplicity within a Complex ... LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... paper describes

Cynt

760

FINWitfor a puwouto thcaseatriuatriucrew

sequspantheyhandryw

As indi

for devbegwor

thia C.Y. Tsao

Proceedi

NALIZINGth a startingatrium faceure corkscreuld be morehe next onee, and he cum face woum face wows to complWorking fruence that nned one oy distributed

ndout introdwall or R fo

Figure 16(T

noted in ticated that iSince the foatrium wor

veloped by gan workingrk starting i

and Glenn J. H

ings IGLC-22,

G THE SEQg point (i.e.e work, the aew path (Fie efficient fe. They checonfirmed iork sequencork started ilete an entir

rom both a pconsidered r two floord in a meetiduced a newor rail work

6: Final SeqThird and sethe “Planniit was atriumforemen hadrk up to thithe atrium

g with the in mid-Janu

Hammons

June 2014 |

QUENCE F, work zonatrium teamigure 6). Thfinishing oucked-in witt was. As ace that was in work zonre E-sectionpush and puall of thes

s. They outing with thew coding s][Priority o

quence for Aecond floorsng the Atr

m work as od participates point, theteam and

foremen touary 2014. A

Oslo, Norway

FOR ATRIne B2) and m then examhe atrium te

ut an entire th the drywa result, tha hybrid v

ne B2, wenn before moull perspectse factors intlined the sue foremen insystem for f work com

Atrium Faces not shownrium Workopposed to bed in a majoey readily a

proposed io implemenAs of April

y

UM FACEdirection (i

mined whetheam suspecE-section aall foreman

he atrium tevariation of nt clockwiseoving on to tive, the atrin addition tubsequent sn early Januatrium wor

mpletion].”

e Work on fn due to spac” section, bed tower wority of the greed with in Figure 1nt the final

2014, the a

E WORK .e., clockwi

her work shoted that the

at a time befn to confirmeam needed

Figures 6 ae, and allowthe next oneium team thto the fact sequence inuary 2014 (Frk: “[Floor

fifth and fouce limitationthe “B” in

work. productionthe final se6. Then, thsequence f

atrium face

wise) establisould proceee drywall crfore moving

m if this wasd to developand 8 – tha

wed the drye. hen developthat E-sect

n a handout Figure 16). level]B-[E

urth floors ns)

n the code

n planning sequencing lhe atrium tfor atrium

e work has b

shed ed in rews g on s the p an at is, ywall

ped a tions that The

E for

just

steps logic team face been

Page 11: LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... · PDF fileLearning to See Simplicity within a Complex ... LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... paper describes

Learning to See Simplicity within a Complex Project Through the Lens of Pull Planning

Production Planning and Control 761

flowing well, and the trades have only worked out of sequence on occasion as opposed to regularly. Thus, the atrium team found that their investment in planning has paid off since all trades are on the same page with regards to sequencing and the foremen are committed to the plan since they bought into it after participating in the pull planning sessions.

CONCLUSIONS The contractor’s experiment with the use of pull planning to organize build out of the atypical atrium space evolved over a period of four months. During that time, the contractor methodically considered various activity sequences and work flows to uncover hidden production lines. Along the path of this experimentation, the project team reached three primary conclusions:

• At first, the atrium design seemed like a “one of a kind” work of art to the project team, and there would be no ability to implement much of a flow other than the typical work breakdown by level or elevation. The atrium team’s pull planning efforts revealed that complex, artistic building spaces can be broken down into distinct production lines that provide better clarity, structure, and discipline to the construction process.

• Implementing pull planning in the later stages of a project can still generate value. Whereas an initial belief was that it was too late to use lean on atrium work, the final process in planning atrium work revealed that benefits can be derived even if implementation occurred in later project phases.

• Significant gains are achievable through the use of pull planning. The project team originally regarded the atrium as a distressed portion of the schedule, and it eventually became one of the most successful parts of the project.

In addition, the project team reached three other conclusions about pull planning:

• Changing the culture is difficult but achievable. During the pull planning sessions, the trade foremen could not resist the temptation to overstate their durations. Everyone wants to under promise and then overachieve. Then, since the attendees only started to unravel the details that would impact how work might be handed off between trades, the first pull planning session was inconclusive. When the trade foremen were faced with a lack of clear direction for atrium work, they became argumentative, obstinate, and defensive, and a few literally walked away from the meeting. It took several follow-up meetings until the trade foremen realized that the planning meetings would result in less supervisory effort, so their quality and production would actually increase if they maintained the required production rates to make work flow.

• In some cases, trade foremen do not really know enough about what they are doing to provide accurate information. When asked to assign times to their work in the pull planning sessions, some really did not seem to know, knew but could not express it, or did not want to divulge the information. “You have to ask the Project Manager” or “Ask my office” was a typical reply. Trade foremen need to be informed and empowered individuals to better support efforts in pull planning.

Page 12: LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... · PDF fileLearning to See Simplicity within a Complex ... LEARNING TO SEE SIMPLICITY WITHIN A COMPLEX PROJECT ... paper describes

Cynthia C.Y. Tsao and Glenn J. Hammons

762 Proceedings IGLC-22, June 2014 | Oslo, Norway

• The concept of production system design for organizing workflow is actually foreign to many trade foremen. Boiling work down to one repetitive unit that can be monitored, adjusted, and improved upon to create higher efficiency in construction is not a prevalent way of thinking or acting.

By documenting this project team’s pull planning journey, we hope this case study will inspire other project teams to learn how to see the simplicity within complex project designs and take pull planning to yet another higher level of use.

ACKNOWLEDGMENTS The authors would like to thank Kay Holbrook of AIDHC and Mike Rayburn, Patrick Keenan, Chris Eagle, Nick Denardo, Anthony Colonna, Marty Corrado, Matt Pentz, Derek Counts, Carolyn Samuelian, Leigh Emberton, and the rest of the Skanska Nemours project staff for their involvement and assistance with the effort described in this paper. We would also like to thank the IGLC reviewers and our colleagues who provided valuable feedback to us on how to improve this case study.

REFERENCES Ballard, G. (1999). “Work Structuring.” LCI White Paper-4, LCI, June 12. Ballard, G., and Zabelle, T. (2000). “Project Definition.” LCI White Paper-9, Lean

Construction Institute, Oct 10, 10 pp. FKP (2014). “Nemours/ AIDHC Master Planning and Phase One Expansion.” FKP

webpage, http://www.fkp.com/portfolio/projects/nemours_hospital_expansion. FKP (2012). “Level 3 Build Out, Permit, and Bid Drawing.” Nemours AIDHC

Project, FKP Architects, Apr 20. FKP (2011). “Nemours Expansion ‘Breaks the Sky.’” FKP Architects press release,

Oct 10, http://www.fkp.com/about_us/news/nemours_expansion_breaks_the_sky. Howell, G., and Ballard, G. (1998). “Implementing Lean Construction:

Understanding and Action.” Proc. IGLC-6, 13-15 Aug, Guarujá, Brazil. Lennartsson, M., Bjornfot, A., and Stehn L. (2008). “Lean Modular Design: Value-

Based Progress of Industrialised Housing.” Proc. IGLC-16, Manchester, UK. Miles, B. (1998). “Alliance Lean Design/Construct on a Small High Tech Project.”

Proc. IGLC-6, 13-15 Aug, Guarujá, Brazil. Murray, J. (2011). “Skanska to Construct Hospital Expansion for the Nemours

Foundation.” Skanska USA press release, July 01, http://tinyurl.com/mxutbkc. Olsen, D., and Ralston, W. (2013). “Utilizing Prefabrication in Lean Construction: A

Reasoned Decision or an Educated Guess?” 49th ASC Int’l. Conf. Proc., 8 pp. Roman (2013). “First Floor Epoxy Terrazzo Pattern and Color Drawing.” Nemours

AIDHC Project, Roman Mosaic and Tile Company, West Chester, PA, Sept. 26. Seppänen, O., Ballard, G., and Pesonen, S. (2010). “The Combination of LPS and

Location-Based Management System.” Lean Construction Journal, 6 (1) 43-54. Tsao, C.C.Y., Tommelein, I.D., Swanlund, E., and Howell, G.A. (2004). “Work

Structuring to Achieve Integrated Product-Process Design.” ASCE, J. of Constr. Engrg. and Mgmt., Nov/Dec, 130(6), 780-789.

Tsao, C.C.Y. and Tommelein, I.D. (2004). “Creating Work Structuring Transparency In Curtain Wall Design.” Proc. IGLC-12, 3-5 Aug 2004, Copenhagen, Denmark.